Professional Documents
Culture Documents
02-W019
Note
This mechanical maintenance manual is intended to provide the Paiton Expansion Project
mechanical maintenance personnel with the basic understanding required to perform preventive,
routine, corrective and overhaul maintenance activities on the subject equipment.
No part of this document may be reproduced for use by parties other than Mitsubishi Heavy
Industries, Ltd. and Paiton Expansion Project.
Induced
Draft
Fan
Maintenance
General
Specifications
Preventive Maintenance
Corrective Maintenance
Recommended Lubrication
Appendixes
Contents
Contents
Revision Record i
Important Informationii
Warranty v
Limitation of Liabilityvii
Copyrightix
Personnel to whom the Manual is Directed x
Contact Addressxi
Abbreviations xii
List of Vendor Manuals xiii
Arrangement of the System Maintenance Manualxiv
Chapter1
Safety ____________________________
1.1
1.2
1.2.2
Symbol 1-4
1.2.3
1.2.4
1.3
1.4
1.4.2
MM-M02.02
Contents
Chapter1
1.5
1.5.3
Earthquake 1-22
1.5.4
1.6
Chapter2
General ___________________________
2.1
Purpose 2-1
2.2
References 2-1
2.3
2.4
Components 2-7
2.4.1
Casing 2-7
2.4.2
2.4.3
2.4.4
2.4.5
2.4.6
Coupling 2-12
2.4.7
Chapter3
Specifications _____________________
Chapter4
4.1
Prerequisites 4-1
4.2
MM-M02.02
Rev.003
4.1.1
Scheduling 4-1
4.1.2
4.1.3
4.1.4
Preparation 4-3
4.2.2
Contents
Chapter4
4.3
Preparation 4-11
4.3.2
Chapter5
5.1
5.2
5.3
5.4
5.5
Chapter6
6.1
Prerequisites 6-1
6.2
Preparation 6-2
6.3
Troubleshooting 6-2
Chapter7
Appendixes
Torque Chart A-1
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H
MM-M02.02
Rev.003
Appendix A
Contents
MM-M02.02
Rev.003
List of Figures
Figure1-1
Figure 1-2
Figure 2-1
Figure 2-2
Figure 2-3
Figure 2-4
Figure 2-5
Figure 2-6
Figure 2-7
Figure 2-8-1
Figure 2-8-2
Figure 2-9
Figure 2-10
Figure 2-11
Figure 3-1
Figure 4-1
Figure 5-1A
Figure 5-1B
Figure 5-2
Figure 5-3
Figure 5-4
Figure 5-5
Figure 5-6
Figure 5-7
Figure 5-8
Figure E-1
Figure E-2
Figure E-3
Figure E-4
Figure E-5
Contents
Figure E-7
Figure E-8
Figure E-9
Figure F-1
Figure F-2
MM-M02.02
Rev.003
Figure E-6
Contents
List of Tables
Risk Assessment Standard 1-8
Table 3-1
Table 3-2
Table 3-3
Table 3-4
Table 4-1
Table 4-2
Table 6-1
Table 7-1
Table A-1
Table B-1
Table B-2
Table H-1
Table H-2
Table H-3
Table H-4
Table H-5
Table H-6
Table H-7
Table H-8
MM-M02.02
Rev.003
Table 1-1
Revision Record
MM-M02.02
Rev.003
Page Number
Description of Revision
Revision Issue
Date
Date Revised
6. Jun. 2011
6. Jun. 2011
2-14~2-16
6. Jun. 2011
6. Jun. 2011
2-17
6. Jun. 2011
6. Jun. 2011
3-2
Corrected error
6. Jun. 2011
6. Jun. 2011
3-4
6. Jun. 2011
6. Jun. 2011
4-15~4-19
6. Jun. 2011
6. Jun. 2011
Appendix-B
6. Jun. 2011
6. Jun. 2011
Appendix-H
6. Jun. 2011
6. Jun. 2011
E-4
4-10,4-20,G-17,
G-143~G-151
G-19~G-21
G-28, G-29
G-143~G-151
5-13
E-4
Pages
Inserted
Important Information
Purpose of the Plant Usage
This plant is designed to generate electric power of 815 MW by the steam turbine
generator.
The plant is only used for the electric power generation purpose that supports stable
and reliable electric power supply to the power grid and supplying steam for auxiliary
equipment in the power station.
General
1.
To satisfy the purpose mentioned above the following points must be strictly
observed,
a)
b)
c)
MM-M02.02
Rev.003
3.
Disposal from the power station must be treated to satisfy the local
regulations.
4.
ii
5.
Use or copying of the whole or part of any information provided by MHI for
any purpose other than operation and maintenance of this plant without
written consent is strictly prohibited.
The operator and maintainer must have knowledge about the equipment to
maintain good operating condition and to avoid danger when using the
equipment and systems.
2.
3.
4.
The customer must train the operators and maintainers to act actively and to
prevent the occurrence of an accident by using their knowledge of the power
plant.
5.
The customer must make the operators and maintainers understand that the
most important purpose of safety control is to protect all personnel from
accidents and also to maintain operation of the plant without troubles.
6.
MM-M02.02
Rev.003
7.
a)
b)
c)
MHI can not forecast all possible dangers existing in the plant such as
danger due to human error and/or dangers caused by the operating
environment.
As this manual and the alert label cannot cover all of the dangers, the
operators and maintainers have to pay their full attention to all general safety
notices.
iii
8.
MHI can not be responsible for damages and injury caused by neglecting the
notices in this manual, and other necessary general notices.
2.
3.
4.
Some figures in this manual include internal parts of the equipment which
may not be obvious, when looking at the completed equipment drawing.
5.
6.
This manual is intended for the use by the operators and maintainers and it
must be accessible to them at all times.
7.
If the Customer needs more detailed information, please contact MHI local
office or MHIs official agent.
MM-M02.02
Rev.003
1.
iv
Warranty
The provisions set forth in this section are in addition to all liability and
warranty disclaimers and limitations set forth in the Contract, whether arising
under law or from course of performance, course of dealing, or usage of trade.
For the detailed terms and conditions of the warranty concerning the Works
and Project, refer to the Contract.
In addition to the foregoing, the Contract Warranties will NOT cover any of the
following Accidents and Damages:
Accidents and Damages caused by any deviation from the Rules and
Requirements;
MM-M02.02
Rev.003
Accidents and Damages occurring after the term of the warranty has expired;
Accidents and Damages due to handling, storage and/ or use of the Plant
under severe conditions or in an environment that does not meet the design
specification conditions.
MM-M02.02
Rev.003
vi
Limitation of Liability
Use and Disposal
The contents of this manual are subject to change without prior notice and
without any obligation or liability to MHI.
Use of the Plant must be limited to the use specified by MHI, including without
limitation, use of the Plant in accordance with the Contract, this manual, all
Safety Manuals, all applicable laws and regulations, and any other instructions,
if any, provided by MHI. The Plant components, parts, systems and other
equipment (collectively, Equipment) must be appropriately disposed of in
accordance with the Contract, this manual, all Safety Manuals, all applicable
laws and regulations, and any other instructions, if any, provided by MHI.
MM-M02.02
Rev.003
The Customers personnel must read, understand and abide by all documents
provided by MHI, including without limitation, the operation and maintenance
manuals, safety manuals, and instruction manuals (collectively, Safety
Manuals) and must have received all required and/or necessary safety
training prior to the start of their work. Persons who have not received such
safety training are not permitted to work on the installed Plant. This initial
training, however, is merely the minimum requirements prior to allowing any
personnel to work on the installed Plant. The Customer must, on a continual
and regular schedule, give up-to-date training to its personnel on safety
requirements, provide testing or other methods to confirm their understanding
of the safety training, and confirm that they have the physical and mental
capability to perform their respective roles. The Customers obligation for
safety training and personnel supervision is an ongoing obligation and must
be continuously performed and kept current throughout the operation of the
Plant. Accidents, partial or total failure of the Plant, damage to personnel or
property, loss, injuries, and other liability (collectively, Liability) caused by
inadequate safety training or the Customers personnels failure to abide by
the documents provided by MHI are expressly excluded from the coverage of
any warranty provided by MHI and are the sole and exclusive responsibility of
the Customer.
vii
MHI will NOT be liable for any Liability caused by modification or changes
made in Plant-related documents (including any Safety Manual) by anyone
other than MHI.
MHI will NOT be liable for any Liability resulting from any abuse, misuse,
misapplication of the Equipment supplied by MHI.
MHI will NOT be liable for any Liability caused by an act by the Customer in
violation of the Contract, this manual, any applicable law or regulation, or any
Safety Manual or any other instruction provided by MHI, including without
limitation, a change of the installation environment or the removal and
installation of any Equipment in a location different to that originally selected
by MHI.
MHI will NOT be liable for any Liability caused by a defect, imperfection, or
fault, in material or Equipment that was used during a repair, even when such
a repair was performed by or under an instruction given by MHI.
MM-M02.02
Rev.003
viii
Copyright
COPYRIGHT 2008, MITSUBISHI HEAVY INDUSTRIES, LTD. ALL RIGHTS RESERVED.
ANY REPRODUCTION IS EXPRESSLY PROHIBITED.
All of the content contained in this manual is protected by Japanese, International
and/or United States copyright laws.
All copyright, trade secrets, and other proprietary and intellectual property rights in
the documents provided by Mitsubishi Heavy Industries, Ltd.(MHI) (including
safety-and-instruction manuals) are at all times owned and reserved by MHI. Subject
to your compliance with the restrictions set forth below, MHI grants to you a limited,
non-exclusive license in the copyright for the sole purpose of allowing you to use,
operate, maintain and inspect the Plant.
Use, copying, other reproduction of the whole or part of the documents provided by
MHI (including safety-and-instruction manuals) for any purpose other than the
purpose described above without MHIs prior written consent is strictly prohibited.
Except as specifically set forth above, no right, title or license to the documents
provided by MHI, whether arising from contract, implication, estoppel or otherwise, is
being granted or otherwise transferred.
MM-M02.02
Rev.003
ix
Operator
Maintainer
MM-M02.02
Rev.003
Maintainers are permitted to perform maintenance on the plant. They will also
perform troubleshooting routine and periodical inspections of the installed
equipment. The maintainer will also work under the supervision of MHIs
supervisors during on-the-job training and annual maintenance and overhaul work
if MHIs supervisors are requested to witness periodical inspections, etc.
Maintainers MUST have attended the training programme initially provided by MHI
and subsequently by the Customer, and they must have obtained the necessary
knowledge and maintenance skills to understand the characteristics of their tasks
before actually starting their work.
Contact Address
For any question or any clarification required, please do not hesitate to contact MHI
through the following address (es).
MM-M02.02
Rev.003
xi
Abbreviations
Abb.
Expanded Form
Abb.
Expanded Form
DCS
BMCR
IDF
CCCW
I&C
CCW
Counter-Clock Wise
MB
Moving Blade
DE
Drive End
NDE
Non-Drive End
DP
Differential Pressure
NOL
DTI
PPE
MM-M02.02
Rev.003
ASTM
xii
Manufacturer
MM-M02.02
Rev.003
Item No.
xiii
Chapter 1
Describes health and safety issues during maintenance, disassembly and reassembly
of the Induced Draft Fan.
Chapter 2
Describes the construction, purpose, and function of the Induced Draft Fan and the
associated parts.
Chapter 3
Describes the Induced Draft Fan parts, using the relevant Data Sheets.
Chapter 4
Describes the Preventive, Routine, and Outage Maintenance.
Chapter 5
Describes the disassembly and reassembly procedures, necessary to obtain access
to internal parts for inspection and repair during Induced Draft Fan overhaul.
Chapter 6
Describes the corrective maintenance procedures to be followed to investigate,
identify and remedy defects occurring during operation.
Chapter 7
MM-M02.02
Rev.003
Includes Torque Chart, Spare Parts, Special Tools and Vendor Drawings/Documents
xiv
Chapter 1
Safety
C h a p t er
1 S af et y
1.1
MM-M02.02
Rev.003
Considering the above fact, a constant monitoring of the fan, its oil unit and seal
air fan is necessary. The fan must be closely watched for any oil leakage to
avoid an unsafe condition.
During normal conditions, all the standard safety precautions are to be followed.
During outage maintenance, proper safety procedures are to be followed by the
operating personnel who will purge the system before issuing a Permit to Work
to the Maintenance Staff.
1-1
Chapter 1
1.2
Safety
Warnings Description
Safety of personnel working in the power plant is the most important matter. And
all kinds of consideration to avoid dangerous conditions are studied and applied
to the design of the power plant. However, certain risks are unavoidable due to
the nature of the plant.
This manual classifies the severity and hazard level of such risks by two
categories, DANGER and CAUTION. Read and understand the indications
thoroughly before operation or maintenance of the plant.
The contents of wordings, DANGER and CAUTION are described as follows;
Kinds
Meaning of Warnings
DANGER indicates an imminently hazardous situation
during use of the Induced Draft Fan, which, if not
avoided, could result in death or serious injury, or
serious damage to the property or environment.
CAUTION indicates a potentially hazardous situation
CAUTION
This manual also uses the following indicators in addition to the hazard level
indications described so far.
Kinds
Meaning of Warnings
IMPORTANT describes the particular information or
items that personnel must know during operation and
IMPORTANT
MM-M02.02
Rev.003
Notice
1-2
Chapter 1
Safety
Minor Injury
This term describes injuries, which do not require hospitalization or
prolonged attention at a hospital (injuries other than the serious
injuries described above).
MM-M02.02
Rev.003
This term describes damage, which does not require any suspension
of productive activity due to restoration of the damaged property.
1-3
Chapter 1
Safety
1.2.2 Symbols
In this manual, the following symbols are added for easy understanding
of the contents of warnings and are found next to DANGER,
CAUTION and other indications.
These symbols are in compliance with ISO 3684.
Symbol
Description
This symbol indicates the possible presence of high voltage, and
warns of a hazard which may result in system shock, burn or
death by electric shock if safety precautions are neglected or the
system is handled incorrectly.
This symbol indicates a movable section that is inside a safety
cover or is exposed.
Movable parts may inflict laceration or bone fracture to body parts
such as a hand by pinching the hand and/or clothing.
This symbol indicates the presence of parts the surface of which
could be hot, and may cause a burn if handled incorrectly.
This symbol indicates that care should be taken where you place
your feet when moving around the area.
Risk of injury by tripping is present near this symbol due to
factors such as a location with an unstable surface, or
obstructions such as scaffolding, temporary pipe lines, or other
protrusions.
This symbol indicates the possible presence of gas(es) harmful or
asphyxiant to personnel.
Be sure to ventilate fully before work commences.
This symbol indicates caution against the handling of a heavy
object or working in an abnormal position.
Do not work in an abnormal posture which may damage your back
or waist.
This symbol indicates prohibited items or actions during the
MM-M02.02
Rev.003
1-4
Chapter 1
1.2.2
Safety
Symbol
Description
This symbol indicates that personnel must not touch since the
surface is hot.
Do NOT enter any area where this symbol is displayed.
IMPORTANT
Personnel are requested to confirm the location of, and to read, and
thoroughly understand the contents of all hazard warning labels
applied to the Induced Draft Fan. If any of the hazard warning labels
Rev.003
MM-M02.02
1-5
Chapter 1
WARNING
Safety
DO NOT COME
NEAR TO SHAFT
EXPOSED ZONE
WHEN IN
OPERATION
PINCH POINT
STEEP
DROP
DO NOT
ENTER
DO NOT
TOUCH
DO NOT
TOUCH
MM-M02.02
Rev.003
TB0001_A
FIGURE 1-1
Induced Draft Fan
Mitsubishi
1-6
Chapter 1
1.2.4
Safety
Hazard Area
IMPORTANT
Only trained maintainers or operators are allowed to enter the
maintenance work area. Entry to the area by personnel untrained
could cause not only injury but also serious damage to the Induced
MM-M02.02
Rev.003
Draft Fan.
1-7
Chapter 1
1.3
Safety
Category
Safety
Catastrophic
II
Critical
III
Marginal
VI
Negligible
TABLE 1-1
- Death
- Serious Injury
- Minor Injury
(with
hospitalization)
- Minor Injury
(without
hospitalization)
Description
Category
Detailed
(A)
Frequent
Repeating occurrence
1 time / 1 or 2 months
(B)
Probable
1 time / 1 year
(C)
Occasional
Could occur
1 time / 5 years
(D)
Remote
1 time / 10 years
(E)
Improbable
Practically Impossible
TABLE 1-1
Hazard
Categories
Frequency
of Occurrence
Rev.003
Environment
Definition
MM-M02.02
Health
II
III
VI
Catastrophic
Critical
Marginal
Negligible
(A)
Frequent
13
(B)
Probable
16
(C)
Occasional
11
18
(D)
Remote
10
14
19
(E)
Improbable
12
15
17
20
1-8
Chapter 1
Safety
DANGER ZONE
(Contains the high temperature
& high pressure medium such
as steam, water, air and gas,
coal, oil etc)
MM-M02.02
Rev.003
WORKING FLOOR
MPTD-3-0536
FIGURE 1-2
Chapter 1
1.4
Safety
Safety Measures
1.4.1 Work Permit System (Lockout / Tagout)
Work permit system is applied when equipment is shutdown for
maintenance work, to complete the maintenance work under a safe
condition. The outline of the work permit system is as follows:
(1)
(2)
The Shift Charge Engineer passes the work permit form to the
operator to study and decide the isolation method from the line in
operation on the mechanical and electrical view point and then
report to the Shift Charge Engineer with his comments on the
hazard conditions for the work.
(3)
(4)
The operators will open the breaker and set the valves to the
specified condition, they will drain and vent the equipment to be
worked on, and the breaker and the valves are then locked. The
operators return the work permit to the Shift Charge Engineer.
(5)
The Shift Charge Engineer checks the isolation and will issue the
signed work permit to the Maintenance Engineer, or his
representative.
(6)
(7)
(8)
The Shift Charge Engineer will then send operators to release the
locks and return to the original situation.
(9)
The operators check the situation and report that the system is
now back to the normal condition when signing off the work
permit.
Rev.003
(10) The Shift Charge Engineer makes sure that the work under the
permit is completed and files details in the log book.
MM-M02.02
The work permit system is to clarify responsibility for the works on each
step and to ensure that the work is performed safely.
1-10
Chapter 1
Safety
Make sure that breaker for the motor is opened when you are
required to remove the cover.
1.4.2.2
MM-M02.02
Rev.003
1-11
Chapter 1
1.4.2.3
Safety
CAUTION
Wear suitable working clothing including gloves, to avoid
direct contact to hot spots in the plant.
Clinkers in the boiler bottom are often very hot inside even
though they look cool on the outer surface.
All exhaust pipes of the safety valves and the exhaust pipe of
the boiler flush pipe are not insulated.
MM-M02.02
Rev.003
1-12
Chapter 1
1.4.2.4
Safety
Be well aware of the steam. The steam could leak from the
water system containing water at 100C or higher even if it is
a low pressure type water system.
If not avoided, the steam or vapor can enter the inside of your
working wear through the small gap between the body and
the clothing.
Rev.003
MM-M02.02
CAUTION
Oil leaks make the area slippery and people are advised to
move around these areas carefully.
1-13
Chapter 1
1.4.2.6
Safety
IMPORTANT
Precaution against chemicals:
Disposal:
Emergency response:
1.4.2.7
MM-M02.02
Rev.003
IMPORTANT
1-14
Chapter 1
1.4.2.7
Safety
IMPORTANT
Emergency response:
1.4.2.8
MM-M02.02
Rev.003
1-15
Chapter 1
1.4.2.9
Safety
CAUTION
Do NOT attempt to move or lift equipment in an abnormal
CAUTION
Use leather gloves when handling parts with sharp edges.
