You are on page 1of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]

Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

394

20-Jan-09

17-Feb-10

394

20-Jan-09

17-Feb-10

394

20-Jan-09

17-Feb-10

394
0

20-Jan-09
20-Jan-09

17-Feb-10

Receive Letter of Acceptance [LOA]

0
0

A5670

Hammock Project Duration

387

27-Jan-09

17-Feb-10

A5690

Possession/Access To Site

21

27-Jan-09

16-Feb-09

67

Possession/Access To Site

A5700

Submit of Advance Payment Bank Guarantee

18

27-Jan-09

13-Feb-09

66

Submit of Advance Payment Bank Guarantee

A29580

Commencement Day of The Contract

27-Jan-09

A5710

Provision of Certificates of Verification of Insurance Cover

14-Feb-09

A5740

Completion of Sorbonne Area

A5750

Contract Completion Day

Al Reem Island Development-Sector 5&6-Baseline TB01[200109]


Major Milestones
Major Milestones by Contractor
Milestones
A5660

Completion of Roads Milestones


A5820
Completion of Road 7

Finish

Total
FloatD

0
20-Feb-09

66

30-Jul-09*

17-Feb-10*

23-Jan-10
30-Nov-09

15
69

54
0

30-Nov-09

2009
J

2010

F M A M J Jul A S O N D

F M

Receive Letter of Acceptance [LOA]


Hammock Project

Commencement Day of The Contract


Provision of Certificates of Verification of Insurance Cover
Completion of Sorbonne Area

Contract Completi
Completion of Road 7

A5830

Completion of Road 8

30-Dec-09

39

Completion of Road 8

A5810

Completion of Road 6

05-Jan-10

33

Completion of Road 6

A5800

Completion of Road 5

11-Jan-10

27

A5790

Completion of Road 4

18-Jan-10

20

Completion of Road 4

A5780

Completion of Road 3

23-Jan-10

15

Completion of Road 3

22-Oct-09
25-May-09

34
36

Utilities Milestones
A30170
End of Utilities of Road A3

150
0

25-May-09

Completion of Road 5

End of Utilities of Road A3

A6000

End of Utilities of Road H3

07-Jun-09

23

End of Utilities of Road H3

A5900

End of Utilities of Road C5

10-Jun-09

20

End of Utilities of Road C5

A5870

End of Utilities of Road C2

18-Jun-09

12

End of Utilities of Road C2

A5860

End of Utilities of Road B5

22-Jun-09

End of Utilities of Road B5

A5880

End of Utilities of Road C3

25-Jun-09

End of Utilities of Road C3

A6040

End of Utilities of Ramp 2

28-Jun-09

150

End of Utilities of Ramp 2

A5890

End of Utilities of Road C4

30-Jun-09

End of Utilities of Road C4

A5950

End of Utilities of Road F2

30-Jun-09

148

End of Utilities of Road F2

A5960

End of Utilities of Road F3

18-Jul-09

130

A5980

End of Utilities of Road G3

28-Jul-09

120

End of Utilities of Road G3

A5930

End of Utilities of Road E3

01-Aug-09

116

End of Utilities of Road E3

A6030

End of Utilities of Road K

13-Aug-09

104

End of Utilities of Road K

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 1 of 43

End of Utilities of Road F3

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A6010

End of Utilities of Road J1

23-Aug-09

94

End of Utilities of Road J1

A6050

End of Utilities of Road 1

23-Aug-09

94

End of Utilities of Road 1

A5990

End of Utilities of Road H2

25-Aug-09

92

End of Utilities of Road H2

A6020

End of Utilities of Road J2

25-Aug-09

92

End of Utilities of Road J2

A5910

End of Utilities of Road E1

27-Aug-09

90

End of Utilities of Road E1

A5850

End of Utilities of Road B4

29-Aug-09

88

End of Utilities of Road B4

A5920

End of Utilities of Road E2

30-Aug-09

87

End of Utilities of Road E2

A5940

End of Utilities of Road E4

15-Sep-09

71

End of Utilities of Road E4

A5970

End of Utilities of Road G2

19-Sep-09

67

End of Utilities of Road G2

A6120

End of Utilities of Road 8

03-Oct-09

53

End of Utilities of Road 8

A6090

End of Utilities of Road 5

05-Oct-09

51

End of Utilities of Road 5

A6100

End of Utilities of Road 6

12-Oct-09

44

End of Utilities of Road 6

A6110

End of Utilities of Road 7

14-Oct-09

42

End of Utilities of Road 7

A6080

End of Utilities of Road 4

18-Oct-09

38

End of Utilities of Road 4

A6070

End of Utilities of Road 3

22-Oct-09

34

End of Utilities of Road 3

28-Oct-09
01-Aug-09

28
116

Networks Milestones
A6130
Completion of Sewerage Network

88
0

01-Aug-09

Completion of Sewerage Network


Completion of Potable Water Network

A6160

Completion of Potable Water Network

17-Aug-09

100

A6150

Completion of Gas Network

26-Aug-09

91

Completion of Gas Network

A6180

Completion of Telecommunication Network

29-Aug-09

88

Completion of Telecommunication Netw

A6140

Completion of Irrigation Network

06-Sep-09

80

A6210

Completion of Low Voltage Network

29-Sep-09

57

Completion of Low Voltage Network

A6170

Completion of Surface Water Network

03-Oct-09

53

Completion of Surface Water Netwo

A6190

Completion of Street Lighting Network

27-Oct-09

29

Completion of Street Lighting Ne

A6200

Completion of 22KV Electrical Network

28-Oct-09

28

Completion of 22KV Electrical N

22

27-Jan-09

17-Feb-09

66

Receipt of IFC (Furnished by Client)

22
1

27-Jan-09
27-Jan-09

17-Feb-09
27-Jan-09

66
0

Receipt of Advance Payment from Employer

14-Feb-09

17-Feb-09

66

42

27-Jan-09

09-Mar-09

70

Major Milestones by Client


Milestones
A6300
A6250

Engineering & Submittals

Completion of Irrigation Network

Receipt of IFC (Furnished by Client)


Receipt of Advance Payment from Employer

A6330

Sub of Proposed HSE Management Plan

28

27-Jan-09

23-Feb-09

60

Sub of Proposed HSE Management Plan

A6340

Sub of Proposed QA/QC Plan

28

27-Jan-09

23-Feb-09

60

Sub of Proposed QA/QC Plan

A6360

Sub & Prep Baseline Schedule

28

27-Jan-09

23-Feb-09

70

Sub & Prep Baseline Schedule

A6370

Rev & App Baseline Schedule

14

24-Feb-09

09-Mar-09

70

Rev & App Baseline Schedule

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 2 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Shop Drawings

Original
Duration

Start

213

28-Jan-09

20-Jan-09
Finish

Total
FloatD

28-Aug-09

15

2009
J

F M A M J Jul A S O N D

2010
J

F M

90

28-Jan-09

27-Apr-09

36

A30480

Sub&Prep Shop Drawings for Sorbonne Sewage Crossing

15

28-Jan-09

11-Feb-09

19

A30490

Sub&Prep Shop Drawings for Sorbonne Potable Water Crossing

30

28-Jan-09

26-Feb-09

11

A30500

Sub&Prep Shop Drawings for Sorbonne Gas Crossing

45

28-Jan-09

13-Mar-09

A30510

Sub&Prep Shop Drawings for Sorbonne Irrigation Crossing

60

28-Jan-09

28-Mar-09

10

Sub&Prep Shop Drawings for Sorbonne Irrigation Crossing

A30520

Sub&Prep Shop Drawings for Sorbonne 22kv Crossing

75

28-Jan-09

12-Apr-09

14

Sub&Prep Shop Drawings for Sorbonne 22kv Crossing

A30530

Sub&Prep Shop Drawings for Sorbonne Street Lighting Crossing

90

28-Jan-09

27-Apr-09

36

Submittal & Preparation for Sorbonne Crossings

Sub&Prep Shop Drawings for Sorbonne Sewage Crossing

Sub&Prep Shop Drawings for Sorbonne Potable Water Crossin


Sub&Prep Shop Drawings for Sorbonne Gas Crossing

Sub&Prep Shop Drawings for Sorbonne Street Lighting

90

12-Feb-09

12-May-09

40

A30550

Review and Approval Shop Drawings for Sorbonne Sewage Crossing

15

12-Feb-09

26-Feb-09

48

Review and Approval Shop Drawings for Sorbonne Sewage Cro

A30560

Review and Approval Shop Drawings for Sorbonne Potable Water Crossing

15

27-Feb-09

13-Mar-09

42

Review and Approval Shop Drawings for Sorbonne Potable W

A30570

Review and Approval Shop Drawings for Sorbonne Gas Crossing

15

14-Mar-09

28-Mar-09

53

Review and Approval Shop Drawings for Sorbonne Gas Cro

A30580

Review and Approval Shop Drawings for Sorbonne Irrigation Crossing

15

29-Mar-09

12-Apr-09

59

Review and Approval Shop Drawings for Sorbonne Irrigati

A30590

Review and Approval Shop Drawings for Sorbonne 22kv Crossing

15

13-Apr-09

27-Apr-09

33

Review and Approval Shop Drawings for Sorbonne 22kv

A30600

Review and Approval Shop Drawings for Sorbonne Street Lighting Crossing

15

28-Apr-09

12-May-09

40

Review and Approval Shop Drawings for Sorbonne St

111

28-Jan-09

18-May-09

14

Review & Approval for Sorbonne Crossings

Submittal & Preparation for Sorbonne Network

Sub&Prep Shop Drawings for Temporary STP

A30090

Sub&Prep Shop Drawings for Temporary STP

81

28-Jan-09

18-Apr-09

17

A30280

Sub&Prep Shop Drawings for Sorbonne Sewage Network

15

12-Feb-09

26-Feb-09

19

A30290

Sub&Prep Shop Drawings for Sorbonne Potable Water Network

21

27-Feb-09

19-Mar-09

11

A30300

Sub&Prep Shop Drawings for Sorbonne Gas Network

21

14-Mar-09

03-Apr-09

A30310

Sub&Prep Shop Drawings for Sorbonne Telecommunication Network

21

29-Mar-09

18-Apr-09

10

Sub&Prep Shop Drawings for Sorbonne Telecommunica

A30320

Sub&Prep Shop Drawings for Sorbonne 22kv Network

21

13-Apr-09

03-May-09

15

Sub&Prep Shop Drawings for Sorbonne 22kv Network

A30330

Sub&Prep Shop Drawings for Sorbonne Low Voltage Network

36

13-Apr-09

18-May-09

14

Sub&Prep Shop Drawings for Sorbonne Low Voltage

96

27-Feb-09

02-Jun-09

14

Review & Approval for Sorbonne Network

Sub&Prep Shop Drawings for Sorbonne Sewage Network

Sub&Prep Shop Drawings for Sorbonne Potable Water Netw


Sub&Prep Shop Drawings for Sorbonne Gas Network

A30340

Review and Approval Shop Drawings for Sorbonne Sewage Network

15

27-Feb-09

13-Mar-09

19

Review and Approval Shop Drawings for Sorbonne Sewage N

A30350

Review and Approval Shop Drawings for Sorbonne Potable Water Network

15

20-Mar-09

03-Apr-09

17

Review and Approval Shop Drawings for Sorbonne Potable

A30360

Review and Approval Shop Drawings for Sorbonne Gas Network

15

04-Apr-09

18-Apr-09

17

Review and Approval Shop Drawings for Sorbonne Gas N

A30100

Review and Approval Shop Drawings for Temporary STP

15

19-Apr-09

03-May-09

17

Review and Approval Shop Drawings for Temporary ST

A30370

Review and Approval Shop Drawings for Sorbonne Telecommunication Network

15

19-Apr-09

03-May-09

18

Review and Approval Shop Drawings for Sorbonne Tel

A30380

Review and Approval Shop Drawings for Sorbonne 22kv Network

15

04-May-09

18-May-09

15

Review and Approval Shop Drawings for Sorbonne 2

A30390

Review and Approval Shop Drawings for Sorbonne Low Voltage Network

15

19-May-09

02-Jun-09

14

Review and Approval Shop Drawings for Sorbonne

147

20-Mar-09

13-Aug-09

15

57

20-Mar-09

15-May-09

11

Submittal & Preparation for Remaining Project


A21620

Sub&Prep Shop Drawings for Potable Water Network

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 3 of 43

Sub&Prep Shop Drawings for Potable Water Network

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

Sub&Prep Shop Drawings for Sewage Network

A21580

Sub&Prep Shop Drawings for Sewage Network

21

04-Apr-09

24-Apr-09

15

A21590

Sub&Prep Shop Drawings for Gas Network

57

04-Apr-09

30-May-09

21

A21600

Sub&Prep Shop Drawings for Irrigation Network

72

04-Apr-09

14-Jun-09

A21570

Sub&Prep Shop Drawings for Storm Water Network

87

19-Apr-09

14-Jul-09

10

Sub&Prep Shop Drawings for Storm Water N

A21660

Sub&Prep Shop Drawings for Telecommunication Network

72

19-Apr-09

29-Jun-09

20

Sub&Prep Shop Drawings for Telecommunicati

A21650

Sub&Prep Shop Drawings for 22kv Network

87

04-May-09

29-Jul-09

20

Sub&Prep Shop Drawings for 22kv Network

A21670

Sub&Prep Shop Drawings for Street Lighting Network

87

19-May-09

13-Aug-09

15

Sub&Prep Shop Drawings for Street Light

A21690

Sub&Prep Shop Drawings for Low Voltage Network

87

19-May-09

13-Aug-09

15

Sub&Prep Shop Drawings for Low Voltage

126

25-Apr-09

28-Aug-09

15

Review & Approval for Remaining Project

Sub&Prep Shop Drawings for Gas Network


Sub&Prep Shop Drawings for Irrigation Network

Review and Approval Shop Drawings for Sewage Netw

A27710

Review and Approval Shop Drawings for Sewage Network

15

25-Apr-09

09-May-09

15

A27750

Review and Approval Shop Drawings for Potable Water Network

15

16-May-09

30-May-09

11

Review and Approval Shop Drawings for Potable W

A27720

Review and Approval Shop Drawings for Gas Network

15

31-May-09

14-Jun-09

21

Review and Approval Shop Drawings for Gas Net

A27730

Review and Approval Shop Drawings for Irrigation Network

15

15-Jun-09

29-Jun-09

Review and Approval Shop Drawings for Irrigati

A27790

Review and Approval Shop Drawings for Telecommunication Network

15

30-Jun-09

14-Jul-09

20

Review and Approval Shop Drawings for Tele

A27700

Review and Approval Shop Drawings for Storm Water Network

15

15-Jul-09

29-Jul-09

10

Review and Approval Shop Drawings for Sto

A27780

Review and Approval Shop Drawings for 22kv Network

15

30-Jul-09

13-Aug-09

20

Review and Approval Shop Drawings for 2

A27800

Review and Approval Shop Drawings for Street Lighting Network

15

14-Aug-09

28-Aug-09

15

Review and Approval Shop Drawings for

A27820

Review and Approval Shop Drawings for Low Voltage Network

15

14-Aug-09

28-Aug-09

15

Review and Approval Shop Drawings for

240

27-Jan-09

23-Sep-09

111

90

28-Jan-09

27-Apr-09

142

Procurement and Delivery


Bid & Award
A29800

Bid & Award - Valve (Irrigation)

14

28-Jan-09

10-Feb-09

40

Bid & Award - Valve (Irrigation)

A29810

Bid & Award - Geotextile Fabric

14

28-Jan-09

10-Feb-09

213

Bid & Award - Geotextile Fabric

A29820

Bid & Award - Traffic Sign

14

28-Jan-09

10-Feb-09

218

Bid & Award - Traffic Sign

A29830

Bid & Award - Light Pole & Luminaries

60

28-Jan-09

28-Mar-09

A29840

Bid & Award - Control Cabinet (Street Light)

90

28-Jan-09

27-Apr-09

69

A29850

Bid & Award - LV Cable (Street Light)

90

28-Jan-09

27-Apr-09

22

A29880

Bid & Award - HDPE Pipe (Irrigation)

30

28-Jan-09

26-Feb-09

47

Bid & Award - HDPE Pipe (Irrigation)

A29900

Bid & Award - PE100 Pipe (Gas)

30

28-Jan-09

26-Feb-09

17

Bid & Award - PE100 Pipe (Gas)

A29910

Bid & Award - UPVC Duct (Telecom)

30

28-Jan-09

26-Feb-09

34

Bid & Award - UPVC Duct (Telecom)

A29920

Bid & Award - LV Cable (Power)

30

28-Jan-09

26-Feb-09

59

Bid & Award - LV Cable (Power)

A29930

Bid & Award - Valve (Gas)

30

28-Jan-09

26-Feb-09

25

Bid & Award - Valve (Gas)

A29940

Bid & Award - 22kv Cable (Power)

30

28-Jan-09

26-Feb-09

40

A29960

Bid & Award - HDPE Pipe (Potable Water)

15

28-Jan-09

11-Feb-09

17

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 4 of 43

Bid & Award - Light Pole & Luminaries


Bid & Award - Control Cabinet (Street Light)
Bid & Award - LV Cable (Street Light)

Bid & Award - 22kv Cable (Power)


Bid & Award - HDPE Pipe (Potable Water)

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

A29970

Bid & Award - GRP Duct Pipe (Potable Water)

15

28-Jan-09

11-Feb-09

17

Bid & Award - GRP Duct Pipe (Potable Water)

A29980

Bid & Award - GRP Duct Pipe (Surface Water)

15

28-Jan-09

11-Feb-09

110

Bid & Award - GRP Duct Pipe (Surface Water)

A29990

Bid & Award - Valve (Potable Water)

30

28-Jan-09

26-Feb-09

Bid & Award - Valve (Potable Water)

A30000

Bid & Award - RC Pipe (Surface Water)

14

28-Jan-09

10-Feb-09

93

Bid & Award - RC Pipe (Surface Water)

A30110

Bid & Award - Temporary STP Tank

30

28-Jan-09

26-Feb-09

A29860

Bid & Award - Fire Hydrant & Fittings

14

28-Jan-09

10-Feb-09

Bid & Award - Fire Hydrant & Fittings

A29870

Bid & Award - UPVC Pipe (Sewerage)

14

28-Jan-09

10-Feb-09

Bid & Award - UPVC Pipe (Sewerage)

A29950

Bid & Award - GRP Pipe (Sewerage)

14

28-Jan-09

10-Feb-09

Bid & Award - GRP Pipe (Sewerage)

14

27-Jan-09

09-Feb-09

106

Submittal & Preparation for Sorbonne Crossing & Intersections

Bid & Award - Temporary STP Tank

A30670

Sub & Prep - UPVC Duct Pipe (Sewerage)

14

27-Jan-09

09-Feb-09

37

Sub & Prep - UPVC Duct Pipe (Sewerage)

A30680

Sub & Prep - GRP Duct Pipe (Potable Water)

14

27-Jan-09

09-Feb-09

48

Sub & Prep - GRP Duct Pipe (Potable Water)

A30690

Sub & Prep - GRP Duct Pipe (Irrigation Water)

14

27-Jan-09

09-Feb-09

96

Sub & Prep - GRP Duct Pipe (Irrigation Water)

A30700

Sub & Prep - UPVC Duct Pipe (Gas)

14

27-Jan-09

09-Feb-09

76

Sub & Prep - UPVC Duct Pipe (Gas)

A30710

Sub & Prep - UPVC Duct Pipe (Street Lighting)

14

27-Jan-09

09-Feb-09

106

A30720

Sub & Prep - UPVC Duct Pipe (22kV)

14

27-Jan-09

09-Feb-09

84
142

Sub & Prep - UPVC Duct Pipe (Street Lighting)


Sub & Prep - UPVC Duct Pipe (22kV)

90

11-Feb-09

11-May-09

A28950

Sub & Prep - Valve (Irrigation)

14

11-Feb-09

24-Feb-09

40

Sub & Prep - Valve (Irrigation)

A28960

Sub & Prep - Geotextile Fabric

14

11-Feb-09

24-Feb-09

213

Sub & Prep - Geotextile Fabric

A28970

Sub & Prep - Traffic Sign

14

11-Feb-09

24-Feb-09

218

Sub & Prep - Traffic Sign

A14140

Sub & Prep - Fire Hydrant & Fittings

14

11-Feb-09

24-Feb-09

Sub & Prep - Fire Hydrant & Fittings

A14170

Sub & Prep - UPVC Pipe (Sewerage)

14

11-Feb-09

24-Feb-09

Sub & Prep - UPVC Pipe (Sewerage)

A18690

Sub & Prep - GRP Pipe (Sewerage)

14

11-Feb-09

24-Feb-09

Sub & Prep - GRP Pipe (Sewerage)

A28750

Sub & Prep - RC Pipe (Surface Water)

14

11-Feb-09

24-Feb-09

93

Sub & Prep - RC Pipe (Surface Water)

A21930

Sub & Prep - HDPE Pipe (Potable Water)

14

12-Feb-09

25-Feb-09

17

Sub & Prep - HDPE Pipe (Potable Water)

A21960

Sub & Prep - GRP Duct Pipe (Potable Water)

14

12-Feb-09

25-Feb-09

17

Sub & Prep - GRP Duct Pipe (Potable Water)

A29000

Sub & Prep - GRP Duct Pipe (Surface Water)

14

12-Feb-09

25-Feb-09

110

Sub & Prep - GRP Duct Pipe (Surface Water)

A14200

Sub & Prep - HDPE Pipe (Irrigation)

14

27-Feb-09

12-Mar-09

47

Sub & Prep - HDPE Pipe (Irrigation)

A18280

Sub & Prep - PE100 Pipe (Gas)

14

27-Feb-09

12-Mar-09

17

Sub & Prep - PE100 Pipe (Gas)

A18310

Sub & Prep - UPVC Duct (Telecom)

14

27-Feb-09

12-Mar-09

34

Sub & Prep - UPVC Duct (Telecom)

A18490

Sub & Prep - LV Cable (Power)

14

27-Feb-09

12-Mar-09

59

Sub & Prep - LV Cable (Power)

A18530

Sub & Prep - Valve (Gas)

14

27-Feb-09

12-Mar-09

25

Sub & Prep - Valve (Gas)

A18620

Sub & Prep - 22kv Cable (Power)

14

27-Feb-09

12-Mar-09

40

Sub & Prep - 22kv Cable (Power)

A28310

Sub & Prep - Valve (Potable Water)

14

27-Feb-09

12-Mar-09

Sub & Prep - Valve (Potable Water)

A30120

Sub & Prep - Temporary STP Tank

14

27-Feb-09

12-Mar-09

Sub & Prep - Temporary STP Tank

Submittal & Preparation Remaining Project

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 5 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

Sub & Prep - Light Pole & Luminaries

A28980

Sub & Prep - Light Pole & Luminaries

14

29-Mar-09

11-Apr-09

A14080

Sub & Prep - Control Cabinet (Street Light)

14

28-Apr-09

11-May-09

69

Sub & Prep - Control Cabinet (Street Light)

A14110

Sub & Prep - LV Cable (Street Light)

14

28-Apr-09

11-May-09

22

Sub & Prep - LV Cable (Street Light)

Review & Approval for Sorbonne Crossing & Intersections

14

10-Feb-09

23-Feb-09

106

A30730

Rev & App - GRP Duct Pipe (Irrigation Water)

14

10-Feb-09

23-Feb-09

96

Rev & App - GRP Duct Pipe (Irrigation Water)

A30740

Rev & App - GRP Duct Pipe (Potable Water)

14

10-Feb-09

23-Feb-09

48

Rev & App - GRP Duct Pipe (Potable Water)

