FLUSHING GUIDELINE B&E CLASS GAS TURBINE

FLUSHING GUIDELINE B&E CLASS GAS TURBINE

super user

403A5502
DT-7C

GRD E

Commissioning Guideline

Flushing Guideline
B & E-Class Gas Turbine

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 1 / 32

1 GENERAL INFORMATION:
1.1

Purpose of the document:

The purpose of this document is to guide trained, qualified and authorized GE-commissioning engineers or
GE-technical advisors (TA) or GE-supervisors to perform the various flushing required during the start-up of a
power plant. It has to be adapted according to site conditions and discussed with mechanical team to match
specific site configuration.
Photos and drawings provided in this document are not contractual, they are only given to show how to install
flushing parts and they may not reflect site reality as connections may differ depending supplier selected.
Gas turbine, generator and skids are generally delivered at site in a clean condition. Flushing at site concerns
mainly the off base piping. As per design, pipes used for on-base piping are stainless steel or already factory
cleaned. In spite of keeping pipes in a clean condition during installation, dust and debris may remain inside
the system; therefore the purpose of flushing is to remove these foreign particles.
Piping lengths which cannot be flushed are blown with compressed air and visually inspected.
It is once more recalled that during construction, piping must be stored in dry,
dustless and safe area (shelter is recommended), plugged at each end with relevant caps.
This document can be used as a check-list during flushing, but it is not an official record of the operation. The
official record is the commissioning book of the unit that must include evidence of flushing and results.

1.2

Safety policy:

All EHS (Environment, Hygiene and Safety) rules and recommendations, recorded in the EHS Construction
Plan must be applied, particularly wearing required PPE (Personal Protective Equipment).
No job can be started if people or equipment safety is compromised. This is a GE Global Policy requirement
and nothing can lead to ignore these safety rules.
Commissioning activity generates mainly 2 types of risk:
Electrical hazards:
all needed precautions have to be taken to avoid contact with electrical parts
under voltage. Be conscious that on generator, residual voltage is present even if machine is at
standstill and not excited ;
Mechanical hazards: all needed precautions have to be taken to prevent contact with rotating parts
(shaft line, motor, pumps, etc.).

1.3

Flushing acceptance criteria:

For all circuits, please refer to GEK-110483 for flushing acceptance criteria to be met. The criteria mentioned
in this guideline are for information only and must be verified with the latest version of the GEK before use.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

DT-7C

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
B & E-Class Gas Turbine
1.4
1

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 2 / 32

Summary:
General Information: .................................................................................................................................... 1

1.1

Purpose of the document:.................................................................................................................... 1

1.2

Safety policy:........................................................................................................................................ 1

1.3

Flushing acceptance criteria: ............................................................................................................... 1

1.4

Summary:............................................................................................................................................. 2

1.5

Revision status: ................................................................................................................................... 3

Lube Oil Flushing: ........................................................................................................................................ 4


2.1

Safety complement: ............................................................................................................................. 4

2.2

Acceptance Criteria: ............................................................................................................................ 4

2.3

Flushing process for B-class unit: ........................................................................................................ 5

2.4

Flushing process for E-class unit: ...................................................................................................... 12

2.5

Lube oil flushing record sheet: ........................................................................................................... 21

Gas Fuel Flushing:..................................................................................................................................... 22


3.1

Safety complement: ........................................................................................................................... 22

3.2

Acceptance Criteria: .......................................................................................................................... 22

3.3

Gas fuel flushing: ............................................................................................................................... 22

Liquid Fuel Flushing:.................................................................................................................................. 23


4.1

Safety complement: ........................................................................................................................... 23

4.2

Acceptance Criteria: .......................................................................................................................... 23

4.3

Flushing process: ............................................................................................................................... 23

4.4

Flushing completion: .......................................................................................................................... 26

Water-Cooling Flushing: ............................................................................................................................ 27


5.1

Safety complement: ........................................................................................................................... 27

5.2

Acceptance Criteria: .......................................................................................................................... 27

5.3

Flushing Process: .............................................................................................................................. 27

5.4

Flushing completion: .......................................................................................................................... 31

Reference Documents: .............................................................................................................................. 32

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 3 / 32

Commissioning Guideline

Flushing Guideline
B & E-Class Gas Turbine
1.5

Revision status:

REV.
A

DATE

DOCUMENT

(dd/mm/yyyy)

02/04/2012

Flushing guideline

OBJET
First issue BR

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 4 / 32

2 LUBE OIL FLUSHING:


2.1

Safety complement:

Oil generates mainly 3 types of risk:


Pollution: all precautions must be taken to avoid accidental leakages and spillage during preliminary
tests. These safety precautions must be taken regarding the HSE Plan of the site and the local
regulation.
Pollution fighting means (basin, absorbent, etc.) must be available near the hazardous area.
Fire: oil does not present fire risk by itself. Risks can arise when oil is near an ignition source (heat,
spark, naked flame, etc.).
Respect of work permit and particularly, hot work permit should allow to bring the risk under control.
Firefighting means (hydrocarbon fire extinguishers, sand, etc.) must be available near the hazardous
area.
Chemical: please refer to Material Safety Datasheet and take required precautions

2.2

Acceptance Criteria:

GEK-110483 reminds what the acceptance criteria are for the cleanliness of the lube-oil and HP-oil systems. It
also provides guidelines to evaluate this cleanliness.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 5 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.3

Flushing process for B-class unit:

GT flushing is performed with operating oil, except if dedicated flushing load is specified by the contract. GT
lube oil tank, GT auxiliary lube oil pump (88QA) and GT lube oil filters can be used for the flushing process.
The oil demister (88QV) must not be used during the flushing.
Main lube oil filter must be equipped with standard cartridges which are replaced after flushing completion as
per MLI106.
Before flushing, take samples of the clean oil using procedure 91-438752 as a guideline. Use a clean, dry and
appropriated recipient. Do not spoil sample with a dirty filing pipe / point. Ensure the dead volume between
circulating line and sampling point has been flushed prior to take sample.
Keep oil samples in a clean and safe place (respect EHS rules) during the total presence of GE Personnel at
site. Protect samples from direct sun light.
During flushing, oil temperature must be higher than 40C. Lube oil flows through coolers with cooling water
not running. If oil tank heaters are used to warm up flushing oil, this important guideline must be followed:
Lube oil level must be higher than the heaters when pump 88 QA is running.
Lube oil must circulate when heaters are switched on.
Heaters should be switched off when oil temperature reaches 54C.
Oil temperature must not be over SpeedTronic alarm.
A temporary emergency push button to stop lube oil pump may be installed in the auxiliary compartment.
Flushing supervisor and watchers must know where and how to stop the lube oil pump.
To insure a sufficient flow, flushing is performed in two main sequences:
Phase 1: bearing #2 & load gear by-passed, generator line blocked
Phase 2: bearing #2 & generator bearings by-passed, load-gear blocked
According to site experience, if all the necessary precautions have been taken during installation to
keep piping in a clean condition, the minimum flushing durations are:
12 hours for phase 1
12 hours for phase 2
Remaining short length of feeding pipes, not flushed with a lube oil flow,
must be cleaned using 6 bars compressed air and installed after visual inspection.
During flushing, parameters must be monitored and recorded frequently (15 minutes).
Pump motor amps must be monitored at every change in the flushing circuit to be sure that full load amps are
not exceeded.
Proceed to phases 1 and 2 of the flushing sequences (See hereafter for a detailed procedure).

NB: Bearing #1 feeding pipe is not specifically flushed at site as the auxiliary module comes coupled with the
gas turbine. The oil circulates through the bearing #1 during the 2 flushing phases.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 6 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.3.1

Mechanical preparation Phase 1:

General view of 6B turbine oil system

Remove all servo valves, and install relevant flushing blocks and gaskets

Keep servo valves in a plastic bag to avoid any contamination. Make sure not to lose any O-ring gaskets.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 7 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Disconnect feeding line to bearing #2, to allow oil to flow in the return line

Detail Bearing #2 feeding line WITH gap

By-pass the load gear and close the inlet (use relevant drawing for construction of blue pipe)

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 8 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Install a system to take sample at the oil pump outlet

Disconnect and plug the control line of VPR2-1 to allow this valve to stay fully open during flushing

