You are on page 1of 130

Volume

Installation and
Commissioning Procedures

TJ100CPr4

104-DOC000026-E
Version 1.0

Revision history
Revision

Date

Comments

1.0

03-03-2008

Standard Version

2000-2008 Tejas Networks India Ltd., All Rights Reserved.

To the best of Tejas Networks's knowledge, at the time of its preparation, the information in this document is accurate.
However, Tejas Networks makes no warranty or representation with respect to its accuracy and disclaims all liability
which may result from inaccuracies, or third-party use, or third-party reliance. This information is subject to change
without notice.
No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means,
electronic, mechanical, photocopy, or otherwise, without the prior written consent of Tejas Networks. Tejas Networks
assumes no responsibility for its use, nor for infringements of patents or other rights of third parties. This document
implies no license under patents or copyrights. Trademarks in this document belong to their respective companies.

Table of Contents iii

Table of Contents

About This Document


1.1 Installation 1
1.2 Commissioning 1
1.3 Audience 3
1.4 Reference 3
Technical Support Information
Observing Safety Guidelines
3.1 Safety Recommendations 9
3.1.1
3.1.2
3.1.3

3.2

Guidelines to ensure general safety 9


Maintaining safety with electricity 9
Preventing electrostatic discharge damage

10

Site environment 10
Preventive site configuration 11
Configuring equipment racks 12

Power Supply Considerations 12


Safety Standards 12
Laser RadiationOptical Transmission Systems 13
3.5.1
3.5.2
3.5.3
3.5.4
3.5.5

3.6
3.7
3.8

5
7

General Site Requirements 10


3.2.1
3.2.2
3.2.3

3.3
3.4
3.5

Using optical fibers 13


Handling optical fibers 13
Precautions when splicing optical fibers
Splicing optical fibers 15
Repairing optical fibers 15

14

Working With Power 15


Dissipating Static Electricity 16
Preventing card damage and pluggable module damage 18
3.8.1
3.8.2

Handling, installing, storing, or replacing cards and pluggable modules


Transporting cards and pluggable modules 20

3.9 Controlling Equipment Environment 20


Receiving and Unpacking
4.1 Shipment Verification 21
4.2 Package Handling 21
4.3 Unpacking 22
4.3.1
4.3.2

Tools required 22
Unpacking procedure

19

21

22

Installation Information
5.1 Site preparation 25
5.2 Installation Guidelines 26
5.3 SELV Circuits 26
5.4 Telecommunication Network 27
5.5 TNV Circuit 27
5.6 Installation Items 27
5.7 Installation of the chassis into the rack 28

25

Installation and Commissioning Procedures Version 1.0

iv Table of Contents

5.8

Cabling 29
5.8.1

Labeling cables and optical fibers

29

5.9 Connection 48V Earthing Cable 29


5.10 Power Connection 30
5.10.1
5.10.2

DC Power Connection
AC Power Connection

30
31

5.11 Alarm/Diag Cable Connection 31


5.12 Clock Cable Connection 33
5.13 Network Management System (NMS) Interface Connection 34
5.14 Craft/F1 Cable Connection 35
5.15 E1 Connection 36
5.16 E3/DS3 Connection 37
5.17 Ethernet Connection 38
5.18 STM-1 Connection 39
Nodal Commissioning
41
6.1 Connecting the PC to the NMS interface of the network element 42
6.2 Logging into an Uncommissioned Network Element 43
6.2.1

6.3
6.4

Software delivery from SLAT page

45

Initialising the Network Element 46


Verifying the Serial Numbers of the Cards and the Pluggable Modules
of the Network Element 49
6.5 Setting the Network Element Date and Time 50
6.6 Nominating a Synchronization Reference Clock Source to a Network
Element 52
6.7 Backing up or Restoring the Network Element Configuration Data 53
System Testing
55
7.1 Testing STM-1 Protection Switching with Traffic on the E1 Interface 56
7.2 Testing STM-1 Protection Switching with Traffic on the E3 Interface 60
7.3 Testing STM-1 Protection Switching with Traffic on Ethernet (FE/FX)
Interface 64
7.4 Testing the Timing Source of the Network Element 68
7.5 Verifying Association between Network Elements 76
Network Reconfiguration
77
8.1 SNCP 77
8.2 Adding a Network Element to a Ring Configuration 78
8.3 Deleting a Network Element from a Ring Configuration 82
Recording Data and Test Results
85
9.1 Form 1 86
9.2 Form 2 86
9.3 Form 3 88
9.4 Form 4 88
9.5 Form 5 88
Appendix A: Common Procedures
89
10.1 Cleaning Optical Connectors 89

TJ100CPr4

Table of Contents v
10.1.1
10.1.2

Required tools 90
Inspecting the fiber connector

90

10.2 Fiber Connector Cleaning 92


Appendix B: Connector Pin Assignment
11.1 Power Connector 95
11.2 Alarm/Diag Connector 95
11.3 Clock Connector 96
11.4 NMS Connector 96
11.5 Craft/Modem Connector 97
11.6 E1 (EURO) Connector 98
Appendix C: Cable Color Coding
12.1 Power Cable 101
12.2 Alarm Cable 101
12.3 Clock Cable 102
12.4 Craft/F1 Cable 102
12.5 E1 Cable 103
12.6 Diag Cable 103
12.7 NMS Cable 103
Appendix D: General Configuration
13.1 Accessing and Configuring TJ100CPr4 105
13.1.1

13.2
13.3
13.4
13.5
13.6
13.7
13.8

Logging to the System

95

101

105

106

Configurating Optical Ports 107


Configuring OSPF Parameters 107
Accessing TJ100CPr4 remotely (using router ID) 108
Configuring E1 110
Configuring E3 111
Configuring Ethernet ports 112
Configuring VCG ports 113

13.8.1
13.8.2

Adding new VC 113


Provisioning Cross Connect

114

13.9 Configuring Timing Manager 115


13.10 Checking Alarms 116
13.11 Port settings of Hyper terminal 117
Glossary
Index

119
121

Installation and Commissioning Procedures Version 1.0

vi Table of Contents

TJ100CPr4

1
About This Document

1-

This document version supersets all the previous versions. Any


network element has to be first installed and then commissioned.
Hence this document contains two sections:
Installation Procedures
Commissioning Procedures

1.1

Installation
Installation Procedure comprises of :
receiving and unpacking the network element
installation of the chassis on the rack
peripheral cabling

1.2

Commissioning
Commissioning is the formal handover of operational and
maintenance responsibility for the end-product from the vendor to
the operator.
Commissioning Procedure comprises of :
operation
performance qualification
This process includes environmental compliance checks, verification
of personnel protection equipment and qualification of containment
systems.

Installation and Commissioning Procedures Version 1.0

2 About This Document

Figure 1-1 shows the commissioning flow chart.


Figure 1-1
Commissioning flowchart

Equipment arrives at site, unpack it

Verify shipment

Install the network element in the rack

I
N
S
T
A
L
L
A
T
I
O
N

Connect the power cable to the network element

Power up the network element

Set the Ethernet IP, subnet mask length and router ID on the
network element

Perform tests on a standalone network element

Connect Traffic cables.


Perform system tests on the network element

The network element is ready to carry live traffic

TJ100CPr4

C
O
M
M
I
S
S
I
O
N
I
N
G

T
E
S
T
I
N
G

About This Document 3

1.3

Audience
This document is intended for use by trained installers.

1.4

Reference
This document has references to:
Hardware Description - 104-DOC000025-E
User Interface Guide - 104-DOC000027-E

Installation and Commissioning Procedures Version 1.0

4 About This Document

TJ100CPr4

2
Technical Support Information

1-

This chapter provides technical assistance service phone numbers and


E-mail IDs.
Queries

Contact

For problems that affect service

91-98452-73914
91-80-26591082
91-80-41474440

For 24 hour emergency recover or software


upgrade support
Restoration of service for equipment that has
been carrying traffic
Issues that prevent traffic protection switching
Issues that prevent completion of software
upgrades

For problems that do not affect service


For assistance on technical support and upgrade
notification
For any queries mail to

91-98452-73914
91-80-26591082
91-80-41474440
support@india.tejasnetworks.com

For queries regarding the document


mail

docs@india.tejasnetworks.com

Installation and Commissioning Procedures Version 1.0

6 Technical Support Information

TJ100CPr4

3
Observing Safety Guidelines

1-

This chapter contains safety guidelines that you must follow for
personal safety and to operate the equipment correctly.
Tejas Networks documentation contains precautionary messages and
safety procedures that refer to specific tasks or conditions. You must
read and follow all the precautionary messages before you start to
work on the equipment.
Audience
Personnel working directly on equipment must be
trained, authorized, and qualified to carry out the tasks required
able to follow safety guidelines specific to the product and all local
customer-specific safety procedures
Precautionary messages
To prevent personal injury, equipment damage, and service
interruptions, you must follow all precautionary messages in Tejas
Networks documentation and all local safety standards required by
your company.

Installation and Commissioning Procedures Version 1.0

8 Observing Safety Guidelines

The following precautionary messages appear in Tejas Networks


documentation:
CAUTION
Risk of damage to cards/ interruption to service
A precautionary message with this symbol indicates a risk of static
damage to cards. Use antistatic protection.
This symbol also indicates a risk of service interruption or equipment
damage.

DANGER
Risk of personal injury
A precautionary message with this symbol indicates a risk of
personal injury.

Figure 3- 1 indicates the presence of a LASER source in the card.


Figure 3- 1
Laser source indication

TJ100CPr4

Observing Safety Guidelines 9

3.1

Safety Recommendations
3.1.1

3.1.2

Guidelines to ensure general safety


Keep the chassis clear and dust-free during and after installation.
Keep tools away from walk areas where you and others could fall
over them. Do not wear loose clothing that could get caught in the
chassis. Fasten your tie or scarf and roll up your sleeves.
Wear safety glasses if you are working under any conditions that
might be hazardous to your eyes.
Do not perform any action that creates a potential hazard to
people or makes the equipment unsafe.
Maintaining safety with electricity
Follow these guidelines when working on equipment powered by
electricity:
Locate the emergency power-off switch for the room in which you
are working. Then, if an electrical accident occurs, you can act
quickly to turn off the power.
Disconnect all power by turning off the power and unplugging the
power cord before:
Installing or removing a chassis
Working near power supplies

Do not work alone if potentially hazardous conditions exist.


Never assume that power is disconnected from a circuit, always
check the circuit.
Look carefully for possible hazards in your work area, such as
moist floors, ungrounded power extension cables, frayed power
cords, and missing safety grounds.
If an electrical accident occurs, proceed as follows:
Use caution; do not become a victim yourself.
Turn off power to the system.
If possible, send another person to get medical aid. Otherwise, assess
the condition of the victim and then call for help.
Determine if the person needs rescue breathing or external cardiac
compressions, then take appropriate action.

Installation and Commissioning Procedures Version 1.0

10 Observing Safety Guidelines

3.1.3

Preventing electrostatic discharge damage


Electrostatic discharge (ESD) can damage equipment and impair
electrical circuitry. ESD damage occurs when electronic components
are improperly handled and can result in complete or intermittent
failures.
Always follow ESD-prevention when removing and replacing
components. Ensure that the chassis is electrically connected to
earth ground. Wear an ESD-preventive wrist strap, ensuring that
it makes good skin contact. Connect the grounding clip to an
unpainted surface of the chassis frame to safely ground ESD
voltages. To properly guard against ESD damage and shocks, the
wrist strap and cord must operate effectively. If no wrist strap is
available, ground yourself by touching the metal part of the
chassis.
For safety, periodically check the resistance value of the antistatic
strap, which should be between 1 and 10 megohms (Mohms).

3.2

General Site Requirements


This section describes the requirements your site must meet for safe
installation and operation of your system. Ensure that your site is
properly prepared before beginning installation.
3.2.1

Site environment
Content Networking equipment can be mounted in a rack. The
location of the equipment and the layout of your equipment rack or
wiring room are extremely important for proper system operation.
Equipment placed too close together, inadequate ventilation, and
inaccessible panels can cause system malfunctions and shutdowns,
and can make system maintenance difficult.
When planning your site layout and equipment locations, keep in
mind the precautions described in the section preventive site
configuration to help avoid equipment failures and reduce the
possibility of environmentally caused shutdowns. If you are currently
experiencing shutdowns or unusually high errors with your existing
equipment, these precautions may help you isolate the cause of
failures and prevent future problems.

