Professional Documents
Culture Documents
Title:
Revision Number:
T-PreCom-1000-R0
Prepared By:
PRE-COMMISSIONING TEST
PROCEDURES FOR SEC
TRANSMISSION
ELECTRICAL INSTALLATIONS
00
Original Issue Date:
Pre-Commissioning Committee
Revised By:
2003-06-17
Revision Date:
Recommended By:
Page Number:
Mohammad S. AL-Rafaa
1 of 124
Approved By:
1.0
INTRODUCTION
Proper pre-commissioning of new electrical equipment is important to prove that new equipment has
been properly shipped and correctly erected and installed. This Procedure highlights the necessary steps
related to proper pre-commissioning of new electrical equipment.
As a general practice, all equipment is tested in the factory before delivery to the site. Pre-commissioning
testing at site is done to prove that:
Purpose
Procedure
This Procedure is divided to two parts: the first part describes organizing the work at site before,
during and after pre-commissioning tests.
The second part concerns the mechanical checks, inspections and electrical tests to be
performed on the equipment before commissioning the equipment into service.
PART I. ORGANIZATION OF THE WORK SITE FOR PRE-COMMISSIONING
PART II. MECHANICAL TESTS, VISUAL INSPECTIONS AND ELECTRICAL TESTS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 2 of 124
INTRODUCTION
Pre-commissioning tests for a new or reinforcement project are to be checked thoroughly and witnessed
by SEC Commissioning engineer or technician. During the course of the commissioning it has been
observed that at many stages the contractors are not ready and consequently the Commissioning
personnel have to wait with the result that some tests may be missed or ignored. A procedure is required
to check the complete readiness of the contractor before the pre-commissioning tests and prepare the
commissioning engineer/technician for applying commissioning tests as per SEC commissioning
Procedure. This document briefly outline the necessary steps to be followed to ensure that contractors
are ready to start the pre -commissioning in order to reduce or maintain the approved project milestones
and control the quality of the commissioning test.
The main purpose of this procedure is to provide necessary guidelines to ensure the readiness of the
contractors to start the pre-commissioning testing of new or reinforcement projects and how to apply and
perform the pre-commissioning tests ensuring that:
2.0
PROCEDURES
2.1
Project Management shall confirm the readiness of the contractor from all aspects. A joint
inspection shall be conducted with commissioning personnel and the contractor to ensure the
contractors readiness to start the project after written confirmation is received from Project
Management.
2.1.1 Contents of Confirmation Letter
The Confirmation Letter shall, at minimum, contain:
Equipment is installed and has been inspected and satisfied by the SEC Project
Quality section.
Availability of contractors qualified manpower and testing engineers.
Availability of tools and test equipment with one-year valid calibration certificate.
Insulation Resistance test and pre check of all wiring.
Stable power supply for testing
The site is safe for testing.
Approved relay settings and drawings.
Site office as per SEC requirements.
Over-all approved schedule along with approved outages.
Substation HVAC system is in service; required for protection/control testing.
2.1.2
Joint Inspection
The contractor, Project Engineer and commissioning personnel shall visit the substation
jointly two weeks prior to the start of the pre commissioning testing and the following
points shall be confirmed.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 3 of 124
2.1.2.2
3.0
WITNESSING COMMENCEMENT
After confirmation of all the items of Section 2.1.2, witnessing can begin after two weeks.
3.1
Commissioning File
The Commissioning engineer/technician shall have a Commissioning File for each substation; the
File shall include at minimum:
Site Instructions.
Minutes of Meeting.
Technical Specifications.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 4 of 124
guidelines to be followed by all Commissioning personnel to issue S.I.s in order to achieve
uniformity and consistency. It should be kept in mind that this is a guideline only and it will not
supercede any SEC relevant Specification in any manner.
3.3
Sequence of Events
Any items contrary to SEC Standards, SOW, workmanship and safety will be reflected in the
deficiency section of the Register File, see Attachment No. 1. The Register File has two sections,
one section belongs to the activities (Attachment No. 2) along with the single line diagram to help
an engineer to visualize the project and the other section for the deficiencies. After one week
from the registration of a deficiency in the book, all outstanding items will be sent to the Project
Engineer via Site Instructions/Records (Attachment No. 3). Bi-weekly, the status of the punch list
has to be issued by the contractor on the SEC format, Attachment No. 4. One month prior to the
scheduled energizing of the equipment, the categorized deficiency list shall be issued by the
commissioning personnel to identify the items which must be corrected prior to energization
(Attachment No. 5).
ATTACHMENTS TABLE
ATTACHMENT
NO.
1.
2.
DESCRIPTION
Register
Book/Deficiency
Record
Register Book/Activity
Record
3.
Site Instructions
4.
5.
6.
7.
8.
Pre-Commissioning
Time Utilization
Statistic Sheet
Final PreCommissioning Report
Sample Check
(Optional
Agreement)
9.
Check List
10.
Contractors
Performance Report
REMARKS
The Commissioning engineer/technician shall record all the
items contravening safety, SEC Standards, Scope of Work and
workmanship on the Deficiency Record.
The Commissioning engineer/technician is responsible to daily
update site activities to help any engineer to familiarize him
with the status of the project.
After one week from recording in the Deficiency Record,
incomplete items will conveyed to the Project Engineer via the
Site Instructions Form.
Bi-weekly the status of the punch list shall be updated by the
contractor.
One month prior to energizing the equipment, the categorized
deficiency list shall be issued by the commissioning personnel
to identify the items to be done before energization.
The commissioning engineer/technician shall fill in this sheet on
a daily basis.
The Commissioning engineer/technician shall issue a final Precommissioning Report at the end of the project.
In order to reduce the pre-Commissioning time the sample
check procedure may be exercised based on the contractors
previous performance and the last time utilizations status
sheet. This shall be based on agreement between the
contractor and SEC Transmission.
The check list is intended to provide information to the
commissioning engineer/technician who are assigned to
inspect the contractors work and witness commissioning
testing on behalf of SEC.
The commissioning engineer/technician shall fill this form at the
end of the project to evaluate the performance of the
contractor.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 5 of 124
The contents of the S.I. can be categorized under various headings as noted below. The common
Snags/Punch list mentioned will be issued once in one S.I. for the whole substation and repetition of the
same for different bays shall be avoided.
4.1
This consists of the following deficiencies relating to protection, metering and control equipment.
Missing equipment.
Physical damage to the equipment.
Rating is not matching with relevant specifications.
Equipment with internal fault causing incorrect test results.
The equipment is not on the SEC Approved Manufacturers List.
4.2
4.3
Protection or a part of it is not in line with SEC relevant Specifications and/or Protection
requirements.
Work has not been executed in line with general requirements or has not had approval
during the design stage.
Design comments have not been implemented for the protection scheme and other
equipment.
Poor Work Quality
Segregation of protection CT and VT cables is not maintained and color coded cables are
not used.
Poor ferrule printing quality which will fade over time.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 6 of 124
Cables are directly terminated on terminal blocks without providing adequate clearances
for access during troubleshooting or maintenance.
Equipment or terminals are not sufficiently accessible to allow maintenance.
Ferruling method does not meet relevant specifications.
Apparatus is not properly labeled.
Wiring has either wrong ferrules or no ferrules.
Improper use of terminal lugs.
Control cables do not carry proper number tags.
Proper wiring dressing has not been done in panels.
Labels with incorrect spelling, uneven engraved letters, improperly aligned, letters too
small, badly cut edges, etc.
Alarm annunciator labels/text with letters too small to read from a distance, and
acknowledge/reset/test push buttons at difficult to reach locations.
Congested wiring obstructs other terminals on a terminal block.
Very loose plug/socket arrangement. These should always be locking type.
Improper locking of panel doors has caused frequent breaking of the panel door locking
mechanism.
Adequate illumination does not reach all working places, terminals, in the panel, in front
of relays, etc.
Terminals, auxiliary relays, flag relays mounted at very low level or very high level.
Wiring not supported properly causing undue termination tension, which may result
eventually slipping of wire/breaking off from crimp.
Bad crimping of wires. For CT circuit this is most dangerous as this may lead to open
circuiting of energized circuits. Open circuited energized CT circuits may cause fires and
serious electrical hazards.
Inadequately rated relays used for continuously energized relays in fail safe, scheme, etc.
4.4
A protection scheme may not operate properly in spite of implementation of the relevant
specification. Examples are listed as follows:
4.5
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
4.6
T-PreCom-1000-R0
Page Number:
Page 7 of 124
The following Punch list/ snags are found repeatedly in substation construction. Most of them are
clearly mentioned in the SEC Specifications/General Requirements. Irrespective of this fact, they
are usually repeatedly discovered. When these types of points are raised at site, the contractor
generally tries to avoid implementation. Every effort should be made to have the contractor
promptly correct the inadequacies. Some examples are listed as follows:
Color-coded cables shall be used for control and/or alarm functions and black ones shall
be used for CT, PT or AC circuits.
Quality of printing and the placement of ferrules is poor in many cases.
While terminating cables, the contractor does not leave any margin inside/outside the
panel for re-terminating the cables in another location in the same panel, in case it is
required.
While laying cables, segregation is not maintained section-wise, so that in case of fire in
one section the other sections will also be affected.
Paralleling of alarms is done with software, whereas it is necessary to do this with help of
wiring for system reliability.
Equipment lists do not correlate with the installed equipment and details such as ordering
number and the numbers of NO/NC contacts, etc., are not correct.
More than one earth point has been made for the CTs feeding the unit protection, e.g.,
Restricted Earth fault, Differential, Breaker Failure and Bus bar protection.
From the maintenance point of view the access to relay terminal blocks is very important;
some contractors do not pay enough attention to this.
Positive (+), Negative (-) and trip marked in red are not provided on the relevant wires.
Contractors do not allocate fault recorder channels as per SEC specifications.
Site modifications are not properly reflected in the drawings.
CT shorting and isolating arrangement is not in line with SEC standard arrangements
including shorting/isolating, instruction and caution notices.
Lack of proper labeling to the protection and control equipment in different location, e.g.,
relay panels, control panels, LCC and AVC panels, AC/DC distribution boards, power
transformer marshalling kiosks, CB isolators and earth switches, etc. This equipment
includes main relays, auxiliary relays, contactors, trip relays, MCBs terminal blocks,
points on the test switch (MMLG or ABB type), trip links and other links used for other
specific functions.
CT and VT protection cables are not segregated.
Terminal block wiring is too low for convenient access, especially CT shorting and
isolating switches. These shall be at working height level.
Crimping of terminal lugs is not done properly, particularly for CT and VT wires.
Length of the metallic part of CT and VT lugs is not enough to provide proper grip when
they are tightened in the terminal blocks.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 8 of 124
Plug in type miniature relays are used in tripping and interlock circuits. After a period of
time, these relays do not function properly, due to displacement from their original
position.
Normal earth switch was used on the line instead of high-speed type.
In one substation, the backup main protection was found not working when the DC
supply to the first main protection was switched off since the isolator image was
controlled by the first main DC supply.
Power cables for the fans from the AC distribution board to the transformer marshalling
kiosk were found underrated.
Protection coordination of MCBs installed in the DC distribution board was not
maintained, so the contacts of an ON/OFF switch were burnt due to a short circuit in the
DC wiring.
During on-load checks 12 volts were observed across the CT terminals of feeder cable
protection.
The manual mode status of the Halon was found not annunciated.
As per SEC specifications it is necessary to install an independent synchrocheck relay for
manual and auto re-closing for each CB rated 110 kV and above.
The bus-bar protection trip logic for double bus-bar substations does not conform with
SEC specifications.
The annunciator output contacts did not follow the initiation when the input was reset as
per SEC specifications.
Remote end breakers also trip in case the HV E/F relay of transformer operates. It
should only trip the local breaker.
The A/R did not close the breaker when the D.E.F. tripped the breaker. It was due to the
tripping of the breaker in advance before the initiation of the A/R.)
The phases R and B were found interchanged for the reactors.
Two phases of earth switch were on one side of the CTs whereas the third one was on
the other side of CTs.
CT polarity if it was left reversed on one of the spare feeders and the loading of the spare
feeder led to operation of BBP.
The anti pumping circuit is not operational for CBs. This deficiency will lead to re-closing
of the CB on to fault when a long duration closing pulse is initiated.
The pilot wire protection 87PW is commissioned with reverse pilot; this will lead to
indiscriminate tripping.
The DEF relay for one circuit is commissioned with wrong direction this will lead to
indiscriminate tripping of the circuit.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 9 of 124
Labeling of relays, pressure relief devices, oil temperature gauges and winding
temperature gauges, etc.
Blocking of spare plugs.
Avoiding use of plug in connections and plug-in type auxiliary relays.
It is very important to clear the Punch List/Snag items as soon as possible after confirming their
implementation. Sometimes it is very difficult to confirm their implementation once the substation
is energized, if they are not cleared during the pre-commissioning stage. It is very useful that the
witnessing engineer/technician keeps the site instruction records updated by putting his signature
with date without any delay after inspecting and approving the relevant snag.
5.0
The following sections listed below elaborate the techniques to ensure that all equipment tests are done
with optimal use of the time available.
5.1
Check List
The Check List is intended to provide information to commissioning personnel who are assigned
to inspect the contractors work and witness commissioning testing on behalf of SEC to verify that
substation and transmission line equipment and system are acceptable as per SEC- Standards
and Specifications. The listing of commissioning checks and tests are based on the SECCommissioning Procedure T-PreCom-1000-01.
5.2
A time utilization statistics sheet is being included in this Procedure. This sheet must be filled in
daily. The contents of this sheet will be used for planning future projects by using the total time
consumed. Moreover this sheet will also allow corrective measures to be taken to reduce the precommissioning time. The number of hours lost should be filled correctly, see Attachment No. 6.
5.3
Testing Schedule
In order to start witnessing after two weeks from confirmation, the contractor shall submit to SEC
the testing schedule, giving details for each test of the time and the commissioning personnel
required. Every week, the contractor shall submit a three-week testing program giving details of the
previous weeks completed jobs and the current and following weeks proposed jobs. If in the
previous week, some job was not completed, a reason for the deferral and its effect on the overall
schedule should also be mentioned.
5.4
Marked Up Drawings
The contractor is responsible to provide enough qualified manpower to prepare three sets of markedup drawings during the pre-commissioning testing period in order to expeditiously finalize the as-built
drawings without using the substation marked-up drawing. The three copies of the marked up
drawing shall be distributed as the following:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 10 of 124
In order to reduce the pre-Commissioning time, sample checks could be exercised based on the
following criteria, see Attachment No. 8.
6.0
If the overall rating of the contractor performance in his immediately previous contract
was GOOD.
If the hours lost due to the contractor is less than 5% of the work, for the last time
utilization statistic sheet.
Project completion depends on the pre commissioning report, which has to be issued by the
commissioning engineer/technician (Attachment No. 7). In case of separate contractors working on the
same substation (lines and substation), the line-commissioning engineer/technician shall provide a copy
of the final reports to the substation-commissioning engineer/technician and vise versa. Each
commissioning engineer/technician shall evaluate the contractor at the end of the project, see Attachment
No. 10.
6.1
The commissioning engineer/technician shall issue the Report based on but not limited to the
following.
The status of the Punch List (A, B) for which A refers to any deficiency requiring an
outage to clear it or equipment damage or a safety requirements. B is any deficiency
other than A.
Marked up drawing are available at site in good condition.
Emergency contact list provided.
Operation spare parts are available.
Operation and Maintenance Manuals are available.
Test results provided.
6.2
Contractor Evaluation
The commissioning engineer/technician shall use SEC format to evaluate the contractor using the
following criteria:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 11 of 124
IMPLEMENTATION
The following steps need to be given special consideration, for implementation of this procedure:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 12 of 124
INTRODUCTION
This Procedure describes the tests and checks to be performed during the pre-commissioning stage of
SEC Transmission projects. It deals primarily with the pre-commissioning tests to be followed for
protection schemes and main equipment such as cables, transformers and switchgear, etc., keeping in
view the SEC standard practices for various types of tests. Further, this listing of tests and checks is
based on the requirements and recommendations of international standards such as IEC, ANSI, etc.
