Fundamentals of Shipbuilding
Quality Procedures and Standards
New Building Surveys
Construction Monitoring Procedures
Electrical/control surveyors
Division of work:
Who does what, (London Office, Local P.A., Site Surveyor, Other LR
Offices) and Extant Instructions, Checklists, Reports, Flag state
authorisations.
Key Data
Special steel locations
- High Tensile, through thickness, forgings, castings
Welding Details
- Leg-Lengths, Throat, Thickness, Full and Partial Penetration, Spec
Techniques
Building Standards
Shipbuilding Quality Standard
IACS Shipbuilding and Repair Quality Standard
Tank Testing
Approved Tank Testing Plan
All Tank Boundaries to be tested to confirm that their design and
construction is satisfactory. All pressure gauges to be calibrated.
Air Leak Tests
The application of a protective coatings is not allowed prior
to test excluding the shop primer
Air pressure be raised to 0.2 bar for 1hour and then lowered
to 0.15 bar
Hydrostatic Strength Tests (Structural Testing)
Hose Testing: Max distance of 1.5m (not less than 2.0bar)
Fillet Weld Air Tests
Vacuum Leak Tests
IACS UR-S14 Testing Procedures for Watertight Compartments
IACS Recommendation No. 72 Confined Space Entry
Structural Testing
Materials
Forming
Block Surveys
Pre-erection Surveys
Dock Erection joints Surveys
Patrols of work in progress
Construction Monitoring Procedures
Deck house and Accommodation
Anchoring and Mooring Equipment
Other items
Materials
From stockyard to production, there needs to be clear identification
of different grade of plates and sections: Visible colour coding and
marking
Block Surveys
Pre-erection Survey
Pre-erection of fore
body section
Four individual units
brought together to
form one single
block
Lifting lugs will also
be removed after
erection
Pre - erection
of a very large
section of
main hull and
LPG tank
LR ShipRight Procedure
ShipRight (CM) assigned as a class notation
Materials
Alignment
Welding
Construction procedures
Objective
To ensure that special attention is given to critical joints
to avoid stress concentrations
Midship
Section Plan
showing location
of Critical Areas
Same reference
mark (100mm)
for hopper joints
alignment to
double bottom
girder
Another typical
example of a
Critical joint at
the connection
of the tank top
with the
longitudinal
bulkhead
transverse web
brackets
Typical complete
Deckhouse being
erected as single
unit.
Theses units are
often constructed
outside the
shipyard at a
specialist
contractor.
Other Items