You are on page 1of 17

C32 Methods of Procurement of Construction

Questions
Discuss the need for a contract in civil engineering works. Comment on a form of contract you
have used and evaluate its strengths and weaknesses for the signatories.
What are the advantages and disadvantages of design and construct contracts by
comparison with other procurement methods? Discuss, giving examples from your own
experience.
Discuss how cost risks are identified and managed in the feasibility, design, tender and
construction stage of a project. How does consideration of cost risk affect the choice of
method procurement?
Compare the various forms of contract available to a civil engineer and discuss which you
would use under what circumstances. Explain how each of the forms relate to Egan
principles.
Discuss the factors that a civil engineer should take into account when advising a client as to
which method of procurement would be appropriate for a particular project.

1. Introduction
A Contract is an agreement between two or more parties. Contracts have a number of
functions. In the case of Civil Engineering Construction Projects the Contract sets out the
following details.

Specifies the work to be carried out by the Contractor (inc. quality, programme
constraints)
Defines the payment schedule (inc. when payments are to be made and
additional/reduced fees)
Defines which parties are responsible for events affecting the works that occur outside the
direct control of the parties (such events may include bad weather, unforeseen ground
conditions, local authority restrictions etc.)
Defines the responsibilities of each party (inc. making decisions, giving instructions,
administration duties, disputes, claims adjudication, arbitration etc.)

Contract law and relevant legislation also apply to such contracts.

Time, Cost, Quality Pick 2. Egan Report


The selection is linked to Risk Management

3 Methods of Procurement

Traditional

Design and Build

Management

All are forms of JCT

2.0

Traditional

Design work is separated from construction


Consultants carry out the design, cost control and site supervision
A Contractor is chosen to build the project, usually by competitive tendering
A complete set of drawings should be prepared before tendering which has a time implication.
Contractor has no design input other than Temporary Works
The client must be sufficiently experienced / knowledgeable to control costs of design and
quality.
Price basis is either Lump Sum or Measurement (Remeasurement)
Lump Sum The price is fixed and agreed upon before the Agreement is signed. A fixed sum
of money for a fixed amount of work.
Measurement The work is substantially design prior to signing the agreement but work on
site is measured and the contractor paid accordingly.
A variation of measurement is Cost Plus fee The amount of work is undetermined prior to
signing the agreement. The contractor is paid for the materials, labour and plant based on
rates plus a percentage / fixed fee.

2.1

JCT Traditional

large lump sum building works with price certainty.


There are 6 forms of this contract with quantities, without quantities or with approximate
quantities each available to the public and private sector.
The With Quantities version should only be used where the Employer through professional
consultants has provided at Tender a full set of Construction Drawings and Specifications
priced to SMM7 (Standard Method of Measurement 7 th edition) by the Quantity Surveyor.
The Without Quantities version also has a full set of Construction Drawings and Specifications
at Tender but the competing Contractors are required to provide a Cost Sum Analysis in order
to give the Employer a degree of cost certainty. The accuracy of this certainty is defined by
the Employer at Tender stage.
JCT 98 requires a Contract Administrator who is usually the Architect and as such the
Architects duties are defined within the Contract.
With regard to Time and Delay the Contractor is required to start and finish on or before dates
set out in the Contract.
Failure by the Principal Contractor to complete the Works within the defined period constitutes
grounds for the payment of Liquid Ascertained Damages to the Employer set at a rate
predetermined at the date of commencement of the contract. Notice is required from the
Employer in advance of this event.
The Architect will issue a Final Certificate to notify the Employer that Practical Completion has
been achieved and the Employer has a duty to make the Final Payment within an amount of
time defined within the Contract.
Under this form of Contract the Engineer is employed by the Architect as a Sub Consultant
and as such the responsibility for the Engineers decisions lies with the Architect.

3.0

Design and Build

The Contractor is responsible for design as well as construction.


The benefits to the Client are that time and cost is saved but at the expense of quality.
The risk of the project is given almost entirely to the Contractor. There is in theory one
organisation to blame if things go wrong.
The Client produces a performance specification called the Employers Requirements which
the Contractor must satisfy.
The Contractor will demonstrate how this will be achieved by producing his Contractors
Proposals.
This may include value engineering the Employers Requirements to satisfy the Clients
budget.
The Contractor will price the works from Scheme drawings and specifications.
This brings benefit to the Client in cost as an experienced contractor is the specialist in the
best way to achieve the finished article.
Once the contract is signed the Contractor has to build the works to the contract documents.
The interpretation may lead to a difference in quality to the expectations of the Client.
The Client produces the Employers Requirements by appointing consultants for services.
Once the contract is entered into the Consultants are novated to the Contractor.
Detailed design can run in parallel with construction and savings to time are given as
compared to the normal route.

