You are on page 1of 29

Mehran University of Engineering & Technology

Project: Quantity Estimation & Rate Analysis of Building

Quantity Surveying & Estimation For Civil Works


Submitted to Sir Dr. Nafees Ahmed Memon

Prepared By: Group-9


11CE32(G.L)
11CE40(A.G.L)
11CE34
11CE52
11CE108
11CE48

Calculations of Brickwork & other Essential items of R.C.C Framed Building.


S.No
Particulars of Items
1
Earthwork in Excavation
in Foundation
Columns
In between Columns
I.
Section A wall
II.
Section B wall
III.
Section C wall
IV.
Section D wall
V.
Section E wall
VI.
Outer Verandah
wall
VII.
Outer bathroom
wall
VIII.
Separation wall of
bathroom
IX.
Bathroom at
corner
X.
Verandah wall
along garden
2
3

Lean concrete 1:4:8 in


Base of column
R.C.C work (1:2:4) in
Beams ,Columns & Slabs
Fair Finished excluding
steel & its bending but
including its centering,
shuttering & Binding steel
Footing of Columns
Square Bottom
Trapezoidal
portion
Columns
Plinth Beam &
Roof Beam
XI.
Section A wall
XII.
Section B wall
XIII.
Section C wall
XIV.
Section D wall
XV.
Section E wall
XVI.
Outer Verandah
wall

No

Length(ft)

Breadth(ft) Height(ft) Quantity(cuft)

15

3.75

900

02
02
02
02
02
01

42.84
8.5
25.34
15.33
10.5
31.09

.5
.5
.5
.5
.5
.5

.75
.75
.75
.75
.75
.75

32.13
6.375
19.005
11.4975
7.875
11.658

01

5.16

.5

.75

1.935

01

5.5

.5

.75

2.0625

01

7.05

.5

.75

2.643

01

29

.5

.75

10.875
1006.056

15

.25

60

15
15

1.667

15

1.5

.5

13.833

400.08
15x10.468
=157.02
155.621

04
04
04
04
04
02

50.34
12
12
31.34
15.33
37.34

.5
.5
.5
.5
.5
.5

1.5
1.5
1.5
1.5
1.5
1.5

151.02
36
36
94.02
45.99
56.01

Explanatory

Using
H/6[A1+A2+4AM]

XVII.
XVIII.
XIX.
XX.

Outer bathroom
wall
Separation wall of
bathroom
Bathroom at
corner
Verandah wall
along garden

02

8.66

.5

1.5

12.99

02

5.5

.5

1.5

8.25

02

9.55

.5

1.5

14.325

02

32

.5

1.5

48

214.06
1215.326
4

Mild Steel including


Bending in reinforcement
in R.C.C works
R.C.C footing @
0.5%
R.C.C Column @
1.5%
R.C.C Beams@
1.0%
st
1 Class Brickwork in (1:6)
cement mortor
I.
Section A wall
II.
Section B wall
III.
Section C wall
IV.
Section D wall
V.
Section E wall
VI.
Outer Verandah
wall
VII.
Outer bathroom
wall
VIII.
Separation wall of
bathroom
IX.
Bathroom at
corner
X.
Verandah wall
along garden

Density of Mild
steel 78.5q/cum
218.66q
1059.75q
606.05q

02
02
02
02
02
01

50.34
12
12
31.34
15.33
37.34

.5
.5
.5
.5
.5
.5

11.75
11.75
11.75
11.75
11.75
11.75

591.495
141
141
368.245
180.127
219.37

01

8.66

.5

11.75

50.87

01

5.5

.5

11.75

32.312

01

9.55

.5

11.75

56.10

01

3.2

.5

11.75

18.8
1799.319

557.1x.5/100x78.5q/cum

Deduction From Brickwork


Doors
D1
D2
D3
Special
Windows
W1
W2

.06ft thick Plastering


1:6(Inside)

6
2
3
1

66.36
14.7
23.1
14

7
1

41.16
5.565
164.885

378.1

.06ft thick Plastering


1:6(outside)

Deduction

4064.57ft2

460.11ft2
3586.46 ft2

Deduction
8

10.75

1799.319-164.885
=1634.434cuft
Inside means
inside
Rooms,kitchen,
Verandah
excluding Garden
& outside