TJ100CPr4

Observing Safety Guidelines 11

3.2.2

Preventive site configuration


The following precautions will help you plan an acceptable operating
environment for your equipment and will help you avoid
environmentally caused equipment failures:
Electrical equipment generates heat. Ambient air temperature
might not be adequate to cool equipment to acceptable operating
temperatures without adequate circulation. Ensure that the room
in which you operate your system has adequate air circulation.
Always follow the ESD-prevention procedures described
previously to avoid damage to equipment. Damage from static
discharge can cause immediate or intermittent equipment failure.
Ensure that the chassis cover is secure. The chassis is designed to
allow cooling air to flow effectively within it. An open chassis
allows air leaks, which may interrupt and redirect the flow of
cooling air from internal components.
CAUTION
Risk of damage to the equipment
Proper hydraulic/pneumatic material handling equipment must be
used for mounting the equipment. If the network element is heavy
and the hydraulic equipment is not available then ensure that atleast
two installers are at the installation site.

Installation and Commissioning Procedures Version 1.0

12 Observing Safety Guidelines

3.2.3

Configuring equipment racks


The following tips will help you plan an acceptable equipment rack
configuration:
Enclosed racks must have adequate ventilation. Ensure that the
rack is not overly congested, because each unit generates heat. An
enclosed rack should have lowered sides and a fan to provide
cooling air.
When mounting a chassis in an open rack, ensure that the rack
frame does not block the intake or exhaust ports. If the chassis is
installed on slides, check the position of the chassis when it is
seated all the way into the rack.
In an enclosed rack with a ventilation fan in the top, excessive heat
generated by equipment near the bottom of the rack can be drawn
upward and into the intake ports of the equipment above it, in the
rack. Ensure that you provide adequate ventilation for equipment
at the bottom of the rack.
Baffles can help to isolate exhaust air from intake air, which also
helps to draw cooling air through the chassis. The best placement
of the baffles depends on the airflow patterns in the rack.
Experiment with different arrangements to position the baffles
effectively.

3.3

Power Supply Considerations


Check the power at your site to ensure that you are receiving proper
power (free of spikes and noise). Install a power conditioner if
necessary.
DC power supplies operate at a range of -40 volts DC to -60 volts DC.
AC power supplies operate at a range of 165 volts AC to 240 volts AC.

3.4

Safety Standards
Tejas Networks network elements conform to all relevant safety
standards. The network element complies with the following safety
standards:
IEC/EN 60950-1:2001 and UL 60950Information technology
equipment - Safety, Part 1: General requirements
IEC 60825-1:2001 and IEC 60825-2:2004 Safety of Laser
Products

TJ100CPr4

Observing Safety Guidelines 13

3.5

Laser RadiationOptical Transmission Systems


Tejas Networks optical products use laser or light-emitting diode
(LED) sources that emit light energy into optical fibers. This energy
is within the red (visible) and infrared (not visible) areas of the
electromagnetic spectrum.
3.5.1

Using optical fibers


Optical fibers are either single mode or multiple mode. The
information in the following paragraphs applies to all optical fibers.

3.5.2

Handling optical fibers


When you handle optical fibers, you must take the following
precautions:
Wear safety glasses when you install optical fibers.
CAUTION
Risk of laser radiation exposure
Do not look directly into the optical beam. Invisible light can severely
damage your eyes. Keep all optical connectors capped.

Do not look into the opening of an optical fiber, or the opening


of an optical fiber connector, if the optical fiber is active or the
unit has the power turned on.
Avoid direct exposure to optical fiber ends or optical connector
ends where you can access the laser signal directly.

Installation and Commissioning Procedures Version 1.0

14 Observing Safety Guidelines

3.5.3

Precautions when splicing optical fibers


When you splice optical fibers, you must take the following
precautions:
Clean your hands after you handle optical fibers. Small pieces of
glass are not always visible and can damage your eyes.
CAUTION
Risk of eye injury
If you have a piece of a glass in your eye, get medical assistance
immediately.

Do not handle pieces of optical fiber with your fingers. Use


tweezers (preferably non metallic) or adhesive tape to lift and
discard any loose optical fiber ends.
Wear rubber gloves when you clean optical connectors. The
gloves prevent direct contact with the isopropyl alcohol and
prevent contamination of the ferrules with skin oils.
Place all optical fiber clippings in a plastic container provided for
that purpose.
Handle optical fibers with caution. Place the optical fibers in a safe
location during installation.
Protect all optical fiber connectors with clean dust caps at all
times.
Follow the manufacturer instructions when you use an optical test
set. Incorrect calibration or control settings can create hazardous
levels of radiation.

TJ100CPr4

Observing Safety Guidelines 15

3.5.4

Splicing optical fibers


When you must look at a spliced optical fiber with a small magnifier,
take the following precautions:
Power off all laser sources to the optical fiber or disconnect the
remote optical fiber end from the laser sources before you start
splicing. Make sure that all laser sources remain disconnected or
have the power turned off. The laser sources can be in a central
office, on subscriber premises, or in a remote location.
Disconnect all optical test sets from the optical fiber before you
start splicing. The connections can be local or remote.
Use only the optical instruments approved by your company.

3.5.5

Repairing optical fibers


When an accidental break occurs in the optical fiber, do the following:
Report the location of the damaged optical fiber to both the
central office and the field repair personnel.
Power down all laser sources to the optical fiber or disconnect the
remote optical fiber end from the laser sources. The laser sources
can be in a central office, on subscriber premises, or in a remote
location.

3.6

Working With Power


DANGER
Risk of electrical shock
The battery feeds can be at a high enough potential to constitute a
shock hazard. Read and understand the power procedures you are
performing. Take necessary precautions and use the appropriate
insulated tools when working with power.

CAUTION
Risk of personal injury, energy hazard
The battery feeds are capable of supplying very high current which,
during an unintentional short, can cause burns. Read and
understand the power procedures you are performing. Take
necessary precautions and use the appropriate insulated tools when
working with power.

Installation and Commissioning Procedures Version 1.0

16 Observing Safety Guidelines

When you install power feeds to the product input terminals or if you
perform routine power maintenance, make sure that you do the
following:
Read and understand the power procedures you are performing.
Take the necessary precautions and use the appropriate insulated
tools to perform any tasks.
A continuously lit green LED at the faceplate on the base card
indicates that the card is functioning correctly and is powered up. If
the green LED on the base card is lit, the power at the associated
feeder is present and the conditions can be assumed to be normal.
If the green LED on the base card is not lit, the possible causes can
include, but are not limited to:

damaged or non-functional power supply unit


damaged or non functional base card
feeder low voltage or power failure
an over-current fail
A reverse polarity condition at the input terminals has caused a
fuse in the power supply unit to blow

The circuit breaker on the power supply unit is an electronic circuit


breaker. A circuit breaker cuts of the power to the card on
over-current condition.

3.7

Dissipating Static Electricity


The level of static electricity increases on your body when you move
around or come into contact with other charged surfaces. Excessive
levels of static electricity can damage equipment. You must either
wear a properly functioning heel grounder (that attaches to your leg
and foot) and/or an antistatic wrist-strap, or another personal
grounding device when you work on any of the following:
network element chassis (including the metal frame and cover)
cables connected to cards
cards

TJ100CPr4

Observing Safety Guidelines 17

Note : Heel grounders or similar worn footwear attachments work when the floor is
designed to dissipate static electricity. Also check for the ESD foot wear
attachment connectivity to ground using suitable ESD tester. If the properties
of the floor are unknown or in doubt, use a wrist-strap and make sure it is
connected to a piece of electrostatic discharge (ESD) grounding equipment
before proceeding with any maintenance or installation activity.

Any one of the previously mentioned grounding devices dissipate


electrostatic charges to the ground quickly and safely. Use grounding
devices correctly to eliminate the ESD threat you pose to the
equipment.
When you wear an antistatic wrist-strap or a heel grounder, you must
make sure the grounding straps are in contact with a moist part of
your skin. Connect the grounding cord to the grounding plug on a
grounded fixture of the product you are working on, such as the shelf
ESD jack. Grounded fixtures are accessible on most Tejas Networks
products.
The following guidelines provide optimal electrostatic discharge
protection:
Install bays on conductive floor coverings.
Provide conductive shoes, antistatic wrist-straps, and heel
grounders to all personnel working on the equipment.
Maintain local environmental conditions so that relative humidity
around equipment to be serviced is in excess of 20% (preferably
higher than 40%). This lowers the threat of developing damaging
electrostatic levels.
You can implement an ESD training and control program that
educates personnel on the hazards of ESD and simple mitigation
procedures that can easily be applied.

Installation and Commissioning Procedures Version 1.0

18 Observing Safety Guidelines

3.8

Preventing card damage and pluggable module damage


Note : In this section, the generic term card is used to refer to cards or pluggable
modules as applicable.

All cards are subject to damage by rough handling or by electrostatic


discharges. Review the following sections for more information on
how to prevent damage to cards. If Tejas Networks ships cards
separately from the network element shelf, then these cards can come
in shielded containers marked with the following symbol:
ATTENTION: Follow precautions for handling electrostatic
sensitive devices

TJ100CPr4

Observing Safety Guidelines 19

3.8.1

Handling, installing, storing, or replacing cards and pluggable


modules
When you handle, install, or replace cards, you must take the
following precautions:
Wear an antistatic wrist-strap, a heel grounder, or another personal
grounding device before you remove a module from its package or
from the shelf.
Follow installation and removal procedures for each module.
Make sure to understand and perform each precautionary message
in these procedures (for example, opening/closing the latches of
the card simultaneously).
Do not touch the solder side of the module, the pin connector, or
the components.
Inspect all pin connectors on each module for damage before use.
Inspect each module for damage before you insert the component
into the shelf.
Store uninstalled cards separately in a shielded box.
Do not stack cards on or against each other.
Do not force cards into their packaging material.
Do not store several cards in the same container.
Allow each module to reach room temperature before you insert
the module into the shelf.
Protect all optical connectors of the transmit (Tx) and receive (Rx)
optical cards with clean dust caps at all times.
Store pluggable modules in their protective static-dissipative
containers (when not in use) to prevent damage to the exposed
connector terminals.
Leave spare cards in the original shielded containers until you need
the cards. To prevent damage to cards in storage, follow procedures
that prevent:
accumulation of dirt or dust on the pin connectors
damage to the printed-circuit board or its components
wrappage (of printed-circuit boards stored in areas where the
humidity can exceed 95% and the temperature can exceed 70C)

Installation and Commissioning Procedures Version 1.0

20 Observing Safety Guidelines

3.8.2

3.9

Transporting cards and pluggable modules


When you transport cards, pack each module in its original shielded
container and padding, or in an electrostatically shielded bag. If you
lose the original material, place the module in a shielded bag and use
another container with sufficient padding.

Controlling Equipment Environment


The maximum operational long-term ambient temperature of the
system location is 40C. A temperature above 40C is permissible
(according to ETSI EN 300 019-1-3 V2.1.2 Edition 2003-04 for
Environmental Class 3.1: Temperature controlled locations and ETSI
EN 300 019-2-3 V2.1.2 for Environmental Class T3.1 and T3.1E:
Temperature controlled locations) provided the probability of
occurrence is less than 1%. A temperature of 50C is permissible but
the duration should not exceed 72 continuous hours.

TJ100CPr4

4
Receiving and Unpacking

1-

This chapter describes the procedure to be followed when TJ100CPr4


equipment is delivered to the customer as part of a supply-only
contract.

4.1

Shipment Verification
The TJ100CPr4 network element is delivered in one carton and all the
accessories in another. Compare the package list information with the
alphanumeric information provided on the shipping labels. The
package list and shipping labels should contain the same information.
If there are any discrepancies between the shipping label information
and the package list information, call the Tejas Networks Technical
Assistance Center (TAC).

4.2

Package Handling
Identify the top face of the container, (identifiable by packing labels)
and keep the top face uppermost at all times. The package contents
are to be considered fragile at all times. If packages are to be handled
in wet weather conditions, adequate waterproofing is a must to
protect the package.

Installation and Commissioning Procedures Version 1.0

22 Receiving and Unpacking

4.3

Unpacking
Consider the following points while unpacking and storing the
TJ100CPr4 equipment:
Leave the equipment packed unless it is installed immediately.
Store the packed equipment in the temperature and environmental
conditions described in the Hardware Description,
104-DOC000007-E.
Preserve the packing material (after unpacking the equipment) for
future use in case the equipment must be returned.
If the packaging is damaged and possible equipment damage is
present, preserve as much of the packaging as possible to allow
customer service and the shipper to analyze the damage. To report
damage to shipped articles, contact the Tejas Networks Technical
Assistance Center (TAC) to open a Return Materials
Authorization (RMA).
4.3.1

Tools required
The following tools are required to unpack a TJ100CPr4 equipment:
Sharp pointed blade/knife
Conductive bonded wrist strap

4.3.2

Unpacking procedure
CAUTION
Static sensitive devices
Static charge can damage the equipment. While unpacking and
handling cards, or making network element interconnections, wear a
grounding wrist strap to discharge the static buildup.

