You are on page 1of 80

200 Soils, Foundations and Concrete

Abstract
This section includes guidelines for planning and administering soil investigations;
information on foundation design, including shallow and piled foundations, foundations for high-temperature equipment and vibrating machinery; retaining walls;
deadman anchors and anchor bolts; concrete and grouting, and concrete repair.
Abstracts of the Companys computer programs for foundation design are also
given. A detailed design procedure, followed by a design example, is given for
spread footings, cantilever walls, cast-in-place anchor bolts, and deadman anchors.
The section also refers to Company specifications, standard drawings and engineering forms that relate to foundations and concrete work. See also ACI 301-96, in
the specifications section, as well as two design practices, Appendices A and B of
the manual.
The guidelines are written for entry-level engineers or experienced engineers
working outside their discipline or area of expertise.
For design of tank foundations, see the Companys Tank Manual.

Chevron Corporation

Contents

Page

210

Introduction

200-3

211

Industry Codes and Practices

220

Soil Investigations

221

Introduction

222

Phases of Soil Investigation

223

Checklist of Services Available

224

Administering Soil Investigation Contracts

230

Foundations

231

Foundation Types

232

Foundation Design

233

Shallow Foundations

234

Piles and Piled Foundations

235

Foundations for High-temperature Equipment

200-4

200-11

200-1

June 1997

200 Soils, Foundations and Concrete

June 1997

Civil and Structural Manual

236

Foundations for Vibrating Machinery

237

Retaining Walls

238

Deadman Anchors

240

Anchor Bolts

241

Cast-In-Place Anchor Bolts

242

Post-installed Anchors

250

Concrete and Grouting

251

Concrete Mix Selection

252

Grouting

260

Concrete Repair

200-71

270

Computer Program Abstracts

200-76

271

OCTFNDDesign of Reinforced Concrete Octagonal Foundations

272

PLSUPFNDDesign of Reinforced Concrete Pile-supported Octagonal Foundations

273

ENGR 389Design of Reinforced Concrete Foundations for Horizontal Vessels

280

Model Specifications, Standard Drawings, and Engineering Forms

281

Specifications

282

Standard Drawings

283

Engineering Forms

290

References

200-52

200-65

200-78

200-79

200-2

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

210 Introduction
Many engineering structures, such as road pavements, containment berms, embankments, and dams use soil as a construction material. Ultimately, all structures,
regardless of the material of which they are constructed, rest upon the soil. Therefore, the foundation design and settlement behavior of the completed structure
depend on the characteristics of the underlying soil.
Soil mechanics deal with the action of forces on soil masses and involve engineering study to obtain soil properties used in foundations design.
Foundation engineering deals with the application of soil mechanics and the
resulting soil-structure interaction. The foundation engineer must keep in mind that
any foundation must be designed to satisfy two essential requirements:
1.

The foundation must have an adequate factor of safety against ultimate failure.

2.

The foundation settlement under allowable soil bearing pressure must not
exceed the allowable settlement.

Proper design of an adequate but not wasteful foundation requires engineering judgments and evaluations of:

Bearing capacity of soil


Settlement amount and rate
Earth pressures
Pore water pressures and dewatering quantities

211 Industry Codes and Practices


The following industry codes are most commonly referenced when dealing with soil
and reinforced concrete foundations:
American Concrete Institute (ACI). ACI maintains and publishes the Building Code
Requirements for Reinforced Concrete (ACI 318). This code covers the design and
construction of reinforced concrete buildings, foundations, walls, slabs, etc.
The American Concrete Institute also publishes annually the ACI Manual of
Concrete Practice. This manual is a compilation of current ACI standards and technical committee reports.
American Institute of Steel Construction (AISC). AISC publishes the Manual of
Steel Construction. This manual contains structural steel dimensions and properties,
specifications and codes, and other miscellaneous design aids. Steel piles and
anchor bolts should be designed in accordance with AISC.
Portland Cement Association (PCA). PCA publishes the Design and Control of
Concrete Mixtures, which is an excellent reference for the design of concrete mixes
for all applications.
Concrete Reinforcing Steel Institute (CRSI). CRSI publishes design handbooks
which contain complete designs of common reinforced concrete elements, including

Chevron Corporation

200-3

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

designs for Square Footings for Individual Columns, Pile Caps for Individual
Columns, Drilled Pier (Caisson) Foundations, and Cantilevered Retaining Walls.
Uniform Building Code (UBC). UBC is published by the International Conference
of Building Officials (ICBO) and is a comprehensive code on building construction. This code provides minimum standards for the design, construction, quality of
materials, use and occupancy, and location and maintenance of all buildings and
structures.
Local Governing Codes. Local governing codes supplement national codes. You
are responsible to ensure that your designs, drawings, specifications, and construction practices comply with local governing codes before final design.

220 Soil Investigations


221 Introduction
This section discusses soil investigations and related engineering. The possible
phases of a soil investigation are described along with the type of services available
from a soil consultant. The selection and evaluation of consultant services are
discussed along with guidelines for administration and control of contracts for soil
consulting services.
Soil mechanics and foundation engineering are usually part of planning work on
plant facilities. Soil mechanics and foundation engineering services are usually
directed toward one or both of two prime objectives:
1.

Saving money by decreasing the overall cost of the project either in construction or in maintenance over the life of the project.

2.

Avoiding costly project delays during construction or repairs after completion.

Soil engineering provides a basis for comparative cost studies and behavior for
different types of foundations, and for other soil aspects of design and construction.
It is possible to effect cost savings through comprehensive analysis, but the costs of
soil engineering must be carefully weighed against the expected savings in the cost
of foundation construction. Use existing data for adding on buildings in existing
plants wherever possible.

222 Phases of Soil Investigation


One or more of the soil investigation phases listed below may be appropriate for a
given project. The extent of services required may vary from recommendations
based upon review of available data or visual inspection of site conditions, through
a rough estimate based upon limited data, to a comprehensive engineering study and
recommendations based upon thorough exploration, test programs, and detailed
calculations.
Only selected portions of the phases described below would ordinarily be needed on
any specific job or project. For large projects, it is not always possible to accurately

June 1997

200-4

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

outline the complete investigative program. However, good planning will produce a
more efficient program and more effective results.

Preliminary Investigation or Reconnaissance and Design Studies


This phase aids in site selection from an earthwork and foundation cost standpoint.
It includes review of available topographic, geological, and other specific soil information.

Soil Boring and Testing


This phase helps to determine the engineering properties of soil to be used in the
design of foundations. This phase includes recommendations for foundation types,
allowable soil bearing and pile capacities, factors of safety, and estimated settlements. It is impractical to make detailed studies of all possible foundation types for
every structure. Therefore, it is desirable that these analyses be done in steps to
answer specific design questions as they arise for particular structures.

Final Soil Report


This phase incorporates all soil data and recommendations for use in the final foundation design.

Consultation During Construction


This phase usually includes inspection by and consultation with the soil consultant
regarding unexpected variations in subsurface conditions at locations where no
explorations were made. Such conditions may require modifications in foundation
details, pier depths, pile lengths, etc. Consultation may also involve evaluating
construction tools or equipment, quality and placement of fill materials, and shoring
or underpinning procedures.

Post-Construction Consultations
This phase includes observations of settlement and analyzing structure behavior
characteristics. Such studies may reduce costs or improve behavior of future additions to the project.

223 Checklist of Services Available


The following is a checklist of the types of services and recommendations that can
be provided during phases of the soil investigation and related engineering. The
types of services, and the number of soil borings and laboratory tests should be
appropriate to the magnitude of the project and to the importance of the structures
involved. Significant cost savings will be realized by holding the soil consultant to
the scope of work as defined in the contract documents and by rejecting additional
unnecessary soil borings and laboratory tests.

Chevron Corporation

1.

Site Exploration

2.

Evaluation of Project Sites

3.

Soil Borings and Sampling

200-5

June 1997

200 Soils, Foundations and Concrete

4.

5.

6.

7.

8.

June 1997

Civil and Structural Manual

Laboratory Tests and Test Properties


a.

Soil classification and index properties, such as moisture content, unit


weight, etc.

b.

Permeability

c.

Consolidation

d.

Shear strength, including liquefaction


potential

e.

Compaction

Field Tests and Measurements


a.

Soil properties in situ

b.

Pile load tests

c.

Plate bearing

d.

Seismic reflection survey

Settlement Analysis
a.

Soil stress conditions, both existing and from applied loads

b.

Total settlement

c.

Differential settlement

d.

Time rate of settlement

e.

Allowable settlement

f.

Methods of reducing or accelerating settlement (surcharge, sand drains,


wellpoints)

g.

Magnitude of swell or volume expansion and rebound

Stability Analysis
a.

Natural slopes

b.

Embankments

c.

Foundations

d.

Slope and soil stabilization methods

Seepage and Drainage


a.

Seepage analysis

b.

Seepage control

c.

Dewatering

200-6

Chevron Corporation

Civil and Structural Manual

9.

200 Soils, Foundations and Concrete

Compaction
a.

Embankments

b.

Earth dikes

c.

Compaction procedures and compaction control

d.

Slope protection

10. Bearing Capacity


a.

Spread foundations

b.

Mat foundations

c.

Caissons

d.

Pile load capacity both individual piles and pile groups

11. Retaining Walls and Retaining Structures


a.

Earth pressure coefficients (active, passive, at rest)

b.

Crib walls, reinforced earth, other proprietary types

c.

Sheet piles

d.

Braced cuts

12. Buried Structures


a.

Concrete pipes

b.

Steel pipes

c.

Culverts

d.

Tunnels

e.

Electrical conduits

13. Soil Stabilization


14. Shoring and Underpinning
15. Vibration Problems
a.

Dynamic soil properties (modulus of elasticity, shear modulus, Poissons


ratio) for use in design of foundations for compressors and other vibratory
equipment.

b.

Seismic reflection survey

16. Response Spectra

Chevron Corporation

200-7

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

17. Construction Support


a.

Evaluation of methods and equipment for placing compacted fills

b.

Verification of density and compliance with compaction and placement


criteria

c.

Advice on subsurface drainage or special stabilization problems

d.

Evaluation of quality, stability, and probable behavior of fill and materials


beneath the fill

e.

Consultation and inspection of piling, caissons, or footings placement

f.

Evaluation of field loading tests on footings, piling, or caissons

g.

Instrumentation in slope stability problems or underpinning problems, such


as strain gages, settlement readings, or inclinometer installations

h.

Advice on operating conditions for earthmoving, including trafficability,


striping arrangements and possible weather considerations

i.

Evaluation of criteria for control of pile-driving operations, with provisions for adapting to possible variations in subsurface condition

j.

Evaluation of criteria for installation of piers or caissons

k.

Evaluation of stability of construction excavations and possible risks to


adjacent structures

l.

Consultation on subsurface construction problems

224 Administering Soil Investigation Contracts


The need for soil and foundation engineering consulting services on any project
must be recognized by the responsible Company engineers, and steps should be
initiated to define the services needed for each project. The Civil/Structural team in
CRTC can provide input at this stage. Since the program for a soil or foundation
investigation can range from a very limited to a very involved study, the appropriate extent of study depends on a number of factors.
The most important aspect of planning a study for a particular project is to reach a
complete and mutual understanding of the exact problems for which answers are
desired. It is imperative that the specific purposes of the studies be clearly understood by all participants and that the contractor be held to the agreed scope of work.

Soil Consultant Selection


The consultant must be selected to provide the desired engineering services. The
consultant is usually selected in one of the following ways:

June 1997

1.

Solicit competitively-bid proposals from qualified consultants

2.

Negotiate a contract with the preferred consultant

200-8

Chevron Corporation

Civil and Structural Manual

3.

200 Soils, Foundations and Concrete

Prepare an authorization to an existing standing contract with the preferred


consultant

Review the Companys Construction Contracts and Services Manual for procedures
on bidding, negotiating, and authorizing professional services contracts.
For large projects in areas where little or no previous soil investigation work has
been performed, competitive bidding for the soil investigation and engineering is
recommended. In order to prepare a proposal for a soil investigation program, the
consultants will need to know the major facilities that are considered.
For work in areas where significant soil investigation work has been done, it is often
beneficial to retain the services of the consultant who performed the previous work.
This can frequently be done by negotiating a contract or supplementing an existing
contract with the consultant.
Contact the Civil/Structural team in CRTC for information on soil consultants with
whom the Company has had prior satisfactory experience.

Establish Scope of Services and Prepare Cost Estimate


Request an initial proposal for a foundation investigation which describes the
purposes and detailed services which the soil consultant will provide. The
consultant should include an estimate of the costs to perform the proposed services.
The evolution of some projects may require changes by either increasing or
decreasing the initial scope of work. During the initial planning of a soil investigation, the total program should be anticipated and at least tentatively outlined, with
the understanding that the scope and details of future portions will be influenced by
developments during the successive steps.

Clarify Division of Responsibilities


The Company will always maintain overall administrative responsibility of direct
contracts with the consultant. Where technical responsibilities are divided between
the Company and the consultant, the division should be very clear.
The division of responsibilities, as well as the scope, timing and presentation of a
soil investigation, will be influenced by the manner in which the design and
construction work is contracted. When work is contracted on a turnkey basis,
responsibility for detailed foundation design and construction may be placed on the
contractor. In this case, the soil investigation program might be limited to general
site information for planning purposes, with the contractor later handling the
detailed soil investigation. The preferred method is for the Company to be responsible for the entire soil investigation program and to furnish such data (or a design
basis) to the contractor. Accordingly, it is necessary that the soil consultant be aware
of the contracting plan and the division of Company-Contractor responsibilities.
When parts of the engineering design are carried out by design, or design and
construction contractors, additional problems of communication and division of
responsibility must be considered. For example, if a soil consultant is retained by a
design and construction contractor directly, the consultants primary responsibility
may be to help save the contractor the maximum amount of construction costs. This

Chevron Corporation

200-9

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

situation may involve difficult decisions about whether to approve construction


which is acceptable in performance at a minimum cost, or to select slightly safer or
more desirable construction having a higher margin of safety at slightly greater
construction cost.

Maintain Open Communications


Communications between the soil consultant and Company must always be open
and it is essential that all concerned be kept informed of plans which affect their
work or which may be affected by their work. Some knowledge of the project as a
whole and of the functional demands of equipment to be supported may permit the
soil consultant to suggest an attractive alternate design, rather than simply to answer
specific questions. Also, if you have a good understanding of the reasons and basis
for the foundation recommendation, you may be able to modify designs to take best
advantage of site conditions.

Request Complete Reports


Reports should be prompt, concise, should point out specific objectives and conclusions, and may often need to be presented in stages to meet the timing needs of the
projects development. A complete report should:
1.

Call attention to unresolved problems which may need further study.

2.

Evaluate areas of uncertainty due to variability of soil or unknown conditions.

3.

Indicate the range of accuracy in the results presented.

4.

Address any anticipated special construction problems.

5.

List detailed data, such as boring logs and test results.

A draft soil report should be reviewed with the consultant before issuing the final
report to ensure that all questions have been satisfactorily covered in the report.
During the course of all phases of a soil investigation program (field, lab, and
office), a continuing review between you and the soil consultant of results to date,
current status of work, outlook for completions, and preliminary conclusions will
help ensure that the results are adequate and timely.

