Professional Documents
Culture Documents
a r t i c l e
i n f o
Article history:
Received 26 March 2012
Received in revised form 24 July 2012
Accepted 3 December 2012
Keywords:
Chilled water systems
Optimization
Modeling and simulation
Dymola/Modelica
HVAC system congurations
Energy performance
a b s t r a c t
The paper presents an incremental development of the methodology for chilled water system design
optimization. Initially, the system conguration parameters are varied with xed design conditions
to conrm the established best practice design criteria, followed by a comprehensive system design
optimization. The implemented simulation-based optimization approach couples the Dymola/Modelica
dynamic modeling and simulation program with GenOpt generic optimization program to nd optimal
system conguration. A dynamic system model is developed to vary and simulate different chilled water
system congurations. Optimization of the chilled water system is achieved at both design and conguration level using ve design variables. Two discrete variables are related to system conguration: number
of chillers and number of cooling towers and three continuous variables are related to system design:
building load demand, temperature difference across condenser, and cooling tower fan speed. The strategy of varying system design and conguration variables together for overall system optimization proved
to be the most energy efcient. For a xed building load demand, power consumption of the considered
system can be reduced 1743% by selecting an optimal system conguration.
2012 Elsevier B.V. All rights reserved.
1. Introduction
Energy performance of buildings strongly depends on selection
of heating, ventilation, and air-conditioning (HVAC) system conguration as HVAC systems account for approximately 3060% of
the total building energy consumption, depending on the building type [13]. As buildings are responsible for 2040% of the total
energy consumed [1], climatization systems consume 1020% of
total energy in the developed countries. It has been observed that
chilled water system consisting of primary HVAC system components, e.g. chillers, cooling towers, pumps accounts for most of
the electricity use in the HVAC system [3]. Thus, selecting optimal
chilled water system conguration can result in substantial power
savings. In practice, however, selection of optimal system conguration is a complex task in terms of effort and time as multifaceted
chilled water system congurations need to be analyzed. Therefore
HVAC practitioners select the system congurations and design
112
8175 [2325]
Centrifugal
2725 [775]
446.4 [127]
457 [130]
6.1
6.7/12.2 [44/54]
57 [900]
29.4 [85]
111[1760]
Cooling towers
Type
Water ow rate l/s [gpm]
Fan motor power kW [hp]
Design wet bulb temperature C [ F]
Design dry bulb temperature C [ F]
Design approach temperatures C [ F]
Design range temperature C [ F]
Draw-through
76 [1200]
18.65 [25]
17 [62.6]
26 [78.8]
8.3[15]
5.56 [10]
Pumps
Rated power of each chilled water pump kW [hp]
Rated power of each condenser water pump kW [hp]
30 [40]
19 [25]
113
pump and cooling tower models were part of the Buildings library.
All component models were operating in parallel arrangement
under the design conditions specied in Table 1.
Centrifugal chillers were operated with xed chilled water supply and return temperatures at 6.7 C (44 F) and12.5 C (54 F),
respectively. Chiller sequencing allowed the running chillers to
operate at the same part load conditions. The demand loads, Qload ,
were applied from an external text le with an increment of
35.16 kW (10 tons) up to the peak load demand. Each applied load
determined the evaporator mass ow rate assuming xed design
temperature difference of 5.55 C (10 F) across the evaporator.
Thus, load-based mass ow rates were applied through the prescribed ow chilled water pumps on the evaporator side of the
chillers. Similarly, the condenser water ow rate was determined
to satisfy the required amount of heat rejection by the condenser.
Such heat rejection was computed from the chiller model based
on the applied load, Qload . The condenser water ow rates were
114
Table 2
Summary of estimated initial costs (costs in D are estimated based on the 1.23$/D exchange rate).
Description
Cost/ton (D [$])
147 [180]
37 [45]
106 [130]
4.1 [5]
113,925 [139,500]
28,370 [34,875]
42,400 [52,000]
1640 [2000]
13,015 [16,000]
19,523 [24,000]
4393 [5400]
2440 [3000]
218,873 [268,375]
54,718 [67,094]
273,591 [335,469]
146,688 [179,775]
36,672 [44,944]
183,360 [224,719]
46,480 [57,000]
11,620 [14,250]
58,100 [71,250]
[33,38,41,42]. The initial and installation costs of water-cooled centrifugal chillers and cooling towers are estimated based on the unit
capacity, i.e. cost per ton. The piping costs, including ttings and
valves, are estimated using Pipe Size Optimization tool [33,43]. The
tool calculates the initial piping costs based on the ow rate for
specied piping segments. In addition, the tool also accounts for
the number and types of various valves and ttings typically used
in chilled water systems. The costs of different valves and ttings
are also provided based on the respective pipe sizes. In the current study, the number and type of valves and ttings are decided
from the piping schematic of the reference system [26]. The initial and installation costs of water-cooled centrifugal chillers and
cooling towers along with the piping/tting/valve costs are summarized in Table 2. The estimated value of 25% contractor markup
is considered in the calculations [38].
