Shore Protection Works for River front at RIL Hazira

Technical Specification

This work shall include providing, fabricating, transporting, erecting and painting
structural steel, rivet steel, cast steel, steel forgings, cast iron and other incidental
metal construction of the kind, size and quantity in conformity with the drawings and
these specifications or as desired by the Engineer.

15.1

General
General requirements relating to the supply of material shall conform to the
specifications of IS : 1387. Materials

15.1.1

Welding consumables
Welding consumables shall comply with the following Indian Standards as appropriate:

15.1.2

IS : 814

Covered Electrodes for Metal Arc Welding of structural steel for (Part
1) welding other than sheet

IS : 814

For welding sheets (Part 2)

IS : 1278

Filler rods and wires for gas welding

IS : 1395

Low and medium alloy Steel covered electrodes for manual Metal Arc
Welding

IS : 3613

Acceptance Tests for wire flux combinations for sub-merged arc


welding of structural steel

IS : 7280

Bare wire electrodes for gas shield arc welding of structural steel

IS : 6419

Welding rods and bare electrodes for gas shielded arc welding of
structural steel

IS : 6560

Molybdenum and chromium-molybdenum low alloy steel welding


rods and bare electrodes for gas shielded arc welding

Paints
All material for paints and enamels shall conform to the requirements specified on the
drawings or other special provisions laid down by the Engineer. Only epoxy paint shall
be used
Unless otherwise specified, paints shall conform to the relevant IS specifications. The
paints which have been tested for the following qualities as per specifications given in
the relevant IS codes only shall be used:
-

Weight test (weight for 10 litre of paint, thoroughly mixed)

Drying time

Consistency

Dry thickness and rate of consumption.

15.2

Fabrication

15.2.1

General

Page 18 of 27

Shore Protection Works for River front at RIL Hazira


Technical Specification

All work shall be in accordance with the IFC drawings and as per the specifications
approved by EIC.
The Contractor shall prepare shop drawings for fabricating any member and obtain
approval of the Engineer before the start of work. Complete information regarding the
location, type, size and extent of all welds shall be clearly shown on the shop
drawings. These drawings shall distinguish between shop and field welds.

15.3

Painting

15.3.1

General
All metal work shall be given approved shop coats as well as field coats of painting as
specified. The item of work shall include preparation of metal surfaces, application of
protective covering and drying of the paint coatings and supply of all tools, scaffolding,
labour and materials necessary.
Coatings shall be applied only to dry surfaces and the coated surfaces shall not be
exposed to rain or frost before they are dry. The coatings shall be applied to all
surfaces excluding shear connectors and inner surfaces of fully sealed hollow
sections. Care shall be taken during coating of adjacent surfaces to build up primer on
the shear connectors.

16.0

SHEET PILE

16.0

General
Construction of the steel sheet pile wall shall be performed in the following order. Contractor
shall prepare and submit his proposed construction time schedule for the works in the order
as listed below and obtain approval of COMPANY/PMC in writing prior to starting the work
General

16.1

Initial banking for driving of sheet piles


All initial banking has to be formed at contractor's own cost for taking the machinery to drive
the sheet piles. The area shall be filled with pit sand for leveling the ground.

16.2

Driving of steel sheet piles

16.3

Interlocking sheet piles are OZ 28A section with interlock of Arcelor Mittal or approved
equivalent as per manufacturers specification and minimum Section modulus of 2850 cm3/m
are to be driven for shore protection as per drawings.

16.4

Piles shall be driven, true to plumb and alignment. Hammer for sheet pile driving shall be
drop hammer, or vibratory hammer. In order to maintain alignment, temporary guide frames
shall be fixed in place and checked prior to actual driving Sheet pile driving shall commence
initially with minimum impact of hammer, which can be increased later after ensuring that the
piles are being driven vertically through the interlocking grooves along with designed
alignment. The sheet piles are to be driven with batten welded at suitable intervals. The Steel
Sheet Pile may be lifted by suspending from single point.