Prepare Cost Estimates Early


An estimate of the cost of the services to be performed by the soil consultant should
be prepared as soon as the program is defined and before starting the program in
order that the work be properly authorized. The soil consultant should prepare a
detailed cost estimate which should be reviewed and approved by you. In case of a
stepwise approach to the investigation, an approximate overall cost should be estimated, with detailed estimates made as each step is defined.

June 1997

200-10

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

The estimate should include as applicable:


1.

Field Costs
a.

Field engineering including expenses

b.

Testing or sampling equipment charges

c.

Drilling subcontract costs

d.

Access assistance (clearing, roads, barges, surveying).

2.

Laboratory costs including number and types of various tests proposed.

3.

Office costs including manhours estimates for performing analyses and


preparing recommendations.

4.

Report Preparation and printing costs.

5.

Design and construction consultation.

During the course of the work, the soil consultant should keep you currently advised
of expenditures, preferably through weekly reports. Further authorization is usually
needed if the final expenditures exceed those previously authorized.

230 Foundations
This section of the manual presents design guidelines and discusses other considerations for commonly used foundations.

231 Foundation Types


Foundations can be separated into two broad categories, shallow and deep.
Retaining walls can also be considered as foundations.

Shallow Foundations
Shallow foundations transfer superstructure loads to the soil directly underneath the
foundation. Shallow foundations are categorized as spread footings or wall footings. Spread footings are the most commonly used type of foundation because they
are usually more economical than other types. From a design point of view they are
classified as spread footings, combined footings and mat foundations. The choice
among these types depends primarily upon the relative cost.
Spread Footings. A spread footing supports one column or one piece of equipment. Spread footings can be square, rectangular, circular, or octagonal in shape. A
pedestal is often used with spread footings in order to reduce the thickness of the
footing and to develop the full strength of dowels or anchor bolts. Examples of
spread footings are shown in Figure 200-1. Design of spread footings is discussed
in Section 233 of this manual.
Combined Footings. Combined footings are used to support two or more column
loads in a row or when two or more spread footings would overlap. A combined

Chevron Corporation

200-11

June 1997

200 Soils, Foundations and Concrete

Fig. 200-1

Civil and Structural Manual

Spread Footings

footing is recommended when minimizing differential settlement between columns


is important. Combined footings are limited to rectangular, trapezoidal and other
simple shapes. Trapezoidal shapes are used to create equal soil bearing pressure
under unequal applied loads. Examples of combined footings are shown in
Figure 200-2.
Strap Footings. A strap footing is comprised of two or more spread footings
connected by a beam called a strap. Figure 200-2 shows an example of a strap
footing.
Mat Foundations. Mat foundations (Figure 200-3) are large concrete slab foundations which transmit the loads from several columns in two or more rows or pieces
of equipment to the soil. Mat foundations are used in locations where the soil
bearing capacity is low and foundation settlements, particularly differential settlements, may be a problem. By combining individual footings into a mat the bearing
capacity is often increased.
Wall Footings. Wall footings are used to support building walls. They are shaped
like spread footings except that they are continuous for the entire length of the wall.

Deep Foundations
Pile Foundations are the most common deep foundations. Piles can be made of
timber, concrete, steel, and combinations of each to transmit surface loads to firm
strata at greater depths. Figure 200-4 shows the usual types of piles and the

June 1997

200-12

Chevron Corporation

Civil and Structural Manual

Fig. 200-2

200 Soils, Foundations and Concrete

Combined and Strap Footings

optimum load and length range. Further discussion of pile foundation types, materials, and design is continued in Section 234 of this manual.
Retaining Walls. Retaining walls are structures used to provide stability for earth or
other materials where conditions prevent the soil or material mass from assuming its
natural slope. The different types of retaining walls are shown in Figure 200-5.
Gravity Walls. Gravity walls are plain concrete walls with no tensile stresses on
any portion of the wall. The gravity wall depends upon its own weight for stability.
Because of the large volume of concrete required they are not very economical for
high walls.
Semigravity Walls. Semigravity walls use small amounts of reinforcing steel in
order to reduce the volume of concrete. Like gravity walls they are not very
economical for high walls.
Cantilever Walls. Cantilever walls are the most common type used. They are made
of reinforced concrete. They are suitable and economical for moderate heights (2025 feet). A key may sometimes be required to prevent sliding.

Chevron Corporation

200-13

June 1997

200 Soils, Foundations and Concrete

Fig. 200-3

Mat Foundations

Fig. 200-5

June 1997

Civil and Structural Manual

Fig. 200-4

Pile Foundations

Retaining Walls

200-14

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Counterfort Walls. Counterfort walls are also made of reinforced concrete. Both
the base slab and wall span horizontally between vertical brackets known as counterforts. This type of wall is suitable for retaining high fills (greater than 20 feet).
Sheet Piling Walls. Sheet piling walls are commonly used for large and small
marine structures and also for slope stability and erosion control. The two common
types of sheetpiling walls are cantilevered sheetpiling and anchored sheetpiling.
Braced sheetpiling is also shown in Figure 200-6.
Fig. 200-6

Sheet Piling Structures

Proprietary Walls. Proprietary walls can be very economical in certain applications. The most widely used are prefabricated steel crib walls and reinforced earth
walls. Reinforced earth walls have precast concrete wall panels with clips for
connecting steel ties which extend into the retained earth behind the wall. Reinforced earth walls have been used to retain fills as high as 50 feet. Crib walls are
suitable for fills to 20 feet high.

232 Foundation Design


This section outlines the steps to follow in the design of any foundation, as well as
the design considerations that accompany each stage of the design procedure.
Recommendations on factors of safety and allowable settlements are also given.
Determine Scope Of Work. Identify the structure or piece of equipment that needs
to be supported. Also identify any special problems that are associated with
supporting the particular item.

Chevron Corporation

200-15

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Assemble Design Aids. Assemble all pertinent reference materials that are needed
to assist you in the foundation design. These materials include:

Company Model And Standard Specifications And Forms


Drawing Record Books
Basic Engineering Design Data (Bedd) Sheets
Plot Plans
Vendor Drawings
Preliminary Layout Drawings
Soil Report
Governing Codes, Including AISC, UBC, ACI, AWS, and API

Establish Design And Loading Criteria. That is, define the following:

Type and magnitude of applied loads


Allowable soil bearing
Allowable settlement
Factors of safety against failure
Material properties

Make Preliminary Calculations And Estimates. Make preliminary, but conservative calculations and estimates of structure or equipment weights, forces, and/or
moments that will act on the foundation. It is important to use the best available data
at this stage. If your estimates are more accurate, future revisions may be reduced or
not required.
Select Foundation Type. Using the design aids and loading criteria assembled,
select the type of foundation to be used. The soil report will commonly provide
recommendations on foundation types for large or special structures and foundations. The extent of these recommendations depends upon the scope of services
requested from the soil consultant.
Wherever possible, use a conventional spread footing, provided a reasonably sized
footing can adequately transfer the foundation loads to the soil without overloading
the soil or resulting in excessive settlement. Spread footings are commonly used and
are generally considered the most economical choice of foundation. If the loads
cannot be supported by a spread footing or expected settlements will exceed allowable values, then deep foundation such as piles should be considered to transfer the
loads to deeper soil.
At this stage, consideration should be given to the configuration and size of the
foundation. In many cases, it is advantageous to combine two spread footings in
order to reduce construction costs.
Establish Schedule. The schedule is often an important consideration in the design
of foundations or underground structures. For the majority of projects, the foundation construction follows closely after the site preparation work, and the foundation
design must be as complete as possible before all of the design information is available.

June 1997

200-16

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Determine Design Requirements. Special considerations must be given to


vibrating equipment, frost heave, groundwater table, liquefaction, and settlementsensitive equipment or structures.
Prepare Preliminary Design. Using the assembled design aids, computer
programs, and codes as necessary, along with the latest design information (for
example, piping layouts, equipment sizes), prepare the foundation design including
size, shape, and location. Remember to develop a design that is flexible and conservative to allow for probable revisions or modifications as the design information is
further developed and finalized.
Confirm Design And Loading Criteria. This stage involves review of the preliminary design. The review includes coordinating and incorporating the latest design
information into the preliminary design. This design information includes piping
layouts, vendor drawings of equipment, preliminary and existing structural drawings, and potential underground interferences (for example, drain lines, conduit
banks, and existing foundations).
Complete The Final Design. After all items affecting the design have been
confirmed and any problems resolved, the foundation design can be finalized.
Document The Designs. Proper documentation of foundation designs should be
done as with any civil engineering design. Documentation of design criteria and
loads, allowable loads, governing codes, and other information will allow rapid
evaluation of the foundation if future changes in loads or service are considered.

233 Shallow Foundations


This section presents the design considerations and a design procedure for the
design of shallow foundations. Shallow foundations most commonly refer to footings that bear directly on the native soil, which are capable of carrying the foundation loads without piles. An example design problem is also presented.

Design Considerations
Bearing Capacity. Allowable bearing capacity recommendations will be developed during the soil investigation. The soil report will include soil bearing capacity
values for the project site with appropriate factors of safety for the anticipated
loading conditions. Use old reports for existing plants.
In the absence of recommendations for allowable bearing capacities, 1991 Uniform
Building Code Table No. 29-B which gives allowable soil pressures for different
soil types may be used for preliminary design or final design for projects involving
only one or two small foundations supporting static loads.
Foundation Settlements. Settlement is often a controlling factor in the design of
any foundation, and particularly, spread footings. The soil report should discuss estimates of the expected settlement for different foundation types and major facilities
in the project area. Foundation recommendations to minimize settlement should also
be included.

Chevron Corporation

200-17

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Differential foundation settlements are usually more critical than the settlement of
individual foundations. Special consideration must be given to the settlement of critical structures or equipment which could impose excessive stresses on other structures, connections, and piping. Differential settlement should be limited to 0.5-0.75
inches whenever possible. For adjacent equipment, foundations should be combined
or tied together to avoid differential settlement.
Factors of Safety. The soil report will recommend appropriate factors of safety for
spread footing design. Following are recommended minimum factors of safety
against ultimate bearing capacity failure.

Dead loads and operating loads:


Minimum factor of safety of 2.0 to 3.0 depending on the type of structure and
the reliability of the condition of the soil.

Temporary, wind, or seismic loading:


Minimum factor of safety of 1.5 to 2.0

In some instances, lower factors of safety may be justified based on a thorough soil
investigation, sound engineering principles and type of soil.

Other Considerations
The depth of shallow foundations should be selected so that the bottom of the foundation is placed below:

Frost line
Topsoil or other organic material
Unconsolidated fill material

Layers of expansive soils (clays)


The stability ratio of the resisting moments about the edge of any foundation to the
overturning moments due to wind and earthquake loads should not be less than 1.5.

Design Procedure, Spread Footings


The design procedure that follows outlines the steps for designing a spread footing
supporting a single load applied at the center of the foundation. Spread footings for
overturning moment in one direction only may be designed by the following procedure. The procedure has two parts: calculating the footing size (9 steps) and
preparing the footings structural design (6 steps.) An example problem follows the
design procedure.

Footing Size
1.

Calculate the applied vertical load, P, shear, V, and moment, M, at the top of
footing or top of pedestal, whichever applies. The loads are due to one or a
combination of the following.

June 1997

Dead load
Live load
Wind load

200-18

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Thermal forces
Seismic forces
Equipment loads (operating, hydrotest) and associated piping

2.

Choose the minimum depth of footing, D, below grade and the height of the
pedestal, h, above grade. The bottom of footing should be below the frost line
and should bear on soil with adequate bearing capacity. The top of the pedestal
is normally six (6) to twelve (12) inches above grade to protect the anchor bolts
from moisture, dirt, or debris.

3.

Translate the loads from top of footing or pedestal to bottom of footing. Vertical
load, P, and shear, V, remain the same but the moment at the footing bottom,
Mb, increases by the product of shear, V, times distance (D+h). See
Figure 200-7.
Mb = M + V ( D + h )
(Eq. 200-1)

4.

Estimate the plan dimensions of footing (L,B) based on the allowable soil
bearing qa, vertical load P, and moment Mb, but first transform the load P and
moment Mb to a new location at an eccentricity, e = Mb/P, from footing centerline. The footing plan dimensions (L,B) are estimated with the aid of the soil
pressure distribution as shown in Figure 200-8. For equilibrium, the summation of forces in the vertical direction must equal zero. Use a trial and error
process in estimating footing plan dimensions (L,B). Select the larger initial
dimensions based on a) maximum vertical load and allowable soil bearing pressure, and b) maximum vertical load with overturning moment and maximum
soil bearing pressure allowed for wind and earthquake load conditions.
a.

Maximum vertical load only


BL = P q a
(Eq. 200-2)

b.

5.

Maximum vertical load with overturning


Assume e = Mb/P > L/6
3 (L/2 - e) qaB/2 = P
(L/2 - e)B = 2P/3qa

Select a footing thickness, t, and pedestal dimensions (a,b). If the pedestal


supports a steel column, the column base plate size and anchor bolt requirements will dictate minimum rectangular pedestal dimensions (a,b) or round
pedestal radius (r). The footing thickness, t, in inches can be estimated from
beam shear (V) and Figure 200-9.
L t
V = 1.7q a --- ------ , lb ft
2 12
(Eq. 200-3)

Chevron Corporation

200-19

June 1997

200 Soils, Foundations and Concrete

Fig. 200-7

Footing Force Translation

Civil and Structural Manual

Fig. 200-8

Footing Force Transformation and Soil

V c = 2 f c ( 12t )
(Eq. 200-4)

Where Vc = allowable shear in the concrete


V = Vc
L t
1.7q a --- ------ = 24t f c
2 12
1.7q a t
--------------- + 24t f c = 0.85q a L
12
0.85q a L
t = -----------------------------------1.7q a
------------- + 24 f c
12
where:
t =

June 1997

thickness of footing, in.

200-20

Chevron Corporation

Civil and Structural Manual

Fig. 200-9

200 Soils, Foundations and Concrete

Free Body Diagram for Estimating Footing Thickness t

6.

L =

length of footing in direction of overturning, ft.

qa =

allowable soil bearing pressure, psf.

fc =

compressive strength of concrete, psi.

Compute the weight, Wt , of footing, pedestal, and of the soil over the footing.
The unit weight of normal weight reinforced concrete is 150 pcf. The unit
weight, , of soil will be given in the soils report. However, if not given, use
100 pcf. Be sure to use consistent units for the variables in the following equations and the submerged weights if the water table is above the bottom of the
footing (from Figure 200-7, Footing Force Translation.)
a.

Rectangular pedestal
W t = [ BLt + ( D + h t )ab ]150 + ( BL ab ) ( D t )
(Eq. 200-5)

b.

Round pedestal
W t = [ BLt + ( D + h t )r 2 ]150 + ( BL r 2 ) ( D t )
(Eq. 200-6)

7.

Chevron Corporation

Calculate the factor of safety against overturning. The applied load P plus the
footing, pedestal and soil weight, Wt, should provide a minimum factor of
safety (F.S.) against overturning of 1.5. The factor of safety is often called
stability ratio (S.R.). The stability ratio equals Resisting Moment (Mr) divided

200-21

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

by Overturning Moment (Mo). Sum the moments about point zero in


Figure 200-7.
M r = L ( P + Wt ) 2
(Eq. 200-7)

Mo = M b
S.R. = M r M o 1.5
For combined footings, the resisting and overturning moments are determined
by considering the loads from all columns.
8.