CAUTION
Do NOT permit anyone to stand below any item being lifted
occur.
A forklift is often used to transfer small machines. Check fork
MM-M02.02
Rev.003
1-16
Chapter 1
Safety
CAUTION
A crane is often used to transfer heavy parts. Check for any
possible risks which could occur during hoisting and
transportation before operating the crane.
Check of the equipment:
Check the crane, the crane hook and all related items before
use. Use wire ropes which can withstand the weight of the parts
multiplied by a safety factor.
Inspect the shackles, eyebolts, jigs and wire ropes provided for
Hoisting method:
Hoist the part parallel to the ground while paying attention to
hoisting points.
Unpacking:
Do NOT unpack any part until it is located in the designated
location.
Rev.003
Protection of machine:
MM-M02.02
1-17
Chapter 1
1.4.2.13
a)
Safety
Disposal
Water disposal including oily drain
The water is disposed to the plant drain system. The water
must be carefully disposed according to the materials
contained in the water. The water drain system is
separated into three categories that are rain water,
chemical water and oily water.
The waste waters are treated and then discharged into the
public drain system.
b)
Chemical disposal
Chemicals must be handled following the instruction of the
MSDS and disposed to the chemical drain system.
c)
MM-M02.02
Rev.003
1-18
Chapter 1
1.5
Safety
Emergency Measure
1.5.1 Evacuation on Emergency Case
1.5.1.1
Evacuation Route
Following items are considered on design and installation
of emergency evacuation.
IMPORTANT
Each building installed in the plant is provided with at least two
tools.
1.5.1.2
IMPORTANT
It is recommended to keep a stretcher available for
MM-M02.02
Rev.003
1-19
Chapter 1
1.5.1.3
Safety
IMPORTANT
An evacuation place for personnel to gather in after evacuation
MM-M02.02
Rev.003
1-20
Chapter 1
Safety
IMPORTANT
Clearly show the location of fire alarm push button and fire
discover a fire.
Start fire fighting using the fire extinguisher located near the
fire site.
The operators must check the plant is ready for trip, and wait
to the fire fighting team when they arrive at the fire site and the
operators must wait for instruction from the Shift Charge
Engineer. All other personnel must immediately start
evacuation.
If unit trip is decided, the operator must trip the plant manually.
The operators must evacuate from the power house according
MM-M02.02
Rev.003
1-21
Chapter 1
Safety
1.5.3 Earthquake
In the case of an earthquake, the shift charge engineer or operator
must judge whether the unit trip is necessary according to the intensity
of the earthquake, and immediately trip the unit manually. If the unit is
tripped, all equipment must be carefully checked on its operation status
and tripped if abnormal phenomena are found.
In the local area, mechanical and/or thermal shocks may be given to
the equipment, piping, instruments and electrical panels. Be sure to
observe the following when completing the inspection.
fire does start, make sure that CO2 fire fighting system is properly
operated.
Check the position of boiler seismic stopper. Since the boiler
CAUTION
Check the piping and equipment for breaking and the dropping of
Rev.003
MM-M02.02
(hydrogen gas, oxygen gas, coal, fuel oil, etc.) are stored or
handled. Use of a fire in a hazardous area could cause serious
injury to personnel and serious damage to the equipment due to
an explosion.
1-22
Chapter 1
1.6
Safety
Operator and Maintainer can read and fully understand the description of
this manual.
Operator and Maintainer can understand the related P & ID, logic diagram.
Operator can operate the equipment and the system manually at the local
stations.
Operator can operate the system remotely using the DCS system.
Operator knows the location of emergency exit on the power house and is
available to provide first aid treatment.
MM-M02.02
Rev.003
1-23
Chapter 2
General
C h a p t er
2 General
2.1
Purpose
The purpose of this maintenance manual is to provide specific information to the
PAITON III Power Plant maintenance personnel regarding the maintenance of
the ID Fans. Although this document will convey a good knowledge and direction
regarding maintenance of the ID Fans, it is recommended that in the event of a
problem not covered in the document the person responsible should seek
assistance or instruction from the manufacturer.
References
a)
b)
c)
d)
e)
f)
MM-M02.02
Rev.003
2.2
2-1
Chapter 2
2.3
General
MM-M02.02
Rev.003
Two 100% capacity seal air fans supply sealing and cooling air to the fan
internal compartments containing bearing box and moving blade regulating
mechanism.
2-2
General
MM-M02.02
Rev.003
Chapter 2
FIGURE 2-1
Induced Draft Fan
Mitsubishi
2-3
Chapter 2
General
CW
OIL UNIT
LOCAL PANEL
CL OF SUCTION
IDF 3A
DRIVE UNIT
CL OF BOILER
DIFFERNTIAL PRESSURE
PURGE
IDF 3B
CL OF SUCTION
MOTOR
CW
KEY PLAN
SCALE 1/400
NOTE
1. THIS DRAWING SHOWS IDF 3B LAYOUT.
IDF 3A LAYOUT IS MIRROR IMAGE OF THIS DRAWING.
FAN SPECIFICATION
FAN TYPE
AXIAL FAN
45400
mmAq(Gage)
430
mmAq(Gage)
140
FAN SPEED
735
FLOW
0.8323
CL OF SUCTION
ROTOR
-540
FLUID DENSITY
CL OF MOTOR
FLOW
m /min/FAN
8580
rpm
kg/m3
kW
ROTATION
CL OF FAN
MM-M02.02
Rev.003
MANHOLE
FL+- 0
MPTD-3-0001
FIGURE 2-2
2-4
Chapter 2
45
44
43
46
42
ITEM
1
2
3
4
5
6
MOTOR SIDE
FLOW
61
31
34
15
23
17
60
12
40
14
26
21
22
13
19
30
ROTATION
20
33
16
29
28
27
CL OF 1ST M/B
11
SEAL AIR
SEAL AIR
37
10
24
DESCRIPTION
MOVING BLADE
ROTOR
M/B SHAFT
CRANK ARM
MAIN SHAFT
REGULATING SHAFT
Rev.003
41
38
CL OF 2ND M/B
35
36
39
25
18
32
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
60
61
General
MM-M02.02
MPTD-3-0023
FIGURE 2-3
Induced Draft Fan
Mitsubishi
2-5
Chapter 2
General
22
1
7
19
16
21
18
20
14
8
12
17
3
9
10
MM-M02.02
Rev.003
ITEM
DESCRIPTION
DESCRIPTION
ITEM
SUCTION CASING
12
13
14
FLEXIBLE COUPLING
15
16
LADDER
DIFFUSER
17
18
19
MOVING BLADE
20
BEARING BOX
10
21
11
22
MOTOR
MPTD-3-0027
FIGURE 2-4
Induced Draft Fan
Mitsubishi
2-6
Chapter 2
2.4
General
Components
Each IDF consists of the following major components:
Casing
Rotor assembly
Coupling
2.4.1
Casing
Refer to Figure 2-5.
The fan casing consists of the following sections:
suction casing
impeller casing
rear casing
diffuser casing
The fan casing sections are all bolted and seal welded (except
overhaul section) to each other.
The suction casing is connected to the suction duct through an
expansion joint. A blind drain pipe is provided for the bottom of the
suction casing lower part.
The fan drive shaft penetrates the suction casing to connect with the
electric drive motor installed outside of the fan casing. The suction
casing shape changes from rectangular to circular, in the direction of
the flow.
The impeller casing, rear casing and diffuser sections are provided with
inner casings concentric to the horizontal axis of the fan and are
supported on the outer casings with support plates. A band for casing is
provided around the flanged joint of the suction casing and the impeller
casing.
MM-M02.02
Rev.003
Sound proofing insulation is provided for each outer casing. For the
suction casing sound proofing insulation is done internally. Ladder is
provided on both the impeller and rear casing outer side for outage
maintenance.
The casing shape is specially designed to provide a streamline flow of
flue gas to the moving blades.
Induced Draft Fan
Mitsubishi
2-7
Chapter 2
General
Flue gas flows down into the suction casing. It is directed towards the
moving blades via a 90-degree bend. The air flows through the annular
space between the inner casings and the outer casings.
The diffuser is connected to the discharge duct through an expansion
joint.
Oil line is routed through the inner casing bottom side to the oil unit.
Instrument tapping points are provided on the suction casing to
facilitate the measurement of static pressure.
Impeller casing
The impeller casing houses of the following:
rotor assembly
bearing assembly
Rear casing
The rear casing is of a uniform diameter and is located between the
impeller casing at the upstream side and the diffuser at the
downstream side. The impeller casing and the rear casing are axially
split, enabling maintenance access to the rotor and the components of
the moving blade regulating mechanism.
MM-M02.02
Rev.003
The rear casing facilitates the routing of the moving blades operating
shaft. The seal cooling air, control oil supply and return lines to the
moving blade regulating mechanism are also routed through the rear
casing.
2-8
Chapter 2
General
The rear casing is provided with an inner casing to protect the moving
blade regulating mechanism components from damage. The rear inner
casing is supported by the stationary blades around the circumference.
A manhole is provided on the inner casing for the inspection and
maintenance of the moving blade regulating mechanism. The inner
surface of the rear inner casing is insulated to protect the moving blade
regulating mechanism from overheating.
Diffuser
The diffuser is installed downstream of the rear casing and is
connected to the discharge duct through an expansion joint. The
diffuser section gradually increases in cross-sectional area, recovering
the kinetic energy imparted by the moving blade.
The diffuser is provided with an inner casing and is supported by plate
at two locations. A manhole is provided on the diffuser inner casing for
the entry of personnel from the discharge duct and to carryout
inspection and maintenance of the moving blade regulating
mechanism.
MM-M02.02
Rev.003
2-9
Chapter 2
General
The moving blades, made of cast steel, have a good wear and
corrosion resistance properties. The moving blades have a laminar flow
blade profile, high efficiency and a good performance characteristic.
The moving blades are bolted onto the moving blade shafts. Provision
is made on the side plates of the rotor to fix balance weights required
for the dynamic balancing of the unit.
The torque limiter provided on the fan shaft limits the torque transmitted
to the bushes in the rotating blade shafts, thus reducing the wear and
tear of the bushes at fan startup.
MM-M02.02
Rev.003
2-10
Chapter 2
General
MM-M02.02
Rev.003
The oil pumps mounted on the top of the tank draw oil from the tank
through dedicated suction strainers. The oil is then filtered by two 100%
capacity oil strainers and supplied as control oil at about 7.5~7.85MPa
for the blade regulating mechanism. An oil accumulator (pre-charge N2
pressure at 1.4 MPa) installed in the control oil supply line to supply
lubricating oil to pilot valve in tripping of both of control oil pump.
2-11
Chapter 2
General
Pressure reducing valves reduce the pressure of the control oil to about
0.16 to 0.19 MPa for lubricating oil supply to the fan bearings. The
return control oil from the blade regulating mechanism is also directed
to the lubricating oil supply line. Oil cooler receives cooling water from
the CCCW System to cool the lubricating oil before admitting to the
bearing boxes.
The oil tank is provided with a return oil filter to collect debris in the
return oil.
For further details please refer to the Vendor manual, Appendix F.
2.4.6 Coupling
Refer to Figure 2-11.
The fan rotor is coupled to the drive motor with a flexible coupling. The
flexible coupling accommodates any minor angular, parallel and axial
misalignment due to thermal expansion.
The coupling consists of two hubs, a spacer, two flexible elements, an
end plate, overload washers, bushes, reamer bolts and nuts. Each
flexible element is an assembly of thin metal laminations.
MM-M02.02
Rev.003
One of the two 100% capacity seal air fans draw atmospheric air
through dedicated suction strainers and supply seal air separately to
the inner impeller casing and the rear casing. Seals provided inside the
inner casings prevent excessive seal air leakage along the rotor and
the drive shaft.
2-12
Chapter 2
82
83 62 73
DESCRIPTION
ITEM
84
71
61 72
General
24
FLEXIBLE COUPLING
50
SUCTION CASING
67 75 84
66 76
51L
84 65 76
52L
53
DIFFUSER
54
FLOW
A-A
68
60
52U
60
51U
55IU
54
60
68
A
51IU
80
64 76
57
24
81
MOTOR SIDE
63
59
CL OF 1'st M/B
C
L OF 2'nd M/B
52IU
CL OF SUCTION
53
79
58
77
52IL
51IL
78
67
56
57
58
59
COVER
60
LADDER
61
62
63
BOLT M10x16
64
BOLT M12x25
65
BOLT,NUT M12x25
66
BOLT,NUT M12x65
67
BOLT,NUT M16x50
68
BOLT,NUT M16x45
69
BOLT,NUT M20x50
70
BOLT,NUT M20x55
71
BOLT,NUT M20x75
72
NUT M30
73
NUT M24
74
75
76
77
78
79
80
81
82
BOLT,NUT M20x70
83
SPECIAL NUT
84
GASKET
NOTE
50
MM-M02.02
Rev.003
GL+0
-
MPTD-3-0061
69
56
52L
70
51L
55IL
71
70 74
FIGURE 2-5
Chapter 2
ITEM
ROTATION
MOVING BLADE
MAIN SHAFT
REGULATING SHAFT
DRIVING COUPLING
1ST ROTOR
2ND ROTOR
M/B SHAFT
CRANK ARM
10
11
56
12
SIDE PLATE
13
14
15
43 36
16
17
37 38
18
NUT
19
KEY
11
20
KEY
21
41 28
21
KEY
31
22
KEY
23
24
25
26
RETAINING RING
27
28
29
BOLT M30x80
30
BOLT M30x142
31
BOLT M30x105
32
BOLT M32
33
BOLT M30x70
34
WASHER
35
WASHER
36
BALANCING WEIGHT
37
U NUT
38
SET SCREW
M10x45
39
REAMER BOLT
M42
40
NUT
M42
41
17
42
SET SCREW
M8x12
43
SET SCREW
M10x40
33
44
SET SCREW
M12x16
45
RETAINING RING
12
46
47
48
O RING P315
49
50
SPACER
51
SERVO CYLINDER
52
SIDE PLATE
53
54
TORQUE LIMITER
55
FRICTION DISK
56
57
FLEXIBLE COUPLING
58
59
23
13
8
19
48
19
58
26
45
9
CLOSE
OPEN
ROTATION
ROT
ATIO
N
29
53
59
CLOSE
No.1 M/B
50
BEARING BOX ASS'Y
10
OPEN
27
24
30
51
FLOW
20
FLOW
32
4
22 57 49
A
42
A-A
18
34
55
35
25
44
CL OF 1ST BRG.
CL OF BRG.
CL OF BRG.
46
CLOSED
OPEN
STROKE RANGE
-40 DEG.
+20 DEG.
RATED STROKE
-40 DEG.
( 0% )
+16.3 DEG.
( 100% )
15
54
39 40
NOTES
1. REPLACE PARTS SHALL BE PURCHASED FROM MHI.
2. THE CASE OF PURCHASE THE PARTS,
PLEASE INFORM THE PARTS ORDER No. AND NAME
IN APPENDIX "H".
M10
MPDT-3-0062
MM-M02.02
Rev.003
CL OF 2ND M/B
52
CL OF 2ND BRG.
14 47
CL OF 1ST M/B
16
DESCRIPTION
MOTOR SIDE
General
FIGURE 2-6
Induced Draft Fan
Mitsubishi
ROTOR ASSEMBLY
2-14
Chapter 2
12
19
46
ITEM
2
41
13
18
32 24
11
43
45
D
31 25
43
4
E
OPEN
84.2
21
42 30
CLOSE
20
41
A-A
40.8
ROTATION
8
9
3
ROTATION
A
7
44
37
3
38
27
46
PILOT LEAK
17
47
B-B
40
28 49 48
36
15
OIL SUPPLY
OIL RETURN
OIL LEAK
PILOT MOVES IN
PILOT MOVES OUT
29
C-C
10
1
2
14
34
14
23
36
DET. D
34 26 30
ROTATION
General
DESCRIPTION
SERVO CYLINDER
CYLINDER COVER
PILOT VALVE
PILOT SLEEVE
PISTON
COVER
JOINT
PACKING
10
11
12
BOLT M12x126.5
13
PISTON RING
14
SCROLL
15
FLOATING RING
16
BLADE
17
MV PACKING
18
MV PACKING
19
WASHER
20
O RING
21
O RING
22
BEARING
23
OIL SEAL
24
BOLT M8x16
25
BOLT M10x25
26
27
SCREW M8x12
28
STRAIGHT PIN
29
STRAIGHT PIN
30
SPRING WASHER M6
31
32
WASHER M8
33
SPRING PIN
34
RETAINING RING 60
35
RETAINING RING 80
36
RETAINING RING 80
37
RETAINING RING 18
38
O RING G100
39
O RING G105
40
O RING G15
41
PLUG
42
SCREW M6x16
43
44
BUSH
45
BUSH
NTP 3/8
46
SCREW M8x8
47
BOLT M10x25
48
BOLT M10x25
49
RETAINING RING 18
14
33
3
16
39
DET. F
E-E
MPTD-3-0063
MM-M02.02
Rev.003
35 22
NOTES
FIGURE 2-7
Induced Draft Fan
Mitsubishi
Chapter 2
MOTOR SIDE
20
19
12
12
20
19
CL OF 2nd M/B
19
CLOSE SIDE
OPEN SIDE
32
4
9
FLOW
13 14
32
22
26
30
18
DET. B
C
A-A
30
OPEN SIDE
CLOSE SIDE
33
21
23
11 16
15 17
33
7
14 13
9
DUST PROTECT COVER
29
CONTROL DRIVE
TYPE:DU-35SHL
O
LL
FU
3o
No.A FAN
No.B FAN
LL
FU
E
OS
CL
MM-M02.02
Rev.003
34
35
KEY PLAN
VIEW FROM MOTOR SIDE
MARK B IS OPPOSITE TO MARK A WITH
REGARD TO LOCATIONS OF LINK MECHANISM
MPTD-3-0064
C-C
28
31
N
PE
64.
10 25
27
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
LEVER
STAND FOR SCALE PLATE
SCALE PLATE
PIECE
PIN
SPHERICAL BEARING
BALL BEARING UNIT
BALL BEARING UNIT
BOLT M12x45
BOLT M16x35
SOCKET HEAD BOLT M8x25
NUT M8
WASHER M12
SPRING WASHER M12
SPRING WASHER M4
WASHER M8
SCREW M4x6
SET SCREW M8x20
SET SCREW M5x6
SPLIT PIN
TAPER PIN
THREAD END TAPER PIN
THREAD END TAPER PIN
SPRING PIN
WASHER
M16
U-NUT
M8
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
U-NUT
M6
SET SCREW M8x14
BLADE STICKING DETECTOR
OPERATING SHAFT
POINTER
LEVER
LEVER
STAND FOR DRIVE UNIT
HAWK ANCHOR BOLT M16
NOTES
1. THIS DRAWING SHOWS MOVING BLADES ARE IN NEUTRAL
POSITION.(MOVING BLADE ANGLE 0 )
ASSEMBLY WORK AT FULL CLOSE POSITION.
2. OPERATING DIRECTION OF CONTROL DRIVE LEVER
(VIEW FROM LEVER SIDE)
A = CLOCKWISE (CLOSE > OPEN)
B = COUNTER- CLOCKWISE (CLOSE > OPEN)
3. PUNCHING THE SET SCREW (*1) AND TAPER PIN (*1) AT 2 PLACES
EACH ON CIRCUMFERENCE AFTER ASSEMBLING.