A30750

Rev & App - UPVC Duct Pipe (22kV)

14

10-Feb-09

23-Feb-09

84

Rev & App - UPVC Duct Pipe (22kV)

A30760

Rev & App - UPVC Duct Pipe (Gas)

14

10-Feb-09

23-Feb-09

76

Rev & App - UPVC Duct Pipe (Gas)

A30770

Rev & App - UPVC Duct Pipe (Sewerage)

14

10-Feb-09

23-Feb-09

37

Rev & App - UPVC Duct Pipe (Sewerage)

A30780

Rev & App - UPVC Duct Pipe (Street Lighting)

14

10-Feb-09

23-Feb-09

106

90

25-Feb-09

25-May-09

142

Review & Approval Remaining Project

Rev & App - UPVC Duct Pipe (Street Lighting)

A2360

Rev & App - Valve (Irrigation)

14

25-Feb-09

10-Mar-09

40

Rev & App - Valve (Irrigation)

A2370

Rev & App - Geotextile Fabric

14

25-Feb-09

10-Mar-09

213

Rev & App - Geotextile Fabric

A2380

Rev & App - Traffic Sign

14

25-Feb-09

10-Mar-09

218

Rev & App - Traffic Sign

A14150

Rev & App - Fire Hydrant & Fittings

14

25-Feb-09

10-Mar-09

Rev & App - Fire Hydrant & Fittings

A14180

Rev & App - UPVC Pipe (Sewerage)

14

25-Feb-09

10-Mar-09

Rev & App - UPVC Pipe (Sewerage)

A18700

Rev & App - GRP Pipe (Sewerage)

14

25-Feb-09

10-Mar-09

Rev & App - GRP Pipe (Sewerage)

A28760

Rev & App - RC Pipe (Surface Water)

14

25-Feb-09

10-Mar-09

93

Rev & App - RC Pipe (Surface Water)

A21920

Rev & App - HDPE Pipe (Potable Water)

14

26-Feb-09

11-Mar-09

17

Rev & App - HDPE Pipe (Potable Water)

A21950

Rev & App - GRP Duct Pipe (Potable Water)

14

26-Feb-09

11-Mar-09

17

Rev & App - GRP Duct Pipe (Potable Water)

A2400

Rev & App - GRP Duct Pipe (Surface Water)

14

26-Feb-09

11-Mar-09

110

Rev & App - GRP Duct Pipe (Surface Water)

A14210

Rev & App - HDPE Pipe (Irrigation)

14

13-Mar-09

26-Mar-09

47

Rev & App - HDPE Pipe (Irrigation)

A18290

Rev & App - PE100 Pipe (Gas)

14

13-Mar-09

26-Mar-09

17

Rev & App - PE100 Pipe (Gas)

A18320

Rev & App - UPVC Duct (Telecom)

14

13-Mar-09

26-Mar-09

34

Rev & App - UPVC Duct (Telecom)

A18500

Rev & App - LV Cable (Power)

14

13-Mar-09

26-Mar-09

59

Rev & App - LV Cable (Power)

A18540

Rev & App - Valve (Gas)

14

13-Mar-09

26-Mar-09

25

Rev & App - Valve (Gas)

A18630

Rev & App - 22kv Cable (Power)

14

13-Mar-09

26-Mar-09

40

Rev & App - 22kv Cable (Power)

A28320

Rev & App - Valve (Potable Water)

14

13-Mar-09

26-Mar-09

Rev & App - Valve (Potable Water)

A30130

Rev & App - Temporary STP Tank

14

13-Mar-09

26-Mar-09

Rev & App - Temporary STP Tank

A2390

Rev & App - Light Pole & Luminaries

14

12-Apr-09

25-Apr-09

A14090

Rev & App - Control Cabinet (Street Light)

14

12-May-09

25-May-09

69

Rev & App - Control Cabinet (Street Light)

A14120

Rev & App - LV Cable (Street Light)

14

12-May-09

25-May-09

22

Rev & App - LV Cable (Street Light)

197

11-Mar-09

23-Sep-09

111

96

11-Mar-09

14-Jun-09

Fabrication & Delivery


Fabrication & Delivery for Sorbonne
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 6 of 43

Rev & App - Light Pole & Luminaries

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A29640

Fab & Del [Sorbonne]- Fire Hydrant & Fittings

25

11-Mar-09

04-Apr-09

28

Fab & Del [Sorbonne]- Fire Hydrant & Fittings

A29650

Fab & Del [Sorbonne]- UPVC Pipe (Sewerage)

25

11-Mar-09

04-Apr-09

Fab & Del [Sorbonne]- UPVC Pipe (Sewerage)

A29740

Fab & Del [Sorbonne]- GRP Pipe (Sewerage)

25

11-Mar-09

04-Apr-09

Fab & Del [Sorbonne]- GRP Pipe (Sewerage)

A29760

Fab & Del [Sorbonne]- HDPE Pipe (Potable Water)

25

12-Mar-09

05-Apr-09

17

Fab & Del [Sorbonne]- HDPE Pipe (Potable Water)

A29770

Fab & Del [Sorbonne]- GRP Duct Pipe (Potable Water)

25

12-Mar-09

05-Apr-09

17

Fab & Del [Sorbonne]- GRP Duct Pipe (Potable Water)

A29680

Fab & Del [Sorbonne]- PE100 Pipe (Gas)

25

27-Mar-09

20-Apr-09

17

Fab & Del [Sorbonne]- PE100 Pipe (Gas)

A29690

Fab & Del [Sorbonne]- UPVC Duct(Telecom)

25

27-Mar-09

20-Apr-09

34

Fab & Del [Sorbonne]- UPVC Duct(Telecom)

A29700

Fab & Del [Sorbonne]- Valve (Gas)

25

27-Mar-09

20-Apr-09

30

Fab & Del [Sorbonne]- Valve (Gas)

A29750

Fab & Del [Sorbonne]- LV Cable (Power)

25

27-Mar-09

20-Apr-09

59

Fab & Del [Sorbonne]- LV Cable (Power)

A29790

Fab & Del [Sorbonne]- Valve (Potable Water)

25

27-Mar-09

20-Apr-09

A30140

Fab & Del - Temporary STP Tank

80

27-Mar-09

14-Jun-09

Fabrication & Delivery For Remaining Project


A29010
Fab & Del - Valve (Irrigation)

197
90

11-Mar-09
11-Mar-09

23-Sep-09
08-Jun-09

111
40

A29020

Fab & Del - Geotextile Fabric

30

11-Mar-09

09-Apr-09

213

A29030

Fab & Del - Traffic Sign

90

11-Mar-09

08-Jun-09

218

A14160

Fab & Del - Fire Hydrant & Fittings

100

11-Mar-09

18-Jun-09

Fab & Del [Sorbonne]- Valve (Potable Water)


Fab & Del - Temporary STP Tank
Fab & Del - Valve (Irrigation)
Fab & Del - Geotextile Fabric
Fab & Del - Traffic Sign
Fab & Del - Fire Hydrant & Fittings

A14190

Fab & Del - UPVC Pipe (Sewerage)

30

11-Mar-09

09-Apr-09

32

Fab & Del - UPVC Pipe (Sewerage)

A21750

Fab & Del - GRP Pipe (Sewerage)

28

11-Mar-09

07-Apr-09

34

Fab & Del - GRP Pipe (Sewerage)

A28770

Fab & Del - RC Pipe (Surface Water)

60

11-Mar-09

09-May-09

93

A21910

Fab & Del - HDPE Pipe (Potable Water)

60

12-Mar-09

10-May-09

22

Fab & Del - HDPE Pipe (Potable Water)

A21940

Fab & Del - GRP Duct Pipe (Potable Water)

42

12-Mar-09

22-Apr-09

40

Fab & Del - GRP Duct Pipe (Potable Water)

A29060

Fab & Del - GRP Duct Pipe (Surface Water)

42

12-Mar-09

22-Apr-09

110

Fab & Del - GRP Duct Pipe (Surface Water)

A14220

Fab & Del - HDPE Pipe (Irrigation)

60

27-Mar-09

25-May-09

47

A18300

Fab & Del - PE100 Pipe (Gas)

60

27-Mar-09

25-May-09

48

Fab & Del - PE100 Pipe (Gas)

A18330

Fab & Del - UPVC Duct(Telecom)

30

27-Mar-09

25-Apr-09

53

Fab & Del - UPVC Duct(Telecom)

A18550

Fab & Del - Valve (Gas)

100

27-Mar-09

04-Jul-09

25

A18640

Fab & Del - 22kv Cable (Power)

30

27-Mar-09

25-Apr-09

40

A21790

Fab & Del - LV Cable (Power)

90

27-Mar-09

24-Jun-09

82

A28330

Fab & Del - Valve (Potable Water)

100

27-Mar-09

04-Jul-09

60

A29040

Fab & Del - Light Pole & Luminaries

151

26-Apr-09

23-Sep-09

A21700

Fab & Del - LV Cable (Street Light)

90

26-May-09

23-Aug-09

22

A21710

Fab & Del - Control Cabinet (Street Light)

112

26-May-09

14-Sep-09

69

14

24-Feb-09

09-Mar-09

106

14

24-Feb-09

09-Mar-09

37

Procurement For Sorbonne Intersections/Crossings


A29500

Proc [Sorbonne] - UPVC Duct Pipe (Sewerage)

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 7 of 43

Fab & Del - RC Pipe (Surface Water)

Fab & Del - HDPE Pipe (Irrigation)

Fab & Del - Valve (Gas)


Fab & Del - 22kv Cable (Power)
Fab & Del - LV Cable (Power)
Fab & Del - Valve (Potable Water)
Fab & Del - Light Pole & Luminaries
Fab & Del - LV Cable (Street Light)

Fab & Del - Control Cabinet (Street Lig


Proc [Sorbonne] - UPVC Duct Pipe (Sewerage)

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

A29510

Proc [Sorbonne] - GRP Duct Pipe (Potable Water)

14

24-Feb-09

09-Mar-09

48

Proc [Sorbonne] - GRP Duct Pipe (Potable Water)

A29520

Proc [Sorbonne] - UPVC Duct Pipe (Gas)

14

24-Feb-09

09-Mar-09

76

Proc [Sorbonne] - UPVC Duct Pipe (Gas)

A29530

Proc [Sorbonne] - UPVC Duct Pipe (Street Lighting)

14

24-Feb-09

09-Mar-09

106

Proc [Sorbonne] - UPVC Duct Pipe (Street Lighting)

A29550

Proc [Sorbonne] - GRP Duct Pipe (Irrigation Water)

14

24-Feb-09

09-Mar-09

96

Proc [Sorbonne] - GRP Duct Pipe (Irrigation Water)

A29570

Proc [Sorbonne] - UPVC Duct Pipe (22kV)

14

24-Feb-09

09-Mar-09

84

Proc [Sorbonne] - UPVC Duct Pipe (22kV)

46

03-Feb-09

20-Mar-09

60

Pre-Construction Works

46

03-Feb-09

20-Mar-09

60

Site Preparation Works


A5730
Mobilization

46
21

03-Feb-09
03-Feb-09

20-Mar-09
23-Feb-09

60
60

Mobilization & Temporary Works

Mobilization

Site Clearance, Removal & Disposal of any Structures, Trees &

A1970

Site Clearance, Removal & Disposal of any Structures, Trees & Obstructions

10

24-Feb-09

05-Mar-09

60

A1620

Grading & Grabbing Works

10

06-Mar-09

15-Mar-09

60

Grading & Grabbing Works

A1650

Site Leveling Works

10

11-Mar-09

20-Mar-09

60

Site Leveling Works

331

27-Feb-09

23-Jan-10

76

10-Mar-09

24-May-09

37

32
11
3

10-Mar-09
10-Mar-09
10-Mar-09

10-Apr-09
20-Mar-09
12-Mar-09

51
37
37

<C5-SEW-CR>Excavation & Surface Preparation

Construction
Crossings For Sorbonne
Utilities in Crossing-C5
Sewerage Network
B6090
<C5-SEW-CR>Excavation & Surface Preparation
B6230

<C5-SEW-CR>Pipe Laying

13-Mar-09

16-Mar-09

37

<C5-SEW-CR>Pipe Laying

B6290

<C5-SEW-CR>Concrete Encasement

14-Mar-09

17-Mar-09

37

<C5-SEW-CR>Concrete Encasement

B6240

<C5-SEW-CR>Testing/Backfilling & Compaction

18-Mar-09

20-Mar-09

37

<C5-SEW-CR>Testing/Backfilling & Compaction

10
4

21-Mar-09
21-Mar-09

30-Mar-09
24-Mar-09

37
37

<C5-PW-CR>Excavation & Surface Preparation

Potable Water Network


B6580
<C5-PW-CR>Excavation & Surface Preparation
B6590

<C5-PW-CR>Pipe Laying

25-Mar-09

27-Mar-09

37

<C5-PW-CR>Pipe Laying

B6610

<C5-PW-CR>Concrete Encasement

26-Mar-09

28-Mar-09

37

<C5-PW-CR>Concrete Encasement

B6600

<C5-PW-CR>Testing/Backfilling & Compaction

Gas Network
B6320
<C5-Gas-CR>Excavation & Surface Preparation

29-Mar-09

30-Mar-09

37

<C5-PW-CR>Testing/Backfilling & Compaction

11
4

31-Mar-09
31-Mar-09

10-Apr-09
03-Apr-09

51
51

<C5-Gas-CR>Excavation & Surface Preparation

B6330

<C5-Gas-CR>Pipe Laying

04-Apr-09

06-Apr-09

51

<C5-Gas-CR>Pipe Laying

B6440

<C5-Gas--CR>Concrete Encasement

05-Apr-09

07-Apr-09

51

<C5-Gas--CR>Concrete Encasement

B6400

<C5-Gas-CR>Testing/Backfilling & Compaction

Utilities in Crossing-C4
Sewerage Network
B6100
<C4-SEW-CR>Excavation & Surface Preparation
B6250

<C4-SEW-CR>Pipe Laying

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

08-Apr-09

10-Apr-09

51

<C5-Gas-CR>Testing/Backfilling & Compaction

62
9
3

21-Mar-09
21-Mar-09
21-Mar-09

21-May-09
29-Mar-09
23-Mar-09

40
93
44

<C4-SEW-CR>Excavation & Surface Preparation

24-Mar-09

26-Mar-09

93

<C4-SEW-CR>Pipe Laying

Page 8 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

B6300

<C4-SEW-CR>Concrete Encasement

25-Mar-09

27-Mar-09

93

<C4-SEW-CR>Concrete Encasement

B6410

<C4-SEW-CR>Testing/Backfilling & Compaction

28-Mar-09

29-Mar-09

93

<C4-SEW-CR>Testing/Backfilling & Compaction

12
4

31-Mar-09
31-Mar-09

11-Apr-09
03-Apr-09

37
37

<C4-PW-CR>Excavation & Surface Preparation

Potable Water Network


B6640
<C4-PW-CR>Excavation & Surface Preparation
B6650

<C4-PW-CR>Pipe Laying

04-Apr-09

07-Apr-09

37

<C4-PW-CR>Pipe Laying

B6740

<C4-PW-CR>Concrete Encasement

05-Apr-09

08-Apr-09

37

<C4-PW-CR>Concrete Encasement

B6660

<C4-PW-CR>Testing/Backfilling & Compaction

09-Apr-09

11-Apr-09

37

<C4-PW-CR>Testing/Backfilling & Compaction

10
2

12-Apr-09
12-Apr-09

21-Apr-09
13-Apr-09

50
50

<C4-Gas-CR>Excavation & Surface Preparation

Gas Network
B6420
<C4-Gas-CR>Excavation & Surface Preparation
B6430

<C4-Gas-CR>Pipe Laying

14-Apr-09

17-Apr-09

50

<C4-Gas-CR>Pipe Laying

B6450

<C4-Gas-CR>Concrete Encasement

15-Apr-09

18-Apr-09

50

<C4-Gas-CR>Concrete Encasement

B6700

<C4-Gas-CR>Testing/Backfilling & Compaction

19-Apr-09

21-Apr-09

50

<C4-Gas-CR>Testing/Backfilling & Compaction

Irrigation Network
B6670
<C4-IRR-CR>Excavation & Surface Preparation

11
3

22-Apr-09
22-Apr-09

02-May-09
24-Apr-09

50
50

<C4-IRR-CR>Excavation & Surface Preparation

B6680

<C4-IRR-CR>Pipe Laying

25-Apr-09

28-Apr-09

50

<C4-IRR-CR>Pipe Laying

B6750

<C4-IRR-CR>Concrete Encasement

26-Apr-09

29-Apr-09

50

<C4-IRR-CR>Concrete Encasement

B6690

<C4-IRR-CR>Testing/Backfilling & Compaction

30-Apr-09

02-May-09

50

<C4-IRR-CR>Testing/Backfilling & Compaction

9
2

13-May-09
13-May-09

21-May-09
14-May-09

40
40

<C4-SL-CR>Excavation & Surface Preparation

Street Light Network


B6710
<C4-SL-CR>Excavation & Surface Preparation
B6720

<C4-SL-CR>Pipe Laying

15-May-09

17-May-09

40

<C4-SL-CR>Pipe Laying

B6760

<C4-SL-CR>Concrete Encasement

16-May-09

18-May-09

40

<C4-SL-CR>Concrete Encasement

B6730

<C4-SL-CR>Testing/Backfilling & Compaction

19-May-09

21-May-09

40

<C4-SL-CR>Testing/Backfilling & Compaction

9
9
2

12-Apr-09
12-Apr-09
12-Apr-09

20-Apr-09
20-Apr-09
13-Apr-09

71
71
37

<C3-PW-CR>Excavation & Surface Preparation

Utilities in Crossing-C3
Potable Water Network
B6830
<C3-PW-CR>Excavation & Surface Preparation
B6840

<C3-PW-CR>Pipe Laying

14-Apr-09

16-Apr-09

71

<C3-PW-CR>Pipe Laying

B6880

<C3-PW-CR>Concrete Encasement

15-Apr-09

17-Apr-09

71

<C3-PW-CR>Concrete Encasement

B6850

<C3-PW-CR>Testing/Backfilling & Compaction

18-Apr-09

20-Apr-09

71

<C3-PW-CR>Testing/Backfilling & Compaction

Utilities in Crossing-C2
Potable Water Network
A30430
<C2-PW-CR>Excavation & Surface Preparation

19
9
2

14-Apr-09
14-Apr-09
14-Apr-09

02-May-09
22-Apr-09
15-Apr-09

52
37
37

<C2-PW-CR>Excavation & Surface Preparation

A30440

<C2-PW-CR>Pipe Laying

16-Apr-09

18-Apr-09

37

<C2-PW-CR>Pipe Laying

A30450

<C2-PW-CR>Concrete Encasement

17-Apr-09

19-Apr-09

37

<C2-PW-CR>Concrete Encasement

A30460

<C2-PW-CR>Testing/Backfilling & Compaction

20-Apr-09

22-Apr-09

37

<C2-PW-CR>Testing/Backfilling & Compaction

10

23-Apr-09

02-May-09

52

Gas Network
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 9 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

B6890

<C2-Gas-CR>Excavation & Surface Preparation

23-Apr-09

25-Apr-09

52

<C2-Gas-CR>Excavation & Surface Preparation

B6900

<C2-Gas-CR>Pipe Laying

26-Apr-09

28-Apr-09

52

<C2-Gas-CR>Pipe Laying

B6960

<C2-Gas-CR>Concrete Encasement

27-Apr-09

29-Apr-09

52

<C2-Gas-CR>Concrete Encasement

B6910

<C2-Gas-CR>Testing/Backfilling & Compaction

30-Apr-09

02-May-09

52

<C2-Gas-CR>Testing/Backfilling & Compaction

Utilities in Crossing-B5
Potable Water Network
B6770
<B5-PW-CR>Excavation & Surface Preparation

22
15
4

23-Apr-09
23-Apr-09
23-Apr-09

14-May-09
07-May-09
26-Apr-09

47
37
37

<B5-PW-CR>Excavation & Surface Preparation

B6780

<B5-PW-CR>Pipe Laying

27-Apr-09

01-May-09

37

<B5-PW-CR>Pipe Laying

B6860

<B5-PW-CR>Concrete Encasement

28-Apr-09

02-May-09

37

<B5-PW-CR>Concrete Encasement

B6790

<B5-PW-CR>Testing/Backfilling & Compaction

03-May-09

07-May-09

37

<B5-PW-CR>Testing/Backfilling & Compaction

7
2

08-May-09
08-May-09

14-May-09
09-May-09

47
47

<B5-Gas-CR>Excavation & Surface Preparation

Gas Network
B6800
<B5-Gas-CR>Excavation & Surface Preparation
B6810

<B5-Gas-CR>Pipe Laying

10-May-09

11-May-09

47

<B5-Gas-CR>Pipe Laying

B6870

<B5-Gas-CR>Concrete Encasement

11-May-09

12-May-09

47

<B5-Gas-CR>Concrete Encasement

B6820

<B5-Gas-CR>Testing/Backfilling & Compaction

13-May-09

14-May-09

47

<B5-Gas-CR>Testing/Backfilling & Compaction

Utilities in Crossing-B4
Potable Water Network
B6920
<B4-PW-CR>Excavation & Surface Preparation

17
17
6

08-May-09
08-May-09
08-May-09

24-May-09
24-May-09
13-May-09

37
37
37

<B4-PW-CR>Excavation & Surface Preparation

B6930

<B4-PW-CR>Pipe Laying

14-May-09

18-May-09

37

<B4-PW-CR>Pipe Laying

B6950

<B4-PW-CR>Concrete Encasement

15-May-09

19-May-09

37

<B4-PW-CR>Concrete Encasement

B6940

<B4-PW-CR>Testing/Backfilling & Compaction

20-May-09

24-May-09

37

<B4-PW-CR>Testing/Backfilling & Compaction

79

27-Feb-09

16-May-09

45

24
20
7

27-Feb-09
27-Feb-09
27-Feb-09

22-Mar-09
18-Mar-09
05-Mar-09

75
79
83

Intersections For Sorbonne


Intersection1 [H3-H2-C5]
Sewerage Network
B6110
<Int1-SEW>Dewatering

<Int1-SEW>Dewatering

B6080

<Int1-SEW>Excavation & Surface Preparation

10-Mar-09

11-Mar-09

79

<Int1-SEW>Excavation & Surface Preparation

B6210

<Int1-SEW>Pipe Laying

12-Mar-09

14-Mar-09

79

<Int1-SEW>Pipe Laying

B6310

<Int1-SEW>Concrete Encasement

13-Mar-09

15-Mar-09

79

<Int1-SEW>Concrete Encasement

B6220

<Int1-SEW>Testing/Backfilling & Compaction

16-Mar-09

18-Mar-09

79

<Int1-SEW>Testing/Backfilling & Compaction

9
2

14-Mar-09
14-Mar-09

22-Mar-09
15-Mar-09

42
42

<Int1-PW>Excavation & Surface Preparation

Potable Water Network


B6550
<Int1-PW>Excavation & Surface Preparation
B6560

<Int1-PW>Pipe Laying

16-Mar-09

18-Mar-09

42

<Int1-PW>Pipe Laying

B6620

<Int1-PW>Concrete Encasement

17-Mar-09

19-Mar-09

42

<Int1-PW>Concrete Encasement

B6570

<Int1-PW>Testing/Backfilling & Compaction

20-Mar-09

22-Mar-09

42

<Int1-PW>Testing/Backfilling & Compaction

23-Mar-09

31-Mar-09

42

Intersection 2 [H4-H3-B5]
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 10 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Potable Water Network


