Professional Documents
Culture Documents
by
Abstract
An alternative structural system for short span bridges is presented: a precast segmental double-T
with external, unbonded post-tensioning tendons. Single-span designs from 20 to 45 m long
show that the system can be implemented over a wide range of spans and that the systems
sensitivity to post-tensioning losses reported in previous literature can be reduced by aligning the
prestressing force more concentrically.
Designs for multi-span bridges using this system are presented using simply supported spans
connected by thin flexible linking slabs made of ultra high-performance fibre-reinforced concrete
and using sections made fully continuous over intermediate supports.
A simplified method of geometry control is presented to facilitate the proper alignment of precast
segments without the use of match casting.
The precast segmental double-T bridge is compared to sixteen existing slab on girder bridges and
found to be a competitive alternative in terms of material use, cost, construction schedule, and
aesthetic merit.
ii
Acknowledgments
Funding for this research has been provided by the National Science and Engineering Research
Council and by McCormick Rankin Corporation.
My interest in bridges has grown from a curiosity when I first began my studies for this degree to
a passion today. Professor Paul Gauvreau has kindled what was once a small spark into a hearty
fire. He has also taught me to take the time to do things thoroughly, neatly, and with style, and
how to comport myself as a designer.
Doug Dixon has been a mentor to me for the past ten years. His ability to stay calm and
approachable while being extremely productive and industrious is inspiring. His confidence in
me has been an encouragement throughout my career.
Bob Stofko and the rest of my friends at McCormick Rankin have supported me in my return to
university and for that I thank them.
Various colleagues at the University of Toronto have helped me in the writing of this thesis.
Eileen Li graciously provided me with all the information I required to start my research on the
double-T bridge that she originally developed. Negar Elhami Khorasani showed me the ropes
(strands?) of unbonded tendon analysis. Jason Salonga walked me through some concepts
related to ultra high performance fibre-reinforced concrete and passed on some great ideas for
sophisticated ways of presenting data. Andrew Lehan has been a great sounding board and
friend to talk shop with over a couple of pints. Nick Zwerling has been a friend and insightful
Devils advocate in the office. Coffee breaks wouldnt have been the same without David
Johnson.
The myriad formalities and bureaucratic requirements of academic life have all passed relatively
smoothly thanks to the smiling administrative staff of the Civil Engineering Department: Alison
Morley, Shayni Clarke, Colin Anderson, Colleen Kelly, and Nelly Pietropaolo.
iii
Matt Mitrovich, my good friend, provided valuable insight and comforting common sense from a
practicing structural engineer.
Earla and Stuart Smith, my parents, have given me so much. They are always supportive. They
are always loving. I hope I have made them proud.
Throughout the writing of this thesis, Bo Cheyne, my wife, has offered support and insight from
one who has been here before. Her love, encouragement, and strength inspire me to be my best.
iv
Table of Contents
Acknowledgments.......................................................................................................................... iii
Table of Contents ............................................................................................................................ v
List of Tables .................................................................................................................................. x
List of Figures ............................................................................................................................... xii
List of Symbols ........................................................................................................................... xvii
List of Appendices ....................................................................................................................... xxi
Chapter 3 Versatility of the Double-T Base Concept for Simply Supported Spans ..................... 12
3.1 Extensions of Previous Work............................................................................................ 12
3.1.1 Application to a Range of Spans ........................................................................... 12
3.1.2 Variability of Post-tensioning Force ..................................................................... 13
3.1.3 Reduction of Sensitivity to Post-tensioning Force................................................ 13
3.2 Modifications to the Double-T Base Concept .................................................................. 16
3.3 Validation Parametric Studies........................................................................................ 19
3.3.1 Loads and Load Cases .......................................................................................... 19
3.3.1.1 Dead and Superimposed Dead Loads ..................................................... 20
3.3.1.2 Live Loads .............................................................................................. 20
3.3.1.3 Live Load Distribution ........................................................................... 20
3.3.2 Analysis Under Serviceability Limit States .......................................................... 27
3.3.2.1 Bounds for Stage I Tendons ................................................................... 28
3.3.2.2 Bounds for Stage II Tendons .................................................................. 28
3.3.3 Analysis at Ultimate Limit State ........................................................................... 33
3.3.4 Combining Serviceability Limit States and Ultimate Limit States Results .......... 38
3.3.5 Results of Parametric Study .................................................................................. 41
3.3.6 Selection of Section Depths and Midspan Tendon Eccentricities ........................ 46
3.3.7 Preliminary Post-tensioning Anchorage Considerations ...................................... 46
3.3.8 Suggested Post-tensioning Arrangements............................................................. 47
3.3.9 Post-tensioning Details ......................................................................................... 48
3.3.9.1 Transition from Wide to Thin Webs....................................................... 48
3.3.9.2 Number of Segments .............................................................................. 49
3.3.9.3 End Diaphragm Location........................................................................ 49
3.3.10 Finalised Preliminary Concepts ............................................................................ 50
3.4 Conclusions ....................................................................................................................... 51
vi
vii
viii
ix
List of Tables
Table 2.1 Assumed material properties ....................................................................................... 8
Table 3.1 Comparison of live loads derived using two methods ............................................... 27
Table 3.2 Range of bridge variants that satisfy all SLS and ULS criteria ................................. 41
Table 3.3 Permissible range of variation from nominal post-tensioning force.......................... 42
Table 3.4 Selected double-T variants for further study ............................................................. 46
Table 3.5 Feasible and constructible bridge variants ................................................................. 48
Table 3.6 Location of web width transition ............................................................................... 49
Table 3.7 Segment divisions ...................................................................................................... 49
Table 4.1 Rotations imposed on linking slab due to service live loads ..................................... 65
Table 4.2 University of Toronto ultra high-performance fibre-reinforced concrete composition
(adapted from Habel et al., 2008) ................................................................................................. 68
Table 4.3 University of Toronto ultra high-performance fibre-reinforced concrete properties
(adapted from Habel et al., 2008) ................................................................................................. 68
Table 4.4 Flexible linking slab dimensions ............................................................................... 73
Table 4.5 Selected short elastomeric bearings for two-span system ......................................... 74
Table 4.6 Selected tall elastomeric bearings for abutments of four-span system ...................... 75
Table 4.7 Tendon details for continuous configurations ........................................................... 83
Table 4.8 Reinforcing steel requirements to resist transverse tension in diaphragms ............... 93
Table 4.9 Tendons stresses after all losses | p,final as a fraction of fpu, (with an assumed jacking
stress of 0.800fpu) .......................................................................................................................... 97
Table 5.1 Total horizontal misalignment of single span due to compounding geometry error 106
Table 5.2 Total vertical misalignment of single span due to compounding geometry error ... 106
Table 5.3 Alignment errors after segment placement .............................................................. 107
Table 5.4 Alignment errors after segment placement with compensatory adjustments .......... 109
Table 6.1 Segmental double-T mock unit costs (adapted from Li, 2010) ............................... 116
Table 6.2 Construction schedules for various alternative methods | two 40-m spans ............. 120
Table 6.3 Construction schedules for various alternative methods | four 40-m spans............. 120
Table 6.4 Overall comparison of construction methods .......................................................... 121
Table 6.5 Comparison of construction schedules between continuous and simply-supported
double-T options ......................................................................................................................... 122
Table 6.6 Comparison of construction schedules between simply-supported double-T
constructed on falsework and constructed on erection girder ..................................................... 123
Table 6.7 Comparison of construction schedules between precast segmental double-T and
conventional precast girder with cast-in-place deck slab ........................................................... 123
xi
List of Figures
Figure 1.1 Example of a typical overpass structure in Ontario (Iroquois Cranberry Marsh Road
Bridge over Highway 400, Ontario, taken by P. Gauvreau) ........................................................... 1
Figure 1.2 Transverse live load sharing in (a) a slab-on-girder system with (b) infinitely
flexible deck slab and (c) infinitely stiff deck slab ......................................................................... 2
Figure 1.3 The double-T base concept | 1:500 (adapted from Li, 2010) .................................... 4
Figure 2.1 The double-T base concept | 1:500 (adapted from Li, 2010) .................................... 6
Figure 2.2 External tendon layout in plan | 1:200 ........................................................................ 6
Figure 2.3 Assumed material stress-strain relationships for (a) concrete, (b) reinforcing steel,
and (c) post-tensioning steel ........................................................................................................... 8
Figure 3.1 Limits on post-tensioning force and the areas that dictate them .............................. 14
Figure 3.2 Concrete stress sensitivity to level of prestress for double-T base concept (adapted
from Li, 2010) ............................................................................................................................... 15
Figure 3.3 Parameters changed to create bridge variants for parametric study ......................... 17
Figure 3.4 Seventy-three bridge variants for parametric study.................................................. 18
Figure 3.5 Transformation of (a) asymmetric load into (b) pure symmetric and (c) pure
antisymmetric components ........................................................................................................... 21
Figure 3.6 Dimensions used to calculate the torsional constant ................................................ 22
Figure 3.7 Parameters used to calculate the twist due to warping ............................................. 23
Figure 3.8 Live loads used in analysis for parametric study...................................................... 26
Figure 3.9 Explanatory Plot amounts of post-tensioning satisfying serviceability limit state
criteria for a 36.6-m span .............................................................................................................. 30
xii
Figure 3.10 Amounts of post-tensioning satisfying serviceability limit state criteria for 2000mm-deep spans of (a) 20 m, (b) 25 m, (c) 30 m, (d) 36.6 m, (e) 40 m, and (f) 45 m ................... 31
Figure 3.11 Amounts of post-tensioning satisfying serviceability limit state criteria for
(respectively) section depths and spans of (a) 1095 mm, 20 m; (b) 1365 mm, 25 m; (c) 1640 mm,
30 m; (d) 2000 mm, 36.6 m (duplicate of Figure 3.10d); (e) 2185 mm, 40 m; (f) 2460 mm, 45 m
....................................................................................................................................................... 32
Figure 3.12 Bilinear concrete stress-strain curve for 70-MPa concrete (adapted from CEB-FIB,
2010) ............................................................................................................................................. 33
Figure 3.13 Equivalent loading after tendon removal ............................................................... 34
Figure 3.14 Strain and stress profiles for (a) cracking moment, (b) linear elastic moment, and
(c) ultimate moment ...................................................................................................................... 34
Figure 3.15 (a) Dead, superimposed dead, live, and prestress loads and (b) resulting schematic
bending moment diagram ............................................................................................................. 35
Figure 3.16 Scaled bending moment diagram ........................................................................... 35
Figure 3.17 (a) Significant points on bending moment diagram and (b) corresponding concrete
strains at level of prestress ............................................................................................................ 35
Figure 3.18 Elongation of tendon due to deformation ............................................................... 36
Figure 3.19 Elongation of tendon due to force .......................................................................... 36
Figure 3.20 Elongation of tendon due to deformation plotted with elongation due to force when
tendons are assumed to yield and actually (a) do yield or (b) do not yield .................................. 36
Figure 3.21 (a) Result of second iteration and (b) interpolation of actual stress in tendon ....... 37
Figure 3.22 Amounts of post-tensioning satisfying both serviceability and ultimate limit state
criteria for 2000-mm-deep spans of (a) 20 m, (b) 25 m, (c) 30 m, (d) 36.6 m, (e) 40 m, and (f) 45
m ................................................................................................................................................... 39
xiii
Figure 3.23 Amounts of post-tensioning satisfying both serviceability and ultimate limit state
criteria for (respectively) section depths and spans of (a) 1095 mm, 20 m; (b) 1365 mm, 25 m;
(c) 1640 mm, 30 m; (d) 2000 mm, 36.6 m (duplicate of Figure 3.22d); (e) 2185 mm, 40 m; (f)
2460 mm, 45 m ............................................................................................................................. 40
Figure 3.24 Amounts of post-tensioning satisfying both serviceability and ultimate limit state
criteria for varying span lengths for 2000-mm-deep sections with a midspan tendon eccentricity
of (a) 1000 mm, (b) 1075 mm, (c) 1150 mm, (d) 1225 mm, (e) 1300 mm, and (f) 1367 mm ..... 45
Figure 3.25 Anchorage spiral footprints for required number of strands for spans of: (a) 20 m,
(b) 25 m, (c) 30 m, (d) 36.6 m, and (e) 40 m and 45 m | 1:100 .................................................... 47
Figure 3.26 Determination of location of web width transition................................................. 48
Figure 3.27 Design considerations for end diaphragm placement | 1:100 ................................. 50
Figure 3.28 Conceptual design of precast segmental double-T for 20-m spans ........................ 52
Figure 3.29 Conceptual design of precast segmental double-T for 25-m spans ........................ 53
Figure 3.30 Conceptual design of precast segmental double-T for 30-m spans ........................ 54
Figure 3.31 Conceptual design of precast segmental double-T for 36.6-m spans ..................... 55
Figure 3.32 Conceptual design of precast segmental double-T for 40-m spans ........................ 56
Figure 3.33 Conceptual design of precast segmental double-T for 45-m spans ........................ 57
Figure 4.1 Effect of support conditions on linking slab behaviour with (a) two roller supports,
(b) two pin/hinge supports, and (c) one of each type of support (adapted from Okeil and ElSafty,
2005) ............................................................................................................................................. 61
Figure 4.2 Effect of distance between neutral axes on linking slab behaviour with (a) lower
neutral axis and (b) higher neutral axis (adapted from Okeil and ElSafty, 2005) ........................ 62
Figure 4.3 Parameters to be designed for linking slab ............................................................... 64
xiv
Figure 4.4 (a) Strain hardening and (b) strain softening fibre-reinforced concrete stress-strain
relationships (adapted from Habel, 2004) ..................................................................................... 67
Figure 4.5 Schematic of test setup for University of Toronto UHPFRC beam modulus of
rupture tests ................................................................................................................................... 69
Figure 4.6 Results of University of Toronto UHPFRC beam modulus of rupture tests ............ 70
Figure 4.7 Assumed strains in extreme tensile fibres of University of Toronto UHPFRC beams
....................................................................................................................................................... 71
Figure 4.8 Maximum extreme fibre strains in University of Toronto UHPFRC beam modulus
of rupture tests............................................................................................................................... 72
Figure 4.9 Maximum tensile strains in flexible linking slabs as a function of (a) length, with
constant thickness of 100 mm, and (b) thickness, with constant length of 400 mm .................... 73
Figure 4.10 Configurations of flexible linking slabs and bearings for (a) two- and (b) four-span
bridges ........................................................................................................................................... 74
Figure 4.11 Conceptual design of flexible linking slab for adjacent 20-m spans ...................... 76
Figure 4.12 Conceptual design of flexible linking slab for adjacent 25-m spans ...................... 77
Figure 4.13 Conceptual design of flexible linking slab for adjacent 30-m spans ...................... 78
Figure 4.14 Conceptual design of flexible linking slab for adjacent 36.6-m spans ................... 79
Figure 4.15 Conceptual design of flexible linking slab for adjacent 40-m spans ...................... 80
Figure 4.16 Conceptual design of flexible linking slab for adjacent 45-m spans ...................... 81
Figure 4.17 Continuous double-T pier segment ........................................................................ 83
Figure 4.18 Temperature differentials and resulting imposed moments in continuous system. 86
Figure 4.19 Positive moment serviceability limit state analysis for two 45-m spans ................ 88
Figure 4.20 Negative moment serviceability limit state analysis for two 45-m spans .............. 89
xv
Figure 4.21 Truss models for alternative layouts for diaphragm with (a) bearings under webs,
(b) bearings inclined inward, and (c) bearings shifted inward...................................................... 92
Figure 4.22 Proposed diaphragm design | 1:100 ........................................................................ 93
Figure 4.23 Conceptual design of continuous configuration for adjacent 20-m spans .............. 99
Figure 4.24 Conceptual design of continuous configuration for adjacent 36.6-m spans ......... 100
Figure 4.25 Conceptual design of continuous configuration for adjacent 45-m spans ............ 101
Figure 5.1 Match casting (adapted from Interactive Design Systems, 2005) .......................... 103
Figure 5.2 Exaggerated alignment effect of differences in vertex length for a bridge segment
..................................................................................................................................................... 105
Figure 5.3 Alignment error after segment placement .............................................................. 107
Figure 6.1 Effective depth versus span length of double-T bridges ........................................ 111
Figure 6.2 Post-tensioning use versus span length of double-T bridges.................................. 112
Figure 6.3 Span-to-depth ratio versus span length of double-T and conventional bridges ..... 114
Figure 6.4 Effective depth versus span length of double-T and conventional bridges ............ 115
Figure 6.5 Post-tensioning use versus span length of double-T and conventional bridges ..... 115
Figure 6.6 Unit cost of bridge superstructure versus span length of double-T and conventional
bridges ......................................................................................................................................... 117
Figure 6.7 Visual comparison of (a) continuous, (b) simply-supported segmental double-T, and
(c) conventional options .............................................................................................................. 125
Figure 6.8 Visual comparison of (a) double-T and (b) conventional precast girder options ... 128
xvi
List of Symbols
Lp
Lpd
Lpf
av
bot
cp
cp,cr
strain in the concrete at the height of the prestressing steel at a section at the cracking
moment
cp,le
strain in the concrete at the height of the prestressing steel at a section at the
maximum moment resulting from a stress profile entirely within the linear elastic
portion of a bilinear stress-strain relationship
cp,r
strain in the concrete at the height of the prestressing steel at a section at the
maximum moment
cr
strain in the concrete at the extreme compressive fibre at a section at the cracking
moment
le
strain in the concrete at the extreme compressive fibre at a section at the maximum
moment resulting from a stress profile entirely within the linear elastic portion of a
bilinear stress-strain relationship
max
strain in the concrete at the extreme compressive fibre at a section at the maximum
moment
angle of twist
SV
bot,mid
p1
initial assumed value of stress in post-tensioning tendons for ultimate limit state
analysis
p2
second assumed value of stress in post-tensioning tendons for ultimate limit state
analysis
p3
final assumed value of stress in post-tensioning tendons for ultimate limit state
analysis
p,final
top,dev
an
b0
bw
width of web
CR
CGS
df
diameter of fibre
DL
dead load
modulus of elasticity
etendon,mid
Ec
Ep
Es
fc
xviii
fcds
fcir
fcr
fpu
fpy
fsj
fst
fy
Fm
FR
shear modulus
h0
Ic
In
torsional constant
Kcr
lf
length of fibre
span length
LL
live load
Mcr
Mle
maximum moment resulting from a stress profile entirely within the linear elastic
portion of a bilinear stress-strain relationship
xix
Mmax
Mr
MSD,mid
Ns
number of segments
P128 days
P1f
P1j
P2f
P2j
QW
REL2
prestress losses due to relaxation of strands after transfer of forces to the concrete
RH
relative humidity
SDL
SH
t0
TSV
TW
vi
wv
xx
List of Appendices
Appendix A Live Load Sharing and Grillage Models
Appendix B Parametric Study
Appendix C Flexible Linking Slabs
Appendix D Continuous Configuration Design
Appendix E Geometry Control Calculations
Appendix F Existing Bridge Comparison
Appendix G Schedule Comparison
xxi
Chapter 1
Chapter 1
Highway Overpasses: Current Practice and an Alternative
Despite its ubiquity, this widely used structural system has several shortcomings.