(STRICT OBSERVANCE)
4. APPLY GREASE TO FRICTIONAL SURFACE AND SPHERICAL
BRG. AT ASSEMBLING.
5. REPLACE PARTS SHALL BE PURCHASED FROM MHI.
6. THE CASE OF PURCHASE THE PARTS,
PLEASE INFORM THE PARTS ORDER No. AND NAME
IN APPENDIX "H".
FIGURE 2-8-1
Induced Draft Fan
Mitsubishi
DESCRIPTION
NEUTRAL
90
36
24
D-D
ITEM
General
Chapter 2
NORMAL LENGTH
22 21 40
35
13
37
33
19
16
34
34 30
17
31
15
20 23
16
12
ITEM
6
16
16
15
39
29 25
EXTENSION
36
5
27 24
11
b
3
15
15
a
13
30
14
20 23
34
19
"A"
33
18
35
1 26
38
NORMAL
POSITION
16 16
COMPRESSION
"B"
ALARM POSITION
ALARM
POSITION
OPEN(CLOSE)
MAX.
DISPLACEMENT
COMPRESSION
CLOSE(OPEN)
EXTENSION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
a
12
21
12
22
Rev.003
MAX.
DISPLACEMENT
32
28
21 24
25
10
A-A
MM-M02.02
ALARM
POSITION
21
22
MPTD-3-0033-2
"C"
12 22 40
b
c
ALARM POSITION
OPEN(CLOSE)
CLOSE(OPEN)
DESCRIPTION
BOLT M8x15
SPRING SEAT
SPRING SEAT
SPRING HOLDING FLANGE
SWITCH MOUNT
STOPPER
LIMIT SWITCH SUPPORT
STOPPER
LINER
LINER
PACKING
PACKING
DISTANCE PIECE
SHAFT
SPRING
BUSH
CONNECTING ROD
BOLT (PIN)
SPHRICAL JOINT
BOLT M10x25
BOLT M6x20
WASHER M6
SPRING WASHER M10
SPRING WASHER M6
SPRING WASHER M4
WASHER M8
MACHINE SCREW M6x16
MACHINE SCREW M4x40
MACHINE SCREW M4x10
NUT M20
NUT M24
NUT M4
NUT M16
SPLIT PIN
SPLIT PIN
O-RING P20
PIN
LIMIT SWITCH
TERMINAL BOX
BOLT M6x14
DETECTIVE CYLINDER
LIMIT SWITCH COVER
SPRING HOLDING FLANGE
NOTES
1. PURPOSE
(1) DETECTION OF MB. STICKING AND PROTECT
OF LINKAGE ASS'Y.
2. MECHANISM OF MOVING BLADE STICKING DETECTOR
(1) "A" : NORMAL OPERATION POSITION.
(2) "B" : MB STICKING OR LINKAGE ASS'Y IS ABNORMAL
POSITION AT MB CLOSE OPERATION.
(3) "C" : MB STICKING OR LINKAGE ASS'Y IS ABNORMAL
POSITION AT MB OPEN OPERATION.
3. REPLACE PARTS SHALL BE PURCHASED FROM MHI.
4. THE CASE OF PURCHASE THE PARTS,
PLEASE INFORM THE PARTS ORDER No. AND NAME
IN APPENDIX "H".
FIGURE 2-8-2
General
DETECTED BY
MB. STICKING
DETECTOR
Chapter 2
10
9
37
ITEM
36
34
21
18
23 30
40
A
E A
24 29
16
OIL SUPPLY
OF BEARING
OIL SUPPLY
OF BEARING
CL OF SHAFT
8
38
MOTOR SIDE
B-B
17
C
1
D
22
16
F
DET. D
24 29
D
ROTATION
44
43
42
28
OIL SURFACE
45
46
11
10
9
D
48
47
OIL
RETURN
J
51
K-K
15 14 13 12
C-C
A-A
41
35
35
BEARING BOX
PIN
SEAL PACKING
PACKING
ADJUSTABLE RING
PACKING
SPECIAL BOLT
10
STOPPER
11
BUSH
12
13
14
15
16
O RING
17
O RING
18
O RING
19
SEAL RING
20
O RING
21
O RING
22
O RING
23
BOLT
24
25
26
27
28
PARALLEL PIN
29
WASHER
30
WASHER
31
WASHER
32
WASHER
33
WASHER
34
PLUG
35
PLUG
36
37
38
39
LUB.OIL STRAINER
40
BUSH
41
O RING
42
DE BEARING (ROLLER)
43
44
45
BEARING SPACER 1
46
BEARING SPACER 2
47
48
49
SLEEVE
50
51
MAIN SHAFT
19 50 49
27 33
26 32
39
Rev.003
MM-M02.02
DESCRIPTION
1
2
35
39
20
20
F-F
25 31
7
E-E
General
DET. G
4
DET. J
DET. H
MPTD-3-0067
FIGURE 2-9
Induced Draft Fan
Mitsubishi
2-18
Chapter-2
PI
10
PI
9
TE
4
TE
2
TI
8
FT
1
XE
1
TE
3
PT
1
TI
BUTTERFLY VALVE
TE
TE
1
BUTTERFLY VALVE
PI
DPI
BF-2
BF- P
PT
03HNC01AN101
(03HNC01AN102)
FT
IDF
XE
PS
MOTOR
ZS
LS
20A
25A
25A
65A
25A
15A
20A
15A
15A
20A
LI
65A
20A
20A
ZS
2
PILOT
LEAK OIL
U-SEAL
U-SEAL
CONTROL OIL LEAK OIL
20A
F-4
40A
PI
3
PS
5
20A
PS
4
25A
100A
40A
25A
40A
40A
PS
1
PS
6
20A
20A
FOR MAINTENANCE
100A
PS
2
PS
3
LOCAL PANEL
40A
A-1
FOR MAINTENANCE
40A
DU-1
40A
ZS
1
PI
6
F-5
PI
2
PI
1
PRESSURE GAUGE
TI
7
XE
2
PRESSURE SWITCH
TI
6
DPI
7
INSTRUMENTS LIST
THERMOMETER
DPI
8
EXPLANATION OF SYMBOL
DESCRIPTION
INSTRUMENT(FIELD MOUNTED)
LOCAL PANEL MOUNTED INSTRUMENT
CONTROL AND/OR DISPLAY FUNCTION IN DCS
CONTROL AND/OR DISPLAY FUNCTION IN PLC
THERMOMETER
(LOCAL)
THERMOCOUPLE
PRESSURE GAUGE
(LOCAL)
DIFFERENTIAL PRESSURE GAUGE
(LOCAL)
PRESSURE TRANSMITTER
DIFFERENTIAL PRESSURE TRANSMITTER
VIBRATION METER
PRESS. SWITCH
LIMIT SWITCH
LEVEL SWITCH
LEVEL GAUGE
GLOBE VALVE
GLOBE VALVE (NORMALLY CLOSED)
REGULATING VALVE
SAFETY VALVE
3-WAY VALVE
STOP CHECK VALVE
BUTTERFLY VALVE
NEEDLE VALVE
REDUCER
SIGHT FLOW
STRAINER
OIL COOLER
ORIFICE
ACCUMULATOR
CHECK DAMPER
FLANGE
EXPANSION JOINT
FLEXIBLE HOSE
CAP
OIL LINE
DRAIN LINE
COOLING WATER LINE
AIR LINE
CAPILLARY
ELECTRIC SIGNAL
AIR SIGNAL
THERMOCOUPLE
M
TI
5
SYMBOL
D-2
03HNC01AN202
(03HNC01AN204)
B-2
250A
D-1
03HNC01AN201
(03HNC01AN203)
B-1
SEAL AIR
250A
250A
General
03HNC01CP311
(03HNC01CP321)
03HNC01CP312
(03HNC01CP322)
03HNC01CP313
(03HNC01CP323)
03HNC01CP314
(03HNC01CP324)
03HNC01CP315
(03HNC01CP325)
03HNC01CP316
(03HNC01CP326)
03HNC01CP711
(03HNC01CP721)
03HNC01CP712
(03HNC01CP722)
03HNC01CP317
(03HNC01CP3270
03HNC01CP318
(03HNC01CP328)
DESCRIPTION
IDF CONTROL OIL PUMP 3 A1/B1 OUTLET
IDF CONTROL OIL PUMP 3 A2/B2 OUTLET
IDF CONTROL OIL SUPPLY PRESS.
IDF LUBRICATING OIL COOLER INLET
IDF LUBRICATING OIL COOLER OUTLET
LUBRICATING OIL SUPPLY PRESS.
PILOT BOX SEAL DIFFERENTAL PRESS.
BEARING BOX SEAL DIFFERENTAL PRESS.
IDF SEAL AIR FAN 3 A1/B1 AIR FILTER OUTLET
IDF SEAL AIR FAN 3 A2/B2 AIR FILTER OUTLET
SET POINT
RANGE
0~15MPa
0~15MPa
0~15MPa
0~1.0MPa
0~1.0MPa
0~0.4MPa
0 ~ 10kPa
0 ~ 10kPa
-2~0kPa
-2~0kPa
SYMBOL
PI-1
PI-2
PI-3
PI-4
PI-5
PI-6
DPI-7
DPI-8
PI-9
PI-10
0~10MPa
0~10MPa
0~10MPa
0.02~0.2MPa
0.02~0.2MPa
0.02~0.2MPa
PS-1
PS-2
PS-3
PS-4
PS-5
PS-6
0~100 C
0~100 C
0~100 C
0~100 C
0~100 C
0~100 C
0~100 C
0~100 C
TI-1
TI-2
TI-3
TI-4
TI-5
TI-6
TI-7
TI-8
0~150 C
0~150 C
0~150 C
0~150 C
TE-1
TE-2
TE-3
TE-4
0~300um(P-P)
l
0~300um(P-P)
l
XE-1
XE-2
03HNC01CP211
(03HNC01CP221)
03HNC01CP212
(03HNC01CP222)
03HNC01CP213
(03HNC01CP223)
03HNC01CP214
(03HNC01CP224)
03HNC01CP215
(03HNC01CP225)
03HNC01CP216
(03HNC01CP226)
03HNC01CT311
(03HNC01CT321)
03HNC01CT312
(03HNC01CT322)
03HNC01CT313
(03HNC01CT323)
03HNC01CT314
(03HNC01CT324)
03HNC01CT315
(03HNC01CT325)
03HNC01CT316
(03HNC01CT326)
03HNC01CT317
(03HNC01CT327)
03HNC01CT318
(03HNC01CT328)
03HNC01CT011
(03HNC01CT021)
03HNC01CT012
(03HNC01CT022)
03HNC01CT013
(03HNC01CT023)
03HNC01CT014
(03HNC01CT024)
03HNC01CY011
(03HNC01CY021)
03HNC01CY012
(03HNC01CY022)
03HNC01CG211
(03HNC01CG221)
03HNC01CG212
(03HNC01CG222)
FULL CLOSE ON
ZS-1
ZS-2
03HNC01CL211
(03HNC01CL221)
LS-1
03HNC01CL311
(03HNC01CL321)
LI-1
03HNC01CF101
(03HNC01CF151)
FT-1
03HNC01CP101
(03HNC01CP151)
PT-1
P>
= 5.88 MPa ON
P<
= 5.39 MPa ON
P<
= 2.45 MPa ON
> 0.14 MPa ON
P=
P<
= 0.13 MPa ON
P<
= 0.09 MPa ON
T>
=100
T>
=100
>100
T=
>100
T=
CON
CON
CON
CON
V>
= 130um
l ON
V>
l ON
= 130um
F-6
PI
4
03HNC01AC101
(03HNC01AC102)
C-1
PI
5
03HNC01AP201
(03HNC01AP203)
TI
2
03HNC01AP202
03HNC01AP204
P-2
LS
1
TI
4
OIL DRAIN
P
P-1
AIR BREATHER
TI
1
WATER DRAIN
TI
3
OIL SUPPLY PLUG
EQUIPMENTS LIST
SYMBOL
F-1
LI
1
T-1
03HNC01BB101
(03HNC01BB102)
F-3
MM-M02.02
Rev.003
65A
OIL UNIT
65A
40A
F-2
COOLING WATER
MPTD-3-0024
P-1
P-2
F-1
F-2
F-3
F-4
F-5
F-6
C-1
A-1
T-1
DU-1
B-1
B-2
BF-1/2
D-1/2
DESCRIPTION
IDF CONTROL OIL PUMP 3 A1/B1
IDF CONTROL OIL PUMP 3 A2/B2
RETURN OIL STRAINER
CONTROL OIL PUMP 3 A1/B1 SUCTION STRAINER
CONTROL OIL PUMP 3 A2/B2 SUCTION STRAINER
FIGURE 2-10
Induced Draft Fan
Mitsubishi
REMARKS
7.85 MPax 135 /min
AC 416 V x 50 Hz
30 kW x 6P
100 mesh
150 mesh
150 mesh
20u
l
20u
l
200 mesh
10 TON/Hr
60
1400
Torque 102 N-m
80m3/min x 650 mmAq
x 15 kW x 3000 rpm
10u
l
SWING CHECK VALVE
3
45400 m /min x 970 mmAq
8580kW x 8P
2-19
General
MM-M02.02
Rev.003
Chapter 2
FIGURE 2-11
2-20
Chapter 3
Specifications
C h a p t er
3 Specifications
TABLE 3-1
Subject
Specifications
Equipment number
03HNC01AN101, 03HNC01AN102
Quantity
2 sets
Fan
Coupling
Bearing
Manufacturer
MHI
Model
ML-H2-R200/375
Type
Manufacturer
Type
Flexible Coupling
Manufacturer
JTEKT
Type
Major Material
Weight
(approximately)
Static
NU364AY3CS240
1970
2880
83A385ADT/41
1990
10100
NJ364AY3CS24041
1970
2880
Casing
Moving Blade
Cast steel
Rotor
Forged steel
Rotor Shaft
Forged steel
Bearing (Box/Body)
Coupling
Rotor
31.5 t
Suction casing
Diffuser
18 t (including insulation)
735rpm
Blades
16
MM-M02.02
Rev.003
Clockwise
45,400 m3/min
-540 mm Aq (Gauge)
430 mm Aq (Gauge)
Fluid
Flue Gas
140C
0.8323 kg/m3
3-1
Chapter 3
TABLE 3-2
IDF MOTOR
Subject
Specifications
Manufacturer
Type
HRP3 1129-88E
Rated Output
8,580 kW
Rated Voltage
13,200 V
Rated Current
456.9 A
Frequency
50 Hz
Poles
Coupling
Direct
Rating
Continuous
Thermal Class
40C
Bearing
Split Sleeve
41,500 kg
TABLE 3-3
Specifications
Subject
Oil Specification
Specifications
ISO VG 32
Electric Power
Power
Type
Vane Pump
Quantity
Capacity
135 L/min
Working Pressure
7.85 MPa
Type
Quantity
Oil Tank
Total Volume
1,400 l
Oil Cooler
Type
Quantity
Water quantity
10 Ton/H
150 mesh
100 mesh
200 mesh
20
Accumulator
60 l
MM-M02.02
Rev.003
3-2
Chapter 3
TABLE 3-4
Specifications
Subject
Specifications
Electric Power
Power
Type
Centrifugal
Quantity
Capacity
80m3/min
Working Pressure
650mmAq
Type
Quantity
Motor
10
MM-M02.02
Rev.003
Suction Filter
3-3
Specifications
MM-M02.02
Rev.003
Chapter 3
FIGURE 3-1
Induced Draft Fan
Mitsubishi
PERFORMANCE CURVE
3-4
Chapter 4
Preventive Maintenance
C h a p t er
4 Preventive Maintenance
Preventive maintenance is carried out to avoid or minimize the possibility of failure or
deterioration of equipment performance. This requires a constant effort from
maintenance staff to ensure that the Unit is available on demand.
There are two categories of preventive maintenance, Routine Maintenance and Annual
Outage Maintenance. Routine maintenance helps to reduce the possibility of outage
and hence the downtime of machinery. Annual outage maintenance is required to
maintain the internal components of the installed equipment.
Though vendor/manufacturers recommendations provide a good basis for the
provision of a preventive maintenance schedule, the frequency and other details should
be updated from time to time based on practical experience and actual feedback
gathered through inspection and normal operation of the equipment/plant.
Consideration of these site related specific issues will make the preventive
maintenance more effective.
4.1
Prerequisites
The necessary prerequisites for the preventive maintenance of the IDF are as
follows:
4.1.1 Scheduling
Scheduling is the first activity in the preparation of a preventive
maintenance program. The schedule is to include planning to attend all
operating equipment on a fixed regular basis. Initially, schedules will be
prepared based on vendor/manufacturers generic instructions, the
schedules will, however, be updated (frequency, nature of inspection,
etc.) as site specific data becomes available.
Preventive maintenance is to be coordinated with other concerned
departments. In the case of a major scheduled outage, maintenance
personnel and other concerned departments should jointly produce a
plan of activities, well in advance, to decide the inspection activities and
other logistics (such as the availability and supply of required
equipment, spare parts, and tools, etc.).
MM-M02.02
Rev.003
4-1
Chapter 4
Preventive Maintenance
4.1.3 Isolation of EquipmentIt is important that isolations are agreed and valid clearances and work
permits are obtained before any maintenance work is performed. The
isolation boundaries of the particular equipment to be taken under
maintenance are to be clearly identified.
In the case of an electrical isolation the power supply shall be
disconnected and/or the fuses removed or pad locked. In the case of
mechanical isolation, the valves or other mechanical means of isolation
(blinding), at the isolation boundaries are to be closed and if possible
locked closed. The system within the isolation boundaries is to be
vented and depressurized.
MM-M02.02
Rev.003
Prior to the commencement of actual work, the person carrying out the
work is to make a safety check based on the above method statement
and also use his own judgment to ensure that the equipment and the
prevailing working conditions are safe. During maintenance work,
every employee should follow the safe working procedures detailed in
the method statement.
4-2
Chapter 4
4.2
Preventive Maintenance
Routine Maintenance
The purpose of routine maintenance is the implementation of the preventive
maintenance program on a day-to-day basis through a planned and correctly
executed inspection.
The routine maintenance activities are very important in that if they are properly
carried out, they will enhance equipment reliability. As a result, good routine
maintenance activities may help in cost reduction in the long run through the
minimization of equipment downtime.
Cleaning is an important and necessary maintenance activity to prevent the
ingress of foreign material. Other major points are as follows: (Summarized
major routine activities are also shown in Table 4-1).
4.2.1 Preparation
a)
b)
Documentation
Documentation is an important part of any maintenance duty. All
findings should be noted on a comprehensive log sheet, reporting
all aspects of the equipment observed during the routine
inspection.
The data recorded in these documents will be useful in
determining the root cause of equipment failure found during
annual outage/corrective maintenance work.
MM-M02.02
Rev.003
4-3
Chapter 4
Preventive Maintenance
Dont come closer around the suction silencer inlet less than
2 m.
CAUTION
a)
MM-M02.02
Rev.003
4-4
Chapter 4
Preventive Maintenance
CAUTION
Dont come closer to drive unit and moving blade sticking
detector.
c)
Casing
The fan casing is to be checked for leakage. Erosion, abrasion or
cracking may occur in the casing during fan operation. In the
event of air leakage through any part of the casing, external patch
welding work may be undertaken as a temporary measure, and
this event should be recorded for inclusion in the annual overhaul
program.