They are the minimum tests and checks to be performed during pre-commissioning.
2.0
PURPOSE
The main purpose of this Procedure is to present a list of checks and tests to be performed on
transmission equipment. They shall be performed by the project contractor and witnessed by SEC
Precommissioning personnel.
3.0
PROCEDURE
ITEM NUMBER
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
3.17
3.18
3.19
3.20
3.21
3.22
3.23
3.24
3.25
3.26
3.27
3.28
3.29
3.30
3.31
3.32
3.33
3.34
EQUIPMENT
Oil Filled Power Transformers
Shunt Reactors
Bushings Inspection and Testing
Surge Arrestors
Station Service Transformers
Neutral Earthing Resistors
Current Transformers
Potential Transformers
Capacitive Voltage Transformers
Coupling Capacitor Voltage Transformer s
Gas Insulated Switchgear (GIS)
Metal Clad Switchgear
Metal Enclosed Bus Duct
Indoor and Outdoor Bus Structures
Indoor Circuit Breakers
Outdoor Circuit Breakers
Disconnect and Grounding Switches
Circuit Switchers
LV Switchgear (110/220 V)
230 kV and 380 kV XLPE Cables
230 kV and 380 kV LPOF Cables
110 kV, 115 kV and 132 kV XLPE Cables
110 kV, 115 kV and 132 kV LPOF Cables
69 kV XLPE Cables
13.8 kV and 33 kV XLPE Cables
LV Cables
Control Cables
Pilot Cables
Over Head Lines
Protection and Control
Substation Batteries
Battery Chargers
AC Distribution Panels
DC Distribution Panels
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 13 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 14 of 124
3.1.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
DESCRIPTION
Check the impact recorder for any abnormal impact during
transit.
Check all components are installed.
Check for quality of paint, lifting lugs, quality of weld areas, rust
spots and wheel stoppers.
Check nameplates information (visible location) as per contract
specifications.
Check tightness of all bolts (torque wrench method).
Check that all grounding is securely connected (two grounding
connections to main tank are required).
Check that the piping to Buchholz relay has proper slope.
Check that the tank pressure is positive, if applicable.
Check that the valves between the main tank and radiators are
open.
Check the HV, LV and TV (if applicable) bushings for damage
and completeness.
Check for correct color and quantity of desiccant (moisture
absorbing media) in breathers. Check for correct breather oil
levels.
Check heaters and humidity meters in local panel are at correct
settings.
Check that phase marking in cable box matches with GIS and
cables.
Check all pipes, hoses and fan protection (not rubber or plastic).
Check the vertical and horizontal clearances of live parts to
adjacent grounded points conform to standard.
Check integrity of diaphragm/air bag in the conservator.
Perform all of the manufacturers specific checks.
Check labeling of all auxiliary devices as per approved drawing.
Check proper operation of auxiliary devices as follows:
a.
Cooling fans/pumps (for all settings).
b.
Tap changer (upperlowerout of step and interlock).
c.
Oil level gauges.
d.
Top oil temperature gauges.
e.
Buchholz relay by gas injection.
f.
Winding temperature gauges.
g.
OLTC oil/gas surge (pressure) relay.
h.
Ensure correct operation of the Pressure Relief Device
microswitch.
i.
Push buttons and indicators.
j.
Oil sampling port (main tank and OLTC).
k.
Upper and lower main tank valves.
l.
Tap changer diverter switch compartment, oil filtering
pumps and filter in good condition (if available).
Check oil leakage; if any noted, apply 0.35 kPa over pressure
for 24 hrs to make sure.
Check that the oil sampling valves for the main tank and OLTC
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
3.
4.
5.
6.
7.
8.
9.
10.
11
12.
13.
14.
15.
Page Number:
Page 15 of 124
ITEM
1.
2.
T-PreCom-1000-R0
Electrical Tests
DESCRIPTION
Core Insulation Resistance Test.
Winding Insulation Resistance Test and Polarization Index Test
at 5 kV DC.
Winding Resistance Test (all taps).
Excitation Current measurements from primary side at each tap
during ratio test and from secondary side when energized from
secondary terminals keeping primary side open or winding
excitation current measurement test at 10 kV during power
factor testing.
Insulation power factor and bushing test at 10 kV AC.
Vector Relationship Test.
Winding temperature device test by heating the sensor in oil
bath and checking against standard thermometer. Also check
by current injection. Setting as per approved drawing to be
applied and tested.
Oil temperature device to be calibrated by heating in oil bath.
Setting as per approved drawing to be applied and tested.
Percent Impedance test at nominal tap.
Turn Ratio (all taps).
Check for current and voltage ratings of all motors for tap
changer and fans match to SEC standard supply. Check that
MCBs for protection are set at proper over load settings.
Fan motor currents shall be measured and checked against
rating. Check wiring size is adequate to carry the current.
Check that the phase sequence of supply voltage to fan motors
is correct. Check fan rotation direction and confirm air flow is
towards radiator.
MCBs in cooler control cubicle to be checked by current
injection for alarm and trip.
On load Tap Changer tests:
a.
Check current and voltage ratings of tap changer
motor.
b.
Raise/Lower Control (localremote) and indication, and
perform adjustment as required.
c.
End of tap travel control.
d.
End of winding travel control (both ends).
e.
AVR setting of bandwidth, mid point, time delay, etc.,
and adjust as per approved setting.
f.
Master/Slave check out of step blocking alarm.
g.
Master/Slave control check either transformer as
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
16.
17
18.
19.
master.
h.
Parallel Operation Disturbedcheck alarm.
i.
Check that the windings are not open circuited during
tap changing. This should be done during the winding
resistance test.
Bushing Current Transformer Tests:
a.
Polarity.
b.
Insulation Resistance.
c.
Secondary Winding Resistance (all windings and all
taps).
d.
Current Ratio (inject current)
e.
Magnetization Characteristics (minimum five points
below and two points above the knee point).
f.
Verify secondary circuits, terminal to terminal.
g.
Burden Test.
Demagnetize CT cores after all tests. Ensure no open circuit on
CT secondary side.
Functional Checks for the Following:
a.
Liquid level (alarm and trip).
b.
Top Oil Temperature Device: fans/pumps (stop, start
alarm and trip).
c.
Winding Temperature Device.
d.
Buchholz Relay (alarm and trip).
e.
Oil / Gas Surge (pressure) relay (alarm and trip).
f.
Pressure Relief Device (alarm and trip)
Insulating Oil Tests:
Prior to energization, the contractor shall submit insulating oil
test reports tested at an independent laboratory, for the
following:
a.
Dielectric Strength
i.
ASTM D 877 (2.5 mm gap) for unprocessed oil
and for OLTC oil
ii.
ASTM D 1816 (1.0 mm gap) for oil in main
tank
b.
Neutralization Number (ASTM D 974)
c.
Interfacial Tension (ASTM D 971)
d.
Color (ASTM D 1500)
e.
Moisture Content (ASTM D 1533)
f.
Power Factor Test (ASTM D 924)
g.
Dissolved Gas in Oil Analysis (ASTM D3 612)
h.
(Dielectric Dissipation Factor, Resistivity, Sediment
and/or Precipitable Sludge).
Another oil sample shall be given to SEC transmission for their
own analysis and comparison purposes. A syringe oil sample
shall be taken by contractor.
A main tank insulation oil sample for dissolved gas analysis
shall be taken immediately prior to first energizing a power
transformer and another sample three days after continuous
energization.
T-PreCom-1000-R0
Page Number:
Page 16 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 17 of 124
Shunt Reactors
3.2.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
DESCRIPTION
Check the impact recorder for any abnormal impact during
transit.
Check all components are installed.
Check for quality of paint, lifting lugs, quality of weld areas, rust
spots and wheel stoppers.
Check nameplates information (visible location) as per contract
specifications.
Check tightness of all bolts (torque wrench method).
Check that all grounding is securely connected (two grounding
connections to main tank are required).
Check that the piping to Buchholz relay has proper slope.
Check that the tank pressure is positive, if applicable.
Check that the valves between the main tank and radiators are
open.
Check the bushings for any damage and completeness.
Check for correct color and quantity of desiccant (moisture
absorbing media) in breather. Check for correct breather oil
level.
Check heaters and humidity meters in local panel are at correct
settings.
Check that phase marking in cable box matches with GIS and
cables.
Check all pipes, hoses and fan protection (not rubber or plastic).
Check the vertical and horizontal clearances of live parts to
adjacent grounded points conform to standard.
Check integrity of diaphragm/air bag in the conservator.
Perform all of the manufacturers specific checks.
Check labeling of all auxiliary devices as per approved drawing.
Check proper operation of auxiliary devices as follows:
a.
Cooling fans/pumps (for all settings).
b.
Oil level gauges.
c.
Top oil temperature gauges.
d.
Buchholz relay by gas injection.
e.
Winding temperature gauges.
f.
Ensure correct operation of the Pressure Relief Device
microswitch.
g.
Push buttons and indicators.
h.
Oil sampling port (main tank).
i.
Upper and lower main tank valves.
Check oil leakage; if any noted, apply 0.35 kPa over pressure
for 24 hrs to make sure.
Check that the oil sampling valves for the main tank are
accessible from ground level.
Check oil level in main tank, conservator and bushings, etc.
Test the oil level gauges and their alarms.
Bleed trapped air at the bushing turrets and radiators.
Check all external wiring for correctness and tightness.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
7.
8.
9.
10.
11.
T-PreCom-1000-R0
Page Number:
Page 18 of 124
Electrical Tests
DESCRIPTION
Core Insulation Resistance Test
Winding Insulation Resistance Measurement Test and
Polarization Index (P.I.) Test at 5 kV DC.
Winding Resistance Test.
Inductance Measurement.
Impedance Measurement.
Winding temperature device test by heating the sensor in oil
bath and checking against standard thermometer. Also check
by current injection. Setting as per approved drawing to be
applied and tested.
Oil temperature device to be calibrated by heating in oil bath.
Setting as per approved drawing to be applied and tested.
Insulation power factor and bushing test at 10 kV AC.
Bushing Current Transformer Tests:
a.
Polarity.
b.
Insulation Resistance.
c.
Secondary Winding Resistance (all windings and all
taps).
d.
Current Ratio (inject current)
e.
Magnetization Characteristics (minimum five points
below and two points above the knee point).
f.
Verify secondary circuits, terminal to terminal.
g.
Burden Test.
Demagnetize CT cores after all tests. Ensure no open circuit on
CT secondary side.
Functional Checks for the Following:
a. Liquid level (alarm and trip).
b. Top Oil Temperature Device: fans/pumps (stop, start
alarm and trip).
c. Winding Temperature Device.
d. Buchholz Relay (alarm and trip).
e. Pressure Relief Device (alarm and trip)
Insulating Oil Tests:
Prior to energization, the contractor should submit insulating oil
test reports tested at an independent laboratory, for the
following:
a.
Dielectric Strength
i.
ASTM D 877 (2.5 mm gap) for unprocessed oil
ii.
ASTM D 1816 (1.0 mm gap) for oil in main
tank
b.
Neutralization Number (ASTM D 974)
c.
Interfacial Tension (ASTM D 971)
d.
Color (ASTM D 1500)
e.
Moisture Content (ASTM D 1533)
f.
Power Factor Test (ASTM D 924)
g.
Dissolved Gas in Oil Analysis (ASTM D3 612)
h.
(Dielectric Dissipation Factor, Resistivity, Sediment
and/or Precipitable Sludge).
Another oil sample shall be given to SEC transmission for their
own analysis and comparison purposes. A syringe oil sample
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 19 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 20 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
DESCRIPTION
Cleaning the insulator surface.
Check for tightness test between transformer and bushing
flange and outer terminal.
Visually inspect for any damage or cracks.
Check for leakage.
Check and adjust of oil level. Note that adding insulating oil to a
bushing shall be done under vacuum.
Measurement of capacitance and tan delta. The bushing shall
be tested in a vertical position and the lower portion set into an
oil reservoir.
Check of through resistance.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 21 of 124
Surge Arrestors
3.4.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
For multi-unit stacks, check that the physical arrangement of the
units are erected according to the manufacturers specifications.
Check that all grounding cables are correctly and secured
connected.
Check name plate information for correctness as per SECs
specifications.
Check that impulse counter and leakage current meter glasses
are not broken or cracked.
3.4.2
ITEM
1.
2.
3.
Electrical Tests
DESCRIPTION
Check calibration of leakage current meters.
Insulation resistance test at 5 kV DC.
Power factor test at 10 kV AC.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 22 of 124
3.5.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Check the Impact recorder for any abnormal impacts during
transit (if applicable).
Check earthing, color, painting, external damage, oil leakage,
wheel stopper, cable connection and bolt tightness, etc.
Check nameplate data against contract specifications.
Perform all special checks according to the manufacturers
instructions.
Check oil level in HV side cable box and its oil level indicator or
HV fuses.
Check all devices are labeled correctly as per drawing.
3.5.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Electrical Tests
DESCRIPTION
Check LV side MCB setting as per transformer current rating
Ratio Test (all taps), Insulation resistance measurement test on
all windings and polarization index (P.I.) test.
Polarity and Vector Group symbols confirmation Test.
Check oil level and its indicator alarms.
Check oil temperature gauge by oil bath method and its alarms.
Check LV and HV side phases match with the LV bus bar
phasing in the distribution panels and with the main transformer
phases.
Check phasing at the automatic transfer switch (as applicable )
Winding resistance measurement (at all taps).
Excitation current test (all taps).
Back energization test at rated voltage for 15 minutes.
Check that the off load tap changer is set at the nominal voltage
tap.
Perform functional tests of all auxiliary devices (as applicable )
Insulating Oil Tests:
Prior to energization, the contractor should submit insulating oil
test reports tested at an independent laboratory, for the
following:
a.
Dielectric Strength
i.
ASTM D 877 (2.5 mm gap) for unprocessed oil
ii.
ASTM D 1816 (1.0 mm gap) for oil in main
tank
b.
Neutralization Number (ASTM D 974)
c.
Interfacial Tension (ASTM D 971)
d.
Color (ASTM D 1500)
e.
Moisture Content (ASTM D 1533)
f.
Power Factor Test (ASTM D 924)
g.
Dissolved Gas in Oil Analysis (ASTM D3 612)
h.
(Dielectric Dissipation Factor, Resistivity, Sediment
and/or Precipitable Sludge).
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 23 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 24 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Check the value of resistance and current ratings against
specifications.
Check that the external earth connection to main earth is copper
wire at least 240 mm2 in size.
Test NER HV side associated CT and power cable.
Visually inspect the interior for broken insulators.
Measure the main circuit resistance.
Insulation Resistance Test.
Ensure that the interior and exterior of the NER is clean prior to
energization.
Check identification and function of NER isolator (if applicable).
REMARKS
>=1000 megaohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 25 of 124
Current Transformers
Note that Bushing current transformer tests and inspections are covered in the sections relating
to the equipment into which they are installed.
3.7.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check that outdoor secondary wiring terminations are installed
in moisture proof enclosures.
Check tightness of all bolted connections (torque wrench
method).
Check that all grounding cables are securely connected.
Check secondary wiring is correctly color coded and size of
wires is as specified.
Check proper lugs have been used on terminations.
Check CT locations physically and secondary terminal labeling
has been done correctly.
3.7.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Electrical Tests
DESCRIPTION
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 26 of 124
Potential Transformers
3.8.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connection.
Check that the HV connection does not transfer stress to the HV
terminal.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolation and grounding devices (as applicable).
Check integrity of primary fuses (if applicable).
Check insulation liquid level (if applicable).
Gas leakage check for GIS VTs.
3.8.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Electrical Tests
DESCRIPTION
Winding Resistance Test.
Insulation resistance tests HV TO G, LV TO G and HV TO LV
using a one kV insulation tester.
Ratio Test.
Polarity Test.
Primary and secondary fuses rating checks for 11 kV VTs and
above (if applicable).