Procedure
Step Action

TJ100CPr4

Remove the plastic shrink-wrap and open the top of the


cardboard shipping container.

Pick the TJ100CPr4 documentation CD-ROM out of the


shipping container.

Receiving and Unpacking 23

Remove the TJ100CPr4 network element out of the shipping


container.

Take the equipment out of the plastic protective bag.

The TJ100CPr4 shipping container contains the following items:


One TJ100CPr4 configured as ordered

Installation and Commissioning Procedures Version 1.0

24 Receiving and Unpacking

TJ100CPr4

5
Installation Information

1-

This chapter provides information on installing a TJ100CPr4 network


element.

Note : The instructions in this chapter primarily address the installation of the
TJ100CPr4 network element and cards supplied by Tejas Networks. The
installation of racks, electrical wiring, raceways, and other equipment are not
covered in this guide. The relevant local/state/federal or international (if
applicable) codes and regulations should be followed when assembling the
same.

5.1

Site preparation
The installation site should meet the following criteria:
All the environmental specifications as mentioned in the
Hardware Description, 104-DOC000025-E.
The power supply requirements as given below:
Equipment type DC -40 to -60V DC
Equipment type AC 165 V to 240 V AC

The circuit breakers requirements as given below:

Circuit breaker 2A

Installation and Commissioning Procedures Version 1.0

26 Installation Information

5.2

Installation Guidelines
The guidelines for TJ100CPr4 network element installation are:
Consider the effect of additional electronic equipment and its
generated heat on the TJ100CPr4 network element.
Make sure the equipment rack is properly bolted to the ground.
Ensure that the weight of the equipment does not make the rack
unstable.
When mounting the equipment between two posts or rails, ensure
that minimum clearance between the sides is 485 mm.
Install the first network element of the rack in the lowest possible
position.
Ensure that the wire size and dimension requirements are based
on cable length and local engineering standards and practices.
Note 1: The TJ100CPr4 network element must only be installed in a Restricted
Access Location (RAL) in accordance with IEC 60950. In this context,
restricted access locations are defined as locations where access can be
restricted to suitably trained personnel and where unsupervised members (of
the general public) are not allowed.

Note 2: The TJ100CPr4 must be properly installed in a rack with brackets or in other
ways properly connected to a safety ground. The TJ100CPr4 AC/ DC must not
be powered on from a source external to the Restricted Access Locaion (RAL).
All the electrical interfaces used must be limited to Safety Extra-Low Voltage
(SELV).

Definitions
5.3
SELV Circuits
SELV circuits are ports that have maximum DC working voltage level
less than 60 V (42.4 V AC). In addition, the ports must not be
connected to telecommunication networks as defined in EN 60950
(see CEI/ IEC 60950-1 2001-10, standard clause 1.2.13.8).

TJ100CPr4

Installation Information 27

In practice, the electrical cables shall not exit the building. In addition,
the electrical cables shall connect to an equipment that meets one of
the following requirements:
Installed in the RAL
Does not have electrical cables that exit the building unless those
ports are Telecommunication Networks Voltage circuits (TNV)

5.4

Telecommunication Network
A telecommunication network is a metallically terminated
transmission medium intended for communication between
equipment that may be located in separate buildings, excluding:
SELV circuits connecting units of information technology
equipment
Main network element for supply, transmission and distribution of
electrical power, if used as a telecommunication transmission
medium
Cable distribution network element

5.5

TNV Circuit
A TNV circuit is so designed and protected that, under normal
operating conditions and single fault conditions (see CEI/IEC
60950-1 2001-10, standard clause 1.4.14), the voltages do not exceed
specified limit values.

5.6

Installation Items
In addition to the standard installers tool kit provided by us, the
following items are also required for installation:
Phillips screwdriver (PH3) to attach the TJ100CPr4 to the rack
Phillips screwdriver (PH1) to attach the earth cable to the
TJ100CPr4
4 mounting screws, M6 and nuts
Power cable
Earth cable
Plugs for optical adapters
Cable ties

Installation and Commissioning Procedures Version 1.0

28 Installation Information

5.7

Installation of the chassis into the rack

Procedure
Step Action
1

Depending on the access requirements, front or rear access,


decide which side you want to use as the front side in the rack.

Move the TJ100CPr4 network element to the desired rack


position.

Affix the TJ100CPr4 to the rack with four M6 screws and nuts
as shown in Figure 5-1.

Figure 5-1 shows the installation points on the chassis.


Figure 5-1
Installation of the chassis to the rack




TJ100CPr4




Installation Information 29

5.8

Cabling
5.8.1

5.9

Labeling cables and optical fibers


All the cables and optical fibers used for connectivity should be
labeled according to the site engineering practices.

Connection 48V Earthing Cable


The TJ100CPr4 is grounded via the 48V power connector to the rack
ground.
230V earth connection

The TJ100CPr4 network element is grounded via an external screw


terminal to the building earth. This option is to be used only when the
network element is not installed in a rack. The location of the screw
terminal is on the rear- left of the network element.
Procedure
Step Action
1

Remove the phillips screw from the TJ100CPr4 network


element.

Affix the earth cable to the network element.

Verify that the ground cable is secured firmly to the network


element.

Route the earth cable securely along the rack and connect it
according to local site practice.

Installation and Commissioning Procedures Version 1.0

30 Installation Information

5.10

Power Connection
5.10.1 DC Power Connection
The TJ100CPr4 can be powered using a regular telecommunication
power supply of -48 V DC with a -48 V return.
1

Ensure that the circuit breaker feeding power to the


TJ100CPr4 network element is switched off.

Plug in the power cable to the power supply connector.

If the network element is DC powered, secure the connector


with screws to the network element.

Route the power cable securely along the left side of the rack
and connect it to power distribution panel.

Note : Confirm whether the DC power cable color coding is consistent with the details
given in section 12.1of Appendix C: Cable Color Coding, before the network
element is powered ON. The TJ100CPr4 network element is protected against
reversed polarity and will not switch ON if the power connections are reversed.

Figure 5-2 shows the location of the DC power connector on the


TJ100CPr4 network element.
Figure 5-2
Connecting the DC power cable

DPSU01
GND

OFF

TJ100CPr4

ON

48VDC2A
M-GND

-48V

Installation Information 31

5.10.2 AC Power Connection


The AC power supply consists of two main blocks namely, EMI filter
and AC-DC convertor.
1

Ensure that the circuit breaker feeding power to the


TJ100CPr4 network element is switched off.

Plug in the power cable to the power supply connector.

Route the power cable securely along the left side of the rack
and connect it to power distribution panel.

Figure 5-3 shows the location of the AC power connector on the


TJ100CPr4 network element.
Figure 5-3
Connecting the AC power cable

APSU01
1((

5.11

10

Alarm/Diag Cable Connection


The Alarm cable consists of 7 twisted pair cables fitted, with 15 way
D-type connector. The connector pinouts are given in section 11.2 of
Appendix B: Connector Pin Assignment.
The TJ100CPr4 supports 2 external alarm inputs and 4 external alarm
outputs.
The TJ100CPr4 allows diagnosis through an 15 way D-type
connector available on the base card. This connector will be used for
both Alarm and diagnostic.

Installation and Commissioning Procedures Version 1.0

32 Installation Information

Procedure
Step Action
1

Identify and label the cable.

Connect the cable to 15 way D-type connector accordingly as


indicated by the arrow-heads marked against the connector,
and secure the connector with screws to the network element.

Figure 5-4 shows the location of the Alarm/Diag port on the


TJ100CPr4 network element.
Figure 5-4
Connecting the alarm cable

TJ100CPr4

Installation Information 33

5.12

Clock Cable Connection


The synchronization connectivity is allowed through 9 way D-type
connector on the base card.
The connector pinouts are given in section 11.3 of Appendix B:
Connector Pin Assignment.

Procedure
Step Action
1

Identify and label the cable.

Connect the cable to D-type CLOCK connector, and secure


the connector with screws to the network element.

Route the CLOCK cable securely along the right side of the
rack.

Figure 5-5 shows the location of the BITS CLOCK connector on the
TJ100CPr4 network element.
Figure 5-5
Connecting the clock cable

Installation and Commissioning Procedures Version 1.0

34 Installation Information

5.13

Network Management System (NMS) Interface Connection


The TJ100CPr4 allows external access through an RJ45 connector.
For external connection through a hub, a straight cable is used and to
access directly from PC or Laptop, a crosscable is used.
The connector pinouts are given in section 11.4 of Appendix B:
Connector Pin Assignment.

Procedure
Step Action
1

Identify and label the Ethernet cable.

Connect the cable to RJ45 connector, and ensure that retention


slide operates to hold the connector in place.

Figure 5-6 shows the location of the NMS connector on the


TJ100CPr4 network element.
Figure 5-6
Connecting the NMS cable

TJ100CPr4

Installation Information 35

5.14

Craft/F1 Cable Connection


The Craft/F1 access terminal communicate with TJ100CPr4 via a
female RS232 connector. The Craft/F1 interface on the base card can
be used as modem or craft terminal. The connector pinouts are given
in section 11.5 of Appendix B: Connector Pin Assignment.

Procedure
Step Action
1

Identify and label the cable.

Connect the cable to D-Type Craft/F1 connector, and secure


the connector with screws to the network element.

Route the Craft/F1 cable securely along the right side of the
rack.

Figure 5-7 shows the location of the Craft/F1 connector on the


TJ100CPr4 network element.
Figure 5-7
Connecting the Craft/F1 cable

Installation and Commissioning Procedures Version 1.0

36 Installation Information

5.15

E1 Connection
The E1 traffic is received and transmitted from TJ100CPr4 through
the E1 interface on the (PXAT) card. The E1 traffic is received and
transmitted through the TJ100CPr4 network element through Euro
connector.

Procedure
Step Action
1

Identify and label the E1 cables.

Connect the cable to Euro connector, and secure the


connector with screws to the network element.

Route the E1 cables securely along the right side of the rack.

Figure 5-8 shows the location of the Euro connector on the


TJ100CPr4 network element.
Figure 5-8
Connecting the E1 cable

21 Pin Euro Connector

TJ100CPr4

Installation Information 37

5.16

E3/DS3 Connection
The E3 traffic is received and transmitted from the TJ100CPr4
network element through an E3/DS3 interface (PXAT) card.

Procedure
Step Action
1

Identify and label the E3/DS3 cables.

Connect each cable in turn to the transmit and receive ports.

Figure 5-10 shows the location of the Ethernet ports on the Ethernet
card of the TJ100CPr4 network element.
Figure 5-9
Connecting the E3 cables



Installation and Commissioning Procedures Version 1.0

38 Installation Information

5.17

Ethernet Connection
The Ethernet traffic is received and transmitted from the TJ100CPr4
network element through an Ethernet interface (PXAT) card. The
connectivity is made through an RJ45 connector.

Procedure
Step Action
1

Identify and label the Ethernet cables.

Connect the cable to RJ45 connector, and ensure that retention


slide operates to hold the connector in place.

Figure 5-10 shows the location of the Ethernet ports on the Ethernet
card of the TJ100CPr4 network element.
Figure 5-10
Connecting the Ethernet cables
10/100 baseT FE ports

 

10/100 baseT FX ports

TJ100CPr4

Installation Information 39

5.18

STM-1 Connection
The STM-1 traffic is received and transmitted from the TJ100CPr4
network element through two optical transceivers operating at STM-1
line rate.

Note : Some long haul SFPs will not measure receive power beyond (-8.5dbm).
Hence, before connecting long haul lasers, check with the optical power meter.

Procedure
Step Action
1

Identify and label the optical ports.

Connect the cable to the optical ports securely.

Figure 5-11 shows the location of the STM-1 optical ports on the
TJ100CPr4 network element.
Figure 5-11
Connecting to the STM-1 ports



Installation and Commissioning Procedures Version 1.0

40 Installation Information

TJ100CPr4

6
Nodal Commissioning

1-

This chapter provides the commissioning procedures you must


perform on a newly installed network element. Nodal commissioning
is performed using the web user interface by entering the
commissioning data of the network element. Table 6-1 lists the
procedures that are performed during commissioning.
Table 6-1
Nodal commissioning procedure list
1

Connecting the PC to the NMS interface of the network element

Logging into an Uncommissioned Network Element

Initialising the Network Element

Verifying the Serial Numbers of the Cards and the Pluggable Modules of the Network
Element

Setting the Network Element Date and Time

Nominating a Synchronization Reference Clock Source to a Network Element

Backing up or Restoring the Network Element Configuration Data

Note : The commissioning data record form is used to record the commissioning data
of a network element.

