General Authority of Civil Aviation

New King Abdulaziz International Airport


Development Project - Phase 1: Package 422

1.1

j) External Substation: Structure and rough finishes are complete. Cladding


and MEP installation activities are in progress.
k) Waste Compound: Structural activities are complete. Painting is complete.
l) Guard Houses: Structure is complete. Rough finishes as well as MEP and
SAS services installation activities are in progress.
m) Fuel Tank Station: Structure and rough finishes are complete. MEP and SAS
services installation activities are in progress.
n) Diesel Bulk Storage: Ring beam construction is complete. Backfilling is in
progress.
o) External Utilities: External underground utilities installation is in progress.

LOAD CENTER A

Summary Status:
Design:
100% Design is substantially complete.

Procurement:
The procurement process is in progress. Critical long lead items like generator,
chiller, cooling tower, oil type transformers, switchgears etc are delivered at
site. Delivery of AHUs, HVAC fans, light fixtures, sanitary fixtures etc. are in
progress. Delivery of potable water pumps, chlorination system, MDB, SMDB
etc. are expected. Material submission and approval of equipment like FCU,
SCADA etc. are pending.

Construction:

Key Issues:

Access to the Air Defence fence is affecting the construction of the SEC
tunnel that is between the SEC substation and the Load Center Boundary.

Construction Methodology:
There are many components of the Load Centers and they are as follow:

a) Central Building: Structural activities are complete. Rough finishes are


substantially complete. MEP and SAS installation activities are in progress.
Roofing and cladding are complete.
b) Office Building: Structural activities are complete. Rough finishes are
substantially complete. MEP and SAS installation activities are in progress.
Cladding and glazing are substantially complete.

Generator Building (Transformer area, Switch area ( G + 1) floor,


Generator/Plenum area ( G+ 2 Floor).

District Cooling Plant ( 2 Basement+ 1 Mazzanine+ Roof)

Central Switch Hall ( G + 1)

c) District Cooling Plant: Structural activities are complete. Rough finishes


are in progress. MEP and SAS services installation activities are in
progress. Chillers, pumps and cooling towers are installed.
d) Generator Building: Concrete and steel structural activities are complete.
MEP and SAS services installation activities are in progress. Generators
and transformers are installed. Cladding is in progress. Roofing is
substantially complete.
e) SEC Tunnel within Load Center: Concrete activities are complete. MEP and
SAS services installation activities are in progress.
f) Workshop & Storage: Steel structure, cladding and roofing are
substantially complete. Composite slab construction is in progress.
g) Potable Water Pumping Station: Parapet wall construction is in progress.
Cladding installation is in progress.
h) Potable Water Holding Tank: Structural activities are complete. Roof
waterproofing and cladding installation are in progress.
i) Fire Water Pump Station: Structural activities are complete. Rough finishes
are complete. MEP and SAS services installation activities are in progress.

Office Building ( G + 3 Floor)

