You are on page 1of 93

sr. no.

Particulars

Pg no.

Introduction to precast concrete


1

3
Types and procedure of precast concrete construction

12
Precast technology in residential building

21
Case study on the precast technology in Bandra worli

68
sea link (BWSL)
Research paper study on the future of precast

94
technology in law rise building

Precast technology
Subject:

Advanced construction practice

Topic:

Precast technology

Prepared by: Hardik Patel (PT101214)


Guided by:

Prof. Jyoti Trivedi


Dr. Ganesh Devkar

Date:

7th oct. 2014

Precast Concrete
Introduction to precast concrete
Types and procedure of precast concrete construction
Precast technology in residential building
Case study on the precast technology in Bandra worli
sea link (BWSL)
Research paper study on the future of precast
technology in law rise building
Video on manufacturing of precast wall
Video on installation of precast modular pavement

Precast Concrete
Precast concrete is a construction
product produced by casting concrete in
a reusable mould or "form" which is then
cured in a controlled environment,
transported to the construction site and
lifted into place. In contrast, standard
concrete is poured into site-specific
forms and cured on site.
4

History
precast paneled buildings were pioneered
in Liverpool England, in 1905
A process was invented by city engineer John
Alexander Brodie.
Between 1917 and 1932, they erected 145
such buildings

Why Precast???
Speed to market
Strong image
High quality
Low maintenance
Effective pricing
Safety
Early input

Why precast ?? As a
Project Manager

Elimination of needs for supports / scaffolding

Elimination of temporary structures

Reduced health and safety risks

Reduction in lorry traffic and traffic management

Easier management of steel procurement

Elimination for long and continuous pouring operations

Significant reduction/elimination of temporary shuttering

Controlled curing of concrete

Improved quality controls performed at the factory

Process not subjected to weather conditions

Precast concrete Products


Agricultural Products
Building and Site Amenities
Retaining Walls
Sanitary and Storm water
Utility Structures
Water and Wastewater Products
Transportation and Traffic Related Products
Modular Paving
Marine Products
8

Raw Materials
Portland cement
water
Sand
Gravel
admixtures
For light weight
clay, shale, or slate
pumice and scoria blast furnace

Design
The shapes and sizes of most common concrete blocks have been
standardized to ensure uniform building construction.
block design, called a split-faced block, includes a rough, stone-like
texture on one face of the block instead of a smooth face
we must consider not only the desired shape, but also the
manufacturing process required to make that shape
We must consider the utility facility requirements in building during
design

10

Procedure for
precast
manufacturing
11

Procedure for precast construction

Production of reinforced cages and main connections


Assembly of moulds
Mix being poured
Compaction of concrete using poker vibrator
Precast concrete being moved to the storage area
Storage of high-quality units in storage area
Transport to site
Erection at site
Finished building

12

Production of reinforced cages and


main connections

13

Assembly of moulds

14

Mix being poured

15

Compaction of concrete using poker


vibrator

16

Precast concrete being moved to the


storage area

17

Storage of high-quality units in


storage area

18

Transport to site

19

Erection at site

20

Types of precast construction


Large-panel systems
Frame systems

21

Large-Panel Systems
The designation large-panel system refers to multistory structures
composed of large wall and floor concrete panels connected in the
vertical and horizontal directions so that the wall panels enclose
appropriate spaces for the rooms within a building. These panels
form a box-like structure

22

Large panel

23

24

Frame Systems
Precast frames can be constructed using either linear
Elements or spatial beam-column sub assemblages.
Precast beam-column sub assemblages have the advantage that the
connecting faces between the sub assemblages can be placed away from
the critical frame regions; however, linear elements are generally
preferred because of the difficulties associated with forming, handling,
and erecting spatial elements.
The use of linear elements generally means placing the connecting faces at
the beam-column junctions.

25

Installation CONSIDERATIONS

All safety issues on site when handling precast elements,


especially so when working within a tight site

The lifting capacity of the crane used


The working boom-radius of the crane
The suitability of construction materials for the purpose of use,
i.e. sealant, grouting, shim plate, propping etc
Co-ordination with the precaster and specialist supplier to achieve the best performance and
working method - precaster often provide relevant technical requirements to the contractor
during the design development phase to avoid discrepancy

26

Crane Position

27

28

Setting Out
1. Surveyor to set cross reference.
2. Transfer grid and mark wall position on slab.
3. Mark 100mm offset line from rear building
edge.
4. Offset wall position by 200 mm.
5. Secure 2x2 timber to the floor at wall edge to guide wall.