Installation and Commissioning Procedures Version 1.0

42 Nodal Commissioning

6.1

Connecting the PC to the NMS interface of the network


element

Pre-requisites
Make sure that you have a PC and an Ethernet cross-over cable
with an RJ-45 connector.
Make sure you have the network element IP address information
if the network element has already been commissioned.
Note 1: The IP address must be in the 192.168.1.xxx network, where xxx is between
1 and 253.

Note 2: After powering up the network element you have to wait for approximately 5
minutes for the network element software to be up. The Status/Active LED
indicates the up status of the network element.

Note 3: You have connected the PC to the NMS interface of the network element.

If the expected results do not occur :


Make sure the type of cable used is correct
Contact your next level of support

Procedure
Step Action
1

Connect the NMS port of the network element and the PC


terminal with an Ethernet cable of the RJ-45 connector type.

Configure the IP address of the PC to be in the same subnet as


the network element.

Note : When connecting to an uncommissioned network element, your PC IP address


must be 192.168.1.xxx where xxx is between 1 and 253. When connecting to a
commissioned network element, your PC IP address must reside in the same
subnet as the network element. Also, configure the PC subnet mask to match
the network elements subnet mask and the PC default gateway must be in the
same LAN as the gateway.

TJ100CPr4

Nodal Commissioning 43

6.2

Logging into an Uncommissioned Network Element

Pre-requisites
Ensure that the PC is connected to the NMS interface of the
network element through a cross-over cable with RJ-45
connectors.
Launch the Netscape 4.75/Mozilla/Internet Explorer browser.
CAUTION
Change the initial password of the default user account on the
network element. The default user accounts and passwords are
widely known.

Procedure
Step Action
1

Launch the Netscape 4.75/Mozilla/Internet Explorer browser


and enter the URL http://192.168.1.254:20080/

Determine your next step.


If
the login screen appears
the network element does not respond

Then go to
step 3
step 4

At the login prompt, enter the default userid and password.


where
userid
password

tejas
j72e#05t

The Navigation menu of the network element is displayed.


Note : Node View is the default page of the WUI.

Installation and Commissioning Procedures Version 1.0

44 Nodal Commissioning

Determine your next step.


If
login

Then
completed the
procedure
step 5

login failed

Check for physical connection. Otherwise, contact your next


level of support.

Check if you have entered the correct userid and password.


where
userid
password

tejas
j72e#05t

Otherwise, you have completed the procedure.


The userid and the password rules are given below:
Userid

is unique.
can be alphabetic/numeric/alphanumeric.
supports special characters except space.
supports upto 32 characters
is case sensitive.

Password

is unique.
must be exactly eight characters long
can be alphabetic/numeric/alphanumeric.
supports special characters except space.
is case sensitive.
and the user ID should not be identical.

TJ100CPr4

Nodal Commissioning 45

6.2.1 Software delivery from SLAT page


Pre-requisites
Make sure that you have a PC and an Ethernet crossover cable
with an RJ-45 connector.
Make sure you have the network element IP address information
if the network element has already been commissioned.
Procedure
Step Action
1

Connect the laptop with static IP 192.168.1.254 to the node so


that, it can be accessed or use termserver.

Launch the Netscape 4.75/Internet Explorer 6.0/ Mozilla


1.7.15 browser and enter the URL http://192.168.1.254:20080
The page displayed will have the following options:
a. Restore from a previous back up configuration.
b. Initialize node parameters.
c. Please install the software to proceed.

Click on option Please install the software to proceed and the


page displayed will have the following software download
options:
Deliver release from local machine
Deliver release from remote machine
If
Local machine
Remote machine

Then
step 4
step 5

If local machine is selected then, give the path of the file where
the file is saved.

If a remote machine is selected then, provide the user name,


password, IP of remote machine, FTP (optional), directory and
filename.

Click submit, the new software will be downloaded to the NE.


Once the download is completed, a page will be displayed for initializing
the node parameters.

Installation and Commissioning Procedures Version 1.0

46 Nodal Commissioning

Initialize the node parameters (like Node Name, Ethernet IP


address IP and Router ID)

Note : On initializing the node parameters, node will go for warm reboot and while
the node is coming up the software will get initialized on the NE. Once the node
is up, issue a service disruptive reboot for the FPGAs to get programmed on
the NE.

6.3

Initialising the Network Element

Ethernet IP
Each network element has a Network Management System (NMS)
interface which is a 10/100 Mbps Network Interface Controller
(NIC) port. Ethernet IP is the IP address with which the network
element communicates with the external world.

Note : The Ethernet IP address of two network elements in the same ECC Local Area
Network (LAN) must be in different IP segments, if not the OSPF will not
converge. For example, if one network element has Ethernet IP address as
192.168.3.x, the Ethernet IP address of another network element in the same
network must be similar to 192.168.4.x, where the value of x ranges from 1 to
255.

Subnet mask length


The subnet mask length is an optional parameter that corresponds to
the Ethernet IP address. Subnetting is used to set the subnet mask
parameters.

Note : Do not set the subnet mask for a point-to-point connection (that is, a direct
Ethernet connection between the WUI host and the network element).

TJ100CPr4

Nodal Commissioning 47

Pre-requisites
Log into network element WUI
Make sure your PC is correctly connected to the network element
through the NMS interface.
Make sure that you have the Ethernet IP address, router ID,
subnet mask and static route IP of the network element to be
configured.
Make sure the PC is configured in the same LAN as the network
element.
Procedure
Step Action
1

Determine your next step.


If
Then
Initialize data
step 2
Configure network element from existing backup step 11

Click on Initialize Node Parameters.

Enter the network element name in the name field.

Note : The network element name can be alphabetic/numeric/alphanumeric


consisting of 1-20 characters. Special characters can also be used, except
space.

Enter the functional router ID of the network in the router ID


field of the NE information page. Network element uses the
same entered ID for communication over ECC path.

Note 1: The default router ID displayed is 192.168.1.254.

Note 2: The node IP is to be set as 192.168.1.xxx, where xxx must be between 1 to 253.

Note 3: The last octet of the router ID and Ethernet IP must not be provisioned as 0
or 255 as they are of mask length 24.

Installation and Commissioning Procedures Version 1.0

48 Nodal Commissioning

In the Ethernet IP field, the IP address must be entered. The


Ethernet IP of each, network element in the network must be
in different networks and unique.

Note : The default Ethernet IP displayed is 192.168.1.254

Enter the contact and location details in the respective fields.

Select the SDH mode in which the network element needs to


function.

Select STM-1 for the node capacity of the network element.

Click Submit.
A confirmation page is displayed.

10

Click Accept Valid Modifications.


A network element reboot warning is displayed.

Note 1: The network element reboots after the Ethernet IP, subnet mask and the
router ID are entered. After the network element is up, verify whether all the
changes are reflected. If the changes are not reflected correctly, contact your
next level of support.

Note 2: The PC IP configuration must be updated to match the newly provisioned IP


for the network element.

11

Click on the Restore from a previously backed up


configuration.

12

Enter the parameters for restoring configuration.

13

Click Submit.

14

Click on Accept Valid Modifications.


A success message is displayed.

TJ100CPr4

Nodal Commissioning 49

You have completed the network element backup restoration.


CAUTION
Cold restart
Network element goes for a service disruptive reset.

6.4

Verifying the Serial Numbers of the Cards and the Pluggable


Modules of the Network Element
Use this procedure to verify the serial numbers of the chassis and the
circuit packs present in the network element

Pre-requisites
Make sure that you have the shipment report which contains the card
serial numbers.
Procedure
Step Action
1

Click Inventory in the Navigation menu.

Click on Node inventory link.


Node inventory page is displayed.

View the serial numbers of all the cards in the network element
in the Node Inventory page and verify with the serial numbers
provided on the shipment report.

Verify if the PSU circuit pack is listed with the correct


information in the WUI Inventory application.

Verify if the Power LED is turned on with green color for the
PSU circuit pack.

Installation and Commissioning Procedures Version 1.0

50 Nodal Commissioning

6.5

Setting the Network Element Date and Time


Use this procedure to edit the network element date and time.

Procedure
Step Action
Setting the date and time for a network element
1
Click System Time in the Navigation menu.
2

Click Set time link.


Set Node Time page is displayed.

Set date and time by selecting appropriate values from the drop
down menu.

Click Submit.
Changes are applied and a confirmation message is displayed.

Setting the time zone for a network element


5
Click System Time in the Navigation menu.
6

Click Set time zone link.


Set Time Zone page is displayed.

Set the time zone by selecting appropriate value from the drop
down menu.

Click Submit.
Changes are applied and a confirmation message is displayed.

In case the drop down menu does not display the desired time
zone, then click Other Time Zones.
Other time zone page is displayed.

TJ100CPr4

Nodal Commissioning 51

10

Enter the name of the time zone, the Offset value, Enable Day
light saving from drop down menu and set the following Day
light saving time parameters (if applicable).
Month
Week
Day
Hour
Minute

11

Click Submit.
Changes are applied and a confirmation message is displayed.

Setting the time server for a network element


12
Click System Time in the Navigation menu.
13

Click Set time server link.


Set Time Server page is displayed

14

Enable the field NTP Client Enable

15

Enter the IP address of the server from which the network


element has to derive the date and time.

Note 1: Nominate timing server of stratum level of 14 or less than 10. The network
element will not synchronize to the server if the startum level is not within the
range.

Note 2: If TejNMS is used to manage the network element, the first NTP server (NTP
Server-0) will be automatically provisioned. Provision all other time servers
against the remaining NTP servers.

Note 3: It may take the current NTP server parameter upto 5 minutes to update.

16

Select the Synchronization interval from pull-down menu.

17

Click Submit.
Changes are applied and a confirmation message is displayed.

Installation and Commissioning Procedures Version 1.0

52 Nodal Commissioning

6.6

Nominating a Synchronization Reference Clock Source to a


Network Element

Procedure
Step Action
1

Click Configuration in the Navigation menu.

Click Synchronization.

Click Nominate timing reference under Synchronization.


Nominate timing references page is displayed.

Select the clock reference type for a network element in the


Clock Reference field.

Set the clock reference port and the priority for the selected
clock reference.

Click Submit.
Changes are applied and a confirmation message is displayed.

TJ100CPr4

If the clock source is not nominated as expected then, contact


your next level of support.

Nodal Commissioning 53

6.7

Backing up or Restoring the Network Element


Configuration Data

Pre-requisites
Make sure that you have a PC/laptop with a ftp server.
Make sure that you have the IP address of the source/destination
for the restore or backup operation.
Make sure that you have the directory path from where the
configuration file will be restored from or saved to.
Make sure you have the username and password of the ftp
account.
Note : If you have a linux or unix machine, enable the ftp server. If you are using a
windows machine, you must install a ftp server such as 3com. The ftp server
for windows can be got from the following location.

http://support.3com.com/software/utilities_for_windows_32_bit.h
tm
Procedure
Step Action
1

Click Maintenance in the Navigation menu.


Restore/Backup Config Data page is displayed.

Click Configuration Management.

Note : The network element need to be given a cold reboot after restoring the
database for the new configuration to take effect.

Enter the Username and Password of the server from where


you want to restore configuration. Enter the IP address of the
server and Directory where the configuration information is
stored.

Installation and Commissioning Procedures Version 1.0

54 Nodal Commissioning

Determine your next step.


If you want to

Then click
back up the network element Backup configuration

configuration data
restore the previous network Restore configuration
element configuration
restore factory default settings Restore Factory Defaults
5

Click Submit.
Changes are applied and a confirmation message is displayed.

If you are not able to take a back up or restore network element


data then:
Make sure that the data entered is valid
Contact your next level of support

TJ100CPr4

7
System Testing

1-

After commissioning the network element, system level tests are done
with the network elements cabled together in a working ring network.
Table 7-1 lists the procedures for system testing
Table 7-1
System testing procedure list
1

Testing STM-1 Protection Switching with Traffic on the E1 Interface

Testing STM-1 Protection Switching with Traffic on the E3 Interface

Testing STM-1 Protection Switching with Traffic on Ethernet (FE/FX) Interface

Testing the Timing Source of the Network Element

Verifying Association between Network Elements

Note : Refer to the User Interface Guide, 104-DOC000027-E for configuring the
node.

