You are on page 1of 24

TABLE OF CONTENT

Scope

Reference Documents

Health, Safety, and Environment

Key Personnel

Sequence of Operation

Method And Sequence of Work.

Testing and Commissioning Equipment Certification

Attachment

1. Scope:
1.1 The systems will be Pre-commissioned and Commissioned in accordance with the approved
method of statement.
1.2 Ensure that all permanent wiring has been tested for insulation resistance and continuity prior
to connection.
1.3 Ensure that earthing / grounding arrangements are intact and that leakage currents can be
effectively discharged.
1.4 Ensure that the Booster pump for domestic water systems are properly installed and shall
perform as designed and as per requirement.
2. Reference:
2.1 The Project Specification
AEA-1305-WC-M-S57-P99-LBM-0315 : BASEMENT PLANTROOM HVAC BLOW
UP DETAILS
AEA-1305-WC-M-S57-P99-LBM-0315-1 : BASEMENT PLANTROOM HVAC
BLOW UP DETAILS
AEA-1305-WC-M-S57-P99-LBM-0315-2 : BASEMENT PLANTROOM HVAC
BLOW UP DETAILS
RED-1305-WC-PH-S53-P99-SCH-0101 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 1 OF 7
RED-1305-WC-PH-S53-P99-SCH-0102 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 2 OF 7
RED-1305-WC-PH-S53-P99-SCH-0103 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 3 OF 7
RED-1305-WC-PH-S53-P99-SCH-0104 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 4 OF 7
RED-1305-WC-PH-S53-P99-SCH-0105 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 5 OF 7
RED-1305-WC-PH-S53-P99-SCH-0106 : DOMESTIC HOT&COLD WATER
DISTRIBUTION SCHEMATIC SHEET 6 OF 7
2.2 Material Transmittal
2.3 National Standards (CIBSE & ASRHAE)
2.4 Information for Construction Drawings (IFC)
3. Health, Safety, and Environment:
3.1 ARMA will operate a strict safety policy. ARMA-ELEKTROPANC recognizes the
importance of safety on site and will strictly adhere to the safety requirements for working.
3.2 A team of experienced and well qualified safety officers will be assigned to implement and
control the Health Safety & Environment Plan on site.
4. Key Personnel:
4.1 The Contractors T&C for Mechanical/Electrical Group has the overall responsibility for the
implementation of this Method of Statement.
4.2 The Contractors T&C Manager will ensure that the resources are available to carry-out the
works as per approved drawings, method of statement, and work as scheduled.
4.3 The Contractors Site Engineer/Supervisor is responsible to ensure that the work has been
carried out as per approved drawings. Method statements and assist inspection.
4.4 The Contractors commissioning technician/s is responsible to ensure that they are abiding the
method of statement to achieve the required data as per equipment schedule and project
specification.
4.5 The Contractor Safety Officer will assist in all issues related to the HSE.

5. Sequence of Operation

Domestic water system booster pumps are located in the ENGINEERING ROOM (0315) serves water to
guest room hot & cold water. The other one unit booster pump in the Fire room, see sequence of
adjustment and commissioning activity reports on following pages.

FLT 1 Booster pumps will transfer water from the raw water tank, on the passes through
sand filter and activated carbon filter to potable water tank. Booster pumps is driven by
pressure switch, pressure is 3.0 bar while the start, stop when 4 bars.
5.2
BP1 booster pumps take water from the potable tank and through the softener and then send
it to the domestic system. This booster pump job is to transport water to the domestic use of
the guestroom. This booster pumps is driven by pressure sensor and frequence converter,
pressure is kept constant at 7,0 bar.
5.3
BP2 booster pumps take water from the potable tank and through the softener and then send
it to the domestic system. This booster pump job is to transport water to the domestic use of
the hotel areas. This booster pumps is driven by pressure sensor and frequence converter,
pressure is kept constant at 5,0 bar.
6. Method and Sequence of Work:
5.1