Calculate the soil-bearing pressure.


Figure a new eccentricity, e, using Mo and P+Wt
e = Mo ( P + Wt )
(Eq. 200-8)

From the previously estimated footing dimensions (L,B) calculate the


maximum soil bearing pressure, qmax, which must be less than or equal to the
allowable bearings, qa, and the minimum soil bearing pressure, qmin. The
allowable soil bearing may usually be increased for seismic or wind loads. This
is generally given in the soils report.
Case I
eL6
q max = ( P + W t ) A + M o L 2I = ( P + W t ) A + ( 6M o BL 2 ) q a
(Eq. 200-9)

q min = ( P + W t ) A 6M o BL 2
(Eq. 200-10)

where:
A = plan area of footing = BL
I = moment of inertia of plan area of footing about the overturning
axis = BL3/12
P = applied vertical load
Wt = weight of footing plus pedestal plus weight of soil over the
footing
Case II

June 1997

200-22

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

e>L6
q max = 2 ( P + W t ) [ 3B ( L 2 e ) ] q a
(Eq. 200-11)

q min = 0
(Eq. 200-12)

Figure 200-10 illustrates the soil bearing pressure distribution for the two ranges of
eccentricity e.
Fig. 200-10 Soil Bearing Pressure Distribution

In determining soil bearing pressure, first determine the gross soil pressure using the
full weight of the concrete and soil above the footing. Then determine the net soil
pressure by subtracting the weight of the soil above the base of the footing. The unit
weight of soil will be given in the soils report. However, if it is not given use 100
pcf.
9.

Detail the footing reinforcement as discussed next.

Structural Design of Footing


1.

Chevron Corporation

When the plan dimensions of the footing have been established the footing
concrete design can proceed. The concrete design should be based on ACI 318.

200-23

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

For this purpose the loads must be factored as prescribed in Section 9.2 of ACI
318-89.
Case I
D+L
Pu or Mu = 1.4D + 1.7L
Case II
D+L+W
Pu or Mu = 0.75 (1.4D + 1.7L + 1.7W)
Case III
D+W
Pu or Mu = 0.9D + 1.3W
Case IV
D+L+E
Pu or Mu = 0.75 (1.4D + 1.7L + 1.87E)
Case V
D+E
Pu or Mu = 0.9D + 1.43E
where:
Pu =
Mu =

factored vertical load, lb.


factored overturning moment, lb-ft.

D =

dead load, lb. for Pu, lb-ft. for Mu

L =

live load, lb. for Pu, lb-ft. for Mu

W =

wind load, lb. for Pu, lb-ft. for Mu

E =

seismic load, lb. for Pu, lb-ft. for Mu

Note Cases III and V are intended primarily for stability against overturning of
the super- structure. Do not use Case V where the live load, L, is a substantial part
of the total load used in computing seismic load, E.

June 1997

2.

Calculate the soil bearing pressures using the factored vertical loads and or
moments, and the equations in step 8 of Spread Footing Design Procedure,
Footing Size above. Sketch the factored soil bearing pressures in the manner
outlined in Figure 200-10.

3.

Determine the maximum factored applied vertical load, Pu, at top of footing
and the maximum footing shear and moment due to the factored soil pressure.

200-24

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

The load, Pu, is used in the design of the footing for punching shear. The
footing must be designed to resist shear and bending at the critical sections
illustrated in Figure 200-11. Figure 200-12 shows the free body diagrams for
beam shear and moment.
Fig. 200-11 Critical Sections for Shear and Moment

From Figure 200-12,


Vu = [(quo + quv) / 2]B(L/2 - d - a/2)
(Eq. 200-13)

or substituting r for a/2,


Vu = [(quo + quv) / 2]B(L/2 - d- r)
(Eq. 200-14)

That is, the shear, Vu, is obtained from trapezoidal soil bearing distribution.
Mu = qum(L/2 - a/2)2B/2 + (quo - qum)(L/2 - a/2)2 B/3
(Eq. 200-15)

Chevron Corporation

200-25

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Fig. 200-12 Free Body Diagrams for Shear and Moment

or substituting r for a/2,


Mu=qum(L/2 - r)2B/2 + (quo - qum)(L/2 - r)2 B/3
(Eq. 200-16)

That is, the moment, Mu, is composed of rectangular and triangular soil bearing
distributions.

June 1997

200-26

Chevron Corporation

Civil and Structural Manual

4.

200 Soils, Foundations and Concrete

Check the preliminary footing thickness, t, to resist punching shear and beam
shear at the critical sections without shear reinforcement as shown in
Figure 200-11.
a.

Punching (two-way) shear


4
V c = 2 + ----- 1 f c b o d

s d

--------- + 2 f c b o d
bo

Pu
4 f c b o d V u = -----
(Eq. 200-17)

b.

Beam (one-way) shear


Vu
V c = 2 f c b w d ------
(Eq. 200-18)

where:
s = 40 for interior columns, 30 for edge columns, 20 for corner
columns, i.e., critical sections with 4, 3, or 2 sides respectively
c = ratio of long side to short side of concentrated load or reaction
area.
1) rectangular pedestal c = a/b
2) round pedestal c = 1
bo = perimeter of critical section for punching shear
1) rectangular pedestal
bo = 2 (a + b + 2d), in.
2) round pedestal bo = (2r + d), in.
bw = footing width for beam shear, in
fc = 28-day compressive concrete strength, psi
d = distance from edge of footing (compression fiber) to centroid of
tension reinforcement, in.
Vu = shear force at critical section due to factored soil pressure
Pu = factored applied vertical load at top of pedestal
= strength reduction factor for shear (0.85)
5.

Chevron Corporation

Design the footing to resist the bending moment due to the soil pressure
resulting from factored loads. Figure 200-13 lists reinforcing steel bar properties.

200-27

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Case I
Footing thickness known, amount of reinforcing steel to be determined.
Use minimum footing, d, required for punching shear or beam shear, whichever is greater. Footing thickness may also be limited by underground obstructions or other considerations.
f c M u
f c
f c 2

= 0.85 ------ 0.85 ------ 1.7 ---------------------fy


fy
f y 2 bd 2

(Eq. 200-19)

where:
= ratio of tension reinforcement =As/bd
As = area of tension reinforcement, in.2
b = width of footing at critical section for moment, in.
fy = yield strength of reinforcing steel, 60,000 psi
Mu = moment due to soil pressure resulting from factored loads, lb-in.
= strength reduction factor for flexure (0.9)
min = 200/fy
optimum 0.015

Fig. 200-13 Properties of Steel Reinforcing Bars


Bar Size

Nominal Diameter, in

Weight lb/ft

Cross-Sectional Area, in2

#3

0.375

0.376

0.11

#4

0.500

0.668

0.20

#5

0.625

1.043

0.31

#6

0.75

1.502

0.44

#7

0.875

2.044

0.60

#8

1.000

2.670

0.79

#9

1.128

3.400

1.00

#10

1.270

4.303

1.27

#11

1.410

5.313

1.56

#14(1)

1.693

7.65

2.25

#18(1)

2.257

13.60

4.00

(1) #14 and #18 bars are used primarily as column reinforcement and are rarely used in beams.

June 1997

200-28

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Case II
Amount of reinforcing steel is given or assumed; footing thickness to be determined.
This situation may occur where footing thickness is not restricted but it is desirable to limit the amount of reinforcing steel by limiting the reinforcement ratio
r to a value near the minimum. The minimum footing thickness should be 10
inches.

d =

Mu
f

-------- b fy 1 0.59 -----y-

f c

(Eq. 200-20)

6.

A ts,

Provide shrinkage and temperature reinforcement


normal to flexural reinforcement on top and bottom footing faces in both directions equal to 0.0014
times gross cross-sectional concrete area. The amount of shrinkage and temperature reinforcement need not be more than 0.4 in2/ft.

Example Problem, Spread Footing Design


Footing Size
1.

Calculate applied loads.


Given:
a.

Loads at top of pedestal


Vertical, P
Dead

50 k

Operating

75 k

Seismic

5k

Horizontal (shear), V
Dead

3k

Operating

2k

Seismic

25 k

Moment, M
Dead

15 k-ft

Operating

10 k-ft

Seismic

Chevron Corporation

250 k-ft

200-29

June 1997

200 Soils, Foundations and Concrete

b.

Civil and Structural Manual

Material
Concrete, fc = 3,000 psi
Reinf. steel, fy = 60,000 psi
Soil - firm sand
Unit weight, = 110 lb/ft3
Gross allowable bearing, qga = 4500 psf.
With 1/3 increase for wind or earthquake
loading, qga = 6000 psf.
Net allowable bearing, qna , equals 4500 minus 110D. With 1/3
increase for wind or earthquake loading, qna = 6,000 - 146.67D.

c.
2.

Water table
10 ft. below grade

Choose minimum depth of footing (see Figure 200-14).

Fig. 200-14 Minimum Depth of Footing

3.

June 1997

Fig. 200-15 Load Translations

Translate loads to bottom of footing using Figure 200-15 and the values below:
P

= 50D + 75op + 5E = 130 k

= 3D + 2op + 25E = 30 k

200-30

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

=15D + 10op + 250E

Mb

+(3D + 2op + 25E) 5


= 30D + 20op + 375E = 425 k-ft
4.

Estimate the footing plan dimensions.


a.

Maximum vertical load only


BL = P/qa
= 130/4.5 = 29 ft2
L
= 29/B

b.

Maximum vertical load with overturning


e = Mb/P = 425/130 = 3.27 ft.
(L/2 - e)B = 2P/3 x 1.33qa
(L/2 - 3.27)B = 2 x 130/3 x 1.33 x 4.5
= 14.45
L

= (14.45/B + 3.27) 2
= 28.9/B + 6.54

By inspection, method (b) controls.


L

= 28.9/6 + 6.54 = 11.36 ft.

Try L = 11 ft, B = 6 ft.


L/6 = 1.83 < e = 3.27 ft.
Therefore, the assumption is okay.
5.

Select footing thickness, t, in.


0.85q a L
t = -----------------------------------1.7q a
------------- + 24 f c
12
( 0.85 ) ( 4500 ) ( 11 )
= ---------------------------------------------------------( 1.7 ) ( 4500 )
----------------------------- + 24 3000
12
= 21.6 inches.
Try t = 22 in.
d = t - 3 in. clr. - 1/2 rebar
= 22 - 3 - (~0.5 in.)
= 18.5 inches to center of rebar

Chevron Corporation

200-31

June 1997

200 Soils, Foundations and Concrete

6.

Civil and Structural Manual

Compute weight of footing, pedestal, and soil above footing.


Wt = [BLt + (D + h - t) ab]150 + (BL - ab) (D - t) 110
= [6 x 11 x 22/12 + (4 + 1 - 22/12) x 1.75 x 1.333]150
+ (6 x 11 - 1.75 x 1.333) (4 - 22/12)110
= 19,255 + 15,175
= 34,430 lb

7.

Calculate the factor of safety against overturning.


Resisting moment, Mr = L(P + Wt)/2
Mr = 11 (130 + 34.4)/2 = 904.2 k-ft
Overturning moment, Mo = Mb = 425 k-ft.
S.R. = 904.2/425 = 2.13 > 1.5
The safety factor is okay.

8.

Calculate gross and net soil pressures using the values above and
Figure 200-16.
a.

Gross pressure
e

= Mo/(P + Wt) = 425/(130 + 34.4)


= 2.59 ft. > L/6 = 11/6 = 1.83 ft.

Therefore, Case II controls.


qmax = 2(P + Wt)/[3B(L/2 - e)]
= 2 (164.4) / [3 x 6(11/2 - 2.59)]
= 6.28 ksf > 6 ksf
The result is no good.
b.

Net pressure
qna

= 6,000 - 146.67 x 4 = 5,413 psf/1,000


= 5.413 ksf

Wnet = Wt - LBD
= 34,432 - 11 x 6 x 4 x 110
= 5,392 lb
e

= 425/(130 + 5.39)
= 3.14 ft. > L/6 = 1.83 ft.

Therefore, Case II controls.


qmax = 2(130 + 5.39)/[3 x 6(11/2 - 3.14)]
= 6.37 ksf >qna = 5.413 ksf
The result is no good.

June 1997

200-32

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Try L = 12 ft, B = 6 ft.


Wt

= [6 x 12 x 22/12 + (4 + 1 - 22/12) 1.75 x 1.33]150 +


(6 x 12 - 1.75 x 1.33) (4 - 22/12) 110
= 20,908 + 16,604 = 37,512 lb

Wnet = 37,512 - 12 x 6 x 4 x 110 = 5,832 lb


Mr

= 12 x (130 + 5.832)/2 = 815.0 k-ft.

S.R. = 815/425 = 1.92 > 1.5


The safety factor is okay.
e

= 425/(130 + 5.8) = 3.13 ft. > L/6


= 3.13 ft. > L/6 = 12/6 = 2 ft.

Therefore, Case II controls.


qmax = 2 x 135.8/3 x 6(12/2 - 3.13)
= 5.26 ksf < qna = 5.413 ksf
The result is okay.
9.

Detail the footing reinforcement.

Fig. 200-16 Soil Bearing Pressure Calculation

Chevron Corporation

200-33

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Structural Design of Footing


1.

Factored loads
By inspection it is obvious that loading Case IV controls, i.e. D + L + E
Pu or Mu = 0.75 (1.4D + 1.7L + 1.87E)
Pu = 0.75 [1.4(D + Wt) + 1.7L + 1.87E]
= 0.75 [1.4(50 + 37.5) + 1.7 x 75 + 1.87 x 5]
= 194.5 k
Mu = 0.75(1.4 x 30 + 1.7 x 20 + 1.87 x 375)
= 582.9 k-ft

2.

Calculate soil pressure using factored loads (see Figure 200-17).


e

= Mu/Pu = 582.9/194.5
= 3 ft. > L/6 = 12/6 = 2 ft.

qu = 2Pu / [3B(L/2 - e)]


= 2 x 194.5 / [3 x 6(12/2 - 3)]
= 7.2 ksf
Fig. 200-17 Soil Bearing Pressure Calculation Using Factored Loads

FTG
3.0

3.0

GRADE

194.5

7.2 ksf

3x3.0= 9.0

3.0
12

3.

June 1997

Determine maximum factored applied vertical load, Pu, at the top of the footing
and maximum footing shear and moment (see Figures 200-18 and 200-19).

200-34

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Fig. 200-18 Free Body Diagram for Beam Shear

Fig. 200-19 Free Body Diagram for Moment

FTG
1.542
a/2
3.58

GRADE

7.2 ksf
q

uv

5.42

9.0

At top of pedestal
Pu

= 0.75 (1.4 x 50 + 1.7 x 75 + 1.87 x 5)


= 155.1 k

= 18.5 in. = 1.542 ft.

a/2

= (1'9")/2 = 10.5" = 0.875

L/2 - d - a/2 = 12/2 - 1.542 - 0.875 = 3.58 ft.


