Concept
In this topic, you will navigate to the main Planner Workbench page.
Additional Information
Procedure
Step Action
1. Begin by navigating to the Planner Workbench page.
Step Action
2. Use the Organizations page to select an instance:organization.
Step Action
3. Find organization TST:M1 TST:Seattle Manufacturing.
Step Action
4. Click the TST:M1 TST:Seattle Manufacturing list item.
Step Action
5. Click the OK button.
or Press [Alt+O].
Step Action
6. Click the Plans tab.
Step Action
7. Use the Navigator page, Plans tab to view and act on results from the
material/capacity plan.
Step Action
8. Click the View By list.
Step Action
9. Use the View By populist to specify how to see the hierarchy of entities in each
plan.
Step Action
10. The Plans hierarchy displays the material/capacity plans available for review in
this organization.
Step Action
11. Select the plan whose details you want to see.
Step Action
12. Since View By is Organizations, the planned organizations of this plan display
next in the hierarchy.
Click the TST:D2 tree item.
Step Action
13. Product groups display next.
Step Action
14. Items display next.
Step Action
15. The final level to display is the Supplier.
Step Action
16. You have successfully navigated to the main window of Planner Workbench.
End of Procedure.