Start- up and Commissioning of Booster Pump units will be carried out by Manufacturer/ Specialist
supplier. All check sheets and signed reports from the manufacturer shall be collected and attached.
We will assist their commissioning engineer as required. The main objective is to minimize the risk
of injury and damage to personnel and equipment. Electrical test on control panel shall be
implemented and signed off by supplier or responsible contractor and to be attached on
commissioning checklist.
6.1 Pre-Commissioning
6.1.1 Pump & Motor should be properly mounted, making sure that the base of the unit is
permanently supported.
6.1.2 Proper piping (outlet & inlet), correct foundations and motor mounts must be
implemented to minimize external stress on all piping.
6.1.3 Ensure that all flexible connections are secure.
6.1.4 Lubrication should be observed or implemented as per manufacturers
recommendation.
6.1.5 Ensure sufficient feed water supply. Booster should be thoroughly purged of air before
start-up.
6.1.6 Ensure that the piping system pressure leak test, attached on pre-commissioning
checklist.
6.1.7 Ensure that the pump motor power requirements are connected to a suitable electrical
supply.
6.1.8 Ensure that the pump motor is earth or bonded to earthing system.
6.1.9 Pump control panel is properly commissioned by supplier or installer contractor.
6.1.10 Cables, terminal connections, trunking lines or conduits, cable trays are as per
approved materials and installation.
6.1.11 Ensure that complete installation and start up checks is according to manufacturers
written instruction.
6.1.12 Clean strainer on suction piping.
6.1.13 Verify that each pump is free to rotate by hand. If pump is bound or drags, do not
operate until cause of trouble is determined and corrected.
6.2 Commissioning
6.2.1 Ensure that the entire pre-commissioning checklists are completely done.
6.2.2 Prime the pump by opening suction/discharge valve and prepare pump for operation.
6.2.3 Turn on the power of the pump in AUTO Mode.
6.2.4 Verify that the pump is running in the correct rotation.

6.2.5 Check the charge on the connected cushion tank. It should be the same (or %10 less
then) as the operating pressure: 7.00 Bar for the potable water system for BP1
guestroom, 5,00 bar for BP2 for hotel areasand 3.00 Bar for FLT1 raw water booster.
Recharge or bleed off air if necessary.
6.2.6 Close slowly the discharge valve and record the cut off pressure of the FLT1.
6.2.7 Open the discharge valve slowly and then record the cut in pressure of the FLT1.
6.2.8 With the pump running, check the motor current and volts.
6.2.9 For all pumps, check dry protection level.
6.2.10 Install a temporary bypass line with an isolation valve from the discharge header into
the water storage tank (potable or non-potable tank) to which the booster pump set
under commissioning is connected at the suction side. Isolate the discharge header
from the domestic water system.
6.2.11 Check the operational order of the pumps.
For presostat driven FLT1 ;
6.2.9.1 Switch the booster pump set panel on automatic mode.
6.2.9.2 Open the valve on the bypass line. This would simulate a drop in the system
pressure and the FLT1 should start.
6.2.9.3 Note the pressure at the point in which the FLT1 pump1 starts.
6.2.9.4 Because the discharge line is not feeding into the system, a further drop in
pressure should happen. This would start the FLT1 pump2.
6.2.9.5 Note the order of activation of the pumps.
6.2.9.6 Slowly close the valve on the bypass line. This should raise system pressure
and stop all running pumps.
6.2.9.7 Note the pressure at the point when each pump stops.

For Frequence Converter driven BP1 and BP2;


