Professional Documents
Culture Documents
Abstract
The industry makes a pioneering discovery: 20,000 psi SITP,
100 ppm H2S, 10 % CO2, 400 oF flowing wellhead
temperature. Now what?
Everyone wants production as soon as possible.
What challenges need to be overcome?
What equipment is available, and what needs to be
designed and tested?
How long will it take to design, build, test (and redesign,
re-test), certify, and deliver?
What challenges have yet to be identified?
If you have a failure, can you work it over?
Is there well control equipment in place?
Recent HPHT history indicates that infantile failures
happen, usually caused by something that no one considered
an issue. What are the hidden obstacles awaiting the first ultra
HPHT completion? This paper will summarize current
industry HPHT capability and more importantly, propose
questions in an attempt to stimulate discussion on issues that
we may be missing.
HPHT Completion Challenges
Industry is currently drilling wells to severe HPHT conditions,
e.g., SITP 20 ksi, BHT 470 oF, 25,000 ft depths. One day
someone may have the chance to complete one of these
monsters! Of course, everyone will want production ASAP.
Two critical questions occur:
What are the technology gaps?
WHAT ARE ISSUES THAT WE HAVENT EVEN
THOUGHT ABOUT?
SPE 97589
15,000
17,000
18,000
335
18,500
22,000
23,000
400
20,000
24,000
25,000
410
23,000
27,000
28,000
425
25,000
30,000
32,000
450
385
450
465
500
530
0.6
3?
4?
7?
11 ?
CO2, %
18 ?
21 ?
BHT, oF
Assumptions
SITPs indicate approximate step changes in completion degree of difficulty.
Pressure gradient of 18.4 ppg, SITP = 0.85 * BHP
Temperature gradient of 1.5 oF/100
H2S and CO2 values based on extrapolation of published correlations, Smith for H2S and Bross for CO2.
To assess the challenges we will encounter in this arena, well completion issues and components will be covered in the following
sections. The time-to-acquire and degree of difficulty for each type of equipment has been estimated, and is described in color format
according to the key shown in Table 2.
Table 2 Color-Coded Key Descriptions
Green - Existing equipment.
Delivery times in years
Yellow - Limited sizes or not available, but designs indicate no major hurdles.
Time in years for design,testing and delivery.
Pushing limits of current technology.
Time in years for R & D, design,testing and delivery.
Major technical breakthrough required.
Time in years for R & D, design,testing and delivery.
Green been there, done that, can do again. Delivery time in years for equipment with > 4 month delivery.
Yellow sure it can be done, but either have not done yet or very limited experience. Estimated time in years for design,
testing and manufacturing.
Orange think that it can be done with current technology. Estimated time in years for R & D, design, testing and
manufacturing.
Red major technical breakthrough required. Estimated time in years for R & D, design, testing and manufacturing.
SPE 97589
15,000
17,000
18,000
335
18,500
22,000
23,000
400
20,000
24,000
25,000
410
23,000
27,000
28,000
425
25,000
30,000
32,000
450
BHT, oF
385
450
465
500
530
0.6
3?
4?
7?
11 ?
CO2,%
18 ?
21 ?
CASING
1.0
1.0 - 1.5
1.5 2.0
2.0 2.5
CASING CONNECTION
1.0
1.5 2.0
2.0 2.5
1.0-1.5
1.0-1.5
1.0-1.5
1.0-1.5
1.0 -1.5
1.5 - 2.0
1.5 - 2.0
2.0 3.0
0.5
0.5 - 1.0
1.0 - 2.0
2.0 3.0
0.5 - 1.0
0.5 - 1.0
1.5
1.0
1.0
2.0 - 2.5
1.0
1.0 - 1.5
1.0 - 1.5
3.0
1.5
2.0 - 3.0
1.0 - 1.5
3.0
2.0
0.5?
0.5?
0.5
0.5
1.0 - 2.0
1.0 - 2.0
1.5
1.5
?
2.0
2.0
1.0
?
2.0
?
?
?
?
1.5
1.0
2 - 2.5
1.0 - 2.0
?
?
?
?
?
?
1.5
1.5
3.0
1.0 - 2.0
?
?
?
?
?
?
1.0 - 2.0
1.0 - 2.0
0.5
?
1.5 2.0
3.0
2.0 - 3.0
?
?
?
?
?
?
TUBING
1.0 - 1.5
TUBING CONNECTION
PACKER
SCSSV
WELLHEAD/TREE
PERFORATING - TCP
0.5
0.5
0.5 - 1.0
SPE 97589
SPE 97589
SCSSVs
Again, limited work has been done on SCSSVs, but not at the
ultra HPHT conditions above 20 ksi.
Limited sizes currently available with pressure rating
greater than 15 ksi.
o 4.5 in., 20 ksi OD 7.13 in., ID 3.437 in.
o 3.5 in., 20 ksi OD 5.49 in., ID 2.313 in.
o 3.5 in., 16.7 ksi - OD 5.65 in, ID 2.87 in.
With API 14A requirement of a test pressure of 1.5 times
the working pressure, maximum pressure rating is 20 ksi
and 400 oF due to verification test limits at Southwest
Research. Standard currently under review to reduce test
pressure to 5000 psi above working pressure for SCSSVs
of 10 ksi and greater. Awaiting final committee approval
and MMS approval.
Is more than one SCSSV needed?
Does the slam test requirement in API 14 A provide a
sufficient test?
o Rate is low in regulations (for instance
17.3 MMCFPD for a 3.5 in. valve), but what should
be done for prudent operations (absolute open flow AOF, maximum expected rate, etc?).
o Slam testing is done at atmospheric conditions.