9 - 3.58 = 5.42
quv

= (5.42/9.0)7.2
= 4.34 ksf

Vu

= [(7.2 + 4.34)/2] 3.58 x 6 = 123.9 k

a/2

= 0.875 ft.

12/2 - 0.875 = 5.125 ft.


9 - 5.125 = 3.875 ft.
qum

= (3.875/9.0)7.2
= 3.1 ksf

Mu

= 3.1 x 5.1252 x 6/2


+ (7.2 - 3.1) x 5.1252 x 6/3
= 244.3 + 215.4
= 459.7 k-ft

Chevron Corporation

200-35

June 1997

200 Soils, Foundations and Concrete

4.

Civil and Structural Manual

Check preliminary footing thickness for punching and beam shear without
shear reinforcement.
a.

Punching Shear

Pu = 155.1 k
c = a/b = 1.75/1.33 = 1.32 < 2
s d
( 40 ) ( 18.5 )
--------- = --------------------------------------------------- = 5>2
bo
2 ( 21 + 16 + 2 18.5 )
V c = 4 f c b o d
= 4 3000 ( 18.5 ) ( b o = 2 [ 21 + 16 + 2 ( 18.5 ) ] )
= 4 3000 ( 18.5 ) ( 148 in. ) = 599 ,900 lb
Pu
155.1
V u = ------ = ------------
0.85
= 182.5k < V c = 599.9k
The result is okay.
b.

Beam shear
V c = 2 f c b w d
= 2 3 ,000 6 12 18.5
= 145 ,900 lb
V u = 123.9 0.85
= 145.8 k < 145.9 k

The result is okay.


5.

Design the footing for moment (see Figure 200-20)

Fig. 200-20 Footing Reinforcement

June 1997

200-36

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Mu = 459.7 k-ft
Case I - (t = 22"), d =
18.5"

1
f c
f c 2 1.7f c M u --2 = 0.85 ------ 0.85 ------ ---------------------2
fy
fy

f y bd 2
1--2
(
1.7
)
(
3
)
(
459.7
)
(
12
)
3
3

= 0.85 ------ 0.85 ------ ------------------------------------------------------ 2


60
60
( 0.9 )60 2 ( 6 ) ( 12 )18.5 2

200
= 0.00437 > min = --------------- = 0.0033
60000
Area of steel, As = bd
= 0.00437 x 12 x 18.5
= 0.97 in2/ft
Choose #8 bars
Cross-sectional area = 0.79 in2 from Figure 200-13
Space bars at 0.79 x 12/0.97 = 9.77 in., say 10 inches o.c.
Therefore, a 22-inch thick footing is okay.
6.

Provide shrinkage and temperature reinforcement.


Ats = 0.0014 x 12 x 22 = 0.37 in2/ft/face
Choose #6 bars
Cross-sectional area = 0.44 in2
Space bars at 0.44 x 12/0.37 = 14.27 in., say 14 inches o.c. perpendicular to
flexular reinforcement on the bottom face.

234 Piles and Piled Foundations


The purpose of this discussion is to familiarize you with the materials and advantages and disadvantages of the different types of pile foundations. Pile foundation
design considerations are summarized. Model Specification CIV-MS-4841 is
included in the specification section of this manual. This specification describes the
materials, equipment, and requirements for piling installation.

Types of Piles
Load-bearing piles generally can be grouped into two categories; end-bearing piles
and friction piles.
End-bearing piles are those where loads are transmitted to the soil through the
surface area at the pile tip. Piles that are driven to bedrock are included in this category.
Friction piles transfer the foundation loads to the soil through shear on the surface
area along the length of the pile.

Chevron Corporation

200-37

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Depending upon the soil conditions at the site, end-bearing piles can develop additional capacity from friction and friction piles can develop added capacity from endbearing.

Pile Materials
Piles are available in different materials. Figure 200-4 illustrates the different types
and configurations of piles. The most common are:

Timber. Timber piles are cut from tree trunks and driven with the small end
down.

Composite. Composite piles are a combination of timber and concrete or steel.


Not as common as other types of piles because they are difficult to splice. Good
for light loads.

Concrete. Concrete piles are generally available in two types, (1) precast,
prestressed or nonprestressed and (2) cast-in-place.

Steel. Steel piles can come in a variety of shapes. The most common are pipe,
pipe filled with concrete, and steel HP-shapes.

Timber Piles
Advantages. Timber piles are generally readily available on short notice, are
economical and easy to handle, and their lengths can be easily altered or cut, and
permanently submerged piles are resistant to decay.
Disadvantages. Timber piles are difficult to obtain in long lengths: typical
maximum economic lengths are 60 feet. They are difficult if not impossible to
splice satisfactorily and hard to drive into or through hard formations because of
brooming of the fibers at the pile tip. Consequently, they are not suitable for end
bearing under heavy loads. Timber piles have shorter life than other materials unless
they are treated with wood preservative.

Concrete PilesPrecast Prestressed or Nonprestressed


Advantages. Precast prestressed or nonprestressed concrete piles are high strength
piles capable of carrying heavy loads and have a high resistance to chemical and
biological attack. If necessary, they can be formed with a pipe in the center to facilitate jetting (see Piling Installation below).
Disadvantages. The length of concrete is difficult to alter after they are manufactured. Long length concrete piles are difficult to handle and drive unless prestressed
because of their weight and the care that must be taken in handling to prevent
breakage. Concrete piles have relatively low tensile strength and often require a
long lead time for procurement.

Concrete PilesCast-in-Place with Shell


Advantages. The shell is easily handled and a great deal of flexibility in the length
of the piles is provided as the shells can be furnished in short lengths and assem-

June 1997

200-38

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

bled at the job site. Excess reinforcement to resist the handling and driving stresses
encountered with precast piles is eliminated and it is relatively easy and inexpensive to install additional piles.
Disadvantages. Very low tensile strength. If concrete not reinforced or under-reinforced, slight movement of the earth or uplift on the pile may cause breakage or
failure.

Steel Piles
Advantages. Non-displacement (open-ended pipe or HP-piles) steel piles are generally considered best for driving through debris or boulder fields. Steel piles are
easily spliced due to their weldability. Large diameter pipe and HP-piles, because of
their high strength, can be driven to depths in excess of 200 feet.
Disadvantages. Susceptible to corrosion unless protected by protective coating or
cathodic protection where oxygen or acids are present in the ground.

Composite PilesTimber and Concrete


Advantages. Lower total pile cost. Timber normally totally submerged and therefore, less susceptible to decay.
Disadvantages. Joining the two types of material is difficult. Joint prone to damage
during driving. Pile capacity is limited by the weaker of two component materials.

Pile Foundation Design


The focus of this section is to outline the steps that can be followed and the considerations involved in the design of piling and pile-supported foundations.
Initially, as with all foundation design, the design data must be assembled and the
loading criteria established. There are usually two primary reasons for choosing a
piled foundation:
1.

The bearing capacity of the near-surface soils for the anticipated loads is inadequate.

2.

Excessive or unacceptable, total and differential settlement is anticipated.

The soils report should provide recommendations of the foundation type for specific
items or pieces of equipment.

Selection of Pile Type


Selection of the type of piling to be used involves consideration of many factors.
These include:

Chevron Corporation

Type, size and weight of structure or piece of equipment

Physical properties of soil at site. For instance sand vs clay

Depth to supporting soil layer

200-39

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Possible variations in depth to the supporting soil (soil borings will help determine this). Concrete piles could be expensive if different lengths are required.

Availability of material for piles

Number of piles required

Comparative costs of different types in-place

Durability required

Height of water table. Corrosivity of soil.

It is not practical to make specific rules for the selection of pile type as the above
factors may occur in many combinations.

Pile Capacity
The geotechnical consultants soils report will provide recommendations for type of
pile, pile length, and pile capacity for both single pile and pile group.
The soils report will provide pile capacity curves for recommended types and sizes
of piles for the given site soil conditions. Capacity curves can be prepared for
compressive, tensile (uplift), and lateral loads on the piles. Typical pile capacity
curves are shown in Figure 200-21.
Compression. Compression capacity for friction piles increases with depth and
outer surface area of piles. Maximum capacity is not developed until a certain depth
is reached. Cohesive soils can create downdrag, or negative friction, which throws
additional load on the pile thus decreasing pile capacity.
Tension (Uplift). Uplift capacity for friction piles increases with increasing depth
and with outer surface area.
Lateral. Lateral capacity is limited by pile stresses or deflection of pile top which in
turn depend on the section modulus of the pile section. Deflection of pile top
depends on whether the pile is free to rotate (hinged) at the pile cap or restrained
(fixed).

Factors of Safety
Pile capacity curves are usually prepared with built-in factors of safety recommended by the soils consultant. In the absence of recommendations the following
factors of safety against the ultimate pile capacity are recommended for different
loading conditions.
Axial compression loads:
Minimum factor of safety of 2.0 (dead load plus operating load)
Axial tension (uplift) loads:
Minimum factor of safety of 3.0 (static loads)
Minimum factor of safety of 1.5 (short duration loads)

June 1997

200-40

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Fig. 200-21 Typical Pile Capacity Curves

Temporary, wind, or seismic loading:


Minimum factor of safety of 1.5

Pile Cap Design


After the pile type, lengths, and arrangement have been selected and designed, the
pile cap is then designed. The pile cap is designed in accordance with ACI 318 for
bending, shear, settlement, and stability. Stability refers to the stability of a group of
piles versus the stability of each single pile. Pile caps are most often designed as a
rigid foundation. Punching shear usually controls thickness.

Piling Equipment and Installation


Model Specification CIV-MS-4841 covers specific requirements for the equipment
and installation of foundation piles on land.

Chevron Corporation

200-41

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Pile Driving Evaluation


It is important to maintain driving records for each pile installed, including the pile
driving equipment. The pile driving record can be used to evaluate the in-place
capacity of the pile after it has been installed. Use of Standard Forms CIV-EF-627
and CIV-EF-629 is essential when installing piling.

235 Foundations for High-temperature Equipment


Special considerations should be taken when designing foundations for hightemperature equipment. When furnaces are mounted on concrete slabs at grade or
concrete slabs supported by piles, overheating of the slab and piles is a potential
problem. These high temperatures may extend to a significant depth. Similarly, high
temperatures in tanks may result in general heating of concrete slabs and piles. For
hot tank foundations, additional information may be found in the Tank Manual.

Concrete Slabs
Concrete shows a considerable loss in strength at high temperatures. It will lose
40% of its modulus of elasticity when heated to 500F. Therefore, floors of furnaces
at grade and slabs supporting hot tanks or stacks must be insulated or ventilated to
prevent excessively high temperatures in concrete foundations. For temperatures up
to about 400F, high quality ordinary concrete should be adequate. If the concrete is
exposed to higher temperatures, the above special design considerations are
required.

Timber Piles
If the foundation slab must be pile-supported, as is common at many refinery locations, the additional problem of overheating wood piles must be considered. Wood
will char if exposed to temperatures above 150F for prolonged periods. The
resulting damage to the timber piles may cause failure of the foundation.

Examples

June 1997

Piling under crude unit furnaces F-1 and F-2 at Salt Lake showed severe charring and reduction of cross-section at the butts as well as signs of delignification. This caused loads from the slab to be transmitted directly to the ground
and resulted in soil settlements up to 4-1/2 inches.

A similar problem developed with a pile-supported stack foundation at Richmond after several years, resulting in settling and tipping of the stack.

A 125,000-barrel residuum tank in Mobile, Alabama, was supported by 729


timber piles. The top 6 inches of the piles were cast into the concrete slab and,
thus, were directly in contact with temperatures as high as 212F, causing
serious charring type degradation and subsequent loss of compressive strength.
The pile sections from just below the charred top section down to 10 feet
suffered significant loss of strength due to being immersed in water heated
above 150F for extended periods of time. Fifty piles collapsed because of loss
in pile strength. The tank bottom developed a tear over 20 feet, dumping
100,000 barrels of residuum.

200-42

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Design Recommendations
Special consideration must be given to all pile supported furnaces, stacks and tanks
where the foundations may be subjected to temperatures above 150F. The
following alternatives should be considered:

Where soil conditions permit, use a mat foundation to avoid the use of piles.

Where piling is required:

a.

For small diameter tanks (i.e., diameters less than 30 feet) or stacks and
furnaces with similar areas, composite piles with 10 to 12 foot followers
may be used. The limiting area may be increased if it can be demonstrated
(through soil studies, heat transfer calculations, field measurements, experience, etc.) that timber piles will not be subjected to temperatures above
150F.

b.

For hot foundations with large areas, use only steel or concrete piles.
Timber piles should not be used under large hot tanks.

Avoid direct contact of piles with concrete when the temperature is greater than
400F.

236 Foundations for Vibrating Machinery


All stationary rotating or reciprocating machinery requires a foundation. These
include pumps, turbines, large fans, reciprocating compressors and rotary compressors. Foundations provide firm support for machines and serve to isolate them from
surrounding structures and to absorb or inhibit vibration. The design of machinery
foundations is complex and a knowledgeable civil engineer should be consulted.

Design Considerations
Several special design considerations should be given to the design of foundations
for vibrating machinery to improve the dynamic behavior of the foundation. Some
of the more important factors are:

Chevron Corporation

Use as large a foundation-soil contact area as practical, but the soil bearing
pressure should not exceed 50 percent of the allowable soil bearing for static
loads. For piled foundations, no reduction in allowable pile capacity is required.

The horizontal eccentricity, in the transverse direction, between the centroid of


the soil contact area and the center of gravity of the foundation plus machine
from a vertical plane through the centroid of the soil contact area, should not
exceed 0.05 times foundation width. See Figure 200-22.

The horizontal eccentricity, in the longitudinal direction, between the centroid


of the soil contact area and the center of gravity of the foundation plus machine
from a vertical plane through the centroid of the soil contact area, should not
exceed 0.1 times the foundation length. See Figure 200-22.

200-43

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Fig. 200-22 Vibrating Equipment FoundationsAllowable Eccentricities

Size the foundation block to minimize the mass moment of inertia of the
machine-foundation system about a horizontal axis through the centroid of the
soil contact area. This can be accomplished by using minimum pedestal height.

Foundations for vibrating machinery should be independent of adjacent foundations and buildings.

Multiple machinery foundations are sometimes unavoidable. Ideally each


vibrating machine should have its own independent foundation. When space is
limited or operating considerations dictate otherwise, several machines may be
installed on a common foundation. The Company has installed multiple
machines on a common mat with no known adverse effects. However, there is a
risk that future foundations could have vibration problems because eccentricities were not included in the design. Appendix A, Design of Foundations for
Vibrating Machinery, makes the following recommendations for multiple
engine foundations:

June 1997

a.

Use a common mat.

b.

Design the mat to be rigid.

c.

Compute the dynamic parameters for each pedestal as if they were not
connected by a common mat.

Design the foundation to resist unbalanced forces calculated in accordance with


guidelines in the Compressor Manual or the General Machinery Manual.

200-44

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Proportion the foundation to limit the allowable amplitude of vibration for any
point on the foundation to the smaller of the maximum value specified by the
machine manufacturer or that allowed by Appendix A of the manual.

For smaller machinery not subject to severe vibration, the following guidelines can
be used to select the foundation size:

Width of the foundation should exceed the width of the machine base by 12
inches.