Rev.003
d)
MM-M02.02
4-5
Chapter 4
Preventive Maintenance
CAUTION
If oil leakage is found take care not to come close the leakage
point because workers can get oil in the eyes.
Dont go up the piping not to damage the piping.
The temperature of oil in the tank should be observed on a
routine basis. The temperature should be below 70C.
For further details, please refer to the vendors manual in
(Appendix F).
f)
Coupling
MM-M02.02
Rev.003
4-6
Chapter 4
g)
Preventive Maintenance
MM-M02.02
Rev.003
4-7
Chapter
TABLE 4-1
No.
Description
Rotor main
bearing
4 Preventive Maintenance
Check Method
Check Reference
Vibration
Permanent
instruments
Temperature
Permanent
instruments
Action to be Taken
(if beyond acceptable limit)
Remarks
Recommended
Maintenance
Frequency
Daily
Coupling
Abnormal noise
Visual and
audible
No abnormal noise
No contact between
the coupling and
coupling cover.
Moving Blade
Regulating
Mechanism
Smooth operation
Permanent
Instruments
No alarm
Casing
Visual and
audible
No apparent gas
leakage
Daily
Daily
Daily
MM-M02.02
Rev.003
Rubbing contact
with the coupling
cover
Audible
4-8
Chapter
4 Preventive Maintenance
No.
Description
Bearing vibration
Bearing
temperature
Check Method
Check Reference
Portable
vibrometer
Less than 40 m
Permanent
instruments
Action to be Taken
(if beyond acceptable limit)
Shut down and check for bearing damage.
Check for any foreign material in the lubricating
oil.
Remarks
Recommended
Maintenance
Frequency
Depends on condition
Daily
NA
NA
Abnormal noise
Audible
No abnormal noise
Seal differential
pressure
Permanent
instruments
Every 3 months
Daily
Daily
MM-M02.02
Rev.003
Permanent
Instrument
Touch/
portable
thermometer
No appreciable
temperature rise
Visual
No leak
Daily
4-9
Chapter
4 Preventive Maintenance
No.
Description
6
Control/Lubricating Oil pump shaft
(Cont) Oil System
rotating condition
Oil strainer
Check Method
Visual/audible
Check Reference
No abnormal noise
No abnormal trembling
Permanent
instrument
Not clogged
Color of indicator on the top of
the strainer is not red
(replacement), but
green (Normal)
(Control oil pump discharge
strainer) Diff. press. Less than
0.1MPa
Action to be Taken
(if beyond acceptable limit)
Investigate and take action, to normalize the
condition, such as exchange of bearings.
Remarks
Recommended
Maintenance
Frequency
No leak
Permanent
instrument
Permanent
instruments
Visual,
Permanent
instrument
Rated flow
Visual
Further tightening
Rev.003
Level gauge
Daily
MM-M02.02
Exchange of gaskets
Visual,
Permanent
instrument
4-10
Chapter 4
4.3
Preventive Maintenance
4.3.1 Preparation
a)
b)
Documentation
Refer to Subsection 4.2.1 b), Documentation.
Records are to be maintained to record information regarding
spares and consumables used. These records will be used for
future reference and spare parts replenishment.
MM-M02.02
Rev.003
4-11
Chapter 4
Preventive Maintenance
Rotor Assembly
The rotor assembly is to be checked for erosion, and for the
adhesion of dust that could have occurred during normal
operation of the equipment, either of which could induce severe
rotor imbalance resulting in excessive vibration of the rotating
assembly, which could cause serious equipment damage.
Visual inspection of the rotor wheel and moving blades is to
include checks for erosion, dust adherence, or damage. The
occurrence of wear and cracking is to be further checked through
a non-destructive testing procedure (e.g. dye penetrant test,
etc.).
The rotor wheel, moving blades (two stages) and rotor shaft
clearances with the respective stationary parts are to be checked
against the appropriate tolerances as indicated in Figure 4-1,
Clearance Drawing of IDF. After thorough inspection, if any part
is found to be worn beyond the acceptable limits as specified in
the annual outage maintenance check list table (Table 4-2), the
respective part is to be replaced.
The moving blades (two stages) are to be operated for 100%
opening and full closing positions with the moving blade
regulating mechanism to ensure that all moving blades(two
stages) move uniformly. The moving blade support bearing of
any sticking blade is to be inspected and replaced if found
defective.
The grooves on the rotor shaft corresponding to the bearing box
labyrinth seals on both the drive and non-drive ends are to be
inspected for damage or wear. Minor damage can be corrected
with an oilstone.
b)
Bearings
Replace the fan bearings if they surpass the recommended
replacement period or if they show indications of wear during
operation.
MM-M02.02
Rev.003
4-12
Chapter 4
Preventive Maintenance
c)
d)
Casing
MM-M02.02
Rev.003
4-13
Chapter 4
Preventive Maintenance
e)
f)
Coupling
Coupling alignment checks are to be conducted carefully both
before disassembly and after reassembly, (refer to Appendix D).
Check the coupling bolts, hubs, spacer and flexible discs for
damage or wear. Defective components are to be replaced with
new. Check and confirm the security of the hubs on the
respective shafts.
g)
MM-M02.02
Rev.003
4-14
Chapter 4
TABLE 4-2
No.
1
Descriptio
n
Rotor
Major Check
Item
Check
Method
Check Reference
Action to be Taken
(if beyond acceptable
limit)
Remarks
Wear, cracks
Visual
No appreciable
wear
No crack
Inner casing
and seal
clearances
Measurement
Clearances are
within specified
criteria (Refer to
Figure 4-1)
Adjust clearance by
adjusting of bearing
box position (using by
shim plate, etc.)
Visual
No appreciable
wear
No crack
Moving
Blades
Outer casing
clearances
Measurement
Clearances are
Adjust clearance
within specified
criteria (Refer to Fig
4-1)
Wear, crack
Visual ,
Measurement
*1
Preventive Maintenance
*2
PT check*2
Inspection Date
Inspector
Results
Tightness of
blade fixing
bolts
Visual*
Axial
movement
Measurement
Clearance are
within specified
criteria
(Refer to Figure
4-1)
Adjusted by shim
between the moving
blade support bearing
and nut for moving
blade shaft.
MM-M02.02
Rev.003
Design: L=144mm
No crack
4-15
Chapter 4
Preventive Maintenance
Descriptio
n
Major Check
Item
Check
Method
Check Reference
Action to be Taken
(if beyond acceptable
limit)
Remarks
3
(Cont)
Moving
Blade
Bearing
Security
NA
NA
Replace
Recommended to replace
the bearing assembly
every 4 years
Rotor seal
and
Packing
Wear
Visual
and audible
No rubbing marks
Clearance
Measurement
Clearance is within
specified criteria
(Refer to Figure
4-1)
Adjust clearance
Coupling
Deformation,
crack and
damage
Visual
No defective parts
Replace or repair
Alignment
Measurement
Rubbing with
the coupling
cover
Visual and
Audible
NA
NA
Na
Replace
Clearance check is
carried out when replace
the bearing.
Recommended to replace
every 8 years (if have
spares ), 4 years (if have
not spares).
Clearance are
within specified
criteria (refer to
Figure 4-1)
Replace
Main
bearing
Inspector
Results
MM-M02.02
Rev.003
Inspection Date
4-16
Chapter 4
Preventive Maintenance
MM-M02.02
Rev.003
Major Check
Item
Description
Casing
Check
Method
Check Reference
Action to be Taken
(if beyond acceptable
limit)
Remarks
Wear, cracks
Visual
measurement
No appreciable
wear
Casing to blade
clearance should not be
exceed tolerance limits.
Debris
Visual
No cracks
Clearances are
within specified
criteria (Refer to
Figure 4-1)
Wear of servo
cylinder,
sleeve
Measurement
Clearances are
within specified
criteria. (Refer to
Figure 4-1)
Replace
Oil leakage
Visual
No oil leakage
Moving blade
operation
Visual
Smooth operation
Replace defective
components
Moving blade
adjustment
Visual,
Measurement
Adjust blades
position from
-40 to +16.3
Corresponding control
drive range is 0% to
100%(0 to 90)
Every rotor overhaul
(4 years)
Replacement NA
of consumable
parts
NA
Replace
Replacement NA
of consumable
parts-oil hoses
NA
Replace
Inspection Date
Inspector
Results
4-17
Chapter 4
Preventive Maintenance
Description
Check
Method
Check Reference
Action to be Taken
(if beyond acceptable
limit)
Remarks
Grease up
NA
NA
NA
Every year
Replacement
of
consumables
NA
NA
Replace
Control/
Oil condition*1
Lubricating Oil
System
Visual
NA
Wear or
damage of oil
pump
3
components*
Visual
Damage of
control oil
2
filters*
Visual
No damage
Replace filter
Accumulator
bladder*2
Visual
Pressure
gauge
No ageing, cracks
or damage
Replace bladder
Oil cooler
leakage*3
Visual
Hydraulic test
No leak
Oil cooler
protecting
2
Zinc*
Measurement
9
Linkage
mechanism
Inspection Date
Inspector
Results
MM-M02.02
Rev.003
10
Major Check
Item
4-18
Chapter 4
TABLE 4-2
No
.
Major Check
Item
Description
Check
Method
Check
Reference
Remarks
Tightness of
base bolt
Visual
Not loose
Interval is every 2
years
Internal parts
Visual
No debris
Every overhaul is
every 4 years
Bearing
N/A
N/A
Grease
Recommended to
replace every 4 years
Filter
Visual
No clogging
Damper
Visual
No debris
Inspection Date
Inspector
Results
Every overhaul
4 years
MM-M02.02
Rev.003
Preventive Maintenance
4-19
4.0~9.5
4.0~10.5)
Preventive Maintenance
4.0~9.5
4.0~10.5)
Chapter 4
AXIAL MOVEMENT
OF
MOVING BLADE
0~0.1
(0~0.3)
AXIAL MOVEMENT
OF
MOVING BLADE
0~0.1
(0~0.3)
MOTOR SIDE
FLOW
2.16~3.69
0.29
~0.45
84.2+0.5
2.16~3.69
3.0~9.0
(3.0~15.0)
0.29
~0.45
1.41~2.19
0.45~0.55
( 0.45~0.83)
0.35~0.53
0.02~0.21
(0.02~0.32)
0.02~0.21
(0.02~0.32)
0~0.05
0~0.05
0.02~0.17
(0.02~0.26)
7 +0.25
3.0~9.0
(3.0~15.0)
3.0~9.0
(3.0~15.0)
1.41~2.19
3.0~9.0
(3.0~15.0)
0.02~0.17
(0.02~0.26)
0.02~0.17
(0.02~0.26)
0.02~0.17
(0.02~0.26)
A
0
ROTATION
40.8+0.5
0.05~0.13
(0.05~0.20)
7 +0.25
0.65~0.80
21.7
MM-M02.02
Rev.003
MPDT-3-0069
A-A
1.55~1.75
CL OF 1ST M/B
CL OF 2ND M/B
1.55~1.75
0.65~0.80
0.04~0.07
0.04~0.11
0.04~0.07
0.04~0.11
0.045~0.055
(0.045~0.065)
21.7
NOTES
MARK ( ) ARE CLEARANCE ON RADIUS.
** ~ **
: DESIGN VALUE
(** ~ **) : ALLOWANCE VALUE (TENTATIVE VALUE)
ALLOWANCE VALUE ARE SET IN FIRST
ANNUAL OUTAGE MAINTENANCE IN
REFLECTION OF CONDITION AFTER PLANT
OPERATION ETC..
FIGURE 4-1
Induced Draft Fan
Mitsubishi
4-20
Chapter 5
C h a p t er
Note
MHI recommends that Disassembly and Reassembly of IDF is
carried out under MHI supervision.
5.1
CAUTION
Prior to carrying out any maintenance, confirm that all equipment
is shut down and that all isolations are in place.
a)
Preparation
If IDF disassembly becomes necessary, all associated equipment is to be
mechanically and electrically isolated and an authorized clearance and
work permit shall be in place prior to the commencement of work. The
following points are also to be considered when preparing for disassembly
and reassembly:
Have all necessary drawings (assembly drawings, sectional drawings,
part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to start of work.
MM-M02.02
Rev.003
5-1
Chapter 5
The electrical breaker must switched off and locked at both locations
and the key must be retained by the Charge Engineer.
Bring the moving blades to fully closed position before stopping the oil
pumps.
b)
Disassembly
CAUTION
Dont sit or stand on a rotor during disassembly.
When separating joints and flanges use jacking bolts and wooden
mallets. Never apply force with hammers, chisels or screwdrivers.
All data is to be recorded during disassembly. During disassembly, make
match marks on adjoining parts for ease of identification during
reassembly. The disassembly procedure is described as follows:
Refer to Figures 2-3, 2-4, 2-5, 5-1A and 5-1B.
CAUTION
Take care not to fall while entering the casing.
MM-M02.02
Rev.003
Use the safety belt when entering inside the casing through the
manhole.
5-2
Chapter 5
CAUTION
Use the safety belt when entering inside the casing through the
manhole.
Take precaution against falling.
When entering inside the fan, take precautions not to get trapped.
CAUTION
Special care is to be taken when you work in the fan casing (like
falling down of some thing above, slipping due to oil etc).
Move the moving blades (two stages) to the full close position before
starting disassembly of the IDF. Take care not to be close to moving
blade when direction is changing.
Enter the diffuser inner casing through the diffuser inner casing
manhole (79).
Remove the bolts jointing the diffuser casing and the rear inner casing
upper (52IU) and the bolts the securing the horizontal joint of the rear
inner casing (52IU & 52IL).
Remove the bolts securing the seal plate for rear casing (56) from the
rear inner casing (52I).
Remove insulation from around the joints of the impeller casing (51)
upper and the rear casing upper (52).
Rev.003
Note
Impeller casing (lower) and rear casing (lower) joints are seal
MM-M02.02
welded. Upper impeller and rear casings are not seal welded.
5-3
Chapter 5
Remove the band for casing (54) provided between the suction casing
(50) and impeller casing (51) by loosening the horizontal bolts first
and then removing the vertical bolts.
CAUTION
Special care is to be taken when moving blade operate (Pinch in
the moving blade).
8
Remove the bolts securing the impeller casing upper (51U) and the
rear casing upper (52U) including the horizontal flange joints. Remove
the bolts between the rear casing and (52) diffuser (53).
Clean the inside of the fan casing before disassembly, to prevent the
entry of any foreign material into the bearing box (26 of figure 2-3) and
the servo cylinder (39 of figure 2-3).
10 Refer to Figures 5-1A & 5-1B. Using a jack up bolt, remove the
impeller casing upper (51U) and the rear casing (52U) separately with
their respective inner casings and transport them to the lay down
area.
CAUTION
Rigging and transportation of equipment must be carried out by
authorized persons. Care is to be taken where equipment weight
and center of gravity is to be considered.
Ensure that the moving blades are in the fully closed position.
Removal of rear casing inner casing with moving blades in the
open position leads to damage of the moving blades
Special care is to be taken when lifting the casing to prevent
damage to the moving blades.
MM-M02.02
Rev.003
5-4
Chapter 5
CAUTION
Remove the oil connections only after depressurizing the system
to atmospheric pressure.
12 Remove the control oil inner pipings (flexible hose) (41) from pilot
valve (30) of control oil supply, control oil return, pilot leak and oil leak
line.
13 Cover the openings of oil lines immediately with cloth to prevent the
entry of dust.
CAUTION
Removing the pilot valve from the rotor is carried out in the
casing.
Note
If pilot valve disassembly is to be done follow the steps below,
pilot valve disassemble is carried out at the clean place (work
shop etc.) carefully.
Rev.003
MM-M02.02
(i)
5-5
Chapter 5
(ii)
Remove the retaining ring (35) and the bearing (22) from
the scroll (14).
(iii)
Remove the set screw (27) and then the scroll. Remove the
spring pin (33) from the pilot valve shaft.
(iv)
Remove the cover (7) with oil seal (23) and floating ring
(15) from the pilot valve (3)
(v)
(vi)
Remove the floating ring (15), the oil seal (23) and O ring
(56)
(vii)
Remove the bolts (25) and spring washer (31). Discard the
packing (9).
Note: Pilot parts shall be kept in the oil bath after disassembly.
Coupling Removal:
Refer to Figure 2-5
18 Enter the suction casing (50) through the suction casing manhole (77)
and the suction inner casing manhole (78).
19 Remove the bolts (67&75 and 70&74) securing the suction inner
casing upper (55IU).
20 Remove the suction inner casing upper (55IU) by using chain block.
21 Remove the suction inner casing lower (55IL) and place that in the
suction casing (50).
22 Remove the coupling cover assy (58) by using chain block.
23 Fix the supporting tools with the impeller inner casing and suction
casing to support the form flex coupling spacer as shown in Figure
5-8.
24 Remove the hub (fan side) (80) of the coupling. For details, refer to
disassembly of coupling.
Rev.003
25 Remove the seal plate for rear casing (61 of Figure 2-3)
MM-M02.02
Take care not to drop the part to be lifted while rigging. If the part
drops, it will damage the stationary equipment.
5-6
Chapter 5
CAUTION
While rigging, never stand or sit on the object to be lifted.
Lift the upper casing more than 1.8m high from the horizontal
flange to avoid contact with moving blades.
CAUTION
Dont sit or stand on a rotor and bearing box
during disassembly.
26 Disconnect and remove the lubricating oil supply pipes from the
bearing box cover assembly (Refer to section 5.3). Cover the
openings immediately with cloth to prevent the entry of foreign
material.
27 Remove the temperature measuring elements and the vibration
pickups from the bearing box. Install eye bolts in the threaded holes
provided on the bearing box and rotor.
MM-M02.02
Rev.003
5-7
Chapter 5
30 Remove the bearing box fixing bolts (9 of Figure 2-9) and the dowel
pins (28 of Figure 2-9).
CAUTION
Take care not to lean on the rotor while removing the fixing bolts
to avoid internal contact.
Rigging and transportation of equipment must be carried out by
authorized persons. Care is to be taken where equipment weight
and center of gravity is to be considered.
31 Refer to Figure 5-1B. Adjust the slings to facilitate vertical lifting of the
combined rotor and bearing assembly.
CAUTION
Special care is to be taken when lifting the rotor assembly to
prevent damage to the moving blades, and bearing box.
Pay attention not to work on the rotor while it is being lifted. This
could be dangerous.
32 Slowly lift up the rotor assembly with the bearing box and transport it
to the lay-down area.
33 When the rotor is lifted inside casing, cover the casing drain outlet
pipe in the fan casing and also the pipe for oil return (4 of figure 2-9)
with cloth/tape to avoid entry of foreign materials.
Rev.003
34 When the rotor assembly has been removed from the casing, it should
be lowered into previously prepared supports so arranged as to
support the bearing box.
CAUTION
MM-M02.02
5-8
Chapter 5
c)
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified in Figure 4-1. All contact surfaces are to be
cleaned before starting reassembly and all gaskets are to be replaced.
Before closing the manholes/access doors to the IDF an inspection is to
be carried out to ensure that no material has been left inside.
Note
Before installing the rotor assembly, Oil flushing is finished.
If disassembly of the rotor has been performed, ensure that the rotor
is reassembled and ready for installation as per section 5.2.
Visually inspect the fan casings to ensure that they are clean and free
of foreign material before rotor installation.
Refer to Figure 5-1B. Lift the rotor assembly slightly to ensure that the
load is correctly balanced.
