Professional Documents
Culture Documents
CONTENTS:
1.
2.
3.
4.
5.
6.
7.
ATTACHMENTS:
PURPOSE
SCOPE
DEFINITIONS
RESPONSIBILITIES
INSTRUCTIONS
REFERENCES
ATTACHMENTS
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
Status
SS
Approved
Superseded
DOCUMENT HISTORY
IFR
REV.
NO.
REASON
FOR
ISSUE
28 Apr
2014
Date
PFC
CHANGES
STATUS
Project Procedures
Sign:
Sign:
Sign:
Sign:
Sign:
Sign:
PREPARED
BY
HILL QA/QC
REVEIWED
BY
HILL PM
APPROVED
BY
KCT Qatar
PRA-00002-PP-07-PRM-02 Rev.A
1. PURPOSE
The purpose of this procedure is to map-out the process of approvals and documentation
required to issue Construction Variation Order (CVO) to Contractors due to Change Requests
initiated by the Employer, Hill (as the Project Management Consultant), the Supervision
Consultant, or Contractor in connection with the design and construction and/or installation
works on the IFRANE PALACE Project.
2. SCOPE
This procedure applies to all construction contracts initiated by the Employer for construction
and/or installation works on the IFRANE PALACE Project.
This procedure applies to all construction contracts where the Contractors scope of works
requires changing, including drawing changes, specification changes and changes to the
method and sequence of working. It shall also apply to the expenditure of Provisional Sums.
Changes as a result of Confirmation of Verbal Instructions (CVIs) and Requests for Information
(RFIs) having a time and/or cost impact shall be subject to Employers Approval via this
procedure.
3. DEFINITIONS
OWNER
INITIATOR
PARTICIPANT
SIGNATORY
APPROVER
INFORMED
EMPLOYERS
REPRESENTATIVE
HILL PROJECT DIRECTOR
HILL CONTRACTS MANAGER
HILL PROJECT CONTROLS
MANAGER
HILL DESIGN MANAGER /
CONSTRUCTION MANAGER
DESIGN CONSULTANT
SUPERVISION CONSULTANT
(ENGINEER)
COST CONSULTANT
CONTRACTOR
PROCESS
OWNER
The person in Hill or the other company responsible for ensuring the procedure
is implemented, maintained and controlled
PARTICIPANT
INITIATOR
/
ORIGINATOR
The person in Hill or the other company who starts the process
APPROVER
The person holding final authority for signature for approval of the product of
the process
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
INFORMED
A person who receives a copy of the information and is not otherwise involved
in the process. All the above parties are deemed to be informed.
4. RESPONSIBILITIES
Employers
Representative
Hill Contracts
Manager
Cost Consultant
Supervision
Consultant
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
5. INSTRUCTIONS
Action by
GENERAL
All communication between PMC, Supervision Consultant and the
Contractor relevant to this procedure, shall follow the established
Project Communication Plan and the approved Project Management
Plan (PMP).
5.1
5.1.2
Hill Project
On receipt of the Letter of Instruction from the Employers
Manager,
Representative, Hill Project Manager shall forward copy of the
Hill Contracts Mgr
Letter to Hill Contracts Manager, Hill Design Manager / Hill Design Mgr /
Construction Manager, Hill Project Controls Manager and Cost Construction Mgr,
Hill Project
Consultant. Hill Project Manager shall arrange a meeting for
attendance by the Employer, Hill Contracts Manager, Hill Controls Manager,
Consultant,
Design Manager / Construction Manager, Hill Project Controls CostEmployer
Manager and Cost Consultant to discuss the Construction
Variation.
5.1.3
5.1.4
5.1.5
5.1.6
Project Procedures
Employers Rep.,
Hill Project
Manager,
Contracts Mgr,
PCM
Design Mgr /
Construction Mgr,
Cost Consultant
Employer
Hill Contracts
Manager,
Hill Design
Manager,
Hill Project
Manager,
Employer
Employers Rep.
PRA-00002-PP-07-PRM-02 Rev.A
Hill Project
Manager,
Hill Contracts Mgr
5.1.7
Design
Consultant
5.1.8
5.1.9
5.1.10 After receiving the completed CVPR from the Contractor via
Hill Project Manager / Document Controller, Hill Contracts
Manager in coordination with the Cost Consultant, Hill Project
Controls Manager and Hill Design Manager / Construction
Manager shall review the completed CVPR with
documentation. Hill, Cost Consultant, Supervision Consultant
and the Employers Representative shall meet with the
Contractor if necessary to reconcile any differences and
negotiate an agreed adjustment.
5.1.11 After conclusion of meetings and negotiations, Hill Contracts
Manager shall prepare the draft Construction Variation Order
(CVO) (Form PRA-0002-PP-07-05-FM), sign and obtain
signature from Cost Consultant, Hill Project Manager and
Contractor via the Document Controller.