Length of the foundation should exceed the length of the machine base by 12
inches.

Foundation depth should be selected to provide foundation weight not less than
4 times the machine weight including machine skid.

For detailed design, please refer to Appendix A of this manual, Design of Foundations for Vibrating Machinery.

237 Retaining Walls


Retaining Wall Types
The most common types of retaining walls were illustrated in Figure 200-5. They
are:

Gravity
Semigravity
Cantilever
Counterfort
Proprietary
(not illustrated)

Calculate Earth Pressures


The properties of the soil to be retained must be known to determine the magnitude
of the loads that a retaining wall or structure must be designed to resist.
In addition to vertical forces from the weight of the retaining wall and the backfill
material, lateral soil pressures exert loads on a retaining wall. There are two kinds of
lateral soil pressure: active and passive.
Active soil pressure is the pressure exerted by the soil against the wall caused by the
soils tendency to slip and seek its natural slope (angle of repose). Passive soil pressure is that pressure which develops in the soil in response to the wall moving
toward the soil mass.
Figure 200-23 shows how active and passive soil pressures are calculated.
In the absence of soil property data determined by the soils consultant, the ranges of
values in Figure 200-24 may be used for cohesive and cohesionless soils.

Chevron Corporation

200-45

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Fig. 200-23 Computation of Simple Active and Passive Pressures

Fig. 200-24 Properties of Cohesive and Cohesionless

Unit weight, pcf


Angle of internal friction, , degrees
Cohesion, psf

June 1997

200-46

Cohesive Soils

Cohesionless Soils

100 - 115

115 - 135

0 - 20

28 - 34

200 - 2000

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Design Procedure, Cantilever Walls


The following steps may be used to design a cantilever retaining wall. Refer to the
Figure 200-25 for principal terms used with retaining walls.
Fig. 200-25 Retaining Wall Terms

Chevron Corporation

Fig. 200-26 Tentative Design Dimensions for Cantilever


Retaining Wall

1.

Select tentative dimensions of retaining wall in accordance with guidelines


shown in Figure 200-26.

2.

Determine active soil pressure as shown in Figure 200-23.

3.

Determine passive soil pressure where appropriate. Passive resistance is often


disregarded in evaluating retaining wall stability on the assumption that the
backfill is already in place behind the wall prior to placement of the front fill.

4.

Find the vertical forces against the base.

5.

Calculate moments about the toe of the retaining wall of the vertical forces and
the active soil pressure.

6.

Calculate the location and eccentricity of the vertical force resultant on the
base. If the eccentricity, e, of the vertical force is less than B/6, the pressure
distribution is trapezoidal. If e is greater than B/6, the pressure distribution is
triangular.

7.

Calculate the maximum (at the toe) and minimum (at the heel) soil pressures
acting on the base of the foundation. To calculate these pressures take moments
of the vertical forces and active soil pressure about the toe of the retaining wall.
The maximum pressure should not exceed the allowable soil bearing pressure.

200-47

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

8.

Check stability of the retaining wall about the toe against overturning. The
factor of safety against overturning should be a minimum of 1.5 for cohesionless soils and 2.0 for cohesive soils.

9.

Check sliding resistance of the retaining wall. Sliding resistance is developed


by:
a.

Passive resistance of soil in front of wall

b.

Coefficient of friction between the base and the soil. The coefficient can be
taken as 0.55 for sands and gravels, 0.45 for silty sands and gravels, and
0.35 for silt.

c.

A shear key beneath the base of the wall.

The factor of safety against sliding should also be a minimum of 1.5 for cohesionless soils and 2.0 for cohesive soils.
References 3, 4, and 10 provide detailed design procedures for retaining walls.

238 Deadman Anchors


Deadman anchors are commonly used to anchor guys for stacks or towers. They are
also used to anchor tie rods for sheet piling anchorage. Deadman anchors are large
concrete blocks or beams buried beneath the ground surface. Standard Form CIVEF-336 shows typical details for guys and deadmen.
The capacity of concrete deadman anchors is developed from:

Weight of the concrete anchor block


Weight of soil above the anchor block
Net passive soil pressure

Concrete deadman anchors should be designed with a factor of safety of not less
than 2.0 against the working anchorage load.
Figure 200-27 shows a typical cross-section of a concrete deadman anchor.

Design Procedure, Deadman Anchors


The design procedure for deadman anchors is one of trial and error. Once the anchor
dimensions are selected and a burial depth established, it is not difficult to deter-

June 1997

200-48

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Fig. 200-27 Concrete Deadman Anchors

mine the capacity of the tentative design. Refer to Figures 200-23 and 200-28 for
identification of the following terms used in the deadman anchor design.
P

resultant of the maximum guy forces

Pv

vertical component of maximum guy force P

Ph

horizontal component of maximum guy force P

Wc =

weight of the concrete anchor block

Ws =

weight of the soil above the anchor block

Wt =

W c + Ws

width of concrete anchor block

height of concrete anchor block

length of concrete anchor block

unit weight of soil, pcf

buoyant unit weight of soil, pcf

Pp

passive soil pressure

Pa

active soil pressure

angle of internal friction

cohesion, psf

dimension from ground surface to bottom of anchor block

dimension from ground surface to top of anchor block

hwt =

Chevron Corporation

dimension from ground surface to top of water table

200-49

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

The resistance to vertical force is provided by the weight of the anchor block and
the weight of soil above the anchor block. Be sure to use total unit weights of the
soil and concrete above the water table and buoyant unit weights below the water
table.
The resistance to horizontal force is the net passive soil pressure acting on the face
of the concrete block. Determination of the net passive pressure acting on the
anchor should be done as shown earlier in Figure 200-23.
As in the design of retaining walls, the design and capacity of the deadman anchor
is heavily influenced by the properties of the backfill material surrounding the
anchor. Refer to Figure 200-24 for soil property values to be used in case actual
values are not available.

Example Problem, Deadman Anchor Design


Determine the adequacy of the concrete deadman anchor shown in Figure 200-28
for the given tension in the guys.
Fig. 200-28 Concrete Deadman Anchor Design Example Dimensions Designation

Given:
Soil Conditions:
= 30
C = 0 psf
= 110 pcf
Water table at 6 ft. depth (hwt = 6 ft)

June 1997

200-50

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Loads:
P = 65 k
Pv = 43 k
Ph = 48 k
Solution:
Try block with dimensions:
x = 8 ft
y = 7 ft
L = 10 ft
h = 2 ft
1.

Check resistance to vertical force (see Figure 200-29):


Wc (above water table) = 8 x 10 x 4 x 150 pcf = 48,000 lb
Wc (below water table) = 8 x 10 x 3 x (150 -62.4) = 21,000 lb
Wc = 69,000 lb
Ws = 8 x 10 x 2 x 110 pcf = 17,600 lb
Total weight Wt = Wc + Ws = 69,000 + 17,600 = 86,600 lb

2.

Check safety factors:


Wt/Pv = 86.6/43 = 2.0 2.0
Wc/Pv = 69/43 = 1.6
Therefore, the safety factor is okay.

3.

Check resistance to horizontal force:


From Figure 200-23, for = 30 and C = 0, the coefficient of passive soil pressure Kp = 3.0.
p (at z = 2) = KpZ = 3.0 x 110 pcf x 2 = 660 psf
p (at z = 6) = 3.0 x 110 pcf x 6 = 1980 psf
p (at z = H) = Kp [ (H - hwt) + hwt ]
= 3 [ (9 - 6)(110-62.4) + 6(110)]
= 2,408 psf
Pp = (.5 x 4)(660 + 1980)L + (.5 x 3)(1980 + 2,408) L
= 11,860 L

If L = 10,
Pp = 118,600 lb or 119 k
4.

Check safety factor:


Pp/Ph = 119/48 = 2.5 > 2.0
Therefore, the safety factor is okay.

Chevron Corporation

200-51

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Fig. 200-29 Concrete Deadman Anchor Design Example, Soil Pressures

240 Anchor Bolts


The purpose of this section is to identify the types of anchor bolts commonly available and to describe their applications in foundation design and construction.

Types and Uses of Anchor Bolts


The two types of anchor bolts readily available and commonly used are discussed
below.
Cast-in-place Anchors. The most desirable and strongest type of anchor bolt, castin-place anchors should be specified whenever possible for new construction. The
bolts are fabricated to ASTM A307 or A36 specifications and are set or placed in
the concrete forms, with or without reinforcement, prior to placing the concrete.
Post-installed Anchors. These anchors come in two types; expansion anchors and
epoxy anchors.
Expansion anchors are used most often to fasten equipment and structures to
existing concrete or masonry walls, slabs and columns; epoxy anchors can substitute for expansion anchors.

241 Cast-In-Place Anchor Bolts


Cast-in-place anchor bolts are shown on Standard Drawing GD-Q68922. This
section describes the design procedure and use of the standard drawing for the selection and layout of cast-in-place anchor bolts. An example illustrates the application
of the standard drawing.

Introduction
Anchor bolts embedded in concrete foundations should be placed and sized so that
the tension and shear capacities of an anchorage system are governed by the

June 1997

200-52

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

strength of the anchor bolts rather than by the strength of the concrete foundation.
This approach results in a ductile connection that prevents sudden failure by
allowing the anchor bolts to yield and gradually deform plastically before the
concrete approaches its tensile capacity and fails suddenly. Ductile behavior is
particularly important for connections designed to resist earthquake or other
dynamic loads.

Standard Drawing GD-Q68922


Standard Drawing GD-Q68922 lists allowable anchor bolt loads and placement
dimensions for various bolt diameters which are placed according to the two boltlayout cases shown.
Case A: Anchor bolts placed in concrete foundations where reinforcement is
parallel to the anchor bolt. In this case, loads are transferred from the bolt to the
main reinforcement of the foundation.
Case B: Anchor bolts are placed in concrete foundations where reinforcement is
perpendicular to the anchor bolt. In this case, bolt loads must be resisted by the
concrete strength alone. Concrete slabs, floors, and mat foundations are typical Case
B examples.
The standard drawings allowable loads are based on ASTM A-307 or A 36 bolts
and concrete with a specified compressive strength, fc of 3,000 psi.
High-strength bolts are not recommended because they require more embedment,
spacing, and edge distance than A307 or A36 bolts. The standard anchor bolt
drawing is not valid for high-strength bolts. See Appendix B for the design of highstrength bolts.
The embedment length, edge distance, and bolt spacing listed on Standard Drawing
GD-Q68922 are as follows:
L

12d

6d

13d for d < 1"

16d for 1" d < 2"

The bolt embedment length of twelve times the bolt diameter was used because
(with the edge distance and bolt spacing shown on the standard drawing) the resistance to concrete failure increases very little with embedment depths beyond twelve
bolt diameters. The edge distance of six times the bolt diameter is from the Uniform
Building Code and will also meet the minimum edge distance needed to prevent
lateral bursting failure (blowout) at the bolt head. The bolt spacing used is that
needed to meet the required safety factors listed in Appendix B, given the edge
distance and embedment lengths shown on the standard drawing.
The tension capacities with parallel reinforcing and the allowable shear loads were
determined according to the AISC Specification for Structural Steel Buildings (1989
Edition), using the tensile stress area for tension and the root area for shear instead
of the nominal area.

Chevron Corporation

200-53

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

The allowable shear loads for bolts larger than 1" diameter were limited by the
concrete properties and were determined using the safety factor listed in
Appendix B and the edge distance and bolt spacing listed on the standard drawing.
The tension capacities for corner bolts and bolts without parallel reinforcing were
based on concrete failure using the embedment depth, edge distance, and bolt
spacing listed on the standard drawing. The factor of safety against concrete failure
is that required for a ductile connection as listed in Appendix B.
There are two graphs shown on the standard drawing:
1.

An interaction graph (Figure 1) is given for a concrete failure or a combination


concrete-and-bolt failure. This graph applies in all cases with the allowable
forces shown on the standard drawing. Load combinations which fall within the
curve are acceptable.

2.

A concrete strength adjustment graph (Figure 2) is given for concrete compressive strengths other than 3,000 psi. For the corner, and tension with Case B
reinforcement values, this scaling graph is used by simply multiplying the
allowable load values by the factor corresponding to the specified design
concrete compressive strength. Since the allowable loads for the tension with
parallel reinforcing and most of the shear values are based upon the steel
strength of the bolt, these values cannot be increased beyond those shown on
the standard drawing. They can, however, be decreased for concrete strengths
below 3000 psi.

The required reinforcement for the tension capacity with parallel reinforcing and the
corner bolt values can be omitted by increasing PCR, the strength of the tension
failure cone. The easiest way to satisfy this is to increase the edge distance. Therefore, if the edge distance used is 1/3 greater than that listed on the standard drawing,
parallel reinforcing is not needed when using the tension capacity with parallel
reinforcing and the corner bolt values. For example, with a 1" diameter bolt, if the
edge distance (E) is greater than 8", then the allowable loads of 12,100 lbs and
8,400 lbs may be used without the parallel reinforcing typically required for the
tension with parallel reinforcing and the corner bolt values.
Anchor bolt sleeves may be used for anchor bolts greater than 5/8 inch diameter to
allow for minor adjustment by bending. After installation, the sleeves are filled with
grout, except in the case of vibrating equipment. The sleeves for vibrating equipment are filled with a pliable material other than grout. See Specification MAC-MS3907, Grouting of Machinery, for specific recommendations about fill material.

Anchor Bolt Nomenclature


The terms below appear on the standard drawing, within the text, or in Appendix B,
and are defined as follows:
ABT

Tensile stress area of bolt (in2)

0.7854 (d-0.9743/N)2

where:

June 1997

200-54

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

nominal bolt diameter (in)

number of threads per inch

ASR

total area of reinforcing steel (in2)

distance between two bolts measured from center of the bolts (in)

distance to concrete edge measured from the center of the bolt (in)

embedment length of the bolt (in)

design tensile load on the bolt (lbs)

PA

allowable bolt tension - lesser of PB or


PCR/2.7 (ductile connection) or
PCR/4.0 (non-ductile connection) (lbs)

PB

allowable bolt capacity in tension based upon the steel properties of


the bolt (lbs)

PBY

bolt yield capacity (lbs)

PCR =

tensile capacity of the concrete cone reduced for spacing and edge
interference (lbs)

PE

ultimate strength of the epoxy bond (lbs)

design shear load on the bolt (lbs)

VA

allowable bolt shear, lesser of VB or VCR/1.9 (lbs)

VB

allowable bolt capacity in shear based upon the steel properties of the
bolt (lbs)

VCR =

shear capacity of the concrete reduced for spacing and edge interference (lbs)

db

nominal diameter of the reinforcing steel (in)

fc

specified compressive strength of the concrete (psi)

short dimension of the hexagonal head or bottom plate of the bolt (in)

ld

development length required for the anchor bolt reinforcing steel (in)

distance from the parallel reinforcing steel to the bolt center (in)

Design Procedure, Cast-in-Place Anchor Bolts


The design procedure outlined below describes the steps to follow in selecting and
placing standard A307 or A36 anchor bolts in concrete foundations. This general
procedure applies to cases covered by the standard drawing but not to alternatives
and special conditions for different embedment lengths, bolt spacings, and edge
distances.
Restrictions limiting the placement of the anchor bolts may apply to certain installations. The interference from bolts spaced close together or placed close to the
concrete edge will prevent the full development of the tension and/or shear failure
cones in the concrete. This decreases tension and/or shear capacities of concrete.
The loss in capacity can be compensated for by increasing the bolt embedment
length, edge distance, or spacing. Refer to Appendix B of this manual for the discussion of special conditions.