Take care not to drop the lifted object while rigging. If the lifting
part falls, it will damage the stationary equipment.
Never stand under an object being lifted. This could cause death
or a severe injury.
Install a new gasket (6 of figure 2.9) on the seat for lubricating oil
return (5 of Figure 2-9).
Transport the rotor assembly with bearing box and servo cylinder to
the fan casing, and lower it slowly into the casing so that the bearing
box seats properly on the bearing box support. Do not forget to
remove the temporary covers put on the bearing drain oil pipe lines
before installing the fan assembly.
MM-M02.02
Rev.003
Take care not to drop the lifted object while rigging. If the lifting
part falls, it will damage the stationary equipment.
5-9
Chapter 5
Measure the axial clearance of the rotor with the bottom halves of the
impeller and rear inner casings.
Measure the radial clearance between the impeller and the rear inner
casing seals.
CAUTION
Ensure that the moving blades are in the fully closed position.
Note
If pilot valve disassembly is to be done follow the steps below,
pilot valve disassemble is carried out at the clean place (work
shop etc.) carefully.
Refer to Figures 2-7 and 5-2.
The pilot valve (3) reassembly is done in the following steps:
(i)
Reassemble the pilot valve (3) with the bearing (22), scroll
(14) cover (7) in the reverse order to disassembly.
MM-M02.02
Rev.003
Note:
(ii)
Install the cover (7) with oil seal (23) and floating ring (15)
to the pilot valve(3).
(iii)
Install the scroll (14) with the spring pin (33) and the set
screw (27).
Note:
5-10
Chapter 5
(iv)
(v)
(vi)
Provide packing (9) onto the pilot valve head, install the
joint (8) and secure it with spring washers (31) and bolts
(25).
CAUTION
Installing the pilot valve to rotor should be carried out in the
casing.
17 Smear lubricating oil over the pilot valve assembly and slowly insert
the pilot valve assembly on the servo cylinder (1)
18 Tighten the bolts (24) with washers (32).
19 Install the oil cover for pilot leak (43) and secure it with spring washer
(30) and screw (42).
20 Connect the control oil inner piping (41 of Figure 2-3) to the pilot valve
(3) of control oil supply, control oil return, pilot leak and oil leak line.
CAUTION
Wear the eye protection in oil line assembly while working.
MM-M02.02
Rev.003
5-11
Chapter 5
Start the oil pump and check that the oil pressure is between 1.0
and 1.5 MPa.
Note
Ensuring of moving blade stroking may carried out before rotor
installing (after rotor reassembly) by using N2 gas.
CAUTION
Be careful when adjusting the moving blade. It could result in the
breaking of the equipment.
Start the oil pump and check that the oil pressure is between
7.50MPa and 7.85 MPa.
Rev.003
(ii) Operate the control drive locally from 0% to 100% and ensure
that the moving blade pitch indicator is moved form fully closed
positions to fully open positions and stamped on the rotor is
moved from - 40 to + 16.3. Adjust the linkage mechanism if
required.
MM-M02.02
(iii) Operate the control drive from the DCS from 0% to 100% to
confirm that the moving blade pitch angle is in requirement with
the DCS indication. Adjust the linkage mechanism if required.
(iv) Record the angle of stamped on the rotor and moving blade pitch
indicator on side of outer casing for every 20% DCS demand.
Induced Draft Fan
Mitsubishi
5-12
Chapter 5
CAUTION
Be careful when adjusting the moving blade. It could result in the
breaking of the equipment.
Special care is to be taken when the moving blade operate. (Like
pinching in the moving blade)
Refer to Figure 2-5.
28 Install the suction inner casing (55IU, IL) and secured by bolt, nut (70)
and spring washer (74).
29 Install the impeller casing upper (51U) and the rear casing upper
(52U) and replace the liquid gaskets, if required by using special to
(guide tool and nut).
Note
Check no oil leakage from the bearing box, etc. before installing
the upper halves of casings.
30 Measure the impeller axial clearance of the rear and impeller inner
casings.
31 Measure the radial clearance between the moving blades and the
rear inner casing in the open position as indicated in Figure 4-1.
32 Grind the rear inner casing to achieve a clearance within the tolerance
if required.
CAUTION
Dont operate the moving blade while installing the casing.
MM-M02.02
Rev.003
35 Install and tighten the casing thread end taper pins (61&62) and all
fasteners including those in the horizontal joints and install the band
for casing (54).
Induced Draft Fan
Mitsubishi
5-13
Chapter 5
CAUTION
Dont operate the moving blade while installing the casing.
Be careful not to place your finger between the upper and the
lower casings during reassembly.
MM-M02.02
Rev.003
5-14
Chapter 5
BOILER FRONT
40t TRAILER
(SUPPLIED BY
OWNER)
MOTOR E3
38.1ton
E4
7400
8800
2010
2840
3000
3550
1170
6550
6550
CL of ROAD E: 1160.440
2500
75t
MOBILE CRANE
(SUPPLIED BY
OWNER)
1700
5750
E1
E2
OIL
UNIT
5750
B1
B2
2500
7400
GL+12200
CL of BOILER E: 1210.840
2000
8800
GL+13287
1700
6550
A1
A2
GL+9532
UP
D.N
7000
GL+15842
2010
CL of I.D.F.
N: 769.020
1300
2840
MONORAIL FOR
IMPELLER CASING & ROTOR
BOS GL+13700(I-600x190)
SILENCER
SILENCER
GL+9532
GL+12200
A'
3000
6550
IMPELLER
CASING
12.0ton
REAR
CASING
3.6ton
UP
A5
GL+9532
OIL
UNIT
500
75t
MOBILE CRANE
(SUPPLIED BY
OWNER)
650 1700
3550
B3 B4
A3 A4
UP
B5
UP
ROTOR
31.5ton
1170
RAIN COVER
D.N
UP
C1
C2
D1
D2
R 65
0
W
(c ap ork rad 0
ac ity ius
3 9.4
ton)
GL+9532
MONORAIL FOR
REAR CASING
BOS GL+13700
(I-450x175)
D.N
C3
C4
D3
D4
PLAN
10400
12850
1050
MOTORIZED
HOIST
20ton
GL+15285
MSL+19785
min.
1890
GL+13700
MSL+18200
GL+12200
MSL+16700
REAR
CASING
3.6ton
GL+9500
MSL+14000
5310
A2
A3
A1
2000
RAIN COVER
GL+4500
MSL+9000
A4
OIL
UNIT
Rev.003
CARRIER
(SUPPLIED BY
OWNER)
5200
7020
7050
3. OVERHAUL PROCEDURE
REAR CASING (REF. TO SECTION A-A & B-B)
1) LIFT UP THE REAR CASING FROM THE
POSITION A1 TO A2 WITH MOTORIZED
HOIST
2) MOVE THE REAR CASING FROM THE
POSITION A2 TO A3 AND TURN IT.
3) PUT DOWN THE REAR CASING ON THE
CARRIER FROM THE POSITION A3 TO A4 .
4) MOVE THE REAR CASING FROM THE
POSITION A5 TO TEMPORARY STORAGE AREA.
4. PARTS WEIGHT
IMPELLER CASING
REAR CASING
ROTOR
: 12.0ton
: 3.6ton
: 31.5ton
AIR HOUSING
MOTOR
: 3.4ton
: 38.1ton
GL+9532
MONORAIL
890
4200
GL+12200
ELECTROSTATIC
PRECIPITATOR
3A
650
450
1700
1050
900 1050
2000
GL+12200
NOTES :
FLOOR(GL+12200)
450
4200
GL+9532
FLOOR(GL+12200)
1050 900
ELECTROSTATIC
PRECIPITATOR
3A
40t TRAILER
(SUPPLIED BY
OWNER)
MONORAIL FOR
REAR CASING
BOS GL+13700
(I-450x175)
GL+9532
500
AIR
HOUSING
3.4ton
15t TRUCK
(SUPPLIED BY
OWNER)
RAIN COVER
ELECTROSTATIC
PRECIPITATOR
3A
ELECTROSTATIC
PRECIPITATOR
3B
A'
B'
ELECTROSTATIC
PRECIPITATOR
3B
MONORAIL FOR
IMPELLER CASING & ROTOR
BOS GL+13700(I-600x190)
B'
FGD/EP/
ASH HANDLING
SYSTEM CONT. &
ELEC. BUILDING
7050
(c R6
a 5
W pac 00
o r it y
k
ra 3 9
di .4
us to
n
5200
10400
MM-M02.02
SECTION A-A
OVERHAUL OF REAR CASING
FIGURE 5-1A
Induced Draft Fan
Mitsubishi
5-15
Chapter 5
NOTES :
MOTORIZED
HOIST
37.5ton
IMPELLER
CASING
12.0ton
5050
B2
B3
B1
GL+15285
MSL+19785
GL+13700
MSL+18200
GL+12200
MSL+16700
GL+13700
MSL+18200
GL+12200
MSL+16700
min.
2150
GL+15285
MSL+19785
ROTOR
31.5ton
RAIN COVER
GL+9500
MSL+14000
C3
2000
RAIN COVER
MOTORIZED
HOIST
37.5ton
C2
TEMPORARY
RACK
(SUPPLIED BY
OWNER)
GL+4500
MSL+9000
C1
B4
7050
5200
5200
10400
7020
7050
SECTION A'-A'
OVERHAUL OF ROTOR
2010
1700
1700
2010
5200
10400
SECTION A-A
2840
2840
MOTORIZED
HOIST
37.5ton
4. PARTS WEIGHT
IMPELLER CASING : 12ton
: 3.6ton
REAR CASING
: 31.5ton
ROTOR
: 3.4ton
AIR HOUSING
: 38.1ton
MOTOR
MOTORIZED
HOIST
37.5ton
GL+15285
MSL+19785
GL+15285
MSL+19785
GL+13700
MSL+18200
GL+13700
MSL+18200
GL+12500
MSL+17000
MOTORIZED
HOIST
20ton
IMPELLER
CASING
12.0ton
MOTORIZED
HOIST
20ton
12
B2
REAR
CASING
3.6ton
A2
AIR
HOUSING
3.4ton
ROTOR
31.5ton
OM
BO
MOTOR
38.1ton
m
12
BO
OM
GL+12500
MSL+17000
C2
3550
1170
2000
A1
B1
E1
C1
GL+4500
MSL+9000
D1
GL+4500
MSL+9000
3000
3000
6550
6550
8800
75t
MOBILE CRANE
(SUPPLIED BY
OWNER)
D2
E2
Rev.003
40t TRAILER
(SUPPLIED BY
OWNER)
5200
MM-M02.02
GL+4500
MSL+9000
OIL
UNIT
CARRIER
(SUPPLIED BY
OWNER)
75t
MOBILE CRANE
(SUPPLIED BY
OWNER)
3. OVERHAUL PROCEDURE
IMPELLER CASING (REF. TO SECTION A-A)
1) LIFT UP THE IMPELLER CASING FROM THE
POSITION B1 TO B2 WITH MOTORIZED
HOIST
2) MOVE THE IMPELLER CASING FROM THE
POSITION B2 TO B3 AND TURN IT.
3) PUT DOWN THE IMPELLER CASING ON THE
CARRIER FROM THE POSITION B3 TO B4 .
4) MOVE THE IMPELLER CASING FROM THE
POSITION B5 TO TEMPORARY STORAGE AREA.
C4
OIL
UNIT
7020
GL+9500
MSL+14000
5050
min.
2150
MONORAIL
ELECTROSTATIC
PRECIPITATOR
3B
2000
ELECTROSTATIC
PRECIPITATOR
3A
8800
6550
3550
6550
SECTION B-B
SECTION B'-B'
OVERHAUL OF MOTOR
1170
FIGURE 5-1B
Induced Draft Fan
Mitsubishi
5-16
Chapter 5
5.2
Preparation
If disassembly of the moving blades and the hydraulic cylinder in IDF rotor
becomes necessary, all associated equipment is to be mechanically and
electrically isolated and an authorized work permit and valid isolation
certificate shall be in place prior to the commencement of work. The
following points are also to be considered while preparing for disassembly
and reassembly:
Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.
CAUTION
Wear safety glasses to protect your eyes during any inspection /
maintenance.
CAUTION
Always use the Personnel Protective Equipment (PPE) during
maintenance.
CAUTION
After completing maintenance in the oil lines of the bearing box /
oil unit, do a complete oil flushing.
MM-M02.02
Rev.003
b)
Disassembly
All data is to be recorded during the disassembly of each part. During
disassembly, make match marks on adjoining parts for reference during
the reassembly. The disassembly procedure is described as follows after
removing the ID fan impeller and rear casing assembly as detailed in
section 5.1.
5-17
Chapter 5
Remove the blot (29) and remove the side plate (12), (52).
Note
Remember to match mark the blades and their installed locations
before starting the disassembly of moving blades.
Note
When removing the blade, to prevent rotor rotation due to
unbalance, fix the rotor using chain blocks and remove the blades
in a balanced manner.
Remove the set screws (38) and the U-nut (37) and then unscrew the
nut for M/B shaft (13) by using special tool (spanner) and place it
down inside the rotor.
Take care that the M/B support bearing (56) does not fall down while
removing the nut for M/B shaft (13).
Lightly tap and remove the moving and M/B support bearing (56) and
place it inside the rotor along with the nut for M/B shaft (13).
Slowly pull the moving blade (1) & M/B shaft (7) outwards from the
rotor disk (9&10) handling the M/B support bearing (56), nut for M/B
shaft (13) and spacer (50) carefully.
Remove the M/B support bearing (56) and the nut for M/B shaft (13)
and spacer (50).
Rev.003
Mark the blades 1 to 16, position the shaft such that blade Nos. 1
and 2 are located at the topmost elevation and then remove the
blade Nos. 1 and 2.
(ii) Rotate the rotor by 180 such that blade Nos. 1 and 2 are located
at the bottom side and blade Nos. 9 and 10 at the top side and
then remove the blade Nos. 9 and 10.
MM-M02.02
(i)
(iii) Rotate the rotor by 90 such that blade Nos. 13 and 14 are
located at the top side, then lock the rotor and remove the blade
Nos. 13 and 14.
Induced Draft Fan
Mitsubishi
5-18
Chapter 5
(iv) Rotate the rotor by 180 such that blade Nos. 5 and 6 are located
at the top side, then lock the rotor and remove the blade Nos. 5
and 6.
(v) Rotate the rotor by 90 such that blade Nos. 15 and 16 are
located at the top side, then lock the rotor and remove the blade
Nos. 15 and 16.
(vi) Remove blade Nos.7 and 8.
(vii) Remove blade Nos.11 and 12.
(viii) Remove blade No. 3 and 4.
9
Remove the blade fixing bolts (32) and separate moving blade and
M/B shaft if needed. Usually moving blade and M/B shaft are not
disassembled.
Remove the bolts (47), retaining ring (37) from the servo cylinder (1)
nut (11) and remove the nut (11) and the MV packing (18).
Remove the bolts (12) and then remove the servo cylinder (1)
together with the bush (44). Recover the O-rings (20 and 21).
Remove the bush (44) from the cylinder cover (2) after removing
screw (46).
Unfold the lock washer (19) and unscrew the nut (6) from the rotor.
Remove the piston (5) from the rotor by using special tools (draw out
tool, bolt & nut). Recover the pin (28).
Remove the bolts (48), retaining ring (49) from the cylinder cover (2)
and remove the nut (10) and the MV packing (17).
Remove the pin (29) and withdraw the pilot sleeve carefully by using
special tools (draw out tool, guide bar & nut and bolt) and recover
O-rings (38 & 39).
Note
The pilot sleeve shall be kept in the oil bath together
Rev.003
Note
MM-M02.02
5-19
Chapter 5
Remove the driving coupling (4) from DE side by removing bolts (33).
Remove the side ring of actuator disk (11) from the DE side of the
rotor by removing the bolt (31).
Remove the crank arm (8) from it s position by removing the retaining
ring (26) along with the sliding piece for crank arm (53). Separate the
sliding piece for crank arm (53) from the crank arm (8) by removing
the retaining ring (45).
Note
Remove the torque limiter assembly by removing the lock nut
and keep it safely. No disassembly of the mechanism is to be
done at site. If found damaged, the same shall be replaced and
the defective one shall be sent to MHI, Nagasaki for repairs.
Remove the side ring of actuator disk (11 of Figure 2-6/5-3) from NDE
side of rotor by removing the bolt (31 of Figure 2-6/5-3).
MM-M02.02
Rev.003
Remove the regulating disk tighten nuts (17) and the washer (34&35)
by using special tool (wrench).
5-20
Chapter 5
Using puller remove the operating disks (10) at end of the regulating
shaft (3).
Remove screw (41) and the stopper plate (28) from both ends of the
main shaft.
Pull out the regulating shaft (3) from the NDE side.
Remove the bush (25) from both ends of the main shaft inner side.
Note
Sleeve replacement may involve machining.
Disassembly of Rotor
Refer to Figures 2-6 and 5-3.
CAUTION
When removing the rotor, take care of the proper supporting of
the entire rotor and bearing box assembly. The rotors are to be
gradually moved towards outside in a balanced manner.
Install two hydraulic jacks between the inner faces of the rotors (5&6)
in the same horizontal plane that contains the shaft center line.
By using special tools (spanner, fitting plate, fitting piece, spacer, bolt
and cylinder), partially unscrew the rotor tighten nuts (14&15) from the
driven end and let it remain on the shaft.
Apply heat to the center bore of the 1st rotor through which the main
shaft (2) passes the rotor. In normal operating temperature, the rotor
bore diameter is slightly less than the main shaft (2) outer diameter.
So, heating is required to expand the rotor bore diameter so that the
rotor can be pushed out of the shaft.
Note
Disassembly and reassembly of the rotor / main shaft
MM-M02.02
5-21
Chapter 5
CAUTION
We recommend using a gas burner to heat the rotor rather than
an oil bath. Burner flame must be wide to heat the rotor.
Always use red flame of Propane gas, not the blue flame of
Acetylene gas. To heat the rotor, move the flame uniformly over
the rotor inner and outer surfaces.
Do not heat until the paint is burnt or damaged.
The following steps shall explain the rotor heating procedure.
(i)
Two maintainers shall heat the rotor outer side (5), inside and outside.
(ii) Another two maintainers shall heat the bearing side of the rotor outer
side.
(iii) Target temperature of rotor surface is 100C.
(iv) When the rotor surface temperature reaches 100C, one maintainer
shall start heating the rotor outer side. At the same time, the second
maintainer shall start heating the boss internal i.e. shaft fitting area.
(v) Two maintainers who are heating the rotor on the bearing side, shall
heat the boss part gradually.
(vi) While heating, take extra care not to bend the rotor.
CAUTION
If the rotor is bent, internal component cannot be disassembled.
CAUTION
MM-M02.02
Rev.003
Remove the 2nd rotor using suitable lifting equipment and collect the
key (19).
5-22
Chapter 5
Note
Take care of hydraulic jacks dropping down.
Remove the rotor tighten nut (15) and repeat step 8 for 1st rotor (5).
CAUTION
When removing the rotors (5&6), take care of the proper
supporting of the rotor and bearing box assembly if the IDF is
maintained in the lay down area. The rotors are to be gradually
moved towards outside in a balanced manner.
c)
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified in Figure 4-1, Clearance Drawing for IDF. All used
gaskets and O-rings are to be discarded and replaced with new ones.
Reassembly of Rotor
Refer to Figures 2-6 and 5-3.