Workshop & Storage( G + 1 ) Floor

SEC Tunnel Work

Substation

Fuel Tank Station

Guard House A

Gurad Hause B

Fire Water Pump Station

Potable Water Holding Tank

Potable Water Pump Station

Package 422 CWS BL-02 Rev-01


P a g e |1

Construction Working Schedule BL-02 Rev 01

Diesel Bulk Storage Tank

Basement Service Gallery and Ramp

Waste Compound

Precast Fence

Landscape

Car Parking

Security Fencing

The typical construction sequence of the buildings starts with the earthwork.
Earthwork is followed by blinding, screed and footing pad construction. After
the construction of the footing pad the construction of the foundation walls
and columns start. If the building is steel framed the foundation column and
wall will be concreted with the anchor bolts. After the completion of
foundation wall and column construction waterproofing of the footing takes
place. After waterproofing, backfilling and compaction takes place. The
installation of underground utilities and slab on grade construction is
scheduled after the completion of the first suspended slab above the slab on
grade. After the backfilling and compaction are complete, construction of
walls, columns and suspended slab follows. For steel framed building, after
the completion of backfilling and compaction, the erection of steel structure
progresses. Upon completion of the steel structure erection, fireproof
painting will follow. Slab on grade construction is scheduled to start after the
fireproofing the steel structure. Block wall/drywall partitions, door frame
installation and plastering will progress one after the other following the
completion of the slab on grade. Overhead MEP/SAS services installation
will start along with the block wall construction. After the completion of
plastering, wall finishes like painting initial coats, wall tiling will start and
progress. After the completion of painting initial coats/wall tiling, false
ceiling installation will follow. Before the false ceiling panel installation all
the overhead MEP/SAS activities will complete. After the completion of the
false ceiling, flooring activities will start and progress. Installation of floor
mounted equipment will be after the completion of flooring. Installation of
doors, furniture and final coats of paint will be done after flooring.
In Potable Water Holding Tank, the built tanks will be waterproofed internally
and the waterproofing will be tested. Installation of Tank Mixer and the
associated circuitry will follow.
In Diesel Bulk Storage area, the Diesel Tank will be erected over the
foundation. The installation of the ceiling structure of the tank will be done
deploying the central post, which will be removed once the ceiling structure
installation is complete. The Diesel Tank shell plates are not painted at site.
The completed Diesel Tanks are hydro-tested, one after the other. In parallel
Package 422 CWS BL-02 Rev-02
P a g e |2

to the Diesel Tank, the underground utilities around the diesel tank are
installed. Upon installing the underground utilities, screed is done over the
area that is supposed to be surrounded by dykes. Then, the construction of
dykes around the Diesel Tank continue. The installation of above ground fire

Power Available From SEC :


Permanent power is to be provided from the SEC substation and through SEC
tunnels to enable the testing and commissioning of the Generators, Chillers,
Central Switch Hall and other supporting buildings of Load center A.

Preliminary Testing:
The connection from this facility to the SEC substation will be completed in
order to receive permanent power from SEC. Testing and commissioning of the
Load Center will be completed after receiving the permanent power from the
SEC substations.

1.2

LOAD CENTER B

Summary Status:
Design:
100% Design is substantially complete.

Procurement:
The procurement process is in progress. Critical long lead items like generator,
chiller, cooling tower, oil type transformers, switchgears etc are delivered at
site. Delivery of AHUs, HVAC fans, light fixtures, sanitary fixtures etc. are in
progress. Delivery of potable water pumps, chlorination system, MDB, SMDB
etc. are expected. Material submission and approval of equipment like FCU,
SCADA etc. are pending.

Construction:
p) Central Building: Structural activities are complete. Rough finishes are in
progress. MEP and SAS services installation activities are in progress.
Roofing is in progress.

Construction Working Schedule BL-02 Rev 01


q) Office Building: Structural activities are complete. Rough finishes are in
progress. MEP and SAS installation activities are in progress. Cladding and
glazing are in progress.
r) District Cooling Plant: Structural activities are complete. Rough finishes
are in progress. MEP and SAS services installation activities are in
progress. Chillers, pumps and cooling towers are installed.
s) Generator Building: Concrete and steel structural activities are in
progress. MEP and SAS services installation activities are in progress.
Rough finishes are in progress.
t) SEC Tunnel: Concrete activities are in progress. MEP and SAS services
installation activities are in progress.
u) Workshop & Storage: Steel structure and concrete activities are in
progress.
v) Potable Water Pumping Station: concrete activities are substantially
complete.
w) Potable Water Holding Tank: Structural activities are in progress.
x) Fire Water Pump Station: Structural activities are complete. Rough finishes
are complete. MEP and SAS services installation activities are in progress.
y) External Substation: Structure is complete. Rough finishes activities are in
progress.
z) Guard Houses: Structure is complete.
aa)Fuel Tank Station: Structure is complete. Rough finishes activities are in
progress.
bb)
Diesel Bulk Storage: Ring beam construction is in progress.
cc) External Utilities: External underground utilities installation is in progress.