Chevron Corporation

200-55

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

For anchor bolts, five basic design steps must be followed: 1) determine the loads;
2) select anchor bolt size; 3) check shear and tension interaction; 4) check bolt
spacing, edge distance and embedment length; and 5) select final reinforcement.
These steps follow.
1.

Determine the loads.


A design should begin by determining the loads to be placed on the anchor
bolts and the limitations on physical placement.
The anchor bolt load depends on the type of structure and the structural framing
system, the magnitude of the applied loads, the number of anchor bolts, and the
anchor bolt pattern.
Anchor bolt loads should be determined by applying the appropriate analysis
technique, computer program, or other recognized method.

2.

Select anchor bolt size.


Assuming that edge distance, bolt spacing, and embedment depth can be met, a
bolt is selected by referring to Standard Drawing GD-Q68922. The allowable
bolt loads are compared to the design loads. If loading is from earthquake or
wind, allowable bolt loads may be increased by 33 percent.
Bolt capacities are listed only for standard A307-or A36-type bolts with American standard hexagon heads.

3.

Check shear and tension interaction.


When tension and shear loads are present and act simultaneously on an anchor
bolt, the bolt tensile and shear capacities must be reevaluated by referring to the
interaction chart on Standard Drawing GD-Q68922. Values within the curve are
OK.
The interaction chart is based on the formula from the Uniform Building Code
(UBC) and is listed below:
P 5/3 V 5/3
-----+ ------- 1.0
P
V
A

(Eq. 200-21)

A larger bolt size is needed if this interaction equation cannot be satisfied.


4.

Check bolt spacing, edge distance and embedment length.


Bolt Spacing. The bolt spacing of the structures base plates and foundation
should be compared to the allowable spacing given on the standard drawing.
If bolt spacing requirements cannot be met, the anchors should be reconfigured
by using fewer bolts of larger size.

June 1997

200-56

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Edge Distance. For the selected bolt diameter, the edge distance given by the
foundation design should be compared to the minimum edge distance allowed
by the standard drawing.
Embedment Length. The available embedment length allowed by the foundation design should be determined and compared to the required embedment
length for the selected anchor bolt. Anchor bolt embedment cannot be reduced
where the full capacity of the anchor bolt is required.
If the foundation size cannot be increased to meet the spacing, edge distance, or
embedment requirements, additional design steps are required. See Appendix B
for these design concepts.
5.

Select final reinforcement.


Where reinforcing steel is required parallel to the bolt, the reinforcement must
be developed on both sides of the failure surface. The parallel reinforcing steel
selected for the anchor bolt should be compared to the amount required for the
design of the pedestal. These requirements are not additive, and the larger of
the two requirements controls.
The reinforcing steel needed for the anchor bolt must be spaced evenly. If, for
example, the required reinforcement for the anchor bolt is two #4 bars, and one
#8 bar is already provided from the pedestal design, one #4 bar must still be
placed 180 from the #8 bar at the same distance from the bolt. In practice,
however, it is easier to ignore the contribution of the required pedestal reinforcement and simply add the additional steel required for the bolt.
Development lengths, based on ACI 318-89, are shown on the standard
drawing. The assumed failure surface is a cone which radiates toward the
surface from the anchor bolt head at a 45 angle. A guide for the required reinforcement would be to provide an area of steel equal to the area of the bolt.
Reinforcement should be evenly distributed around the bolt and no more than
five bolt diameters or six inches, whichever is less, from the bolt center. The
minimum clear spacing between the parallel reinforcing and the bolt should be
one inch or the bolt diameter (d), whichever is greater.
Reinforcing steel perpendicular to the bolt should be placed where the edge
distance is less than the embedment length. This reinforcing steel should
consist of continuous spirals of 3/8-inch (minimum) diameter bars with a pitch
of 6 inches (maximum), or closed hoops of #4 bars (minimum) spaced at six
inches starting two inches from the surface of the concrete and continuing to
the embedment length of the bolt.

Anchor Bolt Pretensioning


Pretentioning of anchor bolts installed on certain equipment could enhance the
performance of the bolt or the performance of the system. The recommended
pretension load is one-third the tensile strength of the bolt. Anchor bolts may need
to be re-tightened a week after the initial pretensioning to compensate for pre-load
losses from strain relaxation within the system.

Chevron Corporation

200-57

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Pretensioning of anchor bolts installed on the following equipment is recommended:

Process towers over 100 feet tall or with a height-to-diameter ratio of 15 or


more which are sensitive to lateral deflection due to wind.

Reciprocating compressors or other pulsating or vibrating equipment.

Anchor bolts which are subjected to high thermal variance should not be pretensioned since they are susceptible to failure due to fatigue.
Method of pretensioning. The following methods of bolt pretensioning may be
utilized:
Hydraulic Jacking. This is the most accurate method and is recommended if field
condition permit its use.
Turn-of-nut. This method is the easiest to perform and provides reasonable accuracy.
Calibrated Torque Wrench. This method provides only a rough measure of the
actual pretension load.

Example Problem: Cast-in-Place Anchor Bolts


Determine the anchor bolt diameter and the placement dimensions required to
anchor the stacked exchangers to a reinforced concrete pedestal. Assume the
number of anchor bolts is fixed.
The stacked exchangers and pedestal are shown in Figures 200-30 and 200-31.
Fig. 200-30 Anchor Bolt Design Example

June 1997

200-58

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Fig. 200-31 Anchor Bolt Design Example, Sections

Anchor bolt design


Step 1
The loads shown below were found using the seismic design from Section 100 and
the structures geometry.
Loads on Bolts
N-S Loads
Shear/Bolt (V)

= 3,670 lbs

Tension/Bolt (P)

= 0 lbs

E-W Loads (Simultaneous Loads)


Shear/Bolt (V)

= 1,840 lbs

Tension/Bolt (P)

= 10,400 lbs

Step 2
Since the loads are seismic, the values on the standard anchor bolt drawing may be
increased by one third. Try 1" diameter bolt.
10,400 lbs < 1.33 PA = 1.33 x 8,400 = 11,170 lbs
3,670 lbs < 1.33 VA = 1.33 x 5,500 = 7,320 lbs
OK
Step 3
The E-W loads are simultaneous and must be checked for combined loading.

Chevron Corporation

200-59

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

10 ,400
P
----------------- = ---------------- = 0.93
11 ,170
1.33P A
1 ,840
V
------------------ = ------------- = 0.25
7 ,320
1.33V A
Locating this point on the interaction graph (Figure 1) reveals that it is on the curve.
Therefore, verify interaction numerically
(0.93)5/3 + (0.25)5/3 = 0.99 < 1.0 OK
Step 4
E given =

7"

6"

B given =

18"

16"

OK

It is assumed here that the pedestals height and foundation thickness are more than
adequate for a 12" bolt embedment.
Step 5
Reinforcement:
The standard drawing requires parallel reinforcing for corner bolts. However, as
stated earlier in this chapter, the reinforcement can be omitted if the edge distance
used is one third greater than that listed on the standard drawing. The edge distance
needed for omitting parallel reinforcement is 8". For this example problem, the edge
distance will not be increased and reinforcing steel will be added. However, in most
situations, increasing the edge distance will be preferred.
a.

Parallel
Area of bolt = 0.606 in2
The pedestals reinforcing bars (seven #5s) are not within five bolt diameters of the bolt; therefore, they cannot be counted in providing reinforcement for the bolt.

Try three reinforcing bars:


0.606
A SR bar = ------------- = 0.202 in 2
3
Try three #4 bars:
A SR bar = 0.20 in 2 = 0.202 in 2 OK
From geometry, the minimum distance to the bolt center is
h db
1" + --- + ----- = 2.00". The maximum distance to the bolt center is five bolt
2 2
diameters = 5 * 1" = 5". Place bars at a four inch radius (r) to the bolt
center.
Check development.

June 1997

200-60

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

From the standard drawing, the development length needed is 17" for a
straight bar. The reinforcing bar needs to be developed on both sides of the
failure surface. From geometry, this works out to be:
ld + (r-h/2) = 20.3" above the bolt head
and
ld - (r-h/2) = 13.7" below the bolt head
Values for h used in the above equations can be found in Appendix B of
this manual. Since 20.3" is greater than the 12" bolt embedment length
minus the 2" cover (L - Cover = 10"), try a hooked #4 bar.
From the standard drawing, the development length needed for a hooked
#4 bar is 8". The distance above the bolt head using a hooked bar needs to
be:
8 + (4 - 1.5/2) = 11.3"
Since 11.3" is still greater than 10", increase the bolt embedment length by
2" to 14" total.
Therefore, the parallel reinforcing should be extended at least 12 inches
above and 14 inches below the bolt head.
b.

Perpendicular
The perpendicular reinforcement used must satisfy both that shown for
case A on the standard drawing and that shown on CIV-EF-518, Foundations for Horizontal Equipment.
Therefore, use #4 bar ties in closed hoops with a spacing of three inches
for the first space and six inches for other spaces up to just past the bolt
embedment. The final design is shown in Figure 200-32.

Fig. 200-32 Final Design Example of Cast-in-place Anchor Bolts

Chevron Corporation

200-61

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

242 Post-installed Anchors


Expansion Anchor Bolts
Expansion concrete anchors are shown on Standard Drawing GD-Q99998. They are
made of high-strength steel and placed in a predrilled hole. Anchors have an expansion mechanism that contacts the holes walls upon tightening the bolt and that
creates a frictional resistance to pullout.
Failure Modes. The following failure modes can occur in expansion anchors:
1.

Brittle concrete cone failure: Insufficient embedment or edge distance.

2.

Concrete splitting: Placed too close together or near an edge.

3.

Bolt breakage.

4.

Bolt slip: Insufficient frictional resistance.

Failure modes 1-3 above are similar to cast-in-place anchor bolt failure modes. For
additional information about them, see Appendix B.
Since expansion anchors are made of high-strength steel, bolt breakage is not typical
and the resulting failure mode is brittle with little ductility. Seismic loading, therefore, should be limited to primarily shear loads by requiring the tension load to
allowable load ratio be less than 25% of the total tension and shear interaction ratio.
Usage. In new work, cast-in-place anchor bolts should be specified. An exception
might be made for floor slabs requiring a large number of anchors for equipment. In
this case, loads are usually nominal, mostly in shear; and the advantage of placing
and finishing the floor slab without anchor bolts may outweigh the disadvantages of
using expansion anchors.
If expansion anchors must be used, mounting should be designed wherever feasible
to accommodate shear rather than tension.
Expansion anchors are not recommended for brick or concrete building blocks.
Wherever possible, such anchorages should be through-drilled with a large washer
or metal plate on the back face. If expansion anchors must be used, 20% of the
allowable loads shown for concrete should be taken as the design basis.
As mentioned previously, expansion anchors may be used only in special cases to
resist seismic loads.
Installation. Expansion anchors must be specified and installed with discretion
because their holding power depends upon the care with which the bolts are
installed. As shallow or oversized holes weaken the grip of the bolt, installation for
a specified holding power should be inspected carefully.

June 1997

200-62

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Standard Drawing: Expansion Concrete Anchors. The following seven types of


expansion concrete anchors are represented on the standard drawing:
1.

ITW Ramset/Red Head Trubolt Wedge Anchor, by Phillips Drill Company

2.

Wej-it Wedge Anchors, by Wej-it Expansion Products, Inc.

3.

Wej-it Ankr-Tite Stud Anchor, by Wej-it Expansion Products, Inc.

4.

Wej-it Sleeve Anchor, by Wej-it Expansion Products, Inc.

5.

Molly Parabolt, by Emhart Fastening System Group

6.

Hilti HSL Metric Heavy-Duty Expansion Anchor, by Hilti, Inc.

7.

Hilti Kwik-Bolt II Expansion Anchor, by Hilti, Inc.

Allowable loads in concrete for all seven types of expansion anchor bolts are shown
on Standard Drawing GD-Q99998. They are based upon ICBO test reports. Other
manufactures may be used if they have been evaluated by ICBO.
The recommended edge distance of six bolt diameters may be insufficient for bolts
loaded in shear towards an edge. For this loading case, therefore, the edge distance
should be increased to 8 bolt diameters for the loads shown on Standard Drawing
GD-Q99998.
If loads higher than those shown on the standard drawing are used, per the applicable ICBO report, the allowable shear should be checked with the methodology of
Appendix B.

Adhesive Anchor Bolts


Adhesive anchor bolts are attached to the concrete by a very strong adhesive.
Hilti HVA and Parabond Capsule Anchors are two-part systems composed of a
threaded rod stud and a sealed glass capsule. The capsule contains a pre-measured
amount of adhesive resin with the hardener and aggregate in separate vials.
The threaded rod may be manufactured from standard or high-strength steel.
In conventional mechanical-wedge anchors, the load is transferred to the concrete
through little more than a point contact; whereas, with capsule anchors, the load is
distributed along the entire length of the embedment.
Failure Modes. The following failure modes can occur in adhesive anchors:

Chevron Corporation

1.

Bond breakage: Occurs in bolts with deep embedments, at elevated temperatures, or in conjunction with a concrete cone failure.

2.

Concrete cone failure: Concrete fails suddenly in the shape of a cone. Unlike
cast-in-place anchor bolts or expansion anchor bolts, however, the failure cone
may start somewhere along the anchors length and can be a combination
concrete-cone-and-bond failure.

200-63

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

3.

Concrete splitting: Occurs more frequently when bolts are spaced closer
together, or near an edge.

4.

Bolt breakage: Occurs typically with low-strength bolts which have deep
embedment.

When using standard steel rods and deeper embedments, epoxy anchors may have
sufficient reserve strength to develop the ductility required for seismic loading. For
bolts to resist seismic tension loads, the anchors must meet a required safety factor
of
PE
--------- 2.3
P BY
(Eq. 200-22)

PE is the ultimate load resisted by the epoxy bond. PBY is the bolt yield strength.
For A307 bolts, PBY = 33,000 ABT (lbs).
Usage. An acceptable alternative to expansion concrete anchors, adhesive capsule
and cartridge system anchors are non-expanding chemical anchors that have demonstrated greater load-carrying capacity than the more conventional mechanical
fasteners.
Capsule anchors should neither support fire-resistant construction nor resist pullout
(tensile) forces in walls or overhead installations. The capsule anchors temperaturesensitive epoxy could fail during fires when temperatures reach 170F.
As described earlier, adhesive anchors may be used to resist seismic tension loads if
the required safety factors are met.
Hilti, Inc. and Emhart Fastening Systems Group both manufacture adhesive
cartridge systems which are more economical when installing a large number of
anchors at once. Note that, with these systems, the allowable tension values shown
on Standard Drawing GD-Q99998 should be reduced by 1/3. If these systems are to
be used to resist seismic tension loads, they must satisfy Equation 200-22 using a
safety factor of 3.6 instead of 2.3. The increased factor of safety is a result of the
decreased reliability of these systems.
Installation. To install these systems, a drill bit sized for the capsules diameter
is selected and a hole drilled in the concrete to a depth equal to the length of the
capsule. Any concrete dust and fragments are removed by using compressed air and
a nylon brush. A capsule of appropriate diameter is inserted into the hole. The
pointed end of the threaded rod is rotary-hammer drilled into the capsule, breaking
it and mixing the adhesive resin and hardener.
Standard Drawing: Epoxy Capsule Anchors. Allowable loads for the epoxy
capsule anchors are shown on Standard Drawing GD-Q99998. They are based upon
ICBO reports.
As with expansion bolts, the edge distance should be increased to 8 bolt diameters
for bolts loaded in shear towards an edge.