Installation and Commissioning Procedures Version 1.0

56 System Testing

7.1

Testing STM-1 Protection Switching with Traffic on the E1


Interface
This procedure helps you perform the following tests on the network
element:
E1 interface test (both at the near and far end)
Protection switching on the E1 ports

Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have adequate number of optical patch cords.
Make sure that proper cross-connects are provisioned between the
E1 ports and optical ports at the far end and the near end network
elements.
Make sure that you have a variable attenuator.
Procedure
Step Action
1

Connect the test set and the near and far end network elements
as shown in the Figure 7-1.

Select the type of protection required. Daisy-chain the E1 ports


at the near end.

Determine your next step.


If
Then
Sub network connection
Provision the cross- connects between
protection (SNCP) is required. the E1 ports and the optical ports in
SNCP mode.

Daisy-chaining the E1 ports at the near end


4
Connect the Rx of the first E1 port 1 to the Tx of the E1 test
set and Tx of the 16th E1 port to the Rx of the E1 test set as
shown in Figure 7-1.
5

TJ100CPr4

Connect the other consecutive ports in tandem, that is


connecting the Tx of one port to the Rx of the next port of the
same interface.

System Testing 57

Testing all the E1 ports in the E1 interface, both at the near and far end
6
Feed E1 traffic from the test set to the first E1 port and
connect the remaining E1 ports in tandem so that all the ports
are sourced from the same test set.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind the person. Keep all unused optical connectors capped.

Loopback all the E1 ports of the far end network element. The
traffic generated by the test set will be looped back to the test
set. The E1 traffic of the near and far end are connected
through the optical ports and will transport the signal
generated by the test set.

Verify 0 bit errors at the E1 test set.

Record the data.


The result verifies that all the E1 ports and optical ports are functioning
correctly.

Testing protection switching on the E1 ports


10
Select a VC12 path and set the Admin reversion mode as
non-revertive or revertive with max WTR time.
11

Click Submit.
A confirmation page is displayed. On confirming, a success message is
displayed.

12

Connect the test set to a single E1 port.

Installation and Commissioning Procedures Version 1.0

58 System Testing

13

Generate a Loss of Signal condition (LOS) on the working path


by disconnecting the fiber.
Traffic switches from the working to the protection path within 50ms.

14

Put the fiber back on the working path.

15

Determine your next step.


If the protection type is
revertive
non revertive

Then
step 16
step 17

After the WTR time expires, the traffic will switch from protection to the
working path.
16

During WTR, generate a loss of signal condition (LOS) on the


protection path by disconnecting the fiber.
Traffic switches back to the working path within 50ms.

17

Go to step 19.
Generate a loss of signal condition (LOS) on the protection
path by disconnecting the fiber.
Traffic switches from the protection to the working path.

TJ100CPr4

18

Put the fiber back on the protection path.

19

Record data.

System Testing 59

Figure 7-1 shows the set up for testing the E1s interface.
Figure 7-1
E1 test

Near end network element

E1 test set

TP42

E1

NE

Far end network element

O
p
t
i
c
a
l
P
o
r
t
1

Work Path

Protect Path

O
p
t
i
c
a
l

NE

E1

P
o
r
t
2

Variable optical attenuator


Cable with Telco connectors
Optical fiber

Installation and Commissioning Procedures Version 1.0

60 System Testing

7.2

Testing STM-1 Protection Switching with Traffic on the E3


Interface
This procedure helps you perform the following tests on the network
element:
E3 interface test (both at the near and far end)
Protection switching on the E3 ports

Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have an adequate number of optical patch
cords.
Make sure that proper cross-connects are provisioned between the
E3 ports and optical ports at the far end and the near end network
elements.
Make sure that you have a variable attenuator.
Procedure
Step Action
1

Connect the test set and the near and far end network elements
as shown in the Figure 7-2.

Select the type of protection required. Daisy-chain the E3 ports


at the near end.

Determine your next step.


If
Then
Sub network connection
Provision the cross-connects between
protection is required (SNCP) the E3 ports and the optical ports in
SNCP mode.

Daisy-chaining the E3 ports at the near end


4
Connect the Rx of the first E3 port 1 to the Tx of the E3 test
set and Tx of the 3rd E3 port to the Rx of the E3 test set as
shown in Figure 7-2.
5

TJ100CPr4

Connect the other consecutive ports in tandem, that is


connecting the Tx of one port to the Rx of the next port of the
same interface.

System Testing 61

Testing all the E3 ports in the E3 interface, both at the near and far end
6
Feed E3 traffic from the test set to the first E3 port and the
remaining E3 ports are connected in tandem so that all the
ports are sourced from the same test set.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind the person. Keep all unused optical connectors capped.

Loopback all the E3 ports of the far end network element. The
traffic generated by the test set will be looped back to the test
set. The E3 traffic of the near and far end are connected
through the optical ports will transport the signal generated by
the test set.

Verify 0 bit errors at the E3 test set.

Record the data.


The result verifies that all the E3 ports and optical ports are functioning
correctly.

Testing protection switching on the E3 ports


10
Select a VC3 path and set the Admin reversion mode as
non-revertive or revertive with max WTR time.
11

Click Submit.
A confirmation page is displayed. On confirming a success message is
displayed.

12

Connect the test set to a single E3 port.

Installation and Commissioning Procedures Version 1.0

62 System Testing

13

Generate a loss of signal condition (LOS) on the working path


by disconnecting the fiber.
Traffic switches from the working to the protection path within 50ms.

14

Put fiber back on the working path.

15

Determine your next step.


If the protection type is
revertive
non revertive

Then
step 16
step 17

After the WTR time expires, the traffic will switch from protection to the
working path.
16

During WTR, generate a loss of signal condition (LOS) on the


protection path by disconnecting the fiber.
Traffic switches back to the working path within 50ms.

17

Go to step 19.
Generate a loss of signal condition (LOS) on the protection
path by disconnecting the fiber.
Traffic switches from the protection to the working path

TJ100CPr4

18

Put the fiber back on the protection path.

19

Record data.

System Testing 63

Figure 7-2 shows the set up for testing the E3s.


Figure 7-2
E3 test

Far end network element

Near end network element

E3
test set

P1

NE

Optical Port 1

E3

Optical Port 2

Work
Path
E3

NE

P1

Protect
Path

BNC cable
Optical fiber

Installation and Commissioning Procedures Version 1.0

64 System Testing

7.3

Testing STM-1 Protection Switching with Traffic on Ethernet


(FE/FX) Interface
This procedure helps you perform the following tests on the network
element:
Ethernet port test (in the near and far end network elements in
daisy-chain)
VCG interface test (in the near and far end network elements)
Ethernet frame drop test (when optical receiver is underloaded)

Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have adequate number of optical patch cords.
Make sure that proper cross-connects are provisioned between the
Ethernet (FE/FX) ports and optical ports at the far end and the
near end network elements.
Make sure that you have a variable attenuator.
Procedure
Step Action
1

Connect the test set and the near and far end network elements.

Select the type of protection required. Daisy-chain the


Ethernet ports at the near end.
If
Then
Sub network connection
Provision the cross- connects between
protection (SNCP) is required. the VCG ports and the optical ports in
SNCP mode.

Ethernet port testing and VCG interface test(at the near end and far end
network elements)
3
Create VCG associations between the Ethernet ports in SNCP
mode.

TJ100CPr4

System Testing 65

Daisy-chain the Ethernet ports of the near end network


element as shown in the table below.

Table 7-2
Daisy-chain the Ethernet ports at Far end

From port

to

cable used for


connectivity

Ethernet test set

one

straight

two

Ethernet test set

straight

Three

four

fiber cable

From port

to

cable used for


connectivity

One

Two

fiber cable

Three

four

fiber cable

Table 7-3
Daisy-chain the Ethernet ports at Near end

Generate traffic with the Ethernet test set (full duplex) and
verify that no packets are lost.

Record the data. The result verifies that all the Ethernet ports
and optical ports function correctly.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind the person. Keep all unused optical connectors capped.

Installation and Commissioning Procedures Version 1.0

66 System Testing

Determine your next step.


If protection
mode is of
SNCP

Then
set the reversion mode as non-revertive or revertive
with max WTR time for each VC in the VCG for
the Ethernet port under test.

Click Submit.

A confirmation page is displayed. After confirming, a success message is


displayed.
Connect the test set to a single Ethernet port.

10

Generate a loss of signal condition (LOS) on the working path


by disconnecting the fiber.
Traffic switches from the working to the protection path within 50ms.

11

Put the fiber back on the working path.

12

Determine your next step.


If the protection
type is
revertive
non-revertive

13
14

Then
go to step 13.
then go to step 14.

After the WTR time expires, the traffic will switch from protection to
working path.
During WTR generate a loss of signal condition (LOS) on the
protection path by disconnecting the fiber.
Generate a loss of signal condition (LOS) on the protection
path by disconnecting the fiber.
Traffic switches from the protection to the working path.

15

Put the fiber back on the protection path.

16

Record data.
Note: Repeat the same procedure for other Ethernet
ports/VCGs.

TJ100CPr4

System Testing 67

Figure 7-3
Testing Ethernet on Ethernet (FE/FX) interface

Ethernet
test set

Near end network element

1
2P
X
A
3
T
4

NE

Far end network element

O
p
t
i
c
a
l

O
p
t
i
c
a
l

P
o
r
t
1

P
o
r
t
2

NE

P2
X
A
T3
4

FE Ports
Cats straight cable
Optical fiber

Installation and Commissioning Procedures Version 1.0

68 System Testing

7.4

Testing the Timing Source of the Network Element


This procedure helps you to test the timing source of the network
element for BITS clock (BITS 1).

Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have appropriate test cords.
Make sure the BITS Ref out generated by the test equipment is 2
Mhz.
Procedure
Step Action
1

Connect the test set and the network element as shown in


Figure 7-4.

Feed 2 Mhz rerference out from the test set to the BITS clock
input of the network element.

To nominate BITS as the timing source for the network


element:
Click configuration -> synchronization - > Nominate timing
reference.
The Nominate timinng references page is displayed.
Select BITS in the Clock Reference field.
Select BITSIN-1-4-1 in the Clock Reference Port.
Click Submit.
The BITS1 clock reference is nominated.

To ensure that the network element is locked to the BITS1


clock reference, click Configuration -> Synchronization ->
View nomination timing refernces page in the navigation
menu.
The View nomination timing refernces page is displayed. The * sign in the
Clock Source field indicates the selected clock source for the node.

TJ100CPr4

System Testing 69

Note : When all the external clock sources fail, the network element goes to holdover
mode.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind a person. Keep all unused optical connectors capped.

Figure 7-4 shows the set up to test the timing source of a network
element.
Figure 7-4
Timing source test

BITS interface
2.048 Mbps or 1.544 Mbps input
Test set

Optical port 1
Optical port 2

Installation and Commissioning Procedures Version 1.0

70 System Testing

This procedure helps you to test the timing source of the network element for
E1 port
Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have appropriate test cords.
Make sure the data from the E1 port 2 Mbps.
Procedure
Step Action
1

Connect the test set and the network element as shown in


Figure 7-5.

Feed 2 Mbps E1 data (PCM-30/CRC/non-CRC) to the E1


data port of the network element.

To nominate E1 data as the timing source for the network


element.
Click configuration -> synchronization - > Nominate timing
reference.
The Nominate timinng reference page is displayed.
Select Port in the Clock Reference field.
Select an E1 in the Clock Reference Port field.
Click Submit.
The E1 clock reference is nominated.

To ensure that the network element is locked to the BITS1


clock reference, Click Configuration -> Synchronization ->
View nominated timing references page in the navigation
menu.
The View nominated timing references page is displayed. The * sign in the
Clock Source field indicates the selected clock source for the node.

TJ100CPr4

System Testing 71

Note : When all the external clock sources fail, the network element goes to holdover
mode.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind a person. Keep all unused optical connectors capped.

Vary the E1 (2Mbps data) clock frequency and record the ppm
offset of the signal received at the test equipment.

Note : The ppm offset of the received signal must follow the E1 frequency variation.

Record the data.


The difference between the E1 (2Mbps data) ppm offset and the received
optical signal ppm offset must be less than 1 ppm.
If expected results do not occur then, contact your next level
of support.

