Professional Documents
Culture Documents
Suspension Cranes _
Operating and Maintenance Instructions
Fundamental information
You have purchased a product manufactured by STAHL CraneSystems GmbH.
This crane has been constructed in compliance with the applicable standards and
regulations.
Inspect crane for damage caused in transit immediately upon delivery.
Report damage caused in transit and after consulting the manufacturer/supplier
repair or have repaired before installation and commissioning.
Do not install or commission a damaged crane!
Assembly
installation
commissioning
tests
maintenance and elimination of faults
Seminars:
Comprehensive understanding of material handling products is a prerequisite for the
correct use of equipment. Competent and practically oriented, we impart the specialist knowledge required for the correct use, monitoring and care of your installation.
Ask for our seminar programme you will find information on the inside back cover
of these Operating Instructions.
2
01.08
BA_KRAN_02.FM
Contents
Safety instructions
General layout
3.1
3.2
3.3
3.4
Assembling crane
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.10
4.12
Note .............................................................................................................................. 12
Endcarriages ............................................................................................................... 12
Endcarriages for overhead travelling crane.......................................................... 12
Endcarriages for suspension crane ........................................................................ 13
Adjusting to crane runway........................................................................................ 14
Tightening torques...................................................................................................... 14
Power supply along crane runway.......................................................................... 15
Electrical installation ................................................................................................. 15
Travel limit switches................................................................................................... 16
FSE 508 radio receiver ............................................................................................... 17
FSE 514 radio receiver ............................................................................................... 18
Buffer stop ................................................................................................................... 19
Installing crane
5.1
5.2
5.3
5.4
Notes ............................................................................................................................ 20
Overhead travelling crane ........................................................................................ 20
Suspension crane....................................................................................................... 20
Functional test............................................................................................................. 21
Commissioning crane
6.1
6.2
Commissioning ............................................................................................................ 22
Inspection and testing ............................................................................................... 22
Operating crane
7.1
7.2
7.3
7.4
7.5
7.6
8.1
8.2
8.3
....................................................................................................................................... 35
Inspection and maintenance table.......................................................................... 36
Travel motor brake...................................................................................................... 36
Wheels ......................................................................................................................... 36
Fault-finding
9.1
10
Technical data
10.1
11
12
General information
BA_KRAN_02.FM
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
Symbols.......................................................................................................................... 4
Operating instructions ................................................................................................. 4
Use for intended purpose............................................................................................ 5
Safety-conscious operation ....................................................................................... 5
Organisational safety precautions ............................................................................ 5
General regulations...................................................................................................... 6
General information ..................................................................................................... 6
Installation, commissioning, maintenance and repairs ......................................... 6
Warranty ........................................................................................................................ 7
Periodic tests ................................................................................................................ 7
After sales service ....................................................................................................... 7
........................................................................................................................................ 8
....................................................................................................................................... 39
12.1
Subject to alterations
06.07
1.1
Safety instructions
Symbols
Safety at work
This symbol marks all information on safety at work where risks to life and limb are
entailed.
Safety in operation
Information marked with this symbol must be observed to avoid damage to the crane
or the goods transported.
In these operating instructions, these symbols mark particularly important information on risks and safety in operation.
Operating instructions
BA_KRAN_02.FM
1.2
11.06
1.3
Safety instructions
1.4
Safety-conscious operation
Our cranes are constructed according to the state of the art and equipped with an
overload device or slipping clutch to prevent overloads. In spite of this, we recommend:
Read the operating instructions before starting to work with the crane.
The user (see page 2) is responsible for working being carried out in a safetyconscious manner avoiding risks.
Before starting work, find out where the EMERGENCY STOP facility is (usually in
the control pendant).
Do not remove information plates from the crane. Replace illegible or damaged
plates.
Observe the instructions given above under "Use for intended purpose".
Observe the "Duties of crane operator ", page 22.
Report any damage and defects to the crane to the person responsible
immediately.
Have crane inspected by the relevant authority before commissioning.
BA_KRAN_02.FM
1.5
11.06
Only direct persons to operate the crane if they have been trained or instructed in
its use. Observe the legal minimum age!
Ask for our seminar programme you will find information on the last page of
these Operating Instructions.
At regular intervals, check that work is being caried out in a safety-conscious
manner.
Observe the intervals specified for periodic tests. File the test reports in the test log
book.