Set the transfer valves to one cooler, one main filter, and one HP filter

Close inlet valve of torque converter strainer

Check that electrical power supply is available for AC lube oil pump and heaters

Check GT auxiliaries frame earth connections

Check that the filters are equipped with cartridges :


o

Lube oil filter #1

Lube oil filter #2

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 9 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
o

HP oil filter #1

HP oil filter #2

Check that the low tank drain pipes are closed and locked

Check the cleanliness of the tank before filling up (you might perform TEP01 and tank inspection
before)

Fill up the tank with 6000 liters (30 drums) of oil. (the quantity of oil used for flushing may be less
important than final load)

2.3.2

Flushing Phase 1:
Walk-down all the lines, including instrumentation lines, to prevent any risk of leakages
Proceed to motor-heater tests if not done (see TPE01 and TEP02)
Start the lube oil pump (88QA-1). Check for leak. The motor AC current should not be higher than
nominal current.
During flushing sequence, record AC current, oil pressure, oil temperature, oil filter pressure
drop, according to data sheets hereafter.
Flushing is completed when oil sample reach GEK-110483 criteria
Flushing phase 1 completion date:

2.3.3

Mechanical preparation Phase 2:

Apply proper LOTO procedures

Keep by-pas at bearing #2

Prepare generator for flushing:


o

Remove load gear by-pass and block inlet and outlet

Open generator feeding and return lines

By-pass feed lines to return lines as close as possible from the bearings

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 10 / 32

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 11 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.3.4

Flushing Phase 2:
Start the lube oil pump (88QA-1). Check for leak. The motor AC current should not be higher than
nominal current.
During flushing sequence, record AC current, oil pressure, oil temperature, oil filter pressure
drop, according to data sheets hereafter.
Flushing is completed when oil sample reach GEK-110483 criteria.
Flushing phase 2 completion date:

2.3.5

Flushing completion:

Remove all blank plates special fitting and by-pass

Restore all piping and check the system conformity according to P&ID (orifice plates, instrumentation),
do not forget VPR2-1 control line

Regarding jacking oil, length of site installed tubing must be air blown and thoroughly inspected before
final installation.

Run 88 HQ pump for 2 hours. Carefully monitor 88 HQ motor current and HP filter differential
pressure:
o If differential pressure is above 4 bars investigate for any concern (leaks, opened valves in
instrument lines, filters clogged, etc), change filter if clogged.
o

Run 88HQ till differential pressure is normal (see item 0414)

While performing hydraulic oil flushing, jacking oil length of site installed tubing should be
flushed with jacking oil pumps

Reinstall servo valves

Drain the filters

Replace lube oil main filter cartridges

Add oil in the tank

After restoration, check for any leak and verify bearings return oil flow through sight glasses.

Check the oil tank level, 10 minutes after stopping the pump, and adjust it if necessary.
Flushing restoration completed date:

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 12 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.4

Flushing process for E-class unit:

GT flushing is performed with operating oil, except if dedicated flushing load is specified by the contract. GT
lube oil tank, GT auxiliary lube oil pump (88QA) and GT lube oil filters can be used for the flushing process.
The oil demister (88QV) must not be used during the flushing.
Main lube oil filter must be equipped with standard cartridges which are replaced after flushing completion as
per MLI106.
Before flushing, take samples of the clean oil using procedure 91-438752 as a guideline. Use a clean, dry and
appropriated recipient. Do not spoil sample with a dirty filing pipe / point. Ensure the dead volume between
circulating line and sampling point has been flushed prior to take sample.
Keep oil samples in a clean and safe place (respect EHS rules) during the total presence of GE Personnel at
site. Protect samples from direct sun light.
During flushing, oil temperature must be higher than 40C. Lube oil flows through coolers with cooling water
not running. If oil tank heaters are used to warm up flushing oil, this important guideline must be followed:
Lube oil level must be higher than the heaters when pump 88 QA is running.
Lube oil must circulate when heaters are switched on.
Heaters should be switched off when oil temperature reaches 54C.
Oil temperature must not be over SpeedTronic alarm.
A temporary emergency push button to stop lube oil pump may be installed in the auxiliary compartment.
Flushing supervisor and watchers must know where and how to stop the lube oil pump.
To insure a sufficient flow, flushing is performed in two main sequences:
Phase 1: gas turbine bearings #2 and #3 feeding lines,
Phase 2: gas turbine bearing #3 and generator bearings feeding lines.
According to site experience, if all the necessary precautions have been taken during installation to
keep piping in a clean condition, the maximum average time to flush is around 48 hours circulation.
However, the minimum flushing durations are:
12 hours for phase 1
12 hours for phase 2
Remaining short length of feeding pipes, not flushed with a lube oil flow,
must be cleaned using 6 bars compressed air and installed after visual inspection.
During flushing, parameters must be monitored and recorded frequently (15 minutes).
Pump motor amps must be monitored at every change in the flushing circuit to be sure that full load amps are
not exceeded.
Proceed to phases 1 and 2 of the flushing sequences (See hereafter for a detailed procedure).