1
Note
To fix the main shaft, fill it with dry ice to reduce the
temperature
For fixing the rotor, heat it around to extend the center bore
diameter of the rotor
CAUTION
Rev.003
MM-M02.02
Always use red flame of Propane gas, not the blue flame of
Acetylene gas.
To heat the rotor, move the flame uniformly over the rotor inner
and outer surfaces.
Induced Draft Fan
Mitsubishi
5-23
Chapter 5
Two maintainers shall heat the 2nd rotor outer side (6), inside and
outside.
(ii) Another two maintainers shall heat the bearing side of the rotor
outer side (6).
(iii) Target temperature of rotor surface is 100C.
CAUTION
Do not heat until the paint is burnt or damaged.
CAUTION
If the rotor is bent, internal component cannot be assembled.
CAUTION
MM-M02.02
Rev.003
Install the rotor disks over the respective shaft keys (19).
Install the 2nd rotor (6) and then the 1st rotor disk (5).
Fasten the rotor tighten nuts (14&15) by using special tools (spanner,
fitting plate, fitting piece, spacer, bolt and cylinder).
5-24
Chapter 5
Apply oil/grease on the regulating shaft (3) and insert the operating
shaft from the NDE side.
Locate the bushes (25) on both ends of the main shaft and set the
stopper (41) with the machine screw (28).
Install the keys (20&21) on the DE and NDE ends of the regulating
shaft (3).
Install the regulating disks (9) on the DE and NDE sides such that the
disk buts the collar on the regulating shaft (3).
Locate the washer (34 & 35) and the regulating disk tighten nuts
(14&15) on the DE and NDE ends of the regulating shaft and tighten
them.
Connect the sliding piece for the crank arm (53) to the crank arm (8)
by fixing the retaining ring (45). Install the crank arm (8) in its marked
position with the retaining ring (26) along with the sliding piece for
crank arm (53). Insert the respective bushes (24)
Install the side ring of the actuator disk (11) on the DE side of the rotor
by fixing the bolt (31).
Install the side ring of the actuator disk (11) on the NDE side of the
rotor by fixing the bolt (31).
Install the bush (45) on the cylinder cover (2) by its fixing screws (46).
Install the cylinder cover (2) on the operating shaft along with
packings (17) and the bush (45) by bolts (33 of figure 5-3).
Apply grease to the lip of the MV-packing (45), then insert the
MV-packing into the slot ensuring that the lip is facing towards the
piston by using special tools (guide ring, tightening plate, inset ring,
guide bar & nut)
MM-M02.02
Rev.003
5-25
Chapter 5
Note
Be sure to assemble the MV-Packing in the direction
indicated in the drawing. If assembled in reverse direction, it
may cause oil leakage.
Note
Additional details on MV-packing insertion are provided in
Appendix H.
Note
Use the MV-packing insert tool supplied as a special tool for
the installation of MV-packing.
Install and gradually tighten the plate for MV packing (10) to the
cylinder cover (2) by bolts (48).
Install the retaining ring (49) after final tightening of the plate for MV
packing (10).
Insert the O-rings (38&39) on the pilot sleeve (4) and insert the pilot
sleeve to the regulating shaft by using special tool.
Secure the pilot sleeve (4) with the straight pin (29).
Install the locating pin (28) and locate the piston (5) with piston rings
(13) on the regulating shaft. Lock it in position by the nut for piston (6)
and washer (19).
Install the bush (44) with screw (46) on the cylinder (1).
Rev.003
14 Install the scroll (14) with the retaining rings (34) and screw (27) and
spring pin (33) on the pilot valve (3).
Note
MM-M02.02
5-26
Chapter 5
CAUTION
Remove any spilled oil from the working area to avoid slippage.
CAUTION
After any major inspection, do a complete oil flushing.
Install the bush (23) on the moving blade (1) and M/B shaft (7).
Slide the moving blade (1) and M/B shaft (7) through the hole on the
rotor and simultaneously locate the M/B support bearing (56), cover
(27), nut for M/B shaft (13) and spacer (50) from the inner side of the
rotors (5&6) and insert the shaft bottom end on to the crank arm (8).
Tighten the nut for M/B shaft (13) by using special tool (spanner) and
then lock it with U-nut (37) and set screw (38).
Complete the assembly of all shafts on both the rotors (5&6) following
the same sequence for disassembly.
Note
Control match marks of moving blades and shafts on the rotor
disks (5&6).
Apply lubricant to threads and seating surfaces when tightening
bolts.
Take care to locate the blade assemblies in their original position,
as they were prior to disassembly
CAUTION
MM-M02.02
Rev.003
5-27
Chapter 5
CAUTION
If a moving blade is sticking after assembly, confirm the
clearance and check for any crack.
5
Install side plate (12) on the rotor (5) by tightening bolts (29&30) as
per the torque given in Appendix A. Ensure that the balance weights
on the side plate are all in their original position.
Install side plate (52) on the rotor (6) by tightening bolts (29&30) as
per the torque given in Appendix A. Ensure that the balance weights
on the side plate are all in their original position.
Complete the assembly of all blades on both the rotors (5&6) following
the same sequence as for disassembly.
Measure and record the moving blade radial clearance between the
blade root and the rotor disk and ensure that the clearance is within
tolerance as indicated in Figure 4-1.
CAUTION
Do not machine the moving blades to achieve the required
clearance.
Note
Install the moving blade such that the leading edge of the
moving blade is toward the suction casing and the trailing
edge toward the rear casing.
Note
Ensure the moving blade stroke by using N2 gas etc, if
possible.
After ensuring the moving blade stroking, pilot valve shall be
MM-M02.02
Rev.003
kept in the oil bath till installing the rotor to the casing.
5-28
Chapter 5
SURVO CYLINDER
CYLINDER COVER
6
COVER
JOINT
10
SCROLL
FLOATING RING
19
O RING
21
22
24
BOLT
STRAIGHT PIN
31
SPRING PIN
RETAINING RING
38
PLUG
44
MM-M02.02
Rev.003
21
FIGURE 5-2
Induced Draft Fan
Mitsubishi 30
5-29
Chapter 5
60
1
32
56
MM-M02.02
Rev.003
38 37
FIGURE 5-3
Induced Draft Fan
Mitsubishi
5-30
Chapter 5
DRIVE END
HYDRAULIC
JACK
1st STAGE
ROTOR
BEARING
BOX
KEY
NUT
MAIN SHAFT
NUT
HYDRAULIC
JACK
A-A
HYDRAULIC
JACKS
ROTOR
DISK
Rev.003
B-B
MM-M02.02
MPTD-4-0661
5-31
Chapter 5
5.3
Preparation
If bearing box disassembly becomes necessary, all associated equipment
is to be mechanically and electrically isolated and an authorized work
permit and valid isolation certificate is to be in place prior to
commencement of work. The following points are also to be considered
when preparing for disassembly and reassembly:
Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.
CAUTION
Be careful not to put your finger in between the upper and the
lower casings during reassembly.
CAUTION
Always ensure that the wire slings, shackles, eyebolts and lifting
gear are certified to the Safe Working Load (SWL).
CAUTION
MM-M02.02
Rev.003
5-32
Chapter 5
b)
Disassembly
The disassembly of the bearing box can be carried out after the removal of
rotor wheel as explained in Sections 5.1 and 5.2 as the bearing box is a
single cylinder sandwiched between the two rotor disks.
All data is to be recorded during disassembly of each part. During
disassembly, make match marks on adjoining parts for reference during
reassembly. The disassembly procedure is described as follows:
Note
Protect the openings on the rotor with proper covers to
prevent the entry of dust.
CAUTION
Rigging and transportation of equipment must be carried out by
authorized persons. Care is to be taken where equipment weight
and center of gravity is to be considered.
Care is to be taken to protect the machined surfaces.
Clean the area around the bearing box before disassembly to prevent
foreign material from entering the bearing.
Drain the oil from the bearing box into a suitable container by
removing the drain pipe cover flange.
Note
Take care of damage of the pipe for oil return in transporting.
Note
Bearings removed from the shaft shall not be reused..
Remove the bolt (24) and washer (29) and then remove the bearing
box covers (36 &37) with O ring (16), labyrinth ring (50), seal ring (19)
and O ring (41) from both ends of the shaft.
Rev.003
Note
Take care of foreign material not entering the bearing.
MM-M02.02
Remove adjustable ring (2) from the bearing box by removing the
threaded pin (3) and then the O- ring (17).
5-33
Chapter 5
Remove the inspection hole cover (38) and the lube oil strainers (39)
and clean the oil strainers.
Using suitable chain pulley/block hoist place the bearing and the shaft
assembly in the vertical orientation over a support such that the
non-drive end remains at the top. Refer to Figure 5-6.
Note
Take care of the dropping of the outer surface of drive-end
bearing.
The complete NDE bearing assembly (43&44) and inner race of the
DE bearing (42) shall be lifted during above operation.
Note
MHI recommends to replace the seal ring (19) O-rings (16~18,
20~22, 41) and Packing (6~8) on every overhaul. Bearings are
to be changed during every 4 yearly overhauls. (If there is
spare every 8 years.)
CAUTION
Special care is to be taken to prevent the outer race of radial
bearing and the bush from falling.
Transport the shaft to the lay down area and fix it.
11
Remove the outer race of NDE roller bearings (43) from the non-drive
end of the rotor. Remove the oil distributor ring (48) between the roller
bearing and ball bearing. The inner race and outer race are provided
with 2 tapped holes (M12) for handling purpose. Use suitable lifting
bolts.
12
In order to remove the shrunk fit inner races of the bearings, install the
dry ice into the main shaft. After enough cooling, apply heat to the
inner races of the bearing at drive and non drive end. Add any
additional force required to remove the inner races.
13
14
Remove the inner race of the roller bearing and ball bearings at the
non drive end along with the spacers. Carefully pull out the assembly
such that the loose bearing spacers (45&46) and oil distributor ring
(47&48) do not fall and get damaged.
15
MM-M02.02
Rev.003
10
5-34
Chapter 5
c)
16
Rotate the bearing box and put it in the DE side up position. Then
remove the outer race with rollers of drive end bearing (42).
17
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified in Figure 4-1, Clearance Drawing for IDF. The
used gaskets and O-rings are to be discarded and replaced with new
ones.
Refer to Figures 5-5 & 5-6.
1
Note
The reassembly of the bearings and the coupling hub on the
rotor to be carried out in the vertical position as indicated in
Figure 5-6. Only new bearings shall be assembled.
Locate the O-rings (18) and bush (40) and restore the radial bearing
outer race with rollers inside the DE of the bearing box and put the
bearing box in the NDE side up position on the temporary support.
Heat the inner race of the DE radial bearing (42) in an oil bath to about
100C until the inner race diameter increases by more than 0.1 mm.
Transfer the inner race of radial bearing (42) from the oil bath or oven
and install it on the rotor so that the inner race abuts the step provided
on the rotor. A weight or pressure should be applied to the inner race
to ensure it remains in contact with the step on the rotor as it cools.
Note
Allocation of bearings is referred to the match marks made on
their outer surface.
MM-M02.02
Rev.003
Cool down to ambient temperature and next install the spacer (45)
and oil distributor (47).
5-35
Chapter 5
Following step7 install the 2nd ball bearing (44). Install the bearing
spacer (46) and oil distributor ring (48) and finally the NDE roller
bearing (43).
Install the O-ring (17) in the slot on the inner surface of bearing box.
10 Install the O-ring (41) in the slot on the inner surface of the sleeves
(49) and then install the sleeves onto the rotor ends.
11 Transport the rotor shaft assembly and return it into the bearing box
through the NDE side.
Note
Ensure that all the bearings (42, 43&44), oil distributor ring,
bushes around the radial bearings seat properly in their
respective locations
12 After checking for cleanliness, place the bearing box and shaft
assembly in a horizontal position onto the main support structure
prepared for rotor wheel disassembly.
13 Install the seal rings (19), adjustable rings (2) and the O-rings (16, 17,
20~22) at the bearing box covers (36&37) and tighten the bearing box
covers (36&37) with the fixing bolts and washers (24&29).
Note
Check and adjust the labyrinth seal clearance according to the
value specified in Figure 4-1.
14 Clean the lube oil strainers (39) and the inspection hole cover (38) on
the bearing box.
CAUTION
Take care that there is no foreign matter in the lubricating oil line.
Lubricating holes for strainers, bearing box cover lubricating oil
lines are very small. When assembling, make sure that the
lubricating holes are not blocked.
Rev.003
CAUTION
MM-M02.02
After maintenance in the oil lines of the bearing box / oil unit,
arrange oil flushing.
5-36
Chapter 5
34
50
28
9
Rev.003
24
25
MM-M02.02
MPTD-3-0074
FIGURE 5-5
5-37
Chapter 5
ITEM
46
43
48
44
47
45
BEARING BOX
40
BUSH
42
DE BEARING (ROLLER)
43
44
45
BEARING SPACER 1
46
BEARING SPACER 2
47
48
51
MAIN SHAFT
51
42
DRIVE END
DESCRIPTION
INNER RACE
40
40
42
OUTER RACE
MM-M02.02
Rev.003
TEMPORARY SUPPORT
(SHOP FABRICATED)
MPTD-4-0660
FIGURE 5-6
Induced Draft Fan
Mitsubishi
5-38
Chapter 5
5.4
Preparation
Movable blade regulating mechanism linkage is not normally included in
overhaul maintenance but if it should ever be necessary, the procedure is
as follows. All associated equipment is to be mechanically and electrically
isolated and an authorized work permit and valid isolation certificate shall
be in place prior to commencement of work. The following points are also
to be considered while preparing for disassembly and reassembly:
Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.
MM-M02.02
Rev.003
5-39
Chapter 5
b)
Disassembly
All data is to be recorded during the disassembly of each part. During
disassembly, make match marks on adjoining parts for reference during
the reassembly. The disassembly procedure is described as follows:
Refer to Figures 2-8 and 5-7.
1
Remove the split pins (20&42), pins (5), bolts (40) and nuts (12&41),
thus disconnecting the linkage assembly both from the pilot valve end
and the control drive. Remove the spherical bearings (6) and lever (1).
While removing the pin from the lever, take care not to drop the
spherical bearing (6) or the lever (1).
Note
If control drive unit is to be removed from the foundation during
disassembly, loosen the bolts (10) on the stand for drive unit (34).
Similarly if detective cylinder assembly (29) is to be removed
loosen and remove the bolts (38&39). For disassembly and
reassembly of the control drive unit and detective cylinder
assembly please refer to the respective I&C vendor manual.
Remove the taper pin (22&23), U-nuts (26&27) and set screws
(18&28).
Remove the levers (32&33) from the operating shaft (30) and remove
the piece (4).
Remove the spring pin (24) and the scale pointer (31).
Remove the bolts (9), washers (13) and nuts (14), loosen set screws
(36&46). Remove the dust protect cover (37).
Remove the ball bearing units (7&8) secured to the operating shaft
support (45).
Remove the taper pin (21), bolts (11) and washers (16).
10 Remove the stand for scale plate (2) together with scale plate (3) from
the operating shaft support (45).
MM-M02.02
Rev.003
11 Withdraw the operating shaft (30) axially from outside the rear casing
(43).
5-40
Chapter 5
c)
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.
Refer to Figure 5-7.
1
Clean the operating shaft (30) and insert it through the operating shaft
support (45).
Locate the scale plate stand (2) on the operating shaft support (45)
flange with taper pin (21).
Secure it by bolts (11) and washers (16) from outside the rear casing
(43).
Pack the ball bearing units (7&8) at both ends with lubricating grease
and insert it through the operating shaft (30) from inside the rear inner
casing.
Secure the ball bearing units (7&8) to the operating shaft support (45)
flange with bolts (9), washers (13), (14).
Install the scale pointer (31) and secure it to the operating shaft by the
spring pin (24).
10 Insert the piece (4) then insert the lever (32) onto the operating shaft
(30) from inside the rear inner casing.
11 Install the taper pin (22) and the U-nut (26).
12 Set the lever (32) in line with the pilot valve axis.
MM-M02.02
Rev.003
13 Install and tighten the set screws (18 and 19) after finalizing the lever
position.
14 Install the spherical bearings (6) into the apertures provided on the
lever (1),
15 Install the lever (1) and secure it with pins (5) and nuts (12) on both
ends of the lever.
16 Insert the split pins (20).
Induced Draft Fan
Mitsubishi
5-41
Chapter 5
17 Insert the lever (33) onto the operating shaft (30) from outside the rear
housing.
18 Install the taper pin (23) and the U-nut (27).
19 Set the lever (33) in line with the actuator lever axis.
20 Install and tighten the set screw (28) after finalizing the lever position.
21 Connect the lever (33) to the actuator linkage assembly by installing
the bolt (40), nut (41) and split pin (42).
22 Ensure that the direction of the blade sticking detector (29) as shown
in Figure 5-7 before connecting the lever (33).
23 Start the control oil pump and check the blade operation from 0% to
100% by manually operating the actuator carefully.
24 Carryout any minor adjustments by altering the length of the lever (33)
and/or the blade sticking detector linkage assembly to achieve the full
range of blade operation.
25 Loosen the spring pin (24) and adjust the pointer (31) to match the
blade position of 0% to 100%.
MM-M02.02
Rev.003
5-42
Chapter 5
ITEM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
30
21
22
23
DESCRIPTION
LEVER
STAND FOR SCALE PLATE
SCALE PLATE
PIECE
PIN
SPHERICAL BEARING
BALL BEARING UNIT
BALL BEARING UNIT
BOLT
BOLT
SOCKET HEAD BOLT
NUT
WASHER
SPRING WASHER
SPRING WASHER
WASHER
SCREW
SET SCREW
SET SCREW
SPLIT PIN
TAPER PIN
THREAD END TAPER PIN
THREAD END TAPER PIN
ITEM
DESCRIPTION
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
SPRING PIN
WASHER
U-NUT
U-NUT
SET SCREW
DETECTIVE CYLINDER ASS'Y
OPERATING SHAFT
POINTER
LEVER
LEVER
STAND FOR DRIVE UNIT
HAWK ANCHOR BOLT
SET SCREW
DUST PROTECT COVER
BOLT
BOLT
BOLT
NUT
SPLIT PIN
REAR CASING
REAR INNER CASING
OPERATING SHAFT SUPPORT
SET SCREW
45
8
46
MM-M02.02
Rev.003
MPTD-3-0073
MPTD-3-0386
FIGURE 5-7
Induced Draft Fan
Mitsubishi
5-43
Chapter 5
5.5
Preparation
If IDF coupling disassembly becomes necessary, all associated
equipment is to be mechanically and electrically isolated and an
authorized work permit and valid isolation certificate is to be in place prior
to commencement of work. The following points are also to be considered
when preparing for disassembly and reassembly:
b)
Have all necessary drawings and documents (log sheets, field record
book, etc.) ready prior to the start of work.
Disassembly
All data is to be recorded during disassembly of each part. During
disassembly, make match marks on adjoining parts for reference during
reassembly. The disassembly procedure is described as follows:
Refer to Figure 2-5 and proceed as follows.
1
Thoroughly clean the surrounding area and the suction casing (50)
before commencement of work.
Remove the coupling bolts (8) and U-nuts (9) from the coupling flange
at the non-drive end (fan side) securing the hub (2) and the spacer
(3).
Note
Leave one coupling bolt and nut in position (preferably at the
bottom hole) to prevent the element from falling during
removal. Loosen this bolt and nut to provide a gap for the
Gently tap and remove the overload washers (7) from the coupling
except from the hole where the coupling bolt has not been removed.