Key Issues:

Construction Methodology:
There are many components of the Load Centers and they are as follow:

Generator Building (Transformer area, Switch area ( G + 1) floor,


Generator/Plenum area ( G+ 2 Floor).

District Cooling Plant ( 02 Basement+ 01 Mazzanine+ Roof)

Central Switch Hall ( G + 1)

Office Building ( G + 3 Floor)

Workshop & Storage( G + 1 ) Floor

SEC Tunnel Work

Substation

Package 422 CWS BL-02 Rev-02


P a g e |3

Fuel Tank Station

Guard House A

Gurad Hause B

Fire Water Pump Station

Potable Water Holding Tank

Potable Water Pump Station

Diesel Bulk Storage Tank

Basement Service Gallery and Ramp

Waste Compound

Precast Fence

Landscape

Car Parking

Security Fencing

The typical construction sequence of the buildings starts with the earthwork.
Earthwork is followed by blinding, screed and footing pad construction. After
the construction of the footing pad the construction of the foundation walls
and columns start. If the building is steel framed the foundation column and
wall will be concreted with the anchor bolts. After the completion of
foundation wall and column construction waterproofing of the footing takes
place. After waterproofing, backfilling and compaction takes place. The
installation of underground utilities and slab on grade construction is
scheduled after the completion of the first suspended slab above the slab on
grade. After the backfilling and compaction are complete, construction of
walls, columns and suspended slab follows. For steel framed building, after
the completion of backfilling and compaction, the erection of steel structure
progresses. Upon completion of the steel structure erection, fireproof
painting will follow. Slab on grade construction is scheduled to start after the
fireproofing the steel structure. Block wall/drywall partitions, door frame
installation and plastering will progress one after the other following the
completion of the slab on grade. Overhead MEP/SAS services installation
will start along with the block wall construction. After the completion of
plastering, wall finishes like painting initial coats, wall tiling will start and
progress. After the completion of painting initial coats/wall tiling, false
ceiling installation will follow. Before the false ceiling panel installation all
the overhead MEP/SAS activities will complete. After the completion of the
false ceiling, flooring activities will start and progress. Installation of floor

Construction Working Schedule BL-02 Rev 01


mounted equipment will be after the completion of flooring. Installation of
doors, furniture and final coats of paint will be done after flooring.

Generators and transformers are installed. Cladding is in progress. Roofing


is in progress.
hh)
SEC Tunnel within Load Center: Concrete activities are in progress.
MEP and SAS services installation activities are in progress.
ii) SEC Tunnel from Load Center till substation: Concrete activities are in
progress. MEP and SAS services installation activities are in progress.
jj) Workshop & Storage: Steel structure, cladding and roofing are
substantially complete. Rough finishes activities are in progress. MEP and
SAS services installation activities are in progress.
kk)Potable Water Pumping Station: Concrete activities are in progress.
ll) Potable Water Holding Tank: concrete activities are in progress.
mm) Fire Water Pump Station: Structural activities are complete. Rough
finishes are complete. MEP and SAS services installation activities are in
progress.
nn)
External Substation: Concrete activities are in progress.
oo)Waste Compound: Structural activities are complete. Painting is complete.
pp)
Guard Houses: Structure is complete. Rough finishes as well as MEP
and SAS services installation activities are in progress.
qq)
Fuel Tank Station: Structure and rough finishes are complete. MEP and
SAS services installation activities are in progress.
rr) Diesel Bulk Storage: Ring beam construction is complete. Backfilling is in
progress.
ss) External Utilities: External underground utilities installation is in progress.

Power Available From SEC :


Permanent power is to be provided from the SEC substation and through SEC
tunnels to enable the testing and commissioning of the Generators, Chillers,
Central Switch Hall and other supporting buildings of Load center B.