Ensure VT is included in switchgear and GIS high voltage test.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 27 of 124
TABLE 1
SYSTEM RATED
VOLTAGE (KV)
11
13.8
33
69
110
115
132
230
380
RATED LOAD
FACTOR
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
TEST VOLTAGE
(KV)
9.5
12
28
60
95
99.5
114
199
329
FREQUENCY
60 Hz
TIME PERIOD
REMARKS
I Minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 28 of 124
3.9.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolation and grounding devices (as applicable).
Check oil level (if applicable).
Check for oil leakage.
Check electromagnetic unit spark gaps for correct setting (if
applicable).
Check drain coils (if applicable).
3.9.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Electrical Tests
DESCRIPTION
Winding Resistance Test.
Insulation resistance tests HV TO G, LV TO G and HV TO LV
using a one kV insulation tester.
Ratio Test.
Polarity Test.
Check HV neutral is solidly grounded.
Check electrical operation of all isolating and grounding devices
(if applicable).
Check phase sequence, for the final three-phase assembly.
Loop resistance and burden tests.
Capacitance and dissipation factor measurement tests.
Insulation power factor test, 110 kV and above.
Check on fast damping device (FDD).
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 29 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolating, grounding and shorting devices (as applicable).
Check electromagnetic unit spark gaps for correct setting (if
applicable).
Check drain coil unit spark gaps for correct setting (if
applicable).
Check wave trap mechanical assembly, bird screens, etc.
REMARKS
DESCRIPTION
Winding resistance test
Insulation resistance tests HV TO G, LV TO G and HV TO LV
using a one kV insulation tester.
Ratio test
Polarity test
Check electrical operation of all isolating and grounding devices
(if applicable)
Check phase sequence, for the final three-phase assembly.
Loop resistance and burden tests.
Capacitance and dissipation factor measurement tests.
Insulation power factor test, 110 kV and above.
Perform all specific tests per manufacturers instruction
Phase angle check if the equipment is assembled at site.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 30 of 124
21.
22.
23.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Inspect enclosures for proper alignment and foundation fixing
and grounding.
Check quality of paintwork.
Ensure that all special tools and equipment are provided as
specified and have proper storage.
Ensure that gas-handling cart (if provided) operates correctly
and that special filling and degassing fittings are provided and
have proper storage.
Verify that all lifting devices are correctly labeled for lifting
capability.
Ensure that adequate ladders and walkways are provided for
access to meters, filling ports, cranes, lights, etc.
Check and verify that all grounding of GIS is as per approved
layout drawings and specification and is securely connected.
Check that all specified grounding switches are insulated, with
removable grounding links.
Check operation of all mechanical interlocks.
Check tightness of all bolted connections (torque wrench
method).
Check each gas section filled to correct rated pressure.
Check SF6 gas at each gas section for air and moisture content
after filling at rated pressure.
Gas leak test of all flanges and joints after erection and filling.
Calibrate gas pressure (density) gauges. Check the gauges
have correct, legible and readable scales.
Check the gauges are ambient temperature compensated.
Check operation of all gas density switches (alarm trip signals
and lockout functions). Confirm correct set points.
Check all wiring is correct according to approved drawings or
confirm the correctness of all modifications.
Verify that all front panel mounted devices (meters, push
buttons, switches, indicator lamps, mimic buses, etc.) are
installed as per drawings, fixed permanently and are correctly
labeled.
Verify that all operating devices are correctly labeled.
Perform mechanical checks and visual inspections on all
component equipment:
a. Circuit breakers.
b. Current transformers.
c. Voltage transformers.
d. Disconnect and grounding switches.
Check that all phase marking and circuit labeling have been
installed as per specifications.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
25.
27.
28.
T-PreCom-1000-R0
Page Number:
Page 31 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
DESCRIPTION
Insulation resistance test for all low voltage wiring and cabling.
Functional test of all controls and interlocks.
Resistance of all ground connection joints at 100 A DC.
Resistance of bus joints at 100 amperes DC.
Overall resistance of the main circuit.
Functional check of all alarms, interlocking and indication
circuits from the switchgear through to the local control cubicle.
CB Timing Test (open and close) with contact travel and speed
analysis.
Disconnect switch close and open time tests for the
confirmation of early make and late break operation of auxiliary
contacts with main contacts for CT switching schemes.
Checks on CB hydraulic system or vacuum system for pump
start stop trip/close lockout threshold values.
GIS PTs to be included during AC HV tests on GIS when test
frequency is well above rated frequency, otherwise test at 1.5Un
one minute at rated frequency without secondary load. PT
secondary output volts shall be monitored during the high
voltage test.
All AC/DC MCBS shall be tested by trip test through current
injection.
Check and confirm GIS PTs primary isolation device with
manual operation provided where fitted, along with its
monitoring system locally as well as on mimic diagram in control
room. Check VT HV neutrals externally available especially in
case of VTS installed directly on cable feeder.
Check and confirm that the three-phase test adaptor and
bushing for HV test on GIS has been provided.
Verify the alarms being initiated by SF6 density gauges on LCC
and up to control room during calibration process.
Check that all cubicle space heaters and thermostats are
functional and at correct temperature control settings.
Perform all electrical tests on following GIS components as per
manufacturers instructions and SEC approved procedures.
Circuit breakers.
Current transformers.
Voltage transformers.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 32 of 124
AC HV tests on main circuit of GIS are performed with all CBs and disconnect switches in the closed
position at 80% of the factory routine test voltage for one minute. Partial discharge measurements (If
applicable and possible to be performed) are performed at 1.2 X Un (Un = phase to neutral voltage).
II.
Check and confirm following points and condition to be met before high voltage tests.
i.
ii.
iii.
iv.
v.
vi.
III.
The Switchgear shall be erected completely and filled with gas at rated pressure.
Some part may be disconnected before test, such as:
High Voltage cables and overhead lines.
Power transformer and most voltage transformers.
Surge arrestors and protective spark gaps.
Current transformer secondary windings should be shorted and grounded.
Every newly erected part of GIS shall be tested with high voltage.
The test should be performed at rated frequency (60 Hz.). If such arrangement is not
possible, then the frequency should be limited to the range of 30 to 300 Hz.
AC voltage tests are sensitive in detecting contamination and abnormal field
configuration.
Tests with switching impulse voltages are useful especially for high rated voltage to
detect the presence of contamination as well as abnormal field configuration
Contractor can adopt one of the two procedures A or B to perform high voltage test on GIS after erection
at site
i.
Procedure A
Site AC test voltage level shall be equal to the 80% of the factory routine test voltage.
This test may be performed through series resonance method
Or by a test transformer with sufficient capacity. PD measurements are possible to be measured
in this case at test voltage level = 1.2 Un (Un = phase to neutral rated voltage) during the
HV Test process.
Electrical conditioning at voltage equal to U/3 for longer period such as 30 minutes may be
performed to move and trap the contamination in areas where they become harmless.
Partial discharge measurements may be helpful in detecting some kind of faults.
ii.
Procedure (B)
a.
Site AC test voltage level equal to 1.2 Un for 5 minutes followed by Impulse Voltage test
at a test level equal to 64% of the rated lightening impulse withstand level specified in
IEC-517. Three positive and three negative polarity impulses shall be applied.
b.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 33 of 124
In case the GIS VTs are not suitable to be used as test transformer; a special voltage
transformer shall be used to perform such tests. GIS VT can only be used as a test
transformer if the manufacturer guarantees its safety and capability to perform such tests
otherwise it shall not be used as a test source.
IV.
Sometime in extension projects due to practical and technical reason of joining new and old GIS together,
the test may be performed at reduced voltage level for an extended duration subject to agreement
between SEC and supplier.
V.
Assessment of Tests
i.
ii.
iii.
iv.
VI.
Test is considered passed if no disruptive discharge occurs during the test period.
If disruptive discharge occurs in solid insulation, the compartment should be opened and
repaired. After fault repair, again, test with full site test voltage.
If disruptive discharge occurs in gas, the test may be repeated and if discharge again
takes place, then compartment should be opened to clean out the compartment.
If the discharge occurs and second time it disappears, it should be considered acceptable
after repeating one test more at full site test voltage mentioned in Table 1.
Test may be repeated several times to listen and locate the location of fault point subject to the
agreement between SEC and Contractor.
Table-1 on the next page describes the exact test voltage levels, time and kind of tests to be applied after
erection of GIS at site.
i.
For 132 kV GIS the test voltage shall be 220 kV AC 60 Hz for one minute as per
Procedure A clause 7.107.1.5 of IEC 517- 1990
ii.
For 380 kV GIS and GIBs shall be 416 kV AC 60 Hz for one minute as per procedure A
clause 7.107.1.5 of IEC 517-1990.
iii.
In case of procedure B as per clause 7.107.1.5 of IEC 517-1990 the test voltage for 132
kV rated GIS shall be 84 kV AC for 5 minutes and followed by 416 kV Impulses of three
positive and three negative polarities.
iv.
In case of procedure B to be applied for high voltage tests on 132 kV GIS special VT
should be used as Test voltage source. GIS VTs shall not be used as HV test voltage
source.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 34 of 124
13.8
10 kV for 10
min.
33
22 kV for 15
min.
69
69
110
110
115
115
132
132
44 kV for 30
min.
84 kV for 30
min.
84 kV for 30
min.
84 kV for 30
min.
30
60 Hz
1 min.
56
60 Hz
1 min.
128
44
220
84
220
60 Hz.
or 10300 Hz.
60 Hz.
60 Hz.
or 10300 Hz.
60 Hz.
60 Hz.
or 10300 Hz.
84
60 Hz.
220
60 Hz.
or 10300 Hz.
84
60 Hz.
1 min.
5 min.
1 min.
5 min.
1 min.
5 min.
1 min.
5 min.
248 kV
3
positive
3
negative
416 kV
3
positive
3
negative
416 kV
3
positive
3
negative
416 kV
3
positive
3
negative
REMARKS
Partial
Discharge
Measure
No. Of
Impulses
Swing or
Switching.
Impulse level
Time Of
AC Test
Voltage
Freq.
Of Test
Voltage
AC Test
Voltage
kV
Electrical
Conditioning
System Rated
Voltage
KV
Method
No.
Table 1. Test Voltage Levels for Metal-Enclosed Gas Filled Switchgear (GIS)
Leakage
current
< 1000
mA
Leakage
current
< 0.86
mA
At 48 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
230
230
380
142 kV
for 30
min.
-
245 kV
for 30 min.
316
142
416
10-300
Hz.
Better
60 Hz.
10-300
Hz.
Better at
60 Hz.
10-300
Hz.
Better at
60 Hz.
1 min.
5 min.
1 min.
Page Number:
Page 35 of 124
608 kV
3
positive
3
negative
840 kV
3
positive
3
negative
PD or HF
detection
techniques
to be
applied
Impulse
test is
applied
in
special
cases
only
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 36 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Inspect enclosures for proper alignment, foundation fixing and
grounding and vermin proofing.
Inspect all covers, panels section and doors for paint work and
proper fit.
Check for smooth and proper movement of racking mechanisms
for alignment, shutters, rollers, rails and guides.
Check for proper alignment of the breaker primary and
secondary contacts.
Check operation of all mechanical interlocks.
Check tightness of all bolted connections (torque wrench
method).
Check bus and supports for defects such as cracked welds,
chipped porcelain, cracked insulation, etc., and free from dust
accumulation.
Check main and riser buses for correct phasing.
Verify that all front panel mounted devices (meters, push
buttons, switches, indicator lamps, mimic buses, etc.) are
installed as per drawings.
Perform mechanical checks and visual inspection on all circuit
breakers.
Perform mechanical checks and visual inspection on all current
transformers.
Perform mechanical checks and visual inspection on all voltage
transformers.
Perform mechanical check and visual inspection on all
disconnect and grounding switches.
Check for correct breaker position indication.
Check for correct spring status indication (spring
charged/discharged).
For air magnetic breakers check the arc chutes for damage and
correct positioning above the interrupter contacts.
For minimum oil breakers, check correct oil level in each pole.
For SF6 breakers, check the correct gas pressure, quality and
leakage where possible.
For SF6 breakers, check the operation of the gas density switch
(alarm and lockout functions).
Perform all specific checks on the breaker and spring operating
mechanism according to the manufactures instructions.
Check that all control wiring is correct according to the approved
drawing and terminal connections are secure.
Check all wiring is correct according to approved drawings.
Check that all phase marking have been installed per
specifications.
Verify that correct Dispatch Numbers have been installed.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 37 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
DESCRIPTION
Insulation resistance test of all circuits in the panels.
Functional test of all controls and interlocks.
Bus continuity and phasing test.
Main Circuit Resistance Test with the switchgear erected but
not yet connected to the cables. Performed with 10 or 100
Ampere DC by micro-ohmmeter from panel to panel on each
phase from cable spouts with all circuit breakers racked in
service and in the on position.
Check all AC/DC MCBS in the panel for correct ratings and
grading. Trip test by current injection for one point on curve.
Insulation resistance test at 5 kV DC on all main circuits
between phase to phase and phase to ground (before HV test).
Perform electrical tests on all component equipment as per SEC
approved procedures:
a.
Circuit breakers.
b.
Current transformers.
c.
Voltage transformers.
d.
Disconnect and grounding switches.
Ensure the cable spouts are included in the high voltage tests.
Insulation test on all wiring at 500 V DC.
Functional test of all electrical interlocks.
Functional test of trip free and anti pump circuits.
Functional test of local alarm and indications.
Functional test of remote alarm and indications.
Minimum control voltage trip and close operations.
Check and test capacitor trip circuit (if applicable).
Check spring charge time and motor currents at rated control
voltage.
Functional check of thermostat and space heaters, measure
heater current.
Functional check of breaker operation counter.
Timing test open/close using an electronic oscillograph.
For SF6 breakers, verify electrically the low gas pressure alarm
and lockout functions.
For minimum oil breakers, test insulating oil for dielectric
strength according to ASTM D 877 (with 2.5 mm gap).
Check correct operation of all auxiliary a and b contacts (for
breaker open/closed position).
REMARKS
500 V DC
The resistance values from panel
to panel should vary no more
than 15%. Compare the
measured resistance values with
factory test results, and shall be
within +/- 20% of factory test
results.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 38 of 124
ii.
For vacuum breakers, test across open contact and live parts to ground. Precautions
shall be taken against emission of X-rays.
For all other breakers. Test in conjunction with breaker racked in the switchgear and in
the closed position.
iii.
II.
New switchgear should be tested as a whole unit with all circuit breakers in the closed position
and not connected to cables.
All back shutters must be closed.
Gas circuit breaker interrupters should be checked to be within limits of correct pressure.
VTs, cables or any other voltage indication should be disconnected and VTs secondary side
fuses should be removed.
VTs, cables or any other voltage indication should be in out position and VTS secondary side
fuses should be taken out.
CTs secondary terminals should be short-circuited and earthed.
Test voltage should be applied on each phase to ground with other phases in earthed position.
The test should be repeated on other phases similarly.
The test period should not be more than one minute at full test level and the test voltage
frequency should be kept at 60 Hz.
Charging current for each test is noted and recorded.
HV Test is considered successful if no breakdown occurs during test period.
HV Test levels and time for pre-commissioning testing of switchgear are given in Table 2.
AC High Voltage test
Tests shall be performed with the CB in both the closed and open position
After the high voltage test on main circuit is finished, rack the voltage transformers in service
position and apply a test voltage on the primary side equal to 1.5Un (Un = phase to neutral rated
voltage) on each phase consecutively and measure the secondary output voltage same time
during the test.
Make sure the VTs secondary side MCBs are switched off and any resistor in open delta winding
should have been removed.
The HV Test should be repeated with circuit breakers in open position keeping cable spouts in
earthed condition in all panels.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 39 of 124
SWITCHGEAR RATINGS
AC TEST VOLTAGE
TIME PERIOD
11 kV
25 kV 60 Hz
60 Sec
13.8 kV
30 kV 60 Hz
60 Sec
33 and 34.5 kV
56 kV 60 Hz
60 Sec
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 40 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check bus arrangement for conformance with approved
drawings.
Check tightness of all bolted connections (torque wrench
method).
Check that all enclosure grounding is securely connected.
Inspect internal compartments for cleanliness (free from dust
and moisture).