June 1997

200-64

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

250 Concrete and Grouting


251 Concrete Mix Selection
Introduction
Model Specification CIV-MS-850 details the requirements for materials, proportioning, mixing, placing, finishing and testing concrete. Company practice, when
requesting construction of concrete, is to specify the type and strength of the
concrete desired and to hold the contractor responsible for following the specifications for placing the specified concrete. This section provides information that will
aid in selecting and specifying the desired concrete properties.
Concrete is a three-part mixture, primarily of cement, aggregates, and water.
Concrete also contains some amount of entrapped air. Admixtures may be included
for specific purposes. (See descriptions of aggregates and admixtures in subsequent
paragraphs.)
The cement and water are mixed to make a paste that, when mixed with the aggregate, binds the aggregate into a rocklike mass as the paste hardens by the chemical
reaction of the cement and water.

Cement Types
There are eight types of cement available to mix concrete. Each type, defined by
ASTM, meets different physical and chemical requirements for specific purposes:
Type I

Normal

Type IA

Normal, air-entraining

Type II

Moderate, sulfate-resisting, lower-than-normal heat of hydration

Type IIA Moderate, sulfate-resisting, lower- than- normal heat of hydration,


air-entraining
Type III

High early strength Type IIIA


High early strength, air-entraining

Type IV

Very low heat of hydration

Type V

Sulfate-resisting

Type I cement is used for general concrete construction where no special properties
are required. Type I cement is often not available. Type II cement is usually
provided in lieu of Type I.
Type II cement should be used for general concrete construction, exposed to
moderate sulfate attack from contact with groundwater or flowing water. Type II is
often used in drainage structures such as separators, sumps, and drainage channels.
It has a moderate heat of hydration and, therefore, can be used in moderately large
structures such as piers or heavy retaining walls. Also, the moderate heat of hydration reduces the internal temperature rise of the concrete during placing, which is an
important consideration in warm weather.

Chevron Corporation

200-65

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Type III cement is used for concrete construction when high early strength is
desired. Concrete mixed with Type III cement gains high strength within a week or
less. High early strength concrete is commonly used when the formwork must be
removed as soon as possible or when a structure must be put into service quickly.
Because it cures rapidly, care must be exercised when mixing and placing this type
of concrete.
Type IV cement gains strength more slowly than Type I and is characterized by a
low heat of hydration, making concrete mixed with this cement especially suitable
for massive structures such as dams.
Type V is a sulfate-resisting cement restricted to concrete that will be exposed to
severe sulfate attack, such as is found when the soil groundwater has high sulfate
concentrations.
Other cement types are also available for special purposes.

Aggregate Materials
Coarse and fine aggregates comprise approximately 60 to 80 percent of concrete
volume. Gravel and crushed stones account for nearly all coarse aggregate materials. Minerals, which are products of weathered rocks (such as sand, silt, and clay),
are the compositions of most fine aggregates. The quality of aggregates should
conform to ACI and ASTM requirements.
The location and size of the job and the availability of aggregate materials will
determine the aggregates selected for concrete mixes.

Mixing Water
Nearly any natural water that is drinkable and has no pronounced taste or odor can
be the mixing water for making concrete.

Admixtures
Admixtures are ingredients in concrete added to improve the inherent properties of
the concrete or to impart particular properties. They are other than cement, water,
and aggregates and are added to the mixture just before or during mixing. Admixtures can be classified by function as follows:

Air-entraining admixtures
Water-reducing admixtures
Retarding admixtures
Accelerating admixtures
Pozzolans
Workability agents
Miscellaneous agents, such as bonding, damp-proofing, permeability-reducing,
and gas-forming

Concrete can exhibit the qualities specified above more easily and economically by
adding suitable materials rather than relying on admixtures, except for air-entraining
admixtures.

June 1997

200-66

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Air-Entraining Admixtures. Air-entraining admixtures suspend air bubbles in


concrete. The entrained air dramatically improves the durability of concrete exposed
to moisture and to freezing and thawing cycles. It also improves the workability of
fresh concrete and reduces segregation and bleeding.
Air-entrained concrete should be specified for all concrete that is subject to freezing
and thawing cycles, or to the application of salt for the removal of snow and ice. Air
entrainment can be achieved by air-entrainment cements (Types IA, IIA, IIIA), or
by air-entraining admixtures.
Water-Reducing Admixtures. A water-reducing admixture reduces the amount of
water required to produce concrete of a given consistency. It can also retard the
setting time of the concrete mix. Provided the cement content and slump are
unchanged, a water-reducing admixture will generally increase the strength;
however, it will also increase drying shrinkage.
Retarding Admixtures. Retarding admixtures slow the rate of setting concrete.
Retarders (1) offset the accelerating effect of hot weather on the concretes setting
time or (2) delay the initial set of concrete or grout for difficult or unusual placement. Most retarders also act as water-reducing agents.
Accelerating Admixtures. An accelerating admixture speeds up the development
of the concrete strength at an early age. Most accelerators also increase the drying
shrinkage of the concrete. Calcium chloride should not be used as an admixture.
Pozzolans. Pozzolans are most often used as admixtures to improve the workability
and plasticity of concrete mixes. Some natural pozzolan materials also reduce
internal mix temperatures, and aggregate alkali expansion while providing sulfate
resistance. Fly ash is a popular, artificial workability agent.
Workability Agents. Entrained air is the best workability agent. Natural pozzolans
and fly ash are also used as workability agents.
Miscellaneous Agents. Damp-proofing and permeability reducing agents can
reduce the permeability of concrete with low cement content, high water-cement
ratio, or low fine-aggregate content. In well-proportioned mixes, however, they may
increase the mixing water required, resulting in increased permeability.
Bonding admixtures are added to concrete or applied to the surface of old concrete
to increase the bond strength between old and new concrete.
Aluminum powder and other gas-forming materials are sometimes added to
concrete or grout in very small quantities to cause slight expansion of the mix prior
to hardening. This can be beneficial when grouting in confined areas, such as
beneath equipment bases.

Proportioning of Concrete Mixes


The objective in designing a concrete mix is to determine the most economical and
practical combination of materials to produce a concrete that will meet the requirements of its intended service.

Chevron Corporation

200-67

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Model Specification CIV-MS-850 specifies Company requirements for proportioning, mixing, placing, and testing concrete. References 1 and 2 provide comprehensive procedures for determining concrete mix proportions.
Concrete proportions must be selected to provide necessary workability, consistency, strength, durability, and density for the anticipated service use of the finished
concrete.
Workability is the property that determines the ease with which fresh concrete mix
can be placed, consolidated, and finished without segregation.
Consistency is the wetness of the concrete mixture. Consistency is measured in
terms of the concrete slump.
Concrete compressive strength is the universal measure of concrete quality. Durability and impermeability may, however, be equally important. Concrete strength
depends upon the water-cement ratio of the mix.
The durability of concrete is its ability to resist weathering action, chemical attack,
or any other exposure that may adversely affect its serviceability. Five common
causes of concrete deterioration are

Freezing and thawing


Aggressive chemical exposure
Abrasion
Corrosion of steel or other embedded items
Chemical reaction of the aggregates

Freezing and Thawing. Deterioration of concrete by freezing and thawing is the


result of a physical action not a chemical reaction. Freeze-thaw deterioration of
concrete can be reduced by:

Minimizing exposure of concrete to water or moisture


Establishing low water-cement ratios; not less than 0.45-0.50
Using air entrainment
Using suitable materials for concrete mix
Requiring proper curing and construction practices

Aggressive Chemical Exposure. Deterioration of concrete by chemical exposure


can be divided into two primary categories: sulfate attack or acid attack. Sulfate
attack results from concrete exposure to sulfates in soil or groundwater. Cooling
tower water is a common cause of sulfate attack: there is a gradual buildup of
sulfates from water evaporating from exposed concrete faces. Acid attack often
requires special protection. Concrete can tolerate weak acids, but strong acids
require acid brick paving or special coatings to maintain the concretes integrity.
Concretes resistance to deterioration from chemical attack is increased by:

June 1997

Dense, high-quality concrete


Low water-cement ratio
Air entrainment (also reduces water-cement ratio)

200-68

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Portland cement with sulfate resistance (Types II and V)


Pozzolans

Abrasion. Deterioration of concrete by abrasion is most prevalent in hydraulic


structures or on the floors of industrial buildings. A high-quality, high-strength
concrete is necessary to increase resistance to abrasion. In some extreme cases, a
very hard aggregate must be specified.
Corrosion of Reinforcement or Other Embedded Items. This corrosion is due to
exposure of the reinforcement to water, deicing salts, etc. It can be minimized by
providing ample concrete cover for the reinforcement. Low-permeable, air-entrained
concrete will also assure concrete durability.
Chemical Reaction of Aggregates. Certain aggregates react with Portland cement
when mixed, causing expansion and deterioration of the aggregate and concrete.
This deterioration can be prevented by selecting the proper aggregate. Low-alkali
cement and pozzolans will reduce reactions with the aggregate.
Repair of concrete deterioration is covered in Section 260 (Concrete Repair) of this
manual. ACI Committee Report 211 provides a thorough discussion of the causes
and cures for concrete deterioration.

Concrete Testing
Concrete testing is an indispensable part of the construction process for concrete
placement.
The number and frequency of tests depends upon the job specifications and the
occurrence of variations in the test results. The following types of quality control
tests are commonly made at the job site for all fresh concrete:
Consistency
Air content
Strength
The Building Code Requirements for Reinforced Concrete (ACI-318) specifies that
samples for strength tests of each class of concrete placed should be taken:

Not less than once a day


Not less than once for each 150 cubic yards of concrete
Not less than once for each 5000 square feet of surface area

Concrete compressive strength tests are made on standard test cylinder specimens,
measuring 6 inches in diameter by 12 inches high. Usually three or more specimens
are tested for each test age. Compressive strength tests are usually tested after 7 and
28 days of curing. High early strength concrete specimens are often tested after 1, 3,
7, and 28 days. ASTM Specifications C31 and C192 give requirements for making
and curing concrete test specimens in the field and in the laboratory.
Consistency tests are performed on mix samples from which strength test cylinders
are made. The air content and temperature of the concrete should be measured and
recorded for each sample.

Chevron Corporation

200-69

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

The slump test and ball-penetration test are the two most common tests for the
consistency of concrete. The slump test is made by measuring the subsidence, in
inches, of a concrete pile 12 inches high, formed in a mold that has the shape of the
frustum of a cone. The ball penetration test is made by measuring the settlement of a
six-inch steel ball, weighing 30 pounds, into the concrete surface. The results of the
ball penetration test can be calibrated to relate directly to slump.
Refer to Model Specification CIV-MS-850 for further testing requirements.

Special Types of Concrete


There are numerous types of special concrete: those with out-of-the-ordinary properties or those produced by unusual techniques and made with or without cement.
The most widely used are fiber-reinforced concrete and shotcrete.
Fiber Reinforced. Fiber-reinforced concrete contains fine or fine and coarse aggregate and discontinuous discrete fibers. The fibers are produced from steel, plastic,
glass, and other natural materials.
Fiber-reinforced concrete, with and without normal reinforcement, makes pavements, overlays, hydraulic structures, slabs in tank bottom replacement, and rock
slope stabilization. Steel fiber is most widespread. The significant advantage of
fiber-reinforced concrete is the increased first crack flexural strength.
Shotcrete. Shotcrete is a process of applying mortar or concrete pneumatically to a
surface. Shotcreting is classified according to the process: dry-mix or wet-mix, and
to the type of aggregate: coarse or fine.
Shotcrete can be more cost effective than conventional concrete in several applications, where:

Formwork is impractical or can be reduced or eliminated.


Access to the work area is difficult.
Thin layers and/or variable thicknesses are required.
Normal casting techniques cannot be used.
Concrete bond is important.

Conventional shotcrete uses cement, aggregates, and ordinary admixtures for applications in new structures, linings and coatings, and concrete repair.
Refractory shotcrete uses high-temperature binders and refractory aggregates for
new installations, repair, and maintenance of all types of linings.
Special shotcretes use proprietary combinations of binder and aggregate for corrosion- and chemical-resistant applications. See Section 700 for more information on
shotcrete applications.

252 Grouting
The purpose of this section is to identify and describe the different types of grouting
materials and their common uses. Grouting of structural column and beam base
plates is the primary focus of this section. Model Specification, CIV-MS-985

June 1997

200-70

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Grouting of Structures is included in the specifications section of this manual.


Epoxy and cement grouting of bases for heavy reciprocating machines, e.g.,
compressors, and other similar equipment is covered by Standard Specification
MAC-MS-3907, Grouting of Machinery.

Types of Grout

Non-shrink cement-based grout is preferred. The non-shrink capability is


important to transfer loads.

Sand-cement dry pack, susceptible to shrinkage is not as desirable as cementbased grouts, but is still commonly used.

Epoxy grout is expensive but very good where minimum shrinkage is desired.

Uses of Grout
The primary use of grout from a structural standpoint is to mortar base plates for
structural steel columns and beams. When a structure is erected, an allowance is
required for adjusting the level of the columns or beams. This is accomplished by
allowing approximately a one-inch gap between the top of a foundation and the
bottom of the base plate. Once the structure is leveled, the remaining air gap is filled
with grout. Filling this gap with grout ensures that there is a uniform bearing of the
column loads to the foundation.

Pressure Grouting
Pressure grouting is the process by which liquid grout is pumped into the voids of
soils and then hardens. Pressure grouting is used most often for one or both of the
following to:
1.

Improve the mechanical characteristics of the soil through consolidation.


Bearing capacity of the soil is increased which can be especially important
under concrete paving which could have heavy vehicle traffic (i.e., cranes).

2.

Decrease the permeability of the soil structure, referred to as waterproofing.

260 Concrete Repair


This section describes the types of damage and/or deterioration often experienced
with concrete structures and identifies the materials and methods of repair that are
used to restore the concrete.
Section 251 (Concrete Mix Selection) of this manual and ACI Committee Report
211 describe common causes of concrete deterioration and their prevention through
proper proportioning of concrete mixes.