Store the operating instructions within easy reach where the crane is operated.
5
Safety instructions
1.6
General regulations
1.7
General information
In standard version, the crane components are shot-blasted and treated with an
alcyd resin based primer, colour oxide yellow.
As an alternative, single-coat paint or top coats in various dry film thicknesses are
possible.
Individual operating instructions apply for inspection and maintenance work on the
hoist. See crane documentation.
1.8
Installation,commissioning,
maintenance and repairs
Erection
Installation, commissioning, maintenance and repairs may be carried out by
qualified persons only, see page 2.
We recommend having erection carried out by fitters engaged by the manufacturer.
During erection of the crane, the operator must ensure that unauthorised persons
have no admittance.
Erection over 2 m above the ground may only be carried out from work platforms.
Persons working outside work platforms must be secured with a height safety
device.
Electrical protection measures must be observed. See regulations and circuit diagrams.
Commissioning
The crane may only be commissioned after its serviceability has been ensured.
Maintenance
Maintenance work may only be carried out when the crane is in a no-load condition and has been secured.
The main isolator must be switched off and secured against being switched on in
error or by unauthorised persons.
The accident prevention regulations must be observed.
Repairs
Use only original spare parts for repairs, otherwise the warranty will expire.
Do not carry out any alterations or modifications.
Additional fitments must be approved by the manufacturer.
Electrical connection and the test of electrical functions may only be performed by
a skilled electrician.
BA_KRAN_02.FM
If the crane is always operated outdoors, we recommend protecting the hoist, travel
motors and crane controls with a small roof.
11.06
1.9
Safety instructions
Warranty
The warranty will become invalid if these operating instructions are not observed
for installation, operation, inspection and maintenance.
Repairs and elimination of faults within the scope of the warranty may only be performed by qualified personnel (see page 2) after the manufacturer/supplier has
been consulted and has given his approval.
The warranty will become invalid if the hoist is modified or original spare parts not
used
Hoists and cranes must be inspected by a qualified person, see page 2, at least once
a year, possibly more frequently if so required by national regulations. The results of
the test must be recorded and filed in the test log book.
The periodic tests must be adapted to the use of the crane components. Intensive
use entails shorter maintenance intervals.
All tests must be initiated by the user (see page 2).
With the purchase of this crane, you have decided on high-quality material handling
equipment. Our after sales service will give you advice on its correct use. You will
find information on our after sales service on the back cover.
In order to maintain the safety and constant availability of your crane, we
recommend concluding a maintenance agreement on the basis of which we will
undertake the "periodic tests" on your behalf.
BA_KRAN_02.FM
Repairs will be carried out professionally and quickly by our trained personnel.
06.07
2 General layout
ZL
EH
6
7
8
9
8
BA_KRAN_02.FM
2
3
4
5
11.06
2 General layout
ZL
EH
1
2
3
4
5
BA_KRAN_02.FM
6
7
8
9
11.06
3.1
Safety clearances
Ensure that the safety clearances are observed in the vicinity of the crane (see asbuilt drawing).
3.3
S 15 m: S = 5 mm
S 20 m: S = 6 mm
S 25 m: S = 8 mm
S 30 m: S = 9 mm
S 32,5 m: S = 9,5 mm
BA_KRAN_02.FM
3.2
S = 3 mm
10
06.07
3.3
B = 10 mm
b = 1 mm
C = 10 mm
c = 1 mm
max F = 20 mm
Item
2
3
3.4
D
[mm]
125
160
200
315
400
500
80
100
125
160
A k+
40; 50
40; 50
40; 50; 60
40; 50; 60
50; 60; 70
50; 60; 70; 100
74 - 300
98 - 300
119 - 300
119 - 300
10
12
14
14
15
3
2-6
Festoon cables or safety conductor lines may be used for the main power supply
along the crane runway.
BA_KRAN_02.FM
According to the safety regulations, main power supply systems must be arranged
or protected in such a way that they cannot be touched by the load-bearing parts
even if the load swings.
The power supply must be able to be switched off on all poles by a main isolator.
The main isolator must be lockable to prevent unauthorised use.
In the case of main power supplies where protection is ensured by clearance, the
main isolator must be easily accessible in the area of the crane.
Identify the main isolator as the particular isolator for the crane.