B6370
<Int2-PW>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

9
2

23-Mar-09
23-Mar-09

31-Mar-09
24-Mar-09

42
42

<Int2-PW>Excavation & Surface Preparation

F M A M J Jul A S O N D

2010
J

F M

B6380

<Int2-PW>Pipe Laying

25-Mar-09

27-Mar-09

42

<Int2-PW>Pipe Laying

B6460

<Int2-PW>Concrete Encasement

26-Mar-09

28-Mar-09

42

<Int2-PW>Concrete Encasement

B6390

<Int2-PW>Testing/Backfilling & Compaction

29-Mar-09

31-Mar-09

42

<Int2-PW>Testing/Backfilling & Compaction

Intersection 3 [B4-B5-G3]
Potable Water Network
B5860
<Int3-PW>Excavation & Surface Preparation

9
9
2

01-Apr-09
01-Apr-09
01-Apr-09

09-Apr-09
09-Apr-09
02-Apr-09

42
42
42

<Int3-PW>Excavation & Surface Preparation

B5870

<Int3-PW>Pipe Laying

03-Apr-09

05-Apr-09

42

<Int3-PW>Pipe Laying

B5890

<Int3-PW>Concrete Encasement

04-Apr-09

06-Apr-09

42

<Int3-PW>Concrete Encasement

B5880

<Int3-PW>Testing/Backfilling & Compaction

07-Apr-09

09-Apr-09

42

<Int3-PW>Testing/Backfilling & Compaction

49
16
7

19-Mar-09
19-Mar-09
19-Mar-09

06-May-09
03-Apr-09
25-Mar-09

55
79
79

<Int4-SEW>Dewatering

Intersection 4 [C4-C5-G3]
Sewerage Network
B5970
<Int4-SEW>Dewatering
B5960

<Int4-SEW>Excavation & Surface Preparation

26-Mar-09

27-Mar-09

79

<Int4-SEW>Excavation & Surface Preparation

B6190

<Int4-SEW>Pipe Laying

28-Mar-09

30-Mar-09

79

<Int4-SEW>Pipe Laying

B6470

<Int4-SEW>Concrete Encasement

29-Mar-09

31-Mar-09

79

<Int4-SEW>Concrete Encasement

B6200

<Int4-SEW>Testing/Backfilling & Compaction

01-Apr-09

03-Apr-09

79

<Int4-SEW>Testing/Backfilling & Compaction

9
2

10-Apr-09
10-Apr-09

18-Apr-09
11-Apr-09

42
42

<Int4-PW>Excavation & Surface Preparation

Potable Water Network


B6340
<Int4-PW>Excavation & Surface Preparation
B6350

<Int4-PW>Pipe Laying

12-Apr-09

14-Apr-09

42

<Int4-PW>Pipe Laying

B6480

<Int4-PW>Concrete Encasement

13-Apr-09

15-Apr-09

42

<Int4-PW>Concrete Encasement

B6360

<Int4-PW>Testing/Backfilling & Compaction

16-Apr-09

18-Apr-09

42

<Int4-PW>Testing/Backfilling & Compaction

9
2

04-Apr-09
04-Apr-09

12-Apr-09
05-Apr-09

79
79

<Int4-Gas>Excavation & Surface Preparation

Gas Network
B6260
<Int4-Gas>Excavation & Surface Preparation
B6270

<Int4-Gas>Pipe Laying

06-Apr-09

08-Apr-09

79

<Int4-Gas>Pipe Laying

B6490

<Int4-Gas>Concrete Encasement

07-Apr-09

09-Apr-09

79

<Int4-Gas>Concrete Encasement

B6280

<Int4-Gas>Testing/Backfilling & Compaction

10-Apr-09

12-Apr-09

79

<Int4-Gas>Testing/Backfilling & Compaction

9
2

28-Apr-09
28-Apr-09

06-May-09
29-Apr-09

55
33

<Int4-22kV>Excavation & Surface Preparation

22kV Network
B22130
<Int4-22kV>Excavation & Surface Preparation
B22140

<Int4-22kV>Pipe Laying

30-Apr-09

02-May-09

33

<Int4-22kV>Pipe Laying

B22160

<Int4-22kV>Concrete Encasement

01-May-09

03-May-09

55

<Int4-22kV>Concrete Encasement

B22150

<Int4-22kV>Testing/Backfilling & Compaction

04-May-09

06-May-09

55

<Int4-22kV>Testing/Backfilling & Compaction

14
14

19-Apr-09
19-Apr-09

02-May-09
02-May-09

45
45

Intersection 5 [C3-C4-F3]
Potable Water Network
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 11 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

F M A M J Jul A S O N D

2010
J

F M

B5350

<Int5-PW>Dewatering

19-Apr-09

25-Apr-09

45

<Int5-PW>Dewatering

B5270

<Int5-PW>Excavation & Surface Preparation

26-Apr-09

27-Apr-09

45

<Int5-PW>Excavation & Surface Preparation

B5280

<Int5-PW>Pipe Laying

28-Apr-09

29-Apr-09

45

<Int5-PW>Pipe Laying

B5300

<Int5-PW>Concrete Encasement

29-Apr-09

30-Apr-09

45

<Int5-PW>Concrete Encasement

B5290

<Int5-PW>Testing/Backfilling & Compaction

01-May-09

02-May-09

45

<Int5-PW>Testing/Backfilling & Compaction

Intersection 6 [B4-F3]
Potable Water Network
B6500
<Int6-PW>Excavation & Surface Preparation

7
7
2

03-May-09
03-May-09
03-May-09

09-May-09
09-May-09
04-May-09

45
45
45

<Int6-PW>Excavation & Surface Preparation

B6510

<Int6-PW>Pipe Laying

05-May-09

06-May-09

45

<Int6-PW>Pipe Laying

B6530

<Int6-PW>Concrete Encasement

06-May-09

07-May-09

45

<Int6-PW>Concrete Encasement

B6520

<Int6-PW>Testing/Backfilling & Compaction

08-May-09

09-May-09

45

<Int6-PW>Testing/Backfilling & Compaction

Intersection 7 [C2-C3-J2]
Potable Water Network
B4690
<Int7-PW>Excavation & Surface Preparation

7
7
2

10-May-09
10-May-09
10-May-09

16-May-09
16-May-09
11-May-09

45
45
45

<Int7-PW>Excavation & Surface Preparation

B4700

<Int7-PW>Pipe Laying

12-May-09

13-May-09

45

<Int7-PW>Pipe Laying

B4710

<Int7-PW>Concrete Encasement

13-May-09

14-May-09

45

<Int7-PW>Concrete Encasement

B4750

<Int7-PW>Testing/Backfilling & Compaction

15-May-09

16-May-09

45

<Int7-PW>Testing/Backfilling & Compaction

109

14-Mar-09

30-Jun-09

89
89
89
44
6

14-Mar-09
14-Mar-09
14-Mar-09
14-Mar-09
14-Mar-09

10-Jun-09
10-Jun-09
10-Jun-09
26-Apr-09
19-Mar-09

20
20
20
0
17

<C5-SEW-R>Excavation & Surface Preparation


<C5-SEW-R>Manhole

Utilities of Sorbonne Route


<C5>Road C5
Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B16830 <C5-SEW-R>Excavation & Surface Preparation
B16850

<C5-SEW-R>Manhole

16-Mar-09

22-Mar-09

17

B16840

<C5-SEW-R>Pipe Laying

05-Apr-09

11-Apr-09

<C5-SEW-R>Pipe Laying

B16860

<C5-SEW-R>Inspection & Testing

06-Apr-09

12-Apr-09

<C5-SEW-R>Inspection & Testing

B16870

<C5-SEW-R>Backfilling & Compaction

17

07-Apr-09

26-Apr-09

25
7

27-Apr-09
27-Apr-09

21-May-09
04-May-09

0
0

<C5-PW-R>Excavation & Surface Preparation

Potable Water Network


B16980 <C5-PW-R>Excavation & Surface Preparation

<C5-SEW-R>Backfilling & Compaction

B16990

<C5-PW-R>Pipe Laying

29-Apr-09

06-May-09

<C5-PW-R>Pipe Laying

B17000

<C5-PW-R>Valve Chamber

05-May-09

09-May-09

<C5-PW-R>Valve Chamber

B17010

<C5-PW-R>Valve Fittings

07-May-09

11-May-09

<C5-PW-R>Valve Fittings

B17020

<C5-PW-R>Fire Hydrant

10-May-09

16-May-09

<C5-PW-R>Fire Hydrant

B17030

<C5-PW-R>Inspection & Testing

16-May-09

17-May-09

<C5-PW-R>Inspection & Testing

B17040

<C5-PW-R>Backfilling & Compaction

18-May-09

21-May-09

<C5-PW-R>Backfilling & Compaction

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 12 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name
Telecommunication Network
B11620 <C5-Tele-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

11
3

23-May-09
23-May-09

02-Jun-09
25-May-09

0
0

<C5-Tele-R>Excavation & Surface Preparation

F M A M J Jul A S O N D

2010
J

F M

B16880

<C5-Tele-R>Duct Laying

25-May-09

27-May-09

<C5-Tele-R>Duct Laying

B16890

<C5-Tele-R>Joint Box

27-May-09

30-May-09

<C5-Tele-R>Joint Box

B16900

<C5-Tele-R>Inspection & Testing

30-May-09

31-May-09

<C5-Tele-R>Inspection & Testing

B16910

<C5-Tele-R>Backfilling & Compaction

31-May-09

02-Jun-09

<C5-Tele-R>Backfilling & Compaction

8
3

03-Jun-09
03-Jun-09

10-Jun-09
06-Jun-09

20
0

22kV Network
B17050 <C5-22kV-R>Excavation & Surface Preparation

<C5-22kV-R>Excavation & Surface Preparation


<C5-22kV-R>Cable Laying

B17060

<C5-22kV-R>Cable Laying

04-Jun-09

07-Jun-09

B17070

<C5-22kV-R>Inspection & Testing

07-Jun-09

08-Jun-09

17

<C5-22kV-R>Inspection & Testing

B17090

<C5-22kV-R>Backfilling & Compaction

<C5-22kV-R>Backfilling & Compaction

Utilities in Corridors (Left Side)


Sewerage Network
B16950 <C5-SEW-L>Excavation & Surface Preparation

09-Jun-09

10-Jun-09

17

55
33
7

21-Mar-09
21-Mar-09
21-Mar-09

14-May-09
22-Apr-09
28-Mar-09

47
13
21

<C5-SEW-L>Excavation & Surface Preparation


<C5-SEW-L>Manhole

B17260

<C5-SEW-L>Manhole

24-Mar-09

30-Mar-09

21

B17080

<C5-SEW-L>Pipe Laying

05-Apr-09

11-Apr-09

11

<C5-SEW-L>Pipe Laying

B17270

<C5-SEW-L>Inspection & Testing

06-Apr-09

12-Apr-09

11

<C5-SEW-L>Inspection & Testing

B17250

<C5-SEW-L>Backfilling & Compaction

14

07-Apr-09

22-Apr-09

11

22
7

23-Apr-09
23-Apr-09

14-May-09
30-Apr-09

47
11

<C5-Gas-L>Excavation & Surface Preparation

Gas Network
B17100 <C5-Gas-L>Excavation & Surface Preparation

<C5-SEW-L>Backfilling & Compaction

B17110

<C5-Gas-L>Pipe Laying

26-Apr-09

03-May-09

11

<C5-Gas-L>Pipe Laying

B17120

<C5-Gas-L>Valve Fittings

28-Apr-09

05-May-09

40

<C5-Gas-L>Valve Fittings

B17130

<C5-Gas-L>Inspection & Testing

05-May-09

06-May-09

40

<C5-Gas-L>Inspection & Testing

B17140

<C5-Gas-L>Backfilling & Compaction

<C4>Road C4
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B16420 <C4-PW-R>Excavation & Surface Preparation

<C5-Gas-L>Backfilling & Compaction

06-May-09

14-May-09

40

94
94
57
24
7

29-Mar-09
29-Mar-09
05-May-09
05-May-09
05-May-09

30-Jun-09
30-Jun-09
30-Jun-09
28-May-09
12-May-09

0
0
0
9
7

<C4-PW-R>Excavation & Surface Preparation

B16430

<C4-PW-R>Pipe Laying

07-May-09

14-May-09

<C4-PW-R>Pipe Laying

B16440

<C4-PW-R>Valve Chamber

12-May-09

17-May-09

<C4-PW-R>Valve Chamber

B16450

<C4-PW-R>Valve Fittings

14-May-09

19-May-09

<C4-PW-R>Valve Fittings

B16460

<C4-PW-R>Fire Hydrant

17-May-09

23-May-09

<C4-PW-R>Fire Hydrant

B16470

<C4-PW-R>Inspection & Testing

23-May-09

24-May-09

<C4-PW-R>Inspection & Testing

B16480

<C4-PW-R>Backfilling & Compaction

25-May-09

28-May-09

<C4-PW-R>Backfilling & Compaction

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 13 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name
22kV Network
B16490 <C4-22kV-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

10
4

07-Jun-09
07-Jun-09

16-Jun-09
10-Jun-09

0
0

<C4-22kV-R>Excavation & Surface Preparation

F M A M J Jul A S O N D

2010
J

F M

B16500

<C4-22kV-R>Cable Laying

09-Jun-09

13-Jun-09

<C4-22kV-R>Cable Laying

B16510

<C4-22kV-R>Inspection & Testing

13-Jun-09

14-Jun-09

<C4-22kV-R>Inspection & Testing

B16530

<C4-22kV-R>Backfilling & Compaction

15-Jun-09

16-Jun-09

<C4-22kV-R>Backfilling & Compaction

14
4

17-Jun-09
17-Jun-09

30-Jun-09
21-Jun-09

0
0

<C4-LV-R>Excavation & Surface Preparation

LV Network
B16700 <C4-LV-R>Excavation & Surface Preparation
B16710

<C4-LV-R>Cable Laying

20-Jun-09

23-Jun-09

<C4-LV-R>Cable Laying

B16720

<C4-LV-R>Inspection & Testing

24-Jun-09

25-Jun-09

<C4-LV-R>Inspection & Testing

B16740

<C4-LV-R>Backfilling & Compaction

27-Jun-09

30-Jun-09

<C4-LV-R>Backfilling & Compaction

85
33
8

29-Mar-09
29-Mar-09
29-Mar-09

21-Jun-09
30-Apr-09
06-Apr-09

9
13
21

<C4-SEW-L>Excavation & Surface Preparation


<C4-SEW-L>Manhole

Utilities in Corridors (Left Side)


Sewerage Network
B16540 <C4-SEW-L>Excavation & Surface Preparation
B16560

<C4-SEW-L>Manhole

31-Mar-09

08-Apr-09

21

B16550

<C4-SEW-L>Pipe Laying

12-Apr-09

20-Apr-09

11

<C4-SEW-L>Pipe Laying

B16570

<C4-SEW-L>Inspection & Testing

13-Apr-09

21-Apr-09

11

<C4-SEW-L>Inspection & Testing

B16580

<C4-SEW-L>Backfilling & Compaction

15

14-Apr-09

30-Apr-09

11

19
7

02-May-09
02-May-09

20-May-09
09-May-09

13
11

<C4-Gas-L>Excavation & Surface Preparation

Gas Network
B16650 <C4-Gas-L>Excavation & Surface Preparation

<C4-SEW-L>Backfilling & Compaction

B16660

<C4-Gas-L>Pipe Laying

04-May-09

11-May-09

11

<C4-Gas-L>Pipe Laying

B16670

<C4-Gas-L>Valve Fittings

09-May-09

13-May-09

11

<C4-Gas-L>Valve Fittings

B16680

<C4-Gas-L>Inspection & Testing

13-May-09

14-May-09

11

<C4-Gas-L>Inspection & Testing

B16690

<C4-Gas-L>Backfilling & Compaction

14-May-09

20-May-09

11

17
7

26-May-09
26-May-09

11-Jun-09
02-Jun-09

10
7

Telecommunication Network
B16590 <C4-Tele-L>Excavation & Surface Preparation

<C4-Gas-L>Backfilling & Compaction


<C4-Tele-L>Excavation & Surface Preparation

B16600

<C4-Tele-L>Duct Laying

28-May-09

04-Jun-09

<C4-Tele-L>Duct Laying

B16610

<C4-Tele-L>Joint Box

31-May-09

07-Jun-09

<C4-Tele-L>Joint Box

B16620

<C4-Tele-L>Manhole

31-May-09

07-Jun-09

<C4-Tele-L>Manhole

B16630

<C4-Tele-L>Inspection & Testing

02-Jun-09

09-Jun-09

<C4-Tele-L>Inspection & Testing

B16640

<C4-Tele-L>Backfilling & Compaction

04-Jun-09

11-Jun-09

<C4-Tele-L>Backfilling & Compaction

9
4

13-Jun-09
13-Jun-09

21-Jun-09
16-Jun-09

9
8

<C4-22kV-L>Excavation & Surface Preparation

22kV Network
B16770 <C4-22kV-L>Excavation & Surface Preparation
B16780

<C4-22kV-L>Cable Laying

15-Jun-09

18-Jun-09

<C4-22kV-L>Cable Laying

B16790

<C4-22kV-L>Inspection & Testing

17-Jun-09

20-Jun-09

<C4-22kV-L>Inspection & Testing

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 14 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name
B16810

<C4-22kV-L>Backfilling & Compaction

<H3>Road H3
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B18810 <H3-PW-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

20-Jun-09

21-Jun-09

<C4-22kV-L>Backfilling & Compaction

26
26
26
26
7

13-May-09
13-May-09
13-May-09
13-May-09
13-May-09

07-Jun-09
07-Jun-09
07-Jun-09
07-Jun-09
20-May-09

23
23
23
23
9

<H3-PW-R>Excavation & Surface Preparation

F M A M J Jul A S O N D

2010
J

F M

<H3-PW-R>Pipe Laying

B18820

<H3-PW-R>Pipe Laying

16-May-09

23-May-09

B18830

<H3-PW-R>Valve Chamber

21-May-09

25-May-09

20

<H3-PW-R>Valve Chamber

B18840

<H3-PW-R>Valve Fittings

24-May-09

27-May-09

20

<H3-PW-R>Valve Fittings

B18850

<H3-PW-R>Fire Hydrant

26-May-09

01-Jun-09

20

<H3-PW-R>Fire Hydrant

B18860

<H3-PW-R>Inspection & Testing

01-Jun-09

02-Jun-09

20

<H3-PW-R>Inspection & Testing

B18870

<H3-PW-R>Backfilling & Compaction

03-Jun-09

07-Jun-09

20

<H3-PW-R>Backfilling & Compaction

77
77
27
27
9

07-Apr-09
07-Apr-09
21-May-09
21-May-09
21-May-09

22-Jun-09
22-Jun-09
16-Jun-09
16-Jun-09
31-May-09

8
8
14
14
9

<B5>Road B5
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B15660 <B5-PW-R>Excavation & Surface Preparation

<B5-PW-R>Excavation & Surface Preparation


<B5-PW-R>Pipe Laying

B15670

<B5-PW-R>Pipe Laying

24-May-09

02-Jun-09

B15680

<B5-PW-R>Valve Chamber

31-May-09

04-Jun-09

12

<B5-PW-R>Valve Chamber

B15690

<B5-PW-R>Valve Fittings

02-Jun-09

07-Jun-09

12

<B5-PW-R>Valve Fittings

B15700

<B5-PW-R>Fire Hydrant

04-Jun-09

10-Jun-09

12

<B5-PW-R>Fire Hydrant

B15710

<B5-PW-R>Inspection & Testing

10-Jun-09

11-Jun-09

12

<B5-PW-R>Inspection & Testing

B15720

<B5-PW-R>Backfilling & Compaction

11-Jun-09

16-Jun-09

12

<B5-PW-R>Backfilling & Compaction

77
29
7

07-Apr-09
07-Apr-09
07-Apr-09

22-Jun-09
05-May-09
14-Apr-09

8
36
34

<B5-SEW-L>Excavation & Surface Preparation


<B5-SEW-L>Manhole

Utilities in Corridors (Left Side)


Sewerage Network
B15730 <B5-SEW-L>Excavation & Surface Preparation
B15750

<B5-SEW-L>Manhole

09-Apr-09

16-Apr-09

41

B15740

<B5-SEW-L>Pipe Laying

21-Apr-09

28-Apr-09

24

<B5-SEW-L>Pipe Laying

B15760

<B5-SEW-L>Inspection & Testing

22-Apr-09

29-Apr-09

31

<B5-SEW-L>Inspection & Testing

B15770

<B5-SEW-L>Backfilling & Compaction

11

23-Apr-09

05-May-09

31

20
10

03-Jun-09
03-Jun-09

22-Jun-09
14-Jun-09

8
7

<B5-Tele-L>Excavation & Surface Preparation

Telecommunication Network
B15780 <B5-Tele-L>Excavation & Surface Preparation

<B5-SEW-L>Backfilling & Compaction

B15790

<B5-Tele-L>Duct Laying

10

06-Jun-09

16-Jun-09

<B5-Tele-L>Duct Laying

B15800

<B5-Tele-L>Joint Box

13-Jun-09

17-Jun-09

<B5-Tele-L>Joint Box

B15810

<B5-Tele-L>Inspection & Testing

15-Jun-09

20-Jun-09

<B5-Tele-L>Inspection & Testing

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 15 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name
B15820

<B5-Tele-L>Backfilling & Compaction

<C3>Road C3
Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B15990 <C3-SEW-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

20-Jun-09

22-Jun-09

104
104
104
36
4

14-Mar-09
14-Mar-09
14-Mar-09
14-Mar-09
14-Mar-09

25-Jun-09
25-Jun-09
25-Jun-09
18-Apr-09
17-Mar-09

5
5
5
2
19

<C3-SEW-R>Excavation & Surface Preparation


<C3-SEW-R>Manhole

F M A M J Jul A S O N D

2010
J

B16010

<C3-SEW-R>Manhole

15-Mar-09

18-Mar-09

20

B16000

<C3-SEW-R>Pipe Laying

05-Apr-09

08-Apr-09

<C3-SEW-R>Pipe Laying

B16020

<C3-SEW-R>Inspection & Testing

08-Apr-09

09-Apr-09

<C3-SEW-R>Inspection & Testing

B16030

<C3-SEW-R>Backfilling & Compaction

Potable Water Network


B16170 <C3-PW-R>Excavation & Surface Preparation

F M

<B5-Tele-L>Backfilling & Compaction

<C3-SEW-R>Backfilling & Compaction

09-Apr-09

18-Apr-09

25
7

19-Apr-09
19-Apr-09

13-May-09
26-Apr-09

3
2

<C3-PW-R>Excavation & Surface Preparation

B16180

<C3-PW-R>Pipe Laying

21-Apr-09

28-Apr-09

<C3-PW-R>Pipe Laying

B16190

<C3-PW-R>Valve Chamber

26-Apr-09

30-Apr-09

<C3-PW-R>Valve Chamber

B16200

<C3-PW-R>Valve Fittings

28-Apr-09

03-May-09

<C3-PW-R>Valve Fittings

B16210

<C3-PW-R>Fire Hydrant

30-Apr-09

06-May-09

<C3-PW-R>Fire Hydrant

B16220

<C3-PW-R>Inspection & Testing

06-May-09

07-May-09

<C3-PW-R>Inspection & Testing

B16230

<C3-PW-R>Backfilling & Compaction

09-May-09

13-May-09

18
7

14-May-09
14-May-09

31-May-09
21-May-09

4
2

<C3-Gas-R>Excavation & Surface Preparation

Gas Network
B16300 <C3-Gas-R>Excavation & Surface Preparation

<C3-PW-R>Backfilling & Compaction

B16310

<C3-Gas-R>Pipe Laying

17-May-09

24-May-09

<C3-Gas-R>Pipe Laying

B16320

<C3-Gas-R>Valve Fittings

23-May-09

26-May-09

<C3-Gas-R>Valve Fittings

B16330

<C3-Gas-R>Inspection & Testing

26-May-09

27-May-09

<C3-Gas-R>Inspection & Testing

B16340

<C3-Gas-R>Backfilling & Compaction

27-May-09

31-May-09

<C3-Gas-R>Backfilling & Compaction

17
7

01-Jun-09
01-Jun-09

17-Jun-09
08-Jun-09

5
4

<C3-Tele-R>Excavation & Surface Preparation

Telecommunication Network
B16040 <C3-Tele-R>Excavation & Surface Preparation
B16050