Gently tap and rotate the element (4) with respect to the remaining
coupling bolt.
Support the spacer (3) suitably and remove the last coupling bolt (8)
and nut (9) from the coupling between the spacer (3) and the hub (1).
Remove the washers (5) and bushes (6) provided on this coupling
bolt.
MM-M02.02
Rev.003
5-44
Chapter 5
c)
Support the hub (2) and remove all the reamer bolts and nuts
securing the hub (2) to the fan rotor coupling flange and remove the
spacer (2) by using chain block.
Provide a hub removal tool and withdraw the hub from the shaft.
Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.
Refer to Figure 2-11 and proceed further as follows.
1
Check the shaft and the internal surface of the hub. Remove any
scratches or blemishes on the surface.
Check the shaft key and the key ways to ensure that the surfaces are
smooth.
Insert the key into shaft key way and then into the hub key way to
confirm the fit.
Measure the outside diameter of the shaft and the bore of the hub,
and record these Figures.
Clean the shaft and the hub. Insert the key into shaft key way. Heat
the hub in an oil bath to approximately 100C and fit the hub onto the
shaft.
Install and secure the hub (2) to the driving coupling (Figure 2-6, (4))
with the reamer bolts (39) and nuts (40).
MM-M02.02
Rev.003
10 Grease the faces between the element (4), washers (5) and bushes
(6). Then tighten the reamer bolts to the torque specified in Appendix
A.
Refer to Figure 2-5.
11 Remove the tools and tackles from inside the suction casing (50).
12 Restore the suction inner casing (55) and coupling cover assy (58).
5-45
Chapter 5
MOTOR SIDE
F.F. COUPLING
CL OF FAN
5 3
5 3
4
1
2
A
9
10
B-B
Rev.003
MM-M02.02
FIGURE 5-8
Induced Draft Fan
Mitsubishi
7
A-A
ITEM
MPTD-4-1216
1
2
3
4
5
6
7
8
9
10
DESCRIPTION
JOINT
ADJUSTABLE BOLT
PIN
BEARING
RETAINING RING
BOLT, NUT
BOLT
SUPPORTING PLATE
SUPPORTING PLATE
SUPPORTING PLATE
5-46
Chapter-6
Corrective Maintenance
C h a p t er
6 Corrective Maintenance
Corrective maintenance is the repair or replacement work undertaken for sudden failure of
any part or component of the equipment. Though a well planned preventive maintenance
program tries to minimize the probability of occurrence of sudden failure of equipment,
provision for attending these unscheduled maintenance requirements is to be made.
Corrective maintenance work is to be given priority depending on the seriousness of the
problem faced and the impact on plant operations. The schedule for repair of any
equipment should be carefully planned to keep outage time to a minimum.
During such repair or replacement work, an inspection is to be carefully conducted to
determine why the equipment has failed. Good corrective maintenance requires, not only
the quick restoration of the failed equipment back into service but also demands every
effort to identify and record the root cause of the failure. The inspection results can be of
significant help in exploring the exact reason for the failure. The findings, along with
possible rectification proposals, are to be used as a feedback to update the preventive
maintenance procedures.
6.1
Prerequisites
The necessary prerequisites for the corrective maintenance of the IDF are as
follows:
a)
Scheduling
Unlike preventive maintenance, scheduling activity only starts after failure of
the equipment. Depending on the severity of the problem, the importance of
the service provided by the failed equipment and availability of manpower to
attend to the problem, a contingency schedule is to be prepared to solve the
problem at the earliest opportunity. The schedule should clearly indicate the
critical path activity and assign the priority for different parallel activities.
Finally, once the schedule is agreed, strict adherence to it is to be maintained
to ensure timely completion of the maintenance activity.
b)
Departmental Interface/Notification
Refer to Section 4.1.2, Departmental Interface/Notification.
MM-M02.02
Rev.003
c)
Isolation of Equipment
Refer to Section 4.1.3, Isolation of Equipment.
d)
Safety Precautions
Refer to Section 4.1.4, Safety Precautions.
6-1
Chapter-6
6.2
Corrective Maintenance
Preparation
a)
b)
Documentation
Refer to Subsection 4.2.1 b), Documentation.
6.3
Troubleshooting
MM-M02.02
Rev.003
This section provides information about carrying out troubleshooting and servicing
for the IDF, pertaining to mechanical maintenance staff. Tables of Faults, Possible
Causes and Remedies have been provided to assist in troubleshooting by qualified
users. If any new kind of problem is encountered which is not listed in the following
table, contact the manufacturer for assistance.
6-2
Chapter-6
TABLE 6-1
Fault
Vibration
TROUBLESHOOTING IDF
Possible Cause
Remedy
Bearing damaged
Replace bearings
Coupling deformation
Ingress of debris
Misalignment of linkage/levers
Repair or replace
Strainer plugged
Control/lubricating oil
pressure high
Control/lubricating oil
leakage
Replace O-rings
Bearing temperature
high
Abnormal noise
Control/lubricating oil
pressure low
MM-M02.02
Rev.003
Corrective Maintenance
6-3
Chapter-7
Recommended Lubrication
C h a p t er
MM-M02.02
Rev.003
7-1
Appendix A
A p p en d i x
A Torque Chart
TABLE A-1 TORQUE CHART
Description
Size
Quantity
M32
192
992 Nm
M52
20
4020 Nm
M42
1667 Nm
M30
56
981Nm
M30
48
981Nm
M30
32
981Nm
M10
32
21 Nm
M36
1667 Nm
M36
1666 Nm
M36
1666 Nm
M300
73550 Nm
Remarks
Tighten the diametrically opposite bolts in sequence at Initial Torque - first outer
periphery and then inner periphery.
Tighten the diametrically opposite bolts in sequence at 100% Torque - first outer
periphery and then inner periphery.
Rev.003
MM-M02.02
Note:
Torque
Perform caulking.
A-1
Appendix B
A p p en d i x
MM-M02.02
Rev.003
B Spare Parts
B-1
Appendix B
MM-M02.02
Rev.003
TABLE B-1
Eqt.
Description
Man.
Parts
No.
(Note 2)
Eqt.
Supplier
Parts.
ID. No.
Per
each
Eqt.
MOVING BLADE
SUPPORT BRG.
IDF
LATER
IDF
03HNCO1
AN1
MAIN BEARING
ASSEMBLY
IDF
MHINGA
03HNCO1
AN1
SLIDING PIECE
SLEEVE
MHINGA
03HNCO1
AN1
MHINGA
03HNCO1
AN1
MHINGA
On Hand Qty.
Total Qty.
Spare
Parts
(1yr) Opn
Strategic
Spare
Expected
Frequency of
Replacement
Months
32
64
64
48
36
J-TEXT
LATER
72
MHI-NGA
LATER
48
36
J-TEXT
IDF
LATER
32
64
64
48
MHI-NGA
IDF
LATER
32
64
64
48
MHI-NGA
IDF
LATER
32
64
64
48
MHI-NGA
03HNCO1
AN1
PISTON RING
IDF
LATER
48
MHI-NGA
MHINGA
03HNCO1
AN1
MV PACKING
IDF
LATER
48
MHI-NGA
MHINGA
03HNCO1
AN1
IDF
LATER
48
MHI-NGA
MHINGA
03HNCO1
AN1
10
IDF
LATER
24
MHI-NGA
MHINGA
03HNCO1
AN1
11
IDF
LATER
48
MHI-NGA
Supplier
Name
Eqt. ID
(Note 1)
Parts
ID
MHINGA
03HNCO1
AN1
MHINGA
03HNCO1
AN1
MHINGA
Parts Description
Lead Time
(Month)
Receipt of
PO - FOB
Name of
Manufacture
(Note 3)
Remark
Note1 : Equipment ID No. will be allocated by the buyer for each Project Equipment ID i.e. represents a unique ID No. of the Spare Parts.
Note2 : Where the manufacturers drawings and parts nos is to be provided by the project, such number shall be indicated. If not the equipment supplier shall indicate its own no. such as
catalogue no., product no., Type no. etc, for easy reference.
Note3: If the equipmment supplier recommends The Buyer/Owner purchase the spare parts from the manufacturer, the name of the manufacturer, shall be indicated.
Note4: In accordance with the commercial terms and conditions agreed in purchase order.
Note5: Price should be valid for a period of minimum for 6 months.
Note6: MPIM-8-8-1 MHI document
Note7: Status is categorized into ordered, to be ordered, back ordered and received.
B-2
Appendix B
MM-M02.02
Rev.003
TABLE B-1
Eqt.
Description
Man.
Parts
No.
(Note 2)
Eqt.
Supplier
Parts.
ID. No.
Per
each
Eqt.
IDF
LATER
13
MANHOLE PACKING
IDF
03HNCO1
AN1
14
LINE STRAINER
IDF
MHINGA
03HNCO1
AN1
15
MHINGA
03HNCO1
AN1
16
MHINGA
03HNCO1
AN1
MHINGA
MHINGA
Supplier
Name
Eqt. ID
Note 1
Parts
ID
MHINGA
03HNCO1
AN1
12
MHINGA
03HNCO1
AN1
MHINGA
On Hand Qty.
Expected
Frequency of
Replacement
Months
Lead Time
(Month)
Receipt of
PO - FOB
Name of
Manufacture
Total Qty.
Spare
Parts
(1yr) Opn
Strategic
Spare
LATER
LATER
MHI-NGA
IDF
LATER
120
MHI-NGA
MOVING BLADE
IDF
LATER
32
64
64
120
10
MHI-NGA
17
IDF
LATER
48
MHI-NGA
03HNCO1
AN1
18
V RING
IDF
LATER
48
MHI-NGA
03HNCO1
AN1
19
IDF
LATER
48
MHI-NGA
Parts Description
Remark
MHI-NGA
MHI-NGA
Note1 : Equipment ID No. will be allocated by the buyer for each Project Equipment ID i.e. represents a unique ID No. of the Spare Parts.
Note2 : Where the manufacturers drawings and parts nos is to be provided by the project, such number shall be indicated. If not the equipment supplier shall indicate its own no. such as
catalogue no., product no., Type no. etc, for easy reference.
Note3: If the equipmment supplier recommends The Buyer/Owner purchase the spare parts from the manufacturer, the name of the manufacturer, shall be indicated.
Note4: In accordance with the commercial terms and conditions agreed in purchase order.
Note5: Price should be valid for a period of minimum for 6 months.
Note6: MPIM-8-8-1 MHI document
Note7: Status is categorized into ordered, to be ordered, back ordered and received.
B-3
Appendix C
A p p en d i x
MM-M02.02
Rev.003
C Special Tools
C-1
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
PJ No.
RG
34
03HNC0
1AN1
Tool
ID
1-1
Special Tool
Name/
Description
SUPPORTING
TOOL
Name of Equipment
for which special tools
used
IDF
B07200-0002-001001
2 SET
Purpose
FOR FF
COUPLING
Ref. Instruction /
Doc/DwgsNote # 3
N29-10M-7096
Weight
24.3 kg
Remarks
ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30x1.5 (2PC)
- NUT: M30x1.5 (2PC)
SPECIAL TOOLS SHALL BE USED
UNDER MHI SUPERVISION
RG
35
03HNC0
1AN1
1-2
SUPPORTING
TOOL
IDF
B07200-0002-001002
2 SET
FOR FF
COUPLING
N29-10M-7096
12.0 kg
ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30x1.5 (1PC)
- NUT: M30x1.5 (1PC)
SPECIAL TOOLS SHALL BE USED
UNDER MHI SUPERVISION
RG
36
03HNC0
1AN1
1-3
SUPPORTING
TOOL
IDF
B07200-0002-001003
2 SET
FOR FF
COUPLING
N29-10M-7096
24.9kg
ASSEMBLING PARTS
- ADJUSTING BOLTS:
M30x1.5 (2PC)
- NUT: M30x1.5 (2PC)
SPECIAL TOOLS SHALL BE USED
UNDER MHI SUPERVISION
RG
37
03HNC0
1AN1
1-4
JOINT BAR
ASSEMBLY
IDF
B07200-0002-001-
10 SET
004
FOR
SUPPORTING
TOOL
N29-10M-7096
4.5 kg
ASSEMBLING PARTS
- PIN : 5 PCS
- BEARING: NAST 50R (5
PC)
- RETAINING RING:50
(5PC)
SPECIAL TOOLS SHALL BE USED
UNDER MHI SUPERVISION
RG
38
39
03HNC0
1AN1
1-5
03HNC0
1AN1
BOLT NUT
M16x46
IDF
SPANNER
IDF
B07200-0002-001-
18 SET
FOR
SUPPORTING
TOOL
N29-10M-7096
0.141 kg
1 SET
FOR M/B
FASTENING
NUT
N29-10M-7096
1.12 kg
005
B07200-0002-002001
MM-M02.02
Rev.003
RG
C-2
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
PJ No.
RG
RG
RG
RG
RG
40
41
03HNC0
1AN1
42
43
44
45
03HNC0
1AN1
03HNC0
1AN1
3-1
3-2
3-3
3-4
03HNC0
1AN1
4-1
03HNC0
1AN1
4-2
Special Tool
Name/
Description
INSERT PIECE
PLATE
BOLT, NUT
M12
WIRE BAND
150
GUIDE
TIGHTENING
PLATE
Name of Equipment
for which special tools
used
Suppliers ID No.
(Note 2)
IDF
B07200-0002-003001
IDF
IDF
IDF
IDF
IDF
B07200-0002-003002
B07200-0002-003003
B07200-0002-003-
Purpose
FOR MOVING
BLADE ARM
BUSH
FOR MOVING
BLADE ARM
BUSH
1 SET
FOR MOVING
BLADE ARM
BUSH
2 SET
FOR MOVING
BLADE ARM
BUSH
FOR MV
PACKING
FOR MV
PACKING
004
B07200-0002-004001
B07200-0002-004002
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
2.3 kg
0.93 kg
0.25kg
0.08 kg
N29-10M-7096
3.8 kg
N29-10M-7096
2.8 kg
MM-M02.02
Rev.003
RG
03HNC0
1AN1
Tool
ID
C-3
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
PJ No.
Tool
ID
Special Tool
Name/
Description
Name of Equipment
for which special tools
used
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
FOR CYLINDER
T
RG
46
03HNC0
1AN1
4-3
INSERT RING
IDF
B07200-0002-004003
FOR MV
PACKING
N29-10M-7096
2.6 kg
FOR CYLINDER
T
RG
47
03HNC0
1AN1
4-4
IDF
B07200-0002-004004
3 SET
FOR MV
PACKING
N29-10M-7096
0.19 kg
RG
48
03HNC0
1AN1
5-1
GUIDE RING
IDF
B07200-0002-005001
FOR MV
PACKING
N29-10M-7096
4.5kg
RG
49
03HNC0
1AN1
5-2
TIGHTENING
PLATE
IDF
B07200-0002-005-
002
FOR MV
PACKING
N29-10M-7096
4.0 kg
RG
50
03HNC0
1AN1
5-3
INSERT RING
IDF
B07200-0002-005-
003
FOR MV
PACKING
N29-10M-7096
3.4 kg
51
03HNC0
1AN1
5-4
IDF
B07200-0002-005004
3 SET
FOR MV
PACKING
N29-10M-7096
0.19 kg
MM-M02.02
Rev.003
C-4
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
PJ No.
RG
RG
RG
RG
RG
Special Tool
Name/ Description
Name of Equipment
for which special
tools used
Suppliers ID No.
(Note 2)
B07200-0002-006001
52
03HNC0
1AN1
6-1
RING SPANNER
IDF
53
03HNC0
1AN1
6-2
BOLTM16x50
IDF
03HNC0
1AN1
7-1
03HNC0
1AN1
7-2
03HNC0
1AN1
8-1
03HNC0
1AN1
8-2
54
55
56
57
DRAW OUT
TOOL
IDF
IDF
DRAW OUT
TOOL
IDF
IDF
B07200-0002-006002
B07200-0002-007001
B07200-0002-007-
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
Weight
Remarks
9.0 kg
0.119 kg
1SET
FOR PISTON
N29-10M-7096
21.0kg
2SET
FOR PISTON
N29-10M-7096
0.76 kg
1SET
FOR PILOT
SLEEVE
N29-10M-7096
7.0 kg
2SET
FOR PILOT
SLEEVE
N29-10M-7096
1.56 kg
002
B07200-0002-008001
B07200-0002-008001
MM-M02.02
Rev.003
RG
Tool
ID
C-5
Appendix C
TABLE C-1
RG
RG
RG
RG
RG
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
BOLT M8x20
IDF
B07200-0002-008003
FOR PILOT
SLEEVE
SPANNER
IDF
1 SET
Tool
ID
Special Tool
Name/ Description
58
03HNC0
1AN1
8-3
59
03HNC0
1AN1
9-1
03HNC0
1AN1
9-2
03HNC0
1AN1
9-3
03HNC0
1AN1
9-4
03HNC0
1AN1
9-5
60
61
62
63
FITTING PLATE
FITTING PIECE
FITTING PIECE
SPACER
IDF
IDF
IDF
IDF
B07200-0002-009001
B07200-0002-009002
B07200-0002-009-
Weight
Remarks
N29-10M-7096
0.013 kg
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096-
117.8 kg
2 SET
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096
14.4kg
2 SET
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096
4.9 kg
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096
5.0 kg
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096
1.2 kg
003
B07200-0002-009004
B07200-0002-009005
MM-M02.02
Rev.003
RG
Name of Equipment
for which special
tools used
Eqt. ID
*(Note 1)
PJ No.
C-6
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
Tool
ID
Special Tool
Name/ Description
64
03HNC0
1AN1
9-6
BOLT M30x50
65
03HNC0
1AN1
9-7
03HNC0
1AN1
10-1
03HNC0
1AN1
10-2
PJ No.
RG
RG
RG
RG
RG
RG
RG
66
67
68
69
70
71
03HNC0
1AN1
10-3
03HNC0
1AN1
10-4
03HNC0
1AN1
11-1
03HNC0
1AN1
11-2
CYLINDER
Name of Equipment
for which special
tools used
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
IDF
B07200-0002-009006
6 SET
FASTENING
NUT FOR
ROTOR DISK
N29-10M-7096
2 SET
FASTENING
NUT FOR
ROTOR DISK
IDF
SOCKET
WRENCH M30
IDF
SOCKET
WRENCH M22
IDF
SOCKET
WRENCH M42
SOCKET
WRENCH M30
SPECIAL EYE
BOLT
SPECIAL EYE
BOLT
IDF
IDF
IDF
IDF
B07200-0002-009007
B07200-0002-010001
B07200-0002-010-
Weight
Remarks
0.58 kg
N29-10M-7096-
2.0 kg
FOR TORQUE
WRENCH
3.14kg
FOR TORQUE
WRENCH
0.67 kg
FOR SOCKET
HEAD BOLT
1.6 kg
FOR SOCKET
HEAD BOLT
1.2 kg
FOR ROTOR
3.5 kg
FOR ROTOR
24.5 kg
002
B07200-0002-010003
B07200-0002-010004
B07200-0002-011-
001
B07200-0002-011002
MM-M02.02
Rev.003
RG
C-7
Appendix C
TABLE C-1
RG
RG
RG
RG
RG
RG
RG
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
INSERT PIECE
IDF
B07200-0002-012001
INSERT PIECE
IDF
Tool
ID
Special Tool
Name/ Description
72
03HNC0
1AN1
12-1
73
03HNC0
1AN1
12-2
03HNC0
1AN1
12-3
03HNC0
1AN1
12-4
03HNC0
1AN1
13-1
03HNC0
1AN1
13-2
74
75
76
77
78
79
03HNC0
1AN1
14-1
03HNC0
1AN1
14-2
DISTANCE
SLEEVE
IDF
IDF
GUIDE TOOL
NUT M20
WRENCH
WRENCH
IDF
IDF
IDF
IDF
B07200-0002-012002
B07200-0002-012003
B07200-0002-012-
Weight
Remarks
N29-10M-7096
2.0 kg
N29-10M-7096-
1.9 kg
0.16 kg
1 SET
0.41 kg
FOR CASING
3.5 kg
12
FOR CASING
0.059 kg
FOR
OPERATION
SHAFT NUT
23.0 kg
FOR
OPERATION
SHAFT NUT
18.8 kg
004
B07200-0002-013001
B07200-0002-013-
002
B07200-0002-014001
B07200-0002-014002
MM-M02.02
Rev.003
RG
Name of Equipment
for which special
tools used
Eqt. ID
*(Note 1)
PJ No.