Installation and Commissioning Procedures Version 1.0

72 System Testing

Figure 7-5 shows the set up to test the timing source of a network
element.
Figure 7-5
Timing source test

E1 interface

2.048 Mbps or 2 Mbps input


Test set

Optical port 1
Optical port 2

TJ100CPr4

System Testing 73

This procedure helps you to test the timing source of the network element for
STM Port
Pre-requisites
Make sure that all the optical connectors are cleaned.
Make sure that you have appropriate test cords.
Procedure
Step Action
1

Connect the test set and the network element as shown in


Figure 7-6.

Feed STM 1 data to the STM 1 input port of the network


element.

To nominate STM port as the timing source for the network


element.
Click configuration -> synchronization - > Nominate timing
reference.
The Nominate timinng references page is displayed.
Select Port in the Clock Reference field.
Select STM 1 in the Clock Reference Port drop down menu.
Click Submit.
The STM port clock reference is nominated.

To ensure that the network element is locked to the STM port


for clock reference, click Configuration -> Synchronization ->
View nomination timing refernces page in the navigation
menu.
The View nomination timing refernces page is displayed. The * sign in the
Clock Source field indicates the selected STM1 clock source for the node.

Installation and Commissioning Procedures Version 1.0

74 System Testing

Note : When all the external clock sources fail, the network element goes to holdover
mode.
CAUTION
Risk of damage to circuit packs
Electrostatic discharge can damage electrostatic sensitive devices.
Ensure that you are wearing the antistatic strap connected to the
ESD location on the network element.

DANGER
Risk of eye injury
Avoid direct exposure to laser beam or fiber as the invisible light can
blind a person. Keep all unused optical connectors capped.

Vary the STM clock frequency and record the ppm offset of
the signal received at the test equipment.

Note : The ppm offset of the received signal must follow the E1 frequency variation.

Record the data.


The difference between the STM ppm offset and the received optical signal
ppm offset must be less than 1 ppm.
If expected results do not occur then, contact your next level
of support.

TJ100CPr4

System Testing 75

Figure 7-6 shows the set up to test the timing source of a network
element.
Figure 7-6
Timing source test

STM interface
155 Mbps input
Test set

Optical port 1
Optical port 2

Installation and Commissioning Procedures Version 1.0

76 System Testing

7.5

Verifying Association between Network Elements


This procedure helps you to verify association between the newly
installed network element and other network elements in the network.

Procedure
Step Action
1

Click Maintenance in the Navigation menu.

Click Diagnostics.
Diagnostics page is displayed.

Click OSPF Monitor.

Note : Only OSPF enabled network elements in the network will be shown as
neighbors.

Click Neighbors to view the network elements in the network.


Network elements connected to the network element via OSPF are
displayed, along with the IP address.
This verifies the association between the newly installed network element
and other network elements in the network

Expected results
5

If the expected results does not occur then


Ensure proper physical connectivity between the two
network elements.
Contact your next level of support.

TJ100CPr4

8
Network Reconfiguration

1-

This chapter contains procedures for adding and deleting a network


element in a network. These procedures include network element in
Sub Network Connection Protection (SNCP) configuration.

8.1

SNCP
Sub-network connection protection SNCP is path protection type
that is initiated in the path terminating equipment. In SNCP,
protection is initiated on a failure in the path. Here it is required to
create two paths for each circuit, one working and the other
protection. Traffic in the source network element is bridged on both
the working and the protection paths while the destination network
element selects the best of the signals from the working or protection
paths. SNCP is a dedicated protection mechanism. SNCP operates in
a unidirectional protection switching manner. SNCP is a linear
protection scheme, which can be applied on an individual basis to
VC-n (both HOVC and LOVC) signals.
Table 8-1 list the procedure in this chapter.

Table 8-1
Network reconfiguration procedure list
1

Adding a Network Element to a Ring Configuration

Deleting a Network Element from a Ring Configuration

Installation and Commissioning Procedures Version 1.0

78 Network Reconfiguration

8.2

Adding a Network Element to a Ring Configuration


Consider an STM-1 ring with A, B, C and D network elements. See
Figure 8-1. Network element E is to be added to the ring as shown in
Figure 8-2.

Note : Traffic will be lost for all unprotected traffic between B and D.

Pre-requisites
Log into the WUI of the immediate neighboring network elements
of the network.
Ensure that you note the following criteria in the neighboring
network elements
Ethernet IP, router ID and subnet mask length configured
DCC bytes used
VCG associations created
Cross-connects created
Synchronization scheme used

Procedure
Step Action
1

Query the following data of both the network element (B, D)


and record the values.
Ethernet IP, router ID and subnet mask length
DCC bytes used
Cross-connects created
Synchronization scheme used
VCG associations created

TJ100CPr4

Configure the network element E with the Ethernet IP, router


ID, subnet mask length, static route, timing and the OSPF
parameters.

Set Admin status to DOWN on ports 1-5-1 and 1-5-2 of


network element D and B respectively.

Network Reconfiguration 79

Note : Traffic on all the unprotected circuits passing through either D-1-5-1 or
B-1-5-2 will be lost while adding network element E.

On Node E, create pass-through cross-connects on port 1-5-1


similar to port 1-5-2 of network element B.

On Node E, create pass-through cross-connects on port 1-5-2


similar to port 1-5-1 of network element D.

Set Admin status to UP on ports 1-5-1 and 1-5-2 of network


element E.

Enable the ECC bytes in network element E similar to the


ECC bytes used in the ring.

Connect the Tx fiber between network element D, E and B as


shown in Figure 8-2. Measure the Rx Power and verify that it is
within specification for the type of SFP being used.

Set Admin status to UP on ports 1-5-1 and 1-5-2 of network


element D and B respectively in service.

10

Measure the Rx power at Node B, D and E and verify that the


level are within specification for the type of SFP being used.
Connect the Rx Fiber to the interface.

Expected results
The network element E is added to the network.
11

If the expected result does not occur, contact your next level of
support.

Installation and Commissioning Procedures Version 1.0

80 Network Reconfiguration

Figure 8-1 shows the ring network before adding network element E.
Figure 8-1
Ring network before adding a network element E

A
1-5-1

1-5-2

1-5-2

1-5-1

1-5-1

1-5-2

1-5-2

TJ100CPr4

1-5-1

Network Reconfiguration 81

Figure 8-2 shows the ring network after adding the network element
E.
Figure 8-2
Ring network after adding the network element E

A
1-5-1

1-5-2

1-5-2

1-5-1

B
1-5-2

1-5-1

1-5-1

E
1-5-2

1-5-2

1-5-1

Installation and Commissioning Procedures Version 1.0

82 Network Reconfiguration

8.3

Deleting a Network Element from a Ring Configuration


Consider an STM-1 ring with A, B, C, and D as network elements. See
Figure 8-3. Network element C is to be deleted from the ring as
shown in Figure 8-4.

Note : Traffic will be lost for all unprotected traffic between B and D.

Pre-requisites
Log into the WUI of the immediate neighboring network elements
(B and D) of the network.
Ensure that you note the following criteria in the neighboring
network elements:
DCC bytes used
VCG associations created
Cross-connects created
Synchronization scheme used

Procedure
Step Action
1

Query the following data of both the network element (B, D)


and record the values.
DCC bytes used
Cross-connects created
Synchronization scheme used
VCG associations created

TJ100CPr4

Delete all cross-connections present in the other network


elements of the network, that terminate on the network
element C.

Check for the pass through cross-connects with the


neighboring network elements.

Network Reconfiguration 83

Determine your next step.


If
present
not present

Then go to
step 5
step 6

Note : Traffic on all the unprotected circuits passing through either D-1-5-2 or
B-1-5-1 will be lost while deleting the network element C.

Force all protected cross-connections on D-1-5-2 towards


D-1-5-1 (using force to working or force to protect) and
B-1-5-1 towards B-1-5-2 (using force to protect or force to
working depending on whether 1-5-1 is working or protect,
respectively).

At network element C, disconnect all the fibers going to


network elements B and D.

Measure the Rx power levels and verify that they are within
specifications.

Connect the fiber between node B & D.

Release the force switch commands if operated as per step 4.

10

Verify error free traffic to other nodes.

Expected results
The network element C is deleted from the network.
11

If the expected result does not occur, contact your next level of
support.

Installation and Commissioning Procedures Version 1.0

84 Network Reconfiguration

Figure 8-3 shows the ring before deleting the network element C.
Figure 8-3
Ring before deleting the network element C

1-3-2

1-3-1

1-3-1

1-3-2

1-3-2

1-3-1

1-3-1

1-3-2

Figure 8-4 shows the ring after deleting the network element C.
Figure 8-4
Ring after deleting the network element C

1-5-2

1-5-2

TJ100CPr4

D
1-5-2

1-5-1

1-5-1

1-5-1

9
Recording Data and Test Results

1-

This chapter provides forms to record system data and test results
during commissioning process. The form attached is the
commissioning data record form.
Make a copy of this Commissioning and Testing report (Table 9-1)
and complete the report before performing the commissioning
process.
Fill the other forms as and when you complete the tests during the
network element commissioning process.

Installation and Commissioning Procedures Version 1.0

86 Recording Data and Test Results

9.1

Form 1

Table 9-1
Commissioning and Testing Report
Product description
Name of the
customer
Location
Ethernet IP
Router ID
Representative name
Signature
Customer
representative name
Signature
Date

9.2

Form 2

Table 9-2
BER performance

E1/Ethernet Result
ports

TJ100CPr4

E1/Ethernet
ports

Result

Recording Data and Test Results 87

Table 9-2
BER performance

E1/Ethernet Result
ports

E1/Ethernet
ports

Result

Installation and Commissioning Procedures Version 1.0

88 Recording Data and Test Results

9.3

Form 3

Table 9-3
Synchronization tests

Clock

Status

STM-1
BITS clock, BITS data
Internal
Hold over
E1

9.4

Form 4

Table 9-4
Protection switching on fiber breaks, STM-1 LOS

E1 protection switching
Work to protect
Protect to work

Ethernet protection switching


Work to protect
Protect to work

9.5

Form 5

Table 9-5
Receiver sensitivity measurements

Parameter

Laser type

Spec

Measured values
Port 1

Tx output power
(dBm)
Receiver sensitivity
(dBm)

TJ100CPr4

S1.1

-8 to -15

L1.1

0 to -5

L1.2

0 to -5

S1.1

-8 to -28

L1.1

10 to -34

L1.2

10 to -34

Port 2

Appendix A: Common Procedures


10.1

10
1-

Cleaning Optical Connectors


It is important to keep all interconnects as clean as possible. Leave the
protective dust covers on the connectors when they are not in use.
Since the single-mode fiber has a light-carrying core with diameter less
than 10 micrometers, even a single microscopic speck of dust on the
connector end can significantly attenuate the light traveling through
the fiber. Accurate and repeatable measurements require clean
connections.
CAUTION
Risk of performance degradation
Improper cleaning may result in high attenuation due to dirt or dust or
may cause mechanical damage to the fiber end, resulting in
performance degradation.

CAUTION
Risk of damage to optical fiber
When handling optical fiber, take care not to exceed the minimum
bed radius, typically 35mm or over tighten the cable tie wraps while
dressing the cable.

Observe the following guidelines to achieve the best performance:

Visually inspect fiber ends for signs of damage.


Use dry connections whenever possible.
Follow the cleaning procedure as described.
Keep connectors covered when not in use.

Installation and Commissioning Procedures Version 1.0

90 Appendix A: Common Procedures

10.1.1 Required tools


Tejas Networks recommends the following tools for cleaning the
optical connectors:
99% isopropyl or ethyl alcohol
Lint-free, nonabrasive optical-quality cleaning pads or lens tissue,
or cotton or urethane-foam swabs
Pressurized dry-air duster
Optical fiber scope
10.1.2 Inspecting the fiber connector

Procedure

Step Action

TJ100CPr4

Visually inspect all fiber-optic connections before use. A


minimum of 200X magnification is required for proper
inspection.

Verify that the other end of the fiber is disconnected from its
laser source.

Inspect the end of the fiber face with the optical fiber scope.

Compare with Figure 10- 1 to determine the condition of the


fiber end face.

Refer to the table for the procedure to follow for each fiber
end-face condition. If the condition of the fiber end face is
ideal, no further action is required. If you need to clean or
polish the end face, follow the instructions in Fiber
Connector Cleaning Procedure

Appendix A: Common Procedures 91

Figure 10- 1
Fiber intersection

Table 10-1
Fiber recommended conditions

Fiber End-Face Condition

Recommendation

Ideal

No action required

Light scratches

Polish with 0.3 micron film

Heavy scoring or scratches

Repolish the face

Chip outside the fiber core

Repolish the face

Chipped core

Unacceptable; reject the connector

Rough surface

Repolish the face

Dirt or debris

Clean or repolish the face

Chipped face

Unacceptable; reject the connector

Cracked fiber

Unacceptable; reject the connector

Broken fiber

Unacceptable; reject the connector

Installation and Commissioning Procedures Version 1.0

92 Appendix A: Common Procedures

10.2 Fiber Connector Cleaning


Procedure
Step Action
1

Clean the ferrules and other parts of the connector with a


lint-free, nonabrasive cleaning pad or lens tissue. When you
finish, discard the used pad or tissue.