502.06

5617.145 ft2

304 ft2
5312.99 ft2

Outside house,
walls along
garden& outside
verandah
including
boundary wall

Calculation for Boundary wall


S.No
Particulars of Items
1
Earthwork in Excavation
in Foundation
2

Lean concrete 1:4:8 in


Foundation

1st class brickwork in


Foundation & Plinth
1st footing
2nd footing
Wall portion below G.L

1st class brickwork in


Superstructure
Wall portion above
plinth

No
01

01

Length(ft) Breadth(ft) Height(ft) Quantity(cuft)


Explanatory
138.61
2
3.75
1039.57
60+50x2-12.5x66.39=138.61ft
138.61
2
1
277.22

01
01
01

138.61
138.61
138.61

1.5
1
0.5

0.6
0.6
3.3

124.74
83.16
228.7
436.6

01

138.61

0.5

13.75

952.87

10+ +3=13.75

Sectional View of Column


1'-6"

Roof Beam

Ties #3 Dia 6" Pitch


10'-9"

Plan View of Footing


4'

1'-6"
4'

1'-6"

1'

6"

P.L

1'-6"

Plinth Beam

3'

G.L

Dowel Bars
6 Nos #5 Dia

1'-3"

2'-5"
1'-2"
Concrete Cover .75"

3"

4'

#4 Bars 6"c/c bothway

Calculation of columns
S.No
1

Description of items
Earthwork in
Excavation in
Foundation

NO
15

Length(ft)
4

Breadth(ft)
4

Depth(ft)
3.75

Quantity
900 cuft

Lean concrete 1:4:8


in Base of column
R.C.C work 1:2:4 in
footing
Excluding steel and
its bending but
including centering
and shuttering and
binding of steel
Bottom square
portion
Trapezoidal Portion
Column below
Ground level

15

.25

60 cuft

15

1.667

400.05 cuft
H/6[A1+A2+4AM]

Excluding
bottom portion
of G.L

R.C.C work 1:2:4 in


column
Excluding steel and
its bending but
including centering
and shuttering and
binding of steel
Rectangular portion
below plinth
Rectangular portion
above plinth

15
15

1.5

.5

1.33

157.02 cuft
14.96 cuft
429.97 cuft

15

1.5

.5

1.75

19.68 cuft

15

1.5

.5

10.75

196.87 cuft
216.55 cuft

Steel Reinforcing
bars including
bending
#4 Dia bars @.308
kg/ft in base

#5Dia dowel bar


@.48kg/ft
#3Dia lateral ties
@0.19kg/ft

6x15x
2

19890

61.26q

6x15

1492.57

7.16q

29x15

1740

3.30q
71.72q

Explanatory

Abstract of Estimated Cost of columns


S.No

Name of item & Detail of work

Quantity
900cuft

Rate
Rs.
7

Earthwork in Excavation in foundation

Cement Concrete 1:4:8 in Base

R.C.C work 1:2:4 in footing Excluding steel and its


bending but including centering and shuttering
and binding of steel

R.C.C work 1:2:4 in column above & below G.L


Excluding steel and its bending but including
centering and shuttering and binding of steel

Steel Reinforcements bars including Bending

cuft

Amount
Rs.
6300/-

60cuft

93.5

cuft

5610/-

429.97cuft

220

cuft

94593.4/-

15+216.55cuft
=231.55cuft

220

cuft

50941/-

71.72q

6500

466180/623624.4/-

Add 5% Contingencies & workcharged Establishment

Per

623624.4+31181.22=654805.62/-

L-Section of Beam
#5 Top Bars 2 Nos
#3 Stirrups
#6 Bent up Bars,4Nos

.75" Concrete cover

.75"

12'

#7 Main bars 4 Nos


3"

3"

X-Section of Beam
#3 Stirrups
#5 Top Bars 2 Nos
1'-6"

#6 Bent up Bars,4Nos
0'-6"

#7 Main bars 4 Nos

Calculation of Plinth Beam


S.No
1

Description of items
R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel

Steel Reinforcing
bars(Mild Steel)
including bending
Bending in R.C.C Work
#7 Main Straight Bars
@.92kg/ft
#6 Bentup bars @
.680kg/ft
#5 Top bars @.48kg/ft
#3 Stirrups @0.19kg/ft
@9c/c