11.06
11
Assembling crane
4.1
Note
It is advisable to assemble and complete the crane on the ground before raising it up.
Arrange the crane so that the side for electrical connection is on the side of the main
power supply.
4.2
Endcarriages
Free the connecting surfaces of crane bridge girder and endcarriages from rust,
dust, paint, oil and other impurities.
Danger! Soiling of the contact surface between endcarriage and connection plate
can lead to unintentional loosening of the bolt connection and thus to a fatal accident.
Tighten bolts with a torque spanner to the values given, see table, page 14. Use
only original bolt connection parts.
If the crane is operated outdoors, seal the gap between connection plate and endcarriage with sealant (1), see sketches.
W0917
F0433a
F0433
BA_KRAN_02.FM
4.3
k
A
12
11.06
Assembling crane
4.3
2
6
8
4
2
4
6
F0435
4.4
F0436
Lay endcarriage onto crane bridge girder and assemble bolt connection, see Fig.
Align endcarriage connection and span at right-angles and parallel, and check.
Screw down bolt connection as described in 4.6 (table, page 14).
The tightening torque must be applied by the nut.
See operating instructions "Crane components" for detailed instructions.
KEH-080
KEH-100
KEH-125
KEH-160
If the crane cannot be inserted via a freely accessible end of the crane runway, the
track gauge of the endcarriage must first of all be opened far enough for the flange
width of the crane runway to pass between the clear width of the wheels.
On each crane side, remove the inside split pins (4) and loosen the castellated nut
(2) as required. Secure drive unit with mounting tool, see sketch.
BA_KRAN_02.FM
Mounting tool
8x order no. 23 722 05 92 0
11.06
13
Assembling crane
4.5
Adjusting flange width and correcting span of cranes type EH-.. and ZH-..
The endcarriages are set by the factory to the flange width given in the order. The
flange width can be corrected by shifting the washers (2).
The eccentricity arising must not exceed max. 3 mm, the total stack thickness of
one side cheek must not be altered.
The front and rear travel unit of an endcarriage must be set identically.
KEH-A
80
100
125
160
D
80
100
125
160
f
1,5/3
3
S
1,5/3/
4,5/6
3/6
W0918
Increasing play
by shifting washers (2) from outside to inside.
Washers must be shifted at (A) and (I).
Increasing span +S
by shifting washers (2) on one or both endcarriages:
from inside to outside on the inside (I) of the crane runway, and from outside to inside
on the outside (A).
Reducing span -s
by shifting washers ) on one or both endcarriages:
from outside to inside on the inside (I) of the crane runway, and from inside to outside
on the outside (A).
Caution: After adjusting and after the crane has been set down on the crane runway
the endcarriage travel unit must be able to swivel approx. 5 to both sides!
See operating instructions for crane components for detailed information on adjusting flange width and correcting span.
4.6
Tightening torques
Item 5
*1 Use only hot-dip galvanised MoS2 coated original parts supplied by the
manufacturer.
BA_KRAN_02.FM
M12
M16
M20 *1
M24 *1
MA
[Nm]
130
330
450
800
14
11.06
Assembling crane
4.7
003.eps
4.8
Electrical installation
1
2
OE-S
BA_KRAN_02.FM
KE-S
Route the cables to the crane travel motors and any options through the cable conduits fitted or attach them with the cable clamps, see circuit diagrams.
While the crane is dismantled, route flat cables along crane bridge and into the
crane control panel and the hoist panel box through the cable glands. Connect to
the terminal strip. See circuit diagrams.
Fit towing arm to trolley/crab for the collector trolley in the cable trolley rail.
Plug control pendant into control pendant trolley with plug (1) and secure. Attach
strain relief wires to control pendant trolley. The control pendant must be suspended from the crane without being under strain. Clamp the control cable to the
strain relief wires underneath the plug with a spacer (2).
Connect crane travel motors and any options, see circuit diagrams.
Current collectors are mounted on the hoist trolley/crab.
06.07
15
Assembling crane
4.9
The travel limit switch assembly is supplied ready-wired but not mounted.
The switching contacts are designed for control current.
Switching functions:
1. Limit switching in both directions of travel (1 two-way switch, 2 ramps).
2. Pre-switching and limit switching in both directions of travel (1 two-way switch, 4
ramps).