Clean the fiber end with a new lint-free cleaning pad, lens
tissue, or swab. Move the cleaning pad back and forth across
the fiber end several times. If you are using a swab, gently
rotate the swab as you wipe across the end face.

Aim a filtered, dry compressed-air dust remover at a shallow


angle to the fiber end face and blow across the end face from
a distance of 68 inches.

Verify that the other end of the fiber is disconnected from its
laser source.

Inspect the fiber-optic connector with an optical fiber scope to


verify that it is free of dirt and dust. Then do either of the
following:
If the connector is clean, cover the connector with a
protective dust cover until you are ready to use it.
If the connector is not completely clean, continue with
steps 6 through 14 to clean it with alcohol.

TJ100CPr4

Apply 99% isopropyl or ethyl alcohol to a lint-free,


nonabrasive cleaning pad or lens tissue.

Clean the ferrules and other parts of the connector. When you
finish, discard the used pad or tissue.

Apply alcohol to a new, lint-free cleaning pad, lens tissue, or


swab.

Appendix A: Common Procedures 93

Clean the fiber end with a new lint-free cleaning pad, lens
tissue, or swab. Move the cleaning pad back and forth across
the fiber end several times. If you are using a swab, gently
rotate the swab as you wipe across the end face.

10

Immediately dry the fiber ends with a clean, dry, lint-free


cleaning pad or lens tissue.

11

Discard the used cleaning materials.

12

Aim a filtered, dry compressed-air dust remover at a shallow


angle to the fiber end face and blow across the end face from
a distance of 150-200mm.

13

Inspect the fiber-optic connector with an optical fiber scope to


verify that it is free of dirt and dust.

14

Cover the connector with a protective dust cover until you are
ready to use it.

Installation and Commissioning Procedures Version 1.0

94 Appendix A: Common Procedures

TJ100CPr4

11

Appendix B: Connector Pin Assignment


11.1

Power Connector

Pin Signals
1

RET

GND

-48V

11.2

1-

Diagram

Alarm/Diag Connector

Pin Signal
1

CRIT_ALM_COM

CRIT_ALM_NO

MIN_ALM_COM

MIN_ALM_NO

MAJ_ALM_COM

DIAG_TXD

GND

DIAG_RXD

ALARMIN_1_NO

10

MAJ_ALM_NO

11

ALARMOUT0_COM

12

ALARMOUT0_NO

Diagram

5
10
15

14

2
8

13

1
6

7
12

11

Installation and Commissioning Procedures Version 1.0

96 Appendix B: Connector Pin Assignment

11.2

Alarm/Diag Connector (continued)

Pin Signal
13

ALARMIN_1_COM

14

ALARMIN_0_COM

15

ALARMIN_0_NO

11.3

Diagram

Clock Connector

Pin Signal

Diagram

NC

NC

NC

BITS_CLK0_GND

BITS_CLK0

NC

REF_CLK_OUT_GND

REF_CLK_OUT

Unused

11.4

4
9

3
8

NMS Connector

Pin Signal
1

TX_P

TX_N

RX_P

Unused

Unused

RX_N

Unused

Unused

TJ100CPr4

Diagram

1 2 3 4 5 6 7 8

2
7

1
6

Appendix B: Connector Pin Assignment 97

11.5

Craft/Modem Connector

Pin Signal
1

CD

RD

TD

DTR

GND

DSR

RTS

CTS

RI

Diagram

4
9

3
8

2
7

1
6

Installation and Commissioning Procedures Version 1.0

98 Appendix B: Connector Pin Assignment

11.6

E1 (EURO) Connector

Pin

Signal

Pin

Signal

A1

RX_E1_03_RING

A9

RX_E1_09_RING

B1

TX_E1_01_RING

B9

TX_E1_07_RING

C1

RX_E1_01_RING

C9

RX_E1_07_RING

A2

RX_E1_03_TIP

A10

RX_E1_09_TIP

B2

TX_E1_01_TIP

B10

TX_E1_07_TIP

C2

RX_E1_01_TIP

C10

RX_E1_07_TIP

A3

TX_E1_03_RING

A11

TX_E1_09_RING

B3

TX_E1_02_RING

B11

TX_E1_08_RING

C3

RX_E1_02_RING

C11

RX_E1_08_RING

A4

TX_E1_03_TIP

A12

TX_E1_09_TIP

B4

TX_E1_02_TIP

B12

TX_E1_08_TIP

C4

RX_E1_02_TIP

C12

RX_E1_08_TIP

A5

RX_E1_06_RING

A13

RX_E1_12_RING

B5

TX_E1_04_RING

B13

TX_E1_10_RING

C5

RX_E1_04_RING

C13

RX_E1_10_RING

A6

RX_E1_06_TIP

A14

RX_E1_12_TIP

B6

TX_E1_04_TIP

B14

TX_E1_10_TIP

C6

RX_E1_04_TIP

C14

RX_E1_10_TIP

A7

TX_E1_06_RING

A15

TX_E1_12_RING

B7

TX_E1_05_RING

B15

TX_E1_11_RING

C7

RX_E1_05_RING

C15

RX_E1_11_RING

A8

TX_E1_06_TIP

A16

TX_E1_12_TIP

B8

TX_E1_05_TIP

B16

TX_E1_11_TIP

C8

RX_E1_05_TIP

C16

RX_E1_11_TIP

A17

RX_E1_15_RING

A25

RX_E1_21_RING

B17

TX_E1_13_RING

B25

TX_E1_19_RING

C17

RX_E1_13_RING

C25

RX_E1_19_RING

A18

RX_E1_15_TIP

A26

RX_E1_21_TIP

B18

TX_E1_13_TIP

B26

TX_E1_19_TIP

C18

RX_E1_13_TIP

C26

RX_E1_19_TIP

TJ100CPr4

Appendix B: Connector Pin Assignment 99

Pin

Signal

Pin

Signal

A19

TX_E1_15_RING

A27

TX_E1_21_RING

B19

TX_E1_14_RING

B27

TX_E1_20_RING

C19

RX_E1_14_RING

C27

RX_E1_20_RING

A20

TX_E1_15_TIP

A28

TX_E1_21_TIP

B20

TX_E1_14_TIP

B28

TX_E1_20_TIP

C20

RX_E1_14_TIP

C28

RX_E1_20_TIP

A21

RX_E1_18_RING

A29

B21

TX_E1_16_RING

B29

C21

RX_E1_16_RING

C29

A22

RX_E1_18_TIP

A30

B22

TX_E1_16_TIP

B30

C22

RX_E1_16_TIP

C30

A23

TX_E1_18_RING

A31

B23

TX_E1_17_RING

B31

C23

RX_E1_17_RING

C31

A24

TX_E1_18_TIP

A32

B24

TX_E1_17_TIP

B32

C24

RX_E1_17_TIP

C32

Installation and Commissioning Procedures Version 1.0

100 Appendix B: Connector Pin Assignment

TJ100CPr4

Appendix C: Cable Color Coding


12.1

12
1-

Power Cable

Pin

Color code

Red

Green

Black

12.2

Alarm Cable
Pin

Pair

Color code

P1

White

2
3

Blue
P2

4
5

Orange
P3

10
6

P4
P5
P6

Red
Blue

P7

15
8

White
Grey

12
14

White
Brown

13
11

White
Green

7
9

White

Red
Orange

NC

Red

Installation and Commissioning Procedures Version 1.0

102 Appendix C: Cable Color Coding

12.3

Clock Cable
Pin

Color code

Brown

Brown + Grey Ring

Red

Red + Grey Ring

Orange

Orange + Grey Ring

Yellow

Yellow + Grey Ring

12.4

Craft/F1 Cable

Pin

Color code

Pin

1+6

Black

White

Red

Green

1+6

Brown

Orange

Yellow

Blue

TJ100CPr4

Appendix C: Cable Color Coding 103

12.5

E1 Cable
Pins are provided for wire wrapping.

12.6

Diag Cable

PINS on RJ45

Color code

PINS on 9D Sub
Female

Brown

NC

Brown + Grey Ring

Red

Red + Grey Ring

NC

Orange

Orange + Grey Ring

NC

Yellow

NC

Yellow + Grey Ring

NC

12.7

NMS Cable

PINS on RJ45
Plug(End A)

Color code

PAIR

PINS on RJ45
Plug(End B)

Blue

P1

NC

White

Orange

White

NC

NC

NC

NC

NC

NC

NC

NC

3
P2

Installation and Commissioning Procedures Version 1.0

104 Appendix C: Cable Color Coding

TJ100CPr4

13
Appendix D: General Configuration

1-

This appendix gives the general procedures for configuring the


TJ100CPr4 multiplexer.

Note : For more information on configuration, refer to the User Interface guide,
104-DOC000027-E

13.1

Accessing and Configuring TJ100CPr4

Procedure
Step Action
1

Switch ON the Node, wait for at least 7 minutes for the node
to completely come-up (before trying to ping or access the
node (through Internet Explorer)).

The Factory default IP address for Multiplexer is:


192.168.1.254 or the one which is present on the Sticker, pasted
on the Node.

Use a PC/Laptop and configure the PC/laptop


IP Address to: 192.168.1.200
Subnet Mask to: 255.255.255.0
Default Gateway to: 192.168.1.1 or the Node IP Address

Installation and Commissioning Procedures Version 1.0

106 Appendix D: General Configuration

13.1.1 Logging to the System


Procedure
Step Action
1

Connect the ethernet port of PC/Laptop to the NMS port on


TJ100CPr4 by a cross cable .

Note : Use straight cable only, if both the Tejas Node and PC/Laptop are connected
through Hub/Switch.

Open the Internet Explorer in the PC/Laptop and enter the


address in the address space:
http://192.168.1.254:20080

Log into the WUI with following user name and password.
User Name:tejas
Password : j72e#05t

Configuration: (One Time Configuration)


Name: Enter the Name of the Site/Location. ( As you
desire)
Router ID: Enter the router ID( Ex:192.168.254.1)
Ethernet IP: Enter the Ethernet IP( Ex:192.168.1.254)
Contact: Enter the contact details
Location: Enter the location name

Submit changes and click on Accept the Modifications.


System will go to the warm-reboot state and after 3 minutes,
you can login to the system.

TJ100CPr4

Appendix D: General Configuration 107

If you are connecting with any other other Tejas Node to this Local
Node, then set the Remote node with the Router ID and Ethernet IP
as follows:
Router ID: Enter the router ID of the other Tejas node
(Ex: 192.168.254.2)
Ethernet IP: Enter the Ethernet IP of the other Tejas node
( Ex: 192.168.2.254)

13.2

Configurating Optical Ports

Procedure
Step Action
1

Click Configuration > Facilities > STM Ports >any STM 1


port
Admin Status: Up
TIM Action : tim_ignore

Submit changes and click on Accept the Modifications.

Click on Configuration >Facilities > STM Ports > AU4


Signal Label: tug_structure
TIM Action: Ignore TIM

13.3

Submit changes and click on Accept the Modifications.

Configuring OSPF Parameters

Procedure
Step Action
1

Click Configuration > DCN > OSPF in the navigation


menu..
OSPF Parameters configuration page is displayed.

Enter value for Area.

Installation and Commissioning Procedures Version 1.0

108 Appendix D: General Configuration

Click Submit.
A confirmation page is displayed.

Click Accept Valid Modifications.


A "Successfully Modified" message is displayed

13.4

Accessing TJ100CPr4 remotely (using router ID)


Step Action
1

Configure your laptop/PC default gateway as your local


TJ100CPr4 IP address.

Access the remote TJ100CPr4 node using the router ID and


login to the remote node. (http://192.168.254.2:20080).
Example: If you are at Node A and would like to access Node B
(192.168.254.2), then open a web browser and enter the router ID in the URL
field along with the port number. (Example : http://192.168.254.2:20080).

Configure IP address, subnet mask and default gateway of your


laptop/PC at Local Node A (192.168.1.254) as follows:

IP Address: 192.168.1.200

Subnet Mask: 255.255.255.0

Default Gateway: 192.168.1.254

Log into the WUI with following user name and password:
User Name: tejas
Password: j72e#05t
In the command prompt of Windows PC, enter the following
command:
route add 192.168.254.0 mask 255.255.255.0 192.168.1.254
(and then press enter key).
Now you will be able to ping the remote node with its Router
ID.