<C3-Tele-R>Duct Laying

03-Jun-09

10-Jun-09

<C3-Tele-R>Duct Laying

B16060

<C3-Tele-R>Joint Box

08-Jun-09

11-Jun-09

<C3-Tele-R>Joint Box

B16070

<C3-Tele-R>Manhole

10-Jun-09

13-Jun-09

<C3-Tele-R>Manhole

B16080

<C3-Tele-R>Inspection & Testing

14-Jun-09

15-Jun-09

<C3-Tele-R>Inspection & Testing

B16090

<C3-Tele-R>Backfilling & Compaction

15-Jun-09

17-Jun-09

<C3-Tele-R>Backfilling & Compaction

8
2

18-Jun-09
18-Jun-09

25-Jun-09
20-Jun-09

5
4

<C3-22kV-R>Excavation & Surface Preparation

22kV Network
B16240 <C3-22kV-R>Excavation & Surface Preparation
B16250

<C3-22kV-R>Cable Laying

21-Jun-09

22-Jun-09

<C3-22kV-R>Cable Laying

B16260

<C3-22kV-R>Inspection & Testing

23-Jun-09

24-Jun-09

<C3-22kV-R>Inspection & Testing

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 16 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name
B16280

<C3-22kV-R>Backfilling & Compaction

<C2>Road C2
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B16270 <C2-PW-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

24-Jun-09

25-Jun-09

53
53
53
27
7

27-Apr-09
27-Apr-09
27-Apr-09
27-Apr-09
27-Apr-09

18-Jun-09
18-Jun-09
18-Jun-09
23-May-09
04-May-09

12
12
12
28
15

<C2-PW-R>Excavation & Surface Preparation

F M A M J Jul A S O N D

2010
J

F M

<C3-22kV-R>Backfilling & Compaction

B16350

<C2-PW-R>Pipe Laying

29-Apr-09

06-May-09

15

<C2-PW-R>Pipe Laying

B16370

<C2-PW-R>Valve Chamber

04-May-09

09-May-09

24

<C2-PW-R>Valve Chamber

B16380

<C2-PW-R>Valve Fittings

06-May-09

11-May-09

24

<C2-PW-R>Valve Fittings

B16390

<C2-PW-R>Fire Hydrant

09-May-09

14-May-09

24

<C2-PW-R>Fire Hydrant

B16400

<C2-PW-R>Inspection & Testing

16-May-09

17-May-09

24

<C2-PW-R>Inspection & Testing

B16360

<C2-PW-R>Backfilling & Compaction

18-May-09

23-May-09

24

10
2

09-Jun-09
09-Jun-09

18-Jun-09
10-Jun-09

12
10

<C2-Tele-R>Excavation & Surface Preparation

Telecommunication Network
B15830 <C2-Tele-R>Excavation & Surface Preparation

<C2-PW-R>Backfilling & Compaction

B15840

<C2-Tele-R>Duct Laying

11-Jun-09

13-Jun-09

10

<C2-Tele-R>Duct Laying

B15850

<C2-Tele-R>Joint Box

14-Jun-09

15-Jun-09

10

<C2-Tele-R>Joint Box

B15860

<C2-Tele-R>Inspection & Testing

16-Jun-09

17-Jun-09

10

<C2-Tele-R>Inspection & Testing

B15870

<C2-Tele-R>Backfilling & Compaction

17-Jun-09

18-Jun-09

10

<C2-Tele-R>Backfilling & Compaction

21
21
21
21
4

05-May-09
05-May-09
05-May-09
05-May-09
05-May-09

25-May-09
25-May-09
25-May-09
25-May-09
09-May-09

36
36
36
36
15

<A3-PW-R>Excavation & Surface Preparation

<A3> Road A3
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B16410 <A3-PW-R>Excavation & Surface Preparation
B16520

<A3-PW-R>Pipe Laying

07-May-09

11-May-09

15

<A3-PW-R>Pipe Laying

B16730

<A3-PW-R>Valve Chamber

10-May-09

13-May-09

31

<A3-PW-R>Valve Chamber

B16800

<A3-PW-R>Valve Fittings

12-May-09

16-May-09

31

<A3-PW-R>Valve Fittings

B16920

<A3-PW-R>Fire Hydrant

17-May-09

18-May-09

31

<A3-PW-R>Fire Hydrant

B16930

<A3-PW-R>Inspection & Testing

19-May-09

20-May-09

31

<A3-PW-R>Inspection & Testing

B16940

<A3-PW-R>Backfilling & Compaction

21-May-09

25-May-09

31

<A3-PW-R>Backfilling & Compaction

309

21-Mar-09

23-Jan-10

285
285
212
4

21-Mar-09
21-Mar-09
21-Mar-09
21-Mar-09

30-Dec-09
30-Dec-09
18-Oct-09
24-Mar-09

24
24
91
52

15

04-Oct-09

18-Oct-09

91

Local Roads
Road 8
<8>Road 8
Utility Corridors
A5250
<R8-EW-UC>Earthworks for Utility Corridors
Interlock Paving for Utility Corridors
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 17 of 43

<R8-EW-UC>Earthworks for Utility Corridors

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A9240

<R8-SGIP-UC>Subgarde for Interlock Paving

04-Oct-09

07-Oct-09

<R8-SGIP-UC>Subgarde for Interlo

A9270

<R8-AGB-UC>150mm Aggregate Base Course for Interlock Paving

08-Oct-09

10-Oct-09

75

<R8-AGB-UC>150mm Aggregate

A9280

<R8-COS-UC>50mm Black Sand for Interlock Paving

11-Oct-09

12-Oct-09

75

<R8-COS-UC>50mm Black Sand

A9290

<R8-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

13-Oct-09

15-Oct-09

75

<R8-IVP-UC>Installing 60mm Inte

A9300

<R8-SFM-UC>Sand Filler Material for Interlock Paving

17-Oct-09

18-Oct-09

75

<R8-SFM-UC>Sand Filler Materia

266
4

25-Mar-09
25-Mar-09

15-Dec-09
29-Mar-09

0
159

Roads Carriage Corridor


A9310
<R8-EW-CC>Earthworks

<R8-EW-CC>Earthworks
<R8-SG-CC>Sub grade

A9320

<R8-SG-CC>Sub grade

04-Oct-09

06-Oct-09

A9250

<R8-CS-UC>Curb Stone

11

08-Oct-09

20-Oct-09

A9330

<R8-GT-CC>Geo textile Surface

21-Oct-09

22-Oct-09

16

<R8-GT-CC>Geo textile Surface

A9340

<R8-AGB-CC>300mm Aggregate Base Course

24-Oct-09

25-Oct-09

16

<R8-AGB-CC>300mm Aggregat

A9350

<R8-ASB-CC>180mm Asphalt Base Course

26-Oct-09

27-Oct-09

21

<R8-ASB-CC>180mm Asphalt B

A9360

<R8-ASW-CC>100mm Asphalt Wearing Course

10-Dec-09

15-Dec-09

<R8-ASW-CC>100mm As

147
145
17
4

10-May-09
10-May-09
10-May-09
10-May-09

03-Oct-09
01-Oct-09
26-May-09
13-May-09

0
2
15
13

<R8-SEW-R>Excavation & Surface Preparation

B12750 <R8-SEW-R>Pipe Laying

12-May-09

16-May-09

13

<R8-SEW-R>Pipe Laying

B12760 <R8-SEW-R>Manhole

12-May-09

16-May-09

13

<R8-SEW-R>Manhole

B15180 <R8-SEW-R>Inspection & Testing

14-May-09

17-May-09

13

<R8-SEW-R>Inspection & Testing

B12770 <R8-SEW-R>Backfilling & Compaction

10

16-May-09

26-May-09

13

30
7

01-Jun-09
01-Jun-09

30-Jun-09
08-Jun-09

5
9

<R8-PW-R>Excavation & Surface Preparation

B12920 <R8-PW-R>Pipe Laying

03-Jun-09

10-Jun-09

<R8-PW-R>Pipe Laying

B12930 <R8-PW-R>Valve Chamber

09-Jun-09

13-Jun-09

<R8-PW-R>Valve Chamber

B12940 <R8-PW-R>Valve Fittings

11-Jun-09

15-Jun-09

<R8-PW-R>Valve Fittings

B12950 <R8-PW-R>Fire Hydrant

20-Jun-09

25-Jun-09

<R8-PW-R>Fire Hydrant

B15240 <R8-PW-R>Inspection & Testing

25-Jun-09

27-Jun-09

<R8-PW-R>Inspection & Testing

B12960 <R8-PW-R>Backfilling & Compaction

27-Jun-09

30-Jun-09

<R8-PW-R>Backfilling & Compaction

23
6

01-Jul-09
01-Jul-09

23-Jul-09
07-Jul-09

72
4

B12880 <R8-Gas-R>Pipe Laying

08-Jul-09

14-Jul-09

B12890 <R8-Gas-R>Valve Fittings

12-Jul-09

16-Jul-09

59

<R8-Gas-R>Valve Fittings

B15230 <R8-Gas-R>Inspection & Testing

16-Jul-09

18-Jul-09

59

<R8-Gas-R>Inspection & Testing

Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B12740 <R8-SEW-R>Excavation & Surface Preparation

Potable Water Network


B12910 <R8-PW-R>Excavation & Surface Preparation

Gas Network
B12870 <R8-Gas-R>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 18 of 43

<R8-CS-UC>Curb Stone

<R8-SEW-R>Backfilling & Compaction

<R8-Gas-R>Excavation & Surface Preparation


<R8-Gas-R>Pipe Laying

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

18-Jul-09

23-Jul-09

59

26
7

30-Jun-09
30-Jun-09

25-Jul-09
07-Jul-09

9
8

<R8-IRR-R>Excavation & Surface Preparation

B12980 <R8-IRR-R>Pipe Laying

02-Jul-09

09-Jul-09

<R8-IRR-R>Pipe Laying

B12990 <R8-IRR-R>Valve Chamber

07-Jul-09

12-Jul-09

<R8-IRR-R>Valve Chamber

B13000 <R8-IRR-R>Valve Fittings

09-Jul-09

14-Jul-09

<R8-IRR-R>Valve Fittings

B15250 <R8-IRR-R>Inspection & Testing

15-Jul-09

16-Jul-09

<R8-IRR-R>Inspection & Testing

B15260 <R8-IRR-R>Backfilling & Compaction

18-Jul-09

25-Jul-09

12
3

26-Jul-09
26-Jul-09

06-Aug-09
28-Jul-09

58
8

B12830 <R8-Tele-R>Duct Laying

28-Jul-09

30-Jul-09

B12850 <R8-Tele-R>Joint Box

30-Jul-09

02-Aug-09

48

<R8-Tele-R>Joint Box

B12840 <R8-Tele-R>Manhole

30-Jul-09

02-Aug-09

47

<R8-Tele-R>Manhole

B15220 <R8-Tele-R>Inspection & Testing

03-Aug-09

04-Aug-09

47

<R8-Tele-R>Inspection & Testing

B12860 <R8-Tele-R>Backfilling & Compaction

04-Aug-09

06-Aug-09

47

<R8-Tele-R>Backfilling & Compaction

18
7

30-Jul-09
30-Jul-09

16-Aug-09
06-Aug-09

27
8

<R8-STORM-R>Excavation & Surface Pre

B12900 <R8-Gas-R>Backfilling & Compaction


Irrigation Network
B12970 <R8-IRR-R>Excavation & Surface Preparation

Telecommunication Network
B12820 <R8-Tele-R>Excavation & Surface Preparation

Surface Water Network


A9370 <R8-STORM-R>Excavation & Surface Preparation

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R8-Gas-R>Backfilling & Compaction

<R8-IRR-R>Backfilling & Compaction

<R8-Tele-R>Excavation & Surface Preparat


<R8-Tele-R>Duct Laying

<R8-STORM-R>Pipe Laying

A9380

<R8-STORM-R>Pipe Laying

02-Aug-09

09-Aug-09

A9390

<R8-STORM-R>Manhole

08-Aug-09

11-Aug-09

23

<R8-STORM-R>Manhole

A9400

<R8-STORM-R>Inspection & Testing

11-Aug-09

12-Aug-09

23

<R8-STORM-R>Inspection & Testing

A9410

<R8-STORM-R>Backfilling & Compaction

12-Aug-09

16-Aug-09

23

<R8-STORM-R>Backfilling & Compaction

34
2

29-Aug-09
29-Aug-09

01-Oct-09
30-Aug-09

2
13

<R8-SL-R>Excavation & Surface Prepa

B12790 <R8-SL-R>Cable Laying

31-Aug-09

01-Sep-09

13

<R8-SL-R>Cable Laying

B12800 <R8-SL-R>Smart Pole Foundation

02-Sep-09

05-Sep-09

16

<R8-SL-R>Smart Pole Foundation

B15190 <R8-SL-R>Smart Pole Erection

24-Sep-09

27-Sep-09

<R8-SL-R>Smart Pole Erection

B15200 <R8-SL-R>Inspection & Testing

28-Sep-09

29-Sep-09

<R8-SL-R>Inspection & Testing

B12810 <R8-SL-R>Backfilling & Compaction

30-Sep-09

01-Oct-09

<R8-SL-R>Backfilling & Compactio

57
13
5

08-Aug-09
08-Aug-09
08-Aug-09

03-Oct-09
20-Aug-09
12-Aug-09

0
25
8

Street Light Network


B12780 <R8-SL-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Surface Water Network (Main)
A9420 <R8-STORM-L>Excavation & Surface Preparation

<R8-STORM-L>Excavation & Surface Pre


<R8-STORM-L>Pipe Laying

A9430

<R8-STORM-L>Pipe Laying

10-Aug-09

15-Aug-09

A9440

<R8-STORM-L>Manhole

15-Aug-09

17-Aug-09

21

<R8-STORM-L>Manhole

A9450

<R8-STORM-L>Inspection & Testing

17-Aug-09

18-Aug-09

21

<R8-STORM-L>Inspection & Testing

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 19 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

18-Aug-09

20-Aug-09

21

<R8-STORM-L>Backfilling & Compaction

9
2

19-Aug-09
19-Aug-09

27-Aug-09
20-Aug-09

23
17

<R8-22kV-L>Excavation & Surface Prepa

B15310 <R8-22kV-L>Cable Laying

22-Aug-09

23-Aug-09

18

<R8-22kV-L>Cable Laying

B15320 <R8-22kV-L>Inspection & Testing

24-Aug-09

25-Aug-09

19

<R8-22kV-L>Inspection & Testing


<R8-22kV-L>Backfilling & Compaction

A9460

<R8-STORM-L>Backfilling & Compaction

22kV Network
B15300 <R8-22kV-L>Excavation & Surface Preparation

B15340 <R8-22kV-L>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

26-Aug-09

27-Aug-09

19

14
3

10-Sep-09
10-Sep-09

23-Sep-09
13-Sep-09

10
8

B12240 <R8-LV-L>Cable Laying

13-Sep-09

15-Sep-09

<R8-LV-L>Cable Laying

B15000 <R8-LV-L>Inspection & Testing

16-Sep-09

17-Sep-09

<R8-LV-L>Inspection & Testing

LV Network
B12230 <R8-LV-L>Excavation & Surface Preparation

<R8-LV-L>Excavation & Surface Prep

19-Sep-09

23-Sep-09

<R8-LV-L>Backfilling & Compaction

34
2

31-Aug-09
31-Aug-09

03-Oct-09
01-Sep-09

0
13

<R8-SL-L>Excavation & Surface Prepa

B13020 <R8-SL-L>Cable Laying

02-Sep-09

03-Sep-09

13

<R8-SL-L>Cable Laying

B13030 <R8-SL-L>Smart Pole Foundation

05-Sep-09

07-Sep-09

13

<R8-SL-L>Smart Pole Foundation

B15270 <R8-SL-L>Smart Pole Erection

24-Sep-09

27-Sep-09

<R8-SL-L>Smart Pole Erection

B15280 <R8-SL-L>Inspection & Testing

28-Sep-09

29-Sep-09

<R8-SL-L>Inspection & Testing

B13040 <R8-SL-L>Backfilling & Compaction

30-Sep-09

03-Oct-09

<R8-SL-L>Backfilling & Compaction

9
4

16-Dec-09
16-Dec-09

24-Dec-09
20-Dec-09

24
20

<R8-RM>Road Marking

<R8-RF>Road Furnishings

21-Dec-09

24-Dec-09

20

<R8-RF>Road Furnishing

<R8-T>Punch List

5
5

26-Dec-09
26-Dec-09

30-Dec-09
30-Dec-09

24
20

Road 7
<7>Road 7
Utility Corridors
A4870
<R7-EW-UC>Earthworks for Utility Corridors

251
251
218
4

25-Mar-09
25-Mar-09
25-Mar-09
25-Mar-09

30-Nov-09
30-Nov-09
28-Oct-09
29-Mar-09

54
54
81
63

Interlock Paving for Utility Corridors


A8810
<R7-SGIP-UC>Subgarde for Interlock Paving

17
3

12-Oct-09
12-Oct-09

28-Oct-09
14-Oct-09

81
5

<R7-SGIP-UC>Subgarde for Inter

B12260 <R8-LV-L>Backfilling & Compaction


Street Light Network
B13010 <R8-SL-L>Excavation & Surface Preparation

Roads Furnishing, Marking, Others


A5630
<R8-RM>Road Marking
A5640
Testing
A5650

<R8-T>Punch List

<R7-EW-UC>Earthworks for Utility Corridors

A8840

<R7-AGB-UC>150mm Aggregate Base Course for Interlock Paving

15-Oct-09

18-Oct-09

66

<R7-AGB-UC>150mm Aggregate

A8850

<R7-COS-UC>50mm Black Sand for Interlock Paving

19-Oct-09

21-Oct-09

66

<R7-COS-UC>50mm Black Sand

A8860

<R7-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

22-Oct-09

25-Oct-09

66

<R7-IVP-UC>Installing 60mm In

A8870

<R7-SFM-UC>Sand Filler Material for Interlock Paving

26-Oct-09

28-Oct-09

66

<R7-SFM-UC>Sand Filler Mater

229
4

30-Mar-09
30-Mar-09

13-Nov-09
02-Apr-09

55
165

Roads Carriage Corridor


A8880
<R7-EW-CC>Earthworks
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 20 of 43

<R7-EW-CC>Earthworks

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R7-SG-CC>Sub grade

A8890

<R7-SG-CC>Sub grade

12-Oct-09

15-Oct-09

A8820

<R7-CS-UC>Curb Stone

21-Oct-09

28-Oct-09

A8900

<R7-GT-CC>Geo textile Surface

29-Oct-09

31-Oct-09

11

<R7-GT-CC>Geo textile Surfac

A8910

<R7-AGB-CC>200mm Aggregate Base Course

01-Nov-09

03-Nov-09

11

<R7-AGB-CC>200mm Aggrega

A8920

<R7-COS-CC>50mm Black Sand for Interlock Paving

04-Nov-09

07-Nov-09

44

<R7-COS-CC>50mm Black Sa

A8930

<R7-IVP-CC>Installing 80mm Interlocking Vehicular Pavers

08-Nov-09

12-Nov-09

44

<R7-IVP-CC>Installing 80mm

A9040

<R7-SFM-CC>Sand Filler Material for Interlock Paving

13-Nov-09

13-Nov-09

55

<R7-SFM-CC>Sand Filler Mat

154
141
17
4

14-May-09
14-May-09
14-May-09
14-May-09

14-Oct-09
01-Oct-09
30-May-09
18-May-09

42
14
68
33

<R7-SEW-R>Excavation & Surface Preparation

B12010 <R7-SEW-R>Pipe Laying

17-May-09

20-May-09

33

<R7-SEW-R>Pipe Laying

B12020 <R7-SEW-R>Manhole

17-May-09

20-May-09

58

<R7-SEW-R>Manhole

B14910 <R7-SEW-R>Inspection & Testing

19-May-09

21-May-09

58

<R7-SEW-R>Inspection & Testing

B12030 <R7-SEW-R>Backfilling & Compaction

20-May-09

30-May-09

58

14
2

29-Jul-09
29-Jul-09

11-Aug-09
30-Jul-09

11
8

B12100 <R7-Tele-R>Duct Laying

01-Aug-09

02-Aug-09

B12110 <R7-Tele-R>Joint Box

03-Aug-09

06-Aug-09

10

<R7-Tele-R>Joint Box

B12120 <R7-Tele-R>Manhole

03-Aug-09

06-Aug-09

<R7-Tele-R>Manhole

B14950 <R7-Tele-R>Inspection & Testing

08-Aug-09

09-Aug-09

<R7-Tele-R>Inspection & Testing

B12130 <R7-Tele-R>Backfilling & Compaction

10-Aug-09

11-Aug-09

<R7-Tele-R>Backfilling & Compaction

14
5

13-Aug-09
13-Aug-09

26-Aug-09
18-Aug-09

27
8

Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B12000 <R7-SEW-R>Excavation & Surface Preparation

Telecommunication Network
B12090 <R7-Tele-R>Excavation & Surface Preparation

Surface Water Network


A8940 <R7-STORM-R>Excavation & Surface Preparation

<R7-CS-UC>Curb Stone

<R7-SEW-R>Backfilling & Compaction

<R7-Tele-R>Excavation & Surface Preparat


<R7-Tele-R>Duct Laying

<R7-STORM-R>Excavation & Surface P


<R7-STORM-R>Pipe Laying

A8950

<R7-STORM-R>Pipe Laying

16-Aug-09

20-Aug-09

A8960

<R7-STORM-R>Inlet Chamber

19-Aug-09

23-Aug-09

21

<R7-STORM-R>Inlet Chamber

A8970

<R7-STORM-R>Inspection & Testing

23-Aug-09

24-Aug-09

21

<R7-STORM-R>Inspection & Testing

A8980

<R7-STORM-R>Backfilling & Compaction

24-Aug-09

26-Aug-09

21

<R7-STORM-R>Backfilling & Compactio

30
2

02-Sep-09
02-Sep-09

01-Oct-09
03-Sep-09

14
16

<R7-SL-R>Excavation & Surface Prepa

B12050 <R7-SL-R>Cable Laying

05-Sep-09

06-Sep-09

17

<R7-SL-R>Cable Laying

B12060 <R7-SL-R>Smart Pole Foundation

07-Sep-09

09-Sep-09

23

<R7-SL-R>Smart Pole Foundation

B14920 <R7-SL-R>Smart Pole Erection

24-Sep-09

27-Sep-09

12

<R7-SL-R>Smart Pole Erection

B14930 <R7-SL-R>Inspection & Testing

28-Sep-09

29-Sep-09

12

<R7-SL-R>Inspection & Testing

Street Light Network


B12040 <R7-SL-R>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 21 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

