Professional Documents
Culture Documents
Preheater
M
Drum
Cold
Reheat Line
Application
Attemperators are utilized in Heat Recovery Steam
Generators (HRSGs) between the primary and
secondary superheaters on the High Pressure
(HP) and the Reheat (RH) lines (Figure 1). In
some designs, attemperators are also added after
the nal stage of superheating.
Attemperators installed in the HP interstage will
typically see pressures up to 130 barg (1900
psig) and temperatures of 550C (1020F), with
steam ow rates in the region of 300,000 kg/h
(660,000 lb/h). Attemperators installed on the RH
interstage will typically see similar temperatures
and ow rates, but pressures to only around
30 barg (450 psig). The control temperature for
these attemperators is adjusted so that the nal
temperature after the nal superheater satises
the start-up and steam turbine inlet requirement.
These attemperators are critical to the overall
performance of the HRSG and provide the
following functions:
Control nal temperature from HRSG
Prevent thermal damage of piping and
downstream equipment, such as the steam
turbine
For start-up and allowing gradual heat rate
to the steam turbine
Control steam temperature to the second
stage superheaters
Prevent overheating of superheater tubes
Prevent over stressing of superheater tubes
Feedwater
Control Valve
Economizer
M
Reheater
Superheater
Attemperator
Spraywater
Control Valve
Reheater
IP/LP
Turbine
Superheater
Feedwater Minimum
Flow Valve
HP
Turbine
Condenser
Feedwater Tank
Condensate Pump
The root cause for all of the above problems can be traced
to one, or more, of the following:
Poor attemperator design
Poor design of spray water control element
Poor installation
Poor control of instrumentation
Attemperator Design
The service requirements in an HP or RH interstage
are extremely demanding on attemperators. As the
HRSG cycles, attemperator hardware will remain for
extended periods at elevated steam temperatures without
spraywater owing through it, will then be subjected to
thermal shock when quenched by the relatively cool
spraywater. Attemperators in which the ow control
element resides in the steam ow, such as the multi-nozzle
probe style design (Figure 2), such cycling results in
fatigue and thermal cracks in critical components, such as
the nozzle holder, the nozzles themselves, the lower body
and the piston rings.
Installation
Control Instrumentation
Temperature sensors, for feedback, must be installed
at a sufcient distance downstream to allow for the
complete evaporation of the injected water ow, even
under transient conditions. Additional algorithms and
specications for temperature sensor will inuence
performance, but is beyond the scope of this article.
Primary Atomization
Secondary Atomization
Dynamic force
Surface tension
V2D
Evaporation
Following secondary atomization, the resulting droplets will
have to rst boil and then evaporate. The time for complete
evaporation is dependent on the total surface area of the
water volume, and thus, will be proportional to the droplet
diameter squared. (Figure 8)
If any droplets remain un-evaporated prior to the
temperature sensor, wetting of the sensor may occur,
resulting in problems with temperature control. In addition,
if sufcient quantities of large droplets impinge on the
rst bend following the attemperator, erosion and thermal
shock will occur.
During transients, owing to a combination of poor control
and poor atomization of the droplets, there can be
sufcient carry over of water to the secondary superheater
tubes resulting in damage to tubing and headers.
Consequently, allowing sufcient time for evaporation is of
the utmost importance to operation of the attemperators.
Recommended Practice
Mechanical design, construction and thermal
considerations are of crucial importance in attemperator
selection. Further, proper installation is imperative to its
proper functioning; it is necessary to consider upstream
distance, downstream distance to the rst bend, and
downstream to the temperature sensor.
Thermal Barrier
Figure 9: Thermal Barrier
Liners
Typically, most attemperator suppliers will only provide a
liner to protect the steam pipe wall from thermal shock.
However, a properly engineered liner is capable of
enhancing the attemperator performance. CCI utilizes liners
to provide the following:
0.025 x V
L = 0.067s x V max
L = 0.2S x V max
CCI Solution
Model DAM: Wall mounted variable area nozzles
CCI solution is the DAM attemperator which satises
all mechanical and thermo-dynamic & uid dynamic
considerations.
Control valve element separate from attemperator
Nozzles minimally protrude into the steam ow
Spray
Penetration
Test
Justication:
a. Provides excellent nozzle exit spray pattern
regardless of steam ow, i.e. good primary
atomization. Fixed nozzles will provide poor
atomization at low ow
5.
A liner is required
Justication:
a. Protection of pipe under severe pressure and
thermal stress from impingement of relatively
cool spraywater, particularly in transient
conditions
Justication:
To prevent thermal stresses resulting from the direct
impingement of spraywater onto the hot steam pipe
wall or thermal liner.
6.
b.
c.
d.
3.
a.
b.
Justication:
c.
d.
7.
Justication:
Prevents risk of nozzle leaking water into steam
pipe while feedpump is at full operating pressure
and little or no steam pressure in the pipe
12. For the range of operating conditions, ashing
and/or cavitation shall not be permitted.
Justication:
9.
Justication:
Seat is protected from high velocity thereby
providing extended operating life and repeatable
tight shut-off. Particularly important during sliding
pressure situation when P is high and Cv
required is small
CCI Sweden
(BTG Valves)
Telephone: 46 533 426 00
Fax: 46 533 125 00
Box 603
661 29 Sfe
Sweden
CCI Austria
(Spectris Components GmbH)
Telephone: 43 1 869 27 40
Fax: 43 1 865 36 03
Lembockgasse 63
AT-1233 Vienna
Austria
CCI Switzerland
(Sulzer Valves)
Telephone: 41 52 264 95 00
Fax: 41 52 264 95 01
Im Link 11, P.O. Box 65
CH-8404 Winterthur
Switzerland
CCI Korea
Telephone: 82 31 985 9430
Fax: 82 31 985 0552
26-17, Pungmu-Dong
Kimpo City,
Kyunggi-Do 415-070
South Korea
CCI Japan
Telephone: 81 726 41 7197
Fax: 81 726 41 7198
4-15-20 Shukunosho
Ibaraki-City, Osaka 567-0051
Japan
CCI China
Telephone: 86 10 6501 0350
Fax: 86 10 6501 0286
Room 567/569 Ofce Tower
Poly Plaza
14 Dongzhimen South Avenue
Beijing 100027
China
CCI Italy
(STI)
Telephone: 39 035 29282
Fax: 39 035 2928247
Via G. Pascoli 10A-B
24020 Gorle, Bergamo
Italy
780 2/05