NO
01

Length(ft)
12.5

Breadth(ft)
.5

Depth(ft)
1.5

Quantity
9.375cuft

49.24

45.30kg

48.748

33.14 kg

2
17

23.874
39.66

11.45 kg
7.535 kg
97.425kg

Explanatory

L=T.L2cover+2hooks

Abstract of Estimated Cost of A Plinth Beam


S.No

Name of item & Detail of work

R.C.C work 1:2:4 Excluding steel and its bending


but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C

Quantity
9.375cuft

Rate
Rs.
220

Per
Cuft

Amount
Rs.
2062.5/-

97.425kg

65

kg

6332.3/8394.8/-

Now A beam having 12ft clear span has Quantity of 9.375 cuft of R.C.C
Then for 335.06 Length* it will be 145.9 cuft of concrete.
Similarly 12ft beam contains 97.425kg of steel
Then for 186.76ft length it will be 1516.255kg

*Sum of Total length of Plinth beams.

Abstract of Estimated Cost of Plinth Beams


S.No

Name of item & Detail of work

R.C.C work 1:2:4 Excluding steel and its bending


but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C

Quantity
261.76 cuft

Rate
Rs.
220

Per
Cuft

Amount
Rs.
57588.43/-

1516.255kg

65

kg

98556.57/156144.9/-

Add 5% Contingencies & workcharged Establishment

156144.9+7807.2=163952.1/-

Calculation of Roof Beam


S.No
1

Description of items
R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel

Steel Reinforcing bars


(Mild Steel) including
bending Bending in
R.C.C Work
#7 Main Straight Bars
@.92kg/ft
#6 Bentup bars @
.680kg/ft
#5 Top bars @.48kg/ft
#3 Stirrups @0.19kg/ft
@9c/c

NO
01

Length(ft)
12.5

Breadth(ft)
.5

Depth(ft)
1.5

Quantity
9.375cuft

49.24

45.30kg

48.748

33.14 kg

2
17

23.874
39.66

11.45 kg
7.535 kg
97.425kg

Explanatory

L=T.L2cover+2hooks

Abstract of Estimated Cost of A Roof Beam


S.No

Name of item & Detail of work

R.C.C work 1:2:4 Excluding steel and its bending


but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C

Quantity
9.375cuft

Rate
Rs.
220

Per
Cuft

Amount
Rs.
2062.5/-

97.425kg

65

kg

6332.3/8394.8/-

Now A beam having 12ft clear span has Quantity of 9.375 cuft of concrete
Then for 186.76 Length* it will be 145.9 cuft of concrete.
Similarly 12ft beam contains 97.425kg of steel
Then for 186.76ft length it will be 1516.255kg

*Sum of Total length of Roof beams.

Abstract of Estimated Cost of Roof Beams


S.No

Name of item & Detail of work

R.C.C work 1:2:4 Excluding steel and its bending


but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C

Quantity
261.76 cuft

Rate
Rs.
220

Per
Cuft

1516.255kg

65

kg

Amount
Rs.
57588.43/-

98556.57/156144.9/Add 5% Contingencies & workcharged Establishment

156144.9+7807.2=163952.1/-

Cross Section of Slab


.75" Concrete cover

Top Distrib. Bars #3@11"

.75"

#6 Alt.Bent up Bars @9"

5"

12'

#3 Bottom Distribution Bars @9"

#6 Main bars @9"


3"

3"

Bottom Dist. Bars

Straight Main Bar


Alt Bentup Bar

Plan showing Reinforcement Bars

Outer Face of Wall

Top Dist. Bars

15' Clear

Calculation of Slab
S.No
1

Description of items
R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel

Steel Reinforcing bars


(Mild Steel)including
bending Bending in
R.C.C Work
#6 Main bars @9" @
0.675kg/ft

NO
01

Length(ft)
12.5

20

242.5

Breadth(ft)
15.5

Depth(ft)
.416

Quantity
80.72cuft

162.47kg
193.17kg

#6 Alt.Bent up Bars @9"


@ 0.675kg/ft

19

286.18

Top Distrib. Bars


#3@11" @ 0.168kg/ft

21.25

3.57kg

#3 Bottom Distribution
Bars @9 @ 0.168kg/ft

16

233

39.144kg
398.35kg

Explanatory

Abstract of Estimated Cost of Slab


S.No Name of item & Detail of work
1

Quantity

R.C.C work 1:2:4 Excluding steel and its bending but


including centering and shuttering and binding of
steel
Steel bars including bending in R.C.C

80.72cuft

Rate
Rs.
220

Per
Cuft

Amount
Rs.
17758.4/-

398.35kg

65

kg

25892.75/43651.15/-

Now Slab having 12x15 clear span has Quantity of 80.72 cuft of R.C.C
Then for 1698.16ft2 it will be 760.77 cuft of concrete.
Similarly 12x15 slab contains 398.35kg of steel
Then for 1698.16ft2 length it will be 3758.02kg.