30-Sep-09

01-Oct-09

12

128
23
6

09-Jun-09
09-Jun-09
09-Jun-09

14-Oct-09
01-Jul-09
15-Jun-09

42
15
13

<R7-PW-L>Excavation & Surface Preparation

B12300 <R7-PW-L>Pipe Laying

11-Jun-09

17-Jun-09

13

<R7-PW-L>Pipe Laying

B12310 <R7-PW-L>Valve Chamber

16-Jun-09

20-Jun-09

13

<R7-PW-L>Valve Chamber

B12320 <R7-PW-L>Valve Fittings

18-Jun-09

22-Jun-09

13

<R7-PW-L>Valve Fittings

B12330 <R7-PW-L>Fire Hydrant

21-Jun-09

27-Jun-09

13

<R7-PW-L>Fire Hydrant

B15010 <R7-PW-L>Inspection & Testing

27-Jun-09

28-Jun-09

13

<R7-PW-L>Inspection & Testing

B12340 <R7-PW-L>Backfilling & Compaction

29-Jun-09

01-Jul-09

13

<R7-PW-L>Backfilling & Compaction

29
8

08-Jul-09
08-Jul-09

05-Aug-09
16-Jul-09

5
8

B12200 <R7-Gas-L>Pipe Laying

15-Jul-09

25-Jul-09

<R7-Gas-L>Pipe Laying

B12210 <R7-Gas-L>Valve Fittings

26-Jul-09

29-Jul-09

<R7-Gas-L>Valve Fittings

B14990 <R7-Gas-L>Inspection & Testing

30-Jul-09

01-Aug-09

<R7-Gas-L>Inspection & Testing

B12220 <R7-Gas-L>Backfilling & Compaction

02-Aug-09

05-Aug-09

<R7-Gas-L>Backfilling & Compaction

18
6

06-Aug-09
06-Aug-09

23-Aug-09
12-Aug-09

4
4

<R7-IRR-L>Excavation & Surface Prepara

B12410 <R7-IRR-L>Pipe Laying

08-Aug-09

13-Aug-09

<R7-IRR-L>Pipe Laying

B12420 <R7-IRR-L>Valve Chamber

12-Aug-09

15-Aug-09

<R7-IRR-L>Valve Chamber

B12430 <R7-IRR-L>Valve Fittings

15-Aug-09

17-Aug-09

<R7-IRR-L>Valve Fittings

B15030 <R7-IRR-L>Inspection & Testing

18-Aug-09

19-Aug-09

<R7-IRR-L>Inspection & Testing

B12070 <R7-SL-R>Backfilling & Compaction


Utilities in Corridors (Left Side)
Potable Water Network
B12290 <R7-PW-L>Excavation & Surface Preparation

Gas Network
B12190 <R7-Gas-L>Excavation & Surface Preparation

Irrigation Network
B12400 <R7-IRR-L>Excavation & Surface Preparation

B15040 <R7-IRR-L>Backfilling & Compaction


Surface Water Network (Main)
A8990 <R7-STORM-L>Excavation & Surface Preparation

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R7-SL-R>Backfilling & Compactio

<R7-Gas-L>Excavation & Surface Preparation

20-Aug-09

23-Aug-09

<R7-IRR-L>Backfilling & Compaction

13
3

24-Aug-09
24-Aug-09

05-Sep-09
26-Aug-09

4
4

<R7-STORM-L>Excavation & Surface P

A9000

<R7-STORM-L>Pipe Laying

26-Aug-09

29-Aug-09

<R7-STORM-L>Pipe Laying

A9010

<R7-STORM-L>Manhole

30-Aug-09

31-Aug-09

<R7-STORM-L>Manhole

A9020

<R7-STORM-L>Inspection & Testing

01-Sep-09

02-Sep-09

<R7-STORM-L>Inspection & Testing

A9030

<R7-STORM-L>Backfilling & Compaction

03-Sep-09

05-Sep-09

<R7-STORM-L>Backfilling & Compact

12
3

06-Sep-09
06-Sep-09

17-Sep-09
08-Sep-09

7
4

<R7-22kV-L>Excavation & Surface Pre

B12360 <R7-22kV-L>Cable Laying

09-Sep-09

12-Sep-09

<R7-22kV-L>Cable Laying

B15020 <R7-22kV-L>Inspection & Testing

13-Sep-09

14-Sep-09

<R7-22kV-L>Inspection & Testing

B12380 <R7-22kV-L>Backfilling & Compaction

15-Sep-09

17-Sep-09

<R7-22kV-L>Backfilling & Compactio

22kV Network
B12350 <R7-22kV-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 22 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

26
3

19-Sep-09
19-Sep-09

14-Oct-09
23-Sep-09

42
4

B12150 <R7-SL-L>Cable Laying

24-Sep-09

27-Sep-09

<R7-SL-L>Cable Laying

B12160 <R7-SL-L>Smart Pole Foundation

28-Sep-09

30-Sep-09

<R7-SL-L>Smart Pole Foundation

B14960 <R7-SL-L>Smart Pole Erection

01-Oct-09

04-Oct-09

<R7-SL-L>Smart Pole Erection

B14980 <R7-SL-L>Inspection & Testing

05-Oct-09

07-Oct-09

<R7-SL-L>Inspection & Testing

B12180 <R7-SL-L>Backfilling & Compaction

08-Oct-09

11-Oct-09

<R7-SL-L>Backfilling & Compactio

B12170 <R7-SL-L>Control Cabinet

12-Oct-09

14-Oct-09

36

9
4

14-Nov-09
14-Nov-09

22-Nov-09
17-Nov-09

56
45

<R7-RM>Road Marking

<R7-RF>Road Furnishings

18-Nov-09

22-Nov-09

45

<R7-RF>Road Furnishings

<R7-T>Punch List

8
5

23-Nov-09
23-Nov-09

30-Nov-09
30-Nov-09

54
45

Road 6
<6>Road 6
Utility Corridors
A4530
<R6-EW-UC>Earthworks for Utility Corridors

282
282
217
3

30-Mar-09
30-Mar-09
30-Mar-09
30-Mar-09

05-Jan-10
05-Jan-10
01-Nov-09
01-Apr-09

18
18
77
63

Interlock Paving for Utility Corridors


A8580
<R6-SGIP-UC>Subgarde for Interlock Paving

18
3

15-Oct-09
15-Oct-09

01-Nov-09
18-Oct-09

77
9

<R6-SGIP-UC>Subgarde for Inte

Street Light Network


B12140 <R7-SL-L>Excavation & Surface Preparation

Roads Furnishing, Marking, Others


A5220
<R7-RM>Road Marking
A5230
Testing
A5240

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R7-SL-L>Excavation & Surface Pre

<R7-SL-L>Control Cabinet

<R7-T>Punch List

<R6-EW-UC>Earthworks for Utility Corridors

A8610

<R6-AGB-UC>150mm Aggregate Base Course for Interlock Paving

19-Oct-09

21-Oct-09

63

<R6-AGB-UC>150mm Aggregate

A8620

<R6-COS-UC>50mm Black Sand for Interlock Paving

22-Oct-09

25-Oct-09

63

<R6-COS-UC>50mm Black San

A8630

<R6-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

26-Oct-09

28-Oct-09

63

<R6-IVP-UC>Installing 60mm In

A8640

<R6-SFM-UC>Sand Filler Material for Interlock Paving

<R6-SFM-UC>Sand Filler Mate

Roads Carriage Corridor


A8650
<R6-EW-CC>Earthworks

29-Oct-09

01-Nov-09

63

262
3

04-Apr-09
04-Apr-09

21-Dec-09
06-Apr-09

0
169

<R6-EW-CC>Earthworks
<R6-SG-CC>Sub grade

A8660

<R6-SG-CC>Sub grade

17-Oct-09

20-Oct-09

A8590

<R6-CS-UC>Curb Stone

29-Oct-09

04-Nov-09

<R6-CS-UC>Curb Stone

A8670

<R6-GT-CC>Geo textile Surface

05-Nov-09

07-Nov-09

<R6-GT-CC>Geo textile Surfac

A8680

<R6-AGB-CC>300mm Aggregate Base Course

08-Nov-09

10-Nov-09

<R6-AGB-CC>300mm Aggreg

A8690

<R6-ASB-CC>180mm Asphalt Base Course

11-Nov-09

14-Nov-09

<R6-ASB-CC>180mm Asphal

A8700

<R6-ASW-CC>100mm Asphalt Wearing Course

16-Dec-09

21-Dec-09

<R6-ASW-CC>100mm A

147
118
29
4

19-May-09
15-Jun-09
15-Jun-09
15-Jun-09

12-Oct-09
10-Oct-09
13-Jul-09
18-Jun-09

12
14
42
35

Utilities Works
Utilities in Corridors (Right Side)
Gas Network
B11470 <R6-Gas-R>Excavation & Surface Preparation
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 23 of 43

<R6-Gas-R>Excavation & Surface Preparation

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B11480 <R6-Gas-R>Pipe Laying

17-Jun-09

21-Jun-09

35

B11490 <R6-Gas-R>Valve Fittings

05-Jul-09

08-Jul-09

35

<R6-Gas-R>Valve Fittings

B14650 <R6-Gas-R>Inspection & Testing

08-Jul-09

09-Jul-09

35

<R6-Gas-R>Inspection & Testing


<R6-Gas-R>Backfilling & Compaction

B11500 <R6-Gas-R>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R6-Gas-R>Pipe Laying

09-Jul-09

13-Jul-09

35

19
5

13-Aug-09
13-Aug-09

31-Aug-09
18-Aug-09

12
10

<R6-IRR-R>Excavation & Surface Prepa

B11520 <R6-IRR-R>Pipe Laying

16-Aug-09

20-Aug-09

10

<R6-IRR-R>Pipe Laying

B11530 <R6-IRR-R>Valve Chamber

20-Aug-09

23-Aug-09

10

<R6-IRR-R>Valve Chamber

B11540 <R6-IRR-R>Valve Fittings

23-Aug-09

25-Aug-09

10

<R6-IRR-R>Valve Fittings

B14710 <R6-IRR-R>Inspection & Testing

26-Aug-09

27-Aug-09

10

<R6-IRR-R>Inspection & Testing

B14720 <R6-IRR-R>Backfilling & Compaction

29-Aug-09

31-Aug-09

10

<R6-IRR-R>Backfilling & Compaction

12
3

01-Sep-09
01-Sep-09

12-Sep-09
03-Sep-09

24
10

<R6-STORM-R>Excavation & Surface

Irrigation Network
B11510 <R6-IRR-R>Excavation & Surface Preparation

Surface Water Network


A8710 <R6-STORM-R>Excavation & Surface Preparation
A8720

<R6-STORM-R>Pipe Laying

03-Sep-09

06-Sep-09

10

<R6-STORM-R>Pipe Laying

A8730

<R6-STORM-R>Inlet Chamber

06-Sep-09

08-Sep-09

19

<R6-STORM-R>Inlet Chamber

A8740

<R6-STORM-R>Inspection & Testing

08-Sep-09

09-Sep-09

19

<R6-STORM-R>Inspection & Testing

A8750

<R6-STORM-R>Backfilling & Compaction

09-Sep-09

12-Sep-09

19

<R6-STORM-R>Backfilling & Compac

17
2

24-Sep-09
24-Sep-09

10-Oct-09
26-Sep-09

14
11

<R6-SL-R>Excavation & Surface Pr

B11440 <R6-SL-R>Cable Laying

28-Sep-09

29-Sep-09

10

<R6-SL-R>Cable Laying

B11450 <R6-SL-R>Smart Pole Foundation

30-Sep-09

03-Oct-09

12

<R6-SL-R>Smart Pole Foundation

B14620 <R6-SL-R>Smart Pole Erection

03-Oct-09

05-Oct-09

12

<R6-SL-R>Smart Pole Erection

B14630 <R6-SL-R>Inspection & Testing

06-Oct-09

07-Oct-09

12

<R6-SL-R>Inspection & Testing

B11460 <R6-SL-R>Backfilling & Compaction

08-Oct-09

10-Oct-09

12

<R6-SL-R>Backfilling & Compactio

147
14
3

19-May-09
19-May-09
19-May-09

12-Oct-09
01-Jun-09
21-May-09

12
38
33

<R6-SEW-L>Excavation & Surface Preparation

B11560 <R6-SEW-L>Pipe Laying

21-May-09

24-May-09

33

<R6-SEW-L>Pipe Laying

B11570 <R6-SEW-L>Manhole

21-May-09

24-May-09

33

<R6-SEW-L>Manhole

B14730 <R6-SEW-L>Inspection & Testing

23-May-09

25-May-09

33

<R6-SEW-L>Inspection & Testing

B11580 <R6-SEW-L>Backfilling & Compaction

24-May-09

01-Jun-09

33

22
4

16-Jun-09
16-Jun-09

07-Jul-09
20-Jun-09

70
21

<R6-PW-L>Excavation & Surface Preparation

18-Jun-09

22-Jun-09

24

<R6-PW-L>Pipe Laying

Street Light Network


B11430 <R6-SL-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Sewerage Network
B11550 <R6-SEW-L>Excavation & Surface Preparation

Potable Water Network


B11680 <R6-PW-L>Excavation & Surface Preparation
B11690 <R6-PW-L>Pipe Laying

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 24 of 43

<R6-SEW-L>Backfilling & Compaction

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B11700 <R6-PW-L>Valve Chamber

22-Jun-09

24-Jun-09

59

<R6-PW-L>Valve Chamber

B11710 <R6-PW-L>Valve Fittings

24-Jun-09

27-Jun-09

59

<R6-PW-L>Valve Fittings

B11720 <R6-PW-L>Fire Hydrant

27-Jun-09

02-Jul-09

59

<R6-PW-L>Fire Hydrant

B14780 <R6-PW-L>Inspection & Testing

02-Jul-09

04-Jul-09

59

<R6-PW-L>Inspection & Testing

B11730 <R6-PW-L>Backfilling & Compaction

05-Jul-09

07-Jul-09

59

<R6-PW-L>Backfilling & Compaction

11
3

05-Sep-09
05-Sep-09

15-Sep-09
07-Sep-09

14
10

<R6-STORM-L>Excavation & Surface

Surface Water Network


A8760 <R6-STORM-L>Excavation & Surface Preparation

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A8770

<R6-STORM-L>Pipe Laying

07-Sep-09

09-Sep-09

10

<R6-STORM-L>Pipe Laying

A8780

<R6-STORM-L>Inlet Chamber

09-Sep-09

12-Sep-09

10

<R6-STORM-L>Inlet Chamber

A8790

<R6-STORM-L>Inspection & Testing

12-Sep-09

13-Sep-09

10

<R6-STORM-L>Inspection & Testing

A8800

<R6-STORM-L>Backfilling & Compaction

13-Sep-09

15-Sep-09

10

<R6-STORM-L>Backfilling & Compac

12
2

16-Sep-09
16-Sep-09

27-Sep-09
17-Sep-09

11
10

<R6-22kV-R>Excavation & Surface P

B14670 <R6-22kV-R>Cable Laying

19-Sep-09

22-Sep-09

10

<R6-22kV-R>Cable Laying

B14680 <R6-22kV-R>Inspection & Testing

23-Sep-09

24-Sep-09

10

<R6-22kV-R>Inspection & Testing

22kV Network
B14660 <R6-22kV-R>Excavation & Surface Preparation

26-Sep-09

27-Sep-09

10

<R6-22kV-R>Backfilling & Compact

15
2

28-Sep-09
28-Sep-09

12-Oct-09
29-Sep-09

12
10

<R6-SL-L>Excavation & Surface Pr

B11600 <R6-SL-L>Cable Laying

30-Sep-09

01-Oct-09

10

<R6-SL-L>Cable Laying

B11610 <R6-SL-L>Smart Pole Foundation

03-Oct-09

05-Oct-09

10

<R6-SL-L>Smart Pole Foundation

B14740 <R6-SL-L>Smart Pole Erection

05-Oct-09

07-Oct-09

10

<R6-SL-L>Smart Pole Erection

B14750 <R6-SL-L>Inspection & Testing

08-Oct-09

10-Oct-09

10

<R6-SL-L>Inspection & Testing

B11630 <R6-SL-L>Backfilling & Compaction

11-Oct-09

12-Oct-09

10

<R6-SL-L>Backfilling & Compactio

9
4

22-Dec-09
22-Dec-09

30-Dec-09
26-Dec-09

18
15

<R6-RM>Road Marking

<R6-RF>Road Furnishings

27-Dec-09

30-Dec-09

15

<R6-RF>Road Furnishin

<R6-T>Punch List

6
5

31-Dec-09
31-Dec-09

05-Jan-10
05-Jan-10

18
15

<R6-T>Punch List

Road 5
<5>Road 5
Utility Corridors
A4190
<R5-EW-UC>Earthworks for Utility Corridors

285
285
218
4

02-Apr-09
02-Apr-09
02-Apr-09
02-Apr-09

11-Jan-10
11-Jan-10
05-Nov-09
06-Apr-09

12
12
73
63

Interlock Paving for Utility Corridors


A8350
<R5-SGIP-UC>Subgarde for Interlock Paving

18
4

19-Oct-09
19-Oct-09

05-Nov-09
22-Oct-09

73
11

<R5-SGIP-UC>Subgarde for Inte

24-Oct-09

26-Oct-09

59

<R5-AGB-UC>150mm Aggregat

B14700 <R6-22kV-R>Backfilling & Compaction


Street Light Network
B11590 <R6-SL-L>Excavation & Surface Preparation

Roads Furnishing, Marking, Others


A4840
<R6-RM>Road Marking
A4850
Testing
A4860

A8380

<R5-AGB-UC>150mm Aggregate Base Course for Interlock Paving

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 25 of 43

<R5-EW-UC>Earthworks for Utility Corridors

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A8390

<R5-COS-UC>50mm Black Sand for Interlock Paving

27-Oct-09

29-Oct-09

59

<R5-COS-UC>50mm Black San

A8400

<R5-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

31-Oct-09

02-Nov-09

59

<R5-IVP-UC>Installing 60mm In

A8410

<R5-SFM-UC>Sand Filler Material for Interlock Paving

03-Nov-09

05-Nov-09

59

<R5-SFM-UC>Sand Filler Mate

265
4

07-Apr-09
07-Apr-09

27-Dec-09
11-Apr-09

0
171

Roads Carriage Corridor


A8420
<R5-EW-CC>Earthworks

<R5-EW-CC>Earthworks
<R5-SG-CC>Sub grade

A8430

<R5-SG-CC>Sub grade

21-Oct-09

25-Oct-09

A8360

<R5-CS-UC>Curb Stone

05-Nov-09

11-Nov-09

<R5-CS-UC>Curb Stone

A8440

<R5-GT-CC>Geo textile Surface

12-Nov-09

14-Nov-09

<R5-GT-CC>Geo textile Surfa

A8450

<R5-AGB-CC>300mm Aggregate Base Course

15-Nov-09

17-Nov-09

<R5-AGB-CC>300mm Aggre

A8460

<R5-ASB-CC>180mm Asphalt Base Course

18-Nov-09

21-Nov-09

<R5-ASB-CC>180mm Aspha

A8470

<R5-ASW-CC>100mm Asphalt Wearing Course

22-Dec-09

27-Dec-09

<R5-ASW-CC>100mm A

145
108
24
5

14-May-09
20-Jun-09
20-Jun-09
20-Jun-09

05-Oct-09
05-Oct-09
13-Jul-09
24-Jun-09

51
51
33
35

<R5-Gas-R>Excavation & Surface Preparation

B10810 <R5-Gas-R>Pipe Laying

22-Jun-09

27-Jun-09

35

<R5-Gas-R>Pipe Laying

B10820 <R5-Gas-R>Valve Fittings

05-Jul-09

08-Jul-09

27

<R5-Gas-R>Valve Fittings

B14390 <R5-Gas-R>Inspection & Testing

08-Jul-09

09-Jul-09

27

<R5-Gas-R>Inspection & Testing


<R5-Gas-R>Backfilling & Compaction

Utilities Works
Utilities in Corridors (Right Side)
Gas Network
B10800 <R5-Gas-R>Excavation & Surface Preparation

B10830 <R5-Gas-R>Backfilling & Compaction

09-Jul-09

13-Jul-09

27

20
5

14-Jul-09
14-Jul-09

02-Aug-09
20-Jul-09

31
27

<R5-IRR-R>Excavation & Surface Preparatio

B10850 <R5-IRR-R>Pipe Laying

16-Jul-09

22-Jul-09

27

<R5-IRR-R>Pipe Laying

B10860 <R5-IRR-R>Valve Chamber

22-Jul-09

25-Jul-09

27

<R5-IRR-R>Valve Chamber

B10870 <R5-IRR-R>Valve Fittings

25-Jul-09

27-Jul-09

27

<R5-IRR-R>Valve Fittings

B14400 <R5-IRR-R>Inspection & Testing

28-Jul-09

29-Jul-09

27

<R5-IRR-R>Inspection & Testing

B14410 <R5-IRR-R>Backfilling & Compaction

30-Jul-09

02-Aug-09

27

<R5-IRR-R>Backfilling & Compaction

13
2

03-Aug-09
03-Aug-09

15-Aug-09
04-Aug-09

31
27

<R5-Tele-R>Excavation & Surface Prepara

B10770 <R5-Tele-R>Duct Laying

05-Aug-09

06-Aug-09

27

<R5-Tele-R>Duct Laying

B10780 <R5-Tele-R>Joint Box

08-Aug-09

10-Aug-09

28

<R5-Tele-R>Joint Box

B12080 <R5-Tele-R>Manhole

08-Aug-09

10-Aug-09

27

<R5-Tele-R>Manhole

B14380 <R5-Tele-R>Inspection & Testing

11-Aug-09

12-Aug-09

27

<R5-Tele-R>Inspection & Testing

B10790 <R5-Tele-R>Backfilling & Compaction

13-Aug-09

15-Aug-09

27

<R5-Tele-R>Backfilling & Compaction

14

16-Aug-09

29-Aug-09

45

Irrigation Network
B10840 <R5-IRR-R>Excavation & Surface Preparation

Telecommunication Network
B10760 <R5-Tele-R>Excavation & Surface Preparation

Surface Water Network

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 26 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A8480