The speed is switched over from "fast" to "slow" before the end of the runway is
reached, and is cut off at the end of the runway.
X = stop, left
Y = stop, right
Z = fast / slow
EH suspension crane
W0979
BA_KRAN_02.FM
W0980
16
06.07
Assembling crane
The radio receiver is mounted by means of the support (1) supplied and the mount (2)
attached to the back of the receiver.
The support is attached through the 4 holes.
The receiver is pushed into the support from above until the mount locks into it.
To remove the receiver, press down the release lever (3). This releases the lock and
the receiver can be pulled out in upwards direction.
The radio receiver is connected to the crane or machine electrics via the cable gland
(4).
BA_KRAN_02.FM
11.05
17
Assembling crane
Notes:
However to avoid damaging components, this should only be done by persons
accustomed to dealing with electronic components.
You should acquaint yourself with the control lamp panel (1) before switching on
the radio system.
BA_KRAN_02.FM
18
06.07
Assembling crane
Caution
The safety clearances specified by national regulations must be observed.
On double girder cranes, the buffer stop is bolted to the endcarriage in a specific
position, see Fig.
Tighten bolt connection (1) with 330 Nm as specified.
The tightening torque must be applied by the nut.
BA_KRAN_02.FM
W0922
11.06
19
5.1
Erecting crane
N.B.
Erecting crane
We recommend using a mobile crane to raise the crane.
(See crane drawing for deadweight of crane).
The crane must be raised by trained load attachers using suitable sling equipment.
Protect endangered sections with wooden blocks.
Balance crane and trolley/crab so that the crane is suspended horizontally when
lifted.
Secure trolley/crab against shifting sideways by wedging and lashing it.
Warning: If the trolley/crab shifts while the crane is being lifted or is suspended in
the air, the crane may fall and cause a fatal accident.
Raise the crane. Guide the crane with two ropes when lifting. Each rope must be
guided by one person.
Attach the guide ropes in such a way that the persons holding them are not
standing underneath the load, see Fig.
5.2
When raising the crane, position it diagonally and lift it over the crane runway.
Swivel crane and set down on crane runway.
5.3
Suspension crane
If the end of the crane runway is freely accessible, push crane onto crane runway.
If the end of the crane runway is not accessible, insert the crane from below with
the side cheeks of the travel units open, see page 12. Push side cheeks together
again and screw down with castellated nut (3).
Screw down castellated nut and then slacken by 2 holes for split pin (M30+M36)
or 4 holes (M48).
Fit split pin (4).
BA_KRAN_02.FM
Caution:
The travel unit of the endcarriage must be able to swivel approx. 5 to both sides!
Remove mounting tool, if used.
Mount towing arm for main power supply. The towing arm to the cable trolley or
collector trolley must be mounted with play.
Connect main power supply cable in crane control. See circuit diagrams.
20
11.06
Erecting crane
5.4
Functional test
A functional test must be performed after the crane has been erected and the main
power supply connected.
Please note:
The symbols on the control pendant must correspond to the motions of hoist, trolley/crab and crane.
If the motions are in the opposite direction, inter change 2 poles (L1 and L2) of the
main power supply.
On wire rope hoist, check functioning of limit switch in highest and lowest hook
position.
On chain hoist, check functioning of slipping clutch by running it to highest and
lowest hook position.
Check emergency stop (crane switch) on control pendant.
Run crane and trolley/crab into all end positions.
All buffer stops - on crane bridge and crane runway - must be completely
functional.
Check all equipment. See page 10 for additional equipment.
Check safety clearances. See general arrangement drawing .
5.5
Operating regulations for cranes Check that the operating regulations for cranes are visible on or near the main isolator, see Fig. This excerpt is supplied with every crane. It can also be ordered
separately: document No. 810 564 0.
BA_KRAN_02.FM
06.07
21
Commissioning
6.1
Commissioning
6.2
According to the EC machine directives, the crane may not be commissioned until its
serviceability has been ascertained.
This presupposes that:
the EC certificate of conformity is available.
. the CE symbol is attached to the crane.
the acceptance test has been performed.
The EC certificate of conformity and the CE symbol are valid when the acceptance
test has been performed.
By manufacturer
Every crane is subjected to a mechanical and electrical preliminary and in-process
inspection by the manufacturer's experts. Every crane is equipped with a test log
book.