First, it makes relatively inefficient use of concrete because it does not take full advantage of
load sharing between girders. This is because this system is relatively flexible in the transverse
direction. The results of this property are illustrated in Figure 1.2, in which (a) a load is applied
with a transverse eccentricity to a bridge cross-section and the resulting deformation is shown for
(b) an infinitely stiff (rigid) and (c) an infinitely flexible deck slab. In the case of a rigid deck
slab, loads are distributed to every girder transversely. In the case of an infinitely flexible deck
slab, no sharing of load occurs and a girder must resist the entirety of a load applied directly
above it. The current system of cast-in-place deck slabs on precast girders acts somewhere
between the infinitely flexible deck slab model shown in Figure 1.2c and its opposite shown in
Figure 1.2b. To compensate for the transverse flexibility of the deck slab, girders are spaced
relatively close together in conventional design, i.e., about 2 to 3 m centre-to-centre, resulting in
the use of a large amount of concrete in the superstructure cross-section compared to alternatives
as discussed in the following section.
(a)
(b)
(c)
Figure 1.2 Transverse live load sharing in (a) a slab-on-girder system with (b) infinitely
flexible deck slab and (c) infinitely stiff deck slab
A second shortcoming associated with the current system results from the fact that the concrete
deck slab is cast-in-place. The pouring of concrete components onsite for bridges is a major
contributor to the overall time they take to construct and open to traffic. For conventional
bridges, forming, placing of steel, tying of steel, curing, and stripping of the concrete deck slab
take up a considerable portion of the overall schedule.
A third, related, shortcoming is the potential for concrete quality problems due to the variable
quality of cast-in-place concrete. This variability can lead to regions of concrete in the deck slab
with relatively high permeability. Once cracks form in the deck slab, the penetrability of these
areas increases greatly. This facilitates the penetration of water and dissolved deicing chemicals
which can accelerate the deterioration of reinforcing steel within the deck slab and necessitate
2
Chapter 1
Highway Overpasses: Current Practice and an Alternative
multiple repairs within the design life of the structure. It is accepted policy that the bridge deck
slab will require replacement 30 to 40 years after it is constructed. This increases the life-cycle
cost of the bridge and can be very expensive when bridge user costs are considered.
A fourth shortcoming is that the deck slab and girders of this system shrink at different rates
because they are comprised of concretes of two different types and ages. The girders shrink less
than the deck slab and so they restrain it continuously in the longitudinal direction. This
restrained deformation leads to transverse cracking of the deck slab, often full-depth (Newhouse,
2005).
An alternative system that addresses the deficiencies listed above would be of significant benefit
to bridge owners across North America, most of which are publicly funded. Cast-in-place slab
on girder bridges comprise 41 % of all bridges in the United States (extrapolated from FHWA,
2010). Because so many highway overpass structures are constructed in North America every
year, the benefits of any improvement to durability or structural efficiency gained through the
design and construction of an alternative structural system would multiply significantly.
Chapter 1
Highway Overpasses: Current Practice and an Alternative
five associated key issues: (1) it validates Lis design for a range of span lengths used in highway
overpasses, (2) it demonstrates that it is possible to reduce the systems sensitivity to posttensioning losses, (3) it presents designs using the precast segmental double-T system for multispan bridges without the use of expansion joints, (4) it shows that the onerous technical
requirements of conventional match casting can be relaxed for short spans built using this
method, and (5) it shows that the system is competitive with conventional systems by comparing
material use, cost, scheduling, and aesthetic criteria.
36600
11300
14000
11300
TENDON
ANCHORAGES
CL WEB
CL BRIDGE
CL WEB
TENDONS
PLAN
CL
SUPPORT
CL
DEVIATION
CL
MIDSPAN
CL
DEVIATION
CL
SUPPORT
TENDONS
2950
TENDON
ANCHORAGES
ELEVATION
13800
7900
2950
2000
TENDONS
CROSS-SECTION
AT MIDSPAN
Figure 1.3 The double-T base concept | 1:500 (adapted from Li, 2010)
Chapter 2
Design Parameters
This chapter provides a brief summary of the precast segmental double-T with external,
unbonded tendons designed by Li (2010). Throughout this thesis, this 36.6-m-long, 2000-mmdeep bridge will be referred to as the base concept following the convention laid out by Li
(2010). This chapter describes the original double-T design of Li (2010) and presents the
material properties, load cases, and design criteria used in that design. These parameters are
used in all subsequent design through the rest of this thesis, except where noted.
Chapter 2
Design Parameters
36600
11300
14000
11300
TENDON
ANCHORAGES
CL WEB
CL BRIDGE
CL WEB
TENDONS
PLAN
CL
SUPPORT
CL
DEVIATION
CL
MIDSPAN
CL
DEVIATION
CL
SUPPORT
TENDONS
2950
TENDON
ANCHORAGES
ELEVATION
13800
7900
2950
2000
TENDONS
CROSS-SECTION
AT MIDSPAN
Figure 2.1 The double-T base concept | 1:500 (adapted from Li, 2010)
Construction of the bridge dictates two stages of post-tensioning. After all precast segments are
in place on site, either on an erection girder or on falsework, four tendons of 27 strands each, for
a total of 108 strands, are jacked. This is referred to as Stage I post-tensioning. After Stage I
post-tensioning, the erection girder or falsework is removed, barrier walls are installed, and the
bridge deck is paved with a 90-mm-thick asphalt wearing surface. Following this, the final two
tendons of 24 strands each are jacked in Stage II post-tensioning.
The tendons are anchored within the webs at the supports, but are external to the concrete
beyond the anchorages as shown in Figure 2.2.
C
L
SUPPORT
CL BRIDGE
TENDONS
EXTERNAL
TO WEBS
CL WEB
TENDONS
ANCHORED
WITHIN WEBS
Chapter 2
Design Parameters
anchoring the tendons within the webs of the double-T, a comparatively thin end diaphragm is
required.
Keeping the tendons external beyond their anchorages also minimises the amount of concrete
used in the webs of the section. In internally post-tensioned concrete, web width is often dictated
by construction details such as concrete cover requirements. In this double-T design, web width
is dictated by stress and not the limitations of construction details. This reduction of web width
was a key objective in the design of this concept as it helps to minimise the amount of concrete
used for the system.
The deck is transversely post-tensioned to increase its durability and to reinforce it as efficiently
as possible. Transverse post tensioning reduces transverse tensile stresses in the deck concrete,
limiting the amount of transverse cracking. The penetration of water and deicing chemicals into
the deck can potentially cause corrosion of deck reinforcing steel. By reducing the number and
size of cracks in the deck, the potential for corrosion of deck reinforcing steel can be reduced and
the service life of the bridge can potentially be extended. The life-cycle benefits of this initial
cost are great the typical bridge deck in Ontario has a much shorter service life than the 75-year
design life (CHBDC 2006, Cl. 1.4.2.3) of the structure. Proper construction of the deck of the
double-T is more easily ensured than it is in a conventional system because the deck is
constructed within the controlled environment of a precasting yard rather than onsite. A properly
designed and constructed transversely post-tensioned deck will eliminate the requirement to
replace the deck during the service life of the bridge.
Chapter 2
Design Parameters
Strength
Modulus of Elasticity
Concrete
Reinforcing Steel
Post-tensioning
Tendons
6900
= 36 250 MPa
/2300
More specifically, the following idealised stress-strain relationships were assumed for all design
and analysis in this thesis, again identical to those found in Li (2010). Exceptions to this are the
properties of fibre-reinforced concretes described in Section 4.2.5.
stress
stress
stress
fpy = 0.9fpu
fy
f'c
0.6f'c
1
Es
Ec
'c
strain
(a)
1
sy
strain
(b)
Es
py
strain
(c)
Figure 2.3 Assumed material stress-strain relationships for (a) concrete, (b) reinforcing
steel, and (c) post-tensioning steel
Chapter 2
Design Parameters
After Stage I After Stage I tendons are jacked and the falsework supporting the
superstructure is removed. In this case, the dead load of the precast segments and the initial
jacking force of the Stage I tendons (DL + P1j) are applied to the structure.
After Barriers and Wearing Surface After barriers and wearing surface have been added.
At this point, the Stage I tendons have undergone some losses. In this case, the dead load of
the precast segments, the superimposed dead load of the barriers and the wearing surface, and
the prestressing force of the Stage I tendons after 28 days of losses (DL + SDL + P128 days)
are applied to the structure.
Chapter 2
Design Parameters
After Stage II After Stage II tendons are jacked. In this case, the initial jacking force of
the Stage II tendons in addition to all loads applied during load case After Barriers and
Wearing Surface (DL + SDL + P128 days + P2j) are applied to the structure.
Service Life During the service life of the bridge, after the tendons have undergone all
losses. In this case, in addition to live load, the dead load of the precast segments, the
superimposed dead load of the barriers and the wearing surface, and the prestressing force of
all tendons after all losses (DL + SDL + P1f + P2f + LL) are applied to the structure.
2.4.1.1
All bridge concepts considered in this thesis are precast segmental and have no bonded steel
across any joints. To ensure that segment separation is avoided, no longitudinal tensile stresses
are permitted in the concrete. This criterion adheres to the limitation given in Clause 8.8.4.6(b)
of the CHBDC (2006). This criterion is only applied to the concrete in the longitudinal direction.
Transversely, the concrete is permitted to go into tension but is limited to stresses below its
cracking strength of 3.35 MPa.
2.4.1.2
In all sectional analysis conducted under serviceability limit state conditions, concrete has been
assumed to be linear elastic. To ensure that this assumption remains valid, concrete compressive
stresses have been limited to 0.6fc = 42 MPa. This assumption has been made not only during
construction and transfer, as specified in Cl. 8.8.4.6(a)(i) of the CHBDC (2006), but also during
the entire service life of the structure. In conventional concrete bridge systems, concrete stresses
usually remain well below this limit under service conditions and so this check is not considered
in their analysis. In the design of the double-T, however, an attempt has been made to use the
10
Chapter 2
Design Parameters
concrete as efficiently as possible and so higher compressive stresses are to be expected and this
additional check is thus prudent.
2.5 Conclusions
This chapter has described the double-T base concept and described the parameters to be used in
the designs and discussion that follow in subsequent chapters, beginning in Chapter 3 with a
validation of the versatility of the double-T base concept.
11
Chapter 3
12
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
13
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
of post-tensioning losses that it experiences. The post-tensioning force after losses must be kept
between lower and upper limits so that stresses in the extreme fibres of concrete are limited
under various serviceability limit state load cases. The upper limit prevents tensile stresses in the
top fibres at the deviators and high compressive stresses in the bottom fibres at midspan. The
lower limit prevents tensile stresses in the bottom fibres at midspan. These locations are
illustrated in the schematic elevation views of the bridge presented in Figure 3.1.
IF fp IS TOO HIGH,
THEN > 0
IF fp IS TOO HIGH,
THEN < -0.6f'c
IF fp IS TOO LOW,
THEN > 0
Figure 3.1 Limits on post-tensioning force and the areas that dictate them
The lower limit noted by Li for the post-tensioning stress after losses is approximately 0.64fpu. If
the stress in the tendons falls below this level for the SLS load case After Barriers (after the
Stage I tendons have been jacked and the barriers and wearing surface have been installed, as
described in Section 2.3) or for SLS load case Service Life (when the bridge is in service, as
described in Section 2.3), then tensile stresses are developed in the bottom fibres of concrete at
midspan, a situation that fails to meet the design criteria for segmental construction described in
Section 2.4.1.1.
The upper limit for the post-tensioning stress after losses is approximately 0.74fpu. If the stress in
the tendons does not fall below this limit after losses for load case After Stage II at SLS (when
the Stage II tendons are jacked, as described in Section 2.3), then tensile stresses are developed
in the top fibres of concrete at the deviators which, for segmental construction, would result in
the structure hogging up unstably. This condition occurs because the structure is relatively light.
This sensitivity to too little, and too much, post-tensioning force is illustrated in Figure 3.2
below, adapted from Li 2010, which shows how concrete stresses vary with level of prestress.
14
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
topfibres
4
atdeviators
3.5
4
desired tendonstressrange
SLSAfterStageII
3
2.5
2
Concrete
stress,c
(MPa)
2
bottom fibresat
midspan
1.5
4
6
SLSServiceLife
1
0.5
10
0.64
12
0.60
SLSAfterBarriers
0.74
0.65
0.70
0.75
0
0.80
Levelofprestress(%fpu)
Figure 3.2 Concrete stress sensitivity to level of prestress for double-T base concept
(adapted from Li, 2010)
Preliminary calculations of post-tensioning losses were conducted to determine the extent of
their variability. By varying the concrete age at which post-tensioning stresses were transferred
from 14 to 56 days, the anchor set slip from 5 to 9 mm, and the age at which losses were
measured from 70 to 40 000 days after first casting, it was found that average stress in the
tendons could vary between 0.66fpu and 0.75fpu, a range of 9 %. This is almost as great as the
range that the base concept double-T can tolerate, 10 % (0.64fpu and 0.74fpu), as calculated by Li
(2010) and shown above in Figure 3.2. Based on these calculations, then, it seems that the
double-T system can tolerate the variability in post-tensioning losses that it may experience.
However, the mechanisms by which losses occur are not perfectly understood or modeled and in
a new system under development like the double-T, it is prudent to extend the tolerance to posttensioning losses as much as is feasible.
Upon first inspection, the nature of this sensitivity suggests that it has two conflicting solutions:
to eliminate tensile stresses in the concrete, the prestressing force should be increased, but to
reduce the tendency of the section to pop up at the deviators, the moment due to prestress
should be reduced. These two solutions do not actually conflict, though, because the moment
due to prestress can be reduced without altering the prestressing force: by reducing the
15
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
eccentricity of the tendons. It is hypothesised then, that the sensitivity of the section can be
reduced by increasing the prestressing force while reducing the eccentricity of the tendons at
midspan. To validate this supposition, the following discussion presents an investigation of the
sectional behaviour of the double-T with varying amounts of post-tensioning applied at varying
eccentricities.
16
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
eccentricity when the centroid of the tendons was 280 mm from the bottom of the section and
were varied up from that depth at four to six discrete eccentricities for each section. The
eccentricity of the tendons at the anchorages was held such that the depth from the top of the
deck to the centroid of the tendons was constant. This led to varying eccentricities at the
anchorages for the constant span-to-depth ratio variants.
The combination of all these modifications led to 73 variants of the double-T base concept, i.e.,
six span lengths, each of them with two different depths except the 36.6-m model (the base
1
concept) , for a total of eleven longitudinally unique models as shown in Figure 3.3b, each one
with a varying number of discrete tendon eccentricities as shown in Figure 3.3c, for a total of 73
models. A summary of the 73 variants studied is shown in Figure 3.4.
SPAN:DEPTH = 18.3:1
VARIES
DEPTH = 2.0 m
20 m
VARIES
45 m
6 SPAN LENGTHS
(a)
2 DEPTHS EACH
(b)
VARIES
73 VARIANTS
VARYING MIDSPAN
TENDON ECCENTRICITIES
(c)
Figure 3.3 Parameters changed to create bridge variants for parametric study
For the 36.6-m model, the depth of 2000 mm and that corresponding to an 18.3:1 span-to-depth ratio were equal,
and so only one configuration was tested for this span length.
17
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
SPAN (m)
DEPTH (mm)
HEIGHT TO NEUTRAL AXIS (mm)
CROSS-SECTIONAL AREA OF CONCRETE (m 2)
MOMENT OF INERTIA OF SECTION (m 4)
CENTRE OF GRAVITY OF PRESTRESSING STEEL AT SUPPORTS
HEIGHT (mm) | ECCENTRICITY (mm)
1095
493 | 400
893
4.202
0.180
443 | 450
502 | 391
20
393 | 500
647 |1000
343 | 550
572 |1075
280 | 613
497 |1150
422 |1225
2000
347 |1300
1647
4.741
1.065
925 | 722
322 |1325
1365
1126
4.363
0.342
640 | 486
25
2000
526| 600
297 |1350
476| 650
280 |1367
426 | 700
376 | 750
326 | 800
280 | 846
925 | 722
1356
4.527
0.590
743 | 613
30
925 | 722
36.6
2000
1647
4.741
1.065
456 | 900
406 | 950
297 |1350
280 |1367
647 |1000
306 |1050
572 |1075
280 |1076
497 |1150
422 |1225
647 |1000
2000
1647
4.741
1.065
925 | 722
572 |1075
497 |1150
422 |1225
347 |1300
322 |1325
297 |1350
280 |1367
347 |1300
322 |1325
297 |1350
280 |1367
647 |1000
572 |1075
497 |1150
422 |1225
347 |1300
2185
322 |1325
1793
4.851
1.384
1110 | 683
422 |1225
356 |1000
925 | 722
40
497 |1150
322 |1325
2000
1647
4.741
1.065
572 |1075
347 |1300
1647
4.741
1.065
1640
647 |1000
2000
1647
4.741
1.065
426 |1367
297 |1350
393 |1400
280 |1367
343 |1450
280 |1513
647 |1000
572 |1075
497 |1150
422 |1225
925 | 722
45
2460
456 |1550
322 |1325
2006
5.015
1.963
406 |1600
297 |1350
356 |1650
280 |1367
1385 | 621
280 |1726
18
347 |1300
306 |1700
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
19
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
open. Load cases After Barriers and Service Life correspond to conditions under which the
bridge would not satisfy SLS criteria in positive bending at midspan.