NB: Bearing #1 feeding pipe is not flushed at site but has to be cleaned by hand, air-blown and carefully
inspected before final installation.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.4.1

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 13 / 32

Mechanical preparation Phase 1:

General view of 9E turbine oil system

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 14 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
For 9E-frame, material is part of MLI A125
Remove all servo valves, and install relevant flushing blocks and gaskets

Keep servo valves in a plastic bag to avoid any contamination. Make sure not to lose any O-ring gaskets.

Disconnect feeding line to the gas module (if part of the requisition), to allow oil to flow in the return
line

Detail A Gas module connection WITH gap

Install a closure plate in GT Bearing #1 feeding line

Detail E Bearing #1 feeding line blocked

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 15 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Install a blank plate in GT Bearing #2 feeding line, leave a gap for lube oil flowing to return line

Detail B Bearing #2 feeding line WITH gap

Disconnect feeding line to bearing #3, to allow oil to flow in the return line

Detail C Bearing #3 feeding line WITH gap

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 16 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Disconnect IGV connections and partially plug them

Detail D IGV connection PARTIALLY plugged

Install bypasses made on site on each generator bearing to prevent oil from going into the bearing
(U-pipe between supply and return line) Leave valves closed if any.

Check that generator lifting oil feeding pipe is closed or plugged on supply side

Generator bearing #4 (turbine side)

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 17 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Generator bearing #5 (excitation side)

Install a system to take sample at the oil pump outlet

Disconnect and plug the control line of VPR2-1 to allow this valve to stay fully open during flushing

Set the transfer valves to one cooler, one main filter, and one HP filter

Close inlet valve of torque converter strainer

Check that electrical power supply is available for AC lube oil pump and heaters

Check GT auxiliaries frame earth connections

Check that the filters are equipped with cartridges :


o

Lube oil filter #1

Lube oil filter #2

HP oil filter #1

HP oil filter #2

Check that the low tank drain pipes are closed and locked

Check the cleanliness of the tank before filling up (you might perform TEP01 and tank inspection
before)

Fill up the tank with 10000 liters (50 drums) of oil. (the quantity of oil used for flushing may be less
important than final load)

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 18 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.4.2

Flushing Phase 1:
Walk-down all the lines, including instrumentation lines, to prevent any risk of leakages
Proceed to motor-heater tests if not done (see TPE01 and TEP02)
Start the lube oil pump (88QA-1). Check for leak. The motor AC current should not be higher than
nominal current.
During flushing sequence, record AC current, oil pressure, oil temperature, oil filter pressure
drop, according to data sheets hereafter.
Flushing is completed when oil sample reach GEK-110483 criteria.
Flushing phase 1 completion date:

2.4.3

Mechanical preparation Phase 2:

Apply proper LOTO procedures

Install a plug to the gas module (if part of the requisition)

Detail A Gas module connection WITHOUT gap

Keep the blank plate in GT Bearing #1 feeding line

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 19 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing

Keep the blank plate and close the gap at GT Bearing #2

Detail B Bearing #2 feeding line WITHOUT gap

Keep the by-pass in the GT Bearing #3 feeding line

Plug the remaining IGV connections

Detail D IGV connection TOTALLY plugged

Open valves located in generator bearings bypasses

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 20 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.4.4

Flushing Phase 2:
Start the lube oil pump (88QA-1). Check for leak. The motor AC current should not be higher than
nominal current.
During flushing sequence, record AC current, oil pressure, oil temperature, oil filter pressure
drop, according to data sheets hereafter.
Flushing is completed when oil sample reach GEK-110483 criteria.
Flushing phase 2 completion date:

2.4.5

Flushing completion:

Remove all blank plates special fitting and by-pass

Restore all piping and check the system conformity according to P&ID (orifice plates, instrumentation),
do not forget VPR2-1 control line

Regarding jacking oil, length of site installed tubing must be air blown and thoroughly inspected before
final installation.