29

Setting Out

30

31

Wall Positioning
1. The first wall in place has to be the partition wall
at the rear.
2. Mark a line parallel to and 100mm from the
external edge of the wall.
3. Place shim plate @~500 c/c on the floor and
level to wall soffit. Shim plate may also be
placed on Non-shrink mortar bed and allow to
set.
4. Adjust position of the dowel bar.
32

Setting Out

33

34

Wall Adjustment
1. Position adjacent walls and plumb wall corners
at 200 mm offset
2. Adjust verticality until within +2 or 2 mm
3. Ensure the four faces of every walls are
adjusted
4. Position string 250 mm from face of walls
5. Walls within the same line are to be adjusted
within same tolerance
6. Ensure air-pocket is fully grouted
35

Wall Adjustment

36

37

Beam Setting Out


1. Cast wall joint.
2. Mark 1 m reference line.
3. Confirm pocket level. Position shim plate to
correct beam soffit level if required.
4. Mark position of beam on floor.
5. Hoist beam in place and check top level.
6. Plumb beam to verify position on floor below.
7. Ensure beam verticality with a spirit level.
8. Wedge beam against pocket and grout the
gap between the beam and the wall.
38

Beam Setting Out

39

40

Slab Setting Out


1. Position the slab temporary supports and
adjust the slab soffit level approximately.
2. Raise the height of the supports about 5 mmabove slab
soffit level
3.Hoist slab in place on top of beam and support.
4.Verify level of every plank soffit at four corners
and center.
5. Adjust level of temporary support accordingly

41

Slab Setting Out

42

Staircase
1. Position landing or slab and verify soffit
level at four corners.
2. Adjust level to within tolerance.
3. Position shim plates at staircase support
location to correct level.
4. Verify level difference between pegs on
top and below.
5. Hoist staircase in place.
6. 10mm gap between precast plank andstaircase
43

Staircase

44

45

Installation Requirements
Elements of control
Alignment, Verticality and Levels
Tolerance level

1. For Wall
Vertical deviation +2 mm, -2 mm
Horizontal deviation 0 mm

2. For Beam & Slab


Departure from intended horizontal position, +2 mm or 2 mm
Departure from intended vertical position, +2 mm or 2 mm

46

Connection types

47

48

Columns Connection

49

50

Beam-column connection

51

52

Slab-Beam Connection

53

54

CONSTRAINTS

SOLUTIONS

! Small road in front of site may not !


allow crane and delivery trailers up to 3.Sm wide to
park.
!

Crane and trailer are unable negotiate small to


turning radius junctions of small roads.

Use smaller crane and trailers to deliver


install
small

and

components.
! Study the locality and look for at
available space
for turning. Have one worker direct traffic while crane
and trailer is turning.

Diversion of existing services such ! as


lamp-posts, fire hydrants and overhead electrical
cables may be necessary.

Diversion must be done before installation of precast


components begins.

Existing trees and shrubs in front ! of


site require National Parks Board
approval before they can
be removed and later reinstated.

The
consultants must write
Board for approval much earlier
begins.

in to National Parks
before
construction

55

56

57

Cost saving

58

59

Time saving

60

61

Time comparision

62

Material saving

63

Limitations

Each panel variation (especially openings, bracing inserts and lifting inserts) calls for complex, specialized
engineering design.

It is often more expensive than alternatives (can be offset by reduced construction times, earlier access by following
trades, and simplified finishing and services installation).

Building services (power, water and gas outlets; conduits and pipes) must be accurately cast in and are difficult to add or
alter later. This requires detailed planning and layout at design stage when plumbing and electrical trades are not usually
involved.

Erection requires specialized equipment and trades.

High level site access required

Panel connection and layout for lateral bracing requires detailed design.

Temporary bracing requires floor and wall inserts that have to be repaired
later.

64

Research paper study


The Future for Precast Concrete in Low-Rise Housing
by. Dr Jacqueline Glass (BA (Hons), Dip Arch, Dip BRS, Phd, CertHE.)

Dr Jacqueline Glass is the British Cement Association Senior Lecturer in the School of Architecture at
Oxford Brookes University where she has been carrying out research in concrete construction since 1994.
Dr Glass is currently Project Manager of an EPSRC funded research project in innovation in reinforced
concrete and has previously contributed to Partners in Technology projects on
tilt-up and hybrid concrete construction. Dr Glass is Architectural Consultant to the British Cement
Association and the Reinforced Concrete Council and is an active participant on several concrete industry
trade associations. She has published widely in both trade journals and scholarly publications and has
lectured in the UK and USA on a broad range of concrete related topics.

65

The Future for Precast Concrete in


Low-Rise Housing

This report is about the future use of precast concrete in low-rise housing in the UK. It has been
produced in response to a growing level of interest in prefabrication.
focuses on the use of precast concrete, and considers the history of precast concrete in housing
examines the key features of concrete in general, and precast concrete specifically. Fire resistance,
thermal mass, acoustic insulation and durability are included together with a discussion of cost and value
issues
considerations such as services integration and adaptability are related to the future needs of
occupants, and procurement strategies are noted.