6.2.9.8 BP1 and BP2 boosters driven with frequence converters.
6.2.9.9 For BP1 and BP2, Switch the booster pump set panel on automatic mode.
6.2.9.10 Open the valve on the bypass line. This would simulate a drop in the system
pressure and BP1 and BP2 should start.
6.2.9.11 Because the discharge line is not feeding into the system, a further drop in
pressure should happen. This would start the second pump, and later third pump.
6.2.9.12 Note the order of activation of the pumps.
6.2.12 Repeat 6.2.10 until cyclic changeover function is found to be working properly.
6.3 Performance Test
The objectives of the performance test follow:
6.3.1 To ensure that the Booster pumps are operating automatically as required for system
application.
6.3.2 To ensure that the Booster pumps for Potable and Non-Potable Water Systems are
performing according to the design data and specification.
6.3.3 A representative from each trade shall be available during the performance test as well
as one representative minimum from the owner, engineer, and general contractor. The
trades involved shall include as a minimum Mechanical, electrical, controls, and
commissioning agent.
6.4 Temporary Works during Commissioning Stages
6.4.1 Necessary Permits shall be obtained prior to works.
6.4.2 Location of work to be secured through the use of barricade tapes. Unauthorized
personnel to be excluded from works location.

Testing and Commissioning Equipment Certification


The following equipment / tools are to be use during testing and commissioning works:
Items
Equipment
Nos.
Purpose
Certificates
1
Multi Tester
1
For Testing of Volts
To be provided during
and Current
commissioning stages
2
Hand Tools (set)
1
Use for related works
N/A
3
Pressure Gauge
2
Use for checking the
To be provided during
pressure.
commissioning stages
7. Attachment:
8.1
8.2
8.3
8.4
8.5
8.6
8.7

Booster Pump Pre-Commissioning Checklist


Booster Pump Pre-Commissioning Punch list
Booster Pump Commissioning Checklist
Booster Pump Performance Test Checklist
Booster Pump Equipment Schedule and Pump Performance Curve
Riser Diagram Domestic Water
Material Transmittal Approval

8. Attachments

8.1 Booster Pump Pre-Commissioning Checklist


Contact

ARMA ELEKTROPANC

Ref.

Client

PASHA CONSTRUCTION

Plant Ref.

ENGINEERING ROOM (0315)

Location/ Area Serving

GUEST ROOMS BOOSTER SET / COR-3-MVI7004-22/2-T-3-E 22

Tick Yes if Acceptable; Provide comment if unacceptable

Yes

No

DOMESTIC WATER

Comment

General
Installation is as per manufacturers instructions
Manufacturers recommended spare parts are provided
Equipment label permanently affixed
Pump turns freely
Pump foundation is level within manufacturers tolerances
Pumps in place and properly supported
Isolation valves and piping specialties installed
Flexible connections check and secure.
Shaft seal is leak free
Pump detail checked against the drawings and all devices gages and
appurtenances are in place
Electrical and Controls
Power isolator is located within site of the unit it controls and labeled
Pump motor connected to a suitable electrical supply
All electric cable and terminal connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Operation of Control switch checked in all positions
Installation per manufacturers instructions

BOOSTER PUMP PRE-COMMISSIONING / GUEST ROOMS BOOSTER SET


MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

8.1 Booster Pump Pre-Commissioning Checklist


Contact

ARMA ELEKTROPANC

Client

PASHA CONSTRUCTION

Ref.

Plant Ref.

ENGINEERING ROOM (0315)

Location/ Area Serving

KITCHEN/LAUNDRY Hotel areas BOOSTER SET /

Tick Yes if Acceptable; Provide comment if unacceptable

Yes

DOMESTIC WATER

COR-3-MVI3204-7,5/2
No

Comment

General
Installation is as per manufacturers instructions
Manufacturers recommended spare parts are provided
Equipment label permanently affixed
Pump turns freely
Pump foundation is level within manufacturers tolerances
Pumps in place and properly supported
Isolation valves and piping specialties installed
Flexible connections check and secure.
Shaft seal is leak free
Pump detail checked against the drawings and all devices gages and
appurtenances are in place
Electrical and Controls
Power isolator is located within site of the unit it controls and labeled
Pump motor connected to a suitable electrical supply
All electric cable and terminal connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Operation of Control switch checked in all positions
Installation per manufacturers instructions
BOOSTER PUMP PRE-COMMISSIONING / KITCHEN/LAUNDRY Hotel Areas BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

8.1 Booster Pump Pre-Commissioning Checklist


Contact

ARMA ELEKTROPANC

Client

PASHA CONSTRUCTION

Plant Ref.