Run 88 HQ pump for 2 hours. Carefully monitor 88 HQ motor current and HP filter differential
pressure:
o If differential pressure is above 4 bars investigate for any concern (leaks, opened valves in
instrument lines, filters clogged, etc), change filter if clogged.
o

Run 88HQ till differential pressure is normal (see item 0414 )

While performing hydraulic oil flushing, jacking oil length of site installed tubing should be
flushed with jacking oil pumps

Reinstall servo valves

Drain the filters

Replace lube oil main filter cartridges

Add oil in the tank

After restoration, check for any leak and verify bearings return oil flow through sight glasses.

Check the oil tank level, 10 minutes after stopping the pump, and adjust it if necessary.
Flushing restoration completed date:

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 21 / 32

Commissioning Guideline

Flushing Guideline
Lube Oil Flushing
2.5

Lube oil flushing record sheet:

LUBE OIL FLUSHING PHASE #________

DATE

TIME

88 QA / AC
CURRENT

LUBE OIL
TEMPERATURE

88QA
OUTLET
PRESSURE

OIL FILTER
PRESSURE
DROP

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Gas Fuel Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 22 / 32

3 GAS FUEL FLUSHING:


3.1

Safety complement:
Please be remembered that flammable gas blows are prohibited on GE sites and that
GE personal cannot stay at site if such means are used for gas pipes cleaning.

Please refer to GEK-116771: GE Energy recommendations, Fuel Supply System Cleaning for Gas Turbines
and EPRI Guideline 1023628: Guidelines for Fuel Gas Line Cleaning Using Compressed Air or Nitrogen for
more details on proved alternative cleaning methods

Fuel gas generates mainly 2 types of risk:


Fire or explosion hazards:
all needed precautions have to be taken to avoid fire or explosion at
site, especially when working on Gas, Liquid Fuel, Oil systems ; risks can arise when gas is near an
ignition source (heat, spark, naked flame, etc.). Respect of work permits and particularly, hot work
permits should allow to bring the risk under control.

3.2

Acceptance Criteria:

GEK-110483 reminds what the acceptance criteria are for the cleanliness of the gas system. It also provides
guidelines to evaluate this cleanliness.

3.3

Gas fuel flushing:

Our recommendation for the cleaning of the gas system is to perform air-blows of limited lengths of pipes.
These air-blows will allow chasing out most of the pieces left in the pipes during erection.
We want to emphasize once more that building a clean circuit makes it easier and cheaper to clean by
reaching the acceptance criteria quicker.
The 2 documents cited in the first part of this section are explicit enough and we do not want to reproduce
them here. Please refer to these documents to perform the safest and the most efficient cleaning as possible.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Liquid Fuel Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 23 / 32

4 LIQUID FUEL FLUSHING:


4.1

Safety complement:

Light Distillate Oil and Heavy Fuel Oil generate mainly 3 types of risk:
Pollution: all precautions must be taken to avoid accidental leakages and spillage during preliminary
tests. These safety precautions must be taken regarding the HSE Plan of the site and the local
regulation.
Pollution fighting means (basin, absorbent, etc.) must be available near the hazardous area.
Fire: oil does not present fire risk by itself. Risks can arise when oil is near an ignition source (heat,
spark, naked flame, etc.).
Respect of work permit and particularly, hot work permit should allow to bring the risk under control.
Firefighting means (hydrocarbon fire extinguishers, sand, etc.) must be available near the hazardous
area.
Chemical: please refer to Material Safety Datasheet and take required precautions

4.2

Acceptance Criteria:

GEK-110483 reminds what the acceptance criteria are for the cleanliness of the fuel oil system. It also
provides guidelines to evaluate this cleanliness.