C-8
Appendix C
TABLE C-1
RG
RG
RG
RG
RG
RG
RG
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
GUIDE BAR
IDF
B07200-0002-015001
FOR CYLINDER
COVER
NUT TM30
IDF
Tool
ID
Special Tool
Name/ Description
80
03HNC0
1AN1
15-1
81
03HNC0
1AN1
15-2
03HNC0
1AN1
15-3
03HNC0
1AN1
15-4
03HNC0
1AN1
16
82
83
84
85
86
87
03HNC0
1AN1
17
03HNC0
1AN1
18
03HNC0
1AN1
19-1
GUIDE BAR
NUT TM42
GUIDE TOOL
SOCKET
WRENCH
IDF
IDF
IDF
IDF
TORQUE
WRENCH
IDF
BOX WRENCH
FOR S-65
IDF
B07200-0002-015002
B07200-0002-015003
B07200-0002-015-
Weight
Remarks
1.81kg
FOR CYLINDER
COVER
0.21kg
FOR CYLINDER
3.8kg
FOR CYLINDER
0.58kg
FOR
OPERATING
SHAFT BUSH
11.4kg
FOR TORQUE
LIMITER
1.10kg
004
B07200-0002-016000
B07200-0002-017000
B07200-0002-018-
1 SET
FOR BOLT
21.1kg
FOR FF
COUPLING
5.1kg
000
B07200-0002-019001
MM-M02.02
Rev.003
RG
Name of Equipment
for which special
tools used
Eqt. ID
*(Note 1)
PJ No.
C-9
Appendix C
TABLE C-1
Eqt. ID
*(Note 1)
Tool
ID
Special Tool
Name/ Description
Name of Equipment
for which special
tools used
Suppliers ID No.
(Note 2)
Purpose
Ref. Instruction /
Doc/DwgsNote # 3
88
03HNC0
1AN1
19-2
STRIKING FACE
RING SPANNER
IDF
B07200-0002-019002
FOR FF
COUPLING
89
03HNC0
1AN1
19-3
STRIKING FACE
OPEN END
SPANNER
IDF
03HNC0
1AN1
20-1
GAS CHARGING
3-WAY VALVE
(M3-G02)
IDF
03HNC0
1AN1
20-2
HOSE
(H210-L02)
IDF
PRESSURE
GAUGE
(AT1/4x60x
6MPa)
IDF
ADAPTER
(AD-23)
IDF
PJ No.
RG
RG
RG
RG
RG
RG
90
91
92
93
94
03HNC0
1AN1
20-3
03HNC0
1AN1
20-4
03HNC0
1AN1
20-5
CUP NUT
WRENCH
(TWG81)
IDF
B07200-0002-019003
B07200-0002-020001
B07200-0002-020-
Weight
Remarks
4.4kg
FOR FF
COUPLING
7.5kg
FOR
ACCUMULATOR
0.48kg
FOR
ACCUMULATOR
0.64
FOR
ACCUMULATOR
0.18kg
FOR
ACCUMULATOR
0.18kg
FOR
ACCUMULATOR
1.4kg
002
B07200-0002-020003
B07200-0002-020004
B07200-0002-020005
MM-M02.02
Rev.003
RG
C-10
Appendix D
A p p en d i x
D Coupling Alignment
COUPLING ALIGNMENT (IDF)
The following basic alignment procedure is suitable for fan coupling; however, for certain types of
coupling reference should be made to the manufacturers instructions.
Peripheral Alignment
Using a Dial Test Indicator (DTI).
Match mark the coupling halves.
Turn the shaft of the fan side or motor side 90, check DTI reading at 90.
Turn the shaft of the fan side or motor side a further 90, check DTI reading at 180.
Turn the shaft of the fan side or motor side a further 90, check DTI reading at 270.
Turn the shaft of the fan side or motor side to zero, recheck DTI reading at zero.
MM-M02.02
Rev.003
D-1
Appendix D
Axial Alignment
An inside micrometer or a tapered gap gauge can be used dependent upon the size of the gap
between the coupling faces. This example uses an inside micrometer.
Ensure both match marks at the top:
1
From the readings obtained, adjustments can be made to the liners (shims) installed under the
feet of the driving/driven equipment. Allowable tolerances are as follows:
Flexible Couplings
Peripheral
Axial
0.05 mm
0.05 mm
However, the Flexible Coupling supplier, Daido Precision Industries Ltd, have mentioned the
following specific installation acceptance criteria:
Rev.003
3.1 mm (0.10)
MM-M02.02
31.8 mm (0.50)
D-2
Appendix D
Peripheral Alignment
MM-M02.02
Rev.003
D-3
Appendix D
Axial Alignment
An inside micrometer or a tapered gap gauge can be used dependent upon the size of the gap
between the coupling faces. This example uses an inside micrometer.
Ensure both match marks at the top:
1
From the readings obtained, adjustments can be made to the liners (shims) installed under the
feet of the driving/driven equipment. Allowable tolerances are as follows:
Rigid Couplings
Peripheral
0.05 mm
Peripheral
0.05 mm
The oil pump supplier, Daikin Inc. has mentioned the following specific installation acceptance
criteria:
Rev.003
MM-M02.02
0.05 mm (TIR)
D-4
Appendix E
Applicable Reference
E & Vendor Drawings
MM-M02.02
Rev.003
A p p en d i x
E-1
MM-M02.02
Rev.003
Appendix E
MPTD-3-0503
FIGURE E-1
E-2
MM-M02.02
Rev.003
Appendix E
MPTD-3-0504
FIGURE E-2
E-3
Appendix E
MM-M02.02
Rev.003
MPTD-3-0505
FIGURE E-3
E-4
MM-M02.02
Rev.003
Appendix E
MPTD-3-0506
FIGURE E-4
E-5
MM-M02.02
Rev.003
Appendix E
MPTD-3-1209
FIGURE E-5
E-6
MM-M02.02
Rev.003
Appendix E
MPTD-3-1210
FIGURE E-6
E-7
MM-M02.02
Rev.003
Appendix E
MPTD-3-1211
FIGURE E-7
E-8
MM-M02.02
Rev.003
Appendix E
MPTD-3-1212
FIGURE E-8
E-9
MM-M02.02
Rev.003
Appendix E
MPTD-3-1213
FIGURE E-9
E-10
Appendix F
A p p en d i x
MM-M02.02
Rev.003
F MV Packing Insertion
F-1
Appendix F
BOLT
HYDRAULIC CYLINDER
RETAINING RING
1
TO REPLACE THE MV PACKING,
REMOVE THE BOLT, THE RETAINING
RING AND THE STOPPER PLATE.
REMOVE THE OLD PACKING.
MV PACKING
STOPPER PLATE FOR MV PACKING
GUIDE BAR
GUIDE BAR
GUIDE CYLINDER
INSERT RING
RUBBER PACKING
INNER ADAPTER
MV PACKING
STOPPER PLATE
HYDRAULIC CYLINDER
RETAINING RING
STOPPER PLATE
RUBBER PACKING
OUTER ADAPTER
MM-M02.02
Rev.003
NOTE:
FIGURE F-1
RUBBER PACKING
INNER ADAPTER
MV PACKING
MV PACKING INSERTION
F-2
Appendix F
30 -NON-MOTOR SIDE
138
118
31
D
d
H
30 -MOTOR SIDE
165
140
37
Od
OD
ITEM
1
2
3
4
DESCRIPTION
INNER ADAPTER
MV PACKING
RUBBER PACING
OUTER ADAPTER
MATERIAL
RUBBER
RUBBER
RUBBER
RUBBER
MM-M02.02
Rev.003
MOD-4-0971
FIGURE F-2
F-3
Appendix G
A p p en d i x
Description
Japan
MM-M02.02
Rev.003
Manufacturer
G-1
Appendix G
APPENDIX G-1
HANDLING MANUAL
OF
IDF LUBRICATION & CONTROL OIL UNIT
Rev.003
VENDOR:
DAIKIN HYDRAULIC ENGINEERING CO. LTD.
MM-M02.02
JAPAN
G-2
MM-M02.02
Rev.003
Appendix G
G-3
MM-M02.02
Rev.003
Appendix G
G-4
MM-M02.02
Rev.003
Appendix G
G-5
MM-M02.02
Rev.003
Appendix G
G-6
MM-M02.02
Rev.003
Appendix G
G-7
MM-M02.02
Rev.003
Appendix G
G-8
MM-M02.02
Rev.003
Appendix G
G-9
MM-M02.02
Rev.003
Appendix G
G-10
MM-M02.02
Rev.003
Appendix G
G-11
MM-M02.02
Rev.003
Appendix G
G-12
MM-M02.02
Rev.003
Appendix G
G-13
MM-M02.02
Rev.003
Appendix G
G-14
MM-M02.02
Rev.003
Appendix G
G-15
MM-M02.02
Rev.003
Appendix G
G-16
MM-M02.02
Rev.003
Appendix G
G-17
MM-M02.02
Rev.003
Appendix G
G-18
MM-M02.02
Rev.003
Appendix G
G-19
MM-M02.02
Rev.003
Appendix G
G-20
MM-M02.02
Rev.003
Appendix G
G-21
MM-M02.02
Rev.003
Appendix G
G-22
MM-M02.02
Rev.003
Appendix G
G-23
MM-M02.02
Rev.003
Appendix G
G-24
Appendix G
MM-M02.02
Rev.003
24
G-25
MM-M02.02
Rev.003
Appendix G
G-26
MM-M02.02
Rev.003
Appendix G
G-27
MM-M02.02
Rev.003
Appendix G
G-28
MM-M02.02
Rev.003
Appendix G
G-29
MM-M02.02
Rev.003
Appendix G
G-30
MM-M02.02
Rev.003
Appendix G
G-31
MM-M02.02
Rev.003
Appendix G
G-32
MM-M02.02
Rev.003
Appendix G
G-33
MM-M02.02
Rev.003
Appendix G
G-34
MM-M02.02
Rev.003
Appendix G
G-35
MM-M02.02
Rev.003
Appendix G
G-36
MM-M02.02
Rev.003
Appendix G
G-37
MM-M02.02
Rev.003
Appendix G
G-38
MM-M02.02
Rev.003
Appendix G
G-39
MM-M02.02
Rev.003
Appendix G
G-40
MM-M02.02
Rev.003
Appendix G
G-41
MM-M02.02
Rev.003
Appendix G
G-42
MM-M02.02
Rev.003
Appendix G
G-43
MM-M02.02
Rev.003
Appendix G
G-44
MM-M02.02
Rev.003
Appendix G
G-45
MM-M02.02
Rev.003
Appendix G
G-46
MM-M02.02
Rev.003
Appendix G
G-47
MM-M02.02
Rev.003
Appendix G
G-48
MM-M02.02
Rev.003
Appendix G
G-49
MM-M02.02
Rev.003
Appendix G
G-50
MM-M02.02
Rev.003
Appendix G
G-51
MM-M02.02
Rev.003
Appendix G
G-52
MM-M02.02
Rev.003
Appendix G
G-53
MM-M02.02
Rev.003
Appendix G
G-54
MM-M02.02
Rev.003
Appendix G
G-55
MM-M02.02
Rev.003
Appendix G
G-56
MM-M02.02
Rev.003
Appendix G
G-57
MM-M02.02
Rev.003
Appendix G
G-58
MM-M02.02
Rev.003
Appendix G
G-59
MM-M02.02
Rev.003
Appendix G
G-60
MM-M02.02
Rev.003
Appendix G
G-61
MM-M02.02
Rev.003
Appendix G
G-62
MM-M02.02
Rev.003
Appendix G
G-63
MM-M02.02
Rev.003
Appendix G
G-64
MM-M02.02
Rev.003
Appendix G
G-65
MM-M02.02
Rev.003
Appendix G
G-66
MM-M02.02
Rev.003
Appendix G
G-67
MM-M02.02
Rev.003
Appendix G
G-68
MM-M02.02
Rev.003
Appendix G
G-69
MM-M02.02
Rev.003
Appendix G
G-70
MM-M02.02
Rev.003
Appendix G
G-71
MM-M02.02
Rev.003
Appendix G
G-72
MM-M02.02
Rev.003
Appendix G
G-73
MM-M02.02
Rev.003
Appendix G
G-74
MM-M02.02
Rev.003
Appendix G
G-75
MM-M02.02
Rev.003
Appendix G
G-76
MM-M02.02
Rev.003
Appendix G
G-77
MM-M02.02
Rev.003
Appendix G
G-78
MM-M02.02
Rev.003
Appendix G
G-79
MM-M02.02
Rev.003
Appendix G
G-80
MM-M02.02
Rev.003
Appendix G
G-81
MM-M02.02
Rev.003
Appendix G
G-82
MM-M02.02
Rev.003
Appendix G
G-83
MM-M02.02
Rev.003
Appendix G
G-84
MM-M02.02
Rev.003
Appendix G
G-85
MM-M02.02
Rev.003
Appendix G
G-86
MM-M02.02
Rev.003
Appendix G
G-87
MM-M02.02
Rev.003
Appendix G
G-88
MM-M02.02
Rev.003
Appendix G
G-89
MM-M02.02
Rev.003
Appendix G
G-90
MM-M02.02
Rev.003
Appendix G
G-91
MM-M02.02
Rev.003
Appendix G
G-92
MM-M02.02
Rev.003
Appendix G
G-93
MM-M02.02
Rev.003
Appendix G
G-94
MM-M02.02
Rev.003
Appendix G
G-95
Appendix G
APPENDIX G - 2
HANDLING MANUAL
PLEATED TYPE ACCUMULATOR
VENDOR:
Rev.003
MM-M02.02
JAPAN
G-96
MM-M02.02
Rev.003
Appendix G
G-97
MM-M02.02
Rev.003
Appendix G
G-98
MM-M02.02
Rev.003
Appendix G
G-99
MM-M02.02
Rev.003
Appendix G
G-100
MM-M02.02
Rev.003
Appendix G
G-101
MM-M02.02
Rev.003
Appendix G
G-102
MM-M02.02
Rev.003
Appendix G
G-103
MM-M02.02
Rev.003
Appendix G
G-104
MM-M02.02
Rev.003
Appendix G
G-105
MM-M02.02
Rev.003
Appendix G
G-106
MM-M02.02
Rev.003
Appendix G
G-107
MM-M02.02
Rev.003
Appendix G
G-108
MM-M02.02
Rev.003
Appendix G
G-109
MM-M02.02
Rev.003
Appendix G
G-110
MM-M02.02
Rev.003
Appendix G
G-111
MM-M02.02
Rev.003
Appendix G
G-112
MM-M02.02
Rev.003
Appendix G
G-113
MM-M02.02
Rev.003
Appendix G
G-114
MM-M02.02
Rev.003
Appendix G
G-115
MM-M02.02
Rev.003
Appendix G
G-116
MM-M02.02
Rev.003
Appendix G
G-117
MM-M02.02
Rev.003
Appendix G
G-118
MM-M02.02
Rev.003
Appendix G
G-119
MM-M02.02
Rev.003
Appendix G
G-120
Appendix G
APPENDIX G - 3
INSTRUCTION MANUAL
OF
IDF SEAL AIR FAN
VENDOR:
Rev.003
MM-M02.02
JAPAN
G-121
MM-M02.02
Rev.003
Appendix G
G-122
MM-M02.02
Rev.003
Appendix G
G-123
MM-M02.02
Rev.003
Appendix G
G-124
MM-M02.02
Rev.003
Appendix G
G-125
MM-M02.02
Rev.003
Appendix G
G-126
MM-M02.02
Rev.003
Appendix G
G-127
MM-M02.02
Rev.003
Appendix G
G-128
MM-M02.02
Rev.003
Appendix G
G-129
MM-M02.02
Rev.003
Appendix G
G-130
MM-M02.02
Rev.003
Appendix G
G-131
MM-M02.02
Rev.003
Appendix G
G-132
MM-M02.02
Rev.003
Appendix G
G-133
MM-M02.02
Rev.003
Appendix G
G-134
MM-M02.02
Rev.003
Appendix G
G-135
Appendix G
APPENDIX G- 4
Rev.003
VENDOR :
MM-M02.02
G-136
MM-M02.02
Rev.003
Appendix G
G-137
MM-M02.02
Rev.003
Appendix G
G-138
MM-M02.02
Rev.003
Appendix G
G-139
MM-M02.02
Rev.003
Appendix G
G-140
MM-M02.02
Rev.003
Appendix G
G-141
MM-M02.02
Rev.003
Appendix G
G-142
MM-M02.02
Rev.003
Appendix G
G-143
MM-M02.02
Rev.003
Appendix G
G-144
MM-M02.02
Rev.003
Appendix G
G-145
MM-M02.02
Rev.003
Appendix G
G-146
MM-M02.02
Rev.003
Appendix G
G-147
MM-M02.02
Rev.003
Appendix G
G-148
MM-M02.02
Rev.003
Appendix G
G-149
MM-M02.02
Rev.003
Appendix G
G-150
Appendix H
A p p en d i x
MM-M02.02
Rev.003
H Parts List
H-1
MM-M02.02
Rev.003
Appendix H
H-2
MM-M02.02
Rev.003
Appendix H
H-3
MM-M02.02
Rev.003
Appendix H
H-4
MM-M02.02
Rev.003
Appendix H
H-5
MM-M02.02
Rev.003
Appendix H
H-6
MM-M02.02
Rev.003
Appendix H
H-7
MM-M02.02
Rev.003
Appendix H
H-8
MM-M02.02
Rev.003
Appendix H
H-9
MM-M02.02
Rev.003
Appendix H
H-10
MM-M02.02
Rev.003
Appendix H
H-11
MM-M02.02
Rev.003
Appendix H
H-12
MM-M02.02
Rev.003
Appendix H
H-13
MM-M02.02
Rev.003
Appendix H
H-14
MM-M02.02
Rev.003
Appendix H
H-15
MM-M02.02
Rev.003
Appendix H
H-16
MM-M02.02
Rev.003
Appendix H
H-17
MM-M02.02
Rev.003
Appendix H
H-18
MM-M02.02
Rev.003
Appendix H
H-19
MM-M02.02
Rev.003
Appendix H
H-20
MM-M02.02
Rev.003
Appendix H
H-21
MM-M02.02
Rev.003
Appendix H
H-22
MM-M02.02
Rev.003
Appendix H
H-23
MM-M02.02
Rev.003
Appendix H
H-24
MM-M02.02
Rev.003
Appendix H
H-25
MM-M02.02
Rev.003
Appendix H
H-26
MM-M02.02
Rev.003
Appendix H
H-27