By operator
Acceptance test by authorised person
Authorised persons are qualified persons authorised e.g. by the manufacturers' liability insurance association.
In order to lift the test load, the overload cut-off of a wire rope hoist must be deactivated: See operating instructions of hoist.
In the case of a chain hoist, the slipping clutch has been set to 1.25 times rated load
in the factory. When commissioning a crane with a chain hoist, the test load may only
be lifted to a maximum of 300 mm from the ground. See operating instructions for
chain hoist.
Periodic tests
Depending on operating conditions and local conditions, the crane must be
inspected by a qualified person, see page 2, as required, however at least once a
year.
BA_KRAN_02.FM
We recommend having these inspections carried out by our service technicians who
have been especially trained on the product. This is the best guarantee for safe operation, high availability and long life for your crane.
22
11.06
7.1
Operating crane
BA_KRAN_02.FM
At close of work, secure cranes which are exposed to wind with the wind safety
device.
11.06
23
7.2
Operating crane
Standard design
2-step
Emergency stop
Lifting/lowering:
1st step: slow
2nd step: fast
Cross travel: right/left
1st step: slow
2nd step: fast
Long travel: right/left
1st step: slow
2nd step: fast
Safety note
If the rocker switch is no longer depressed by the operator, it returns to the 0 position, the hoist motion is automatically stopped (dead mans control).
If the hoist malfunctions, e.g. the actual motion does not correspond to the motion
intended in activating the rocker switch, release the rocker switch immediately. If the
motion continues, press the emergency stop button.
7.3
Emergency stop
Every hoist must have a means of disconnecting the power supply to all drives under
load from the ground.
After an emergency stop, the operator must not restart the hoist /crane system until a
qualified person has determined that the fault which led to this function being activated has been eliminated and no danger can arise from the continued operation of the
system.
Note on standard crane with floor control:
The emergency stop button is on the control pendant.
Press emergency stop, the system comes to a halt.
To release the emergency stop: turn the button in the direction shown.
Note on standard crane with radio control:
Caution! The conductor line is still live when the emergency stop function has been
activated.
24
06.07
BA_KRAN_02.FM
In the case of radio remote control this function is provided by the main isolator. It
must be accessible fast and designed as a quick-break switch. If more than one disconnect point is required to ensure "fast accessibility", the main isolator itself is not
sufficient. In this case further disconnect facilities must be provided. The stop button
on the radio transmitter is a further means of stopping the crane in a dangerous
situation. The stop button is not marked or inscribed as an emergency stop facility
although as a rule it performs this function.
7.4
Operating crane
Caution:
Before starting work you should always press button I
to the 2nd step and trigger the acoustic signal. This indicates to your co-workers that they must be prepared
for the movement of machinery.
N.B.:
If the display (3) in the transmitter flashes red and an acoustic signal sounds you
must replace the battery; the transmitter will otherwise switch off after a few minutes. Recharge the empty battery in the relevant charger right away.
BA_KRAN_02.FM
Caution:
This automatic cut-out (APO function) in no way releases the operator from his obligation to switch off the transmitter when it is no longer required.
06.07
25
Operating crane
AUS
EU
UK
US
Only batteries type BA223030 and BA223000 may be charged with this device.
Only use the charger with the matching tray.
Do not use the charger in areas subject to explosion hazards.
Only use the charger in closed rooms.
Use the charger at room temperature and protect it from overheating, dust and
moisture.
Do not cover the charger during operation.
Disconnect the charger from the power supply when it is not being used.
Decommission the charger immediately if a fault appears.
Do not make any technical alterations to the charger.
Have repairs carried out only by a qualified person.
BA_KRAN_02.FM
26
06.07
Operating crane
(Example)
Operating
charging battery
charged
BA_KRAN_02.FM
06.07
27
7.5
Operating crane
button (4).
N.B.:
Before working with the transmitter you should always press the I
button to
the 2nd step and trigger the acoustic signal to warn your co-workers that they must
be prepared for movements of the crane or machine.
Radio connection to the receiver is established when the green LED "Si 1" lights up
(see pilot lamp panel on radio receiver), i.e. the radio system is ready for operation.
Commands can now be entered via the operating elements on the transmitter.
If the display (3) in the transmitter flashes red and an acoustic signal sounds this
means that the battery is nearly discharged. The empty battery should now be replaced by a charged one and the empty battery recharged (see chapter "Battery charger").