ENGINEERING ROOM (0315)

Location/ Area Serving

RAW Water BOOSTER SET /

Ref.

CO-2-MVI5203-7.5/2

Tick Yes if Acceptable; Provide comment if unacceptable

Yes

No

General
Installation is as per manufacturers instructions
Manufacturers recommended spare parts are provided
Equipment label permanently affixed
Pump turns freely
Pump foundation is level within manufacturers tolerances
Pumps in place and properly supported
Isolation valves and piping specialties installed
Flexible connections check and secure.
Shaft seal is leak free
Pump detail checked against the drawings and all devices gages and
appurtenances are in place
Electrical and Controls
Power isolator is located within site of the unit it controls and labeled
Pump motor connected to a suitable electrical supply
All electric cable and terminal connections tight
Grounding installed for components and unit
Safeties installed and operational
Starter overload breakers installed and correct size
All control devices and wiring complete
Control system interlocks connected and functional
Operation of Control switch checked in all positions
Installation per manufacturers instructions
BOOSTER PUMP PRE-COMMISSIONING / RAW water Booster set

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

DOMESTIC WATER

Comment

8.2 Pre- Commissioning Punch List Form

8.3 Booster Pump Commissioning Checklist


Contact

ARMA ELEKTROPANC

Client

PASHA CONSTRUCTION

Plant Ref.

ENGINEERING ROOM (0315)

Ref.

DOMESTIC WATER

Location/ Area Serving


GUEST ROOM BOOSTER SET / COR-3-MVI7004-22/2-T-3-E 22 / BP1
Tick Yes if Acceptable; Provide comment if unacceptable
Yes No
General
The Control switch properly activates and deactivates the unit
Pump rotation verified correct
No unusual noise or vibration
No leaking apparent around fittings
Record cut in and cut off pressure of all pumps.
Specified sequences of operation and operating schedules have been
implemented with all variations documented.
Specified point-to-point checks have been completed and documentation
record submitted for this system.
Check cushion tank pre-charge. It should be the same ( or %10 less then)
as operational pressure (7.00 Bar for potable water system). Bleed or
recharge as required.
Install a temporary bypass line with valve from discharge header to nonpotable or potable water tank, whichever system is being tested.
Sequence of operation
Check and note that the booster set cut in at .. Bar
Check and note that the booster set cut outs at Bar
Check that the pumps cut in when the previous main pump has reached
full speed and line pressure is not restored at 7.00 Bar for potable water
system.
Note order of operation of the pumps
Repeat until cyclic changeover function is found to be working properly
BOOSTER PUMP COMMISSIONING / GUEST ROOMS BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

Comment

8.3 Booster Pump Commissioning Checklist


Contact

ARMA ELEKTROPANC

Client

PASHA CONSTRUCTION

Plant Ref.

ENGINEERING ROOM (0315)

Ref.

DOMESTIC WATER

Location/ Area Serving


KITCHEN/LAUNDRY Hotel Areas BOOSTER SET / COR-3-MVI3204-7,5/2
Tick Yes if Acceptable; Provide comment if unacceptable
Yes No
Comment
General
The Control switch properly activates and deactivates the unit
Pump rotation verified correct
No unusual noise or vibration
No leaking apparent around fittings
Record cut in and cut off pressure of all pumps.
Specified sequences of operation and operating schedules have been
implemented with all variations documented.
Specified point-to-point checks have been completed and documentation
record submitted for this system.
Check cushion tank pre-charge. It should be the same ( or %10 less then)
as operational pressure (5.00 Bar for potable water system). Bleed or
recharge as required.
Install a temporary bypass line with valve from discharge header to nonpotable or potable water tank, whichever system is being tested.
Sequence of operation
Check and note that the booster set cut in at .. Bar for potable water
system
Check and note that the booster set cuts out at Bar for potable water
system
Check that the pumps cut in when the previous main pump has reached
full speed and line pressure is not restored at 7.00 Bar for potable water
system.
Note order of operation of the pumps
Repeat until cyclic changeover function is found to be working properly
BOOSTER PUMP COMMISSIONING / GUEST ROOMS BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

8.3 Booster Pump Commissioning Checklist


Contact

ARMA ELEKTROPANC

Client

PASHA CONSTRUCTION

Plant Ref.