Check for watertight seals at joints including expanding
interface points.
Check bus conductor support insulators for cracked insulation,
chipped porcelain, etc.
Check quality of paint work (inside and outside).
Check that ventilation opening are not blocked, and meet
specified Degree of Protection.
Moisture drain holes available at bottom of enclosure.
Check anti-condensation heaters mounted at the correct
locations (bottom)
REMARKS
DESCRIPTION
Perform phasing checks. Ensure correct phase identification.
Perform continuity check.
Bus joint resistance test.
Insulation resistance test
HV test (to ground and between phases).
Heaters and thermostats functional test. Measure the heater
currents.
REMARKS
Ductor at 100 A DC
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 41 of 124
DESCRIPTION
Inspect bus and support insulators for physical damage or
defects.
Check bus physical arrangement for conformance with
approved drawings.
Check bus connections for correct phasing and marking of
phases.
Check tightness of all bolted connections (torque wrench
method).
Check for proper phase to phase and phase to ground
clearances.
Ensure that PT, etc., connections are flexible, to prevent
transferring expansion stress from the bus
REMARKS
DESCRIPTION
Measure resistance of bus section joints.
Insulation resistance test at 5 kV DC.
HV test (indoor bus work including PTs where applicable, 69 kV
and below).
REMARKS
Ductor at t 100 A DC.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 42 of 124
12.
13.
DESCRIPTION
Inspect bus for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections (torque wrench
method).
Check all wiring is correct according to approved drawings and
that terminal connections are secure.
Check quality of paintwork.
Check that all grounding cables are securely connected.
Check breaker truck, rails, for proper alignment and smooth
movement.
Check operation of all mechanical interlocks with associated
disconnects, grounding switches, racking truck mechanism,
cubicle doors, etc.
Check for correct breaker position indication (breaker
open/closed).
For minimum oil circuit breakers, check for correct oil level in
each pole.
For SF6 breakers:
a.
Check for correct SF6 pressure in each pole.
b.
Check for gas leakage.
c.
Calibrate SF6 pressure gauge.
d.
Check operation of gas density switch (alarm and
lockout functions).
e.
Verify that all special filling adapters have been
provided.
For motor/spring operation mechanisms:
a.
Check manual spring charge operation.
b.
Verify correct spring status indication (spring
charged/discharged).
c.
Perform all specific checks on the mechanism
according to the manufactures instructions.
For pneumatic operating mechanisms(69KV and above):
a.
Check the compressor, air piping, valves, pressure
gauges, air filter, water trap and switches for damage,
defects or blockage.
b.
Calibrate the air pressure gauges.
c.
Check the setting of air pressure switches (compressor
start/stop, alarm, lockout).
d.
Perform all specific checks on the compressed air
system according to the manufacturers instructions.
e.
Check for correct direction of compressor rotation.
f.
Check air-charging time.
g.
Check safety relief valve operating pressure and
resetting pressure.
h.
Measure air consumption for C, O, CO and OCO
operations.
Air storage test, perform as specified, the following
i.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
14.
15.
T-PreCom-1000-R0
Page Number:
Page 43 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
DESCRIPTION
Measure resistance of main conducting circuits at 100 A DC.
Insulation resistance test of each breaker pole at 5 kV DC.
Insulation resistance test of all low voltage wiring and cabling.
Functional test of all electrical interlocks.
Functional check of trip free and anti pump circuits.
Functional check of phase disagreement protection circuit
(applicable to breakers whose poles are not mechanically gang
operated).
Functional check of local control, alarm and indications.
Functional check of remote control, alarm and indications.
Minimum control voltage trip and close operation.
Functional check of breaker operation counter.
Functional check of thermostat and space heaters, and
measurement of heater current.
Check correct operation of all auxiliary a and b contacts (for
breaker open/closed positions).
Timing test using an electronic oscillograph.
For SF6 breakers, verify electrically the low gas pressure alarm
and lockout functions.
For minimum oil circuit breakers, test insulating oil for dielectric
strength.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
18.
T-PreCom-1000-R0
Page Number:
Page 44 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 45 of 124
9.
10.
11.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections (torque wrench
method).
Check all wiring is correct according to approved drawings and
that terminal connections are secure.
Check quality of paintwork.
Check that all grounding cables are securely connected.
Check for correct breaker position indication (breaker
open/closed).
For SF6 breakers:
a.
Check for correct SF6 pressure in each pole.
b.
Check for gas leakage.
c.
Calibrate SF6 pressure gauge.
d.
Check operation of gas density switch (alarm and
lockout functions).
e.
Check air and moisture content of SF6 gas in breaker.
For motor/spring operation mechanisms:
a.
Check manual spring charge operation.
b.
Verify correct spring status indication (spring
charged/discharged).
c.
Perform all specific checks on the mechanism
according to the manufactures instructions.
For pneumatic operating mechanisms:
a.
Check the compressor, air piping, valves, pressure
gauges, air filter, water trap and switches for damage
or defects.
b.
Calibrate the air pressure gauges.
c.
Check the setting of air pressure switches (compressor
start/stop, alarm, lockout).
d.
Perform all specific checks on the compressed air
system according to the manufacturers instructions.
e.
Check for correct direction of compressor rotation.
f.
Check air-charging time.
g.
Check safety relief valve operating pressure and
resetting pressure.
h.
Measure air consumption for C, O, CO and OCO
operations.
i.
Air storage test, perform as specified, the following
without replenishment: 5X CO, or O + CO + 3min. +
CO
j.
Air leakage test (pressure drop method over 24 hours,
CB closed and open).
For hydraulic operating mechanisms:
a.
Check, the pump, piping, valves, gauges and switches
for damage/defects.
b.
Calibrate the fluid pressure gauges.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 46 of 124
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
DESCRIPTION
Measure resistance of main conducting circuits at 100 A DC.
Insulation resistance test of each breakers pole at 5 kV DC.
Insulation resistance test of all low voltage wiring and cabling.
Functional test of all electrical interlocks.
Functional check of trip free and anti pump circuits.
Functional check of phase disagreement protection circuit
(applicable to breakers whose poles are not mechanically gang
operated).
Functional check of local control, alarm and indications.
Functional check of remote control, alarm and indications.
Minimum control voltage trip and close operation.
Functional check of breaker operation counter.
Functional check of thermostat and space heaters, and
measurement of heater current.
Check correct operation of all auxiliary a and b contacts (for
breaker open/closed positions).
Timing test using an electronic oscillograph.
For SF6 breakers, verify electrically the low gas pressure alarm
and lockout functions.
For minimum oil circuit breakers, test insulating oil for dielectric
strength.
For bulk oil breakers:
a.
Test insulating oil for dielectric strength and water
content.
i.
ASTM D 877 (with 2.5 mm gap) for dielectric
breakdown
ii.
ASTM D 1533A for water content.
b.
Timing test using a time travel analyzer, measuring:
i.
Contact stroke, wipe and simultaneity.
ii.
Over travel and damping oscillations during
closing.
iii.
Close and opening speeds.
iv.
O, C, CO and OCO times.
For motor/spring operating mechanisms, measure spring
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
19.
20.
21.
T-PreCom-1000-R0
Page Number:
Page 47 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 48 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check quality of galvanizing (if applicable).
Check tightness of all bolted connections (torque wrench
method).
Check smoothness and ease of operation (both closing and
opening).
Check simultaneity and synchronism of all 3 poles during
closing.
Check for proper contact, fingers spread and contact pressure
in fully closed position.
Check that end of travel stops are correctly adjusted, set and
locked in position.
Check open gap and minimum clearance between phases and
to ground
Check switch opens more than 90 (for horizontally mounted
vertical open disconnects).
Check switch drive linking toggled in both the closed and
opened positions.
Check that switch can be pad locked in both the closed and
opened positions.
Check that all grounding is securely connected.
Check that switch-operating handle is grounded properly as
specified.
Check mechanical interlocks (with grounding switches, CBs,
etc.).
Check that the operators platform is of adequate size and is
properly grounded.
REMARKS
DESCRIPTION
Measure resistance of main current path (terminal to terminal)
at 100 A DC.
Functional test of all electrical interlocks.
Check position-signaling contacts (if applicable).
For motor operated mechanisms:
a.
Check mechanism cabinet is grounded.
b.
Check correct setting of motor limit switched
(open/close).
c.
Check correct operation of all auxiliary a and
b contacts.
d.
Measure switch opening and closing times and
motor current at rated voltage (for fast acting
disconnects and grounding switches, perform
a timing test with an electronic oscillograph).
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
5.
T-PreCom-1000-R0
Page Number:
Page 49 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 50 of 124
Circuit Switchers
DESCRIPTION
Perform mechanical checks and inspection of isolating
disconnect, as per Section 3.17.1, above.
Perform mechanical checks and adjustments on interrupter unit
according to the manufacturers instructions.
Check the low SF6 target at the interrupter units.
Check interrupter position indicator operation.
REMARKS
5.
6.
7.
8.
DESCRIPTION
Resistance of main current path (terminal to terminal) at 100
Amps DC.
Functional check of all electrical interlocks.
Check position-signaling contacts (if applicable).
For motor operating mechanisms:
a.
Check mechanism cabinet properly grounded.
b.
Check correct setting of motor limit switched
(open/close).
c.
Check correct operation of all auxiliary a and b
contacts.
d.
Measure switch opening and closing times and motor
current at rated voltage (for fast acting disconnects and
grounding switches, perform a timing test with an
electronic oscillograph).
e.
Minimum voltage operation (close and open) at 90V
DC.
f.
Functional check of thermostat and space heaters.
Measure heater current.
g.
Insulation test all control and power wiring/cables at
500V DC
h.
Check that in the manual mode, insertion of the
operating handle automatically disconnects the motor
DC supply.
Check shunt trip device operation.
Verify proper operation sequence of interrupters and
disconnects.
Insulation power factor test of the interrupters.
Timing test of the interrupter contacts with electronic
oscillograph.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 51 of 124
LV Switchgear (110/220 V)
DESCRIPTION
Main circuits Continuity Test for tightness of joints and bolts.
Main circuit insulation resistance measurement by 2.5 kV
Megger or 2 kV AC HV test for one minute.
Phasing check.
Check and verify for all MCCBs ratings as per requirement and
Trip Test by current injection.
All ammeters and volt meters shall be calibrated.
Insulation Test on all secondary wiring and cables.
Tests on changeover schemes as per approved drawings if
applicable.
Confirm the neutral cable coming from auxiliary transformer is
grounded in the LV distribution board.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 52 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
Check for proper cable bolted connections.
Check for proper cable support, clamping, trays, blocking.
Check cable bends to ensure that bending radius is equal to or
greater than the minimum bending radius specified.
Link box tightness check.
Verify that shields are terminated as specified (through link box
or directly grounded).
Verification of exact route length from termination to termination
as per approved drawings.
Check that all grounding points are securely connected to
ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter as per
approved design.
Check cable entry path trench as ducts are to be properly
sealed.
For accessories (sealing terminations, instrument panels and
link boxes), check the following as applicable:
a.
Nameplates installed and data is correct.
b.
Condition of paint work.
c.
All bolted connections.
REMARKS
DESCRIPTION
Phase checking for conductor and sheath bonding in every link
box.
Conductor resistance, capacitance and inductance
measurement test.
Sheath DC high voltage test (10 kV for 1 minute) and 5 kV DC
insulation tester before and after high voltage test.
Anti corrosion sheath test.
Measure the ground resistance at all link box positions.
Zero and positive sequence impedance measurement.
SVL (sheath voltage limiter) test with 2.5 kV DC insulation
tester.
Insulation resistance test of cable by 5 kV DC.
Cross bonding verification test.
Contact resistance test on link boxes (less than 20 ).
Metallic sheath continuity test (if applicable).
REMARKS
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 53 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 54 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is equal to or
greater than the minimum bending radius specified.
Check for proper cable support, clamping, trays and blocking.
Verify that shields are terminated as specified (through link box
or directly grounded).
Verification of exact route length as per approved drawings from
termination to termination.
Check that all grounding points are securely connected to
ground grid as specified.
Pressure test of all associated oil piping.
Check that phases are identified and color coded.
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Availability of oil sampling facility valve arrangement.
Check single point or both ends, via voltage limiter as per
approved design.
Check cable entry path trench as ducts are to be properly
sealed.
Oil flow test.
Impregnation test.
RGP test and DGA tests.
For accessories (sealing terminations, pressure tank, gauges,
instrument panels and link boxes), cheek the following as
applicable:
a. Nameplates installed and data is correct.
b. All valve positions according to design (open/closed).
c. Calibrate pressure gauges and pressure switches.
d. Oil pressure.
e. No oil leaks.
f.
Condition of paint work.
g. All bolted connections.
REMARKS
DESCRIPTION
Check Phasing for conductor and sheath bonding in every link
box
Conductor resistance, capacitance and inductance
measurement test.
Sheath DC high voltage test (10 kV for 1 minute) and 5 kV DC
insulation tester before and after high voltage.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 55 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 56 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is equal to or
greater than the minimum bending radius specified.
Check for proper cable support, clamping, trays, blocking.
Link box tightness check.
Verify that shields are terminated as specified (through link box
or directly grounded).
Verification of exact route length as per approved drawings from
termination to termination.
Check that all grounding points are securely connected to
ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter as per
approved design.
Inspection of label inside link boxes and water proofing test.
Check cable entry path trench as ducts are to be properly
sealed.
For accessories (sealing terminations, instrument panels and
link boxes), cheek the following as applicable:
a.
Nameplates installed and data is correct.
b.
Condition of paint work
c.
All bolted connections
REMARKS
DESCRIPTION
Check phasing for conductor and sheath bonding in every link
box.
Sheath DC high voltage test and 5 kV DC insulation tester
before and after high voltage test.
Conductor resistance, capacitance and inductance
measurement test.
Conductor insulation resistance test.
Cross bonding verification test.
Zero and positive sequence impedance measurement.
SVL (sheath/surge voltage limiter) test with 2.5 kV DC insulation
tester.
Measure the ground resistance at all link box positions.
Contact resistance test on link boxes.
Metallic sheath continuity test (if applicable).
REMARKS
10 kV for 1 minute
less than 10
less than 20
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 57 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 58 of 124
(Standard Reference is IEC 60141-1, -2, -3 and relevant SEC Transmission Specifications)
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
Check for proper cable bolted connections.
Check for proper cable support, clamping ,trays, blocking.
Check cable bends to ensure that bending radius is equal to or
greater than the minimum bending radius specified.
Verify that shields are terminated as specified (through link box
or directly grounded).
Verification of exact route length as per approved drawings from
termination to termination.
Check that all grounding points are securely connected to
ground grid as specified.
Pressure test of all associated oil piping.
Check that phases are identified and color coded.
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Availability of oil sampling facility valve arrangement.
Check single point or both ends, via voltage limiter as per
approved design.
Oil flow test.
Impregnation test.
RGP test and DGA test.
Check cable entry path trench as ducts are to be properly
sealed.
For accessories (sealing terminations, pressure tank, gauges,
instrument panels and link boxes), check the following as
applicable:
a.
Nameplates installed and data is correct.
b.
All valve positions according to design (open/closed).
c.
Calibrate pressure gauges and pressure switches.
d.
Oil pressure.
e.
No oil leaks.
f.
Condition of paint work.
g.
All bolted connections.
REMARKS
DESCRIPTION
Check phasing for conductor and sheath bonding in every link
box
Sheath DC high voltage test with 5 kV DC insulation test before
and after high voltage test.
Conductor resistance, capacitance and inductance
measurement.
REMARKS
10 kV for 1 minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 59 of 124
Sheath Current < 3 %
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 60 of 124
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is equal to or
greater than the minimum bending radius specified.
Check for proper cable support, clamping, trays, blocking.
Link box tightness check.
Verify that shields are terminated as specified (through link box
or directly grounded).
Verification of exact route length as per approved drawings from
termination to termination.
Check that all grounding points are securely connected to
ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter as per
approved design.
Check cable entry path trench as ducts are to be properly
sealed.
For accessories (sealing terminations, instrument panels and
link boxes), cheek the following as applicable:
a.
