You are on page 1of 45

Residentia

The user of this template must enter all prices in the Rate column & Workings in the Units Col

Builder
Job Address
Date

Cost Centers
Description
1 Prelim's

Building Permit
Warranty Insurance 250K
Indemnity Insurance
Site Labourer
Cross Over permit
Drafting & Design
Engineering Fees
Contribution fee's
Water Tapping - Dry
Water Tapping - Wet - Short Side
Water Tapping - Wet - Long side inc U/Road bore
Enter extra items here

2 Hire Items

Tarp Hire
Scaffold Hire
Guard Rail Hire
Site Shed Hire
Temp Fence Hire inc errection & dismantle
Temp Power Pole inc errection
Temp Power Pole per week
Crane Hire
Enter extra items here

3 Temp. Services

Chemical Toilet Hire


Pumpout and Clean Site W/C
Power Usage
Water Cartage inc 1000tlr tank hire

Enter extra items here

4 Surveyors

Site set out


Site survey inc heights
Enter extra items here

5 Site Preperation

Earthworks - Bulk cuts


Demolition of existing
Tree Removal
Septic Tank removal
Piling as per quotation
Enter extra items here

6 Retaining Walls

Sleeper Retaining Wall


Sleeper Retaining Wall
Sleeper Retaining Wall
Sleeper Retaining Wall
Enter extra items here

7 Concretor

Stripfooting's inc labour & materials


Bulk fill Concrete 15MPa
Pads inc labour & materials
Dingo for stumps holes & post holes
Slab on ground (A-M) inc steel & labour
Slab on ground (H) inc steel & labour
Suspended 125 THK Slab inc Labour & mat
Suspended 180 THK Slab inc Labour & mat
Concrete pump - Minipump
Concrete pump - Boom or Line pump
Cross Over to council reg's
Enter extra items here

8 Termite Protection

Perimeter Spray
Pre Slab Spray
Penetrations - Red Stop
Perimeter Barrier - Termimesh
Enter extra items here

to
to
to
to

500 high
700 high
1100 high
1700 high

9 Bricklayer

Face Brick Allowance


Clay Commons
Masonary Bricks
Labour to lay face Brickwork - Ground Floor
Labour to lay face Brickwork - First Floor
Labour to lay Sill Bricks
Brick Chimney
Labour to lay Brick piers
Brick Up gable End
Squint Corners
Labour to fit Sislation
Brick Sand
Brighton Lite cement
Portland grey Cement
Limil
Brick hardware
Acidwash face brickwork
Bag brickwork - Single Coat
Bag brickwork - Double Coat
100 x 100 x 6 UA Lintel - Gal
150 x 100 x 6 UA Lintel - Gal
200x200 "T" Bar - Gal
Pressed Metal Door Frame
Enter extra items here

10 Blocklayer

390x190x90 Masonary Blocks


390x190x140 Masonary Blocks
390x190x190 Masonary Blocks
390x190x290 Masonary blocks
Labour to lay 390x190x90 Blocks
Labour to lay 390x190x140 Blocks
Labour to lay 390x190x190 Blocks
Labour to lay 390x190x290 Blocks
20MPa Corefill Mini-Mix Concrete
Labour to Core Fill Concrete
N12 Reio bars
N16 Reio bars
Mini-Line pump for core filling Blocks walls
Enter extra items here

11 Frame Carpenter

Carpentry labour - Frame


Frame hardware
Concrete Stumps

90x45 MGP10 studs to grd flr walls


Panel flooring
Liquid Nails
90 x 45 F17 Joists
Grd floor framing
150x45 Hyspan
300x45 Hyspan
300x63 Hyspan
240x45 Hyspan
90x45 Hyspan
190x45 F17
120x45 F17
90x45 F17
90x90 Cypress
125x125 Cypress
150x50 Cypress
100x50 Cypress
Panel Flooring
Liquid Nails
Ply Brace 2700x900
90x45 MGP10 plates
Mini Brace 4.2 long
Posi-Struts
First Floor Framing
120x45 MGP10
190x45 MGP10
130x36 Hyspan
90x45 Mgp10 Studs
90x45 MGP10 plates
90x35 Mgp10 noggins
Roof trusses
Roof Battens - 90 x 35
Roof Battens - 90 x 45
OBHW - 75 x 25
OBHW - 150 x 25
190x32 T/Pine Fascia
Merch Pine
Enter extra items here