ENGINEERING ROOM (0315)

RAW Water BOOSTER SET / CO-2-MVI5203-7.5/2


Location/ Area Serving
Tick Yes if Acceptable; Provide comment if unacceptable
Yes
General

Ref.

No

The Control switch properly activates and deactivates the unit


Pump rotation verified correct
No unusual noise or vibration
No leaking apparent around fittings
Record cut in and cut off pressure of all pumps.
Specified sequences of operation and operating schedules have been
implemented with all variations documented.
Specified point-to-point checks have been completed and documentation
record submitted for this system.
Check cushion tank pre-charge. It should be the same ( or %10 less then)
as operational pressure (3.00 Bar for RAW water system). Bleed or
recharge as required.
Install a temporary bypass line with valve from discharge header to nonpotable or potable water tank, whichever system is being tested.
Sequence of operation
Check and note that the booster set for pump 1
cut in at .. Bar
Cut out at.bar
Check and note that the booster set for pump 2
cut in at .. Bar
Cut out at.bar
Check that the pumps cut in when the previous main pump has reached
full speed and line pressure is not restored at 3.00 Bar for raw water
system.
Note order of operation of the pumps
Repeat until cyclic changeover function is found to be working properly
BOOSTER PUMP COMMISSIONING / GUEST ROOMS BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

DOMESTIC WATER

Comment

8.4 Booster Pump Performance Test Checklist


Contract

ARMA ELECTROPANC

Client

PASHA CONSTRUCTION

Plant Reference

ENGINEERING ROOM (0315)

Location/Area serving

GUEST ROOM BOOSTER SET / * COR-3-MVI7004-22/2-T-3-E 22

PUMPS

Manufacturer

Ref: DOMESTIC WATER

Model No.

ART No.

Type

Pump 1

WILO

DOMESTIC BOOSTER PUMP

Pump 2

WILO

DOMESTIC BOOSTER PUMP

Pump 3

WILO

DOMESTIC BOOSTER PUMP


Design

PUMP

Cut off (bar)

Cut in (bar)

Cut off (bar)

Pump 1
Pump 2
Pump 3

MOTOR

PERFORMANCE

Cut in (bar)

Actual

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Power
(kW)

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Pump 1
Pump 2
Pump 3

*The figure to the left of the slash (/) is for potable water system and that at the right is for non-potable water system.
Remarks:

BOOSTER PUMP PERFORMANCE CHECKLIST / GUEST ROOM BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

Power
(kW)

8.4

Booster Pump Performance Test Checklist

Contract

ARMA ELECTROPANC

Client

PASHA CONSTRUCTION

Plant Reference

MECHANICAL ROOM 1 LEVEL-1

Location/Area serving

KITCHEN/LAUNDRY and Hotel Areas BOOSTER SET / *COR-3-MVI3204-7,5/2

PUMPS

Manufacturer

Ref: DOMESTIC WATER

Model No.

ART No.

Type

Pump 1

WILO

DOMESTIC BOOSTER PUMP

Pump 2

WILO

DOMESTIC BOOSTER PUMP

Pump 3

WILO

DOMESTIC BOOSTER PUMP


Design

PUMP

Cut off (bar)

Cut in (bar)

Cut off (bar)

Pump 1
Pump 2
Pump 3

MOTOR

PERFORMANCE

Cut in (bar)

Actual

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Power
(kW)

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Pump 1
Pump 2
Pump 3

*The figure to the left of the slash (/) is for potable water system and that at the right is for non-potable water system.
Remarks:

BOOSTER PUMP PERFORMANCE CHECKLIST / KITCHEN/LAUNDRY and Hotel Areas BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

Power
(kW)

8.4

Booster Pump Performance Test Checklist

Contract

ARMA ELECTROPANC

Client

PASHA CONSTRUCTION

Plant Reference

MECHANICAL ROOM 1 LEVEL-1

Location/Area serving

KITCHEN/LAUNDRY and Hotel Areas BOOSTER SET / CO-2-MVI5203-7.5/*

PUMPS

Manufacturer

Ref: DOMESTIC WATER

Model No.