Abstract of Estimated Cost of Slab


S.No Name of item & Detail of work
1

Quantity

R.C.C work 1:2:4 Excluding steel and its bending but


including centering and shuttering and binding of
steel
Steel bars including bending in R.C.C

760.77 cuft

Rate
Rs.
220

Per
Cuft

Amount
Rs.
167354/-

3758.02kg

65

kg

244271.3/411625.3/-

Add 5% Contingencies & workcharged Establishment

411625.3+20581.25=432206.55/-

Rate Analysis for Earthwork in Excavation in Foundation including Filling & up to 30m
Lead & 1.5m lift
Take Quantity = 100cum
Cost of Material : NIL
S.No
Labour
NO
Rate
Total
Rs
1

Head Mason

no

650/-

325/-

Mazdoor(Helpers)

20 no

350/-

7000/-

Coolie

24no

250/-

6000/-

Tools &
Miscellaneous

250/13575/-

Add 10% contractors profit = 1357.5/So Total will be 14932.5/ For 100cum = 14932.5/ For 1cum= 149.32/ For 1cuft =

.
.

=4.228/-

Rate analysis for lean concrete (1:4:8) in foundation


Take quantity = 10cum
Loose quantity =1.5x10=15cum
Cement=[( )x15]=1.15cum
F.A=[( )x15]=4.61cum
C.A=[( )x15]=9.23cum
1.15cum of cement
1 beg of cement =0.035cum
No of begs of cement =

.
.

= 32.8 33begs

S.No Particulars

Cost of material
Quantity
Rate
Rs/-

Per

Total
Rs/-

Cement

33Begs

450/-

Beg

14850/-

F.A

4.61cum

300/-

Cum

1383/-

C.A

9.32cum

700/-

Cum

6524/22757/-

Cost of labour
NO

S.No Labour
1
2
3
4
5

Head Mason
Masons
Mazdoor(Helpers)
Coolie
Tools &
Miscellaneous(Lump
sum)

no
1.5no
12no
18no

Total=Material cost + Labour cost=33032/Add 1.5% water charges = 495.45/Add 10% contractors profit =3303.2/ For 10cum=36830.65/ For 1cum= 3683/ For 1cuft =

=104.3/-

Rate
Rs/-

Total
Rs/-

750/600/350/250/-

375/900/4200/4500/300/10275/-

Rate analysis for R.C.C 1:2:4

Take quantity = 10cum


Loose quantity =1.5x10=15cum
Cement=[( )x15]=2.14cum
F.A=[( )x15]=4.28cum
C.A=[( )x15]=8.57cum
1.15cum of cement
1 beg of cement =0.035cum
No of begs of cement =
Steel bars @1%=

.
.

= 61.22 62begs

x10=0.1cum

78.5 quintal/cum
0.1cum steel=78.5x0.1=7.85x100kg=785kg

S.No Particulars

Cost of material
Quantity
Rate
Rs/-

Per

Total
Rs/-

Cement

62Begs

450/-

Beg

27900/-

F.A

4.28cum

300/-

Cum

1284/-

C.A

8.57 cum

700/-

Cum

5999/-

Steel

785kg

70/-

Kg

54950/-

Binding wire

1.5kg

75/-

kg

112.5/90245.5/-

Cost of labour
NO

S.No Labour
1
2
3
4
5
6

Head Mason
Masons
Mazdoor(Helpers)
Coolie
Waterman
Tools &
Miscellaneous(Lump
sum)

no
3no
12no
20no
6no

Rate
Rs/-

Total
Rs/-

750/600/350/250/200/-

375/1800/4200/4500/1200/300/12375/-

Bending,Cracking & Binding steel


S.no Labour

No

1
2
3

8No
8no

Black smith
Mazdoor
Tools & miscellaneous

Rate
Rs/600/350/-

Total
Rs/4800/
2800/150/7750/-

Centering & Shuttering:


NO Labour
1
2
3
4
5

Timber planks(Lump sum)


Carpenters
Helpers
Nails
T&P

NO

Rate
Rs/-

10NO
10NO

550/350/-

Total=M.Cost+L.Cost+L for steel Cost+Shuttering=121770/Add 1.5% water charges = 1496.79/Add 10% contractors profit =9978.6/ For 10cum=133244.7/ For 1cum= 13324.47/ For 1cuft =

.
.

=377.46/-

Total
Rs/2000/5500/3500/250/150/11400/-

Rate analysis for 1st class brickwork in Super structure with 1:6 Cement Sand mortar
Take quantity = 10cum
30% of dry volume of mortar is required =3cum
1:6 ratio
Cement=[( )x3]=0.428cum
Sand=[( )x3]=2.57cum
0.428 cum of cement
1 beg of cement =0.035cum
No of begs of cement =

.
.

= 12.22 13begs

S.No Particulars

Cost of material
Quantity
Rate
Rs/-

Per

Total
Rs/-

Cement

13Begs

450/-

Beg

5850/-

Bricks(500 per
cum)
Sand

5000nos

7/-

Cum

35000/-

2.57 cum

300/-

Cum

810/-

41660/Cost of labour
NO

S.No Labour
1
2
3
4
5

6
7

Head Mason
Masons
Mazdoor(Helpers)
Coolie
Tools &
Miscellaneous(Lump
sum)
Scaffolding
Water man

Total=M.Cost+L.Cost= 54835/Add 1.5% water charges = 822.525/Add 10% contractors profit = 5483.5/ For 10 cum= 61141/ For 1 cum= 6114.1/ For 1 cuft

.
.

=173.15/-

no
10 no
7no
10no

2no

Rate
Rs/-

Total
Rs/-

750/600/350/250/-

375/6000/2450/2500/1000/-

250/-

350/500/13175/-

Rate analysis for (0.06ft) Plastering (1:6)


Take 100 sq.m
100x0.012m=1.2cum
2 cum will be considered
1:6 Ratio
Cement=[( )x2]=0.0285 cum
Sand=[( )x2]=1.71 cum

Cost of material
Quantity
Rate
Rs/-

S.No

Particulars

Cement

9Begs

Sand

1.7cum

S.No

Labour

1
2
3
4
5

Head Mason
Masons
Mazdoor(Helpers)
Scaffolding
Water man

.
.

=55.03/-

700/-

Cost of labour
NO

Total=M.Cost+L.Cost=17427.5/Add 1.5% water charges = 261.41/Add 10% contractors profit =1742.7/ For 10 cum= 19431.6/ For 1 cum= 1943.16/ For 1 cuft

450/-

Per

Total
Rs/-

Beg

4050/-

Cum

1190/5240/-

Rate
Rs/-

1/3 no
10 no
15no

750/600/350/-

3/4no

250/-

Total
Rs/250/6000/5250/500/187.5/12187.5/-

Summary of Quantities
S.No

Discription of items

Quantity

1
2
3
4
5
6

Earthwork in excavation in foundation


Lean concrete 1:4:8 in base of column & footing
R.C.C work 1:2:4 in footing
R.C.C work 1:2:4 in column
Steel reinforcement bars including bending in column
Quantity of R.C.C Roof beam

2045.6cuft
337.22cuft
557.02cuft
213.51cuft
71.72q
261.76cuft

7
8
9
10
11
12
13

Quantity of steel in Roof beam


Quantity of R.C.C for slab
Quantity of steel for slab
Masonry work in superstructure
0.06ft Thick Plastering(1:6)
Quantity of R.C.C in plinth beam
Quantity of steel in plinth beam

1516.255kg
760.77cuft
3758.02 kg
2587.27cuft
8899.36ft2
261.76cuft
1516.255kg

Plinth Area Rate is

=1111.6/-per cuft

Cost
Rs/8648.7/35172.04/210252.76/80587.7/466180/98803.92/Included
287133.8/Included
447985.8/489731.78/98803.92/Included
2223299.52/-

You might also like