As the current study involves different congurations of the
chilled water system varying the number of chillers and cooling
towers, the nal estimated initial cost of each conguration is
calculated from Eq. (2).
Ctotal = CH CPchiller (Cchiller + Cinst.CH ) + CT CPtower
(Ctower + Cinst.CT ) + Cpiping/fittings/valves
(2)
(1)
(3)
Here Ctotal is the total initial cost, CPchiller , CPtower are the chiller
and cooling tower nominal capacities (tons), Cchiller , Ctower are the
unit initial the chiller and cooling tower costs (cost/ton), Cinst.CH ,
Cinst.CT are the unit installation costs of the chiller and cooling
tower (cost/ton), respectively, Cpiping/ttings/valves is the total cost of
piping/ttings/valves, CCHWside , CCWside are the baseline costs of piping/ttings/valves for the chilled water and condenser water sides,
and Cadd.chiller , Cadd.tower are the costs of piping/ttings/valves for
adding each chiller and cooling tower in the system, respectively.
The estimated initial costs of each conguration are used for
economic considerations related to the automatically chosen system congurations based upon the dened optimization objective
function.
4.4. Optimization algorithm
As previously mentioned, overall optimization of the chilled
water system involves ve design variables with the total system
115
Table 3
Design variables and bounds.
Minimum
Maximum
Step
Initial
Tower fan
speed, F (%)
Temp. difference
condenser side, T ( C) [ F]
No. of
chillers, CH
No. of cooling
towers, CT
0.3
1
0.01
1
3 [5.4]
15 [27]
0.01
3
1
3
1
1
3
18
1
3
1055 [300]
7032 [2000]
Value
Neighborhood topology
Neighborhood size
Number of particles
Number of generations
Seed
Cognitive acceleration
Social acceleration
Max velocity gain continuous
Max velocity discrete
Constriction gain
Mesh size divider
Initial mesh size exponent
Mesh size exponent increment
Number of step reductions
von-Neumann
5
20
5
1
2.8
1.3
0.5
4
0.5
2
0
1
4
116
the nominal load, yielding a chiller COP of 7.68. Chiller COP reduces
to 7.57 and 6.83 when system operates with two and three chillers
at 45% and 30% of the nominal load, respectively.
Fig. 4 summarizes the optimal conguration options minimizing
the total system power consumption with respect to the number
of chillers and cooling towers at full range of load demand. The
optimal congurations shown in Figs. 3 and 4 are in agreement
with the real system design [26] and thus validate the proposed
methodology.
Moreover, due to the initial conguration costs shown in Fig. 3,
savings in total power consumption are more signicant at higher
than at lower demand loads per unit initial cost increment.
5.2. Modied system congurations: 2nd strategy
More cooling towers within the ow limit, i.e. ow turndown
ratio of one-third of the design ow [38], are generally benecial as
lower fan speed and power are required. The original chilled water
system design used ve cooling towers with 76 kg/s design ow.
In the second strategy, the number of cooling towers within the
ow constraint is based on the temperature difference across the
condenser. Such temperature difference determines the required
water ow rate through the condenser and cooling towers to satisfy
the condenser heat rejection for specic Qload . Eqs. (4) and (5) were
used to nd the lower and upper limits for the number of cooling
towers, respectively, satisfying the ow constraints.
Upper limit:
CT
Q
1
C1
load
C2
ml
T
(4)
Lower limit:
CT
C1
Q
1
load
C2
md
T
(5)
117
Fig. 3. Total power consumption and costs of the Baseline system congurations at various demand loads (A) Qload = 1055 kW, (B) Qload = 1582 kW, (C) Qload = 2637 kW, (D)
Qload = 3516 kW, (E) Qload = 5274 kW, and (F) Qload = 7032 kW.
Fig. 5. Number of cooling towers within ow limit at Qload of 2637 kW (750 tons).
118
Table 5
Range of conguration parameters used for optimization at various loads with constant condenser side temperature difference (4.45 C [8 F]) at full fan speed (100%).
Load, Qload (kW [tons])
No. of chillers, CH
7032 [2000]
5274 [1500]
3516 [1000]
2461 [700]
1582 [450]
1055 [300]
3
23
23
13
12
12
617
412
38
26
24
23
Fig. 6. Total power consumption and costs of the modied system congurations at various demand loads (A) Qload = 1055 kW, (B) Qload = 1582 kW, (C) Qload = 2637 kW, (D)
Qload = 3516 kW, (E) Qload = 5274 kW, and (F) Qload = 7032 kW.