3.3.1.1
As part of the parametric study, each span was loaded according to the Canadian Highway
Bridge Design Code (CHBDC) (CSA, 2006). Dead and superimposed dead loads were
multiplied by a load factor of 1.00 for the serviceability limit state. At the ultimate limit state,
the weight of the precast concrete girder was multiplied by a load factor of 1.10, the weight of
the cast-in-place concrete barriers by 1.20, and that of the asphalt wearing surface by a load
factor of 1.50.
3.3.1.2
Live Loads
A two-stage process was followed to determine the live load case causing the most severe
effects. First, for each span length, flexural responses to both the CL-625 truck and lane loads
were determined. Second, as the CHBDC specifies for a deck width of 13.2 m, responses under
live loads in both two and three design lanes were considered. These design lanes were loaded
under truck and lane loads and then analysed for the effects of eccentric loads as described in
Section 3.3.1.3 below.
To account for the statistical unlikelihood of all lanes being occupied by traffic at once, multilane loading reduction factors specified in the CHBDC were applied to all live loads.
To account for the increased vertical loads applied by vehicles travelling over uneven surfaces,
the dynamic load allowance specified in the CHBDC was also applied to the CL-625 truck loads,
but not to the lane loads.
3.3.1.3
Transversely asymmetric loads on a bridge deck induce torsion in the structure. Box girders and
other closed sections resist torsion loads as St. Venant torsion, that is, through a closed shear
flow. Open sections like the double-T resist torsion loads through a combination of St. Venant
torsion and differential web bending or warping. To account for the additional web bending
caused by transversely eccentric live loads, a modification of the method laid out by Menn
20
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
(1990), described in detail below, was used. Li (2010) notes that this method is conservative
when compared to a grillage model analysis. To reduce this conservatism, grillage models were
created and analysed for 20-, 36.6-, and 45-m spans. The amount that Menns method overpredicted bending moments relative to the grillage models was calculated and a reduction factor
was interpolated for span lengths in between these spans. A more detailed description of this
entire process for determining live loads follows.
As stated above, open sections like the double-T resist torsion loads, T, through a combination of
St. Venant torsion, TSV, and differential web bending or warping, TW. The relationship of these
torsions at any longitudinal point, x, is:
(3.1)
Warping induces bending on one side of the structure which is greater than that which would be
induced were equivalent symmetric loading applied to the structure. When considering warping,
it is convenient to break down asymmetric loads into a pure symmetric and a pure antisymmetric
component as shown in Figure 3.5. In a system with two webs such as the double-T, the
symmetric component causes equal positive bending of both webs; the antisymmetric component
causes additional positive bending in the web on the side of the eccentricity and reduced bending
in the other web (Menn 1990).
Q
Q/2
Q/2
(a)
Q/2
Q/2
(b)
(c)
Figure 3.5 Transformation of (a) asymmetric load into (b) pure symmetric and (c) pure
antisymmetric components
When analysing the flexural response of each web, the additional bending due to torsion must be
added to the demand on one web. The ratio of torsion resisted as St. Venant torsion, TSV, to that
resisted as warping, TW, can be assumed to be a constant, k, along the length of a member (Menn
1990), that is,
(3.2)
21
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
To determine the constant, k, for a given span, a simple compatibility condition is introduced: at
any given section along the length of the span, the longitudinal twist due to St. Venant torsion,
SV, is equal to that due to warping, W, that is,
(3.3)
An expression for SV at a length, L, along the member can be derived from the fundamental
mechanics equation:
(3.4)
or
(3.5)
Where G is the shear modulus of the material, which Menn (1990) approximates as 0.4E. For
irregular sections like bridge superstructures, the polar moment of inertia, J, should be replaced
by the torsional constant, K. For non-circular members, the torsional constant is normally
calculated as the sum of moments of inertia of the section about two perpendicular axes. For a
double-T girder, Menn (1990) recommends that K be approximated as:
(3.6)
Where t0 is the thickness of the slab, b is the deck width, bw is the width of the webs, and h0 is the
height to the centre of the deck slab. These dimensions are illustrated in Figure 3.6. The
variable thickness of the deck slab of the double-T is ignored.
b
t0
h h0
bw
b0
22
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
(3.7)
The twist due to warping, W, can be calculated from the section geometry when the webs deflect
in opposite directions due to the asymmetric component of the eccentric load as illustrated in
Figure 3.7.
QW
QW
W
wv
wv
b0
(3.10)
And an is the distance from the middle of the top slab to the neutral axis of the full section and is
given by:
(3.11)
Where all dimensions are as shown in Figure 3.6 and Figure 3.7 above.
23
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Substituting Equations 3.8, 3.9, 3.10, and 3.11, into Equation 3.7 and solving for k, an expression
is obtained that is valid for a given section and span length along its entire length:
(3.12)
From k, an expression for the amplification factor, Fm, was derived. This amplification factor
accounts not only for the flexural effects of a load applied along the centerline of a structure but
also for the additional flexural effects on one web caused by transversely eccentric loading. This
factor is a function of the transverse eccentricity of the applied load, e. The symmetric
component of a load, Q, is resisted in each web equally as 0.5Q; the asymmetric component is
resisted as a warping torsion component, Qw, which is multiplied by the ratio of
to obtain the
components resisted in each single web. The total imposed load on each web is therefore:
0.5
(3.13)
Using the greater of these two expressions, factoring out Q, and doubling the result so that it
considers effects on the entire structure instead of only one web, an expression for Fm was
obtained:
1
(3.14)
This method of analysis overestimates the amount of torsion resisted through warping because it
does not account for the contribution of diaphragms between the webs. Diaphragms act as
transverse shear walls, restraining the webs from bending relative to one another and causing
more torsion to be resisted as St. Venant torsion in their immediate region. This expression was
derived considering a load of a transversely eccentric point load at midspan. For a single simply
supported beam, a point load at midspan causes more deflection than a uniformly distributed
load of equal total magnitude. Similarly, when applied to one web of a two-web system, a point
load causes more twist than a uniformly distributed load of equivalent total force at the same
transverse eccentricity. If a uniformly distributed load were used to derive Equation 3.9, then its
form would be altered and so would the derivation of the parameter k. When the parameter k is
derived using a point load and used in analyses involving distributed loads that would encourage
24
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
more load sharing between webs, it leads to conservatively high additional loads on individual
webs. The reduction factors calculated based on the grillage models analysed for 20-, 36.6-, and
45-m spans eliminated this conservatism.
Considered simply as a two-dimensional system, the bending response of the overall section is
greater for the higher magnitude load of three loaded lanes rather than two. When the transverse
eccentricity of the loads is considered, however, the warping induced by two eccentric loaded
lanes is greater than that induced by three. This creates uncertainty when determining by
inspection which load case causes the greatest flexure in a single web. Because of this
uncertainty, the effects of both cases: two lanes loaded eccentrically and three lanes loaded
eccentrically, were calculated. Once the most severe case was determined, the live load demand
on the web on the side of the eccentricity was applied to both webs and the full-width structure
was analysed under this condition. A summary of the derived live loads used in analysis of the
eleven concrete variants is shown in Figure 3.8.
25
SPAN
DEPTH
(m)
(mm)
MENN AMPLIFICATION
FACTOR, Fm
AMPLIFIED DEMAND
LOADING
1095
20
2000
1365
25
26
1640
30
2000
36.6
2000
2000
40
2185
2000
45
1.7286
1.1911
1.5783
1.1517
1.7061
1.1852
1.6070
1.1595
1.6805
1.1785
1.6267
1.1644
1.6433
1.1687
1.6230
1.1634
1.6494
1.1703
1.5926
1.1554
1.6569
1.1723
5469 | 5655
0.8526
4663 | 4821
4994 | 5163
0.8526
4258 | 4402
8277 | 6952
0.8555
7081 | 5947
7796 | 6548
0.8555
6670 | 5602
11301|10413
0.8548
9660 | 8901
10939|10079
0.8548
9351 | 8616
14711|12472
0.8483
12479|10580
16392|14141
0.8425
13810|11914
16658|14371
0.8425
14035|12108
|16252
17513|
0.8315
|13510
14558|
|16908
18220|
0.8315
|14056
15146|
4901 | 4885
5025 | 5195
4502 | 4488
4474 | 4460
4859 | 5023
4353 | 4339
7457 | 6293
7667 | 6439
6907 | 5829
7024 | 5928
7501 | 6300
6757 | 5703
10295| 9280
10561| 9736
9626 | 8677
9966 | 8983
10440| 9620
9511 | 8573
13873|11789
13950|11827
13155|11179
15749|13541
15667|13515
15053|12942
16005|13762
15760|13596
15142|13019
16599|15721
16940|15456
16842|15951
17188|15683
Chapter 3
2460
MOST
SEVERE
CASE
2000
2 x CL-625 TRUCK
2 x CL-W LANE
3 x CL-625 TRUCK
3 x CL-W LANE
3164 | 3271
2835 | 2826
4219 | 4362
3780 | 3768
3164 | 3271
2835 | 2826
4219 | 4362
3780 | 3768
4852 | 4075
4371 | 3689
6769 | 5433
5828 | 4918
4852 | 4075
4371 | 3689
6769 | 5433
5828 | 4918
6725 | 6196
6126 | 5522
8966 | 8262
8168 | 7363
6725 | 6196
6126 | 5522
8966 | 8262
8168 | 7363
8952 | 7590
8442 | 7174
11936|10120
11256| 9566
10100| 8713
9704 | 8343
13466|11617
12938|11125
10100| 8713
9704 | 8343
13466|11617
12938|11125
10775|10205
10996|10033
14366|13606
14662|13378
10775|10205
10996|10033
14366|13606
14662|13378
GRILLAGE REDUCTION
FACTOR
LIVE LOAD
(kN-m)
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
The live load sharing model described above was chosen because it simplified the analysis of the
44 live load cases presented in Figure 3.8 above. However, Menns equations are conservative
for all cases studied and overpredict moment demand. This was demonstrated by Li (2010) and
can be seen when comparing the loads obtained from this method to a more detailed analysis of a
36.6-m-long span with a depth of 2000 mm and a midspan tendon eccentricity of 1367 mm.
Using the modified Menn analysis, the maximum midspan live load demand was 14 711 kNm or
7355 kNm for a single web. For the exact same bridge variant, a grillage analysis results in a
maximum live load of only 6240 kNm for a single web. This conservative over-prediction varies
with span length and so to reduce the live load moments calculated above, the results of three
representative grillage models (for the 20-, 36.6-, and 45-m spans) were used. The maximum
bending moments due to live load were calculated based on the results of these analyses and, as
expected, found to be less than those predicted by the modified Menn method. The ratio
between these grillage live loads and the Menn live loads was calculated for 20-, 36.6-, and 45-m
spans and interpolated for 25-, 30-, and 40-m spans to develop live load reduction factors to be
used in all subsequent analysis. A summary of these reduction factors and their derivation is
shown in Table 3.1.
Table 3.1 Comparison of live loads derived using two methods
Unfactored live load based on
Span
(m)
Menns modified
model
(kNm)
Grillage
model
(kNm)
20
25
30
36.6
40
45
5655
8277
11 301
14 711
16 392
17 513
4821
7080
9659
12 479
13 810
14 558
Reduction
factor
(grillage/Menn)
Calculated or
interpolated
0.8526
0.8555
0.8548
0.8483
0.8425
0.8315
Calculated
Interpolated
Interpolated
Calculated
Interpolated
Calculated
27
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
for each analysis, regardless of member deflection under serviceability limit states. This is
reasonable because member deflections, which dictate tendon stress, are minimal under SLS
conditions. For each load case, however, the constant stress in the tendons was assumed at a
different level to reflect the expected amount of post-tensioning losses for that particular case,
e.g., stress in the tendons after barriers were installed was assumed to be 0.74fpu, whereas it was
assumed to be 0.67fpu during the service life of the bridge.
The three criteria presented in Section 3.1.2 set upper and lower bounds on the amount of posttensioning steel that can be used for each bridge variant.
3.3.2.1
The Stage I longitudinal post-tensioning force and as an extension, the number of Stage I
tendons, was limited by the lower bound and two upper bounds noted above. The lower bound
was to ensure that the structure resisted loading under SLS load case After Barriers and that the
stresses in the bottom fibres of the concrete at midspan remained compressive. There were two
upper bounds on the Stage I post-tensioning, both applied based on load case After Stage I at
SLS. One bound ensured that the stress in the top fibres at the deviators remained compressive.
The other, which governed for longer spans only, ensured that the concrete in the section at
midspan remained entirely linear elastic, that is, compressive stresses were limited to 0.6fc, or
42 MPa. When converting the limits on the prestressing force to a number of strands, the stress
in the tendons for these load cases was assumed to be 0.74fpu, as corresponds to losses calculated
by Li (2010) for these stages of construction.
3.3.2.2
The Stage II longitudinal post-tensioning force was also limited by a lower bound and two upper
bounds. The lower bound was to ensure that the structure resisted loading under SLS load case
Service Life and that the stresses in the bottom fibres of the concrete at midspan remained
compressive. As with the Stage I tendons, there were also two upper bounds on the Stage II
post-tensioning, both applied based on SLS load case After Stage II: one ensured that the stress
in the top fibres at the deviators remained compressive, the other, which governed for longer
spans only, ensured that the concrete in the section at midspan remained entirely linearly elastic,
that is, compressive stresses were limited to 0.6fc, or 42 MPa. When converting the limits on
28
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
the prestressing force to a number of strands, the stress in the tendons for the lower bound was
assumed to be 0.67fpu and for the upper bounds was assumed to be 0.74fpu. These stresses are
conservative and appropriate for SLS load cases Service Life and After Stage II, respectively.
The application of these bounds yields two ranges of possible amounts of post-tensioning for
each combination of span length and tendon eccentricity. These ranges can be represented
graphically as shown in the example in Figure 3.9. This sample figure helps to explain Figure
3.10 and Figure 3.11, presentations of the actual results of the serviceability limit state analyses.
Each of these figures represents possible numbers of strands for a given span length and depth
over the studied range of eccentricities. For example, reading from Figure 3.10c, for a bridge
variant that is 2000 mm deep and 30 m long, with a midspan tendon eccentricity of 1150 mm, the
number of total strands can vary from 120 to 156.
These ranges are only based on serviceability limit state criteria. To validate options within
these ranges, combinations of span length, eccentricity, and number of strands were checked at
the ultimate limit state as described in the following section.
29
300
Theblueshadedregionrepresentsvalid
numbersoftotal strands(StageIplusStageII)
thatwouldsatisfyallapplicableSLScriteria.
275
250
225
bot, mid < 0
200
minimumforSLS1Dsuchthat
thereisnotension
inbottomfibresatmidspan
maximumforSLS1Csuchthat
concreteremainslinearelastic
inbottomfibresatmidspan
bot,mid >0.6f'c
maximumforSLS1Asuchthat
concreteremainslinearelastic
inbottomfibresatmidspan
bot,mid >0.6f'c
ValidAmountsof
PosttensioningforStageII
175
maximumforSLS1Asuchthat
thereisnotension
intopfibresatdeviators
125
ValidAmountsof
PosttensioningforStageI
100
bot, mid < 0
minimumforSLS1Bsuchthat
thereisnotension
inbottomfibresatmidspan
75
Theredshadedregionrepresentsvalid
numbersofStageIstrandsthatwouldsatisfy
allapplicableSLScriteria.
50
Scope ofStudy
25
0
950
1000
1050
1100
1150
1200
1250
1300
1350
1400
Figure 3.9 Explanatory Plot amounts of post-tensioning satisfying serviceability limit state criteria for a 36.6-m span
Chapter 3
Tendoneccentricityatmidspan(mm)
30
Number
of
150
15mm
strands
350
350
350
325
325
325
300
300
300
275
275
275
250
250
250
225
225
225
200
200
200
Number
of
175
15mm
strands 150
maximumforSLS1A|bot,mid >42MPa
150
150
125
125
StageII
100
75
StageII
50
StageI
25
100
75
50
StageI
950
1000
1050
1100
1150
1200
1250
1300
1350
1000
1050
1100
1150
(a)
25
1200
1250
1300
1350
1400
950
1000
1050
1100
1150
(b)
350
325
325
300
300
275
275
maximumforSLS1A|bot,mid >42MPa
StageII
200
StageII
StageII
275
maximumforSLS1A|bot,mid >42MPa
250
225
maximumforSLS1A|bot,mid >42MPa
200
175
StageI
StageI
200
175
StageI
150
150
125
100
100
125
100
75
75
50
50
50
25
25
25
75
950
1000
1050
1100
1150
1200
1250
1300
1350
1400
1400
300
225
1350
maximumforSLS1C|bot,mid >42MPa
250
250
1300
0
950
1000
Tendoneccentricityatmidspan(mm)
(d)
1050
1100
1150
1200
1250
Tendoneccentricityatmidspan(mm)
(e)
1300
1350
1400
950
1000
1050
1100
1150
1200
1250
1300
1350
Tendoneccentricityatmidspan(mm)
(f)
Figure 3.10 Amounts of post-tensioning satisfying serviceability limit state criteria for 2000-mm-deep spans of (a) 20 m,
Chapter 3
1400
31
350
maximumforSLS1C|bot,mid >42MPa
1250
(c)
325
maximumforSLS1C|bot,mid >42MPa
1200
Tendoneccentricityatmidspan(mm)
350
Number
of
175
15mm
strands 150
75
Tendoneccentricityatmidspan(mm)
Tendoneccentricityatmidspan(mm)
225
StageI
100
950
1400
50
25
0
StageII
175
maximumforSLS1C|bot,mid >42MPa
125
maximumforSLS1C|bot,mid >42MPa
175
maximumforSLS1A|bot,mid >42MPa
maximumforSLS1A|bot,mid >42MPa
350
350
350
325
325
325
300
300
300
275
275
275
250
250
225
225
maximumforSLS1C|bot,mid >42MPa
200
Number
of
175
15mm
strands 150
200
100
175
maximumforSLS1A|bot,mid >42MPa
150
125
125
250
StageII
75
200
maximumforSLS1A|bot,mid >42MPa
175
25
0
350
400
450
500
550
600
650
700
750
800
850
900
850
(b)
350
325
325
300
300
300
275
275
275
250
250
maximumforSLS1A|bot,mid >42MPa
StageII
200
maximumforSLS1C|bot,mid >42MPa
200
StageII
175
StageI
150
StageI
125
100
200
175
150
50
50
25
25
1050
1100
1150
1200
1250
1300
1350
Tendoneccentricityatmidspan(mm)
(d)
1400
StageI
1350
1400
1450
1500
Tendoneccentricityatmidspan(mm)
(e)
1550
1600
75
25
0
1300
maximumforSLS1A|bot,mid >42MPa
125
50
StageII
100
75
1150
maximumforSLS1C|bot,mid >42MPa
225
maximumforSLS1A|bot,mid >42MPa
100
75
1100
250
225
1050
0
1500
1550
1600
1650
1700
1750
1800
Tendoneccentricityatmidspan(mm)
(f)
Figure 3.11 Amounts of post-tensioning satisfying serviceability limit state criteria for (respectively) section depths and spans
(e) 2185 mm, 40 m; (f) 2460 mm, 45 m
Chapter 3
of (a) 1095 mm, 20 m; (b) 1365 mm, 25 m; (c) 1640 mm, 30 m; (d) 2000 mm, 36.6 m (duplicate of Figure 3.10d);
32
350
maximumforSLS1C|bot,mid >42MPa
1000
(c)
325
1000
950
Tendoneccentricityatmidspan(mm)
350
950
900
Tendoneccentricityatmidspan(mm)
(a)
Number
of
175
15mm
strands 150
50
0
600
Tendoneccentricityatmidspan(mm)
225
25
550
650
StageI
75
maximumforSLS1A|bot,mid >42MPa
minimumforSLS1D|bot, mid < 0
100
50
25
125
75
50
maximumforSLS1C|bot,mid >42MPa
150
100
StageI
225
maximumforSLS1C|bot,mid >42MPa
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
0.0020
0.0027
strain
Figure 3.12 Bilinear concrete stress-strain curve for 70-MPa concrete (adapted from
CEB-FIB, 2010)
1. Remove the tendon from the concrete structure shown in Figure 3.13a and apply
equivalent anchorage and deviator forces to the structure as shown in Figure 3.13b.