Types of Concrete Damage or Deterioration


Common concrete problems requiring repairs are due to:

Chevron Corporation

Mechanical damage
Acid attack

200-71

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Excessive heat
Corrosion of reinforcement
Thermal expansion or contraction
Sulfate disintegration

The deterioration effects of these actions upon concrete are evident in these ways:
Popouts, which are caused by unsound coarse aggregate particles near the concrete
surface. Aggregate absorbs water, and the subsequent freeze-thaw cycles cause
pieces of concrete to break away from the surface. Rebar corrosion can also cause
popouts as the rust by-product has four times the volume of the original steel.
Honeycombing, which is a consequence of a cement mix with excessively coarse
aggregate, mortar leaking through the forms, very low slump concrete, and poor
vibration of concrete during placement. A honeycombed surface appears pitted or
full of cavities.
Abrasion, which results from water flowing over or against concrete surfaces.
Appearance is similar to honeycombing.
Cold joints defects, which are due to improper preparation of the concrete surface
before placing new concrete.
Concrete cracking, which is caused by a number of factors, such as drying
shrinkage cracks, resulting from:

Volume changes in the concrete during curing


Design errors
Poor construction practices
Rebar corrosion
Weathering
Overloading

Hairline cracks are to be expected in concrete to allow the reinforcing steel to work;
and, unless they are large, they need not be repaired.

Testing and Evaluation


The initial step in the repair of any concrete deterioration or damage is to evaluate
the cause, type, and extent of the concrete damage.
Determine the location and extent of the damage by any one or combination of the
following methods:
Visual Inspection. Most often this will show the location and extent of the damage.
Movement or propagation of surface cracks should be observed to determine if the
cracks are active or dormant. Signs of settlement should be identified and the condition of exposed surfaces determined. Finally, potential causes of distress (poor
drainage, expansive soils, or exposure to aggressive chemicals) should be identified.

June 1997

200-72

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

Non-destructive Testing Methods. NDT methods can be used in the evaluation:

Internal cracks can be located by tapping the concrete surface with a hammer or
dragging a steel chain along the surface. A hollow sound indicates unsound
concrete.

Ultrasonic testing and radiographic inspection can also be used to evaluate


internal defects in the concrete.

Reinforcing steel locators are available to determine the presence and/or location of any reinforcing steel.

Approximate existing concrete strength can be determined by an explosive,


gun-type tester such as the Schmidt Air Gun.

Concrete Core Tests. These can be used to conduct macroscopic analysis of causes
of deterioration or to determine approximate concrete strength. Petrography can be
used to conduct microscopic examination (ASTM C-856).
Review of construction drawings, concrete placement, and test data should also be
included in the evaluation process to identify possible deficiencies in the original
design. These deficiencies might be insufficient steel cover, inadequate concrete
strength, nonconventional construction details, and load underdesign.

Determine Need for Repair


The need for repair should be based on the judgment of experienced inspectors.
Repair is required if there has been a reduction in the strength, stiffness, or durability of the structure. The repair procedure may be selected to accomplish any one
of the following objectives:

Restore or increase concrete strength


Restore or increase stiffness
Improve functional appearance
Provide water tightness
Improve appearance of concrete surface
Improve durability
Prevent access of corrosive substrata or atmosphere to reinforcement
Renew confidence of structural integrity

Repair Materials
The materials for the repair must be selected in conjunction with choosing the repair
method. Four major factors dictate product selection:

Chevron Corporation

1.

Chemical exposure

2.

Compatibility with the substrate, i.e., coefficient of thermal expansion

3.

Application condition

4.

Type of exposure

200-73

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Common repair materials are listed and described below:


Elastic Sealants. These materials maintain a bond between concrete surfaces
subject to expansion and contraction, and can seal active cracks and replace expansion joints.
Epoxy Resins. Several epoxy or synthetic resin products are available. Epoxy
compounds consist of a two-part mix of resin and hardener. Epoxy bonding agents
are mixed with sand to form epoxy mortar. They are commonly used for the repair
of serious structural defects since the epoxies can be poured or injected into small
cracks. Hardened epoxy creates high strength bond with the concrete. Epoxies also
bond replacement concrete or mortar to old concrete for repairs from 1.5-6.0 inches
deep.
Expanding Mortars. These materials have been developed to reduce shrinking of
the product upon curing.
Latex-modified Compounds. Latex-modified concrete displays excellent bonding
characteristics and resistance to freeze-thaw deterioration, alkalis, and dilute acids.
This material feather edges well and is used for the repair of concrete roads, bridges,
and heavy-duty floors.
Portland Cement Concrete, Grout, or Mortar. Portland cement concrete,
consisting of coarse and fine aggregate and cement, is used for deep repairs. Grout
is used for small repairs where some shrinkage can be accepted and gives best
results when pumped into the opening. Mortar, consisting of a fine aggregate and
cement, is used for many repairs; however, mortar should not be used for shallow
repairs less than 1.5 inches or wherever a featheredge is required.
Quick-setting Materials. Usually referred to as water plugs, wet plugs or hydraulic
cements, these materials are characterized by rapid setting and hardening in
minutes. They are useful for plugging holes or leaks in concrete construction where
water is entering the defect under pressure.
To aid in bonding new concrete or patching material to the existing concrete,
common bonding agents are

Sand-cement mortar
Cement paste
Epoxy resins
Latexes
Polyvinyl acetate
Acrylics

Preparation for Concrete Repairs


Before beginning any repairs to concrete, regardless of the materials and type of
repair method selected, the area to be repaired must be prepared properly.

June 1997

All deteriorative or defective concrete should be removed by light-duty, hand,


or pneumatic chipping tools. The finished cavity should be at least one-inch

200-74

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

deep, with its sides perpendicular to the concrete face, i.e., no feather edges
where possible. Care must be taken not to propagate cracks.

Concrete surfaces should be cleaned thoroughly by abrasive or water blasting


for large surfaces. Wire brushing, scarifying, and acid-etching are other
cleaning methods. All dust and debris must be removed to assure good bonding
of repair material. After the concrete surface has dried, it must be vacuumed to
remove fine dust particles.

Repair areas must be cleaned of existing coatings, oil, acid, grease, or wax solutions. Chemical surface-cleaning agents are acceptable provided they are
washed with soap and rinsed thoroughly with water.

Surface area must be allowed to dry then be rechecked to ensure all unsound
material has been removed. For concrete, mortar, or grout repairs, the repair
surface should be saturated with water but free of standing water. For epoxy
repairs, the surface should be dry and heated to 65-105F at the time of repair.

Concrete surface should be prepared with bonding agent. Certain repair procedures require application of a bonding agent to the repair surface. The surface
should be coated with 1/8-inch of mortar or bonding agent. Bonding coat
should never be allowed to set prior to the placement of concrete, mortar, or
other repair material.

The success of concrete repairs depends as much on preparation of the area to be


repaired as on the repair materials and methods.

Concrete Repair Methods


Visible cracking of concrete surfaces is the most commonly observed problem with
unreinforced and reinforced concrete construction.
Concrete cracks can be divided into two broad categories:

Dormant
Active

Dormant cracks, such as drying shrinkage cracks, are not likely to increase in size
nor affect the structural integrity. These cracks are often sealed with quick-setting
hydraulic cements.
As they can reduce the structural capacity, active cracks (those that propagate under
loads) should be repaired as soon as possible. The most common repair method for
these cracks is pressure and vacuum injection of low-viscosity epoxies and other
monomers which polymerize in place and rebond the parent concrete.
Working cracks, those that show movement under stress, usually must be sealed
with a flexible joint material.
Prior to repairing or resealing cracks, cleaning the cracks is essential, as described
earlier in this section. Common cleaning methods include: compressed air, wire
brushing, sandblasting, routing, and use of picks or similar tools.

Chevron Corporation

200-75

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

Some of the common concrete repair methods are listed below. The method of
repair is dependent upon the size and nature of the repair to be made:

Dry-pack mortar
Concrete replacement
Mortar replacement
Preplaced concrete aggregate
Shotcrete
Epoxy injection

Dry Packing. This method involves ramming a thin layer of very stiff cement-sand
mix into place. The repair surface is covered with a thinly layered bond coat of
grout or mortar prior to placing the dry pack. Most commonly used to fill tie-rod
holes, narrow slots, or other cavities with high depth-to-area ratios, this method is
characterized by high strength and minimal shrinkage.
Concrete Replacement. This is the most common method of repairing defective or
damaged concrete, particularly honeycombed new concrete or concrete that has
deteriorated through the wall or the reinforcement. After surface preparation, new
concrete similar to old in terms of aggregate size and water-cement ratio is
placed into the area. Always place low-slump concrete. Excess water results in
drying shrinkage and bond breakage at the interface.
Mortar Replacement. This repair method is similar to concrete replacement,
except that the mix consists of a fine aggregate and cement only and is used for
smaller repair areas. Best results are obtained when the mortar is applied pneumatically.
Preplaced Concrete Aggregate. This method is especially adaptable to underwater
repairs particularly for large ones where conventional concrete placement is difficult or low-volume change is required. This method involves forcing grout into a
compacted mass of clean coarse aggregate. The grout displaces the water and fills
the voids. Forms must be designed to resist the pumping pressure.
Shotcrete. This repair method is a process of applying concrete mix pneumatically
for shallow repairs on overhead and vertical surfaces without forms. This is usually
an economical method of making large concrete repairs.
Epoxy Injection. This is the common method for sealing or repairing cracks. For
those cracks greater than 1/4 inch, epoxy resin mortar is usually placed into the
cracks. For those less than 1/4 inch, epoxy resin compounds are injected into cracks
under pressure at regular intervals. This type of repair should be carried out by qualified personnel.

270 Computer Program Abstracts


Computer programs have been developed to assist with the design of three types of
foundations commonly used in petrochemical process plant facilities.

June 1997

200-76

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

These programs are not maintained by Chevron Information Technology (CITC).


However, they are in the Engineering (ENGR) library of programs available.
Contact CITC and CRTCs Civil and Structural team for assistance in accessing and
using the programs.
The programs have not been compared to the current requirements of the ACI
Building Code. The programs may be used for preliminary design and the results
should be checked with the current ACI Code for final design.
The programs are as follows:

OCTFNDDesign of Reinforced Concrete Octagonal Foundations

PLSUPFNDDesign of Reinforced Concrete Pile-Supported Octagonal Foundations

ENGR 389Design of Reinforced Concrete Foundations for Horizontal


Vessels

Abstracts of these computer programs follow.

271 OCTFNDDesign of Reinforced Concrete Octagonal Foundations


The objectives of this program are to determine the minimum base thickness,
minimum base diameter, and optimum steel reinforcing that meet all the usual
design and code requirements. In addition, the program calculates the volume of
concrete and reinforcing steel stresses in the base. The program is based on the
Alternate Design Method (Appendix B) of the ACI Building Code (ACI 318-77
including the 1980 Supplement) and on Section 100 of this manual.

272 PLSUPFNDDesign of Reinforced Concrete Pile-supported Octagonal


Foundations
The objectives of this program are to determine the minimum base thickness,
minimum base diameter, optimum pile arrangement, and optimum steel reinforcing
that meet all the usual design and code requirements. In addition, the program calculates the volume of concrete and the minimum and maximum pile loads, and
concrete and reinforcing steel stresses in the base. Minimum stability ratios are
calculated for foundations without uplift. The program is based on the Alternate
Design Method (Appendix B) of the ACI Building Code (ACI 318-77) and on
Section 100 of this manual.

273 ENGR 389Design of Reinforced Concrete Foundations for Horizontal


Vessels
The objective of the program is to determine the minimum sizes of the piers and
footings and steel reinforcing that meet all the usual design and code requirements.
In addition, the program calculates the volume of concrete, net soil pressures or pile
loads, minimum stability ratios, and concrete stresses in the piers and footings. The

Chevron Corporation

200-77

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

program is based on the Ultimate Strength Design of the ACI Building Code (ACI
318-77 including the 1980 Supplement), the 1982 edition of the Uniform Building
Code, and on Section 100 of this manual.
The program designs the following types of vessel supports:

Non-Pile Supported FootingsTwo individual rectangular, spread footings

Pile Supported FootingsIndividual pile supported footings and tie beams.


Limited to a total of four or six piles per foundation

280 Model Specifications, Standard Drawings, and Engineering Forms


This section lists documents that will be of use when planning soils, foundation and
concrete work.

281 Specifications
The following specifications related to this section are included in the Specifications section of the manual or are available in other manuals as indicated.
ACI 301-96

American Concrete Institute, Specifications for Structural


Concrete for Buildings

CIV-MS-850

Plain and Reinforced Concrete Specification

CIV-MS-985

Grouting of Structures

CIV-MS-4841

Piling Installation

MAC-MS-3097 Grouting of Machinery (in Machinery Manual)

282 Standard Drawings


The following standard drawings either are included in the Standard Drawings and
Forms section of this manual or are available in other manuals as indicated.

June 1997

GF-S1121

Secondary Containment and Leak Detection for Tanks (in Tank


Manual)

GD-Q68922

Anchor Bolts

GB-Q99967

Uplift ConnectionsTimber Piles

GD-Q99998

Expansion Bolts

200-78

Chevron Corporation

Civil and Structural Manual

200 Soils, Foundations and Concrete

283 Engineering Forms


The following Standard Engineering Forms relating to this section are included in
the Standard Drawings and Forms section of this manual or are available in other
manuals as indicated.
CIV-EF-336

Details of Guys and Deadmen

CIV-EF-515

Octagonal Foundation with Pedestal

CIV-EF-516

Octagonal Foundation without Pedestal

CIV-EF-517

Simple Foundation without Pedestal

CIV-EF-518

Foundation for Horizontal Equipment

CIV-EF-519

Foundations for Pumps

CIV-EF-627

Pile Driving Data

CIV-EF-629

Concrete Pile Driving RecommendationsBlows/Ft

CIV-EF-725

Triangular Foundation with Pedestal

TAM-EF-364

Tank Foundations (in Tank Manual)

TAM-EF-421

Pile Supported Tank Foundations (in Tank Manual)

290 References
The following references are available through the Corporation Library or other
technical libraries.

Chevron Corporation

1.

Design and Control of Concrete Mixtures, Portland Cement Association, 12th


edition, 1979.

2.

ACI Manual of Concrete Practice, American Concrete Institute, Parts 1-5,


1990.

3.

Foundation Engineering Handbook, Winterkorn, Hans F. and Fang, Hsai-Yang,


Litton Educational Publishing, Inc., 1975.

4.

Foundation Analysis and Design, Bowles, Joseph E., Second edition, McGraw
Hill, Inc., 1977.

5.

Uniform Building Code, International Conference of Building Officials, 1991 .

6.

Handbook of Concrete Engineering, Fintel, Mark, Van Norstrand Reinhold


Company, Inc., 1985.

7.

Soil Engineering, Spangler, Merlin G. and Handy, Richard L., Harper and Row,
Publishers, Inc., Third edition, 1973.

8.

Standard Handbook for Civil Engineers, Merritt, Frederick S., McGraw Hill,
Inc., Third edition, 1983.

9.

Design Manual (NAVFAC DM-7)Soil Mechanics, Foundations, and Earth


Structures, Department of the NavyNaval Facilities Engineering Command,
US Government Printing Office, March, 1971.

200-79

June 1997

200 Soils, Foundations and Concrete

Civil and Structural Manual

10. Structural Engineering Handbook, Gaylord, Edwin H. and Gaylord, Charles N.,
McGraw Hill, Inc., Second edition, 1979.
11. Concrete Manual, US Department of the Interior, US Government Printing
Office, Eighth edition, 1981.
12. Pipe Support Design Manual, D. Russell and Associates, July, 1987. Prepared
for the Richmond Refinery.

June 1997

200-80

Chevron Corporation

You might also like