119
Fig. 7. Iteration runs for the minimization of Ptotal at Qload of 3516 kW [1000 tons].
in lower Ptotal and smaller number of cooling towers than the other
two previously considered strategies. Therefore, such design is also
more appropriate from economic aspects as it would decrease the
initial cost of the overall system.
Table 7 shows the optimal combination of system parameters
to achieve the minimum total power consumption. For example, at
the low load demand of 1054.8 kW (300 tons), the chilled water system optimally operates with one chiller and three cooling towers
maintaining the optimal design T of 4 C (7.2 F) across the condenser, while the optimal cooling tower fan speed is 47.94%. The
system has a minimum total power consumption of 171.56 kW. All
other feasible combinations in terms of the number of chillers, cooling towers, temperature differences across the condenser, and CT
fan speeds will result in higher total system power consumptions.
Similarly, at the peak design load of 7032 kW (2000 tons), the optimal system design conguration yields a total power consumption
of 1557.3 kW comprising of three chillers and ve cooling towers
operating with optimal design T of 16.94 C (30.5 F) at fan speed
of 85.3%. The optimal congurations comprise of maximum ve
cooling towers despite of the fact that the number of cooling towers within the ow limit can be up to 25. Consequently, in the case of
varying condenser water temperature difference, water mass ow
rate and cooling tower fan speed, may not be benecial to run as
many cooling towers as possible within the ow constraints. The
results shown in Table 7 are in agreement with the real system congurations. The optimal fan speeds below 90% also conrm the best
design practice, as suggested by Mark Hydeman, P.E., Taylor Engineering: running the cooling tower fans below 90% speed would
achieve higher energy efciency. Due to the cubic relation between
the fan power and airow rate, the cooling tower energy consumption greatly increases with the top 10% fan speed, achieving a very
small drop in condenser water supply temperature.
5.4. Summary of the chilled water system analyses
A methodology is proposed for design optimization of the chilled
water system by applying three strategies: (1) baseline system
comprising of a maximum of ve cooling towers with xed design
temperature difference across the condenser at full fan speed,
Table 6
Range of system parameters used for optimization at various loads.
Load, Qload (kW [tons])
No. of chillers, CH
7032 [2000]
5274 [1500]
3516 [1000]
2461 [700]
1582 [450]
1055 [300]
3
23
23
13
13
12
325
318
312
38
36
24
325 [5.445]
315 [5.427]
312 [5.421.6]
38 [5.414.4]
35 [5.49]
34 [5.47.2]
30100
30100
30100
30100
30100
30100
120
Fig. 8. Total power consumption and costs of the overall optimized system congurations at various demand loads (bars represent power range due to varying optimization
input parameters) (A) Qload = 1055 kW, (B) Qload = 1582 kW, (C) Qload = 2637 kW, (D) Qload = 3516 kW, (E1) Qload = 5274 kW with 2 chillers, (E2) Qload = 5274 kW with 3 chillers
and (F) Qload = 7032 kW.
of chilled water systems. In addition, the strategies consider initial costs of equipment, including chillers, cooling towers and
piping/ttings/valves, having in mind that additional chillers and
cooling towers typically decrease the annual energy costs and payback period [33,41].
Optimal total system power consumptions and system energy
use in kW/ton from the considered approaches are shown in
Table 7
Optimal values of system parameters and objective function at various loads.
Load, Qload
(kW [tons])
No. of chillers,
CH
No. of cooling
towers, CT
Fan speed,
F (%)
Optimal
Ptotal (kW)
7032 [2000]
5274 [1500]
3516 [1000]
2461 [700]
1582 [450]
1055 [300]
3
3
2
2
1
1
5
5
5
4
4
3
16.94 [30.5]
12.68 [22.8]
8.45 [15.2]
7.63 [13.7]
4.88 [8.8]
4 [7.2]
85.31
75.44
62.8
59.75
49.3
47.9
1557.3
993.1
582.7
394.9
240.7
171.6
121
Table 8
Optimal values of Ptotal and system energy use of all strategies (minimum values highlighted).
Qload (kW [tons])
7032 [2000]
5274 [1500]
3516 [1000]
2461 [700]
1582 [450]
1055 [300]
2757.3
1498.8
752.7
479.7
297.8
207.4
1808.4
1178.8
706.9
479.7
297.8
207.4
1557.3
993.1
582.7
394.9
240.7
171.6
43.5
33.8
22.6
17.6
19.2
17.3
1.37
0.99
0.75
0.68
0.66
0.69
0.9
0.78
0.71
0.68
0.66
0.69
0.78
0.66
0.58
0.56
0.53
0.57
Acknowledgements
The authors express profound gratitude to Mark Hydeman, P.E.,
Fellow ASHRAE, Principal at Taylor Engineering LLC, Alameda, CA,
USA, and Anton Haumer, Senior Engineer, AIT Austrian Institute
of Technology, Vienna, Austria, for their insightful comments and
expertise.