ART No.

Type

Pump 1

WILO

DOMESTIC BOOSTER PUMP

Pump 2

WILO

DOMESTIC BOOSTER PUMP

Pump 3

WILO

DOMESTIC BOOSTER PUMP


Design

PUMP

Cut off (bar)

Cut in (bar)

Cut off (bar)

Pump 1
Pump 2

MOTOR

PERFORMANCE

Cut in (bar)

Actual

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Power
(kW)

Voltage
(volts)

Current
(amps)

Speed
(rpm)

Pump 1
Pump 2

*The figure to the left of the slash (/) is for potable water system and that at the right is for non-potable water system.
Remarks:

BOOSTER PUMP PERFORMANCE CHECKLIST / RAW Water BOOSTER SET

MEP CONTRACTOR
AE ARMA-ELEKTROPANC
Supervisor
Site Engineer
Commissioning Engineer
Commissioning Manager
Commissioning Authority

Comment/s :

Elite Commissioning
Commissioning Engineer
CLIENT
PASHA CONTRUCTION
Lead Engineer

Senior MEP Manager

Comment/s :

Power
(kW)

8.5 Booster Pump Schedule and Performance Curve

Presented as additional files.

8.6 Riser Diagram Domestic Water

Presented as additional files.

8.7 Material Transmittal Approval

Presented as additional files.

MVI 7004 PN16 3~


Phone
Fax

Sys te m : Hig h p re s sure ce ntrifug a l p um p

Customer

Project

Customer no.

Project no.

Contact

Position no.

Care of

Location
Date

2014-05-17
Requested data

[m] Head
110
105
100
95
90
85
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
[%] Efficiency
60

MVI 7004

Flo w

79,2

m /h

He a d

67

Fluid

W a te r, pure

Fluid te m p e ra ture

20

De nsity

0,9982

k g /d m

Kine m a tic vis co s ity

1,001

m m /s

Va p o r pre ss ure

0,1

bar

Pump data
MVI 7004

40
20
[m] NPSH-values
6

MVI 7004

Ma k e

W ILO

T yp e

MVI 7004 P N16 3~

P um p e typ e

Sing le he a d p um p

P re s sure ra ting

P N 16

Min. fluid te m p e ra ture

-15

Ma x . fluid te m p e ra ture 120


Minim um Efficie ncy Ind e x (MEI) >=0,10

4
2
[kW]
15
10
5

Page 1 / 1

Shaft power P2

MVI 7004

Hydraulic data (duty point)


0

10

20

30

40

50

60

70

80

90

100

110

[m/h]

Flo w

82,9

m /h

He a d

73,4

Sp e e d

2950

1/m in

Sha ft p o we r P 2

21,7

kW

NP SH

4,59

Materials / Shaft seal


P um p ba s e

EN-GJL 250 KTL b e s chichte t/co ve re d

Im p e lle rs

1.4401

Sta g e cha m b e rs

1.4404

P re s sure ca sing

1.4301

Sha ft

1.4404

Se a ls

EP DM

Me cha nica l se a l

W o lfra m ca rb id e /g ra p hit
mm

Dimensions per pump


H
h2
M
X
K

1446
927
370
248
8x 19

Suctio n sid e

DN100

/ P N 16

Dis cha rg e sid e

DN100

/ P N 16

W e ight

214

kg

Motordata per Motor/Pump/


R a te d p o we r P 2

22

No m ina l sp e e d

2900

kW

R a te d vo lta g e

3~400 V, 50

Ma x . curre nt

37,5

De g re e o f p ro te ctio n

IP 55

1/m in
Hz
A

P e rm itte d vo lta g e to le ra nce +/- 10%


Ite m no . o f sta nd a rd ve rsio n

Reserves to change any technical data.