Hill Contracts
Manager shall log the CVO using CVO Log form Ref. PRA0002-PP-07-06-LG.
Contractor,
Hill Project
Manager /
Document
Controller
Hill Contracts
Manager,
Hill Document
Controller
Hill Project
Manager
Employers Rep.,
Employer SM
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Employers Rep.
5.1.15 Upon receipt, Hill Project Manager shall issue the approved
CVO to the Contractor with copy to Hill Contracts Manager,
Cost Consultant and Supervision Consultant.
Hill Project
Manager
5.1.16 Hill Contracts Manager shall update the variations log (Form
Hill Contracts
Manager,
PRA-0002-PP-07-06-FM-LG)
and
variations
summary.
Hill Project
Summary of variations is to be provided to Hill Project Controls
Manager,
Manager for issue via Hill Project Manager to Employer in the Controls
Hill Project
Monthly Report.
Manager
5.2
5.2.2
Hill Contracts
Upon receiving the copy of SWI, Hill Contracts Manager and
Manager,
Cost Consultant shall prepare initial estimate of cost and time
Hill Project
(with assistance from Hill Project Controls Manager) and Controls Manager,
forward it together with the SWI to Hill Project Manager for
Hill Project
Manager,
review and signature. Hill Project Manager shall review and
forward the SWI together with attached estimate to Employer Cost Consultant
for approval to proceed.
5.2.3
Employers Rep.
5.2.4
Hill Project
Manager
5.2.5
Contractor,
Supervision
Consultant,
Hill Project
Manager /
Document
Controller
Project Procedures
Supervision
Consultant
PRA-00002-PP-07-PRM-02 Rev.A
5.2.6
Hill Project
Manager,
Hill Contracts Mgr
Hill PCM,
Cost Consultant
5.2.7
5.2.8
5.2.9
Employers Rep.,
Employer SM
Employers
Employers Rep.
5.2.12 Hill Project Manager shall issue the approved CVO to the
Contractor with copy to Hill Contracts Manager, Cost
Consultant and Supervision Consultant.
Hill Project
Manager
Employers Rep.
5.2.14 Hill Contracts Manager shall update the variations log (Form
Hill Project
PRA-0002-PP-07-06-FM-LG)
and
variations
summary. Controls Manager,
Hill Project
Summary of variations is to be provided to Hill Project Controls
Manager
Manager for issue via Hill Project Manager to Employer in the
Monthly Report.
5.3
PRA-00002-PP-07-PRM-02 Rev.A
Contractor
Supervision
Consultant,
Hill Project
Manager /
Document
Controller
Hill Contracts
Manager,
Hill PM,
Hill Design Mgr,
Construction Mgr,
Project Cont. Mgr,
Design
Consultant,
Employer
5.3.2
5.3.3
Hill Contracts Manager shall convene a meeting with Hill Contracts Mgr
Employer's Representatives with participation of Hill Project Cost Consultant,
Hill Project
Manager, Hill Design Manager / Construction Manager, Hill Controls Manager,
Project Controls Manager, Cost Consultant and Design Hill Design Mgr /
Construction Mgr,
Consultant (where applicable) to discuss VO proposal.
Hill Project
Manager
5.3.4
5.3.5
5.3.6
Project Procedures
Employers Rep.,
Hill Project
Manager
Hill Contracts
Manager,
Hill Project
Manager /
Hill Document
Controller
Contractor
Hill Contracts
Manager,
Hill PCM,
Hill Design Mgr /
PRA-00002-PP-07-PRM-02 Rev.A
5.3.7
5.3.8
5.3.9
Construction Mgr.
Hill Project
Manager
Hill Contracts
Manager,
Hill PM,
Hill PCM,
Hill Design Mgr.,
Supervision
Consultant,
Design
Consultant,
Employers Rep.
Hill Contracts
Manager,
Hill Project
Manager,
Cost Consultant,
Contractor
Hill Project
Manager
Employers Rep.,
Employer SM
Employer PD,
Hill Project
Manager
Project Procedures
Employer
Hill Contracts
Manager,
Hill Project
Controls Manager,
Hill Project
Manager
PRA-00002-PP-07-PRM-02 Rev.A
6. REFERENCES
1) KCT-IMS-CM-3707 Rev.0 , Project Claims, Variations and Disputed Items
2) Hill Intl PRA-00002-PP-17-PRM-02, Claims, Change & Extension of Time Procedure
7. ATTACHMENTS
7.1 Employer Driven Variations to Contractors Process Map
7.2 Variations by SWI Process Map
7.3 Variation by Contractor Request Process Map
7.4 Variation Proposal Form
7.5 Variation Order Form
7.6 Variation Order Log
7.7 Site Work Instruction (SWI) Form
7.8 PMC Request for Variation Order (PMRVO) Form
7.9 Contractor's Request for Variation Order (CRVO) Form
7.10 Project Managers Instruction (PMI) Form
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
CC
CONS
ENG
CONT
Contractor
HILL
EMPLOYER
Design Consultant
NOTE: This is a generic procedure and is to be adapted to comply with the project
specific requirements
Cost Consultant
X X
Decide
Attend meeting
Review/Assist
Issue
Optional
R/
A
Contracts Manager
Receive Original/
Copy
Start
Project Director /
Document Controller
O/
C
Perform
Employer
Representative
Employer
Senior Management (SM)
KEY
Input / Output
Letter of
Instruction
Proposed RFQ +
attachments
(rough estimates)
Reject
Technical
Documents
Construction
Variation
Proposal Request
Director for issue to Contractor with request for time and cost proposal.