Preliminary Testing:
The connection from this facility to the SEC substation will be completed in
order to receive permanent power from SEC. Testing and commissioning of the
Load Center will be completed after receiving the permanent power from the
SEC substations.

1.3

LOAD CENTER C

Summary Status:
Design:
100% Design is substantially complete.

Key Issues:

Procurement:
The procurement process is in progress. Critical long lead items like generator,
chiller, cooling tower, oil type transformers, switchgears etc are delivered at
site. Delivery of AHUs, HVAC fans, light fixtures, sanitary fixtures etc. are in
progress. Delivery of potable water pumps, chlorination system, MDB, SMDB
etc. are expected. Material submission and approval of equipment like FCU,
SCADA etc. are pending.

Construction:
dd)
Central Building: Structural activities are complete. Rough finishes are
substantially complete. MEP and SAS installation activities are in progress.
Roofing and cladding are in progress.
ee)Office Building: Structural activities are in progress. Rough finishes are in
progress. MEP and SAS installation activities are in progress. Cladding and
glazing are substantially complete.
ff) District Cooling Plant: Structural activities are complete. Rough finishes
are in progress. MEP and SAS services installation activities are in
progress. Chillers, pumps and cooling towers are installed.
gg)
Generator Building: Concrete and steel structural activities are
complete. MEP and SAS services installation activities are in progress.

Package 422 CWS BL-02 Rev-02


P a g e |4

Delay in the construction completion of the SEC substation has the


potential to delay the integrated testing and commissioning of the
project.

Construction Methodology:
There are many components of the Load Centers and they are as follow:

Generator Building (Transformer area, Switch area ( G + 1) floor,


Generator/Plenum area ( G+ 2 Floor).

District Cooling Plant ( 02 Basement+ 01 Mazzanine+ Roof)

Central Switch Hall ( G + 1)

Office Building ( G + 3 Floor)

Workshop & Storage( G + 01 ) Floor

SEC Tunnel Work

Construction Working Schedule BL-02 Rev 01

Substation

Fuel Tank Station

Guard House A

Gurad Hause B

Fire Water Pump Station

Potable Water Holding Tank

Potable Water Pump Station

Diesel Bulk Storage Tank

Basement Service Gallery and Ramp

Waste Compound

Precast Fence

Landscape

Car Parking

Security Fencing

The typical construction sequence of the buildings starts with the earthwork.
Earthwork is followed by blinding, screed and footing pad construction. After
the construction of the footing pad the construction of the foundation walls
and columns start. If the building is steel framed the foundation column and
wall will be concreted with the anchor bolts. After the completion of
foundation wall and column construction waterproofing of the footing takes
place. After waterproofing, backfilling and compaction takes place. The
installation of underground utilities and slab on grade construction is
scheduled after the completion of the first suspended slab above the slab on
grade. After the backfilling and compaction are complete, construction of
walls, columns and suspended slab follows. For steel framed building, after
the completion of backfilling and compaction, the erection of steel structure
progresses. Upon completion of the steel structure erection, fireproof
painting will follow. Slab on grade construction is scheduled to start after the
fireproofing the steel structure. Block wall/drywall partitions, door frame
installation and plastering will progress one after the other following the
completion of the slab on grade. Overhead MEP/SAS services installation
will start along with the block wall construction. After the completion of
plastering, wall finishes like painting initial coats, wall tiling will start and
progress. After the completion of painting initial coats/wall tiling, false
ceiling installation will follow. Before the false ceiling panel installation all
the overhead MEP/SAS activities will complete. After the completion of the
Package 422 CWS BL-02 Rev-02
P a g e |5

false ceiling, flooring activities will start and progress. Installation of floor
mounted equipment will be after the completion of flooring. Installation of
doors, furniture and final coats of paint will be done after flooring.