Nameplates installed and data is correct.
b.
Condition of paint work.
c.
All bolted connections.
REMARKS
DESCRIPTION
Check phasing for conductor and sheath bonding in every link
box.
Conductor resistance, capacitance and inductance
measurement test.
SVL (sheath voltage limiter) test with 2.5 kV DC insulation
tester.
Anti corrosion sheath test.
Measure the ground resistance at all link box positions.
Zero and positive sequence impedance measurement.
Insulation resistance test for conductor.
Sheath DC high voltage test (10 kV for 1 minute) and 5 kV DC
insulation tester before and after high voltage test.
Cross bonding verification test
Contact resistance test on link boxes.
Metallic sheath continuity test (if applicable).
REMARKS
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 61 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 62 of 124
DESCRIPTION
Inspect for physical damage or defects. Check irregularities of
outer jacket caused by non-uniform shield wire distribution.
Verify all cable connections as per drawing.
Check for proper cable support, clamping, trays, blocking.
Check cable bends to ensure that the bending radius is equal to
or greater than the minimum bending radius specified.
Verify shield grounding as per design (single point, both ends,
via voltage limiters, etc.
Check tightness of all bolted connections (torque wrench
method).
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Check that phases are identified and color coded.
Check cable entry path trench as ducts are to be properly
sealed.
Verification of exact route length as per approved drawings from
termination to termination.
Check for proper cable arrangement in the path (RYB) in order
to prevent circulating current.
REMARKS
DESCRIPTION
Sheath armor continuity test.
Sheath insulation resistance test.
Main conductors insulation resistance test (5KV DC insulation
tester) before and after HV Test.
Phasing and continuity test of main conductor
AC- high voltage test
a.
For new XLPE power cables, AC HV test voltages
should be applied up to 2 Uo for one hour or by VLF at
0.1 Hz at test voltage level of 3 Uo for one hour can be
performed.
b.
For mixed new and old cables, the test voltage shall
depend upon the service life of the old cable.
c.
At least It should be tested at normal working voltage
phase to neutral (Uo).
d.
Mixed new and old cables should not be tested by DC
test voltage at any condition except by AC or VLF
methods.
e.
Where cables are connected to switchgear, the AC HV
test time should be reduced to 5 minutes. One hour
test applies if the cables are fully isolated.
f.
Uo for all the applied tests is equal to phase to neutral
voltage.
REMARKS
IR for sheath > 10 megohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 63 of 124
3.26 LV Cables
(Standard Reference is IEC 60227-2 and relevant SEC Transmission Specifications)
DESCRIPTION
Inspect for physical damage or defects.
Check for proper cable support, clamping, trays, blocking.
Verify all cable connections as per approved drawing.
Verify that all cables and cores are labeled correctly.
Check tightness of terminals and confirm the cables are
secured.
Check that all cable trays are secure and correctly grounded.
Check cable entry path trench as ducts are to be properly
sealed.
Visual Insulation, size and rating confirmation.
Check cable size against rating required.
REMARKS
DESCRIPTION
Phasing and continuity check.
AC HV Test at 2 kV 60 Hz for 1 minute between core to core
and core to grounded armor.
Insulation Resistance Test with 2.5 kV DC insulation tester.
REMARKS
>=100 M
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 64 of 124
Control Cable
DESCRIPTION
Inspect for physical damage/defects.
Verify all cable connections as per approved drawing.
Verify that all cables and cores are labeled correctly.
Check for proper cable duct, support, clamping, trays, blocking.
Check tightness of terminals, ferrule numbering and confirm the
cables are secured.
Check that all cable trays are secure and correctly grounded.
Check all cables are securely supported throughout.
Visual inspection, size and rating confirmation.
Size checking against rating required.
REMARKS
DESCRIPTION
Phasing and continuity check.
Insulation Resistance Test with 1 kV DC insulation tester.
REMARKS
IR > 100 Megohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 65 of 124
Pilot Cables
DESCRIPTION
Inspect for physical damage or defects.
Verify all cable connections as per approved drawing.
Verify that all cables and cores are labeled correctly.
Check for proper cable support, clamping, trays, blocking, etc.
Check tightness of terminals, ferrules, wiring identification and
confirm the cables are secured.
Check that all cable trays are secure and correctly grounded.
Check all cables are securely supported throughout.
Visual inspection, size and rating confirmation.
Size checking against rating required.
Verification of exact route length as per approved drawings from
termination to termination.
REMARKS
DESCRIPTION
Conductor loop resistance test for all pairs.
Core Identification for each core between two ends.
Insulation Resistance for sheath armor to ground by 500V DC
insulation tester for each section before jointing.
Insulation Resistance for sheath armor to ground with a 500 V
DC insulation tester after all joints are completed and before
termination in the pilot boxes (if applicable).
Capacitance measurement for all cores.
Insulation resistance test between core to core and core to
ground with a 5 kV DC insulation tester.
Frequency response test.
End to end terminal and pair matching.
Noise Level Measurement.
Cross-talk and coupling test between pairs.
High voltage test for protection and control core by 15 kV DC for
1 minute.
REMARKS
IR > 10 megohms
IR > 10 megohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 66 of 124
PRE-COMMISSIONING SITE
TEST LEVEL
TIME PERIOD
(MINUTES)
2Uo = 16 kV AC
or
VLF test level = 3Uo = 24 kV
2Uo = 38 kV AC
or
VLF test level = 3Uo = 57 kV
2Uo = 80 kV AC
or
VLF test level = 3Uo = 120 kV
60
60
60
60
60
60
2Uo = 128 kV AC
60
2Uo = 152 kV AC
60
230 kV XLPE/LPOF
POWER CABLES
2Uo = 265 kV AC
60
380 kV XLPE/LPOF
POWER CABLE
2Uo = 438 kV AC
60
REFERENCES
AC HV Test: Recommendation by KEMA Research Laboratory (Netherlands).
VLF Test:
Recommendation by High Voltage Corporation (USA) and Seba-Dynatronic (GERMANY)
as a Manufacturer of VLF Test Sets.
Test Voltage levels for LV Cables, Control Cable and Pilot Cables
SYSTEM RATED
VOLTAGE (KV)
PRE-COMMISSIONING SITE
TEST LEVEL
TIME PERIOD
(MINUTES)
LV Cables
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 67 of 124
Overhead Lines
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
DESCRIPTION
Inspect that the access roads and structure pads are to
specification (locations, widths, depth of base, cover material
properly compacted, etc.).
Check that sand stabilization has been done per specification (if
applicable).
Check the right of way to ensure that there is no construction or
agricultural encroachment.
Check that the ground profile allows water run-off from the
structures.
Check that grounding connection is made properly with steel
structure and protective coating is applied on the concrete cap
(if specified). There shall be no cracks, and the concrete cap
shall slope away from the stub angle.
Check that crash barrier and/or flood protection are being done
as per specification (if applicable).
For wooden pole structures, ensure that pole types and sizes
are the correct specification and have been installed correctly
(depth and plumb). Ensure that the depth indication tags are on
each pole.
For wooden pole structures, check structure guy wire, cross
braces, and other framing work have been done correctly.
Check that all wood structures have been identified correctly
and that the identification plates are to specification. For double
circuit structures, ensure that each circuit is correctly identified.
For steel structures, ensure that type is as per specification /
drawings.
Check galvanizing quality and thickness (rust is not acceptable).
Check bolt types and tightness (torque wrench method).
Ensure anti-climbing guards are correctly installed (if
applicable).
Check step bolt tightness.
For porcelain insulators, check insulators for chips, cracks, etc.
Ensure correct number of insulators have been installed in each
string. Ensure that cotter keys have been properly installed.
For composite insulators, perform close elevated inspection on
each structure to check that the insulator sheaths and sheds are
not cracked, damaged or torn. The inner fiberglass rod should
not be exposed at any location.
Check that all line hardware (insulators, corona rings, vibration
dampers, spacers, conductor clamps, warning spheres, warning
lights, armor rods, counter weights, flag socket/keys, etc.) is
installed correctly and in correct locations as per specification
and drawings.
Make sure that the insulators are clean and line is safe to be
energized.
Check that all splices are correct and installed in correct span
locations.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
29.
T-PreCom-1000-R0
Page Number:
Page 68 of 124
ITEM
1.
2.
3.
4.
5.
DESCRIPTION
Perform phase sequence/rotation check.
Perform sequence impedance and susceptance tests and
mutual impedances (both zero and positive sequence for double
circuit lines.
Check tower foot earth resistance as per company standard.
Check the aircraft warning lights are properly functioning (if
applicable).
Perform continuity and conductivity test.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 69 of 124
(Standard Reference is SEC Transmission Standard Procedures and relevant Manufacturers Recommendations)
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for defects and physical damage from shipping and
handling.
Prior to opening any case or panel, confirm that the equipment
will not be contaminated by dust, excessive humidity or other
pollutants.
Ensure that there is no foreign material, moisture, dust, etc.,
inside panels and device cases.
Check all installed equipment nameplate information for
compliance to approved drawings and equipment/material lists.
Ensure that all relays, relay covers, meters, controls and test
facilities are properly identified as per the approved drawings
and relevant SEC standards and that the identification does not
obscure information displays.
Ensure the mimic bus provides an accurate representation and
that all switchgear identification is accurate and as assigned by
Systems Operations Department.
Confirm that each panel has been properly secured to the floor
in its final service location.
Confirm that panels are constructed and wired as per SEC
relevant specification.
For all internal and external panel wiring, confirm that all screw
terminations are tight and that crimp connectors are firmly
secured to the wire and to the termination point. Ensure that no
part of the wire is bent at the termination point.
Check that panel equipment is mounted securely and protected
against mal operation due to vibration, shock, etc.
REMARKS
DESCRIPTION
Wiring Test / Confirmation
a.
The equipment is safe to work on and free of
construction activities.
b.
Ensure that the approved drawings, relevant
specification, protection requirement, manufacturers
manuals, factory test results, site test procedures, etc.,
are available at site.
c.
All necessary tools and equipment with their valid
calibration certificates are available.
d.
Stable auxiliary power supplies at the rated voltages
are available.
e.
Prior to conducting panel checks, open all supply
breakers, remove all fuses and ensure that all DC
(including alarm, SOE, SCADA, etc.), AC, VT and CT
circuits are properly isolated.
f.
Confirm all DC circuits are ungrounded.
g.
Check CT and VT circuits to confirm the presence of a
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
2.
3.
T-PreCom-1000-R0
Page Number:
Page 70 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 71 of 124
ITEM
1.
2.
3.
DESCRIPTION
Continuity Checks
Cables and external wiring insulation shall be tested as for
panel internal wiring, Section 3.30.2. All control cables shall be
tested using a low ohms reading ohmmeter to check each wire
separately to ground (CT and VT circuits must have their
normal grounding point isolated during this test). The
technician at one end shall ground one core at a time in
communication with the technician at the other end who shall
use an ohmmeter to monitor the cores.
CT Cable Checks
A final check of each CT circuit shall be conducted by current
injection at the source end while measuring magnitude and
phase angle in the downstream circuit test facilities.
VT Cable Checks
A final check of each VT circuit shall be conducted by voltage
injection at the source end while measuring magnitude and
phase angle in the downstream circuit test facilities.
REMARKS
DESCRIPTION
Each panel device shall be mechanically inspected prior to
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
2.
3.
testing.
CAUTION: When working with electronic devices, never
remove modules with the DC supply energized. Use
precautions to prevent static discharge damage to the modules.
Grounded wrist strap, anti-static work surface and electrically
conductive storage bags should be used.
a.
Check condition of internal wiring and solder joints.
b.
Case cover and gasket for proper seal against dust.
c.
Condition of any connectors, contacts, alignment and
travel.
d.
Operation of moving parts, mechanical target
operation and reset.
Relay Tests
Relay tests shall be conducted in accordance with the approved
site test procedure. Additional tests may be required as
recommended by the manufacturer, by Company Standard or
as deemed necessary by the Company from operational
experience.
a. 500 V insulation tests shall be conducted between the
AC circuits and from AC circuits to the relay frame. All
outputs/indications shall be tested.
b. For electromechanical relays, the DC circuits shall be
insulation tested to AC circuits and to the frame of the
relay.
c. Initial tests of new protective relays shall include
operating characteristics checks for a representative
range of available settings with Company approved
computer operated test equipment running routines
developed for the specific relay and test set involved.
d. Relay auxiliary devices such as external resistors,
metrosils, etc., to be tested to conform to required
ratings and manufacturers information.
e. Proper electrical operation of targets/indicators shall be
confirmed.
f.
Final calibration test of all protective relays must be
carried out on approved settings with the relays
mounted in their cases, by secondary injection at the
front panel mounted test facilities.
g. Auxiliary and tripping relay testing shall include:
i.
Insulation testing as above.
ii.
Pickup and dropout voltage, verification of all
contacts.
iii.
Operation timing at 80% and 100% nominal
voltage.
iv.
Time delay relays shall be tested at 0%, set
point and 100% delay.
h. Use of red and green tags for tested relays, meters,
etc.
i.
All the relays and meters which have been tested and
found acceptable shall have green tags.
j.
The relays and meters found defective during tests
shall be tagged red.
Metering Tests
Panel metering calibration shall be tested via front panel
mounted test facilities. The following represent the minimum
T-PreCom-1000-R0
Page Number:
Page 72 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
4.
5.
T-PreCom-1000-R0
Page Number:
Page 73 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 74 of 124
2.
3.
4.
5.
6.
DESCRIPTION
Test to Local Auxiliaries
With all tripping isolating switches opened, operate the
protective relays by secondary injection to test all functions to
the panel auxiliaries. Check and confirm correct operation of all
trip, alarm, SOE and SCADA auxiliaries in the panel as well as
initiation outputs to DFR, breaker failure, etc.
End To End Tests
Communications with the test crew at the remote end are
essential to this test. Where protection signaling equipment
(PSE) is used in the scheme, end to end tests shall be
conducted to confirm operation of each channel individually to
the correct remote tripping/protection inputs in coordination with
personnel at the remote end. Round trip channel delay should
be checked and recorded. Pilot Differential Protection shall be
end to end tested as recommended by the manufacturer.
Test to Remote Functions
Individually operate each control switch, protection output trip,
initiation and alarm function with the associated isolating switch
(if available) first in the open position and then in the closed
position to prove the switch connection. Take care to limit
tripping when testing to transfer tripping or breaker failure
protection prior to initiating. Where no physical or visual
indication of the signal is available, use a multimeter to monitor
the received signal at the appropriate terminals of the remote
panel or equipment. Interlocks such as close blocking from
lockouts shall also be proven. Testing shall include all
reclosing, initiation, trip, SCADA, SOE, annunciator and fault
recorder outputs from the panel to actuate the associated
remote devices.
Primary Injection
Phase and ratio connection of CT and VT circuits shall be
confirmed by primary injection and checked to the panel test
facilities.
Stability Tests
Stability of bus bar, transformer differential protection and
restricted E/F protection circuits shall be confirmed by injecting
current on the primary bus and simulating first internal and then
external fault conditions while monitoring spill current at the
protective relay.
Remote Tap Change Control (RTCC)
a.
Selection of Independent, Master/Follower, Auto,
Manual from RTCC local pushbuttons and from
SCADA.
b.
Raise and lower operation of the tap changer in
Independent/Manual from both the RTCC control
pushbuttons and from SCADA.
c.
Raise and lower operation of the tap changer in
Master-Follower for each possible combination of
paralleled transformers, in Manual mode from both the
RTCC control pushbuttons and from SCADA.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
7.
8.
9.
10.
11.
T-PreCom-1000-R0
Page Number:
Page 75 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 76 of 124
3.30.6 Energization
ITEM
1.
2.
3.
DESCRIPTION
First Time Energization Testing-Checks Prior to Energization
a.
All in service CT circuit shorting is removed.
b.
All VT circuits MCBs closed, fuses in place.
c.
All supplies to protection, control, switchgear, etc., are
normal.
d.
No abnormal relay targets, alarms, SCADA SOE
indications.
e.
All relays have approved settings applied and have
been fully tested and are in service.
f.