33
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
(a)
(b)
Figure 3.13 Equivalent loading after tendon removal
2. The forces shown in Figure 3.13b vary with the force in the tendons. Assume initially
that the stress in the tendons, p1, is equal to the yield stress of the tendons, 0.90fpu.
For the given axial compressive force due to prestress and using the bilinear stress-strain
curve for concrete shown in Figure 3.12 determine the three values of moment for the
concrete section described by the strain and stress profiles in Figure 3.14: the cracking
moment, Mcr; the moment at which strain in the extreme compression fibre is equal to
0.0020, Mle; and the ultimate moment, Mr.
M cr
M le
le = 0.0020
cp,cr
Mr
= f'c = 70 MPa
cp,le
r = 0.0027
= f'c = 70 MPa
cp,r
fcr
cr
(a)
(b)
(c)
Figure 3.14 Strain and stress profiles for (a) cracking moment, (b) linear elastic
moment, and (c) ultimate moment
Also determine corresponding values of strain in the concrete at the level of prestress, cp.
3. The system is loaded with dead, superimposed dead, and live loads as shown in Figure
3.15a, resulting in a bending moment diagram similar in shape to that shown in Figure
3.15b.
34
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
(a)
(b)
Mmax
Figure 3.15 (a) Dead, superimposed dead, live, and prestress loads and (b) resulting
schematic bending moment diagram
Scale the resulting bending moment diagram linearly such that the maximum imposed
moment is equal to the ultimate moment that the section can resist, i.e., Mmax = Mr. as
shown in Figure 3.16.
Mr
(a)
Mcr
(b)
Mle
Mr
Mle
Mcr
cp,le
cp,r
Figure 3.17 (a) Significant points on bending moment diagram and (b) corresponding
concrete strains at level of prestress
35
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
The total area under this curve is the elongation of the tendon due to deformation or
elongation of the duct, Lpd, as shown in Figure 3.18.
A = L pd
tendon
yield
elongation
0.67fpu
0.90fpu
stress in tendons
tendon
stress
p
yield stress of
tendons
tendon
elongation
Lp
p1
tendon
stress
p
p2 p1
tendon
stress
p
(a)
(b)
Figure 3.20 Elongation of tendon due to deformation plotted with elongation due to force
when tendons are assumed to yield and actually (a) do yield or (b) do not yield
36
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
If the point falls above the yield elongation of the tendons similar to the result shown in
Figure 3.20a, then the tendons yield to support this state of equilibrium and the moment
resistance of the section is equal to what was calculated for Mr.
If the point falls below the yield elongation of the tendons similar to the result shown in
Figure 3.20b, then the tendons do not yield to support this state of equilibrium and
another iteration must be made considering a lower stress in the tendons to find the
moment resistance of the section. This new stress should correspond to a force in the
tendon that would produce the elongation, Lpd, calculated above and shown as p2 in
Figure 3.20. Repeat steps 3 through 6 using this new tendon stress, p2.
7. The next plotted point will lie somewhere similar to the second point shown in Figure
3.21a.
tendon
elongation
Lp
tendon
elongation
Lp
p2 p1
tendon
stress
p
p3
(a)
tendon
stress
p
(b)
Figure 3.21 (a) Result of second iteration and (b) interpolation of actual stress in tendon
Draw a line connecting the two plotted points as shown in Figure 3.21b. This line will
intersect with the Lpf line. The stress in the tendon, p3, that equilibrates forces on the
structure will be the stress that corresponds to this intersection point.
8. Calculate Mr using the bilinear stress-strain curve from the CEB-FIB Draft Model Code
(2010) given the axial compressive force due to p3. This Mr is the moment resistance of
the section.
If capacity is found to be greater than demand using this procedure, then the section resists
ultimate loading. This procedure was used to determine the minimum required number of
37
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
tendons to resist ultimate loading for each combination of span length, section depth, and
midspan tendon eccentricity.
38
350
350
325
325
300
300
300
275
275
250
250
250
225
225
225
200
200
200
350
325
minimumforULS1D|Mr > Mf
275
minimumforULS1D|Mr > Mf
Number
of
175
15mm
strands 150
maximumforSLS1C|bot,mid >42MPa
maximumforSLS1A|bot,mid >42MPa
125
175
maximumforSLS1C|bot,mid >42MPa
150
maximumforSLS1A|bot,mid >42MPa
125
75
StageII
50
StageI
25
75
50
100
StageI
25
1000
1050
1100
1150
1200
1250
1300
1350
1400
1000
1050
1100
75
50
1150
1200
1250
1300
1350
1400
950
1000
1050
1100
1150
350
minimumforULS1D|Mr > Mf
300
275
maximumforSLS1A|bot,mid >42MPa
StageII
StageI
225
100
maximumforSLS1A|bot,mid >42MPa
250
StageI
200
maximumforSLS1A|bot,mid >42MPa
175
StageI
150
125
125
100
100
75
50
50
50
25
25
25
75
StageII
275
225
200
150
300
175
125
1400
maximumforSLS1C|bot,mid >42MPa
350
250
200
1350
325
maximumforSLS1C|bot,mid >42MPa
250
1300
0
950
1000
1050
1100
1150
1200
1250
Tendoneccentricityatmidspan(mm)
(d)
1300
1350
1400
minimumforULS1D|Mr > Mf
0
950
1000
1050
1100
1150
1200
1250
Tendoneccentricityatmidspan(mm)
(e)
1300
1350
1400
950
1000
1050
1100
1150
1200
1250
1300
1350
Tendoneccentricityatmidspan(mm)
(f)
Figure 3.22 Amounts of post-tensioning satisfying both serviceability and ultimate limit state criteria for 2000-mm-deep
Chapter 3
1400
39
300
1250
(c)
minimumforULS1D|Mr > Mf
325
1200
Tendoneccentricityatmidspan(mm)
(b)
325
Number
of 175
15mm
strands 150
StageI
100
Tendoneccentricityatmidspan(mm)
(a)
225
0
950
Tendoneccentricityatmidspan(mm)
350
150
25
950
maximumforSLS1C|bot,mid >42MPa
StageII
175
125
StageII
100
350
350
325
325
minimumforULS1D|Mr > Mf
300
275
250
250
225
225
maximumforSLS1C|bot,mid >42MPa
200
150
125
100
minimumforULS1D|Mr > Mf
250
StageII
75
maximumforSLS1C|bot,mid >42MPa
225
200
maximumforSLS1A|bot,mid >42MPa
175
25
0
350
400
450
500
550
600
650
550
600
650
700
750
800
850
900
0
850
300
300
275
275
maximumforSLS1C|bot,mid >42MPa
250
200
StageI
300
200
maximumforSLS1C|bot,mid >42MPa
225
200
175
175
150
150
StageII
StageI
50
50
25
25
1150
1200
1250
1300
1350
1400
0
1300
1350
Tendoneccentricityatmidspan(mm)
(d)
1400
1450
1500
Tendoneccentricityatmidspan(mm)
(e)
1550
75
25
1100
maximumforSLS1A|bot,mid >42MPa
100
50
1050
StageII
125
75
maximumforSLS1C|bot,mid >42MPa
250
225
100
275
1150
325
minimumforULS1D|Mr > Mf
125
100
1100
350
125
1050
(c)
250
maximumforSLS1A|bot,mid >42MPa
StageII
1000
1600
0
1500
minimumforULS1D|Mr > Mf
1550
1600
1650
1700
1750
Tendoneccentricityatmidspan(mm)
(f)
Figure 3.23 Amounts of post-tensioning satisfying both serviceability and ultimate limit state criteria for (respectively)
Figure 3.22d); (e) 2185 mm, 40 m; (f) 2460 mm, 45 m
Chapter 3
section depths and spans of (a) 1095 mm, 20 m; (b) 1365 mm, 25 m; (c) 1640 mm, 30 m; (d) 2000 mm, 36.6 m (duplicate of
1800
40
325
1000
950
Tendoneccentricityatmidspan(mm)
350
minimumforULS1D|Mr > Mf
950
900
(b)
325
Number
of 175
15mm
strands 150
50
Tendoneccentricityatmidspan(mm)
(a)
225
25
Tendoneccentricityatmidspan(mm)
350
StageI
75
50
maximumforSLS1A|bot,mid >42MPa
minimumforSLS1D|bot, mid < 0
100
125
StageI
75
50
maximumforSLS1C|bot,mid >42MPa
150
100
StageI
300
275
175
125
minimumforULS1D|Mr > Mf
200
325
300
275
Number
of
175
15mm
strands 150
350
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Section
depth
(mm)
1095
20
2000
1365
25
2000
1640
30
2000
36.6
Minimum
Minimum
Maximum
150
134
64
50
184
146
104
52
156
136
96
74
190
140
152
76
1367
150
136
136
104
176
142
206
110
1367
192
144
246
164
224
170
170
154
270
194
220
184
268
206
180
166
310
234
248
226
400
450
1000
1350
600
700
1000
1367
900
1000
1000
2000
1000
2000
1000
40
2185
2000
45
2460
Maximum
1367
1367
1513
1000
1367
1550
1726
41
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Conversely, this summary can be presented by selecting a specific number of strands in the
middle of the ranges listed in Table 3.2 for each variant and showing the amount that the tendons
can vary from the nominal stress after losses as has been done in Table 3.3.
Table 3.3 Permissible range of variation from nominal post-tensioning force
Span
length
(m)
Section
depth
(mm)
Selected
number of
strands
400
450
1000
1350
168
140
84
52
0.598
0.641
0.510
0.644
0.810
0.772
0.916
0.740
600
700
1000
1367
174
138
124
76
0.601
0.660
0.519
0.652
0.808
0.751
0.907
0.740
900
1000
1000
1367
164
140
172
108
0.613
0.651
0.530
0.645
0.794
0.751
0.886
0.754
2000
1000
1367
220
154
0.585
0.626
0.827
0.788
2000
1000
1367
1367
1513
248
182
196
170
0.605
0.626
0.581
0.607
0.806
0.789
0.831
0.801
1000
1367
1550
1726
290
220
214
196
0.619
0.627
0.564
0.567
0.791
0.787
0.858
0.853
1095
20
2000
1365
25
2000
1640
30
2000
36.6
Midspan
tendon
eccentricity
(mm)
40
2185
2000
45
2460
In all cases, Stage I sensitivity to prestress losses can be reduced by lowering midspan tendon
eccentricities, as predicted. This is indicated by the widening of most of the Stage I envelopes
toward lower eccentricities on the plots above. The bottom limits of these envelopes (the
serviceability limit state criterion of no tensile stresses in the bottom concrete fibres at midspan)
are relatively flat, as are the bottom limits on the Stage II envelopes. This indicates that less
sensitivity to prestress losses can be achieved with the addition of relatively few strands. In
other words, a more robust system can be obtained for a small marginal cost. This is true for all
bridges except for the more slender 2000-mm-deep 40- and 45-m spans. These two variants are
relatively insensitive to the post-tensioning force (and consequently to the post-tensioning losses)
42
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
for all midspan tendon eccentricities between 1000 and 1367 mm. Therefore, a midspan tendon
eccentricity toward the lower end of those studied is good practice for all variants of the doubleT, except for the 2000-mm-deep 40- and 45-m spans, for which it is unnecessary.
Beyond the validation of its two main hypotheses, this study drew out a number of other
interesting points regarding the double-T concept.
For shorter spans of the 2000-mm-deep sections studied, the range of tendon options is more
limited. The upper serviceability limit on number of strands changes. For shorter spans of 20
and 25 m, the number of strands is limited by tensile stresses in the top fibres at the deviators.
For the 45 m span, it is limited by compressive stresses in the bottom fibres at midspan. For
spans in between, and for all of the variants with 18.3:1 span-to-depth ratios, a combination of
the two criteria limits the number of strands that can be used, with tensile stresses in the top
fibres at the deviators limiting for less eccentric prestress and compressive stresses in the bottom
fibres at midspan limiting for more eccentric prestress. This effect can be summarised as
follows. For spans more slender than 20:1 (40 m long, 2000 mm deep), too much prestress
causes the structure to hog upward unstably and tensile stresses to occur at the top fibres of
concrete over the deviators. For spans less slender than 15:1 (30 m long, 2000 mm deep), this
hogging will be expressed as excessive compressive stresses in the bottom fibres instead of
tensile stresses in the top fibres.
Results for the 2000-mm-deep sections from 20 to 36.6 m in length illustrate an interesting
possibility. For these variants, the regions of valid numbers of Stage I and Stage II strands
overlap at lower midspan tendon eccentricities. A variant with a number of strands that fell
within this overlapping zone would satisfy all criteria for both Stage I and Stage II strands and
would therefore only require one stage of tendon stressing. Construction staging for such shortspan structures would be simplified.
For spans of 20 to 30 m for the constant span-to-depth ratio sections (all of which are shallower
than 2000 mm), the range of valid eccentricities was somewhat limited, but opened up for
smaller midspan tendon eccentricities. This suggests that these sections could benefit from
tendons at an eccentricity even less than the range studied.
43
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
The results presented in Figure 3.22 and Figure 3.23 can be presented slightly differently to
demonstrate other characteristics of the double-T. If midspan tendon eccentricity is held
constant for a single plot, rather than span length, then other trends emerge. This has been done
in Figure 3.24 for the six members of constant 2000-mm depth. These plots show that the two
upper bounds for Stage II strands intersect in the 25- to 40-m span range, creating an area with
the largest viable range of Stage II post-tensioning options. This maximum range corresponds
with variants that are least sensitive to variations in losses. For the Stage I strand envelopes, this
range of spans of low sensitivity occurs around 28 m for 1000-mm midspan tendon eccentricities
and increases from there for increasing eccentricities, eventually moving up to 41 m for 1367mm eccentricities. Figures plotted in this manner cannot be generated for the members with
varying section depth because the range of tendon eccentricity varies with span length for these
five variants.
The results of this study cannot be directly applied in the design of segmental double-T systems
without significant consideration of what is constructible. The following sections address this
requirement.
44
350
350
350
325
325
325
300
300
275
250
275
maximumforSLS1C|bot,mid >42MPa
250
225
200
200
200
175
175
150
125
StageII
maximumforSLS1A|top, dev < 0
100
25
25
minimumforULS1D|Mr > Mf
75
50
20
25
30
35
40
45
50
minimumforULS1D|Mr > Mf
0
15
20
25
30
35
40
45
15
50
20
25
30
(b)
350
325
350
325
325
300
300
45
275
250
250
225
225
200
StageII
225
maximumforSLS1C|bot,mid >42MPa
StageII
maximumforSLS1C|bot,mid >42MPa
175
200
StageII
175
150
100
250
StageI
StageI
150
125
125
100
100
StageI
75
75
75
50
maximumforSLS1A|bot,mid >42MPa
50
maximumforSLS1A|bot,mid >42MPa
50
25
25
25
minimumforULS1D|Mr > Mf
minimumforULS1D|Mr > Mf
0
15
20
25
30
35
40
Spanlength(m)
(d)
45
50
minimumforULS1D|Mr > Mf
15
20
25
30
35
Spanlength(m)
(e)
40
45
50
15
20
25
30
35
40
45
SpanLength(m)
(f)
Figure 3.24 Amounts of post-tensioning satisfying both serviceability and ultimate limit state criteria for varying span
50
Chapter 3
lengths for 2000-mm-deep sections with a midspan tendon eccentricity of (a) 1000 mm, (b) 1075 mm, (c) 1150 mm, (d) 1225
mm, (e) 1300 mm, and (f) 1367 mm
50
275
200
125
45
(c)
350
275
40
35
Spanlength(m)
Spanlength(m)
(a)
Number
of
175
15mm
strands 150
maximumforSLS1A|bot,mid >42MPa
minimumforSLS1B|bot, mid < 0
25
minimumforULS1D|Mr > Mf
Spanlength(m)
300
StageI
50
15
StageII
100
StageI
75
StageI
50
125
StageII
100
maximumforSLS1A|bot,mid >42MPa
75
225
150
125
250
225
Number
of
175
15mm
strands 150
300
275
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Section
depth
(mm)
Span-to-depth
ratio
Midspan tendon
eccentricity
(mm)
Minimum number
of strands
20
25
30
36.6
40
45
1095
1365
1640
2000
2000
2000
18.3:1
18.3:1
18.3:1
18.3:1
20.0:1
22.5:1
400
600
900
1225
1300
1350
150
156
150
160
176
206
The configurations listed above not only satisfy all criteria for Stage II post-tensioning, but also
allow for a number of strands for Stage I post-tensioning that satisfies all related serviceability
criteria.