12 Structural Steel

Structural Steel P/Tonne refer to breakdown


Crane Hire for steel errection
Labour to fit Steel
Enter extra items here

13 Roof Plumber

Corragated Zinc Roofing inc flash, Cap, D/Pipes etc


Corragated C/Bond Roofing inc flash, Cap, D/Pipes etc
Metal Fascia & Gutter
Supply & fit Guard Rail
Box Gutters
Metal Gutter - C/Bond
Downpipes single story no eaves
Downpipes Double story no eaves
Downpipes single story with eaves
Downpipes Double story with eaves
Supply & Fit 75mm Blanket Insulation
Enter extra items here

14 Roof Tiler

T/Cotta new or S/hand supply & lay


Cement Roof tiles
Guard rail Supply & fit
Sarking Supply & fit
Enter extra items here

15 Windows

400 Series Commercial Alum


Domestic Alum
Timber Windows sspecials leadlite
Timber Windows Specials
Enter extra items here

16 Skylights

Solar dome supply & fit


Fixed Skylite supply & fit
Openable skylite supply & fit
Electric Skylite supply & fit
Enter extra items here

17 Electrician

Disconnect & rewire as required


Provide underground power to meterbox
Connection Fee's
Meterbox Supply & fit
Provide Telstra Pit
Provide light point
Labour allowance to fit light point
Provide data point

Provide phone Point


Supply & fit Door Chime
Provide 2 way point
Provide Dimmer switch
Provide appliance points. R/Hood etc
Provide Oven circuit, Spa etc inc fitoff
External Gpo's
Internal Double Gpo's
Smoke Detectors
External appliance Gpo's
Exhaust fans inc ducting to external atmosphere
Swtch board supply & fit
PC Allowance for light fitting's
Intercom Supply & fit
Security Sytem supply & fit
Enter extra items here

18 Plumber

Provide Hot & Cold Point inc Drain


Provide Floor Drain
Gas Allowance
Stacks
Sewer Suspended
Stormwater supply & fit
Septic Tank Allowance
Stormwater pit Allowance
Garden tap supply & fit
Fit Spa bath
Fit off D/Washer, W/c etc
Enter extra items here

19 Lockup Carpenter

Lock Up Carpentry labour


Lock Up hardware
90 x 35 Merch pine
4.5mm hardieflex
140x20 Dar Pine Bird Brds
Gable Infils no details provided
Cavity Slider - 2040x720
Double Cavity Slider
Weather Brds - Timber
Weather Brds - primeline - 170mm
Tile Underlay 1800x900
Masonite packers
60x32 Crn Mouldings to w/brds

30x32 Crn Mouldings to w/brds


150x25 T/Pine Plinth
190x35 F17 Bearers
Sislation Tyvek 2700x30mtr Roll
Decking Brds - Merbau 90 x 19
90 x 45 F17 joists
Enter extra items here

20 Mechanical Services

Supply & fit Jetmaster


Supply & Fit Combustion Heater
8 Point Ducted Heating
12 Point Ducted Heating
Supply & Fit Split System
Enter extra items here

21 Insulation

Supply & fit R1.5 Wall batts


Supply & Fit R2.5 Ceiling batts
Supply & fit Acoustic Batts
Enter extra items here

22 Stairs

Timber Staircase Inc Standard balustrade


Steel & Timber Staircase no Balustrade
Enter extra items here

23 Plasterer

Supply & fit plasterboard to walls


Supply & fit plasterboard to ceiling's
Wet Area Walls
Supply & fit 90mm scotia cornice
Patch & Reapir exisitng as required
P50 stopping Bead
Enter extra items here

24 Renderer

Sup & fit 50mm Poly & coloured render


Sup & fit 75mm Poly & coloured render
Sup & fit 100mm Poly & coloured render
Render inc colour coat
Render for paint finsh by others
Membrane finish
Enter extra items here