Report also contains an account of the current market success of


other materials in the prefabricated housing sector

66

Conclusions and recommendations


1. The problems of the past can be avoided
2. Low-rise is not high rise
3. Cultural and perceptual views are critical
4. The market potential for precast concrete exists
5. The balance of cost and value needs to be clear
6. Precast means innovation in delivery
7. People need to be convinced

67

Case study on
Precast deck of
BWSL
68

Why precast segmental deck????


Total length

: 5.6 kilometres

Width

: 2 x 20 meters (66 ft)

Height

:126 meters (413 ft)

Longest span :2 x 250 meters (820 ft)


Clearance below

:20 meters (66 ft)

The Maritime Board does not allow marine traffic in monsoon


season.

69

Decision for precast segmental


construction
800m long Precast Segmental Approach Bridge on
Bandra Side.
200m long Precast Segmental Approach Bridge between Bandra
Cable Stayed Bridge and Worli Cable Stayed Bridge.
1400m Precast Segmental Approach Bridge on Worli
Side.
811m long link to Khan Abdul Ghaffar Khan Road
comprising 510m Precast Segmental Bridge and
310m Cast-in-Situ Bridge.

70

SAGMENT PARAMETERS

a hollow concrete box section with 3 cores

Length:1.5m to 3.1m.

post tensioned

slender and lightweight deck is to reduce the longitudinal


stiffness

pre-casting yard using short line method


A typical 50m span comprises of 15 numbers of precast
segments, a Pier segment and 200mm (nominal) in-situ wet
joints

8 cells to makes all the different types of segments.

centralized pre-casting yard using short line method of casting

Sophisticated software for correct casting curves

A complete construction of a segment takes about a month (20


to 30 days)
71

72

60

73

Segment Construction Procedure

survey team sets the bulkhead, the rebar setup


takes place
After rebar setup is done, the concrete is poured in the
formwork
initial tensioning about 30% of its maximum capacity
After strength of about 40Mpa final testing with rest of
the 70% load
Shifted to store at yard
Transported by trailer truck to site
Transported by barge in the sea
Erection by gantry
74

Connection of male-female segment with wet concrete

75

equipments which deployed in


the pre-casting yard

1)

Hydraulic Jacks of different capacities

2)

Turn Buckles

3)

Gantry, for lifting segments

4)

Tower Crain

5)

Concrete Pumps

6)

Cutting and bending machines for rebar

of

segments.
76

77

Formwork and rebar setup

78

79

A segment being cast and its


conjugate

80

65

Casting Yard

81

82

83

Erection of segment

The precast concrete sections of the deck were launched incrementally


between the pillars using a truss system, known as the balanced cantilever
method
The two segments are being linked through a male-female joint, in the
meanwhile the casted segment is allowed to gain strength and also its curing is
done side by side.
The precast sections were then epoxied together and given a certain degree of prestress to hold them in place
Once each span had completed and geometrical adjustments made the primary
continuous tendons were stressed to the required level.

84

Equipments which deployed in the


erection

Launching Truss: Weighing 1250 tonnes and measuring 112 m in length, it was used for lifting segments
each weighing 130 tonnes. This has been fabricated in India.
Flat barge: Size 30x12x2m. Like motor boats, they are driven inside the sea for material transportation.

Self-propelled barge: It is a barge with a machine component and is


used for concrete transportation.

Crawler crane: Capacity ranges from 75-150 tons. It is used for material and heavy lifting activities.
13 barges for concrete
eight steel boats
three tug boats
six smaller passenger boats.

85

The Erection Gantry

86

71

87

Erection of segment

88

72

89

90

Challenge of Ground Stabilisation for Pre-Cast Yard


located on reclaimed land
yard caters to casting, storing and handling of precast Segments
numbers of segments 2342
The storage capacity of yard 470nos.
Area is limited, the segments stored in three layers.
The bearing capacity of the ground was was very
poor to less than2 T/Sqm.

91

Solution
Excavation of the ground to a depth of ~
2.5Mtrs.
Strengthening the ground using rubble soling
and filling the voids with sand.
The soling thus done was compacted layer by
layer using vibratory rollers.
Total area of the Pre-cast Yard was covered with
a layer of PCC.
RCC Footing done to facilitate storing of
segments.
92

Challenges for project manager

The superstructure of the approach bridges was the heaviest spans in the country
to be built with span-by-span method using overhead gantry through a series of
vertical and horizontal curves.
Erection of 20000 MT Bandra cable-stayed deck supported on stay cables within a
very close tolerance of deviations in plan and elevation.

Navigation and transporting 19 precast segments in 24


hours at different open sea locations was a challenge.
How to move the large truss from the Bandra end of the bridge to the Worli end
without having to dismantle the truss which would be too time consuming on
such a high profile structure with a strict timescale.

93

You might also like