46
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
MAXIMUM
162 TOTAL STRANDS
MAXIMUM
162 TOTAL STRANDS
(a)
(b)
MAXIMUM
162 TOTAL STRANDS
(c)
MAXIMUM
162 TOTAL STRANDS
(d)
MAXIMUM
222 TOTAL STRANDS
(e)
Figure 3.25 Anchorage spiral footprints for required number of strands for spans of: (a)
20 m, (b) 25 m, (c) 30 m, (d) 36.6 m, and (e) 40 m and 45 m | 1:100
An effort was made to maintain the width of the webs of the end segments for all sections at the
corresponding width on the base concept, 1055 mm. The webs that required widening were
those of the 1095-mm-deep section, which were widened to 1278 mm and those of the
2000-mm-deep sections for 40- and 45-m spans, which were widened to 1135 mm.
Specific, feasible designs for the six discrete span lengths studied are developed further and
presented in the following section.
47
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Span
(m)
Section
depth
(mm)
Midspan
tendon
eccentricity
(mm)
20
25
30
36.6
40
45
1095
1365
1640
2000
2000
2000
400
600
900
1225
1300
1350
Tendon arrangement
Number of
strands
(Stage I | Stage II)
Stage I
100 | 150
104 | 156
100 | 150
108 | 160
120 | 176
148 | 206
2 x 2 x 25/27
2 x 2 x 26/27
2 x 2 x 25/27
2 x 2 x 27
2 x 2 x 30/37
2 x 2 x 37
Stage II
+ 2 x 25/27 tendons
+ 2 x 26/27 tendons
+ 2 x 25/27 tendons
+ 2 x 26/27 tendons
+ 2 x 28/37 tendons
+ 2 x 29/37 tendons
The location of the transition from wide (665 mm) to thin (285 mm) webs was governed by the
geometry of where the tendon ducts left the concrete of the webs. This transition was placed at
such a distance that the ducts would not pass through the longitudinal faces of the webs as
illustrated in Figure 3.26a and Figure 3.26b below, but would rather pass entirely through the
transverse face of the transition as illustrated in Figure 3.26c. In each of the illustrations, the
geometry of the ducts does not change; only the location of the transition changes.
(a)
(b)
48
(c)
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
Table 3.6 below summarises the location of the transition for each design.
Table 3.6 Location of web width transition
Span
(m)
20
25
30
36.6
40
45
3300
2740
3280
4000
4000
5300
3.3.9.2
Number of Segments
Each design was divided into segments that made for even lengths of all non-end segments. The
end segment lengths were chosen such that segments were as long as possible but did not exceed
60 t. Non-end segment lengths were selected such that they did not exceed 2800 mm and
weights did not exceed 60 t. Segment lengths were chosen such that deviators were placed at the
longitudinal centre of a segment and all thin-webbed interior segments were the same length.
Table 3.7 below summarises the segment lengths chosen.
Table 3.7 Segment divisions
Span
(m)
20
25
30
36.6
40
45
3.3.9.3
Number of
segments
End
segment length
(mm)
Wide-webbed
segment length
(mm)
Deviator
segment length
(mm)
Standard interior
segment length
(mm)
10
11
14
14
17
20
2600
2500
2500
2500
2540
2500
2200
2640
2020
2800
2255
1895
2000
2360
2280
2800
1800
2210
2100
2400
2300
2800
2700
2500
The force due to the inward lateral deviation of the tendons from their anchorages in the webs to
the deviators pulls the webs laterally inward at the ends of the bridge. This inward force must be
resisted by a diaphragm. If the centerline of the diaphragm is not aligned with the intersection of
the lines of action of the tensile force in the tendons and the compressive force in webs, then it
must be designed to resist not only compression, but bending as well. An example of a
49
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
diaphragm properly positioned is illustrated in Figure 3.27 below, which shows the lines of
action of all three forces intersecting at the same point.
CL WEB
CL
DIAPHRAGM
CL
SUPPORT
3.3.10
The concepts described in general in previous sections become concrete when conceptual
drawings for the six variants are presented as shown in Figure 3.28 through Figure 3.33 on the
following pages.
50
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
3.4 Conclusions
Feasible, constructible segmental double-T options exist for all spans from 20 to 45 m. Span-todepth ratios of up to 22.5:1 are feasible, and it is possible that even more slender bridges could
be constructed.
Reducing the midspan tendon eccentricity does indeed reduce sensitivity to post-tensioning
losses with a minimum sensitivity realised between spans of 28 and 38 m for midspan tendon
eccentricities of 1000 to 1225 mm. For shorter spans, the upper efficiency limit on eccentricity
is 1200 mm; for longer spans, it is 1300 mm.
The possibility exists for single-stage stressing for shorter spans.
The construction of multi-span bridges using the single-span designs presented in this chapter is
discussed in the following chapter.
51
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.28 Conceptual design of precast segmental double-T for 20-m spans
52
SECTION AT END
1:100
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.29 Conceptual design of precast segmental double-T for 25-m spans
53
SECTION AT END
1:100
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.30 Conceptual design of precast segmental double-T for 30-m spans
54
SECTION AT END
1:100
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.31 Conceptual design of precast segmental double-T for 36.6-m spans
55
SECTION AT END
1:100
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.32 Conceptual design of precast segmental double-T for 40-m spans
56
SECTION AT END
1:100
Chapter 3
Versatility of the Double-T Base Concept for Simply Supported Spans
PLAN
1:200
ELEVATION
1:200
SECTION AT MIDSPAN
1:100
Figure 3.33 Conceptual design of precast segmental double-T for 45-m spans
57
SECTION AT END
1:100
Chapter 4
58
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
once during the service life of a bridge, problems with the joints themselves can lead to
maintenance and durability issues with other components. For example, if the neoprene seal and
waterproofing connection to the expansion joint, which can never be maintained watertight
(Menn, 1990), leak, then bridge components below them such as bearings, bearing seats, and
ballast walls / end diaphragms can be exposed to deck runoff, which hastens their degradation
(Zia and Caner, 1998). Furthermore, because of their location, these components are often
difficult to access and inspect. In essence, for bridges with expansion joints over the supports,
the weakest point in the structure from a penetration perspective is placed above the point of
worst consequence.
In addition to these durability issues, expansion joints often fail to perform their intended role. If
their seals break and they fill with debris, they no longer accommodate the translations or
rotations for which they were intended (Thippeswamy et al., 2002).
To avoid the problems listed above, the CHBDC (Cl. 2.3.2.5.1, 2006) states that, Wherever
practical, expansion and/or fixed joints in decks shall be avoided or placed in the approach
pavements. It is therefore desirable to connect adjacent spans of the proposed double-T system
in some way. One proposed method would be to construct adjacent spans one at a time and
leave them essentially simply supported. End rotations at each support would be accommodated
with a connecting slab. This option is discussed in Section 4.2. Another alternative is to make
the system fully continuous. All spans for this option would be constructed at the same time and
the bridge would be designed to resist the resulting large negative moments at supports. This
alternative is discussed in Section 4.3.
59
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
which are long and extend into the adjacent spans and accommodate both translations and
2
rotations; and flexible linking slabs, which are much shorter and only accommodate rotations .
Lam et al. (2008) note that the Ministry of Transportation of Ontario has been using linking slabs
in the rehabilitation of existing bridges since the mid-1990s following the success had by the
City of Toronto with linking slabs used to replace expansion joints on the Gardiner Expressway
in the late-1980s. The performance of these slabs led the Ministry to develop guidelines for
their design in 2001 (Lam et al., 2008).
In this section, designs for flexible linking slabs connecting adjacent spans of each of the six
design variants in Chapter 3 are presented.
4.2.1.1
The literature on linking slabs is inconclusive as to whether they act primarily as axial or as
flexural members. They have been described as purely flexural (Lam et al., 2008), purely axial
(Okeil and ElSafty, 2005), and a combination of both (Caner and Zia, 1998). Generally for all
types of linking slab, the axial component of the deformation induced in the slab is influenced by
the support conditions of the adjacent members.
The flexible linking slabs designed in this thesis are considered only to be subjected to imposed
rotation and not imposed elongation for three reasons: (1) All spans in the connected system will
be on elastomeric bearings, essentially rollers, allowing them to translate horizontally; (2) The
elastomeric bearings will act more as rollers than pins and allow span ends to rotate about their
neutral axes; and (3) The neutral axis of the double-T section is quite high and so imposed end
rotations in the spans adjacent to the flexible linking slabs will induce mostly flexural
deformation and very little axial deformation.
Much of the literature on this subject does not make a firm distinction between these two systems, referring to both
simply as flexible linking slabs or flexible links; however, the distinction makes subsequent discussion in this thesis
clearer.
60
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
The first reason presented obviously eliminates horizontal reactions at supports and, therefore,
longitudinal tensile stresses in the flexible linking slabs. An explanation of how the second and
third reasons eliminate axial deformations follows.
To explain why roller supports reduce axial deformation in a flexible linking slab, consider two
adjacent simply supported members attached by a linking slab. When the members are subjected
to positive bending, the ends subsequently rotate and induce an axial deformation in the attached
linking slab. This deformation is greater if the linking slab is farther away from the point of
rotation, hence for the same magnitude of rotation, a pin connection (whose point of rotation is
the pin at the bottom of the member) induces more axial deformation than a roller (whose point
of rotation is the neutral axis at the end of the member), which is closer to the linking slab (Okeil
and ElSafty, 2005). Figure 4.1 shows two girder ends with a linking slab between them modeled
as a stick with pinned ends. It can be seen from this figure that axial deformation is (a) least in
an linking slab connecting two roller-supported members and is equal to 2R, (b) greatest in an
linking slab connecting two pin/hinge-supported members and is equal to 2H, and (c)
somewhere in between in a linking slab connecting a roller- and a pin/hinge-supported member,
and is equal to R + H.
R
AL AXIS
NEUTR ER
D
OF GIR
AL AXIS
NEUTR ER
D
IR
G
F
O
(a)
(b)
AL AXIS
NEUTR ER
D
OF GIR
(c)
Figure 4.1 Effect of support conditions on linking slab behaviour with (a) two roller
supports, (b) two pin/hinge supports, and (c) one of each type of support (adapted from
Okeil and ElSafty, 2005)
61
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
To explain why a high neutral axis reduces axial deformation in a flexible linking slab, consider
an end of a simply supported beam on a roller. When the beam bends, the end rotates about the
beams neutral axis. A linking slab connected to the roller-supported end of the beam undergoes
axial deformations proportional to the horizontal distance between the neutral axis of the beam
and that of the linking slab. The farther between these two neutral axes, the greater the axial
deformation imposed on the flexible linking slab for a given end rotation of the members. In
Figure 4.2, it can be seen that the end displacement, R, of the linking slab is greater when the
neutral axis of the attached beam is lower (a) than if it is higher (b).
R
FLEXIBLE
LINKING SLAB
FLEXIBLE
LINKING SLAB
AL AXIS
NEUTR ER
D
OF GIR
AL AXIS
NEUTR ER
D
IR
G
F
O
(a)
(b)
Figure 4.2 Effect of distance between neutral axes on linking slab behaviour with (a)
lower neutral axis and (b) higher neutral axis (adapted from Okeil and ElSafty, 2005)
To connect adjacent spans of a multi-span double-T system, it is proposed that all intermediate
supports be elastomeric bearings that will act as rollers and that all spans be connected with short
flexible linking slabs. These two design features will ensure that axial deformations in the
flexible linking slabs are minimised. This means that there will be no horizontal fixity within the
structure. Calculations, shown in Appendix C, were performed to check the response of the
structure to longitudinal wind and braking forces. The resulting horizontal demand was well
below the horizontal shear capacity for corresponding elastomeric bearings for all span length
from 20 to 45 m, and so the lack of horizontal fixity is deemed not to be of concern for this
structure.
62
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
that these cracks and the failure of the linking slab do not create stability or safety concerns
because the area considered sits on the abutments or piers of the bridge.
63
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
LENGTH OF LINKING SLAB
CONCRETE TYPE
CL WEB
CL WEB
PLAN
CL
CL
SUPPORT SUPPORT
ELEVATION
64
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Table 4.1 Rotations imposed on linking slab due to service live loads
Span
(m)
Depth
(mm)
20
25
30
36.6
40
45
1095
1365
1640
2000
2000
2000
0.0107
0.0103
0.0098
0.0086
0.0104
0.0123
To resist these end rotations, a novel, durable material will be used: ultra high-performance fibrereinforced concrete (UHPFRC). This material is described in the following section before
describing the actual finalised designs of the flexible linking slab.
65
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
4.2.5.1
It is generally accepted that there are three main zones along the length (not width) of a crack in
fibre-reinforced concrete. These zones are best categorised by Visalvanich and Naaman (1983)
as the stress free zone (near the concrete surface, where nothing bridges the gap), the
pseudoplastic zone (where fibres bridge the gap and carry stresses through tension, bond with the
matrix, and bending of the matrix in the case of inclined fibres), and the process zone (where the
crack is currently forming within the matrix and the fibres have not yet engaged to carry more
stress than the surrounding matrix).
Fibre reinforced concretes can be either strain hardening or strain softening; their behaviour after
first cracking is dependent on fibre strength compared to concrete matrix strength and on the
volume fraction of fibres. Fibre reinforced concretes that strain harden are generally
distinguished as HPFRCCs. As tensile deformations increase in HPFRCCs and fibres elongate
and pull out at cracks, more stress is carried by the member with increasing strain, i.e., it strain
hardens. In regular fibre-reinforced concretes, there are not enough fibres bridging a crack to
carry more load than what was originally carried by the uncracked concrete matrix, fibres fail
before they pull out, and there is a sharp drop in stress after the peak stress, i.e., the concrete
strain softens (Visalvanich and Naaman, 1983). A comparison of the stress-strain relationships
of strain hardening and strain softening fibre-reinforced concretes is shown in Figure 4.4.
Whether a given mix is strain hardening or softening depends on the volume of fibres, their yield
strength, and their bond strength with the surrounding matrix. Specifically, the determining
factor is whether the bond holding all fibres bridging a crack is strong enough to carry enough
force to crack the matrix at another location before fibre pullout or yield. If it is high enough,
then strain hardening occurs.
66
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
stress
stress
a2
b1
a1
a3
b2
a4
strain
b3
strain
(a)
(b)
Figure 4.4 (a) Strain hardening and (b) strain softening fibre-reinforced concrete stressstrain relationships (adapted from Habel, 2004)
The stages of the curves above represent the following behaviours: For a strain-hardening fibrereinforced concrete: (a1) The member responds elastically until the first crack occurs. (a2)
Additional cracks form. Fibres engage at each crack, carrying increasing amounts of stress up to
their pullout or yield strength. (a3) No additional cracks form. Fibres pull out and yield, and a
process called matrix spalling occurs. This process involves fibres inclined to the direction of
stress bending and breaking off small pieces of the surrounding matrix within each crack. During
this stage, fibres are still able to carry more force than necessary to crack the matrix at other
uncracked locations. (a4) All fibres have yielded or pulled out at one or more cracks. For a
strain-softening fibre-reinforced concrete or HPFRCC: (b1) The member responds elastically
until first crack. (b2) Additional cracks form while fibres pull out and yield and matrix spalling
occurs at inclined fibres. Stress decreases because fibres slip and carry less load. (b3) All fibres
have yielded or pulled out at one or more cracks.
4.2.5.2
UHPFRC is an excellent candidate material for the linking slab application, but it is not as
readily available as high-performance concrete, nor do local contractors work with it often.
Work has been done, however, at the University of Toronto to show that a mix of UHPFRC is
viable in Ontario (Habel et al., 2008). This mix uses locally sourced constituents that can be
mixed at existing facilities in Ontario. A summary of the composition and relevant properties of
this material, taken from Habel et al. (2008) and Salonga (2010), is presented in Table 4.2 and
Table 4.3.
67
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Weight
(kg/m3)
GU cement
white silica fume, 15-18 m2/g
sand, grain size < 0.5 mm
steel fibres, straight, lf = 10 mm, df = 0.2 mm
superplasticizer, polycarboxylate, 35 % solid content by mass
Water
Total
967
251
675
430
35
244
2602
Percent by mass
37.2 %
9.6 %
25.9 %
16.5 % (5.5 % by volume)
1.3 %
9.4 %
100.0 %
Value
128 MPa
24.4 MPa
7.0 MPa *
72 C
Extremely high
The extreme durability of this material is due primarily to its high strength and the high density
of its matrix. These properties enable two other characteristics that are important to concrete in
bridges subjected to winter conditions and deicing chemicals.
1. The measured rapid chloride permeability result is exceptionally low. It is well below
values achieved with conventional high performance concretes as evinced by a study
from Bickley and Mitchell (2001). This study surveyed high performance concrete
specifications in Canada and noted an average specified value of 1000 C or less (Bickley
and Mitchell, 2001). A permeability of less than one tenth of this value has been achieved
with the University of Toronto UHPFRC mix and other similar mixes (Habel et al.,
2008).
2. The freeze-thaw cycle resistance of UHPFRC is considered to be very high for a number
of reasons. Foremost is the high tensile strength of the concrete, which resists the
expansive effect of ice formation in pores. Also relevant is the fact that UHPFRC self
68
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
desiccates relatively quickly and so the water available to expand within pores is low and
usually below the critical saturation of 91 % relative humidity (Habel et al., 2008).
150
112
38
300
300
300
900
Figure 4.5 Schematic of test setup for University of Toronto UHPFRC beam modulus of
rupture tests
69
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
90
80
Beam1
70
Beam2
60
Beam3
Loadat 50
third
points 40
(kN)
30
20
10
0
0.000
0.001
0.002
0.003
0.004
0.005
0.006
0.007
0.008
0.009
0.010
Averagestrainatthreequarterdepth
Figure 4.6 Results of University of Toronto UHPFRC beam modulus of rupture tests
The results above show the average strain in the concrete at the depth of the linear variable
differential transducer. From these results, the maximum strain in the extreme tensile fibres of
the member can be inferred for the initial linear elastic portion of the graph by multiplying
strains by two factors. First, the strains are multiplied by a factor of 2, assuming the neutral axis
is at the centre of the beam and so strains in the extreme tensile fibres are twice those measured
at a three-quarter depth. This yields the average strain in the extreme fibres of the beam.