25 Waterproofing

Caulking Internal Joins


Caulking external Joins / Joints
Waterproofing membrane
Waterproof Shower / bath
Enter extra items here

26 Tiler

PC Allowance for Floor Tiles


PC Allowance for Wall Tiles
Labour to lay Wall Tiles
Labour to lay Floor Tiles
Cement screed to falls
Construct showerbase inc Falls
Enter extra items here

27 Fixing Carpentry

Fixing Carpentry Labour


Fixing Hardware
Prehung 2040 single MDF Door Jamb
Prehung 2040 double MDF Door Jamb
Redicoat 2040 Door
Solidcore 2040 Door
Redicoat 2340 Door
Solidcore 2340 Door
Passage Sets
Privacy Sets
Robe Handles
Door Stops
Flush Pulls
67x18 MDF Architraves
87 x 18 MDF Skirting
110 x 18 MDF
Curved Architraves
Enter extra items here

28 Balustrade

External Balustrade
Internal Balustrade
Enter extra items here

29 Joinery

Supply & fit Robes inc sliding vynil doors

Supply & fit Joinery Carcasses


Linen Fitouts
Stone Benchtops
Enter extra items here

30 Painter

Painter - internal 3 coats inc 2 features


Painter - External Cladding
Enter extra items here

31 Floor Covering's

Supply & lay Carpets inc Underlay inc stairs


Supply & lay Floating Floor
Sand & polish Floor boards
Sand & polish Concrete Slab
Enter extra items here

32 Garage Door

Supply & fit Ply Tilt-a-Door


Supply & fit sectional Garage Door
Supply & fit Ceder Garage Door
Enter extra items here

33 Glazing

Fully Framed Shower Screen


Semi-Framed Shower Screen
Frameless Shower Screen
Colourback Splashback
6mm Mirror Supply & Fit
Enter extra items here

34 Int. Cleaner

Internal Clean inc Windows


Enter extra items here

35 Site Cleaner

Site Clean inc Bobcat & Bins


Enter extra items here

36 Paving

100mm thick Paving Slab - Plain


100mm thick Paving Slab - Coloured
125mm thick Paving Slab - Coloured
Labour to lay pavers

PC Allowance for Pavers


Enter extra items here

37 Fixtures & Fitting's

Taps sets
Basins
Toilet Suites
Pressed metal Baths
Shower Base 900x900
Shower Base 1350x900
Toilet Roll Holders
Towel Rails
Towel Rings
Soap Dishes / Toothbrush Holders
Kitchen Sink
Cistern Stops
L/dry Sink
Enter extra items here

38 Appliances

Cooktop Allowance
Wall Oven Allowance
Rangehood Allowance
Dishwasher Allowance
Insinkerator Allowance
Enter extra items here

39 Window Furnishing's

Blinds, Curtains & Drapes Supply & Fit


Enter extra items here

40 Clothes Lines / Mailbox

Hills Paraline Clothes Hoist


Brass Letterbox & Numerals
Enter extra items here

41 Fencing

1800high Paling Fence


gate
Enter extra items here

42 Landscaping

PC Allowance for soft landscaping


Enter extra items here

Subtotal
Contingency Sum
Supervision Fee's
Builders margins & Overheads
GST

Total of Building Works


Sales Fee's inc Advertising
Finance Fe's

This Template has been provided by Organized Builders with th


indicative range of costs that should be considered within a Bu
specialized items, other consulting, Government or External co
purchasing, signing contracts, ordering materials or any other
advice. Organized Builders recommends that the client is fully
no responsibility for financial loss that may occur due to incorr