3.1

JCT With Contractors Design (D&B)

The Employer will invite usually 3-5 Principal Contractors to go through a competitive
tendering process and select one winning bidder.
Upon completion of this process an agreement can be entered into between the Employer
and Principal Contractor and the contract is formed.
The Contract Documents specify what the Principal Contractor and Employer have entered
into. WCD 98 cl. 2.1 defines the Contract Documents as the ERs, CPs and Contract Sum
Analysis together with the articles of agreement, conditions and appendices.
The ERs and CPs are comprised of drawings and specifications and the Contract Sum
analysis is essentially a bill of quantities.
No architect is specified within the contract, Instructions are given by the Employer. The
architect is a member of the Principal Contractors team and therefore no reference is
required.

4.0

Management Contract

The Client appoints a Management Contractor on a fee basis.


The Client appoints consultants for design services.
The Management Contractor does not build anything but manages other contractors to carry
out the works.
Suitable for large, complex projects where several packages of work are to be completed.
The Management Contractor will be appointed at a stage early enough to contribute to the
work of the professional team for which a fee will be received.
The main contract between the Employer and the Management Contractor covers both the
pre-construction period and the period of actual construction work.
Design work can proceed at the same time as construction.
The work cannot be priced at the start and is usually based on an estimate putting the risk of
cost on the client.
The appointment of the management contractor is not based upon price but on experience,
relationship and trust.
As the project proceeds to the construction period the Management Contractor is responsible
for the appointment of Works Contractors to carry out the Works Packages.
The works contractors will normally be appointed on the basis of competitive tendering.
The Management Contractor starts with a Contract Cost Plan and programme dates and will
be responsible for the coordination, supervision and provision of site facilities.
The responsibility of monitoring the Cost plan is that of the Management Contractor despite
the appointment of an independent Quantity Surveyor to the professional team.
This form of Contract places most of the Risk upon the Employer as the design, specification
and contract administration are placed in the hands of an independent professional team.

Factors to consider
Many factors to be taken into account:

Cost & finance of project


Risk
Time
Flexibility
Client role

Cost

Client may have fixed budget and want maximum cost guarantee before tender
How will project be financed? Project sector works DBFO/BOOT?
Cash flow of client?
Future running costs an issue? Client will require control over design and specification

Lump sum tightest cost control for client, but contractor may price high as a result
Admeasurement client risks the costs of the unexpected
Target cost incentives are provided to both client and contractor to reduce costs (e.g. if
contractor overspends, he pays 60% of costs, if he underspends he receives 50% of savings)
Cost reimbursement client can control contractors profit with open book policy, but obliged
to pay contractor at cost for all work, hence highest risk for client

Quality
Generally, easier to negotiate contracts with emphasis on quality where risk is higher to the
client, i.e. cost reimbursable and target cost contracts. A management contracting approach is
possible with focus on quality
Lump sum and admeasurement contracts benefits of efficiencies gained by contractor tend
to stay with contractor hence risk of quality suffering as contractor looks for savings (needs
a good specification)

Time

Early start on site required?


Completion by a specific date eg school or university
Minimal construction period to avoid high interest costs on invested capital, or to get
returns as early as possible eg developer

Risk
Risks include:

Defining project
Investing in it
Obtaining necessary approvals
Specifying performance
Design risks
Ground conditions
Selecting of sub-contractors
Site productivity
Mistakes and accidents

Client will need to decide which risks he can bear and which he wants to allocate to
someone else
Generally the more risk borne by the contractor the higher the cost
Can risks be managed more effectively elsewhere?

One party may accept higher risk with prospect of higher returns.
Lump sum contracts least risk for client
Admeasurement contracts client risks the unexpected, but contractor generally picks up tab
for poor decisions
Target cost shared risks
Cost reimbursement contractor paid for all costs incurred, hence all risk with client
however, may be suitable for emergency works, or work where a rapid start is needed

Flexibility

Client may require flexibility to change brief, but should be aware that decisions made
late in the day cost more money!

Client role

What expertise does the client have in-house


How involved does he want to be?
Critical aspects require more involvement

New directions
Partnering development of target cost contracts (NEC), with long-term relationships and
supply chain management.
PFI contracts contractors service extends beyond construction to operation, maintenance
etc., over a given period of time an incentive not to compromise on quality?

Conclusions
The most important factor in choosing the form of contract to be used for a construction
project is the allocation of risks (between the client and contractor)
There are tradeoffs to be made between time, cost and quality
The best contracts are likely to offer shared incentives for both clients and contractors to meet
performance targets

7.2

NEC (ECC)

The New Engineering Contract (or Engineering and Construction Contract) is an attempt to
clarify and simplify building contracts and to be used in a variety of different scenarios, eg
Traditional, D&B, Management.
It is intended to provide a modern method for employers, designers, contractors and project
managers to work collaboratively.
The 2 principles on which the ECC is based and which impact upon the objective of
stimulating good management are

foresight applied collaboratively mitigates problems and shrinks risks


clear division of function and responsibility helps accountability and motivates people
to play their part.