All switchgear and other power equipment testing is
completed.
g.
All protection equipment is properly labeled.
h.
All fire/smoke alarm systems are fully tested and in
service.
i.
All necessary fire fighting equipment is on site and
accessible without obstruction.
j.
Confirm all men and tools are clear of equipment to be
energized and that all personnel are aware of the
pending energization.
Phasing Checks
Before paralleling two sources, phasing shall be absolutely
proven by selectively energizing a common three phase VT
set from the two sources one at a time and checking the
phasing (voltage and phase angle) of the VT set to a
reference potential whose source shall remain unchanged for
the duration of the test.
For example, if one new incoming line to an existing station
is to be energized, use the existing incoming line A phase to
neutral potential as a reference and measure and record the
new line VT secondary three phase voltage and phase
angles when energized from the remote end only. Then after
opening the remote end of the new line, energize the new
line from the local station only and repeat the voltage and
phase angle measurements, the results of the two tests
should be identical (within a few degrees) if phasing is
correct. Where possible, phasing sticks can be used.
In Service Checks
a.
Immediately after energization, in-service/on-load
checks should be taken and recorded by measuring
the magnitude and phase of all voltage and current
circuits to a common reference at all of the test points
available to prove VT and CT connection, ratio and
polarity.
b.
Check and record all panel meter readings to compare
with CT/VT measurements in the control circuits.
c.
As soon as sufficient load is available, all directional
and distance type relays shall have their operating
direction proven using in service voltages and currents.
d.
Directional earth fault relays shall be proven by
selectively isolating in service voltages and currents to
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
f.
g.
h.
i.
T-PreCom-1000-R0
Page Number:
Page 77 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 78 of 124
Station Batteries
(Standard Reference is IEC 60623, clause 4 and relevant SEC Transmission Specifications)
10.
11.
12.
13.
14.
15.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness as per standards.
Check tightness of all external wiring and cabling connections.
Verify all panel mounted devices (meters, switches, push
buttons, indicator lamps, etc.) are supplied and installed
according to approved drawings.
Make sure all battery connections are clean and free from
corrosion.
Verify system configuration and capacity with contract
specification.
Check that all cells are properly numbered.
Check protective covers installed.
Check that all battery maintenance tools and accessories
(hydrometer, wall mounted thermometer, insulated torque
wrench, rubber gloves, apron, face shield) have been provided
per specifications. Ensure that all maintenance equipment is
stored in a wall mounted lockable cabinet.
Check that the room ventilation, exhaust fan, etc., are to
specification.
Check installation of safety equipment (eyewash, showers, No
smoking and Warning Caustic/Acid signs).
For flooded lead acid batteries, check for correct specific gravity
and liquid level.
Check that all battery racks are correctly and securely
grounded.
Check that the battery bank is provided with an isolating
disconnect switch.
Check that the Valve Regulated Lead Acid (VRLA) battery bank
has an ammeter provided for monitoring the float charge
current.
REMARKS
DESCRIPTION
For valve Regulated lead Acid Batteries, check the open circuit
voltage of each cell.
Perform initial charging of the battery (equalize voltage,
charging rate and charging time according to the manufacturers
instructions).
Record individual cell voltage electrolyte specific gravity and cell
temperatures at the end of charge cycle.
Battery discharge test:
a.
The battery must not have been discharged within last
7 days before test is performed.
b.
While battery on float, read and record the voltage of
each cell or unit and battery terminals float voltage.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
5.
T-PreCom-1000-R0
Page Number:
Page 79 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 80 of 124
Battery Chargers
(Standard Reference is IEC 60623, clause 4 and relevant SEC Transmission Specifications)
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness as per standards.
Check tightness of all external wiring and cabling connections,
labeling, drawing pocket shall be checked.
Verify all panel mounted devices (meters, switches, push
buttons, indicator lamps, fuses, etc.) are supplied and installed
according to approved drawings.
REMARKS
5.
6.
7.
8.
9.
10.
11.
DESCRIPTION
Insulation test for all external wiring.
Battery charger test by simulation of variable load to check for
correct charger current output response to different values of
load.
Check the adjustment range of output float and equalize
voltage. Note that the adjustment of float and equalize voltage
should be independent of each other.
Functional check of the following:
a.
High and low output voltages alarm/shutdown.
b.
Ground monitoring/ground detector for +ve and ve
alarms.
c.
All other protective alarm/shutdown.
d.
All devices (switches, push buttons, timers, indicating
lamps, etc.).
e.
Current limits.
f.
Soft start.
g.
Impedance monitors (if applicable).
h.
Silicon droppers (if applicable).
Check output voltage ripple content (battery disconnected).
Check regulation at 0%, 50% and 100% of full load.
Measure AC input and DC output voltages and currents and
calculate efficiency at 50% and 100% of rated output current.
Calibrate voltmeters and ammeters.
If applicable measure the following and verify that they are
compatible with and meet the requirements of the
communications equipment:
a.
Voice band noise voltage.
b.
Wideband noise voltage.
Check load sharing operation for parallel chargers.
Ensure that the settings of adjusted control, shutdown, alarm
voltage, etc., have been reset to the final operational values as
specified by SEC.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 81 of 124
AC Distribution Panels
DESCRIPTION
Inspect for physical damage or defects including of quality of
paint work.
Verify circuit layout for conformance with breaker directory
drawing.
Verify correct rating of each circuit breaker per design drawings.
Check tightness of all bolted connections.
Verify that all front panel mounted devices (meters, selector
switches, push buttons, timers, indication lamps, etc.) are
installed per layout drawing and are correctly labeled.
Check for proper grounding connection (torque wrench
method).
REMARKS
DESCRIPTION
Insulation test of all buses and wiring.
Phasing check.
Functional check of main power contactor (or breaker).
Functional check of each branch breaker.
Calibrate voltmeters, ammeters and wattmeters.
Functional check of meters and phase selector switches.
Functional check of all auxiliary devices including individual,
group and main circuit breaker alarms.
Functional check of under voltage protection/alarm circuits.
Functional check of ground fault circuit interrupter (if applicable).
Check all MCBs for their ratings and alarms.
REMARKS
2.5 kV for one minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 82 of 124
DC Distribution Panels
DESCRIPTION
Inspect for physical damage or defects including of quality of
paint work.
Verify circuit layouts for conformance with breaker directory
drawing.
Verify correct rating of each circuit breaker per design drawings.
Check tightness of all bolted connections.
Verify that all front panel mounted devices (meters, selector
switches, push buttons, timers, indication lamps, etc.) are
installed per layout drawing and are correctly labeled.
Check for proper grounding connection (torque wrench
method).
REMARKS
DESCRIPTION
Insulation test for all buses and wiring.
Polarity check.
Functional check of main breaker.
Functional check of each branch breaker.
Calibrate voltmeters, ammeters and wattcmeters.
Functional check of meters.
Functional check of all auxiliary devices including individual,
group and main circuit breaker alarms.
Functional check of under voltage protection and alarm circuits.
Functional check of DC transfer switches and interlocks.
Functional check of positive and/or negative ground alarm
(calibrate resistors for proper detection sensitivity earth fault
relay setting shall be checked).
Check all MCBs for their ratings and alarms.
REMARKS
2.5 kV for one minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 83 of 124
LV AC Auto-Transfer Schemes/Switches
DESCRIPTION
Inspect for physical damage or defects.
Check that all front panel mounted devices are supplied and
arranged according to approved drawings.
Check that all devices and cables are properly identified and
labeled.
Check tightness of all bolted connections (torque wrench
method).
Check that all grounding is correct and securely connected
(including neutral bus).
Check mechanical/electrical interlocks.
REMARKS
DESCRIPTION
Phasing check of incomers and transfer switch connections.
Calibrate under voltage relays and time delays.
Calibrate voltmeter and ammeters.
Functional check of meters and selector switches.
Functional check of electrical and mechanical interlocks.
Functional check of preferred source selector switch.
Check transfer motor fuses.
Functional check of transfer operation (simulate loss of one
source) and retransfer on re-establishment of preferred source
voltage. Check with each source as the preferred source.
Ensure the sources are from two separate buses.
Set under voltage relay and time delay per manufacturers
instructions.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 84 of 124
Grounding Systems
DESCRIPTION
Inspect the grounding system(s) for conformance with approved
design drawings and specification.
Inspect the mechanical integrity and quality of all bolted and/or
thermite welded grounding joints and connection.
Inspect and verify the size and type of conductors conform to
standard requirements.
Check that all metal parts in the substation are grounded.
REMARKS
3.
DESCRIPTION
Measure the ground grid system resistance by the fall of
potential method.
Measure the contact resistance at 100 A DC of all bolted and/or
thermite-welded joints at the grounding conductor between the
equipment to be grounded and the grounding mesh. Note that
bolted below grade connections are not permitted.
Measure the electrical resistance between each major electrical
equipment grounding point, grounded neutral points and the
substation main grounding system by the millivolt drop
method.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 85 of 124
13.
DESCRIPTION
Inspect for physical damage or defects.
Check labeling and marking according to the approved
drawings.
Check tightness of bolts on direct drive and base-mounted
equipment.
Check oil level and leakage and air compressor main
components, air receiver tank design and specification.
Check hour meter, safety relief valve, pressure switch and
gauges.
Check air lines piping according to the approved materials.
Check that the exposed airlines protected against rupture
damage.
Check that all piping runs parallel to flooring or walls and is
clamped properly by u-bolts or metal clamps supported on at
least 6 foot intervals or less.
Check that all piping has sufficient spacing so that each line can
be accessed without disturbing the rest of the piping.
Check that all pipes are supported on steel benches on the floor
of the trench.
Check that all piping fitting connections to be used shall be flare
cup type nuts with sleeve.
Check that air compressors are fitted with:
a.
Automatic drain valve.
b.
Manual drain valve.
c.
Pressure relief valve.
d.
Oil level sight glass.
Check that the receiver tank provided with inlet and outlet stop
valves, manual drain valve, pressure relief valve and pressure
gauge.
REMARKS
5.
DESCRIPTION
Check that the motor for air compressor designed for operation
on 220 V, 3 phase 60 Hz including magnetic contactors, relays
and accessories.
Check that circuit breaker, isolating switch wires and conduit
sizes are suitable for load requirement of the system.
Check that all wiring shall be in rigid steel conduit, wire ducts or
flexible conduit; wires shall be standard type THW and color
coded.
Check that all wiring splices shall be made with wire connector
or terminal bed connectors of approved type and insulated with
two layers of rubber, covered with friction tape to protect the
rubber.
Check that main control panel is equipped with indication lamps,
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 86 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 87 of 124
HVAC Systems
12.
13.
14.
DESCRIPTION
Inspect for physical damage or defects.
Check labeling and marking is according to the drawings.
Check tightness of bolts on direct drive and base-mounted
equipment.
Check for adequate access to the equipment.
Check that ducts exposed to weather are properly insulated and
wrapped with weather proofing materials, e.g., wrapped with
aluminum sheet.
Check that the space clearance around the duct shall be
properly sealed to prevent the passage of rain water or any
other foreign matter.
Check that all panels such as control panel, compressor panel,
motor blower panels shall be provided with left and right
handles.
Check that air conditioning essential components, electrical
controls, breaker, etc., is properly labeled or marked.
Check that all exposed refrigerant suction lines are properly
insulated and wrapped with aluminum sheet and suitably
protected from rupture damage.
Check that the exposed refrigerant liquid line is painted with
liquid refrigerant gas color code paint and fitted with liquid sight
glass, solenoid valves expansion valves and strainer if required.
If semi-hermetic reciprocating compressor with nominal cap of
20 tons and above is used, check that the size of receiver tank
is able to contain all refrigerant charged into the system plus
20% excess volume for gas expansion.
Check that receiver is provided with inlet and outlet shut off
valves, relief valves, purge cock, liquid level sight glass and oil
drain.
Check that the refrigerant compressor is a sealed hermetic type
or semi-hermetic reciprocating type.
Check that the compressor is provided with the following:
For sealed type hermetic compressors:
a.
Suction and discharge service valves with charge plug
fitting connection.
b.
Crank case heater.
c.
High and low pressure cut-out manual reset.
For semi-hermetic reciprocating compressors:
a.
Suction and discharge service valves with charge plug
fitting connection.
b.
Oil level sight glass.
c.
Suction, discharge and oil pressure gauges.
d.
Crank case heater.
e.
Oil pressure protective switch to stop compressor
operation in case of lubrication failure.
f.
High and low pressure cut-out manual reset.
g.
Suction line strainer with service valves.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 88 of 124
ITEM
DESCRIPTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 89 of 124
DESCRIPTION
Inspect for physical damage/defects (cracks, chips, etc., of the
cast resin).
Check nameplate for correctness.
Check tightness of all bolted connections (torque wrench
method.
Check that all grounding is securely connected, including star
point neutral.
Perform all specific checks per manufacturer instructions.
Check proper operation of all auxiliary devices (as applicable).
REMARKS
DESCRIPTION
Insulation resistance and Polarization Index (PI) test.
Turns ratio all (taps) test.
Polarity and vector relationship test.
Winding resistance measurement (all taps).
Excitation current test (at nominal tap).
Back energization test (at rated voltage for 15 minutes).
Check the off load tap changer is set at the rated voltage tap.
Functional test of all auxiliary devices (if applicable).
Control and protective circuit functional tests.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 90 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 91 of 124
Civil Work
Witnessing of civil work is the responsibility of the CTA/DTA Support Facility Project Division to
witness the work of the civil contractor. Transmission witnessing personnel shall check the
accesses and ventilation that affects the main equipment.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 92 of 124
DESCRIPTION
Get the sanction for test document.
Check the safety documents for entering the capacitor bank
area.
Check the safety documents for entering the TCR area.
Check the safety document for touching the capacitor banks
and TCRs.
Check the anti-static instruction prior to handling the electronic
devices.
Never touch the components of electronic cards without antistatic wrist strap.
Check your safety shoes, helmet, goggles and industrial
uniform.
REMARKS
3.42.3.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check leakage.
Check deformation.
Check tightness of the bolts according to specifications.
Check that all grounding cables are securely connected.
Check for any damaged paint.
Check earthing switch.
Capacitor bushing tightness check.
Check for bushing cracks.
Check for proper termination.
Check CT locations physically.
3.42.3.2
ITEM
1.
2.
3.
4.
5.
6.
Electrical Tests
DESCRIPTION
Check of test and measuring instruments calibration certificates.
Check of condition of battery cells of the T&M instruments.
Check individual insulation resistances.
Measure each individual capacitance.
Capacitance bank insulation test.
Capacitance bank measurement test.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 93 of 124
3.42.4.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check for overall body deformation.
Check tightness of the bolts according to specifications.
Check that all grounding cables are securely connected.
Check for any damaged paint.
Check of foreign particles between the layers of the reactor
coils.
Check of any insulation cracks.
Check for proper termination.
Check CT locations physically.
3.42.4.2
ITEM
1.
2.
3.
4.
5.
Electrical Tests
DESCRIPTION
Check of condition of battery cells of the T&M instruments
Check main current path connection contact resistance.
Temperature measurement at different joints after energization.
Check the insulation resistance.
Inductance measurement between different cores.
REMARKS
3.42.5.1
ITEM
1.
2.
3.
4.
5.
6.
7.
DESCRIPTION
Inspect for physical damage or defects for entire system.
Check nameplate information for correctness and installation of
the cooling network according to the drawings.
Check for the redundancy of the fluid circulating pumps in the
cooling system.
Check pressure holding test on the expansion vessel/reservoir.
Check the pressure release valve and its operation on the
expansion vessel/reservoir.
Check the availability of nitrogen regulating system on the
expansion tank and ensure no leakage.
Check the Motor and pump for leveling and alignment.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
Page Number:
Page 94 of 124
ITEM
1.
T-PreCom-1000-R0
Electrical Tests
DESCRIPTION
Check of condition of battery of the T&M instruments.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 95 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 96 of 124
3.42.6.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that the connection does not transfer stress to the
connection terminal.
Check operation of the cooling fan.
Check that the filters for the cooling fan are not dirty..