Software version

3.1.13 - 01.09.2013 (Build 29)

User group

TR

data status

4071175

01.01.2013

MVI 3203/ PN16 3~


Phone
Fax

Sys te m : Hig h p re s sure ce ntrifug a l p um p

Customer

Project

Customer no.

Project no.

Contact

Position no.

Care of

Location
Date

[m] Head
60
56
52
48
44
40
36
32
28
24
20
16
12
8
4

Page 1 / 1

Requested data

Flo w

27

m /h

He a d

35

Fluid

W a te r, pure

Fluid te m p e ra ture

20

De nsity

0,9982

k g /d m

Kine m a tic vis co s ity

1,001

m m /s

Va p o r pre ss ure

0,1

bar

Pump data
MVI 3203

[%] Efficiency
60
50
40
30
20
10
[m]

2014-05-17

MVI 3203

NPSH-values

MVI 3203

Ma k e

W ILO

T yp e

MVI 3203/ P N16 3~

P um p e typ e

Sing le he a d p um p

P re s sure ra ting

P N 16

Min. fluid te m p e ra ture

-15

Ma x . fluid te m p e ra ture 120


Minim um Efficie ncy Ind e x (MEI) >=0,10

8
4
[kW] Shaft power P2
4
3
2
1
0

MVI 3203

12

16

20

24

28

32

36

40

44

48

[m/h]

Hydraulic data (duty point)


Flo w

29,1

m /h

He a d

40,8

Sp e e d

2900

1/m in

Sha ft p o we r P 2

4,94

kW

NP SH

3,33

Materials / Shaft seal


P um p ba s e

C a s t iro n

Im p e lle rs

1.4301

Sta g e cha m b e rs

1.4301

P re s sure ca sing

1.4301

Sha ft

1.4404

Se a ls

EP DM

Me cha nica l se a l

W o lfra m ca rb id e /g ra p hit
mm

Dimensions per pump


H
h2
M
X
K

814
486
220
160
4x 18

Suctio n sid e

DN65

/ P N 16

Dis cha rg e sid e

DN65

/ P N 16

W e ight

88

kg

>5,5 kW

Motordata per Motor/Pump/


3 ~ 230 V

W2

U2

V2

U1

V1

W1

L1

L2

L3

Y Anlauf
L1

3 ~ 400 V

W2
U1

L2
U2
V1

L3
V2
W1

R a te d p o we r P 2

5,5

No m ina l sp e e d

2900

R a te d vo lta g e

3~400 V, 50

Ma x . curre nt

10,6

De g re e o f p ro te ctio n

IP 55

Software version

1/m in
Hz
A

P e rm itte d vo lta g e to le ra nce +/- 10%


Ite m no . o f sta nd a rd ve rsio n

Reserves to change any technical data.

kW

3.1.13 - 01.09.2013 (Build 29)

User group

TR

data status

4035904

01.01.2013

Helix V 1603-1/16/E/400-50
Phone
Fax

Sys te m : Hig h p re s sure ce ntrifug a l p um p

Customer

Project

Customer no.

Project no.

Contact

Position no.

Care of

Location
Date

[m] Head
40
38
36
34
32
30
28
26
24
22
20
18
16
14
12
10
8
6
4
2
[kW]

2014-05-17

Requested data

Helix 1603

Flo w

14,14

m /h

He a d

30

Fluid

W a te r, pure

Fluid te m p e ra ture

20

De nsity

0,9982

k g /d m

Kine m a tic vis co s ity

1,001

m m /s

Va p o r pre ss ure

0,1

bar

Pump data

Shaft power P2

Helix 1603

1,6
1,2
0,8
[%]
60 Efficiency
50
40
30
20
10
[m]
7 NPSH-values
6
5
4
3
2
1
0
2
4

Page 1 / 1

Helix 1603

Ma k e

W ILO

T yp e

He lix V 1603-1/16/E/400-50

P um p e typ e

Sing le he a d p um p

P re s sure ra ting

P N 16

Min. fluid te m p e ra ture

-20

Ma x . fluid te m p e ra ture 120


Minim um Efficie ncy Ind e x (MEI) >=0,70

Helix 1603

Hydraulic data (duty point)