4.3

Flushing process:

Liquid fuel systems flushing are performed with light distillate oil.
The existing tank and the LDO forwarding pumps (centrifugal) may be used for flushing. Tank level must be
sufficient to ensure proper circulation without priming problem.
Please note that in the case there are 2 liquid fuels (LDO and HFO for example), it can be interesting to flush
the 2 feeding lines at the same time to maximize flow. Once feeding lines are clean, return lines are flushed in
a second phase.

Please note that in case of 2 liquid fuels (LDO + HFO), HFO volumetric pump must not be used to
flush HFO lines with LDO. There is a high risk of damaging the pumps.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Liquid Fuel Flushing
4.3.1

Mono-liquid fuel system:

4.3.2

Bi-liquid fuel system:

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 24 / 32

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 25 / 32

Commissioning Guideline

Flushing Guideline
Liquid Fuel Flushing
4.3.3

Mechanical preparation for Off-base flushing:

4.3.3.1 Mono-liquid fuel system:


Mechanical preparation consists mainly in following items:
Check that baskets are present in forwarding pumps strainers

Add a by-pass on fuel heaters

Add a by-pass on filtering skid

Add a filter system on the return line to prevent pollution of the tank, this system must be isolable to
clean the filter without emptying the lines

Ensure that any leakage on flanges will be recovered (basin + mechanical helpers)

By-pass for LDO heating skid

By-pass for LDO Filtering skid

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 26 / 32

Commissioning Guideline

Flushing Guideline
Liquid Fuel Flushing
4.3.3.2 Bi-liquid fuel system:
Mechanical preparation consists mainly in following items:
Add a by-pass on fuel heaters

Add a by-pass on filtering skid

Add a filter system on the return line to prevent pollution of the tank, this system must be isolable to
clean the filter without emptying the lines and return to HFO tank

Ensure that any leakage on flanges will be recovered (basin + mechanical helpers)

Please note that in both cases, the stainless steel pipe between the filtration skid and the unit must be airblown and carefully inspected prior to final assembly.
4.3.4

Off-base flushing:

Ensure proper commissioning of at least one forwarding pump (see TEP01 & TEP02)

Start one pump and circulate fuel till filters are clogged

Clean the filters and star again circulation till filters GEK-110483 criteria are met

To be more efficient it is possible to use the 2 LDO forwarding pumps in parallel, current must be carefully
monitored to avoid electric motor overheat and damage.
Off-base flushing completed on the:
4.3.5

On-base flushing:

For On-base flushing, please refer to document 586A1072: Liquid Fuel Flushing Procedure. This document is
not dedicated to B and E-Class units but can provides guideline if you have any doubt on the On-Base
cleanliness.
On-base flushing completed on the:

4.4

Flushing completion:

When both Off-base and On-base flushing are completed, commissioning can be initiated.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Water-Cooling Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 27 / 32

5 WATER-COOLING FLUSHING:
5.1

Safety complement:

Cooling water generates mainly 2 risks:


Burn: all precautions must be taken to avoid contact with hot pipes and hot water at release points. If
permanent barriers or insulation are not in place, use temporary signalization to prevent access to
hazardous zone (for example vent of the heat-exchanger on atomizing air cooler)
Chemical: please refer to Material Safety Datasheet and take required precautions

5.2

Acceptance Criteria:

GEK-110483 reminds what the acceptance criteria are for the cleanliness of the fuel oil system. It also
provides guidelines to evaluate this cleanliness.

5.3

Flushing Process:

Please note that for some 6B units with only shaft-driven water cooling pump, you will need to use an external
skid for the flushing of the circuit.
Truck equipped with autonomous pumps and separated tanks is a good option to save time and money when
this case arises.

If your cooling water installation has its own circulating pumps, you may proceed as follows.

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Water-Cooling Flushing
5.3.1

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 28 / 32

Mechanical preparation for phase 1 flushing:

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

Commissioning Guideline

Flushing Guideline
Water-Cooling Flushing

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 29 / 32

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 30 / 32

Commissioning Guideline

Flushing Guideline
Water-Cooling Flushing
Mechanical preparation consists mainly in following items:
Check that witch hats are installed upstream circulating pumps

Install by-pass on generator coolers (install vent points if needed)

Install by-pass on turbine coolers (Remove VTR1-1 and VTR2-1)

Install by-pass on finfan radiators

Close valves to flame detectors

Close valves to HP fuel pump (HFO option)

Close line to fuel check valve coolers (Liquid option) and close valve on the return line

Generator By-pass

5.3.2

FinFan Cooler By-pass

Phase 1 flushing (Turbine On-base then generator piping):

Ensure proper commissioning of at least one circulating pump (see TEP01 & TEP02)

Close valves to generator coolers to maximize flow in turbine

Start one pump and circulate water till filters are clogged, monitor pressure and noise to keep safe
situation (site experience proved that first runs can stay less than 15 seconds!)