Copy is also forwarded by Hill to the Supervision Consultant.
9. Contractor prepares time & cost evaluation with completed CVPR form
P
10. Hill, Cost Consultant and Employer analyse the proposal and meet with
Construction
Variation
Proposal Request
Draft CVO
Hill Project Director and Contractor via Document Controller. Hill Contracts
Manager logs the CVO on CVO Log form (Ref.CCC-NNN-PP-07-06-LG).
Memo
Approved CVO
C
16. Hill Contracts Manager updates the variations log
(Form CCC-NNN-PP-07-06-LG) and variations summary. Summary to be
issued to Employer in the Monthly Report.
P
C
I
Document No: CCC-NNN-PP-07-01-PM Rev.1
Revision Date: 12-Oct-2009
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
CC
Attend meeting
Issue
Optional
Cost Consultant
Decide
Review/Assist
X X
R/
A
Contracts Manager
Receive Original/
Copy
Start
Project Director /
Document Controller
O/
C
Perform
Employer's
Representative
Employer
Senior Management
KEY
SWI Method To be used for Site Works Instruction for items which are
ENG
CONT
Input / Output
Contractor
EMPLOYER
of cost and time (with assistance from Hill Project Controls Manager)
and forwards together with Site Works Instruction (SWI) using Form
SWI
Rejected,
SWI Aborted
5. Contractor carries out the work and prepares time & cost estimates
P
forwards to Hill.
Draft CVO
P
C
Memo
Approved CVO
I
C
Document No: CCC-NNN-PP-07-03-PM Rev.1
Revision Date: 12-Oct-2009
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
X X
Attend meeting
Issue
Optional
CONS
When FIDIC rules applies, Contractor's Variations request arises if an Instruction from the
Supervision Consultant Engineer constitutes a Variation as per Clause 3.3 of the Conditions
of Contract for Construction, FIDIC 1999
CONT
Output
Contractor
Decide
SC
Design Consultant
CC
Receive Original/
Copy
Review/Assist
Design Manager
R/
A
Contracts Manager
S Start
O/
C
Perform
Employer's
Senior Management
Employer's Representative
KEY
PMC (Hill)
EMPLOYER
Cost Consultant
NOTE: This is a generic procedure and is to be adapted to comply with the project specific
requirements
for the reasons stated above in items a or b, to Supervision Consultant Eng'r and PMC (Hill)
2. On receipt, Supervision Consultant reviews and assesses request and forwards to
Contractor
Variation
Request
Reject
Hill Contracts Manager and Cost Consultant via Hill Document Controller.
A
C
3. Hill convenes a meeting with The Employer's Representative, Design Consultant and the
along with completed form CCC-NNN-PP-07-08-FM (PMC Request for Variation Order) and
R
Reject
Construction
Variation Proposal
Request (CVPR)
O
P
Completed
CVPR
+ documents
R
9. Hill meets with Contractor, Supervision Consultant, Cost Consultant, Design Consultant and
Employer to finalise.
10. Hill Contracts Manager draft Construction Variation Order (Form CCC-NNN-PP-07-05-FM),
signs & obtains signature from Hill Project Director and Contractor via Document Controller.
11. Hill Project Director forwards signed draft Construction Variation Order to Employer.
X
Draft CVO
C
12. Employer internal process for signature
NOTE: Employer Internal decision to be within contractual time restraints
D
Memo
13. After signature, the Employer's Representative returns the CVO to Hill, and Hill Project
Director issues to the Contractor with copy to Hill Contracts Manager, Cost Consultant,
Approved CVO
R
C
14. Employer's Representative arranges for Employer Project Controls Manager to file memo.
15. Hill Contracts Manager updates the variations log and variations summary (Form
CCC-NNN-PP-07-06-FM-LG). Summary to be issued to Employer in the Monthly Report.
See related process map CCC-NNN-PP-07-01-PM for Variations to Designers
P
P
I
C
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A
Project Procedures
PRA-00002-PP-07-PRM-02 Rev.A