6

10

12

14

16

18

20

22

24

26

28

[m/h]

Flo w

14,6

m /h

He a d

32,1

Sp e e d

2900

1/m in

Sha ft p o we r P 2

1,98

kW

NP SH

1,26

Materials / Shaft seal


P um p ho us ing

1.4301

Im p e lle rs

1.4307

Sta g e ho us ing

1.4307

Sha ft

1.4301

O 'R ing

EP DM

mm

Dimensions per pump


H
H2
X
M

779
512
149
193

Suctio n sid e

G2

/ P N 16

Dis cha rg e sid e

G2

/ P N 16

W e ight

41

kg

Motordata per Motor/Pump/


R a te d p o we r P 2

2,2

No m ina l sp e e d

2900

kW

R a te d vo lta g e

3~400 V, 50

Ma x . curre nt

4,5

De g re e o f p ro te ctio n

IP 55

1/m in
Hz
A

P e rm itte d vo lta g e to le ra nce +/- 10%


Ite m no . o f sta nd a rd ve rsio n

Reserves to change any technical data.

Software version

3.1.13 - 01.09.2013 (Build 29)

User group

TR

data status

4162638

01.01.2013

MVI 7001 PN16 3~


Phone
Fax

Sys te m : Hig h p re s sure ce ntrifug a l p um p

Customer

Project

Customer no.

Project no.

Contact

Position no.

Care of

Location
Date

[m]
28
26
24
22
20
18
16
14
12
10
8
6
4
2

2014-05-17

Page 1 / 1

Requested data

Head

MVI 7001

Flo w

67,68

m /h

He a d

16,5

Fluid

W a te r, pure

Fluid te m p e ra ture

20

De nsity

0,9982

k g /d m

Kine m a tic vis co s ity

1,001

m m /s

Va p o r pre ss ure

0,1

bar

Pump data

[%] Efficiency
60
40

MVI 7001

20
[m] NPSH-values
6

MVI 7001

MVI 7001 P N16 3~

P um p e typ e

Sing le he a d p um p

P re s sure ra ting

P N 16

Min. fluid te m p e ra ture

-15

20

MVI 7001

[kW] Shaft power P2


4
3
2
1
10

W ILO

T yp e

Ma x . fluid te m p e ra ture 120


Minim um Efficie ncy Ind e x (MEI) >=0,10

4
2

Ma k e

Hydraulic data (duty point)


30

40

50

60

70

80

90

100

110

[m/h]

Flo w

72,1

m /h

He a d

18,7

Sp e e d

2950

1/m in

Sha ft p o we r P 2

4,97

kW

NP SH

3,62

Materials / Shaft seal


P um p ba s e

EN-GJL 250 KTL b e s chichte t/co ve re d

Im p e lle rs

1.4401

Sta g e cha m b e rs

1.4404

P re s sure ca sing

1.4301

Sha ft

1.4404

Se a ls

EP DM

Me cha nica l se a l

W o lfra m ca rb id e /g ra p hit
mm

Dimensions per pump


H
h2
M
X
K

867
539
220
160
8x 19

Suctio n sid e

DN100

/ P N 16

Dis cha rg e sid e

DN100

/ P N 16

W e ight

106

kg

Motordata per Motor/Pump/


R a te d p o we r P 2

5,5

No m ina l sp e e d

2900

kW

R a te d vo lta g e

3~400 V, 50

Ma x . curre nt

10,6

De g re e o f p ro te ctio n

IP 55

1/m in
Hz
A

P e rm itte d vo lta g e to le ra nce +/- 10%


Ite m no . o f sta nd a rd ve rsio n

Reserves to change any technical data.

Software version

3.1.13 - 01.09.2013 (Build 29)

User group

TR

data status

4071163

01.01.2013

You might also like