You are on page 1of 6

IES-COR-AA-AI-004

Project No:
Project Title:
PSSR ____ of ____

re-Startup Safety Review- Checklists


MOC No:
Date
Multiple:
PSSR Leader: If
Area Supervisor
Approval:

NOTE: This document must be attached to MOC.

General
1. Have all assigned MOC steps
prior to PSSR on MOC/ Project
been addressed?
2. Has construction and equipment
been checked to ensure that it is
consistent with the P&IDs and all
design specifications?
3. Was a Risk Review been
performed for new or significantly
modified facilities, using
appropriate methodology?
4. Has the Safety Case been
referenced versus the proposed
change to determine if the change
would inadvertently disable/d
defeat any existing safeguards?
5. Have all action items from the
Safety and Health Review, PHA
etc., been resolved?
6. Are utility systems isolated from
process systems? Are flanges or
blinds inserted, check valves
closed, circuit breakers open?
7. All mechanical tools/equipment
not required by the design or for
operations has been removed (i.e.
tarps, hoses, tools, welding
machines, etc.)
8. All combustible material
removed (i.e. scaffold boards,
tarps, plastic, trash, etc.)
9. QA/QC documentation reviewed
and complete.

Ye
s

No

N/A

Responsibilit
y*

Completed
(Sign/Initial)

Commen
ts

10. All protective shipping


brackets, plastic plugs, and
packing have been removed from
controllers, instruments, and other
equipment.
Ye
s
Procedures and Training
1. Are safety, operating
maintenance, and emergency
procedures in place and adequate?
2. Has training of each employee
involved in operating the process
been completed?
3. Have blind lists been updated?
4. Has the unit/equipment
lubrication list been updated to
reflect any changes/additions for
rotating equipment?
5. Training of personnel has been
completed
Controls
1. Have all instrument loops and
safety systems (shutdowns,
alarms, interlocks, etc.) been
checked and are they functioning
as designed?
2. Has all computer control logic
and software been thoroughly
tested?
3. If the equipment has a Safety
System, can the equipment be
bypassed or taken out of service
without a unit shutdown to
perform the Safety system
check?
4. Have all control valves been
stroked & verified?
Safety and Environment
1. Have mechanical safety
systems including relief valves,
ventilation, deluge, SCBA, and fire
protection systems been checked?
2. Are new or revised MSDSs in
place?
3. Have gas detection systems

No

N/A

Responsibilit
y*

Completed
(Sign/Initial)

Commen
ts

been checked?
4. Are environmental control
devices in good order ?
5. Have construction
wastes/materials been disposed in
an acceptable manner ?
6. Has there been a review of
hazardous energy isolation?
7. Firewater system installed per
design and commissioned?
8. Are there any inherent dangers
in the immediate vicinity of the
equipment isolation devices (hot
piping, sharp points, etc.)?

Ye
s
9. Are there adequate isolation
devices to complete hazardous
energy isolation of equipment?
10. Are there adequate safety
protection devices in place on the
equipment e.g.blow-out
preventors, ball cock valves?
11. Safety related painting
complete, (Cross walk railings,
curbs, guardrails, etc.)
12. Eye wash stations and safety
showers installed and tested.
13. Fire extinguishers located as
per layout drawings.
14. Required noise reduction
systems in place.
15 Hearing protection warnings
installed
Mechanical
1. Has rotating equipment been
checked for rotation, alignment,
and lubrication?
2. Pre-service required by vendors
has been performed.
3. Are all required guards in place?
4. Has internal inspection been
performed after installation?

No

N/A

Responsibilit
y*

Completed
(Sign/Initial)

Commen
ts

5. All required lock-wires are in


place.
Piping and Pressure Vessels
1. Have piping, tanks and vessels
been properly hydrotested or
tested per an alternate method?
2. Have all construction blinds
been pulled?
3. Are all drain and vent plugs in
place?
4. Correct bolting & gasketing
materials installed?
5. Have all materials of
construction been properly
identified according to
specifications? (PMI and MTR)
6. Have all valves and orifice
plates been installed in the correct
flow directio
7. Pipe supports installed so that
no piping strain exists?
8. Required NDE/PWHT performed?
Ye
s
9. Required hardness testing
performed?
10. Has internal check for
cleanliness prior to closing been
performed?
11. Have PSVs been installed?
12. Have gags been removed from
springloaded supports and
expansion joints?
13. All chemical treatment
complete (i.e pickling, chemical
cleaning, etc.)
Electrical
1. Is all equipment compatible with
the area electrical classification?
2. Have all motors, feeders,
transformers installed been
properly inspected?
3. Are electrical grounds intact?
4. Are all required guards in place?
5. Have all breakers been checked,
labeled and numbered?
6. Have all motors been tested &

No

N/A

Responsibilit
y*

Completed
(Sign/Initial)

Commen
ts

vibration checked.
7. Have all starters and control
stations been properly labeled?
8. Have all conduit seals been
poured?
9. Is conduit and cable tray
properly supported?
10. All connections sealed and
water tight?
Operational
1. Has all equipment such as
valves, louvers, dampers, etc.,
been operated?
2. Are all screens, orifices, filter
elements, etc., in place for
operation?
3. Is there sufficient devices (drain
bleeders, vent bleeders, etc.) to
properly prepare equipment for
maintenance?
4. Are all required valve car seals
and locks in place and logged
Ergonomics, Access and
Lighting
1. Is access to equipment and
valves adequate for operation,
maintenance, and emergencies?
2. Is there adequate overhead
lighting in the work area?
3. Is there adequate lighting on
the equipment (such as sight
glasses, etc.)?

Ye
s
4 Are the access/work platforms
adequate for normal operation
and/or shut down / start up of
equipment?
5. Is there adequate access to the
equipment isolation devices?
6. Are the equipment isolation
devices ergonomically acceptable?
7. Are the equipment isolation

No

N/A

Responsibilit
y*

Completed
(Sign/Initial
)

Commen
ts

devices positioned for access


during emergency situations?
8. Are the equipment isolation
devices fitted with any required
mechanical assistance devices
(such as control valves, motor
operated valves, etc.) to close
them during emergency
situations?
Final Confirmation
1. Is this change ready for safe
operation?
*Responsible person for action items checked whether yes or no in columns to
left.

Resolution of Action Items:


Action Item

Address
Prior to
Startup

Follow-up
Responsibilit
y

Date
Completed

Resolution/Comm
ents

Have all action items identified as NO been resolved? (Start-up cannot proceed
until all action items checked NO are resolved unless classified for after
commissioning) Yes / No.

See PSSR Summary sheet - Appendix 7(a) for signatures of all participants in
the PSSR.

You might also like