All input and output cables are secure.
Fiber optics cables are secure without squeezing and without
severe bends.
All modules are properly labeled.
Check the panels are well ventilated with dust filter.
Check that the connection ports which are under use have dust
covers and all other unused ports should be sealed off.
Check that the connections ports are clearly and correctly
identified.
Check that the ferrules are properly marked.
Card locations are clearly numbered.
Sequence event recorder panel check.
Annunciator panel check.
Check the labeling on thyristor towers.
Check of proper extractor tool.
Panel lighting is operating properly.
Check that the panel heaters are not installed.
Check that the terminals are furnished with isolator links.
Check that the wire terminals have banana sockets for the
testing purposes.
Check that all grounding cables are securely connected.
Verification against drawings and contract specification.
3.42.6.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Electrical Tests
DESCRIPTION
Check of Test and Measuring instruments calibration
certificates.
Check of condition of battery cells of the T&M instruments.
Check of hardware.
Check of software.
Hardware jumpers check.
Micro console and PC with software check.
Check of user program loading.
Input and output operation check.
Test of light guides passing from controller to TCR towers.
Firing pulses tests to thyristors simulation.
Snubber circuit testing.
DC functional tests.
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 97 of 124
3.42.7.1
ITEM
1.
2.
3.
4.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that the connection does not transfer stress to the
connection terminal
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 98 of 124
Electrical Tests
DESCRIPTION
Check of Test and Measuring instruments calibration
certificates.
Check of condition of battery cells of the T&M instruments.
Test the protection relays related to transformer.
Test the protection relays related to HV CB.
Test the protections related to TCR and Harmonic Filters.
Check and test the modified schemes.
Check of alarms from the SVC local panel, and remote alarm in
the control panel and corresponding alarm to the Control
Center.
REMARKS
Electrical Tests
(Standard References are manufacturers instruction manual and SEC relevant Transmission
Standard))
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
DESCRIPTION
SVC pre-energization check list.
Check the SVC energization list.
Confirm the final settings.
Operation division shall issue caution for energization process.
Check and follow the switching program.
Check that the operating division has issued a warning to the
contractor for the Energization, copy to the Control Center.
Final NPS settings shall be issued to the Control Center,
Protection and Test and to 132/380 kV Projects Division.
Re-check and confirm final settings, except the settings of TCR
temperature, pressure, flow and VarMach.
Check, clean and lock transformer area.
Check, clean and lock disconnect room.
Check, clean and lock filter area.
Check, clean and lock TCR area.
Remove the firing optical fibers connected to the thyristor
valves, so that the thyristor valves are tested without
conduction. Red fibers only (16x3=48).
Check HV CB grounding switch opened from GIS.
Check bus isolator closed from control room.
Send close command to HV CB.
Check the indication on SER for CB closed.
Verify the synchronism by indication pulses generated from the
TCU (thyristor control unit).
Open the CB and close with H5h harmonic filter.
Check the bus voltage before and after the CB close and
calculate short circuit power of the network.
Record measurements on the mimic panel, and MVAR meter
should read 20 MVAR to confirm that the filter H5 is rated for -
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Page 99 of 124
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
TRANSMISSION
Pre-commissioning test procedure
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
General
Pre-Energization Checklist
With bus bar energized voltage response to VAR Control was checked.
Primary voltage according to existing metering: ________ kV
Input to Data Acquisition Computer measured:
Phase: R-Y: ________V
Y-B: ________V
B-R: ________V
VRESP: _______________
VRESPNOM: _______________
R-Y: ________V
Y-B: ________V
Y-B: ________V
B-R: ________V
B-R: ________V
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Energization of Filters
Page Number:
Performed: -----------
Energization of TCR
CT ration: _____________________
R-Y
Current
Y-B
B-R
Sec
Prim
Im = ___________ A
R-Y
Current
Y-B
B-R
Sec
Prim
Average measured values: Um = ___________ kV
Im = ___________ A
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Time
Time
Test with Max load on cooling system, SVC operated at __________ MVAR.
Ambient temp: __________
Time
9.
Increase and decrease ramp of control signals for all phases checked: -------------------
TCR No.: _____________
_____________
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Measurement of load-sharing:
TCR ________________
Load
10.
Ph. R
Ph. Y
TCR ________________
Ph. B
Ph. R
Ph. Y
Ph. B
_____________
Final parameter setting:
________________
ILIMLEV: ____________
Current limit
ILIMGAIN: ____________
Parameters corresponds to _______ A primary TCR current and __________ sec time constant
for the current limit operation.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Reactive Symmetry
Prim. Values
Q-tot Ph.
Prim. Values
Q-tot Ph.
b-c
c-a
b-c
c-a
b-c
c-a
Impedance ()
a-b
b-c
c-a
b-c
c-a
Impedance ()
a-b
b-c
c-a
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Static Characteristic
In: ________A
Bn: ________mS
SwitchPoint
U (kV)
SwitchPoint
U (kV)
I (A)
B (mS)
B (p. u.)
Name
Value
Parameter
I (A)
B (ms)
B (p. u.)
Name
Name
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
U (kV)
I (A)
B (ms)
B (p.u.)
Name
Value
____________ _____________
____________ _____________
____________ _____________
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
BREF
U (kV)
I (A)
B (ms)
B (p.u.)
Value
Name
Value
_______
_______
________
________
_______
_______
________
________
_______
_______
________
________
_______
_______
________
________
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
TFOL: ______________
BREFNOM: ____________
SLOPE: ____________
Measurement of slope:
Slope
(%)
Uprim
(kV)
Iprim
(A)
Slope
(%)
Uprim
(kV)
Iprim
(A)
Uprim - Uref
Uref
(value)
(kV)
Uref
(value)
(kV)
Uprim - Uref
(kV)
(value)
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
set __________%
T-PreCom-1000-R0
Page Number:
Measured ____________%
set __________%
Measured ____________%
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
VREGKI: _________
VREGNI: _________
1.
Minloss function:
Name
Value
Corresponds to
_________
__________
______________
_________
__________
______________
_________
__________
______________
_________
__________
______________
_________
__________
______________
MLOSSLEV: ___________
MLOSST: ____________
Name
__________
__________
______________
__________
__________
______________
__________
__________
______________
__________
__________
______________
__________
__________
______________
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
14.
Name
Value
Corresponds to
__________
__________
_______________
__________
__________
_______________
__________
__________
_______________
__________
__________
_______________
__________
__________
_______________
__________
__________
_______________
Redundancy Systems
It was checked that the SVC operates correct during the following change-overs to redundant functions.
Checked
To standby pump in cooling system: -----------------
___________________________:
-------------------------------------
________________________: ---------------------
___________________________: ------------------
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
Site Conditions
All the tools and equipment with valid calibration certificate shall be available at site.
3.
Documents
The following documents shall be available at site before start of SEC witnessing:
a.
b.
c.
d.
e.
4.
Approved drawings bearing very clear name and signature of the approving authority with
approval stamp on each sheet along with complete approval correspondence.
The manuals giving detailed test procedure of each equipment, technical data of all
electrical equipment, factory test records of all equipment, cable schedules, equipment
interconnection wiring schedule and wiring tables/diagrams.
SEC approved test procedure and test formats carrying approval stamp with name and
signature of the approving authority.
The project specifications and protection requirements.
List of deviations from SEC specs and SEC approval letters for the same.
Relay Settings
a.
b.
c.
d.
The contractor shall submit his proposed relay settings for all settable relays one month
before starting of pre-commissioning witnessing.
SEC-Engineering Protection Division shall provide final approved settings before precommissioning witnessing is started.
Pre-commissioning witnessing will not be started in the absence of approved relay
settings, in order to avoid re-setting.
Commissioning Program.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
5.
T-PreCom-1000-R0
Page Number:
e.
f.
A three-week testing program based on the approved overall program shall be submitted
every Tuesday indicating the proposed activities for the following two weeks and this
program will indicate activities completed in the current week and the reasons for not
completing any planned activity and its impact on the overall program with proposed
remedial measures.
Pre-commissioning Procedures
Pre-commissioning of all equipment shall be carried out in line with SEC Pre-commissioning Procedure
and in line with this agreement.
6.
7.
The contractor shall demonstrate a sample test for each equipment mentioned under (I-V) according to
the approved test procedure in presence of SEC-Commissioning Personnel and record the results on the
approved test format. If the SEC Commissioning personnel are satisfied with test procedures and results,
the contractor can complete the tests of the remaining equipment under (I-V) accordingly without SEC
present.
I.
II.
III.
IV.
V.
Secondary injection of all the aux. Relays, MCBs, Timers and O/C or E/F relay.
CTs magnetic curves.
AC/DC Distribution boards.
All VTs.
The contractor shall prepare the detailed test procedure and format to perform the
functional tests.
The contractor shall carry out on his own 100% functional tests for all relay panels, control panels, LCCs,
AVC panels and transformer-marshalling kiosk etc. The tests shall ensure the following:
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
All DC functional checks and the test results for the same shall be tabulated in special
formats and this format shall include the following items:
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
VI.
VII.
VIII.
IX.
X.
XI.
XII.
8.
The SEC witnessing personnel will select 20% of the equipment covered under I-IV and
the contractor will test all this equipment under SEC witnessing. SEC commissioning
personnel will sign only those test results which will be done under his presence.
SEC witnessing engineer/technician will do sample test by 20% of each type of panels
with minimum of 1 of each type. The contractor will carry out all the functional tests as
mentioned under V for these sample-selected panels under witnessing of SEC
commissioning personnel. SEC engineer will sign only those test results, which will be
done under his presence. SEC engineer has the right to witness complete bay in respect
of all panels, i.e., LCC, relay and control panels, etc.
Secondary injection of all main protection relays except O/C and E/F relays.
All indicating and recording meters.
All transducers.
Primary injection and stability and sensitivity test of all unit protections, i.e., BBP,
transformer differential and REF protection and underground cable protection, etc.
Final trip tests, closing tests, SCADA alarm tests. End to end tests, operation and
interlock checks and on-load tests, etc.
All tests relating to the fault recorder.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
Page Number:
10.
T-PreCom-1000-R0
The test record formats will be duly signed by the contractors testing engineer and SEC
Commissioning personnel simultaneously at the completion of formats for any test. No
formats shall be left unsigned for signing next day for quite obvious reasons.
SEC Commissioning personnel shall clear the snags after confirming satisfactory
completion and such clearance shall not be deferred to a later date in any case.
11.
The contractor will submit complete test record to SEC. This test record will include all the tests
conducted by the contractor on his own and all those tests conducted by him under SEC
witnessing.
12.
This agreement can also be applied by the contractor to other substations under the same contract.
13.
This agreement will be considered null and void at the end of Contract No. _________ and the
contractor will have to make a fresh agreement for any other contract/substation in the future.
For SEC
Names
PMD
CSD
Contract No.
Project Title.
Date:
S/S NAME/NUMBER
For Contractor
Signature
Names
Signature
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
The following items have to be confirmed at the end of the pre commissioning tests:
ITEMS
YES
NO
N/A
Further Remarks:
Contract No.
Contractor Name.
Project Title.
Substation Name/Number:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
EVALUTE THE CONTRACTORS PERFORMANCE NY CIRCLING APPROPRIATE NUMBER
UNSATISFAC
CATEGORY
VERY
GOOD
SATISFACTORY
NEEDS
TORY
GOOD
IMPROV.
QUALITY OF THE
25
21
19
15
11
WORK
AVAILBILTY Of
QUALIFIED
22
19
16
13
10
TESTING ENG.
PUNCTUALITY
20
17
15
12
9
SAFTEY
15
13
11
9
7
COOPERATION
10
9
7
6
5
AVAILABILITY OF
PROPER TOOLS
8
7
6
5
4
AND TEST
EQUIPMENT
1009279-68
6753-46
TOTAL POINTS
93
80
54
OVER ALL RATING
FURTHER REMARKS
( )
Evaluated By (Comm. Eng)
:
SIGNATURE:
NAME
DATE
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
SITE INSTRUCTION
ATTACHMENT No. 3
Page Number:
Circuit
Contract No
Project Title
Contractor Name
Attention Mr..
contractor
Issued by
SEC
Prepared by
Name
Sign
Job Title
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
REGISTER BOOK/FILE
DEFICIENCY FILE
ATTACHMENT No. 1
T-PreCom-1000-R0
Page Number:
Project Title:
Sr.#
Substation Name/Number:
Deficiency
Issued by
Issued
Date
Status
* Assigned
Punch list/
Snag No.
* Date of
assigning
Punch list/
Snag
* S.I #
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
Project Title:
Sr.#
Date
T-PreCom-1000-R0
Page Number:
Substation Name/Number :
Contractor
Witnessed
Engineer
by
Name
Remarks
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
CONTRACT #:
S/S NAME/NUMBER :
S.I.
#
Snag/
Punch
list No.
PROJECT TITLE:
DATE:
Issued Date
Issued By
Expected Time of
Completion by
Confirmed By
Commissioning
Personnel
Commissioning Eng.
Contractor
Name:
Name:
Name:
Signature:
Signature:
Signature:
Date:
Date:
Date:
To be filled by the Contractor
Remark
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART I
Title:
Index Number:
T-PreCom-1000-R0
Sr#
Initial
By
Date
Time Spent by
Comm. Personnel
Hrs
From To
.
Page Number:
Description of the
Job
Time
Lost
Hrs.
Time Lost
SEC
CSD
PMD
SOD
Others
Test
Equip
Contractors
Staff
Staff Others
Exper. NA
Remarks
TRANSMISSION
Pre-commissioning test procedure
PART I
Title:
Index Number:
T-PreCom-1000-R0
Page Number:
PROJECT TITLE:
DATE:
S/S NAME/NUMBER :
S.I. #
Snag/
Punch
list No.
Type of
Deficiency
A or B
Issued
Date
Issued By
Date to be
Completed by the
Contractor
Remarks
Contractor
Name:
Name:
Name:
Signature:
Signature:
Signature:
Date:
Date:
To be filled by Commissioning engineer/technician prior one month from the Energization.
Date:
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
Index Number:
Title:
Revision Number:
T-PreCom-1000-R0
Prepared By:
PRE-COMMISSIONING TEST
PROCEDURES FOR SEC
TRANSMISSION
ELECTRICAL INSTALLATIONS
00
Original Issue Date:
Pre-Commissioning Committee
Revised By:
2003-06-17
Revision Date:
Recommended By:
Page Number:
Mohammad S. AL-Rafaa
1 of 96
Approved By:
A.
INTRODUCTION
The check list is intended to provide information to commissioning engineer/technician who are
assigned to inspect the contractor work and witness commissioning testing on behalf of SEC to verify
that substation and transmission line equipment and system are acceptable as per SEC- standard and
specifications. The listing of commissioning checks and tests are based on the SEC- Commissioning
standard.(attachment#9)
ITEM NUMBER
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0
16.0
17.0
18.0
19.0
20.0
21.0
22.0
23.0
24.0
25.0
26.0
27.0
28.0
29.0
30.0
31.0
32.0
33.0
34.0
35.0
36.0
37.0
EQUIPMENT
Oil Filled Power Transformers
Shunt Reactors
Bushings Inspection and Testing
Surge Arrestors
Station Service Transformers
Neutral Earthing Resistors
Current Transformers
Potential Transformers
Capacitive Voltage Transformers
Coupling Capacitor Voltage Transformers
Gas Insulated Switchgear (GIS)
Metal Clad Switchgear
Metal Enclosed Bus Duct
Indoor and Outdoor Bus Structures
Indoor Circuit Breakers
Outdoor Circuit Breakers
Disconnect and Grounding Switches
Circuit Switchers
LV Switchgear (110/220 V)
230 kV and 380 kV XLPE Cables
230 kV and 380 kV LPOF Cables
110 kV, 115 kV and 132 kV XLPE Cables
110 kV, 115 kV and 132 kV LPOF Cables
69 kV XLPE Cables
13.8 kV and 33 kV XLPE Cables
LV Cables
Control Cables
Pilot Cables
Over Head Lines
Protection and Control
station Batteries
Battery Chargers
AC Distribution Panels
DC Distribution Panels
LVAC Auto-Transfer Schemes/Switches
Grounding Systems
Switchgear Air Compressor Systems
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
38.0
39.0
40.0
41.0
42.0
HVAC Systems
Dry Type Transformers
Fire Detection and Suppression Systems
Civil Work
Static VAR Compensation Systems
T-PreCom-1000-R0
Page Number:
Page 2 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
1.0
Page Number:
Page 3 of 96
1.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
DESCRIPTION
Check the impact recorder for any abnormal impact
during transit.