References
[1] L. Perez-Lombard, J. Ortiz, C. Pout, A review on buildings energy consumption
information, Energy and Buildings 40 (2008) 394398.
[2] J.C. Lam, R.Y.C. Chan, C.L. Tang, D.H.W. Li, Electricity use characteristics of
purpose-built ofce buildings in subtropical climates, Energy Conversion and
Management 45 (2004) 829844.
[3] J.C. Lam, Energy analysis of commercial buildings in subtropical climates, Building and Environment 35 (2000) 1926.
122
[25] M. Wetter, GenOpt Generic Optimization Program, User Manual. Available at:
http://gundog.lbl.gov/GO/download/manual-2-1-0.pdf (accessed 16.08.10).
[26] M. Hydeman, G. Zhou, Optimizing chilled water plant control, ASHRAE Journal
(June) (2007) 4454.
[27] W.L. Lee, S.H. Lee, Developing a simplied model for evaluating chiller-system
congurations, Applied Energy 84 (2007) 290306.
[28] R.T. Olson, J.S. Liebman, Optimization of a chilled water plant using
sequential quadratic programming, Engineering Optimization 15 (1990)
171191.
[29] F.W. Yu, K.T. Chan, Strategy for designing more energy efcient chiller
plants serving air-conditioned buildings, Building and Environment 42 (2007)
37373746.
[30] M. Ali, V. Vukovic, M.H. Sahir, Methodology for automated optimization of
HVAC system conguration, in: 41st KGH International Congress on HVAC&R,
Belgrade, December 13, Serbia, 2010.
[31] F.W. Yu, K.T. Chan, Optimization of water-cooled chiller system with load-based
speed control, Applied Energy 85 (2008) 931950.
[32] F.W. Yu, K.T. Chan, Economic benets of optimal control for water-cooled chiller
system serving hotels in a subtropic climate, Energy and Buildings 42 (2010)
203209.
[33] Taylor Engineering Company, Chilled Water Plant Design Guide. Availat:
http://www.taylor-engineering.com/downloads/cooltools/EDR
able
DesignGuidelines CoolToolsChilledWater.pdf (accessed 07.03.11).
[34] Air-Conditioning and Refrigeration Institute, Performance Rating of WaterChilling Packages Using the Vapor Compression Cycle, ARI Standard
550/590-2003, 2003.
[35] Cooling Technology Institute, CTI Standard STD-201 Certied Cooling Towers,
2009.
[36] ASHRAE, ASHRAE Standard 90.1-2004, Energy Standard for Building Except
Low-Rise Residential Buildings, SI edition, 2004.
[37] J.K. Cross, An evaluation of ice and chilled water supply system as thermal
storage media for combustion turbine inlet air cooling systems, MS Thesis at
University of Wisconsin-Madison, 1994.
[38] M. Hydeman, S. Taylor, J. Stein, Codes and Standards Enhancement Report, 2005
Title 24 Building Energy Efciency Standards Update, Code Change Proposal for
Cooling Towers, April 8, 2002.
[39] The TRANE Company, Chilled Water Plant Cost Estimated. Available at:
http://www.trane.com/commercial/uploads/pdf/865/ctv-trt-001-en.pdf
(accessed 11.06.12).
[40] The Carrier Company, Personal Communication with Business Development
Manager in Vienna.
[41] W.P. Bahneth, E.B. Peyer, Variable primary ow chilled water systems:
potential benets and application issues, in: Technical Report Under HVAC&R
Research for 21st Century (21CR) program, March 2004.
[42] J.W. Furlong, F.T. Morrison, Optimization of water-cooled chiller-cooling tower
combinations, Cooling Technology Institute Journal 26 (2004) 1219.
[43] S.T. Taylor, M. McGuire, Sizing pipe using life-cycle costs, ASHRAE Journal
(2008) 2432.
[44] M. Wetter, J. Wright, A comparison of deterministic and probabilistic optimization algorithms for non-smooth simulation-based optimization, Building and
Environment 39 (2004) 989999.
[45] Modelica Library for Building Energy and Control System. Available at:
https://gaia.lbl.gov/bir (accessed 05.08.11).
[46] Modelica Libraries, Catalog Version 2.1. Available at: http://www.bauschgall.de/Modelica Libraries Catalog.pdf (accessed 05.08.11).