Second, the strains are multiplied by a factor of . To obtain the maximum strain in the extreme
fibres, the strains in the beam while linear elastic are assumed to follow the shape shown in
Figure 4.7 below, increasing from zero at the ends to a maximum, constant value between the
load points. The maximum strain in such a trapezoidal shape, max, would correspond to times
the average strain, av.
The maximum strain in the extreme tensile fibres is thus 2
linear variable differential transducer.
70
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
av
max
Figure 4.7 Assumed strains in extreme tensile fibres of University of Toronto UHPFRC
beams
These assumptions are valid for the beams while they remain linear elastic. Because the beams
exhibit very slow transitions from the uncracked to the cracked state while multiple microcracks
develop with increasing load, these assumptions can be applied with reasonable accuracy even
when the beams have been loaded slightly beyond their initial cracking strength. Multiplying the
strains obtained by an overall factor of yields the maximum strains in the extreme tensile fibres
shown plotted in Figure 4.8 below.
It can be seen from these results that a maximum tensile strain due to flexure of approximately
0.0025 can be imposed on University of Toronto UHPFRC with no significant permanent
damage to the material. Indeed, for the current application, it is reasonable to assume that even
more maximum deformation is possible because the strains being imposed are due to an imposed
rotation from adjacent spans and not imposed moments. In essence, this means the application is
controlled by displacement and cracks formed at the maximum imposed rotation are not widened
further due to subsequent impositions of this rotation.
71
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
90
80
Beam1
70
Beam2
60
Beam3
Loadat 50
third
points 40
(kN)
30
20
10
0
0.000
0.001
0.002
0.003
0.004
0.005
0.006
0.007
0.008
0.009
0.010
Straininextremetensilefibresatmidspan
Figure 4.8 Maximum extreme fibre strains in University of Toronto UHPFRC beam
modulus of rupture tests
Following the results outlined above, the flexible linking slabs were designed to accommodate
strains due to rotation only, and so were dimensioned to a maximum thickness and a minimum
length such that tensile strains were accommodated without plastic deformation in the slab.
Using a tensile strain limit of 0.0025, the parameters of slab thickness and length were varied to
determine optimal values for these dimensions. Constructability criteria dictated that slabs be
made thick enough to be suitably durable. A lower limit of 75 mm was set on slab thickness to
promote a random distribution of fibre orientation. An upper limit of 1500 mm was set on slab
length to limit the amount of material placed and the associated cost. The results of the
parametric study are summarised in Figure 4.9 below, in which maximum tensile strains due to
imposed rotations (which differ for each span) are shown plotted against the varied dimensions.
The results of this study were used to set reasonable dimensions for slabs for the six bridge
variants that would ensure the flexible linking slabs remained linear elastic while undergoing the
maximum imposed rotations. These dimensions are shown below in Table 4.4.
72
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
0.0030
0.0025
0.0020
45mspan
Maximum
strainin 0.0015
topfibres
20mspan
25mand40mspans
30mspan
0.0010
36.6mspan
0.0005
0.0000
200
Flexible linking slab:
400
600
800
40
Length(mm)
60
80
100
120
140
Thickness (mm)
(a)
(b)
Figure 4.9 Maximum tensile strains in flexible linking slabs as a function of (a) length,
with constant thickness of 100 mm, and (b) thickness, with constant length of 400 mm
Table 4.4 Flexible linking slab dimensions
Span
(m)
Length
(mm)
Thickness
(mm)
20
25
30
36.6
40
45
400
375
350
325
375
450
90
90
90
90
90
90
0.0024
0.0025
0.0025
0.0024
0.0025
0.0025
The required lengths of flexible linking slab shown in the table above decrease with increasing
adjacent span length for spans from 20 to 36.6 m and then increase from 36.6 to 45 m. This
follows the trend in imposed end rotations, which vary as a function of the stiffness of the
adjacent spans and imposed live load, as described in Section 4.2.4.
These flexible linking slabs accommodate only rotations between adjacent spans. Translations
due to service conditions are accommodated by allowing the adjacent spans to move. These
translations still require that some type of expansion joint be present in the entire bridge system,
but this can be placed at the end of an approach slab where expansion joint leakage results in the
73
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
seepage of water into the underlying soil and not in the exposure of underlying bridge hardware
to deicing chemicals.
The bearings required to accommodate these translations were dimensioned and are summarised
below in Table 4.5. The bearings selected were chosen from the AGOM catalogue (2009) and
are all Type 5 elastomeric bearings with a specified bearing strength of 15 N/mm2. Smaller
bearings are possible with an increased bearing strength, but the trade-off for this added strength
is the ratio of height of elastomer to height of bearing, i.e., horizontal translation capacity is
sacrificed for smaller bearing area.
Table 4.5 Selected short elastomeric bearings for two-span system
Span
(m)
ULS
weight per
bearing
(kN)
Required
area
(mm2)
SLS imposed
horizontal
translation
(mm)
Dimensions
of selected
bearing
(mm)
Height of
selected
bearing
(mm)
Height of
elastomer
(mm)
20
25
30
36.6
40
45
1842
2254
2667
3111
3300
3468
122 813
150 247
177 832
207 418
219 999
231 217
25.2
34.3
51.8
60.1
69.6
71.0
350 x 450
350 x 450
400 x 500
400 x 600
400 x 600
400 x 600
76
91
121
151
181
181
44
55
77
99
121
121
This table is for bridges with two adjacent spans in a configuration shown in Figure 4.10a below.
For bridges with four adjacent spans, like the configuration shown in Figure 4.10b, horizontal
translations at the abutments are greater and require larger, taller bearings such as those listed in
Table 4.6 below. All of these bearings can be accommodated physically under the widened webs
of the end segments.
EXPANSION JOINT
APPROACH SLAB
APPROACH SLAB
SHORT
ELASTOMERIC
BEARINGS
SHORT
ELASTOMERIC
BEARING
EXPANSION JOINT
SHORT
ELASTOMERIC
BEARING
(a)
EXPANSION JOINT
APPROACH SLAB
TALL
ELASTOMERIC
BEARING
SHORT
ELASTOMERIC
BEARINGS
SHORT
ELASTOMERIC
BEARINGS
SHORT
ELASTOMERIC
BEARINGS
APPROACH SLAB
EXPANSION JOINT
TALL
ELASTOMERIC
BEARING
(b)
Figure 4.10 Configurations of flexible linking slabs and bearings for (a) two- and (b) fourspan bridges
74
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Table 4.6 Selected tall elastomeric bearings for abutments of four-span system
Span
(m)
SLS imposed
horizontal
translation
(mm)
Dimensions
of selected
bearing
(mm)
Height of
selected
bearing
(mm)
Height of
elastomer
(mm)
20
25
30
36.6
40
45
50.4
68.6
103.6
120.2
139.2
142.0
350 x 450
400 x 500
700 x 800
700 x 800
900 x 900
900 x 900
121
166
225
275
291
291
77
110
165
195
216
216
These configurations are, of course, not an exhaustive list. Configurations of three spans and
those with mixed span lengths and span lengths between those studied all require different
dimensioning of flexible linking slabs and bearings to accommodate translations. The results
shown above, though, demonstrate that it is feasible to design such configurations.
75
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
76
Figure 4.11 Conceptual design of flexible linking slab for adjacent 20-m spans
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
77
Figure 4.12 Conceptual design of flexible linking slab for adjacent 25-m spans
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
78
Figure 4.13 Conceptual design of flexible linking slab for adjacent 30-m spans
Chapter 4
79
Figure 4.14 Conceptual design of flexible linking slab for adjacent 36.6-m spans
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
80
Figure 4.15 Conceptual design of flexible linking slab for adjacent 40-m spans
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
81
Figure 4.16 Conceptual design of flexible linking slab for adjacent 45-m spans
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
82
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
below 0.6fc, or 42 MPa. At the ultimate limit state, the section is required to resist negative
moments without crushing concrete.
Number of
strands
Eccentricity of
tendons over supports
(mm)
150
160
206
168
417
267
83
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
In a continuous system it might seem intuitive to bring the post-tensioning tendons as high as
possible over the piers in order to reduce their eccentricity and the resulting imposed negative
moment. This causes a related effect, however: increased secondary moment due to prestress
increases positive moments in the adjacent spans. To reduce this effect, tendons are brought up
over the supports, but not to their minimum possible eccentricity.
4.3.3.1
Dead and superimposed dead loads were multiplied by a load factor of 1.00 for the serviceability
limit state. At the ultimate limit state, the weight of the precast concrete girder was multiplied by
a load factor of 1.10, the weight of the cast-in-place concrete barriers by 1.20, and that of the
asphalt wearing surface by a load factor of 1.50.
4.3.3.2
Live Loads
For each of the six systems of two adjacent spans, flexural responses to both the CL-625 truck
and lane loads were determined. Then, as for the single span systems, responses under live loads
in both two and three design lanes were considered.
To account for the statistical unlikelihood of all lanes being occupied by traffic at once, multilane loading reduction factors specified in the CHBDC were applied to all live loads.
To account for the increased vertical loads applied by vehicles travelling over uneven surfaces,
the dynamic load allowance specified in the CHBDC was also applied to the CL-625 truck loads,
but not the lane loads.
Truck placements that produced the most severe positive moments within the span and the most
severe negative moment over the support were considered. For positive moment, the CL-625
truck load produced the most severe effects in all bridges. For negative moment, the lane load,
with the truck at a slightly different location, produced the most severe effect.
84
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
The amplification factors calculated based on Menns model (Menn, 1990) and the grillage
models determined previously in Section 3.3.1.3 were used to account for the uneven sharing of
load between webs due to eccentric live load. It is likely, however, that load sharing between
webs would be slightly better in a continuous system than a simply-supported system. This is
because when one span is loaded, positive flexure is induced in adjacent spans and the
diaphragms of adjacent spans contribute additionally to load sharing, not just those of the span
being loaded.
Because load sharing is probably more even in a continuous system, using these amplification
factors was felt to be slightly conservative. To determine the degree of this conservatism, the
36.6-m structure was analysed with reduced live loads that assumed perfect live load sharing
between webs. The results of this analysis indicate that the number of required post-tensioning
strands would be decreased by only 10 % in such a system. Live load sharing in the actual
continuous system would therefore dictate a number of strands somewhere between the number
required for the poor live load sharing of the simply-supported system (160 strands) and that
required for the perfect load sharing system (144 strands). Using the higher number is therefore
conservative.
It is not overly conservative, though. Menn (1990) has compiled a survey of nineteen
prestressed concrete highway bridges. The bridges considered are larger than the double-T, but
still give a good indication of relative costs of component materials. The survey found that
prestressing steel accounted for an average of 11.2 % of total structure cost. It can be inferred,
then, that if perfect live load sharing existed in the double-T structure, a 1.12% savings in cost
could be realised because of the lower required amount of post-tensioning steel. Perfect live load
sharing does not exist, though, and so a more detailed analysis would yield cost savings
somewhat lower than this figure. For a large project in which many continuous double-T
structures were being built, such an analysis would be warranted but for the purposes of this
thesis, the load sharing model used for single-span bridges, and the conservative results it yields,
are appropriate.
Load factors of 0.90 and 1.70 were used for the serviceability and ultimate limit states,
respectively.
85
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
4.3.3.3
Temperature Effects
The effects of temperature must be considered at serviceability limit states for a continuous
system. A temperature differential across the section induces moment in a two-span system due
to restraint at the middle support. The resulting bending moment diagram shape is triangular
with a maximum over the support. The differential considered was a hot on top differential
across the 225-mm depth of the deck slab. The self-equilibrating stress distributions and
resulting imposed moment are shown in Figure 4.18. A load factor of 0.80 was used for the
serviceability limit state when calculating positive moment demand. Temperature effects were
not applied when considering negative moment demand as they reduced the total applied
moment.
SECTION
SELF-EQUILIBRATING
STRESS DISTRIBUTION (MPa)
RESULTING
MOMENT (kNm)
+1.873
-3.300
-2.880
+2.064
-1.848
4.3.3.4
86
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
87
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
DeadandSuperimposedLoad
60000
50000
40902kNm
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
50
60
70
80
90
60
70
80
90
60
70
80
90
60
70
80
90
60
70
80
90
70
80
90
Locationalongbeam(m)
20000
30000
40000
50000
LiveLoadTruck
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
6105kNm
50
Locationalongbeam(m)
20000
30000
40000
50000
PrimaryMomentduetoPrestress
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10341kNm
10
20
30
40
50
Locationalongbeam(m)
20000
30000
40000
50000
SecondaryMomentduetoPrestress
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
50
Locationalongbeam(m)
20000
30000
40000
49788kNm
50000
TemperatureDifferentialacrossDeckHotonTop
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
50
1878kNm
Locationalongbeam(m)
20000
30000
40000
50000
TotalBendingMomentImposedonConcreteSection
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
20000
Capacity=24648kNm
Demand=13519kNm
10
20
Demand=4871kNm
Capacity=5283kNm
30
40
50
60
Locationalongbeam(m)
30000
40000
50000
N.B. Thissectionalanalysisisnotvalidinthedisturbedregionsattheendsofthebeam.
Figure 4.19 Positive moment serviceability limit state analysis for two 45-m spans
88
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
DeadandSuperimposedLoad
60000
50000
40902kNm
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
50
60
70
80
90
60
70
80
90
60
70
80
90
60
70
80
90
60
70
80
90
Locationalongbeam(m)
20000
30000
40000
50000
LiveLoadLane
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
9070kNm
10
20
30
40
50
Locationalongbeam(m)
20000
30000
40000
50000
PrimaryMomentduetoPrestress
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10341kNm
10
20
30
40
50
Locationalongbeam(m)
20000
30000
40000
50000
SecondaryMomentduetoPrestress
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
10
20
30
40
50
Locationalongbeam(m)
20000
30000
40000
49788kNm
50000
TotalBendingMomentImposedonConcreteSection
60000
50000
40000
30000
20000
Bending 10000
0
moment
0
(kNm)
10000
20000
Capacity=24648kNm
Demand=14961kNm
10
20
Demand=4765kNm
Capacity=5283kNm
30
40
50
Locationalongbeam(m)
30000
40000
50000
N.B. Thissectionalanalysisisnotvalidinthedisturbedregionsattheendsofthebeam.
Figure 4.20 Negative moment serviceability limit state analysis for two 45-m spans
89
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
90
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Temperature effects were not considered at the ultimate limit state, nor were creep and shrinkage
as they are not significant in a cracked structure under ultimate conditions (Menn, 1990). The
ultimate capacity of all sections considered was greater than the factored demand. Positive
bending within the spans was found to govern over negative bending over the piers. This is as
expected. The double-T concrete section considered on its own is far stronger in negative
bending than positive bending. This is because the neutral axis of the cracked section is
relatively high for both positive and negative flexure. In positive flexure, the contribution of the
concrete to the moment resistance is from the deck slab. Because the deck slab is so wide, only a
small depth of concrete is in compression and the neutral axis stays high, within the deck slab.
In negative flexure, the contribution of the concrete to the moment resistance is from the webs.
Because the webs are so thin, a large depth of concrete is in compression and the neutral axis
once again stays high, near the haunches of the webs. In the former case, the moment arm of the
compressive force when taken from the uncracked neutral axis is relatively small compared to
the latter case and so the moment resistance is less in positive flexure.
Tendons do not yield in the two-span system as they do in the simply-supported system. The
reason is twofold. First, the tendons in the continuous system are twice as long and so can
undergo twice the elongation prior to yield. Second, no tendon elongation is associated with
negative bending in the cracked section over the pier because the tendons are so low within the
section. This means that in negative bending, the tendons are located at a height at which
adjacent concrete is in compression and so negative bending actually contributes to the
shortening of the tendons in this region.
Diaphragm Location
In the base concept simply-supported double-T, downward forces from gravity loads carried in
the webs and from the anchored tendons over the supports act in line with the upward reactions
of the bearings. For this reason, the original diaphragms over the supports only have to resist the
inward component of the forces from the anchored tendons. The proposed continuous double-T
does not deviate the tendons laterally at interior supports, though, so the downward forces noted
above must flow laterally through the concrete to meet the reactions that occur at the bearings.
91
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
This lateral shift in the flow of forces causes some internal forces in the diaphragms at the
supports which must be carefully considered. Figure 4.21 below shows alternative layouts of the
diaphragm and their associated truss models. Tensile forces are shown in red and compressive
forces in green.
(a)
(b)
(c)
Figure 4.21 Truss models for alternative layouts for diaphragm with (a) bearings under
webs, (b) bearings inclined inward, and (c) bearings shifted inward
Of primary concern is the tensile force along the bottom of the diaphragm shown in Figure 4.21a.
There is no simple way to cancel out this force. If the bearings are inclined inward to counteract
the outward force as shown in Figure 4.21b, then the tension does not disappear, but must be
resisted somewhere lower in the pier. If the bearings are moved inward as shown in Figure
4.21c, then tension must be carried in the top to move the loads from the webs to the bearings.
The layout shown in Figure 4.21a is most suitable for the purposes of this thesis as it avoids the
pier design associated with the layout shown in Figure 4.21b and involves less complicated
reinforcement than the layout shown in Figure 4.21c. Concrete dimensions for this design were
established as shown in Figure 4.22 below.
The diaphragm was dimensioned 300 mm thick to fit the considerable amount of reinforcing
steel required to resist the tensile forces along its bottom. This thickness was widened to 700
mm in a 1:1 haunch between the webs and the deck slab to transfer downward forces from the
deviation of the tendons into the webs. Table 4.8 below outlines the required steel for each
variant to carry tension along the bottom of the diaphragm.
92
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
A
1
1
A'
700
225
2000
1775
CL
SUPPORT
Alternative 1
Alternative 2
20
36.6
45
8, hooked 35M
13, hooked 35M
19, hooked 35M
4.3.7 Losses
Sections 4.3.1 through 4.3.6 show that it is possible to modify the double-T section in such a way
that it resists negative moments at supports and so is appropriate for a continuous girder system.
The feasibility of such a system, however, is dependent on whether it can be post-tensioned
along its entire length without unreasonably high losses of post-tensioning force. Li (2010)
showed that the losses for a 36.6-m-long single span brought the final stress in the tendons to
0.67fpu. The following sections present calculations of losses for one- to four-span systems, each
with identical span lengths from 20 to 45 m, and show that losses are reasonably low for all
systems. The losses considered, as specified in Clause 8.7.4.1 of the CHBDC (2010), are those
93
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
that occur initially at jacking and subsequent transfer of stress to the concrete, i.e., losses due to
friction and anchor set and those that occur during the service life of the member, i.e., due to
creep, shrinkage, and relaxation of the tendons.