A Project Manager is employed to act as the central figure of the contract. The Project
Managers duties are to manage the Procurement of the Works for the Employer, issue
Instructions, monitor progress and certify payments when due.
There are a number of Core Clauses, and Optional and Secondary Option Clauses that can
be introduced to tailor the Contract however desired.
Claims are called Compensation Events. A principle of the ECC is that the Project Manager
should be presented with options for dealing with problems from which he can choose.
The Contractor should be unaffected by the choice made and so the Project Manager will
select the option that will serve the best interests of the Employer. In some cases the lowest
cost, in others the least delay.

7.3

ICE 7th Edition

On this type of contract the Engineer is the central figure. It is not suitable for building work or
lump sum as it is designed to facilitate the unexpected nature of civil engineering works that
produce uncertainties through work in the ground.
It is in the Contactors duties to construct and complete the Works as inferred in the Contract
and to the satisfaction of the Engineer.
The Engineers duties are to carry out the design and produce specifications and inspect the
site prior to commencement of the Works. During the construction phase the Engineer is to
regularly inspect the Works to ensure that the Contractor is working to the correct mode,
manner and speed. Any Instructions required shall be issued by the Engineer and any resubmissions of the Programme by the Contractor shall require approval by the Engineer.
Any applications for Extensions of Time must be submitted by the Contractor to the Engineer
within 28 days of the event leading to the delay and must include particulars of the event. Any
award is reviewed after the completion of the Contract.
Where the Engineer believes that the progress of the Works is too slow the Engineer will give
notice of this in writing to the Contractor to be resolved at cost to him.
Upon completion the Engineer will issue a Certificate of Completion when the whole of the
Works have been substantially completed and any tests required by the contract have been
passed.

FIDIC

4.0

Sub Contractors

Domestic
A domestic sub-contractor is one appointed by the Principal Contractor, usually from a list of
preferred sub-contractors that have been used before.
Nominated
A nominated Sub-Contractor is one appointed by the Principal Contractor under Instruction of
the Architect. For example a drawing may read Windposts by Ancon. As such the Architect is
liable. If the drawing were to read Windposts by Ancon or other approved however, then this
puts the liability on the Contractor to appoint a competent sub-contractor.
Named
A named sub-contractor is one appointed by the Employer and as such under JCT 98 the risk
of the Sub Contractor performance is with the Employer.
Under WCD 98 all risk is transferred to the Principal Contractor and so in effect becomes
Nominated.

5.0

Claims

It is for the Contractor to prove a link between an event and a period of delay. It is not
sufficient for the Contractor to show a delay and point to an event, in effect saying that it must
have been that.
Under JCT 98 and WCD 98, clause 25.2 states that The Principal Contractor must submit a
notice in writing as soon as he thinks he is being delayed, or that he is likely to be delayed
and must do this whether the delay is his own fault or the fault of another party. The purpose
of this provision is to enable the Architect (under JCT 98) or Employer (under WCD 98) to
take whatever action is necessary at the earliest possible opportunity to mitigate the effect of
the delays. The Contractor is in breach of Contract if he fails to do so. Furthermore the notice
must include which of the relevant events listed in Clause 25.4 has given rise to the delay. As
soon as possible after this notification, the Contractor must submit in writing an estimate of
the length of time beyond the original date of completion the project will finish.
If the Principal Contractor has made any reference to any Sub Contractor within this
notification then they must receive a copy and any associated documents.
One of the reasons listed under Clause 25.4 is the Failure of the Architect to comply with the
Information Release Schedule or if not provided, to provide information at the right time.
Under JCT 98, if an IRS has been provided a failure of the architect is sufficient to trigger the
event.
Under WCD 98 there is no IRS as all the relevant information is to be provided by the
Principal Contractor. The Contractor is to receive decisions or information for which he has
specifically applied for in writing neither too early or too late by submitting and keeping up to
date a programme marked with the information required in effect, a design programme.

6.0

Dispute Resolution

6.1

Adjudication

The Housing Grants, Construction and Regeneration Act 1996 section 108 gives the right to
any party to a construction contract to submit disputes to an independent adjudicator.
The act provides that the contract must:

enable a party to give notice of adjudication at any time;


provide a timetable to secure an appointment and referral to the adjudicator within
seven days of the initial notice;
require the adjudicator to make a decision within 28 days of referral;
allow the adjudicator to extend the period as agreed by both parties for 14 days if just
the party who started the procedure agrees;
impose a duty on the adjudicator to act impartially;
enable the adjudicator to investigate the facts and relevant law without being
requested to do so.