N.B.:
If the empty battery is not replaced by a charged one the transmitter will automatically switch off in a few minutes.
BA_KRAN_02.FM
N.B.:
This automatic cut-out in no way releases the operator from his obligation to switch
off the transmitter when it is not required.
28
06.07
Operating crane
AUS
EU
UK
US
Only batteries type BA223030 and BA223000 may be charged with this device.
Only use the charger with the matching tray.
Do not use the charger in areas subject to explosion hazards.
Only use the charger in closed rooms.
Use the charger at room temperature and protect it from overheating, dust and
moisture.
Do not cover the charger during operation.
Disconnect the charger from the power supply when it is not being used.
Decommission the charger immediately if a fault appears.
Do not make any technical alterations to the charger.
Have repairs carried out only by a qualified person.
BA_KRAN_02.FM
11.06
29
7.5
Operating crane
(Beispiel)
Operation
charging battery
charged
Entering numbers:
Move the cursor to the input field and press the iCON.
Turn the iCON until the desired number is set and press the iCON again.
An input aid helps to enter large numbers:
The tens digit changes after moving from the ones to the tens. If the iCON is not
turned for one second, the ones digit changes again. The hundreds digit changes
after moving from the tens to the hundreds. If the iCON is not turned for one second
the ones digit changes again.
To save the number, move the cursor to
BA_KRAN_02.FM
Caution! The transmitter must not be switched off during the save process, otherwise data are lost and the transmitter must be reconfigured!
30
06.07
7.6
Operating crane
7.6.1 Operation
1. Place a charged battery into the battery compartment (1) with the printing to the
outside. Make sure the battery is correctly poled.
2. Make sure the STOP switch (2) is released. If necessary turn the STOP switch to
release it.
3. Turn the key-operated switch (3) to position "1". The state indicator (4) flashes
green, the transmitter is ready for operation.
4. Press the button "(Crane) on (5).
N.B.s:
Before starting work you should always:
Press the "horn" button (6). This warns your co-workers that they must be prepared
for movements of the crane or machinery.
Check that the STOP button is functioning.
Printing on battery
(Example
BA_KRAN_02.FM
N.B.:
If the empty battery is not replaced by a charged one the transmitter will automatically switch off in a few minutes.
11.06
31
7.6
Operating crane
If the transmitter has been switched off with the STOP switch, the following steps
must be taken to continue transmitting:
1. Turn key-operated switch to position "0"
2. Turn STOP switch to release it
3. Turn key-operated switch to position "1".
4. Press button "(Crane) on".
N.B.:
Switch the transmitter off and on with the key-operated switch. Use the STOP switch
only in emergencies and for malfunctions in the work area.
BA_KRAN_02.FM
Battery FuB 10 AA fr
spectrum 3 und speotrum 2
FaB 10 AA option
32
11.06
Operating crane
BA_KRAN_02.FM
LED red
LED yellow
LED green
06.07
33
7.6
Operating crane
Operation
Battery faulty
Battery being charged
Battery is charged
BA_KRAN_02.FM
34
06.07
This section deals with operational reliability, availability, and maintaining the value
of your crane.
Although this crane is practically maintenance-free, the components subject to wear
must be inspected regularly. This is required by the accident prevention regulations.
The inspedctions must be performed by qualified persons (see page 2).
General information on inspection and maintenance
Maintenance and repair work may only be carried out when the crane is unloaded.
If repairs must be performed on live parts a second person must be present who
can in an emergency stop any dangerous movements with the emergency stop
switch or activate the main isolator/disconnect switch to cut the voltage.
Switch off and lock main isolator.
Observe the requirements of the accident prevention regulations.
A general overhaul must be carried out after the useful life of the hoist has expired.
The inspection intervals given in the table apply for use in mechanism group 1 Bm
or 1 Am and stress group B3. If the crane is operated in a higher mechanism group,
stress group and/or more than one shift, the maintenance intervals must be reduced.
BA_KRAN_02.FM
06.07
35
8.1
4
5
6
7
8
9
10
13
14
15
16
17
11
12
Brake *7
Periodic maintenance
every 12 months *2
2
3
Maintenance 12 months
after commissioning *1
Periodic inspections
every 12 months *3
First inspection
after 3 months *1
Daily inspection
on starting work *2
No.