Residential House Building Template

kings in the Units Column. The user must seek professional advice on all costs

Description

Supplier

Including 4 x inspections

Based on ?hrs per week


Non-refundable amount

PC Allowances

PC Allowance

D/Pipes etc

PC Allowance
PC Allowance
PC Allowance

PS Allowance

PS
PS
PS
PS
PS

Allowance
Allowance
Allowance
Allowance
Allowance

PC Allowance
PC Allowance

PC
PC
PC
PC
PC

Allowance
Allowance
Allowance
Allowance
Allowance

PS Allowance
PS Allowance

PS Allowance

PS Allowance
PS Allowance
PS Allowance

PS
PS
PS
PS

Allowance
Allowance
Allowance
Allowance

PC Allowance

PC
PC
PC
PC
PC
PC
PC
PC
PC
PC
PC
PC
PC

Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance
Allowance

PC
PC
PC
PC
PC

Allowance
Allowance
Allowance
Allowance
Allowance

PC Allowance

nized Builders with the clear understanding that this document is to provide an
onsidered within a Building Estimate. This template does not take into account
nment or External costs. The user should check the relevance of this template prior to
aterials or any other cost related excerise until they have recieved qualified written
hat the client is fully aware of all costs prior to committing to any purchase & accepts
y occur due to incorrect pricing, quantities or unforeseen reasons bearing financial interests.

Units

Total Quantity

Rate

Per
Each
Each
%
Week
Each
%
Each
Each
Each
Each
Each
?? Unit

Week
M2
L/M
Week
L/M
Each
Week
Hr
?? Unit

Week
Each
Month
Week

?? Unit

Each
Each
?? Unit

Each
Each
Each
Each
Each
?? Unit

L/M
L/M
L/M
L/M
?? Unit

M3
M3
M3
M2
M2
M2
M2
M2
Each
Each
Each
?? Unit

L/M
M2
Each
L/M
?? Unit

1000
1000
1000
1000
1000
L/M
Each
Each
L/M
Each
Each
M3
Each
Each
Each
Each
M2
M2
M2
L/M
L/M
L/M
Each
?? Unit

1000
1000
1000
1000
1000
1000
1000
1000
M3
Hr
L/M
L/M
Each
?? Unit

Hrs
Each
L/M

Each
Each
Each
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
Each
Each
Each
L/M
Each
L/M
L/M
L/M
L/M
L/M
L/M
L/M
L/M
M2
L/M
L/M
L/M
L/M
L/M
L/M
?? Unit

P/T
Hr
Hr
?? Unit

M2
M2
L/M
L/M
L/M
L/M
Each
Each
Each
Each
Roll
?? Unit

M2
M2
L/M
M2
?? Unit

M2
M2
M2
M2
?? Unit

Each
Each
Each
Each
?? Unit

Each
Each
Each
Each
Each
Each
Each
Each

Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
?? Unit

Each
Each
Each
L/M
L/M
L/M
Each
Each
Each
Each
Each
?? Unit

Each
Each
L/M
M2
L/M
Each
Each
Each
L/M
L/M
Each
Each
L/M

L/M
L/M
L/M
Each
L/M
L/M
?? Unit

Each
Each
Each
Each
Each
?? Unit

M2
M2
M2
?? Unit

Each
Each
?? Unit

M2
M2
L/M
L/M
L/M
L/M
?? Unit

M2
M2
M2
M2
M2
M2
?? Unit

L/M
L/M
M2
Each
?? Unit

M2
M2
M2
M2
M2
Each
?? Unit

Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
L/M
L/M
L/M
Each
?? Unit

L/M
L/M
?? Unit

Each

Each
Each
M2
?? Unit

M2
M2
?? Unit

M2
M2
M2
M2
?? Unit

Each
Each
Each
?? Unit

Each
Each
Each
M2
M2
?? Unit

Each
?? Unit

Each
?? Unit

M2
M2
M2
M2

M2
?? Unit

Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
Each
?? Unit

Each
Each
Each
Each
Each
?? Unit

Each
?? Unit

Each
Each
?? Unit

L/M
L/M
?? Unit

PC Allowance

Each
?? Unit

provide an

template prior to
alified written
chase & accepts
aring financial interests.

0.01
0.03
0.18
0.1

Item Totals

Cost Center Totals

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

$0.00

Compatibility Report for Prelimanary Costing.xls


Run on 20/03/2009 10:37
The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when you save this workbook in
an earlier file format.
Minor loss of fidelity
Some cells or styles in this workbook contain formatting that is not supported by
the selected file format. These formats will be converted to the closest format
available.

# of occurrences
3

You might also like