<R5-STORM-R>Excavation & Surface Preparation

16-Aug-09

20-Aug-09

27

<R5-STORM-R>Excavation & Surface P

A8490

<R5-STORM-R>Pipe Laying

18-Aug-09

23-Aug-09

27

<R5-STORM-R>Pipe Laying

A8500

<R5-STORM-R>Inlet Chamber

22-Aug-09

25-Aug-09

37

<R5-STORM-R>Inlet Chamber

A8510

<R5-STORM-R>Inspection & Testing

25-Aug-09

26-Aug-09

37

<R5-STORM-R>Inspection & Testing

A8520

<R5-STORM-R>Backfilling & Compaction

26-Aug-09

29-Aug-09

37

<R5-STORM-R>Backfilling & Compacti

37
2

30-Aug-09
30-Aug-09

05-Oct-09
31-Aug-09

51
37

<R5-SL-R>Excavation & Surface Prepa

B10730 <R5-SL-R>Cable Laying

01-Sep-09

02-Sep-09

37

<R5-SL-R>Cable Laying

B10740 <R5-SL-R>Smart Pole Foundation

03-Sep-09

06-Sep-09

39

<R5-SL-R>Smart Pole Foundation

B14350 <R5-SL-R>Smart Pole Erection

24-Sep-09

27-Sep-09

25

<R5-SL-R>Smart Pole Erection

B14370 <R5-SL-R>Inspection & Testing

28-Sep-09

29-Sep-09

25

<R5-SL-R>Inspection & Testing

B10920 <R5-SL-R>Backfilling & Compaction

30-Sep-09

01-Oct-09

25

<R5-SL-R>Backfilling & Compactio

B10750 <R5-SL-R>Control Cabinet

03-Oct-09

05-Oct-09

44

<R5-SL-R>Control Cabinet

141
22
5

14-May-09
14-May-09
14-May-09

01-Oct-09
04-Jun-09
19-May-09

30
37
31

<R5-SEW-L>Excavation & Surface Preparation

B10890 <R5-SEW-L>Pipe Laying

17-May-09

21-May-09

31

<R5-SEW-L>Pipe Laying

B10900 <R5-SEW-L>Manhole

17-May-09

21-May-09

31

<R5-SEW-L>Manhole

B14420 <R5-SEW-L>Inspection & Testing

19-May-09

23-May-09

31

<R5-SEW-L>Inspection & Testing

B10910 <R5-SEW-L>Backfilling & Compaction

14

20-May-09

04-Jun-09

31

<R5-SEW-L>Backfilling & Compaction

25
5

06-Jun-09
06-Jun-09

30-Jun-09
10-Jun-09

85
31

<R5-PW-L>Excavation & Surface Preparation

B11030 <R5-PW-L>Pipe Laying

08-Jun-09

13-Jun-09

33

<R5-PW-L>Pipe Laying

B11040 <R5-PW-L>Valve Chamber

11-Jun-09

15-Jun-09

73

<R5-PW-L>Valve Chamber

B11050 <R5-PW-L>Valve Fittings

14-Jun-09

17-Jun-09

73

<R5-PW-L>Valve Fittings

B11060 <R5-PW-L>Fire Hydrant

20-Jun-09

25-Jun-09

70

<R5-PW-L>Fire Hydrant

B14470 <R5-PW-L>Inspection & Testing

25-Jun-09

27-Jun-09

70

<R5-PW-L>Inspection & Testing

B11070 <R5-PW-L>Backfilling & Compaction

28-Jun-09

30-Jun-09

70

<R5-PW-L>Backfilling & Compaction

12
4

22-Aug-09
22-Aug-09

02-Sep-09
25-Aug-09

34
27

<R5-STORM-L>Excavation & Surface P

Street Light Network


B10720 <R5-SL-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Sewerage Network
B10880 <R5-SEW-L>Excavation & Surface Preparation

Potable Water Network


B11020 <R5-PW-L>Excavation & Surface Preparation

Surface Water Network


A8530 <R5-STORM-L>Excavation & Surface Preparation
A8540

<R5-STORM-L>Pipe Laying

24-Aug-09

27-Aug-09

27

<R5-STORM-L>Pipe Laying

A8550

<R5-STORM-L>Inlet Chamber

27-Aug-09

30-Aug-09

27

<R5-STORM-L>Inlet Chamber

A8560

<R5-STORM-L>Inspection & Testing

30-Aug-09

31-Aug-09

27

<R5-STORM-L>Inspection & Testing

A8570

<R5-STORM-L>Backfilling & Compaction

31-Aug-09

02-Sep-09

27

<R5-STORM-L>Backfilling & Compacti

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 27 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

10
2

03-Sep-09
03-Sep-09

12-Sep-09
05-Sep-09

33
27

<R5-22kV-L>Excavation & Surface Pre

B11090 <R5-22kV-L>Cable Laying

06-Sep-09

07-Sep-09

27

<R5-22kV-L>Cable Laying

B14480 <R5-22kV-L>Inspection & Testing

08-Sep-09

09-Sep-09

27

<R5-22kV-L>Inspection & Testing

B11110 <R5-22kV-L>Backfilling & Compaction

10-Sep-09

12-Sep-09

27

<R5-22kV-L>Backfilling & Compaction

19
2

13-Sep-09
13-Sep-09

01-Oct-09
14-Sep-09

30
27

<R5-SL-L>Excavation & Surface Prep

B10940 <R5-SL-L>Cable Laying

15-Sep-09

16-Sep-09

27

<R5-SL-L>Cable Laying

B10950 <R5-SL-L>Smart Pole Foundation

17-Sep-09

22-Sep-09

27

<R5-SL-L>Smart Pole Foundation

B14430 <R5-SL-L>Smart Pole Erection

24-Sep-09

27-Sep-09

25

<R5-SL-L>Smart Pole Erection

B14440 <R5-SL-L>Inspection & Testing

28-Sep-09

29-Sep-09

25

<R5-SL-L>Inspection & Testing

B10960 <R5-SL-L>Backfilling & Compaction

30-Sep-09

01-Oct-09

25

<R5-SL-L>Backfilling & Compaction

9
4

28-Dec-09
28-Dec-09

05-Jan-10
31-Dec-09

12
10

<R5-RM>Road Marking

<R5-RF>Road Furnishings

02-Jan-10

05-Jan-10

10

<R5-RF>Road Furnishi

<R5-T>Punch List

6
5

06-Jan-10
06-Jan-10

11-Jan-10
11-Jan-10

12
10

Road 4
<4>Road 4
Utility Corridors
A3860
<R4-EW-UC>Earthworks for Utility Corridors

287
287
217
4

07-Apr-09
07-Apr-09
07-Apr-09
07-Apr-09

18-Jan-10
18-Jan-10
09-Nov-09
11-Apr-09

5
5
69
82

Interlock Paving for Utility Corridors


A8120
<R4-SGIP-UC>Subgarde for Interlock Paving

17
4

24-Oct-09
24-Oct-09

09-Nov-09
27-Oct-09

69
13

<R4-SGIP-UC>Subgarde for Int

22kV Network
B11080 <R5-22kV-L>Excavation & Surface Preparation

Street Light Network


B10930 <R5-SL-L>Excavation & Surface Preparation

Roads Furnishing, Marking, Others


A4500
<R5-RM>Road Marking
A4510
Testing
A4520

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R5-T>Punch List

<R4-EW-UC>Earthworks for Utility Corridors

A8150

<R4-AGB-UC>150mm Aggregate Base Course for Interlock Paving

28-Oct-09

31-Oct-09

56

<R4-AGB-UC>150mm Aggrega

A8160

<R4-COS-UC>50mm Black Sand for Interlock Paving

01-Nov-09

03-Nov-09

56

<R4-COS-UC>50mm Black Sa

A8170

<R4-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

04-Nov-09

07-Nov-09

56

<R4-IVP-UC>Installing 60mm I

A8180

<R4-SFM-UC>Sand Filler Material for Interlock Paving

08-Nov-09

09-Nov-09

56

<R4-SFM-UC>Sand Filler Mate

266
3

12-Apr-09
12-Apr-09

02-Jan-10
14-Apr-09

0
174

Roads Carriage Corridor


A8190
<R4-EW-CC>Earthworks

<R4-EW-CC>Earthworks
<R4-SG-CC>Sub grade

A8200

<R4-SG-CC>Sub grade

26-Oct-09

29-Oct-09

11

A8130

<R4-CS-UC>Curb Stone

12-Nov-09

17-Nov-09

<R4-CS-UC>Curb Stone

A8210

<R4-GT-CC>Geo textile Surface

18-Nov-09

19-Nov-09

<R4-GT-CC>Geo textile Surfa

A8220

<R4-AGB-CC>300mm Aggregate Base Course

21-Nov-09

23-Nov-09

<R4-AGB-CC>300mm Aggre

A8230

<R4-ASB-CC>180mm Asphalt Base Course

24-Nov-09

26-Nov-09

<R4-ASB-CC>180mm Asph

A8240

<R4-ASW-CC>100mm Asphalt Wearing Course

28-Dec-09

02-Jan-10

<R4-ASW-CC>100mm

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 28 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

152
148
15
4

20-May-09
20-May-09
20-May-09
20-May-09

18-Oct-09
14-Oct-09
03-Jun-09
24-May-09

20
24
90
74

<R4-SEW-R>Excavation & Surface Preparation

B10220 <R4-SEW-R>Pipe Laying

23-May-09

26-May-09

74

<R4-SEW-R>Pipe Laying

B10230 <R4-SEW-R>Manhole

23-May-09

26-May-09

76

<R4-SEW-R>Manhole

B14070 <R4-SEW-R>Inspection & Testing

25-May-09

27-May-09

76

<R4-SEW-R>Inspection & Testing

B10240 <R4-SEW-R>Backfilling & Compaction

26-May-09

03-Jun-09

76

16
3

21-Jul-09
21-Jul-09

05-Aug-09
23-Jul-09

54
37

<R4-IRR-R>Excavation & Surface Preparatio

B10310 <R4-IRR-R>Pipe Laying

23-Jul-09

26-Jul-09

37

<R4-IRR-R>Pipe Laying

B10320 <R4-IRR-R>Valve Chamber

26-Jul-09

28-Jul-09

44

<R4-IRR-R>Valve Chamber

B10330 <R4-IRR-R>Valve Fittings

28-Jul-09

30-Jul-09

44

<R4-IRR-R>Valve Fittings

B14110 <R4-IRR-R>Inspection & Testing

01-Aug-09

02-Aug-09

44

<R4-IRR-R>Inspection & Testing

B14120 <R4-IRR-R>Backfilling & Compaction

03-Aug-09

05-Aug-09

44

<R4-IRR-R>Backfilling & Compaction

12
3

26-Aug-09
26-Aug-09

06-Sep-09
29-Aug-09

34
27

<R4-STORM-R>Excavation & Surface P

Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B10210 <R4-SEW-R>Excavation & Surface Preparation

Irrigation Network
B10300 <R4-IRR-R>Excavation & Surface Preparation

Surface Water Network


A8250 <R4-STORM-R>Excavation & Surface Preparation

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<R4-SEW-R>Backfilling & Compaction

A8260

<R4-STORM-R>Pipe Laying

29-Aug-09

31-Aug-09

27

<R4-STORM-R>Pipe Laying

A8270

<R4-STORM-R>Inlet Chamber

31-Aug-09

02-Sep-09

27

<R4-STORM-R>Inlet Chamber

A8280

<R4-STORM-R>Inspection & Testing

02-Sep-09

03-Sep-09

27

<R4-STORM-R>Inspection & Testing

A8290

<R4-STORM-R>Backfilling & Compaction

03-Sep-09

06-Sep-09

27

<R4-STORM-R>Backfilling & Compac

11
2

19-Sep-09
19-Sep-09

29-Sep-09
22-Sep-09

20
17

<R4-22kV-R>Excavation & Surface P

B14100 <R4-22kV-R>Cable Laying

23-Sep-09

24-Sep-09

17

<R4-22kV-R>Cable Laying

B14190 <R4-22kV-R>Inspection & Testing

26-Sep-09

27-Sep-09

17

<R4-22kV-R>Inspection & Testing

22kV Network
B14090 <R4-22kV-R>Excavation & Surface Preparation

28-Sep-09

29-Sep-09

17

<R4-22kV-R>Backfilling & Compact

15
2

30-Sep-09
30-Sep-09

14-Oct-09
01-Oct-09

24
17

<R4-SL-R>Excavation & Surface Pr

B10370 <R4-SL-R>Cable Laying

03-Oct-09

04-Oct-09

17

<R4-SL-R>Cable Laying

B10380 <R4-SL-R>Smart Pole Foundation

05-Oct-09

07-Oct-09

20

<R4-SL-R>Smart Pole Foundation

B14160 <R4-SL-R>Smart Pole Erection

07-Oct-09

10-Oct-09

20

<R4-SL-R>Smart Pole Erection

B14170 <R4-SL-R>Inspection & Testing

11-Oct-09

12-Oct-09

20

<R4-SL-R>Inspection & Testing

B10390 <R4-SL-R>Backfilling & Compaction

13-Oct-09

14-Oct-09

20

<R4-SL-R>Backfilling & Compact

130
20

11-Jun-09
11-Jun-09

18-Oct-09
30-Jun-09

20
113

B14210 <R4-22kV-R>Backfilling & Compaction


Street Light Network
B10250 <R4-SL-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Potable Water Network
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 29 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B10260 <R4-PW-L>Excavation & Surface Preparation

11-Jun-09

14-Jun-09

31

<R4-PW-L>Excavation & Surface Preparation

B10270 <R4-PW-L>Pipe Laying

14-Jun-09

16-Jun-09

33

<R4-PW-L>Pipe Laying

B10280 <R4-PW-L>Valve Chamber

16-Jun-09

18-Jun-09

94

<R4-PW-L>Valve Chamber

B10290 <R4-PW-L>Valve Fittings

18-Jun-09

21-Jun-09

94

<R4-PW-L>Valve Fittings

B10400 <R4-PW-L>Fire Hydrant

21-Jun-09

27-Jun-09

94

<R4-PW-L>Fire Hydrant

B14080 <R4-PW-L>Inspection & Testing

27-Jun-09

28-Jun-09

94

<R4-PW-L>Inspection & Testing

B10410 <R4-PW-L>Backfilling & Compaction

29-Jun-09

30-Jun-09

94

<R4-PW-L>Backfilling & Compaction

16
3

03-Oct-09
03-Oct-09

18-Oct-09
05-Oct-09

20
17

<R4-SL-L>Excavation & Surface Pr

B10340 <R4-SL-L>Cable Laying

05-Oct-09

07-Oct-09

17

<R4-SL-L>Cable Laying

B10350 <R4-SL-L>Smart Pole Foundation

07-Oct-09

10-Oct-09

17

<R4-SL-L>Smart Pole Foundation

B14130 <R4-SL-L>Smart Pole Erection

10-Oct-09

12-Oct-09

17

<R4-SL-L>Smart Pole Erection

B14140 <R4-SL-L>Inspection & Testing

13-Oct-09

14-Oct-09

17

<R4-SL-L>Inspection & Testing

<R4-SL-L>Backfilling & Compact

Street Light Network


B9950 <R4-SL-L>Excavation & Surface Preparation

B10360 <R4-SL-L>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

15-Oct-09

18-Oct-09

17

10
5

03-Jan-10
03-Jan-10

12-Jan-10
07-Jan-10

5
4

<R4-RM>Road Marking

<R4-RF>Road Furnishings

09-Jan-10

12-Jan-10

<R4-RF>Road Furnish

<R4-T>Punch List

6
5

13-Jan-10
13-Jan-10

18-Jan-10
18-Jan-10

5
4

Road 3
<3>Road 3
Utility Corridors
A3530
<R3-EW-UC>Earthworks for Utility Corridors

287
287
215
4

12-Apr-09
12-Apr-09
12-Apr-09
12-Apr-09

23-Jan-10
23-Jan-10
12-Nov-09
15-Apr-09

0
0
66
82

Interlock Paving for Utility Corridors


A3540
<R3-SGIP-UC>Subgarde for Interlock Paving

16
3

28-Oct-09
28-Oct-09

12-Nov-09
31-Oct-09

66
15

<R3-SGIP-UC>Subgarde for In

Roads Furnishing, Marking, Others


A4160
<R4-RM>Road Marking
A4170
Testing
A4180

<R4-T>Punch List

<R3-EW-UC>Earthworks for Utility Corridors

A3570

<R3-AGB-UC>150mm Aggregate Base Course for Interlock Paving

01-Nov-09

03-Nov-09

53

<R3-AGB-UC>150mm Aggrega

A3580

<R3-COS-UC>50mm Black Sand for Interlock Paving

04-Nov-09

07-Nov-09

53

<R3-COS-UC>50mm Black Sa

A3590

<R3-IVP-UC>Installing 60mm Interlocking Vehicular Pavers

08-Nov-09

10-Nov-09

53

<R3-IVP-UC>Installing 60mm

A3600

<R3-SFM-UC>Sand Filler Material for Interlock Paving

11-Nov-09

12-Nov-09

53

<R3-SFM-UC>Sand Filler Mat

266
3

16-Apr-09
16-Apr-09

06-Jan-10
19-Apr-09

0
175

Roads Carriage Corridor


A3610
<R3-EW-CC>Earthworks

<R3-EW-CC>Earthworks
<R3-SG-CC>Sub grade

A3620

<R3-SG-CC>Sub grade

31-Oct-09

03-Nov-09

12

A3550

<R3-CS-UC>Curb Stone

18-Nov-09

22-Nov-09

<R3-CS-UC>Curb Stone

A3630

<R3-GT-CC>Geo textile Surface

23-Nov-09

26-Nov-09

<R3-GT-CC>Geo textile Sur

A3640

<R3-AGB-CC>300mm Aggregate Base Course

30-Nov-09

05-Dec-09

<R3-AGB-CC>300mm Agg

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 30 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A3650

<R3-ASB-CC>180mm Asphalt Base Course

06-Dec-09

09-Dec-09

<R3-ASB-CC>180mm Asp

A3660

<R3-ASW-CC>100mm Asphalt Wearing Course

03-Jan-10

06-Jan-10

<R3-ASW-CC>100mm

151
151
16
4

25-May-09
25-May-09
25-May-09
25-May-09

22-Oct-09
22-Oct-09
09-Jun-09
28-May-09

34
34
88
74

<R3-SEW-R>Excavation & Surface Preparation

Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B9710 <R3-SEW-R>Excavation & Surface Preparation
B9720

<R3-SEW-R>Pipe Laying

27-May-09

31-May-09

74

<R3-SEW-R>Pipe Laying

B9730

<R3-SEW-R>Manhole

27-May-09

31-May-09

74

<R3-SEW-R>Manhole

B13800 <R3-SEW-R>Inspection & Testing

30-May-09

01-Jun-09

74

<R3-SEW-R>Inspection & Testing

B9740

31-May-09

09-Jun-09

74

16
3

25-Jul-09
25-Jul-09

09-Aug-09
27-Jul-09

45
37

<R3-IRR-R>Excavation & Surface Preparati

27-Jul-09

29-Jul-09

37

<R3-IRR-R>Pipe Laying

<R3-SEW-R>Backfilling & Compaction

Irrigation Network
B9790 <R3-IRR-R>Excavation & Surface Preparation

<R3-SEW-R>Backfilling & Compaction

B9800

<R3-IRR-R>Pipe Laying

B9810

<R3-IRR-R>Valve Chamber

29-Jul-09

01-Aug-09

37

<R3-IRR-R>Valve Chamber

B9820

<R3-IRR-R>Valve Fittings

02-Aug-09

03-Aug-09

37

<R3-IRR-R>Valve Fittings

B13900 <R3-IRR-R>Inspection & Testing

04-Aug-09

05-Aug-09

37

<R3-IRR-R>Inspection & Testing

B13910 <R3-IRR-R>Backfilling & Compaction

06-Aug-09

09-Aug-09

37

<R3-IRR-R>Backfilling & Compaction

11
2

10-Aug-09
10-Aug-09

20-Aug-09
11-Aug-09

46
37

<R3-Tele-R>Excavation & Surface Prepar

Telecommunication Network
B9750 <R3-Tele-R>Excavation & Surface Preparation
B9760

<R3-Tele-R>Duct Laying

12-Aug-09

13-Aug-09

37

<R3-Tele-R>Duct Laying

B9770

<R3-Tele-R>Joint Box

15-Aug-09

17-Aug-09

37

<R3-Tele-R>Joint Box

B13840 <R3-Tele-R>Inspection & Testing

17-Aug-09

18-Aug-09

37

<R3-Tele-R>Inspection & Testing

B9780

19-Aug-09

20-Aug-09

37

<R3-Tele-R>Backfilling & Compaction

12
4

30-Aug-09
30-Aug-09

10-Sep-09
02-Sep-09

38
30

<R3-STORM-R>Excavation & Surface

<R3-Tele-R>Backfilling & Compaction

Surface Water Network


A3670 <R3-STORM-R>Excavation & Surface Preparation
A3680

<R3-STORM-R>Pipe Laying

01-Sep-09

05-Sep-09

30

<R3-STORM-R>Pipe Laying

A3700

<R3-STORM-R>Inlet Chamber

05-Sep-09

07-Sep-09

30

<R3-STORM-R>Inlet Chamber

A5430

<R3-STORM-R>Inspection & Testing

07-Sep-09

08-Sep-09

30

<R3-STORM-R>Inspection & Testing

A3690

<R3-STORM-R>Backfilling & Compaction

08-Sep-09

10-Sep-09

30

<R3-STORM-R>Backfilling & Compac

11
2

12-Sep-09
12-Sep-09

22-Sep-09
13-Sep-09

35
30

<R3-22kV-R>Excavation & Surface Pr

B13860 <R3-22kV-R>Cable Laying

14-Sep-09

15-Sep-09

30

<R3-22kV-R>Cable Laying

B13870 <R3-22kV-R>Inspection & Testing

16-Sep-09

17-Sep-09

30

<R3-22kV-R>Inspection & Testing

B13890 <R3-22kV-R>Backfilling & Compaction

19-Sep-09

22-Sep-09

30

<R3-22kV-R>Backfilling & Compactio

17

06-Oct-09

22-Oct-09

34

22kV Network
B13850 <R3-22kV-R>Excavation & Surface Preparation

Street Light Network


Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 31 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

B9870

<R3-SL-R>Excavation & Surface Preparation

06-Oct-09

07-Oct-09

19

<R3-SL-R>Excavation & Surface P

B9880

<R3-SL-R>Cable Laying

08-Oct-09

10-Oct-09

19

<R3-SL-R>Cable Laying

B9900

<R3-SL-R>Smart Pole Foundation

11-Oct-09

13-Oct-09

20

<R3-SL-R>Smart Pole Foundation

B13830 <R3-SL-R>Smart Pole Erection

13-Oct-09

15-Oct-09

20

<R3-SL-R>Smart Pole Erection

B13820 <R3-SL-R>Inspection & Testing

17-Oct-09

18-Oct-09

20

<R3-SL-R>Inspection & Testing

B9890

<R3-SL-R>Backfilling & Compaction

19-Oct-09

20-Oct-09

20

<R3-SL-R>Backfilling & Compac

B9910

<R3-SL-R>Control Cabinet

21-Oct-09

22-Oct-09

29

<R3-SL-R>Control Cabinet

129
20
3

15-Jun-09
15-Jun-09
15-Jun-09

21-Oct-09
04-Jul-09
17-Jun-09

22
106
31

Utilities in Corridors (Left Side)