Inspection on
commissioning*1
Power supplies
Cable glands
Cable trolleys
Connection terminals
Control pendant, control cable and strain relief
Hoist *4
8.3
Wheels
8.2
36
11.06
9.1
Fault-finding
BA_KRAN_02.FM
11.06
37
10 Technical data
The cranes are designed for use in industry and for the ambient conditions usual in
industry.
Special measures must be taken for particular applications such as e.g. high degree
of chemical pollution, outdoor use, offshore application, etc.
The manufacturer will be pleased to advise you.
BA_KRAN_02.FM
38
11.06
11.1 Wheels
For crane type EH- and ZH see operating instructions for crane components
11.2 Wheels
For crane type El- and ZL see operating instructions for crane components
For crane type KZL see operating instructions for crane components
quadrix
micron 6
(508)
micron 6
(516)
spectrum 1
(508)
spectrum 1
(516)
Transmission
frequency
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
Order No.
579 556 0
579 557 0
579 558 0
579 533 0
579 534 0
579 535 0
579 539 0
579 540 0
579 541 0
579 542 0
579 543 0
579 544 0
579 548 0
579 549 0
579 550 0
Order No.
(battery)
579 986 0
579 986 0
579 991 0
FSE 508
FSE 516
Receive frequency
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
433 MHz
869 MHz
900 MHz
Order No.
579 968 0
579 969 0
579 970 0
579 971 0
579 972 0
579 973 0
579 530 0
579 531 0
579 532 0
Sticker
blue / yellow
Long travel
red / green
Hoist +
cross travel
rred / green
Hoist +
cross travel
Designation
Order No.
BA_KRAN_02.FM
06.07
39
W0969
1
2
W0968
W0970
BA_KRAN_02.FM
40
06.07
41
BA_KRAN_02.FM
42
BA_KRAN_02.FM
12 General information
12.1 Seminars
We offer seminars covering all main product groups, such as seminars for crane
operators, wire rope hoist seminar, chain hoist seminar, seminar on load suspension
equipment and seminar for material conveying equipment.
However we would be please to offer a special programme orientated on your individual specifications and requirements.
The seminars are individual modules or can form part of a long-term training course;
they are held in German or English.
Each seminar is concluded with a certificate.
You can obtain information on our seminar programme from:
STAHL CraneSystems GmbH
Daimlerstrae 6 | D-74653 Knzelsau | Tel. +49 7940 128-0
marketing@stahlcranes.com
BA_KRAN_02.FM
Or visit www.stahlcranes.com
43
F-BA-8.1-EN-01.08-mp
Tochtergesellschaft
Subsidiary
Vertriebspartner
Sales partner
Tochtergesellschaft/Subsidiary
Austria
Steyregg
Tel +43 732 641111-0
Fax +43 732 641111-33
office@stahlcranes.at
Great Britain
Birmingham
Tel +44 121 7676400
Fax +44 121 7676485
info@stahlcranes.co.uk
Portugal
Lissabon
Tel +351 21 44471-60
Fax +351 21 44471-69
ferrometal@ferrometal.pt
Switzerland
Dniken
Tel +41 62 82513-80
Fax +41 62 82513-81
info@stahlcranes.ch
China
Shanghai
Tel +86 21 6257 2211
Fax +86 21 6254 1907
service_cn@stahlcranes.cn
India
Chennai
Tel +91 44 4352-3955
Fax +91 44 4352-3957
indiasales@stahlcranes.in
Singapore
Singapore
Tel +65 6271 2220
Fax +65 6377 1555
sales@stahlcranes.sg
France
Paris
Tel +33 1 39985060
Fax +33 1 34111818
info@stahlcranes.fr
Italy
S. Colombano
Tel +39 0185 358391
Fax +39 0185 358219
info@stahlcranes.it
Spain
Madrid
Tel +34 91 484-0865
Fax +34 91 490-5143
info@stahlcranes.es
USA
Charleston, SC
Tel +1 843 767-1951
Fax +1 843 767-4366
sales@stahlcranes.us
Vertriebspartner/Sales partner
Die Adressen von ber 100 Vertriebspartnern weltweit finden Sie im Internet auf www.stahlcranes.com unter Kontakt.
You will find the addresses of over 100 sales partners on the Internet at www.stahlcranes.com under Contact.