4.3.7.1
Friction
Frictional forces between the tendons and ducts during stressing reduce the overall force in the
tendon. These reductions, FR, were calculated according to CHBDC (2010) Clause 8.7.4.2.3 as
1
(4.1)
Where fsj is the stress in the tendon at the time of jacking; is the coefficient of friction between
tendon and duct at a deviator, taken as 0.25 for rigid steel pipe ducts; and is the angle break at
the deviator. The values obtained for frictional losses were lower than those that would be
expected for draped internal tendons of similar length. This is because friction losses in external
tendons only occur at the locations of discrete angle breaks such as deviators.
4.3.7.2
Anchorage Slip
Anchorage slip, or anchor set, losses were calculated based on a 7-mm slip of the anchorage
seating wedges, which is a typical value for most post-tensioning hardware. The loss associated
with this slip is due to the loss of strain equivalent to the slip spread over a length of tendon
between the anchor and a remote deviator. The exact location of this deviator was not initially
known but was determined as follows:
(1) The normal force at the closest deviator to the jacking anchorage was calculated based on
the jacking force in the tendon and the angle break imposed by the deviator.
(2) The frictional force at that deviator due to this normal force was calculated based on a
coefficient of friction of 0.25 as specified in Table 8.3 of the CHBDC (2010) for external
ducts.
(3) A resulting stress difference across the deviator was calculated based on the loss in stress
from the jacking side of the deviator to the dead end side.
(4) A frictional stress capacity for the deviator was calculated based on the area over which
the tendon rubbed in this location.
94
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
(5) This process was repeated for each subsequent deviator farther from the jack (within the
spans and at the supports). The tendon was assumed to hang up at the deviator at which
the frictional stress capacity (the capacity of the deviator to hold the tendon) was greater
than the stress difference across it caused by the cumulative loss in frictional stresses of
previous deviators (the pull of the tendon across the deviator).
It was found that, contrary to other types of loss, those due to anchorage slip actually decreased
with longer span and overall structure lengths. This was because anchorage slip is a fixed
amount of shortening. The resulting stress loss is reduced when this shortening is spread over a
longer total length of strand in a longer bridge system.
4.3.7.3
Creep
Creep is the plastic shortening of concrete members over time under long-term loads. Under the
constant load of a post-tensioning force, concrete members shorten in the direction of that force,
thereby reducing the prestressing force. This reduction was calculated according to CHBDC
Clause 8.7.4.3.2 as
1.37
0.77 0.01
(4.2)
This equation contains a term, RH, to account for the mean annual relative humidity to which the
member is subjected. Creep is primarily due to water molecules moving out from between
adjacent sheets of calcium silicate hydrate within a concrete matrix and escaping to the
atmosphere. A higher relative humidity, literally a higher partial pressure of water within air,
keeps more moisture within the concrete matrix and slows down the rate of creep. For the
purposes of this thesis, a value of 65 % was used as given for Toronto in Figure A3.1.3 of the
CHBDC (2010). Kcr is a factor taken as 1.6 for post-tensioned components; fcir is as described
above in the section on elastic shortening; and fcds is the stress in the concrete at transfer at the
same location at which fcir is calculated due to the effects of subsequently added dead loads and
is taken as
,
95
(4.3)
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
4.3.7.4
Shrinkage
Shrinkage results from a loss of water within the concrete and is not affected by member loading.
The simplified method presented in Clause 8.7.4.3.3 of the CHBDC (2010) has been used to
determine the effects of concrete shrinkage on prestressing losses:
94
0.85
(4.4)
As with creep, the value for mean annual relative humidity in Toronto of 65 % was used as given
in Figure A3.1.3 of the CHBDC (2010).
4.3.7.5
Relaxation
Relaxation of tendons after transfer, REL2, was calculated using the formula given in Clause
8.7.4.3.4 of the CHBDC (2010):
0.55
0.34
0.002
(4.5)
The subscript 2 in the term REL2 distinguishes the relaxation of strands that occurs after transfer
from that which occurs in pretensioned members after stressing but prior to concrete placement,
REL1. This stage does not occur in the post-tensioning process and so REL1 is neglected in this
thesis. The subscript is kept, however, to maintain consistency with the code. The formula
above takes into account the stress in the tendons at the time of transfer, fst; the ultimate stress of
the tendons, fpu, the losses due to creep, CR, and those due to shrinkage, SH.
4.3.7.6
The total losses of stress in the tendons were calculated as the sum of the losses mentioned
above. These are applicable to strands jacked from one end. Strands jacked from both ends
would not exhibit significantly lower amounts of losses because this would only reduce friction
losses, which are a small component of total losses in this external, unbonded tendon system. A
summary of stresses in the tendons after all losses is presented in Table 4.9.
96
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Table 4.9 Tendons stresses after all losses | p,final as a fraction of fpu, (with an assumed
jacking stress of 0.800fpu)
Span Length (m)
Number
of Spans
20
36.6
45
1
2
3
4
0.725
0.739
0.743
0.746
0.716
0.724
0.726
0.726
0.679
0.685
0.687
0.688
These results differ from those originally calculated by Li (2010) for this system. The current
model differs from the original one calculated by Li in three ways: the calculated friction losses
are smaller in this model because the angle break term, , has been input in radians instead of
degrees; the losses due to creep and shrinkage are calculated based on the 2010 CHBDC rather
than Gauvreau (1993); and the 36.6-m span in this calculation contains 160 strands instead of
156, at a different eccentricity. If the base concept of a 36.6-m-long, 2000-mm-deep bridge with
156 strands were analysed using the current method, stress in the tendons after all losses would
be 0.697fpu, rather than 0.670fpu.
Losses do not vary significantly between the highest amount (0.121fpu for the single 45-m-span)
and the lowest (0.054fpu for the four 20-m-spans) and all calculated losses are reasonably close to
what has been assumed in design calculations, i.e., 0.670fpu. Losses for all configurations are
reasonably low because the tendons are external and have no drape but only discrete angle
breaks at which friction losses can occur.
Configurations with more spans have fewer losses. This is due to the way anchor set loss is
distributed across the spans as discussed in Section 4.3.7.2.
It is possible that even longer multi-span configurations could be stressed with continuous
tendons without undue prestress losses. For the purposes of this thesis, however, only
configurations with up to four spans are considered.
97
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
4.4 Conclusions
Durable multi-span alternatives for a wide variety of highway overpass structures are possible
using the segmental double-T concept. The design alternatives of simply supported spans with
flexible linking slabs and real continuous structures presented above are compared and
contrasted with each other and the conventional slab on girder system in detail in Chapter 6.
First though, the following chapter addresses another barrier to the adoption of the precast
segmental method for short overpass bridges: the technically onerous requirement for matchcasting of segments.
98
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Figure 4.23 Conceptual design of continuous configuration for adjacent 20-m spans
99
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Figure 4.24 Conceptual design of continuous configuration for adjacent 36.6-m spans
100
Chapter 4
Application of the Precast Segmental Double-T to Multi-span Structures
Figure 4.25 Conceptual design of continuous configuration for adjacent 45-m spans
101
Chapter 5
102
Chapter 5
Geometry Control
Figure 5.1 Match casting (adapted from Interactive Design Systems, 2005)
The precise surveying required before and after the casting of each segment and the calculations
required to set each new segment and ensure proper alignment can be onerous for precasters and
not many in Canada are equipped to handle such work.
103
Chapter 5
Geometry Control
span (Holden and Sammler, 1999), or even 1/300th of span (Galambos et al., 1993) is almost
completely invisible to the human eye.
A common standard used for precasting of structural and architectural concrete (PCI, 2000) was
consulted to determine tolerances that precasters are accustomed to following for everyday
components. The most rigorous tolerance given in this reference for dimensions of handmeasured wood formwork is 6 mm (). It is reasonable, therefore, to demand such rigorous
tolerances from precasters for dimensions of double-T segments. For overall structural
geometry, the tolerance that would often be applied is 1:800 for deviations from the entire length
of the structure, as given in CSA A23.4, Clause 12.1.2. For reasons stated above, it is reasonable
that this tolerance could be relaxed to a maximum deviation of 1/400th of span length for short
structures such as the segmental double-T.
104
Chapter 5
Geometry Control
Overall width The effects of a 6-mm variation in width between segments are also not
severe. Such a difference would not cause problems with fit of components and would be
mainly aesthetic.
Deck slab thickness - The effects of a 6-mm variation in deck slab thickness between
segments are not severe. If the differences in height are so severe that they cause problems
with differential compaction of asphalt on the deck, then problem areas can be milled to
ensure a more uniform surface.
Web width - The effects of a 6-mm width variation between webs are also not severe. Such a
difference would not cause problems with fit of components and would be mainly aesthetic.
If the same formwork is used for each segment, then it is unlikely that the three parameters above
will vary much. The dimension that will be most difficult to control between segments and will
have the most significant impact will be the length of longitudinal vertices of the segment,
controlled by the alignment of the two bulkheads with one another. A difference between
vertices will cause a change in alignment of the overall structure as shown in Figure 5.2, in
which the misalignment has been exaggerated. If the left side is longer than the right, then the
overall structure will curve to the right. If the top is longer than the bottom, then the overall
structure will curve downward.
Figure 5.2 Exaggerated alignment effect of differences in vertex length for a bridge
segment
105
Chapter 5
Geometry Control
In the process of match casting segments for curved bridges, vertex lengths are intentionally
varied to introduce curve (in plan or elevation, or both) into the structure. The proposed doubleT with external, unbonded tendons is for straight bridge applications and so such deviation is
undesirable. A worst case would be if an error of the same magnitude as the construction
tolerance (6 mm) were introduced into all segments along the same vertex and the error
compounded. These errors would result in misalignments as listed in Table 5.1 and Table 5.2
below for deviations from the horizontal (in plan) and vertical (in profile), respectively.
As can be seen from the following tables, very large deviations result from the worst possible
case of errors. The most severe errors in both plan and elevation are for the longest
configuration, the 45-m span: 217 mm and 1500 mm, respectively.
Table 5.1 Total horizontal misalignment of single span due to compounding geometry
error
Span
(m)
Error in one
vertex
(mm)
Width of
segment
(mm)
Deviation
per segment
(radians)
Number of
segments
Resulting radius
of curvature
(m)
Total horizontal
misalignment
(mm)
20
25
30
36.6
40
45
6
6
6
6
6
6
13800
13800
13800
13800
13800
13800
0.000435
0.000435
0.000435
0.000435
0.000435
0.000435
10
11
14
14
17
20
4830
5520
5290
6440
6210
5750
46
63
98
119
170
217
Table 5.2 Total vertical misalignment of single span due to compounding geometry error
Span
(m)
Error in one
vertex
(mm)
Height of
segment
(mm)
Deviation
per segment
(radians)
Number of
segments
Resulting radius
of curvature
(m)
Total vertical
misalignment
(mm)
20
25
30
36.6
40
45
6
6
6
6
6
6
1095
1365
1640
2000
2000
2000
0.005479
0.004396
0.003659
0.003000
0.003000
0.003000
10
11
14
14
17
20
383
546
629
933
900
833
575
638
824
823
1170
1500
106
Chapter 5
Geometry Control
misalignments are exaggerated, shows that the worst-case deviation introduced into the segments
from vertex length errors occurs at midspan once the segments are in place and is equal to only a
quarter of the original error.
REALIGNMENT
MISALIGNMENT
WITH
REALIGNMENT
Span
(m)
Vertical
Misalignment
at Midspan
(mm)
Vertical
Deviation as
Fraction of Span
Horizontal
Misalignment
at Midspan
(mm)
Horizontal
Deviation as
Fraction of Span
20
25
30
36.6
40
45
11
16
24
30
42
54
1/1752
1/1584
1/1224
1/1227
1/943
1/828
144
160
206
206
293
375
1/139
1/157
1/146
1/178
1/137
1/120
107
Chapter 5
Geometry Control
It can be seen from Table 5.3 above that the horizontal misalignment errors are all less than
1/400th of the span length and are acceptable by the standards for global tolerance laid out earlier.
The worst of the vertical misalignment errors occurs for the 45-m span and is 1/120th of span
length. In contrast to the errors in plan, this error is significant and unacceptable.
(5.1)
Where vi is the vertex length for segment i, L is the total proposed length of the bridge, N is the
total number of segments in the bridge, and i is the number of segments cast prior to the current
segment.
Of course such measurements introduce additional errors. The precision of a good hand tape
measurement is usually no better than 0.794 mm (1/32). Two measurements are associated with
the casting of each segment: one of the segment previously cast and one of the forms for the new
segment. The measurement errors associated with the casting of each segment, then, could be as
great as 2 x 0.794 = 1.588 mm. Conservatively rounding this up to 2 mm and adding it to the
maximum formwork construction error of 6 mm yields a total tolerance per segment of 8 mm.
When an error compounds in a worst-case scenario as described above, the resulting corrected
alignments would be as shown in Table 5.4 below.
This method corrects vertical misalignment errors, which were already within tolerances without
the corrections, to almost imperceptible values. It corrects horizontal alignment errors to
108
Chapter 5
Geometry Control
acceptable levels, with the worst case being the 36.6-m span, with a global deviation in profile of
1/625th of span length.
Table 5.4 Alignment errors after segment placement with compensatory adjustments
Span
(m)
Vertical
Misalignment at
Midspan
(mm)
Global Vertical
Deviation Ratio
Horizontal
Misalignment at
Midspan
(mm)
Global Horizontal
Deviation Ratio
20
25
30
36.6
40
45
2.6
3.5
5.0
9.0
6.3
7.5
1:8625
1:7670
1:6418
1:4311
1:6718
1:6249
32
36
42
62
43
52
1:684
1:759
1:763
1:625
1:974
1:906
Such worst-case errors in elevation alignment alter the tendon eccentricity at midspan. However,
results presented in Chapter 3 indicate that the double-T system will accommodate a significant
variation in post-tensioning moment without adverse effect; and so such a small error will not be
a major concern.
The discussions above relate only to single-span structures. The conclusions presented can also
be applied to multi-span systems, though. To ensure that alignment deviations in one span do
not adversely affect the adjacent span, a short closure pour can be constructed. This pour
between segments could make up the difference in alignment between spans. Because tendons
are external, this closure would not require any ducts and could easily be formed and poured on
site.
5.6 Conclusions
Match casting is not required to construct adequately straight short-span double-T bridges. Any
precaster accustomed to the standard forming tolerance of 6 mm () can construct sufficiently
precise segments for double-T bridges using hand measurements and simple calculations and so
the structures can be built by almost any precaster in Canada. Another potential barrier to
adoption of the double-T system: cost, will be addressed in the following chapter.
109
Chapter 6
110
Chapter 6
Comparison of Double-T and Conventional Systems
slenderness was not found in this study and it is reasonable to expect that slightly more slender
bridges could be designed.
There are measurements of material use efficiency for concrete bridges other than slenderness,
though. One of them is effective depth, which is calculated by dividing the volume of concrete
in the superstructure by the deck area. Menn (1990) gives a formula for what he believes is an
3
0.0045 .
Figure 6.1 below shows effective depth values for the six bridges selected in Section 3.3.8 of
Chapter 3 and plots them against Menns formula. As can be seen from the figure, the chosen
variants all have approximately the same effective depth. All variants are much more efficient
than what would be suggested by Menns formula. This is to be expected as the systems take
advantage of the relatively high-strength concrete employed in their construction. Menns
formula was primarily derived to describe longer, multi-span, concrete box girder bridges and so
is not very applicable to these shorter span double-T bridges, though.
0.65
Menn:0.35+0.0045L
0.60
0.55
0.50
Concretevolume/ 0.45
deckarea(m)
0.40
0.35
0.30
10
20
30
40
50
Longestspanlength(m)
For multi-span bridges, Menn recommends using a geometrical average of the span lengths.
111
60
70
Chapter 6
Comparison of Double-T and Conventional Systems
Another measure of the efficiency of a post-tensioned concrete bridge is the amount of posttensioning steel used per unit volume of concrete. Figure 6.2 below shows the amounts of posttensioning in the six chosen bridge variants plotted against two formulae which describe
4
relatively efficient post-tensioned concrete bridges. The first is Menns (1990) : 0.4 . The
second is Schlaich and Scheefs (1982): 4.5
0.5 .
60
50
Prestressing
steelmass/
concrete
volume(t/m3)
40
SchlaichandScheef:4.5+0.5L
30
Menn:0.4L
20
10
0
10
20
30
40
50
Longestspanlength(m)
60
70
Again, Menn recommends using a geometric average of span lengths for multi-span structures.
112
Chapter 6
Comparison of Double-T and Conventional Systems
113
Chapter 6
Comparison of Double-T and Conventional Systems
system is in the deck slab, a slight reduction in deck slab thickness would lead to large savings in
concrete, and so it is likely that these bridges could be made slightly more slender.
25
20
Span:depth
BridgeType
15
singlespanCPCIgirder
multispanCPCIgirder
doubleT
10
10
20
30
40
50
Longestspanlength(m)
60
70
Figure 6.3 Span-to-depth ratio versus span length of double-T and conventional bridges
The effective depths, also described above, for each of the sixteen conventional bridges
considered were calculated and plotted against the six chosen double-T variants in Figure 6.4.
Conventional single-span bridges are shown in green, multi-span in blue. The six double-T
spans considered are shown in red. This figure shows that the double-T designs are more
efficient than most comparable conventional bridges for spans of 30 to 45 m, but do not lie
outside the normal range for this type of bridge.
114
Chapter 6
Comparison of Double-T and Conventional Systems
0.65
0.60
0.55
0.50
Concrete
volume/
deck
area(m)
0.45
BridgeType
0.40
0.35
singlespanCPCIgirder
multispanCPCIgirder
doubleT
0.30
10
20
30
40
50
Longestspanlength(m)
60
70
Figure 6.4 Effective depth versus span length of double-T and conventional bridges
The double-T is slightly more efficient than conventional systems in terms of concrete without
using more prestressing steel than a conventional precast girder system. Figure 6.5 below
compares area of prestressing steel to longest span length. This plot shows that the double-T
uses about the same amount of prestressing steel as any conventional configuration for a
comparable span. Conventional single-span bridges are shown in green, multi-span in blue. The
six double-T spans considered are shown in red.