Potable Water Network
B9830 <R3-PW-L>Excavation & Surface Preparation

<R3-PW-L>Excavation & Surface Preparation

B9840

<R3-PW-L>Pipe Laying

17-Jun-09

20-Jun-09

33

<R3-PW-L>Pipe Laying

B9850

<R3-PW-L>Valve Chamber

20-Jun-09

22-Jun-09

88

<R3-PW-L>Valve Chamber

B9860

<R3-PW-L>Valve Fittings

22-Jun-09

24-Jun-09

88

<R3-PW-L>Valve Fittings

B9970

<R3-PW-L>Fire Hydrant

24-Jun-09

30-Jun-09

88

<R3-PW-L>Fire Hydrant

B13950 <R3-PW-L>Inspection & Testing

30-Jun-09

01-Jul-09

88

<R3-PW-L>Inspection & Testing


<R3-PW-L>Backfilling & Compaction

B9980

<R3-PW-L>Backfilling & Compaction

Surface Water Network


A8070 <R3-STORM-L>Excavation & Surface Preparation

02-Jul-09

04-Jul-09

88

12
2

03-Sep-09
03-Sep-09

14-Sep-09
05-Sep-09

45
37

<R3-STORM-L>Excavation & Surface

A8080

<R3-STORM-L>Pipe Laying

06-Sep-09

07-Sep-09

37

<R3-STORM-L>Pipe Laying

A8090

<R3-STORM-L>Inlet Chamber

08-Sep-09

10-Sep-09

37

<R3-STORM-L>Inlet Chamber

A8100

<R3-STORM-L>Inspection & Testing

10-Sep-09

12-Sep-09

37

<R3-STORM-L>Inspection & Testing

A8110

<R3-STORM-L>Backfilling & Compaction

13-Sep-09

14-Sep-09

37

<R3-STORM-L>Backfilling & Compac

14
2

08-Oct-09
08-Oct-09

21-Oct-09
10-Oct-09

22
19

<R3-SL-L>Excavation & Surface P

Street Light Network


B9920 <R3-SL-L>Excavation & Surface Preparation
B9930

<R3-SL-L>Cable Laying

11-Oct-09

12-Oct-09

19

<R3-SL-L>Cable Laying

B9940

<R3-SL-L>Smart Pole Foundation

13-Oct-09

14-Oct-09

19

<R3-SL-L>Smart Pole Foundation

B13920 <R3-SL-L>Smart Pole Erection

15-Oct-09

17-Oct-09

19

<R3-SL-L>Smart Pole Erection

B13940 <R3-SL-L>Inspection & Testing

18-Oct-09

19-Oct-09

19

<R3-SL-L>Inspection & Testing

B9960

20-Oct-09

21-Oct-09

19

<R3-SL-L>Backfilling & Compact

11
5

07-Jan-10
07-Jan-10

17-Jan-10
12-Jan-10

0
0

<R3-RM>Road Markin

<R3-RF>Road Furnishings

13-Jan-10

17-Jan-10

<R3-RF>Road Furnish

<R3-T>Punch List

6
5

18-Jan-10
18-Jan-10

23-Jan-10
23-Jan-10

0
0

<R3-SL-L>Backfilling & Compaction

Roads Furnishing, Marking, Others


A3830
<R3-RM>Road Marking
A3840
Testing
A3850

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 32 of 43

<R3-T>Punch List

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Road 1
<1>Road 1
Utilities Works
Utilities in Corridors (Right Side)
Telecommunication Network
B8400 <R1-Tele-R>Excavation & Surface Preparation

20-Jan-09

Original
Duration

Start

Finish

Total
FloatD

2009

12
12
12
12
12
2

12-Aug-09
12-Aug-09
12-Aug-09
12-Aug-09
12-Aug-09
12-Aug-09

23-Aug-09
23-Aug-09
23-Aug-09
23-Aug-09
23-Aug-09
13-Aug-09

88
88
88
88
88
74

<R1-Tele-R>Excavation & Surface Prepar

2010

F M A M J Jul A S O N D

F M

B9630

<R1-Tele-R>Duct Laying

15-Aug-09

16-Aug-09

74

<R1-Tele-R>Duct Laying

B9640

<R1-Tele-R>Joint Box

17-Aug-09

18-Aug-09

74

<R1-Tele-R>Joint Box

B13780 <R1-Tele-R>Inspection & Testing

19-Aug-09

20-Aug-09

74

<R1-Tele-R>Inspection & Testing

B9650

22-Aug-09

23-Aug-09

74

<R1-Tele-R>Backfilling & Compaction

186

18-Mar-09

19-Sep-09

67

73
73
73
73
31
10

18-Jun-09
18-Jun-09
18-Jun-09
18-Jun-09
18-Jun-09
18-Jun-09

29-Aug-09
29-Aug-09
29-Aug-09
29-Aug-09
18-Jul-09
29-Jun-09

88
88
88
88
60
31

<B4-PW-R>Excavation & Surface Preparation

B15600 <B4-PW-R>Pipe Laying

10

23-Jun-09

04-Jul-09

31

<B4-PW-R>Pipe Laying

B15610 <B4-PW-R>Valve Chamber

30-Jun-09

06-Jul-09

53

<B4-PW-R>Valve Chamber

B15620 <B4-PW-R>Valve Fittings

05-Jul-09

11-Jul-09

51

<B4-PW-R>Valve Fittings

B15630 <B4-PW-R>Fire Hydrant

07-Jul-09

13-Jul-09

51

<B4-PW-R>Fire Hydrant

B15640 <B4-PW-R>Inspection & Testing

12-Jul-09

14-Jul-09

51

<B4-PW-R>Inspection & Testing


<B4-PW-R>Backfilling & Compaction

<R1-Tele-R>Backfilling & Compaction

Regional Roads
Road B
<B4>Road B4
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B15580 <B4-PW-R>Excavation & Surface Preparation

B15650 <B4-PW-R>Backfilling & Compaction

13-Jul-09

18-Jul-09

51

28
12

20-Jul-09
20-Jul-09

16-Aug-09
02-Aug-09

88
51

B13370 <B4-Gas-R>Pipe Laying

12

26-Jul-09

08-Aug-09

48

<B4-Gas-R>Pipe Laying

B13380 <B4-Gas-R>Valve Fittings

04-Aug-09

10-Aug-09

74

<B4-Gas-R>Valve Fittings

B15530 <B4-Gas-R>Inspection & Testing

10-Aug-09

11-Aug-09

74

<B4-Gas-R>Inspection & Testing

Gas Network
B13360 <B4-Gas-R>Excavation & Surface Preparation

<B4-Gas-R>Excavation & Surface Preparat

11-Aug-09

16-Aug-09

74

<B4-Gas-R>Backfilling & Compaction

13
3

17-Aug-09
17-Aug-09

29-Aug-09
19-Aug-09

88
74

<B4-Tele-R>Excavation & Surface Prepa

B13320 <B4-Tele-R>Duct Laying

19-Aug-09

22-Aug-09

74

<B4-Tele-R>Duct Laying

B13340 <B4-Tele-R>Manhole

20-Aug-09

23-Aug-09

75

<B4-Tele-R>Manhole

B13330 <B4-Tele-R>Joint Box

22-Aug-09

24-Aug-09

74

<B4-Tele-R>Joint Box

B15520 <B4-Tele-R>Inspection & Testing

24-Aug-09

26-Aug-09

74

<B4-Tele-R>Inspection & Testing

B13390 <B4-Gas-R>Backfilling & Compaction


Telecommunication Network
B13310 <B4-Tele-R>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 33 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

26-Aug-09

29-Aug-09

74

84
84
84
30
30
8

03-Jun-09
03-Jun-09
03-Jun-09
05-Jul-09
05-Jul-09
05-Jul-09

25-Aug-09
25-Aug-09
25-Aug-09
03-Aug-09
03-Aug-09
13-Jul-09

86
86
86
108
108
94

B18680 <H2-PW-R>Pipe Laying

11-Jul-09

20-Jul-09

91

<H2-PW-R>Pipe Laying

B18690 <H2-PW-R>Valve Chamber

16-Jul-09

22-Jul-09

91

<H2-PW-R>Valve Chamber

B18700 <H2-PW-R>Valve Fittings

20-Jul-09

25-Jul-09

91

<H2-PW-R>Valve Fittings

B18710 <H2-PW-R>Fire Hydrant

22-Jul-09

28-Jul-09

91

<H2-PW-R>Fire Hydrant

B18720 <H2-PW-R>Inspection & Testing

28-Jul-09

29-Jul-09

91

<H2-PW-R>Inspection & Testing

B18730 <H2-PW-R>Backfilling & Compaction

30-Jul-09

03-Aug-09

91

<H2-PW-R>Backfilling & Compaction

84
25
5

03-Jun-09
03-Jun-09
03-Jun-09

25-Aug-09
27-Jun-09
08-Jun-09

63
43
36

<H2-SEW-L>Excavation & Surface Preparation

B17370 <H2-SEW-L>Pipe Laying

06-Jun-09

10-Jun-09

36

<H2-SEW-L>Pipe Laying

B17380 <H2-SEW-L>Manhole

06-Jun-09

10-Jun-09

36

<H2-SEW-L>Manhole

B17390 <H2-SEW-L>Inspection & Testing

08-Jun-09

11-Jun-09

36

<H2-SEW-L>Inspection & Testing

B17400 <H2-SEW-L>Backfilling & Compaction

16

09-Jun-09

27-Jun-09

36

16
7

01-Aug-09
01-Aug-09

16-Aug-09
08-Aug-09

20
8

B20330 <H2-Tele-L>Duct Laying

03-Aug-09

10-Aug-09

B20340 <H2-Tele-L>Joint Box

05-Aug-09

12-Aug-09

17

<H2-Tele-L>Joint Box

B20350 <H2-Tele-L>Inspection & Testing

10-Aug-09

13-Aug-09

17

<H2-Tele-L>Inspection & Testing

B20360 <H2-Tele-L>Backfilling & Compaction

13-Aug-09

16-Aug-09

17

<H2-Tele-L>Backfilling & Compaction

9
2

17-Aug-09
17-Aug-09

25-Aug-09
18-Aug-09

63
17

<H2-22kV-L>Excavation & Surface Prepa

B19630 <H2-22kV-L>Cable Laying

19-Aug-09

20-Aug-09

18

<H2-22kV-L>Cable Laying

B19640 <H2-22kV-L>Inspection & Testing

22-Aug-09

23-Aug-09

52

<H2-22kV-L>Inspection & Testing

B19660 <H2-22kV-L>Backfilling & Compaction

24-Aug-09

25-Aug-09

52

<H2-22kV-L>Backfilling & Compaction

120
115
115
115

23-May-09
28-May-09
28-May-09
28-May-09

19-Sep-09
19-Sep-09
19-Sep-09
19-Sep-09

61
61
61
38

B13350 <B4-Tele-R>Backfilling & Compaction


Road H
<H2>Road H2
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B18670 <H2-PW-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Sewerage Network
B17360 <H2-SEW-L>Excavation & Surface Preparation

Telecommunication Network
B20320 <H2-Tele-L>Excavation & Surface Preparation

22kV Network
B19620 <H2-22kV-L>Excavation & Surface Preparation

Road G
<G2>Road G2
Utilities Works
Utilities in Corridors (Right Side)
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 34 of 43

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<B4-Tele-R>Backfilling & Compaction

<H2-PW-R>Excavation & Surface Preparation

<H2-SEW-L>Backfilling & Compaction

<H2-Tele-L>Excavation & Surface Prepara


<H2-Tele-L>Duct Laying

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

24
5

28-May-09
28-May-09

20-Jun-09
02-Jun-09

105
36

B17210 <G2-SEW-R>Pipe Laying

31-May-09

04-Jun-09

36

<G2-SEW-R>Pipe Laying

B17220 <G2-SEW-R>Manhole

31-May-09

04-Jun-09

87

<G2-SEW-R>Manhole

B17230 <G2-SEW-R>Inspection & Testing

03-Jun-09

06-Jun-09

87

<G2-SEW-R>Inspection & Testing

B17240 <G2-SEW-R>Backfilling & Compaction

14

04-Jun-09

20-Jun-09

87

18
5

03-Aug-09
03-Aug-09

20-Aug-09
08-Aug-09

59
51

<G2-Gas-R>Excavation & Surface Prepara

B20800 <G2-Gas-R>Pipe Laying

09-Aug-09

13-Aug-09

48

<G2-Gas-R>Pipe Laying

B20810 <G2-Gas-R>Valve Fittings

12-Aug-09

16-Aug-09

48

<G2-Gas-R>Valve Fittings

B20820 <G2-Gas-R>Inspection & Testing

16-Aug-09

17-Aug-09

48

<G2-Gas-R>Inspection & Testing

B20830 <G2-Gas-R>Backfilling & Compaction

17-Aug-09

20-Aug-09

48

<G2-Gas-R>Backfilling & Compaction

11
2

09-Sep-09
09-Sep-09

19-Sep-09
10-Sep-09

38
32

<G2-22kV-R>Excavation & Surface Pr

B19480 <G2-22kV-R>Cable Laying

13-Sep-09

14-Sep-09

31

<G2-22kV-R>Cable Laying

B19490 <G2-22kV-R>Inspection & Testing

15-Sep-09

16-Sep-09

31

<G2-22kV-R>Inspection & Testing

<G2-22kV-R>Backfilling & Compactio

Sewerage Network
B17200 <G2-SEW-R>Excavation & Surface Preparation

Gas Network
B20790 <G2-Gas-R>Excavation & Surface Preparation

22kV Network
B19470 <G2-22kV-R>Excavation & Surface Preparation

B19510 <G2-22kV-R>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<G2-SEW-R>Excavation & Surface Preparation

<G2-SEW-R>Backfilling & Compaction

17-Sep-09

19-Sep-09

31

81
27
7

27-Jun-09
27-Jun-09
27-Jun-09

15-Sep-09
23-Jul-09
04-Jul-09

65
25
24

<G2-PW-L>Excavation & Surface Preparation

B18470 <G2-PW-L>Pipe Laying

02-Jul-09

09-Jul-09

21

<G2-PW-L>Pipe Laying

B18480 <G2-PW-L>Valve Chamber

07-Jul-09

12-Jul-09

21

<G2-PW-L>Valve Chamber

B18490 <G2-PW-L>Valve Fittings

09-Jul-09

14-Jul-09

21

<G2-PW-L>Valve Fittings

B18500 <G2-PW-L>Fire Hydrant

12-Jul-09

18-Jul-09

21

<G2-PW-L>Fire Hydrant

B18510 <G2-PW-L>Inspection & Testing

18-Jul-09

20-Jul-09

21

<G2-PW-L>Inspection & Testing

B18520 <G2-PW-L>Backfilling & Compaction

21-Jul-09

23-Jul-09

21

<G2-PW-L>Backfilling & Compaction

16
7

09-Aug-09
09-Aug-09

24-Aug-09
16-Aug-09

9
8

<G2-Tele-L>Excavation & Surface Prepar

B20230 <G2-Tele-L>Duct Laying

11-Aug-09

18-Aug-09

<G2-Tele-L>Duct Laying

B20240 <G2-Tele-L>Joint Box

13-Aug-09

20-Aug-09

<G2-Tele-L>Joint Box

B20250 <G2-Tele-L>Inspection & Testing

18-Aug-09

22-Aug-09

<G2-Tele-L>Inspection & Testing

B20260 <G2-Tele-L>Backfilling & Compaction

22-Aug-09

24-Aug-09

<G2-Tele-L>Backfilling & Compaction

9
3

25-Aug-09
25-Aug-09

02-Sep-09
27-Aug-09

10
8

Utilities in Corridors (Left Side)


Potable Water Network
B18440 <G2-PW-L>Excavation & Surface Preparation

Telecommunication Network
B20220 <G2-Tele-L>Excavation & Surface Preparation

22kV Network
B19520 <G2-22kV-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 35 of 43

<G2-22kV-L>Excavation & Surface Prep

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B19530 <G2-22kV-L>Cable Laying

27-Aug-09

30-Aug-09

<G2-22kV-L>Cable Laying

B19540 <G2-22kV-L>Inspection & Testing

30-Aug-09

31-Aug-09

<G2-22kV-L>Inspection & Testing

B19560 <G2-22kV-L>Backfilling & Compaction

01-Sep-09

02-Sep-09

<G2-22kV-L>Backfilling & Compaction

13
4

03-Sep-09
03-Sep-09

15-Sep-09
07-Sep-09

65
8

B21380 <G2-LV-L>Cable Laying

06-Sep-09

09-Sep-09

B21390 <G2-LV-L>Inspection & Testing

09-Sep-09

10-Sep-09

54

<G2-LV-L>Inspection & Testing

B21410 <G2-LV-L>Backfilling & Compaction

12-Sep-09

15-Sep-09

54

<G2-LV-L>Backfilling & Compaction

67
67
20
20
5

23-May-09
23-May-09
23-May-09
23-May-09
23-May-09

28-Jul-09
28-Jul-09
11-Jun-09
11-Jun-09
27-May-09

114
114
161
161
36

B17320 <G3-SEW-R>Pipe Laying

25-May-09

30-May-09

36

B17330 <G3-SEW-R>Manhole

25-May-09

30-May-09

135

<G3-SEW-R>Manhole

B17340 <G3-SEW-R>Inspection & Testing

27-May-09

31-May-09

135

<G3-SEW-R>Inspection & Testing

B17350 <G3-SEW-R>Backfilling & Compaction

13

28-May-09

11-Jun-09

135

38
38
5

21-Jun-09
21-Jun-09
21-Jun-09

28-Jul-09
28-Jul-09
25-Jun-09

114
114
21

B18610 <G3-PW-L>Pipe Laying

27-Jun-09

01-Jul-09

21

<G3-PW-L>Pipe Laying

B18620 <G3-PW-L>Valve Chamber

02-Jul-09

07-Jul-09

96

<G3-PW-L>Valve Chamber

B18630 <G3-PW-L>Valve Fittings

08-Jul-09

13-Jul-09

96

<G3-PW-L>Valve Fittings

B18640 <G3-PW-L>Fire Hydrant

14-Jul-09

20-Jul-09

96

<G3-PW-L>Fire Hydrant

B18650 <G3-PW-L>Inspection & Testing

21-Jul-09

26-Jul-09

96

<G3-PW-L>Inspection & Testing

B18660 <G3-PW-L>Backfilling & Compaction

23-Jul-09

28-Jul-09

96

<G3-PW-L>Backfilling & Compaction

129
9
9
9
9
2

10-May-09
19-Aug-09
19-Aug-09
19-Aug-09
19-Aug-09
19-Aug-09

15-Sep-09
27-Aug-09
27-Aug-09
27-Aug-09
27-Aug-09
20-Aug-09

65
61
61
61
61
48

<E1-22kV-L>Excavation & Surface Prepa

B19500 <E1-22kV-L>Cable Laying

22-Aug-09

23-Aug-09

48

<E1-22kV-L>Cable Laying

B19550 <E1-22kV-L>Inspection & Testing

24-Aug-09

25-Aug-09

50

<E1-22kV-L>Inspection & Testing

B19570 <E1-22kV-L>Backfilling & Compaction

26-Aug-09

27-Aug-09

50

<E1-22kV-L>Backfilling & Compaction

LV Network
B21370 <G2-LV-L>Excavation & Surface Preparation

<G3>Road G3
Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B17310 <G3-SEW-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Potable Water Network
B18600 <G3-PW-L>Excavation & Surface Preparation

Road E
<E1>Road E1
Utilities Works
Utilities in Corridors (Left Side)
22kV Network
B19450 <E1-22kV-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 36 of 43

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<G2-LV-L>Excavation & Surface Prepa


<G2-LV-L>Cable Laying

<G3-SEW-R>Excavation & Surface Preparation


<G3-SEW-R>Pipe Laying

<G3-SEW-R>Backfilling & Compaction

<G3-PW-L>Excavation & Surface Preparation

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

113
113
113
15
4

10-May-09
10-May-09
10-May-09
10-May-09
10-May-09

30-Aug-09
30-Aug-09
30-Aug-09
24-May-09
13-May-09

58
58
58
76
31

<E2-SEW-L>Excavation & Surface Preparation

B17160 <E2-SEW-L>Pipe Laying

12-May-09

16-May-09

31

<E2-SEW-L>Pipe Laying

B17170 <E2-SEW-L>Manhole

12-May-09

16-May-09

64

<E2-SEW-L>Manhole

B17180 <E2-SEW-L>Inspection & Testing

14-May-09

17-May-09

64

<E2-SEW-L>Inspection & Testing

B17190 <E2-SEW-L>Backfilling & Compaction

16-May-09

24-May-09

64

28
6

30-Jun-09
30-Jun-09

27-Jul-09
06-Jul-09

83
33

<E2-PW-L>Excavation & Surface Preparation

B17780 <E2-PW-L>Pipe Laying

05-Jul-09

11-Jul-09

31

<E2-PW-L>Pipe Laying

B17790 <E2-PW-L>Valve Chamber

09-Jul-09

13-Jul-09

69

<E2-PW-L>Valve Chamber

B17800 <E2-PW-L>Valve Fittings

12-Jul-09

15-Jul-09

69

<E2-PW-L>Valve Fittings

B17810 <E2-PW-L>Fire Hydrant

14-Jul-09

21-Jul-09

69

<E2-PW-L>Fire Hydrant

B17820 <E2-PW-L>Inspection & Testing

21-Jul-09

22-Jul-09

69

<E2-PW-L>Inspection & Testing

B17830 <E2-PW-L>Backfilling & Compaction

23-Jul-09

27-Jul-09

69

<E2-PW-L>Backfilling & Compaction

9
2

22-Aug-09
22-Aug-09

30-Aug-09
23-Aug-09

58
48

<E2-22kV-L>Excavation & Surface Prep

B19430 <E2-22kV-L>Cable Laying

24-Aug-09

25-Aug-09

48

<E2-22kV-L>Cable Laying

B19440 <E2-22kV-L>Inspection & Testing

26-Aug-09

27-Aug-09

48

<E2-22kV-L>Inspection & Testing


<E2-22kV-L>Backfilling & Compaction

<E2>Road E2
Utilities Works
Utilities in Corridors (Left Side)
Sewerage Network
B17150 <E2-SEW-L>Excavation & Surface Preparation

Potable Water Network


B17770 <E2-PW-L>Excavation & Surface Preparation

22kV Network
B19420 <E2-22kV-L>Excavation & Surface Preparation

B19460 <E2-22kV-L>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<E2-SEW-L>Backfilling & Compaction

29-Aug-09

30-Aug-09

48

26
26
26
26
4

07-Jul-09
07-Jul-09
07-Jul-09
07-Jul-09
07-Jul-09

01-Aug-09
01-Aug-09
01-Aug-09
01-Aug-09
11-Jul-09

110
110
110
110
33

B17920 <E3-PW-L>Pipe Laying

12-Jul-09

15-Jul-09

31

<E3-PW-L>Pipe Laying

B17930 <E3-PW-L>Valve Chamber

14-Jul-09

18-Jul-09

93

<E3-PW-L>Valve Chamber

B17940 <E3-PW-L>Valve Fittings

16-Jul-09

21-Jul-09

93

<E3-PW-L>Valve Fittings

B17950 <E3-PW-L>Fire Hydrant

20-Jul-09

26-Jul-09

93

<E3-PW-L>Fire Hydrant

B17960 <E3-PW-L>Inspection & Testing

26-Jul-09

27-Jul-09

93

<E3-PW-L>Inspection & Testing

B17970 <E3-PW-L>Backfilling & Compaction

28-Jul-09

01-Aug-09

93

<E3-PW-L>Backfilling & Compaction

66
66

12-Jul-09
12-Jul-09

15-Sep-09
15-Sep-09

65
65

<E3>Road E3
Utilities Works
Utilities in Corridors (Left Side)
Potable Water Network
B17910 <E3-PW-L>Excavation & Surface Preparation

<E4>Road E4
Utilities Works
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 37 of 43