If you are able to ping, then enter http://RouterID:20080 in the web


browser, you will be able to see the Remote node UI page, after
entering the User name and Password.

TJ100CPr4

Appendix D: General Configuration 109

The above explanation is represented in the Figure 13-1.


Figure 13-1
Remote Access of TJ100CPr4

Node A
IP: 192.168.1.254
RID:192.168.254.1

Optical Link (Fibers)

Ethernet Cross Cable


connected to NMS Port on Node-A
Laptop/PC
IP: 192.168.1.200
Subnet Mask: 255.255.255.0
Default Gateway: 192.168.1.254

Remote Node B
IP: 192.168.2.254
RID:192.168.254.2

Optical Link (Fibers)

Remote Node C
IP: 192.168.3.254
RID: 192.168.254.3
Optical Link
(Fibers)
Remote Node D
IP: 192.168.4.254
RID: 192.168.254.4

In the command prompt of Windows Laptop/ PC, enter the


following command:
route add 192.168.254.0 mask 255.255.255.0 192.168.1.254 (then
press enter key).
The above command will allow your Laptop/PC connected to the
Local Node-A on its NMS Port, to ping or access (through Web
browser):
the local Node (Node A) by IP address and router ID as well.
remote Nodes (Nodes: B, C and D) through its router ID only.
When you take the Windows Laptop/ PC to remote node say node-D,
then connect the Laptop/ PC to Node-D NMS port and then:
Configure IP address, subnet mask and default gateway of your
laptop/PC at Local node D (192.168.4.254) as follows:
IP Address: 192.168.4.200
Subnet Mask: 255.255.255.0
Default Gateway: 192.168.4.254
In the command prompt of Windows PC, give the following
command:

Installation and Commissioning Procedures Version 1.0

110 Appendix D: General Configuration

route add 192.168.254.0 mask 255.255.255.0 192.168.4.254 (then


press enter key).
With this command, you will be able to Log-in any Node through its
Router-ID.

13.5

Configuring E1
Step Action
1

Click Configuration > Facilities > E1 in the navigation


menu.
The E1 Interface Configuration page is displayed.

Click on E1 port.
The Provision Interface page is displayed.

Configure values as follows:


Admin Status: Up
Alarm Reporting Status: Report
TCA Settings: Enable or Disable
Identifier: Enter any alphanumeric string to identify the
port

Click Submit.
A confirmation page is displayed.

Click Accept Valid Modifications


A "Successfully Modified" message is displayed.

TJ100CPr4

Repeat the above steps to configure the required E1 ports.

Appendix D: General Configuration 111

13.6

Configuring E3
Step Action
1

Click Configuration > Facilities > E3 in the navigation


menu.
The E3 Interface Configuration page is displayed.

Click on E3 port.
The Provision Interface page is displayed.

Configure values as follows:


Admin Status: Up
Alarm Reporting Status: Report
TCA Settings: Enable or Disable
Identifier: Enter any alphanumeric string to identify the
port

Click Submit.
A confirmation page is displayed.

Click Accept Valid Modifications


A "Successfully Modified" message is displayed.

Repeat the above steps to configure the required E3 ports.

Installation and Commissioning Procedures Version 1.0

112 Appendix D: General Configuration

13.7

Configuring Ethernet ports


Step Action
1

Click Configuration >Facilities > Ethernet in the


navigation menu
Admin Status : Up
Include Alarm Reporting Status : Report
Link Integrity : Enable at both ends
Auto Negotiation : Enable or Disable depending on end
equipment configuration
Flow Control: Manual TX-Rx
Threshold Enable for 15 min Interval: Enable or Disable
Circuit Identifier :User dependent /Convenient

Click Submit.
A confirmation page is displayed.

Click Accept Valid Modifications


A "Successfully Modified" message is displayed

TJ100CPr4

Repeat the above steps to configure the required Ethernet


ports.

Appendix D: General Configuration 113

13.8

Configuring VCG ports


Step Action
1

Click Configuration >Facilities > VCG> VCG Group


LCAS : Enable (Has to be enabled at both ends)
VCAT: Enable
Operating Granularity: VC-12 depending on customer
requirement
Payload FCS: Enable
Circuit Identifier: Any alphanumeric string to identify the
interface

Click Submit.
A confirmation page is displayed.

Click Accept valid modifications


A "Successfully Modified" message is displayed

Repeat the above steps to configure the required VCG ports.

13.8.1 Adding new VC


Step Action
1

Click Configuration > Facilities > VCG.


The VCG interface configuration page is displayed.

Click on the VCG to be configured.


The Provisioning VCG Interface page is displayed.

Click Add new VC.


The Add VC to VCG page is displayed.

Installation and Commissioning Procedures Version 1.0

114 Appendix D: General Configuration

Configure values as follows:


Number of connections: Enter the number of VCs to be
created.
Working Port: select a work port and corresponding K, L,
M values
Protection Port: Select a Protection port and
corresponding K, L, M values.
Reversion Mode: Non-Revertive / Revertive
WTR Time: Select value when Revertive is selected for
Reversion Mode.
Protection type on network: No Protection/50ms
Protection/Slow Protection

Click Submit.
A confirmation message is displayed.

Click Accept Valid Modifications.


A "Successfully Modified" message is displayed.

Repeat the above steps to add more VCs.

13.8.2 Provisioning Cross Connect


Step Action
1

Click Configuration > Cross-connect.


The Configure Cross-connect page is displayed.

Click Add Cross-connect.


The Add Cross-connect page is displayed.

TJ100CPr4

Appendix D: General Configuration 115

Configure values as follows:


Cross connect capacity :VC12
Circuit Identifier :User dependent
Source port :STM1-1-5-1
Source time slot (K,L,M ) : select from the menu (TUG
Structure)
Destination port : E1-1-N-1 (where N is the number
displayed on the WUI)
Destination time slot : -- Enable Source protection and select the TUG Structure
Select Reversion mode parameters.
Select WTR time if Revertive is selected for reversion mode.

13.9

Submit the changes and Accept the Modifications.

Repeat the above steps to add cross-connects to other STM


ports.

Configuring Timing Manager


Step Action
1

Click Configuration > Synchronization > Synchronization


Status in the navigation menu
QL Mode: Enable and then submit

Click Nominate timing reference. Select a value from the


drop down menu for the following
Clock Reference
Clock reference Port
Priority

Click View Nominated timing reference to verify the


nominated clock.
Repeat the same steps, If you want to nominate more than one
Clock source.

Installation and Commissioning Procedures Version 1.0

116 Appendix D: General Configuration

Click Nominate timing reference.


Provide the second reference source.
Assign the second priority to it and verify the same by clicking
View Nominated timing references.

13.10

Checking Alarms
Step Action

TJ100CPr4

Click Faults in the Navigation menu > Active Alarms > you
can see the current Active Alarms

Click Faults in the Navigation menu > Suppressed Alarms >


You can see all the alarms suppressed on the node.

Click Faults in the Navigation menu > Alarm Filters > you can
provision new alarm filters.

Click Faults in the Navigation menu > Event history > you
can see the History of Alarms

Click Faults in the main menu > Alarm Severity. You can view
and change the severity of alarms. An asterisk appears before
the name of alarms for which severity has been changed.

Appendix D: General Configuration 117

13.11

Port settings of Hyper terminal

Figure 13-2

Connect the Diag. Cable (9 pin D connector to PC COM1 port and


RJ45 connector to the Diag marked port on the Node).
Now press enter key on the PC, enter
User name: root
Password: swtn100tj
now enter: ifconfig eth0
Now the IP address of the Node would be displayed.
You can reach us on: 0-99019 71880, for further clarifications/
information.

Installation and Commissioning Procedures Version 1.0

118 Appendix D: General Configuration

TJ100CPr4

14
Glossary

1-

Table 14-1: Acronyms and their Expansions

Acronym

Expansion

AID

Access Identifier

AINS

Auto In-Service

AIS

Alarm Indication Signal

ALS

Automatic Laser Shutdown

APS

Automatic Protection Switching

AU

Administrative Unit

BITS

Building Integrated Timing Supply

BIPS

Bit Interleaved Parity

CD-ROM

Compact Disk - Read Only Memory

CRC

Cyclic Redundancy Check

SDH

Synchronous Digital Hierarchy

ESD

Electro Static Discharge

LED

Light Emitting Diode

TAC

Technical Assistance Center

RMA

Return Materials Authorization

RAL

Restricted Access Location

SELV

Safety Extra Low Voltage

TNV

Telecommunication Networks Voltage

PSU

Power Supply Unit

NMS

Network Management System

IDF

Intermediate Distribution Frame

Installation and Commissioning Procedures Version 1.0

120 Glossary

Table 14-1: Acronyms and their Expansions (continued)


SC

Standard Connector

LC

Lucent Connector

LASER

Light Amplification by Stimulated Emission of Radiation

SFP

Small Formfactor Pluggable

SFF

Small Formfactor Fixed

SSM

Synchronization Status Messaging

TUG

Transport Unit Group

STM

Synchronous Transport Module

VC

Virtual Container

LAN

Local Area Network

TJ100CPr4

Index 121

Index

1-

Symbols
1+1 MSP

77

A
Accessing TJ100CPr4 remotely
Adding new VC/VT 113
adequate 56, 60, 64
admin 57, 61
alphabetic 44
alphanumeric 44
antistatic strap 57, 61, 65

B
backing 53
BER 86
BITS 68, 73
bridged 77
browser 43, 45

D
daisy-chaining 56, 60, 64
Daisy-chaining the E3/DS3 ports at
the near end 60
dBm 88
DCC bytes 78
deleting 77
destination 53
Diag Cable 103
directory path 53
discharge 57, 61, 65
DOWN 78

E
E3 Connection 37
electrostatic 57, 61, 65
environmental 1
ESD 57, 61, 65
Ethernet 42, 45
Ethernet Connection
Ethernet IP 46
eye injury 57, 61, 65

C
capped 57, 61, 65
Checking Alarms 116
circuits 79
clock reference type 52
clock source 52
compliance 1
Configurating Optical Ports
configuration 53
Configuring E1 110
Configuring E1/DS1 110
Configuring E3 111
Configuring E3/DS3 111
Configuring Ethernet ports

108

Configuring OSPF Parameters 107


Configuring Timing Manager 115
Configuring VCG ports 113
confirmation message 50
containment 1
cross cable 42, 45
Cross-connects 78

107

112

38

F
far end 56, 60, 64
fiber 57, 61, 65
flowchart 2
form 85
ftp account 53
Installation and Commissioning Procedures Version 1.0

122 Index

functional

operational 1
optical connectors

47

handover 1
HOVC 77
hyphen 49

passing 79
password 44
performance qualifications 1
personnel 1
pluggable 49
Port settings of Hyper terminal
powering up 42
ppm 71, 74
product description 86
protection scheme 77
provisioned 56, 60, 64

I
internal clock 69, 71, 74
Internet Explorer 43, 45
IP address 42

L
laser beam 57, 61, 65
laser type 88
linear 77
locked synchronous sources
LOS 58, 62
LOVC 77

M
maintenance

near end 56, 60, 64


Netscape 43, 45
NIC 46
nodal 41
node Inventory 49
nominating 52
non-revertive 57, 61
numeric 44

TJ100CPr4

69, 71, 74

117

R
receiver sensitivity
record form 41
Reference 3
restoring 53
revertive 57, 61

88

offset 71, 74
offset value

56, 60, 64

51

sensitive devices 57, 61, 65


SFP 79
signature 86
SNCP 56, 60, 64, 77
source 53
sub network connection protection
(SNCP) 77
Subnet mask length 46
success message 57, 61
Synchronization 78
system testing 7, 55

Index 123

T
Tejas representative 86
test equipment 56, 60, 64
test results 85
Testing all the E3/DS3 ports in the
E3/DS3 interface, both at the near
and far end 61
Testing protection switching on the
E3/DS3 ports 61
Testing STM-1/4/16/OC-3/12/48
Protection Switching with Traffic on
the E3/DS3 Interface 60
time server 51
time zone 50
Timing Source 68
traffic generated 57, 61

U
under score 49
unidirectional protection
unique 48
unprotected 78
userid 44

77

V
VC12 57, 61
VC-n 77
verification

W
WTR
WUI

57, 61
78

Installation and Commissioning Procedures Version 1.0

124 Index

TJ100CPr4

You might also like