Would a low rate high-pressure slam test better
simulate what would happen in a real emergency?
Test facilities do not exist for this type of testing.
SCSSVs require high strength (140 ksi) inconel 718/725.
o Very hard to obtain, typically requires hand picking
pieces.
ID/OD constraints are critical.
o OD needs to be minimized to fit in tie back strings
and potentially BOP bores.
o ID needs to be maximized to allow for electric line
operations, especially pipe recovery and perforating.
What are the temperature effects on control line fluids and
dynamic seals?
o Degradation of control line fluid and dynamic seals
over time needs to be evaluated.
SPE 97589
successful cuts.
Can make cutters with higher temperature explosives
but performance goes down.
o For HPHT applications, cutters would likely have to
be designed and tested based on actual temperatures
and pressures and metallurgy of tubular goods.
Chemical Cutters
o Limited to 350 degrees and 20 ksi with the same size
limitations as jet cutters.
o
Plugs
Limited sizes of slickline plugs available with ratings
above 15 ksi and 400 oF.
Well Control
Well control in the event of an infantile failure is a major gap
HPHT completion technology.
Limited 20 ksi BOPs stacks and choke manifolds. Stacks
have not been used in years and may need reconditioning.
It will require two years for new BOP stacks. No
equipment available for pressures > 20 ksi. Is it prudent
to complete a well without having a BOP stack available
that can handle maximum SITP?
Can the shear rams shear the heavy wall, high strength
tubulars that will be run?
Well kill - Currently limited availability of 20 ksi
equipment and none available for pressures > 20 ksi.
Pumps, piping, chicksans, or coflexit would have to be
developed, 1-2 years delivery. Is it prudent to complete a
well without having equipment rated to the maximum
SITP available in industry for an emergency kill?
Height and weight of BOPs, wellheads, choke manifolds
etc. will be larger then what is currently used and may
require special handling equipment.
Kill weight completion fluids.
o Can heavy weight brines be inhibited at these high
temperatures? Corrosion inhibitors for ZnBr tend to
degrade to H2S and zinc sulfide scales. Needs to be
tested with CRAs, elastomers, high strength work
strings etc.
o Are Cesium formates the answer?
o Oil base mud will work, but there are issues.
OBM can destabilize and the weighting agent
drop out over time plugging the tubing,
complicating future work over. Clean out of the
weighting agent with coiled tubing difficult due
to low pump rates.
Potential for severe formation damage. Limited
ability to clean up formation damage with
stimulations due to pressures and temperatures.
Relief wells - Temperature limit of 350 oF of magnetic
proximity tool for detecting blowout well would limit
relief well depth. Deepest relief well to date is around
22,000 feet.
How do we want to configure the trees/wellheads for
emergency kill operations? Topsides design and layout
needs to address tree leaks, fires and emergency kill
access.
SPE 97589
Remedial Operations
Remedial operations are not normally planned as part of an
initial completion.
However, for ultra HPHT wells
contingency planning will be required.
Snubbing Units maximum rated snubbing units are
20,000 psi.
Coiled tubing maximum rating 15 ksi and 400 oF.
Workstrings.
o Heavy wall tiebacks and liners will limit workstring
sizes and torque ratings. May not be able to wash
over.
o S-135 workstrings can be used in inhibited mud or
completion brines before perforating (i.e. no H2S),
but can heavy weight completion brines be inhibited
sufficiently for use of S-135 for remedial operations?
o Premium connections such as XTM40 or PH6 will be
required. These connections are very susceptible to
pitting on MTM seal face in heavy weight brines.
o Workstrings that are sour gas compatible are in
limited supply and may not have sufficient strength.
Long lead time required for new strings.
Sand Control not any time soon!
o It is likely that formations will be competent initially.
o Remedial sand control may be possible after
depletion, but would have to be taken into
consideration in initial completion. Small liners,
CRA packers to mill up, temperatures, and poor
cement jobs are all issues to be considered.
Fracturing not anytime soon!
o Issues with fluids, packer loads, surface pressures etc.
o May be possible after depletion, but would have to be
taken into consideration in initial completion.
Integration And Production Operations
Good communication between drilling, completion, facility,
and production personnel is critical to insure successful
handoffs.
How many wells do you want on a platform? Should
independent jackets be used if water is shallow enough?
Wellhead growth
o Accurate modeling wellhead growth is required for
proper facility and flow line design.
o Shell has experienced growth below the mud line,
especially if several wells clustered together.
o Will casing growth put unexpected loads on
conductor casings?
Understanding and managing annular pressures
o The effect of trapped annular pressures due to
trapped fluids between cement needs to be addressed.
o A annulus pressures can be reduced by putting N2
blanket
This reduces the need to bleed off annular fluid
and reduces the risk of getting oxygen into the
annulus during shut in.
N2 blanket reduces hydrostatic head, thus
o
o
Conclusion
The industry has completed HPHT wells in the past.
However, the new higher temperature and pressure horizons
being drilled today will require an industry-wide technology
and development effort in order to deliver a reliable
completion. These new ultra-HPHT completions will tax our
industry resources people and infrastructure to deliver a
safe completion in a timely fashion.
As a result of our past efforts, we are confident that the
technology to complete these wells can be made available.
However, many of those who pioneered this effort are no
longer active. There has not been a recent, strong industry
focus on HPHT wells and we are at risk of losing industry
knowledge if we do not work to capture our past learnings.
There is a stronger need than ever before to pool our efforts in
preparing for the new HPHT future.
Acknowledgements
I would like to thank the management of Shell Exploration
and Producing Company for the opportunity to prepare and
present this paper. I would also like to extend my appreciation
for the input into this project by other Shell personnel and
numerous equipment suppliers.