<E3-PW-L>Excavation & Surface Preparation

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

66
31
9

12-Jul-09
12-Jul-09
12-Jul-09

15-Sep-09
11-Aug-09
22-Jul-09

65
36
33

<E4-PW-L>Excavation & Surface Preparatio

B18060 <E4-PW-L>Pipe Laying

16-Jul-09

27-Jul-09

31

<E4-PW-L>Pipe Laying

B18070 <E4-PW-L>Valve Chamber

26-Jul-09

29-Jul-09

31

<E4-PW-L>Valve Chamber

B18080 <E4-PW-L>Valve Fittings

28-Jul-09

01-Aug-09

31

<E4-PW-L>Valve Fittings

B18090 <E4-PW-L>Fire Hydrant

30-Jul-09

05-Aug-09

31

<E4-PW-L>Fire Hydrant

B18100 <E4-PW-L>Inspection & Testing

05-Aug-09

06-Aug-09

31

<E4-PW-L>Inspection & Testing

B18110 <E4-PW-L>Backfilling & Compaction

08-Aug-09

11-Aug-09

31

<E4-PW-L>Backfilling & Compaction

8
2

08-Sep-09
08-Sep-09

15-Sep-09
09-Sep-09

65
8

B21160 <E4-LV-L>Cable Laying

10-Sep-09

12-Sep-09

B21170 <E4-LV-L>Inspection & Testing

13-Sep-09

14-Sep-09

54

<E4-LV-L>Inspection & Testing

B21190 <E4-LV-L>Backfilling & Compaction

14-Sep-09

15-Sep-09

54

<E4-LV-L>Backfilling & Compaction

49
28
28
28
28
4

31-May-09
03-Jun-09
03-Jun-09
03-Jun-09
03-Jun-09
03-Jun-09

18-Jul-09
30-Jun-09
30-Jun-09
30-Jun-09
30-Jun-09
07-Jun-09

124
142
142
142
142
124

<F2-PW-R>Excavation & Surface Preparation

B18200 <F2-PW-R>Pipe Laying

06-Jun-09

09-Jun-09

124

<F2-PW-R>Pipe Laying

B18210 <F2-PW-R>Valve Chamber

09-Jun-09

11-Jun-09

124

<F2-PW-R>Valve Chamber

B18220 <F2-PW-R>Valve Fittings

11-Jun-09

14-Jun-09

124

<F2-PW-R>Valve Fittings

B18230 <F2-PW-R>Fire Hydrant

20-Jun-09

25-Jun-09

119

<F2-PW-R>Fire Hydrant

B18240 <F2-PW-R>Inspection & Testing

25-Jun-09

27-Jun-09

119

<F2-PW-R>Inspection & Testing

B18250 <F2-PW-R>Backfilling & Compaction

28-Jun-09

30-Jun-09

119

<F2-PW-R>Backfilling & Compaction

49
49
49
49
3

31-May-09
31-May-09
31-May-09
31-May-09
31-May-09

18-Jul-09
18-Jul-09
18-Jul-09
18-Jul-09
02-Jun-09

124
124
124
124
124

<F3-PW-L>Excavation & Surface Preparation

B18340 <F3-PW-L>Pipe Laying

02-Jun-09

04-Jun-09

124

<F3-PW-L>Pipe Laying

B18350 <F3-PW-L>Valve Chamber

06-Jun-09

07-Jun-09

127

<F3-PW-L>Valve Chamber

B18360 <F3-PW-L>Valve Fittings

05-Jul-09

06-Jul-09

104

<F3-PW-L>Valve Fittings

B18370 <F3-PW-L>Fire Hydrant

07-Jul-09

13-Jul-09

104

<F3-PW-L>Fire Hydrant

Utilities in Corridors (Left Side)


Potable Water Network
B18050 <E4-PW-L>Excavation & Surface Preparation

LV Network
B21140 <E4-LV-L>Excavation & Surface Preparation

Road F
<F2>Road F2
Utilities Works
Utilities in Corridors (Right Side)
Potable Water Network
B18190 <F2-PW-R>Excavation & Surface Preparation

<F3>Road F3
Utilities Works
Utilities in Corridors (Left Side)
Potable Water Network
B18330 <F3-PW-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 38 of 43

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<E4-LV-L>Excavation & Surface Prepa


<E4-LV-L>Cable Laying

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B18380 <F3-PW-L>Inspection & Testing

13-Jul-09

14-Jul-09

104

<F3-PW-L>Inspection & Testing

B18390 <F3-PW-L>Backfilling & Compaction

15-Jul-09

18-Jul-09

104

<F3-PW-L>Backfilling & Compaction

161
159
159
159
36
3

18-Mar-09
18-Mar-09
18-Mar-09
18-Mar-09
18-Mar-09
18-Mar-09

25-Aug-09
23-Aug-09
23-Aug-09
23-Aug-09
22-Apr-09
21-Mar-09

63
65
65
65
32
45

<J1-SEW-R>Excavation & Surface Preparation

B17470 <J1-SEW-R>Manhole

21-Mar-09

23-Mar-09

45

<J1-SEW-R>Manhole

B17460 <J1-SEW-R>Pipe Laying

11-Apr-09

13-Apr-09

27

<J1-SEW-R>Pipe Laying

B17480 <J1-SEW-R>Inspection & Testing

13-Apr-09

14-Apr-09

27

<J1-SEW-R>Inspection & Testing

Road J
<J1>Road J1
Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B17450 <J1-SEW-R>Excavation & Surface Preparation

B17490 <J1-SEW-R>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<J1-SEW-R>Backfilling & Compaction

14-Apr-09

22-Apr-09

27

16
3

10-May-09
10-May-09

25-May-09
12-May-09

36
15

<J1-PW-R>Excavation & Surface Preparation

B18890 <J1-PW-R>Pipe Laying

12-May-09

14-May-09

15

<J1-PW-R>Pipe Laying

B18900 <J1-PW-R>Valve Chamber

16-May-09

17-May-09

31

<J1-PW-R>Valve Chamber

B18910 <J1-PW-R>Valve Fittings

18-May-09

19-May-09

31

<J1-PW-R>Valve Fittings

B18920 <J1-PW-R>Fire Hydrant

19-May-09

21-May-09

31

<J1-PW-R>Fire Hydrant

B18930 <J1-PW-R>Inspection & Testing

21-May-09

23-May-09

31

<J1-PW-R>Inspection & Testing

B18940 <J1-PW-R>Backfilling & Compaction

23-May-09

25-May-09

31

<J1-PW-R>Backfilling & Compaction

12
4

23-May-09
23-May-09

03-Jun-09
26-May-09

7
2

<J1-Gas-R>Excavation & Surface Preparation

B20900 <J1-Gas-R>Pipe Laying

25-May-09

28-May-09

<J1-Gas-R>Pipe Laying

B20910 <J1-Gas-R>Valve Fittings

28-May-09

31-May-09

<J1-Gas-R>Valve Fittings

B20920 <J1-Gas-R>Inspection & Testing

31-May-09

01-Jun-09

<J1-Gas-R>Inspection & Testing

B20930 <J1-Gas-R>Backfilling & Compaction

01-Jun-09

03-Jun-09

<J1-Gas-R>Backfilling & Compaction

10
4

04-Jun-09
04-Jun-09

13-Jun-09
08-Jun-09

17
6

B20380 <J1-Tele-R>Duct Laying

06-Jun-09

09-Jun-09

B20390 <J1-Tele-R>Joint Box

08-Jun-09

10-Jun-09

15

<J1-Tele-R>Joint Box

B20400 <J1-Tele-R>Inspection & Testing

10-Jun-09

11-Jun-09

15

<J1-Tele-R>Inspection & Testing

B20410 <J1-Tele-R>Backfilling & Compaction

11-Jun-09

13-Jun-09

15

<J1-Tele-R>Backfilling & Compaction

9
2

15-Aug-09
15-Aug-09

23-Aug-09
16-Aug-09

65
48

<J1-22kV-R>Excavation & Surface Prepa

17-Aug-09

18-Aug-09

48

<J1-22kV-R>Cable Laying

Potable Water Network


B18880 <J1-PW-R>Excavation & Surface Preparation

Gas Network
B20890 <J1-Gas-R>Excavation & Surface Preparation

Telecommunication Network
B20370 <J1-Tele-R>Excavation & Surface Preparation

22kV Network
B19770 <J1-22kV-R>Excavation & Surface Preparation
B19780 <J1-22kV-R>Cable Laying
Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 39 of 43

<J1-Tele-R>Excavation & Surface Preparation


<J1-Tele-R>Duct Laying

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B19790 <J1-22kV-R>Inspection & Testing

19-Aug-09

20-Aug-09

54

<J1-22kV-R>Inspection & Testing

B19810 <J1-22kV-R>Backfilling & Compaction

22-Aug-09

23-Aug-09

54

<J1-22kV-R>Backfilling & Compaction

157
157
157
37
3

22-Mar-09
22-Mar-09
22-Mar-09
22-Mar-09
22-Mar-09

25-Aug-09
25-Aug-09
25-Aug-09
27-Apr-09
24-Mar-09

63
63
63
33
46

<J2-SEW-R>Excavation & Surface Preparation

B17520 <J2-SEW-R>Manhole

24-Mar-09

26-Mar-09

46

<J2-SEW-R>Manhole

B17510 <J2-SEW-R>Pipe Laying

14-Apr-09

16-Apr-09

28

<J2-SEW-R>Pipe Laying

B17530 <J2-SEW-R>Inspection & Testing

16-Apr-09

18-Apr-09

28

<J2-SEW-R>Inspection & Testing

B17540 <J2-SEW-R>Backfilling & Compaction

18-Apr-09

27-Apr-09

28

13
4

27-May-09
27-May-09

08-Jun-09
31-May-09

2
3

<J2-Gas-R>Excavation & Surface Preparation

B21000 <J2-Gas-R>Pipe Laying

30-May-09

02-Jun-09

<J2-Gas-R>Pipe Laying

B21010 <J2-Gas-R>Valve Fittings

02-Jun-09

04-Jun-09

<J2-Gas-R>Valve Fittings

B21020 <J2-Gas-R>Inspection & Testing

04-Jun-09

06-Jun-09

<J2-Gas-R>Inspection & Testing

B21030 <J2-Gas-R>Backfilling & Compaction

06-Jun-09

08-Jun-09

<J2-Gas-R>Backfilling & Compaction

13
4

09-Jun-09
09-Jun-09

21-Jun-09
13-Jun-09

9
2

<J2-Tele-R>Excavation & Surface Preparation

B20480 <J2-Tele-R>Duct Laying

13-Jun-09

14-Jun-09

<J2-Tele-R>Duct Laying

B20490 <J2-Tele-R>Joint Box

14-Jun-09

18-Jun-09

<J2-Tele-R>Joint Box

B20500 <J2-Tele-R>Manhole

15-Jun-09

17-Jun-09

<J2-Tele-R>Manhole

B20510 <J2-Tele-R>Inspection & Testing

18-Jun-09

20-Jun-09

<J2-Tele-R>Inspection & Testing

B20520 <J2-Tele-R>Backfilling & Compaction

20-Jun-09

21-Jun-09

<J2-Tele-R>Backfilling & Compaction

9
2

17-Aug-09
17-Aug-09

25-Aug-09
18-Aug-09

63
48

<J2-22kV-R>Excavation & Surface Prepa

B19880 <J2-22kV-R>Cable Laying

19-Aug-09

20-Aug-09

48

<J2-22kV-R>Cable Laying

B19890 <J2-22kV-R>Inspection & Testing

22-Aug-09

23-Aug-09

52

<J2-22kV-R>Inspection & Testing

B19910 <J2-22kV-R>Backfilling & Compaction

24-Aug-09

25-Aug-09

52

<J2-22kV-R>Backfilling & Compaction

22
22
3

13-May-09
13-May-09
13-May-09

03-Jun-09
03-Jun-09
16-May-09

27
27
15

<J2-PW-L>Excavation & Surface Preparation

B19030 <J2-PW-L>Pipe Laying

16-May-09

18-May-09

15

<J2-PW-L>Pipe Laying

B19040 <J2-PW-L>Valve Chamber

19-May-09

20-May-09

23

<J2-PW-L>Valve Chamber

B19050 <J2-PW-L>Valve Fittings

21-May-09

23-May-09

23

<J2-PW-L>Valve Fittings

<J2>Road J2
Utilities Works
Utilities in Corridors (Right Side)
Sewerage Network
B17500 <J2-SEW-R>Excavation & Surface Preparation

Gas Network
B20990 <J2-Gas-R>Excavation & Surface Preparation

Telecommunication Network
B20470 <J2-Tele-R>Excavation & Surface Preparation

22kV Network
B19870 <J2-22kV-R>Excavation & Surface Preparation

Utilities in Corridors (Left Side)


Potable Water Network
B19020 <J2-PW-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 40 of 43

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<J2-SEW-R>Backfilling & Compaction

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

B19060 <J2-PW-L>Fire Hydrant

24-May-09

30-May-09

23

<J2-PW-L>Fire Hydrant

B19070 <J2-PW-L>Inspection & Testing

30-May-09

31-May-09

23

<J2-PW-L>Inspection & Testing

B19080 <J2-PW-L>Backfilling & Compaction

01-Jun-09

03-Jun-09

23

<J2-PW-L>Backfilling & Compaction

142
142
142
142
43
7

25-Mar-09
25-Mar-09
25-Mar-09
25-Mar-09
25-Mar-09
25-Mar-09

13-Aug-09
13-Aug-09
13-Aug-09
13-Aug-09
06-May-09
01-Apr-09

98
98
98
98
55
63

<K-SEW-CL>Excavation & Surface Preparation

B17570 <K-SEW-CL>Manhole

28-Mar-09

04-Apr-09

65

<K-SEW-CL>Manhole

B17560 <K-SEW-CL>Pipe Laying

18-Apr-09

25-Apr-09

45

<K-SEW-CL>Pipe Laying

B17580 <K-SEW-CL>Inspection & Testing

22-Apr-09

26-Apr-09

47

<K-SEW-CL>Inspection & Testing

B17590 <K-SEW-CL>Backfilling & Compaction

12

23-Apr-09

06-May-09

47

30
15

15-Jul-09
15-Jul-09

13-Aug-09
02-Aug-09

98
82

<K-Tele-CL>Excavation & Surface Prepara

B20540 <K-Tele-CL>Duct Laying

15

18-Jul-09

04-Aug-09

82

<K-Tele-CL>Duct Laying

B20550 <K-Tele-CL>Joint Box

10

26-Jul-09

05-Aug-09

82

<K-Tele-CL>Joint Box

B20560 <K-Tele-CL>Inspection & Testing

02-Aug-09

06-Aug-09

82

<K-Tele-CL>Inspection & Testing

B20570 <K-Tele-CL>Backfilling & Compaction

10

03-Aug-09

13-Aug-09

82

28
28
10

17-May-09
17-May-09
17-May-09

13-Jun-09
13-Jun-09
27-May-09

17
17
15

<K-PW-R>Excavation & Surface Preparation

B19170 <K-PW-R>Pipe Laying

10

19-May-09

30-May-09

15

<K-PW-R>Pipe Laying

B19180 <K-PW-R>Valve Chamber

26-May-09

01-Jun-09

15

<K-PW-R>Valve Chamber

B19190 <K-PW-R>Valve Fittings

28-May-09

03-Jun-09

15

<K-PW-R>Valve Fittings

B19200 <K-PW-R>Fire Hydrant

31-May-09

06-Jun-09

15

<K-PW-R>Fire Hydrant

B19210 <K-PW-R>Inspection & Testing

06-Jun-09

07-Jun-09

15

<K-PW-R>Inspection & Testing

Road K
<K>Road K
Utilities Works
Utilities in Road Edge/Median
Sewerage Network
B17550 <K-SEW-CL>Excavation & Surface Preparation

Telecommunication Network
B20530 <K-Tele-CL>Excavation & Surface Preparation

Utilities in Corridors (Right Side)


Potable Water Network
B19160 <K-PW-R>Excavation & Surface Preparation

B19220 <K-PW-R>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

<K-SEW-CL>Backfilling & Compaction

<K-Tele-CL>Backfilling & Compaction

<K-PW-R>Backfilling & Compaction

08-Jun-09

13-Jun-09

15

14
14
5

01-Jun-09
01-Jun-09
01-Jun-09

14-Jun-09
14-Jun-09
06-Jun-09

16
16
14

<K-Gas-L>Excavation & Surface Preparation

B21050 <K-Gas-L>Pipe Laying

03-Jun-09

08-Jun-09

14

<K-Gas-L>Pipe Laying

B21060 <K-Gas-L>Valve Fittings

08-Jun-09

10-Jun-09

14

<K-Gas-L>Valve Fittings

B21070 <K-Gas-L>Inspection & Testing

10-Jun-09

11-Jun-09

14

<K-Gas-L>Inspection & Testing

B21080 <K-Gas-L>Backfilling & Compaction

11-Jun-09

14-Jun-09

14

<K-Gas-L>Backfilling & Compaction

Utilities in Corridors (Left Side)


Gas Network
B21040 <K-Gas-L>Excavation & Surface Preparation

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 41 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

20-Jan-09

Original
Duration

Start

86
86
86
86
32
8

04-Apr-09
04-Apr-09
04-Apr-09
04-Apr-09
04-Apr-09
04-Apr-09

28-Jun-09
28-Jun-09
28-Jun-09
28-Jun-09
05-May-09
12-Apr-09

2
2
2
2
41
40

<RP2-PW-L>Excavation & Surface Preparation

B19310 <RP2-PW-L>Pipe Laying

06-Apr-09

14-Apr-09

40

<RP2-PW-L>Pipe Laying

B19320 <RP2-PW-L>Valve Chamber

13-Apr-09

16-Apr-09

40

<RP2-PW-L>Valve Chamber

B19330 <RP2-PW-L>Valve Fittings

21-Apr-09

25-Apr-09

35

<RP2-PW-L>Valve Fittings

B19340 <RP2-PW-L>Fire Hydrant

23-Apr-09

29-Apr-09

35

<RP2-PW-L>Fire Hydrant

B19350 <RP2-PW-L>Inspection & Testing

29-Apr-09

30-Apr-09

35

<RP2-PW-L>Inspection & Testing


<RP2-PW-L>Backfilling & Compaction

Ramp 2
<R2> Ramp 2
Utilities Works
Utilities in Corridors (Left Side)
Potable Water Network
B19300 <RP2-PW-L>Excavation & Surface Preparation

B19360 <RP2-PW-L>Backfilling & Compaction

Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

02-May-09

05-May-09

35

15
7

14-Jun-09
14-Jun-09

28-Jun-09
21-Jun-09

2
2

<RP2-Tele-L>Excavation & Surface Preparation

B20640 <RP2-Tele-L>Duct Laying

16-Jun-09

23-Jun-09

<RP2-Tele-L>Duct Laying

B20650 <RP2-Tele-L>Joint Box

18-Jun-09

25-Jun-09

<RP2-Tele-L>Joint Box

B20660 <RP2-Tele-L>Manhole

18-Jun-09

25-Jun-09

<RP2-Tele-L>Manhole

B20670 <RP2-Tele-L>Inspection & Testing

23-Jun-09

27-Jun-09

<RP2-Tele-L>Inspection & Testing

B20680 <RP2-Tele-L>Backfilling & Compaction

24-Jun-09

28-Jun-09

<RP2-Tele-L>Backfilling & Compaction

88

04-May-09

30-Jul-09

88
4

04-May-09
04-May-09

30-Jul-09
07-May-09

0
15

<struc>:<STP>: Formwork for PC for Raft

Telecommunication Network
B20630 <RP2-Tele-L>Excavation & Surface Preparation

Structures
Temporary Sanitary Treatment Plant [STP]
A30010
<struc>:<STP>: Formwork for PC for Raft
A30040

<struc>:<STP>: Concrete Pouring for PC Raft

09-May-09

10-May-09

15

<struc>:<STP>: Concrete Pouring for PC Raft

A30020

<struc>:<STP>: Reinforcement for RC Raft

11-May-09

18-May-09

15

<struc>:<STP>: Reinforcement for RC Raft

A30050

<struc>:<STP>: Formwork for RC for Raft

12-May-09

19-May-09

15

<struc>:<STP>: Formwork for RC for Raft

A30030

<struc>:<STP>: Concrete Pouring for RC Raft

20-May-09

21-May-09

15

<struc>:<STP>: Concrete Pouring for RC Raft

A30080

<struc>:<STP>: Curing for RC Raft

23-May-09

27-May-09

15

A30060

<struc>:<STP>: Installation of STP

20

15-Jun-09

07-Jul-09

A30070

<struc>:<STP>: Testing and Commissioning of STP

15

08-Jul-09

26-Jul-09

<struc>:<STP>: Testing and Commissioning

A30150

<struc>:<STP>: Cleaning of STP

27-Jul-09

29-Jul-09

<struc>:<STP>: Cleaning of STP

A30160

<struc>:<STP>: Handover of STP

<struc>:<STP>: Handover of STP

Pre-Cast Chambers & Manholes

30-Jul-09

30-Jul-09

198

14-Mar-09

27-Sep-09

53

<struc>:<STP>: Curing for RC Raft


<struc>:<STP>: Installation of STP

A30610

Fabrication of pre-cast Manholes (Sewerage Network)

60

14-Mar-09

12-May-09

191

Fabrication of pre-cast Manholes (Sewerage Network)

A30470

Fabrication of pre-cast Valve Chambers (Potable Water Network)

60

04-Apr-09

02-Jun-09

170

Fabrication of pre-cast Valve Chambers (Potable W

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 42 of 43

Al Reem Island Development-Sector 56-Baseline TB01[200109]


Activity ID

Classic Schedule Layout

Activity Name

Original
Duration

Start

20-Jan-09
Finish

Total
FloatD

2009
J

2010

F M A M J Jul A S O N D

F M

A30620

Fabrication of pre-cast Manholes (Telecommunication Network)

60

04-May-09

02-Jul-09

140

Fabrication of pre-cast Manholes (Telecommun

A30540

Fabrication of pre-cast Valve Chambers (Irrigation Network)

60

30-Jun-09

28-Aug-09

83

Fabrication of pre-cast Valve Chambers

A30630

Fabrication of pre-cast Manholes (Surface Water Network)

60

30-Jul-09

27-Sep-09

53

232

01-Jul-09

17-Feb-10

Testing and Commissioning

Fabrication of pre-cast Manholes (Su

93

27-Jul-09

27-Oct-09

29

A12630

Testing of Sewage Network

27-Jul-09

01-Aug-09

98

A11940

Testing of Potable Water Network

12-Aug-09

17-Aug-09

84

A2320

Testing of Gas Network

22-Aug-09

26-Aug-09

76

Testing of Gas Network

A11830

Testing of Telecommunication Network

24-Aug-09

29-Aug-09

74

Testing of Telecommunication Network

A15800

Testing of Irrigation Network

01-Sep-09

06-Sep-09

67

A13560

Testing of Low Voltage Network

24-Sep-09

29-Sep-09

49

Testing of Low Voltage Network

A15600

Testing of Surface Water Network

27-Sep-09

03-Oct-09

46

Testing of Surface Water Network

A12000

Testing of 22KV Electrical Network

30-Sep-09

05-Oct-09

24

Testing of 22KV Electrical Network

A12060

Testing of Street Lighting Network

Testing of Street Lighting Networ

Testing and Commissioning for Utilities

Testing and Commissioning for All Project

22-Oct-09

27-Oct-09

25

222

01-Jul-09

07-Feb-10

Testing of Sewage Network


Testing of Potable Water Network

Testing of Irrigation Network

A28990

Testing & Commissioning of Sorbonne Area

20

01-Jul-09

20-Jul-09

Testing & Commissioning of Sorbonne Area

A7950

Testing & Commissioning of Whole Project

60

29-Oct-09

10-Jan-10

24

Testing & Commission

A8000

Punch List of Whole Project

Punch List of Who

Final Inspection

15

24-Jan-10

07-Feb-10

212

21-Jul-09

17-Feb-10

A29490

Final Inspection for Sorbonne Area

10

21-Jul-09

30-Jul-09

A29470

Final Inspection of Whole Project

10

08-Feb-10

17-Feb-10

23

06-Oct-09

28-Oct-09

28

20

06-Oct-09

28-Oct-09

24

35

13-Jan-10

16-Feb-10

35

13-Jan-10

16-Feb-10

Cable Pulling
A30400

Cable Pulling for Power Network

Demobilization
A29480

Demobilization

Remaining Level of Effort

Remaining Work

Milestone

Actual Work

Critical Remaining Work

Actual Level ...

Page 43 of 43

Final Inspection for Sorbonne Area

Final Inspection of

Cable Pulling for Power Network

Demobilization

You might also like