Clean the filters and start again circulation till filters can run 2 hours without dirt inside

Open valves to generator and close valves to turbine to maximize flow in generator piping

Start one pump and circulate water till filters are clogged, monitor pressure and noise to keep safe
situation (site experience proved that first runs can stay less than 15 seconds!)

Clean the filters and start again circulation till filters can run 2 hours without dirt inside

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 31 / 32

Commissioning Guideline

Flushing Guideline
Water-Cooling Flushing
5.3.3

Mechanical preparation for phase 2 flushing (Finfan radiators):

Apply needed LOTO procedure to change configuration

Remove Finfan radiators by-pass

5.3.4

Phase 2 flushing (Finfan radiators):


Start one pump and circulate water till filters are clogged, monitor pressure and noise to keep safe
situation (site experience proved that first runs can stay less than 15 seconds!)

5.3.5

Clean the filters and start again circulation till filters can run 2 hours without dirt inside

Mechanical preparation for normalization:

Apply needed LOTO procedure to change configuration

Remove all by-pass

Install VTR1-1 and VTR2-1

Open valves to HP fuel pump

Remove plug to fuel check valve coolers (optional) and open the return line

Fill the circuit with clean tap water

5.3.6

Phase 3 flushing:
Open all valves to get final configuration (force open the solenoid valve to optional fuel check valve
coolers)

Start one pump and circulate water till filters are clogged, monitor pressure and noise to keep safe
situation (site experience proved that first runs can stay less than 15 seconds!)

5.4

Clean the filters and start again circulation till filters can run 2 hours without dirt inside

Flushing completion:

When circulation can be let for several hours a day without filters clogged, the flushing is considered OK.
Normalize the circuit and circulate in normal configuration.
Change water for demineralized one and add needed chemicals according procedure #249A4685
Cooling water flushing completion date:
Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.

GPO / GFO / M&I


403A5502
Revision: A
Unit: B & E GT
Page : 32 / 32

Commissioning Guideline

Flushing Guideline
Reference Documents

6 REFERENCE DOCUMENTS:
Please find here below the list of the documents used to establish this guideline. Please check that there are
still up-to-date prior to use information published in this guideline.
EPRI Guideline 1023628 (Update Dec. 2011): Guidelines for Fuel Gas Line Cleaning Using
Compressed Air or Nitrogen. EPRI, Palo Alto, CA: 2011
GE Energy drawing # 145E6599 (Rev.A):

Piping Lube-Oil Flush Field (6B)

GE Energy drawing #249A4685 (Rev.A):


GE Water

Commissioning Manual Cooling Water Chemicals

GE Energy drawing #586A1072 (Rev.B):

Liquid Fuel Flushing Procedure

GE Energy drawing #91-438752 (Rev.C):

Monitoring of Lubricating Oil

GE Energy GEK-110483 (Rev.D):


Cleanliness
Installation, Commissioning, and Maintenance

Requirements

for

Power

Plant

GE Energy GEK-116771 (Dec. 2012):


Cleaning for Gas Turbines

GE Energy recommendations, Fuel Supply System

GE Energy GEK-116944 (Nov.2011):


Systems with Motor Driven Main Oil Pumps

Flushing Recommendations for Turbine Lube Oil

--- End of document ---

Observations :

This document, sole property of our company, is


strictly confidential. It must not be
communicated, copied or reproduced without our
written consent.

Ce document, proprit exclusive de notre


Socit, est strictement confidentiel. Il ne peut
tre communiqu, copi ou reproduit sans notre
autorisation crite.

Este documento, proprietad exclusiva de nuestra


Compania, es estricamente confidential. No puede
ser communicado, copiado o reproducido sin su
autorizacion escrita.