As and when the referral to adjudication is made, both it and any accompanying documents
that are sent with it to the adjudicator must be simultaneously copied to the other party.
The adjudicator has immunity from liability with the exception of acting under bad faith where
it can be proved that he has done so.

6.2

Arbitration

Arbitration is governed by the Arbitration Act 1996 and the principles are as follows;

the object is to obtain the fair resolution of disputes by an impartial tribunal without
unnecessary delay or expense;
the parties should be free to agree how their disputes are resolved subject only to the
public interest;
the courts should not intervene except as provided for by the Act.

Arbitration is similar to adjudication in that two parties who are in dispute agree to allow a third
party to settle the matter between them and agree to abide by the decision.
Arbitration can involve solicitors, barristers and expert witnesses and is therefore more
cumbersome, time consuming and costly than adjudication. It is therefore more suited to
cases involving substantial sums of money.
It does allow for in smaller cases and where both parties agree, the use of documented
evidence only and the omission of legal advisors to provide a relatively quick solution.
Under JCT 98 and WCD 98 the dispute must be between the Employer and The Principal
Contractor. The consultants are not party to the contract and as such cannot be a party to the
arbitration process although they can be a witness.

Consultant Appointment
7.4

ACE Conditions of Engagement

The Association of Consulting Engineers Conditions of Engagement


- forms the contractual link between the Consulting Engineers and their client.
There are variants of the Terms and Conditions as listed below.
A the Contract is between the Employer and Consultant who acts as Lead Consultant
B the Contract is between the Employer and Consultant who acts as non lead consultant.
C the Contract is between the Contractor and Consultant, as would be the case under a
Design and Build contract.
Where the letter above is followed by a (1) this indicates that the Consultant is a Civil or
Structural Engineer (or both.)
Where the letter above is followed by a (2) this indicates that the Consultant is a Mechanical
or Electrical Engineer (or both.)
For example, a B (1) Appointment would be for a Civil or Structural Engineer working as a non
lead consultant.
The document for standard conditions of engagement consists of the following sections;

Introduction

Fee proposal stating project value, fee basis and amount, fee for each RIBA Stage,
programme, contract procurement.

Scope of service what services will be provided to the client by the consultant

Level of service the degree of service provided to the client.

Description of deliverables for each RIBA Stage

standard terms of agreement consist of;


the agreement,
consultant obligations,
client obligations,
payment,
insurance,
liability,
procedures for notices and disputes and
governing law.

7.5

Target Cost Contracts

Introduction
With cost reimbursement contracts there are no incentives for the contractor to minimise
costs. Application of Targets in three areas, time, cost and quality will affect the contractors
profit giving them the incentive to consider these areas carefully.

What are Target Cost Contracts?


Target cost contracts first have a target fee to cover overheads and profit, then have
target costs and a share proportion for any under/over actual costs know as the share
formula. The fee can be lump sum or actual costs.

The share formula can be distributed 50/50 to client/contractor or if it is known that there
will be a lot of changes and increase in cost 90/10.

There can be a guaranteed fixed price in case the actual costs go over too much. The
prices are lump sum prices for each activity.

There are other forms like Time targets which are used on many contracts as a liquidation
damages clause. Time targets can cause contention when the work has been subject to
variations. Used when time is of importance and the contractor is given a bonus for early
completion.

Can also be used with the Engineer/Client relationship therefore incurring savings in case
of over design.

Normal for target to be adjusted during the course of the contract to allow for variations,
delays and cost escalation.

When to use Target Cost Contracts


When additional flexibility is required
Scope of works is well defined but the risk is unquantifiable OR

Scope of works is undefined at time of tender and the tender costs must be developed as
the works proceeds

Reduction in or risk/claims is required

Client is concerned about the engineer over designing/contractor not considering costs

Advantages of Target Cost Contracts


Flexibility to change/variations
Fairer distribution of risk

Potential saving of time and cost of tendering

Reduces claims and the final account is generally settled quickly

Client can monitor the costs of the contract and have more involvement

Good involvement/relationship between designers/contractors/client if all under target


cost contract as all aiming at the same targets.

Disadvantages of Target Cost Contracts


Difficult to predict final cost of project
Need to set a realist target and keep the incentive for the contractor, therefore need a lot
of information at an early stage.

Concerns with the quality of the work to cut costs issue quality targets too.

Conclusions

Tenders are usually awarded on lowest estimate rather than most accurate. This causes
problems in budget and completing project on time Target costs are an accurate way of
minimising costs

You might also like