Power Available From SEC :


Permanent power is to be provided from the SEC substation and through SEC
tunnels to enable the testing and commissioning of the Generators, Chillers,
Central Switch Hall and other supporting buildings of Load center C.

Preliminary Testing:
The connection from this facility to the SEC substation will be completed in
order to receive permanent power from SEC. Testing and commissioning of the
Load Center will be completed after receiving the permanent power from the
SEC substations.

1.4

SOLID WASTE PROCESSING


CENTER

Summary Status:
Design:
The 100% design preparation, submission and approval are in progress. The site
layout design is under preparation.

Procurement:
The procurement process for MEP and SAS items will commence with
material submissions and approval prior to fabrication. Material submissions
are waiting for the final MEP design approval.
The material submission of the critical long lead equipment which are
specific to the facility like; Trommel screen, Ballistic separator, hand sort
cabins, baler, conveyors, optical separator etc. are waiting for the final
design completion.

Construction:
Foundation is in progress for the Guard House, Administration and
Support Staff & Workers Buildings.
Key Issues:
The delay in the finalization of the Solid Waste Processing Center location has
delayed the design, procurement and construction of the facility.

Construction Working Schedule BL-02 Rev 01


Any delay in the material submission and approval process has the potential to

The typical construction sequence of the buildings starts with the earthwork.

delay the construction activities.

Earthwork is followed by blinding, screed and footing pad construction. After


the construction of the footing pad the construction of the foundation walls and

Construction Methodology:
There are many components of the Solid Waste Processing Center and they are
as follow:

columns start. If the building is steel framed the foundation column and wall
will be concreted with the anchor bolts. After the completion of foundation wall
and column construction waterproofing of the footing takes place. After
waterproofing, backfilling and compaction takes place. The installation of
underground utilities and slab on grade construction is scheduled after the

Material Recovery Facility (Steel Framed)

Waste Transfer Station (Steel Framed)

Bulky Waste Area (Steel Framed)

suspended slab follows. For steel framed building, after the completion of

Green Waste Area (Steel Framed)

backfilling and compaction, the erection of steel structure progresses. Upon

Workshop & Storage Area (Steel Framed)

Hazardous Waste Storage Area (Steel Framed)

Administration Building

Support Staff & Workers Building

construction. After the completion of plastering, wall finishes like painting

Substation (Steel Framed)

initial coats, wall tiling will start and progress. After the completion of painting

Generator Building (Steel Framed)

Guard House

After the completion of the false ceiling, flooring activities will start and

Fuel Station

progress. Installation of floor mounted equipment will be after the completion

Vehicle & Truck Parking

Truck Wheel Washing Bay

Weighbridges

Asphalt & Precast Pavement Areas.

Green Areas

Security Fence

External Underground Utilities

There are 11 buildings in the facility. Out of the 11 buildings, 8 are steel framed
buildings.

Package 422 CWS BL-02 Rev-02


P a g e |6

completion of the first suspended slab above the slab on grade. After the
backfilling and compaction are complete, construction of walls, columns and

completion of the steel structure erection, fireproof painting will follow. Slab on
grade construction is scheduled to start after the fireproofing the steel
structure. Block wall/drywall partitions, door frame installation and plastering
will progress one after the other following the completion of the slab on grade.
Overhead MEP/SAS services installation will start along with the block wall

initial coats/wall tiling, false ceiling installation will follow. Before the false
ceiling panel installation all the overhead MEP/SAS activities will complete.

of flooring. Installation of doors, furniture and final coats of paint will be done
after flooring.
The installation of the external utilities work will progress in parallel with the
structural and MEP activities of the buildings. After the installation of the
underground utilities, asphalt pavement will start. The asphalt pavement area is
categorized into 6 zones. After the completion of the asphalt roads, the precast
pavement activities start and progress. Vehicle parking shade construction is
scheduled after asphalt road construction. The installation of the weighbridges
as well as the truck wheel washers are started after the completion of the
pavement.