0.09
0.08
0.07
0.06
Areaof
prestressing
steel(m2)
0.05
0.04
BridgeType
0.03
0.02
0.01
singlespanCPCIgirder
multispanCPCIgirder
doubleT
0.00
10
20
30
40
50
Longestspanlength(m)
60
70
Figure 6.5 Post-tensioning use versus span length of double-T and conventional bridges
115
Chapter 6
Comparison of Double-T and Conventional Systems
Unit
Low
High
Notes
Longitudinal Post-tensioning
-- $8500 --
Transverse Post-tensioning
-- $11,500 --
Fabrication
m3
-- $1171.10 --
Transportation
m3
$143.24
$286.47
Erection
m3
$166.35
$332.70
Precast concrete
For transportation and erection of segments, high and low unit prices are used. These costs could
vary substantially from contract to contract. Because double-T segments could be transported by
regular wide-load flatbed truck, rather than the multi-vehicle, police-escorted system used to
transport long girders, the mock unit price used for this item was considered to range from the
average for precast girders down to half of the average.
116
Chapter 6
Comparison of Double-T and Conventional Systems
Erection of the segments would require some sort of falsework or erection girder, something not
required for the simpler erection of precast girders. For this reason, the mock price used for
double-T segments was considered to range from the average for precast girders up to twice the
average. These variations are consistent with assumptions originally made by Li (2010).
Figure 6.6 below presents total superstructure cost data, including only the items listed in Table
6.1, divided by total deck area for each bridge. This is plotted against span length. Conventional
single-span bridges are shown in green, multi-span in blue. High and low costs for the six
double-T spans considered are shown in red, linked together for each span length. From this
figure, it can be seen that the initial superstructure costs of double-T bridges lies somewhere in
the middle of the range of costs for conventional precast girder bridges and so the double-T can
be said to be competitive with the conventional system in terms of cost.
$2,000
$1,500
Costperunit $1,000
deckarea
(2010$/m2)
BridgeType
$500
singlespanCPCIgirder
multispanCPCIgirder
doubleT
$0
10
20
30
40
50
Longestspanlength(m)
60
70
Figure 6.6 Unit cost of bridge superstructure versus span length of double-T and
conventional bridges
The discussions above present comparisons of material use and construction costs. The
following sections present a comparison of the various designs considering construction logistics
and scheduling.
117
Chapter 6
Comparison of Double-T and Conventional Systems
118
Chapter 6
Comparison of Double-T and Conventional Systems
119
Chapter 6
Comparison of Double-T and Conventional Systems
Table 6.2 Construction schedules for various alternative methods | two 40-m spans
Construction method
Duration of Superstructure
Construction
(working days)
Duration as percentage of
precast girder option
Precaster Start-up
(number of working days
prior to start of
superstructure
construction)
Falsework below new
overpass
Large crane use
Number of mobilisations of
paving crew
Continuous
segmental
double-T on
falsework
Simply-supported
spans segmental
double-T on
falsework
Simply-supported
spans segmental
double-T on
erection girder
Conventional
precast girders
with cast-inplace deck slab
51
47
33
61
84 %
77 %
54 %
100 %
38
36
50
29
under spans
individually for
19 days each
2 mobilisations of
2 days each over
16 working days
3
none
none
1 mobilisation of
16 days
1 mobilisation of
1 day
Table 6.3 Construction schedules for various alternative methods | four 40-m spans
Construction method
Duration of Superstructure
Construction
(working days)
Duration as percentage of
conventional precast girder
option
Precaster Start-up
(number of working days
prior to start of
superstructure
construction)
Falsework below new
overpass
Large crane use
Number of mobilisations of
paving crew
Continuous
segmental
double-T on
falsework
Simply-supported
spans segmental
double-T on
falsework
Simply-supported
spans segmental
double-T on
erection girder
Conventional
precast girders
with cast-inplace deck slab
84
75
49
105
80 %
71 %
47 %
100 %
79
70
98
59
under all
spans for
70 days
1 mobilisation of
8 days
under spans
individually for
19 days each
4 mobilisations of
2 days each over
44 working days
5
none
none
1 mobilisation of
30 days
1 mobilisation of
1 day
120
121
Simply-supported spans
segmental
double-T on erection girder
least impact,
no major closures
least impact,
no major closures
less
more
more
none
none
required
none
Continous segmental
double-T on falsework
Potential
requirement
for road
closures
Traffic
control
Construction
duration
Precast
concrete
Cast-in-place
concrete
Posttensioning
Falsework
Erection
girder
Large crane
use
Chapter 6
Simply-supported spans
segmental
double-T on falsework
Construction
Method
Chapter 6
Comparison of Double-T and Conventional Systems
6.4.3.1
Of the two major groups of double-T alternatives considered in this thesis, the simply-supported
option requires less time onsite and less overall falsework, but more intensive onsite operations,
e.g., more use of a crane onsite and more mobilisations of a paving crew. When only
considering construction schedules, it appears to be the better option, but it is understood that
other factors such as the higher durability inherent in a fully continuous structure could lead a
designer to choose it as a preferred option. Table 6.5 below compares the advantages and
disadvantages of the real continuous and simply-supported options presented in this thesis.
Table 6.5 Comparison of construction schedules between continuous and simplysupported double-T options
Advantages
Continuous
6.4.3.2
The simply supported system with flexible linking slabs can be constructed using falsework or an
erection girder. Use of an erection girder speeds up production and allows for a shorter
construction schedule, but there are no major differences in scheduling between this option and
building on falsework. Table 6.6 below compares the advantages and disadvantages of
constructing on falsework to those of construction using an erection girder. The major deciding
factor between these two options is whether the contractor has access to an affordable and
suitable erection girder. On very large-scale projects where many structures of the same span are
to be constructed, then it might make sense to construct an erection girder for this particular
application and its cost could be offset by the savings realised by a shorter construction schedule
and less traffic control.
122
Chapter 6
Comparison of Double-T and Conventional Systems
Advantages
Disadvantages
Advantages
Disadvantages
Segmental double-T
123
Chapter 6
Comparison of Double-T and Conventional Systems
124
Chapter 6
Comparison of Double-T and Conventional Systems
(a)
(b)
(c)
Figure 6.7 Visual comparison of (a) continuous, (b) simply-supported segmental
double-T, and (c) conventional options
125
Chapter 6
Comparison of Double-T and Conventional Systems
Both the options presented above, though, stand out when compared to a similar conventional
girder bridge with cast-in-place deck slab as shown in Figure 6.7c. Three main factors contribute
to this superiority:
1. The conventional precast girder option requires that all girders be supported and so
necessitates some sort of pier cap to extend the entire width of the deck at the supports
whereas the double-T option only needs to be supported under the webs and so the piers
do not need to extend the full width of the deck. Hiding away the visual element of this
pier makes the entire structure appear more slender because the span one sees is the entire
bridge length rather than two divided spans.
2. The outer girders of the conventional system cannot be placed very far from the edges of
the deck whereas the webs of the double-T system are tucked far in under the deck slab.
This allows a longer shadow to be cast on the webs than on the girders and so imparts
upon the double-T a higher visual slenderness.
3. There are many girders required for the conventional system whereas the double-T
system requires only two webs. This reduction in the number of elements significantly
reduces the amount of visual clutter under the deck.
These points are illustrated in Figure 6.8 on the following page.
126
Chapter 6
Comparison of Double-T and Conventional Systems
elements, but rather, having them post-tensioned by other companies. This change can be
facilitated by reducing the cost of new formwork as explained in Chapter 5.
Second, local contractors in Ontario will have to become familiar with post-tensioned concrete, a
material used in jurisdictions throughout the world. It will take some time for existing firms to
move into the province and local contractors to develop the proficiency with the system that will
allow them to bid competitively.
Third, owners, designers, and contractors will have to become comfortable with the use of
higher-strength concretes. Most bridges in Ontario are currently constructed with highperformance concretes with specified strengths no higher than 50 MPa.
6.8 Conclusions
The precast segmental double-T makes efficient use of concrete when compared to the
conventional cast-in-place deck slab on precast girders. It can be made more slender, using less
concrete and a comparable amount of prestressing steel. This can be accomplished for an initial
superstructure cost that is comparable to the conventional system. The double-T can take less
time to build than the conventional system. It also offers some aesthetic benefits. Despite all of
this, there are still several reasons that the system will not be adopted quickly in Ontario.
127
Chapter 6
Comparison of Double-T and Conventional Systems
(a)
(b)
Figure 6.8 Visual comparison of (a) double-T and (b) conventional precast girder options
128
Chapter 7
Conclusions
The precast segmental double-T with external, unbonded tendons is intrinsically more durable
than conventional systems. This is due to the fact that its deck slab (normally the component of
a bridge most attacked by deicing chemicals) is precast and transversely post-tensioned. Precast
concrete is generally more durable than cast-in-place concrete because of the controlled
environment in which it is cast. Also, transverse post-tensioning reduces cracking in the deck
slab, making it less penetrable.
This thesis advances the development of the precast segmental double-T presented in Li (2010)
and provides a body of knowledge necessary to facilitate the adoption of this system by
designers by addressing five associated key issues:
1. It validates the double-T design for a range of span lengths used in highway overpasses, and
2. It demonstrates that it is possible to reduce the systems sensitivity to post-tensioning losses.
Results of the parametric study presented in Chapter 3 show that the system can be used over a
range of spans (from 20 to 45 m) and with lower sensitivity to post-tensioning loss than reported
in previous literature.
129
Chapter 7
Conclusions
3. It presents designs using the precast segmental double-T system for multi-span bridges
without the use of expansion joints.
Designs presented in Chapter 4 show that there are two viable methods to make the system
multi-span without using expansion joints within the structure. It can be made as a series of
simply-supported spans connected by flexible linking slabs made of ultra high-performance
fibre-reinforced concrete, a material which can be produced from readily-available constituents
in Canada. It can also be made fully continuous over the supports.
4. It shows that the onerous technical requirements of conventional match casting can be
relaxed for short spans built using this method.
The segmental double-T does not need to be match cast to achieve adequate precision as shown
in Chapter 5 and so any precaster in Canada can construct segments using normal formwork
tolerances.
5. It shows that the system is competitive with conventional systems by comparing material use,
cost, scheduling, and aesthetic criteria.
As demonstrated in Chapter 6 through a comparison with data from existing conventional
bridges using cast-in-place deck slabs on precast girders, the segmental double-T can be built
more quickly than conventional systems, it uses concrete more efficiently, it can be built at a
price comparable to the average price of examples of the existing system, and is an elegant
alternative to conventional overpass bridges.
130
Bibliography
AGOM, 2009. AGOM Elastomeric Bridge Bearings. Ossona, Italy.
Atcin, P.-C., 1998. High-Performance Concrete. E & FN Spon.
Al-Taan, S., and J.R. Al-Feel, 1989. Prediction of crack width in fibrous reinforced concrete
members. Fibre Reinforced Cements and Concretes: Recent Developments; Cardiff; UK;
18-20 Sept.1989: 209-18.
Bagrianski, S., 2010. Geometry Control of Precast Segments: A Precise Alternative to MatchCasting. BASc dissertation. Department of Civil Engineering, University of Toronto.
Bickley, J.A. and D. Mitchell, 2001. A State-of-the-art Review of High Performance Concrete
Structures Built in Canada: 1990-2000. Toronto, Ontario.
Canadian Standards Association, 2006a. CAN/CSA-S6-06: Canadian Highway Bridge Design
Code. CSA, Mississauga, Ontario.
Canadian Standards Association, 2006b. S6.1-06: Commentary on CAN/CSA-S6-06, Canadian
Highway Bridge Design Code. CSA, Mississauga, Ontario.
Caner, A., and P. Zia, 1998. Behavior and design of link slabs for jointless bridge decks. PCI
Journal 43 (3): 68-80.
CEB-FIP, 2010. Draft Model Code for Concrete Structures. Comit Euro-International du Bton,
Paris.
Chen, W., and E.M. Lui, 2005. Handbook of Structural Engineering. 2nd ed. CRC Press.
Collins, M.P., and D. Mitchell, 1997. Prestressed Concrete Structures. Toronto: Response.
Departement des Travaux Publics du Canton de Vaud, 1989. Catalogue of le viaduc dOrbe for
Routes nationales suisses N9.
FHWA National Bridge Inventory, as of December, 2010. Federal Highway Administration,
Washington.
Fincher, H.E., 1983. Evaluation of rubber expansion joints for bridges. Rep. No. FHWA/IN/RTC83/1, Washington, D.C., 1516.
Galambos, T.V., R.T. Leon, C.W. French, M. Barker, and B. Dishongh, 1993. Inelastic Rating
Procedures for Steel Beam and Girder Bridges. NCHRP Report 352.
Gauvreau, P., 1993. Ultimate Limit States of Concrete Girders Prestressed with Unbonded
Tendons. Institute of Structural Engineering, Swiss Federal Institute of Technology,
Report No. 198. Basel: Birkhuser-Verlag.
Gauvreau, P., 2006. Bridges. Chapter 12 (pp. 195-240) of Post-tensioning Manual. 6th ed.
Phoenix: Post-Tensioning Institute.
Gergely, P., and L.A. Lutz, 1968. Maximum Crack Width in Reinforced Concrete Flexural
Members. Causes, Mechanisms, and Control of Cracking in Structures. SP-20,
American Concrete Institute, Detroit, Michigan, 87-117.
131
Habel, K., 2004. Structural behaviour of elements combining ultra-high performance fibre
reinforced concretes and reinforced concrete. Doctoral dissertation. Gnie Civil, cole
Polytechnique Fdrale de Lausanne, Switzerland.
Habel, K., J.P. Charron, S. Braike, R.D. Hooton, P. Gauvreau, and B. Massicotte, 2008. Ultrahigh performance fibre-reinforced concrete mix design in central Canada. Canadian
Journal of Civil Engineering. 35(2): 217-224.
Holden, A., and B. J. Sammler, 1999. Structural Design for the Stage. Focal Press, Boston.
Interactive Design Systems, 2005. <http://www.idssoft.com/solutions/products/geometrey.html> Match cast diagram (May, 2011)
Jenq, Y.S., and S.P. Shah, 1986. Crack propagation in fiber-reinforced concrete. Journal of
Structural Engineering 112 (1) (Jan.): 19-34.
Jungwirth, J., and A. Muttoni, 2004. Structural Behavior of Tension Members in UHPC. Swiss
Federal Institute of Technology (EPFL). Lausanne, Switzerland.
Kullaa, J., 1998. Micromechanics of multiple cracking. I. fibre analysis. Journal of Materials
Science (UK) 33 (16) (15 Aug.): 4213-24.
Lam, C., D. Lai, J. Au, L. Lim, W. Young, B. Tharmabala, 2008. Development of Flexible Link
Slab for Elimination of Existing Expansion Joints on Steel Girder Bridges, Report BO01-01, Bridge Office, Ministry of Transportation of Ontario, April 1, 2001.
Leonhardt, F., 1979. Vorlesungen uber Massivbau. Berlin: Springer-Verlag.
Leutbecher, T. and E. Fehling, 2009. Rissbildung und zugtragverhalten von mit fasern
verstrktem stahlbeton am beispiel ultrahochfesten betons. Beton- Und Stahlbetonbau
104 (6, pp. 357-367): June.
Li, Y.E., 2010. Bridge System with Precast Concrete Double-T Girder and External Unbonded
Post-tensioning. MASc dissertation. Department of Civil Engineering, University of
Toronto.
Menn, C., 1990. Prestressed Concrete Bridges. Translated from German and edited by P.
Gauvreau. Basel: Birkhuser Verlag.
Menn, C., 1991. An Approach to Bridge Design. Engineering Structures. 13 (Apr.):106-12.
Naaman, A.E., 2000. HPFRCCs: Properties and Applications in Repair and Rehabilitation, HighPerformance Fiber-Reinforced Concrete in Infrastructure Repair and Retrofit, ACI SP
185-1, Michigan.
Naaman, A.E., and K. Visalvanich, 1983. Modeling fracture in fiber reinforced concrete. Paper
presented at Proceedings of the 4th Engineering Mechanics Division Specialty
Conference: Recent Advances in Engineering Mechanics and their Impact on Civil
Engineering Practice.
Newhouse, C. D., 2005. Design and Behavior of Precast, Prestressed Girders Made Continuous
An Analytical and Experimental Study. Doctoral dissertation. Civil and Environmental
Engineering, Virginia Polytechnic Institute and State University.
Okeil, A.M., and A. ElSafty, 2005. Partial continuity in bridge girders with jointless decks.
Practice Periodical on Structural Design and Construction 10 (4) (November): 229-38.
132
Precast/Prestressed Concrete Institute, 2000. MNL 135-00. Tolerance Manual for Precast and
Prestressed Concrete Construction. PCI, USA.
Salonga, J.A., 2010. Innovative Systems for Arch Bridges Using Ultra High-Performance FibreReinforced Concrete. PhD dissertation. Department of Civil Engineering, University of
Toronto.
Schlaich, J., and H. Scheef, 1982. Concrete Box Girder Bridges. Structural Engineering
Documents, International Association for Bridge and Structural Engineering. Zurich.
Schlaich, J., K. Shfer, and M. Jennewein, 1987. Towards a Consistent Design of Structural
Concrete. PCI Journal. 32, 3: 74-150.
Straski, J., M. Korenek, 1986. Short span segmental bridges in Czechoslovakia. PCI Journal 31
(1) (Jan.Feb.): 106-32.
Stussi, B., 1958. Grundsatzliches zum Projekt, zur Ausfuhrung und zur Berechnung. In
Offentlichen Bauten des Kantons, Weinlandbrucke Andelfingen (32-47).
Susetyo, J., 2009. Fibre Reinforcement for Shrinkage Crack Control in Prestressed, Precast
Segmental Bridges. PhD dissertation. Department of Civil Engineering, University of
Toronto.
Thippeswamy, H.K., H.V.S. GangaRao, and J.M. Franco, 2002. Performance evaluation of
jointless bridges. Journal of Bridge Engineering 7 (5) (September/October): 276-89.
Walraven, J.C., 2009. High performance fiber reinforced concrete: Progress in knowledge and
design codes. Materials and Structures 42 (9) (Nov): 1247-60.
133