Check all components are installed.
Check for quality of paint, lifting lugs, quality of weld
areas, rust spots and wheel stoppers.
Check nameplates information (visible location) as
per contract specifications.
Check tightness of all bolts (torque wrench method).
Check that all grounding is securely connected (two
grounding connections to main tank are required).
Check that the piping to Buchholz relay has proper
slope.
Check that the tank pressure is positive, if
applicable.
Check that the valves between the main tank and
radiators are open.
Check the HV, LV and TV (if applicable) bushings for
damage and completeness.
Check for correct color and quantity of desiccant
(moisture absorbing media) in breathers. Check for
correct breather oil levels.
Check heaters and humidity meters in local panel
are at correct settings.
Check that phase marking in cable box matches with
GIS and cables.
Check all pipes, hoses and fan protection (not
rubber or plastic).
Check the vertical and horizontal clearances of live
parts to adjacent grounded points conform to
standard.
Check integrity of diaphragm/air bag in the
conservator.
Perform all of the manufacturers specific checks.
Check labeling of all auxiliary devices as per
approved drawing.
Check proper operation of auxiliary devices as
follows:
a.
Cooling fans/pumps (for all
settings).
b.
Tap changer (upperlowerout of
step and interlock).
c.
Oil level gauges.
d.
Top oil temperature gauges.
e.
Buchholz relay by gas injection.
f.
Winding temperature gauges.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 4 of 96
g.
20.
21.
22.
23.
24.
26.
27.
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
Electrical Tests
DESCRIPTION
Core Insulation Resistance Test.
Winding Insulation Resistance Test and Polarization
Index Test at 5 kV DC.
Winding Resistance Test (all taps).
Excitation Current measurements from primary side
at each tap during ratio test and from secondary side
when energized from secondary terminals keeping
primary side open or winding excitation current
measurement test at 10 kV during power factor
testing.
Insulation power factor and bushing test at 10 kV
AC.
Vector Relationship Test.
Winding temperature device test by heating the
sensor in oil bath and checking against standard
thermometer. Also check by current injection.
Setting as per approved drawing to be applied and
tested.
Oil temperature device to be calibrated by heating in
oil bath. Setting as per approved drawing to be
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
9.
10.
11
12.
13.
14.
15.
16.
17
T-PreCom-1000-R0
Page Number:
Page 5 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
b.
18.
19.
T-PreCom-1000-R0
Page Number:
Page 6 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
2.0
Page Number:
Page 7 of 96
Shunt Reactors
2.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
DESCRIPTION
Check the impact recorder for any abnormal impact
during transit.
Check all components are installed.
Check for quality of paint, lifting lugs, quality of weld
areas, rust spots and wheel stoppers.
Check nameplates information (visible location) as per
contract specifications.
Check tightness of all bolts (torque wrench method).
Check that all grounding is securely connected (two
grounding connections to main tank are required).
Check that the piping to Buchholz relay has proper slope.
Check that the tank pressure is positive, if applicable.
Check that the valves between the main tank and
radiators are open.
Check the bushings for any damage and completeness.
Check for correct color and quantity of desiccant
(moisture absorbing media) in breather. Check for correct
breather oil level.
Check heaters and humidity meters in local panel are at
correct settings.
Check that phase marking in cable box matches with GIS
and cables.
Check all pipes, hoses and fan protection (not rubber or
plastic).
Check the vertical and horizontal clearances of live parts
to adjacent grounded points conform to standard.
Check integrity of diaphragm/air bag in the conservator.
Perform all of the manufacturers specific checks.
Check labeling of all auxiliary devices as per approved
drawing.
Check proper operation of auxiliary devices as follows:
a.
Cooling fans/pumps (for all settings).
b.
Oil level gauges.
c.
Top oil temperature gauges.
d.
Buchholz relay by gas injection.
e.
Winding temperature gauges.
f.
Ensure correct operation of the
Pressure Relief Device microswitch.
g.
Push buttons and indicators.
h.
Oil sampling port (main tank).
i.
Upper and lower main tank valves.
Check oil leakage; if any noted, apply 0.35 kPa over
pressure for 24 hrs to make sure.
Check that the oil sampling valves for the main tank are
accessible from ground level.
Check oil level in main tank, conservator and bushings,
etc. Test the oil level gauges and their alarms.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
23.
24.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Page 8 of 96
ITEM
1.
Page Number:
Electrical Tests
DESCRIPTION
Core Insulation Resistance Test
Winding Insulation Resistance Measurement Test and
Polarization Index (P.I.) Test at 5 kV DC.
Winding Resistance Test.
Inductance Measurement.
Impedance Measurement.
Winding temperature device test by heating the sensor in oil
bath and checking against standard thermometer. Also check
by current injection. Setting as per approved drawing to be
applied and tested.
Oil temperature device to be calibrated by heating in oil bath.
Setting as per approved drawing to be applied and tested.
Insulation power factor and bushing test at 10 kV AC.
Bushing Current Transformer Tests:
a.
Polarity.
b.
Insulation Resistance.
c.
Secondary Winding Resistance (all windings
and all taps).
d.
Current Ratio (inject current)
e.
Magnetization Characteristics (minimum five
points below and two points above the knee
point).
f.
Verify secondary circuits, terminal to terminal.
g.
Burden Test.
Demagnetize CT cores after all tests. Ensure no open circuit on
CT secondary side.
Functional Checks for the Following:
a. Liquid level (alarm and trip).
b. Top Oil Temperature Device: fans/pumps
(stop, start alarm and trip).
c. Winding Temperature Device.
d. Buchholz Relay (alarm and trip).
e. Pressure Relief Device (alarm and trip)
Insulating Oil Tests:
Prior to energization, the contractor should submit insulating oil
test reports tested at an independent laboratory, for the
following:
a.
Dielectric Strength
i.
ASTM D 877 (2.5 mm gap) for unprocessed oil
ii.
ASTM D 1816 (1.0 mm gap) for oil in main
tank
b.
Neutralization Number (ASTM D 974)
c.
Interfacial Tension (ASTM D 971)
d.
Color (ASTM D 1500)
e.
Moisture Content (ASTM D 1533)
f.
Power Factor Test (ASTM D 924)
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
g.
h.
12.
T-PreCom-1000-R0
Page Number:
Page 9 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
3.0
Page Number:
Page 10 of 96
ITEM
1.
2.
3.
4.
5.
6.
7.
DESCRIPTION
Cleaning the insulator surface.
Check for tightness test between transformer and bushing
flange and outer terminal.
Visually inspect for any damage or cracks.
Check for leakage.
Check and adjust of oil level. Note that adding insulating oil to a
bushing shall be done under vacuum.
Measurement of capacitance and tan delta. The bushing shall
be tested in a vertical position and the lower portion set into an
oil reservoir.
Check of through resistance.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
4.0
Page Number:
Page 11 of 96
Surge Arrestors
4.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque wrench
method).
For multi-unit stacks, check that the physical arrangement of the
units are erected according to the manufacturers specifications.
Check that all grounding cables are correctly and secured
connected.
Check name plate information for correctness as per SECs
specifications.
Check that impulse counter and leakage current meter glasses
are not broken or cracked.
4.2
ITEM
1.
2.
3.
REMARKS
Electrical Tests
DESCRIPTION
Check calibration of leakage current meters.
Insulation resistance test at 5 kV DC.
Power factor test at 10 kV AC.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
5.0
Page Number:
Page 12 of 96
5.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Check the Impact recorder for any abnormal impacts during
transit (if applicable).
Check earthing, color, painting, external damage, oil leakage,
wheel stopper, cable connection and bolt tightness, etc.
Check nameplate data against contract specifications.
Perform all special checks according to the manufacturers
instructions.
Check oil level in HV side cable box and its oil level indicator or
HV fuses.
Check all devices are labeled correctly as per drawing.
5.2
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Check LV side MCB setting as per transformer current rating
Ratio Test (all taps), Insulation resistance measurement test on
2.
all windings and polarization index (P.I.) test.
3.
Polarity and Vector Group symbols confirmation Test.
4.
Check oil level and its indicator alarms.
5.
Check oil temperature gauge by oil bath method and its alarms.
Check LV and HV side phases match with the LV bus bar
6.
phasing in the distribution panels and with the main transformer
phases.
7.
Check phasing at the automatic transfer switch (as applicable )
8.
Winding resistance measurement (at all taps).
9.
Excitation current test (all taps).
10. Back energization test at rated voltage for 15 minutes.
Check that the off load tap changer is set at the nominal voltage
11.
tap.
12. Perform functional tests of all auxiliary devices (as applicable )
Insulating Oil Tests:
Prior to energization, the contractor should submit insulating oil
test reports tested at an independent laboratory, for the
following:
.
Dielectric Strength
i.
ASTM D 877 (2.5 mm gap) for unprocessed oil
ii.
ASTM D 1816 (1.0 mm gap) for oil in main
13.
tank
b.
Neutralization Number (ASTM D 974)
c.
Interfacial Tension (ASTM D 971)
d.
Color (ASTM D 1500)
e.
Moisture Content (ASTM D 1533)
f.
Power Factor Test (ASTM D 924)
g.
Dissolved Gas in Oil Analysis (ASTM D3 612)
(Dielectric Dissipation Factor, Resistivity, Sediment
h.
ITEM
1.
DONE
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
and/or Precipitable Sludge).
Another oil sample shall be given to SEC transmission for their
own analysis and comparison purposes. . A syringe oil sample
shall be taken by contractor.
T-PreCom-1000-R0
Page Number:
Page 13 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
6.0
Page Number:
Page 14 of 96
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Check the value of resistance and current ratings against
specifications.
Check that the external earth connection to main earth is copper
wire at least 240 mm2 in size.
Test NER HV side associated CT and power cable.
Visually inspect the interior for broken insulators.
Measure the main circuit resistance.
Insulation Resistance Test.
Ensure that the interior and exterior of the NER is clean prior to
energization.
Check identification and function of NER isolator (if applicable).
DONE
REMARKS
>=1000 megaohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
7.0
Page Number:
Page 15 of 96
Current Transformers
Note that Bushing current transformer tests and inspections are covered in the sections relating to the
equipment into which they are installed.
7.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check that outdoor secondary wiring terminations are installed
in moisture proof enclosures.
Check tightness of all bolted connections (torque wrench
method).
Check that all grounding cables are securely connected.
Check secondary wiring is correctly color coded and size of
wires is as specified.
Check proper lugs have been used on terminations.
Check CT locations physically and secondary terminal labeling
has been done correctly.
7.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
8.0
Page Number:
Page 16 of 96
Potential Transformers
8.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connection.
Check that the HV connection does not transfer stress to the HV
terminal.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolation and grounding devices (as applicable).
Check integrity of primary fuses (if applicable).
Check insulation liquid level (if applicable).
Gas leakage check for GIS VTs.
8.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
REMARKS
Electrical Tests
DESCRIPTION
Winding Resistance Test.
Insulation resistance tests HV TO G, LV TO G
and HV TO LV using a one kV insulation tester.
Ratio Test.
Polarity Test.
Primary and secondary fuses rating checks for
11 kV VTs and above (if applicable).
Ensure VT is included in switchgear and GIS
high voltage test.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 17 of 96
TABLE 1
SYSTEM
RATED
VOLTAGE
(KV)
11
13.8
33
69
110
115
132
230
380
RATED
LOAD
FACTOR
VOLTAGE
(KV)
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
1.5
9.5
12
28
60
95
99.5
114
199
329
DONE
TEST
FREQUENCY
60 Hz
TIME PERIOD
I Minute
REMARKS
These tests
are applicable
to
electromagneti
c VTs
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
9.0
Page Number:
Page 18 of 96
9.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolation and grounding devices (as applicable).
Check oil level (if applicable).
Check for oil leakage.
Check electromagnetic unit spark gaps for correct setting (if
applicable).
Check drain coils (if applicable).
9.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
10.0
Page Number:
Page 19 of 96
10.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that all grounding cables are securely connected.
Check mechanical clearances and proper operation of all
isolating, grounding and shorting devices (as applicable).
Check electromagnetic unit spark gaps for correct setting (if
applicable).
Check drain coil unit spark gaps for correct setting (if
applicable).
Check wave trap mechanical assembly, bird screens, etc.
10.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
11.0
Page Number:
Page 20 of 96
11.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Inspect enclosures for proper alignment and
foundation fixing and grounding.
Check quality of paintwork.
Ensure that all special tools and equipment are
provided as specified and have proper storage.
Ensure that gas-handling cart (if provided) operates
correctly and that special filling and degassing fittings
are provided and have proper storage.
Verify that all lifting devices are correctly labeled for
lifting capability.
Ensure that adequate ladders and walkways are
provided for access to meters, filling ports, cranes,
lights, etc.
Check and verify that all grounding of GIS is as per
approved layout drawings and specification and is
securely connected.
Check that all specified grounding switches are
insulated, with removable grounding links.
Check operation of all mechanical interlocks.
Check tightness of all bolted connections (torque
wrench method).
Check each gas section filled to correct rated
pressure.
Check SF6 gas at each gas section for air and
moisture content after filling at rated pressure.
15.
16.
17.
18.
19.
20.
DONE
REMARKS
Permissible Dew
Point is -35 C or
lower.
Wrap all joints with
sealed plastic
sheeting and test
for gas leakage
after 24 hours.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
21.
22.
23.
24.
25.
27.
28.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Page 21 of 96
ITEM
1.
Page Number:
Electrical Tests
DESCRIPTION
Insulation resistance test for all low voltage wiring and
cabling.
Functional test of all controls and interlocks.
Resistance of all ground connection joints at 100 A
DC.
Resistance of bus joints at 100 amperes DC.
Overall resistance of the main circuit.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
11.
12.
13.
14.
15.
16.
17.
I.
Page Number:
Page 22 of 96
AC HV tests on main circuit of GIS are performed with all CBs and disconnect switches in the closed position
at 80% of the factory routine test voltage for one minute. Partial discharge measurements (If applicable and
possible to be performed) are performed at 1.2 X Un (Un = phase to neutral voltage).
II.
Check and confirm following points and condition to be met before high voltage tests.
i.
ii.
iii.
iv.
v.
vi.
The Switchgear shall be erected completely and filled with gas at rated pressure.
Some part may be disconnected before test, such as:
High Voltage cables and overhead lines.
Power transformer and most voltage transformers.
Surge arrestors and protective spark gaps.
Current transformer secondary windings should be shorted and grounded.
Every newly erected part of GIS shall be tested with high voltage.
The test should be performed at rated frequency (60 Hz.). If such arrangement is not
possible, then the frequency should be limited to the range of 30 to 300 Hz.
AC voltage tests are sensitive in detecting contamination and abnormal field configuration.
Tests with switching impulse voltages are useful especially for high rated voltage to detect the
presence of contamination as well as abnormal field configuration
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
III.
T-PreCom-1000-R0
Page Number:
Page 23 of 96
Contractor can adopt one of the two procedures A or B to perform high voltage test on GIS after erection at
site
i.
Procedure A
Site AC test voltage level shall be equal to the 80% of the factory routine test voltage.
This test may be performed through series resonance method
Or by a test transformer with sufficient capacity. PD measurements are possible to be measured in
this case at test voltage level = 1.2 Un (Un = phase to neutral rated voltage) during the HV
Test process.
Electrical conditioning at voltage equal to U/3
for longer period such as 30 minutes may be
performed to move and trap the contamination in areas where they become harmless.
Partial discharge measurements may be helpful in detecting some kind of faults.
ii.
Procedure (B)
a.
Site AC test voltage level equal to 1.2 Un for 5 minutes followed by Impulse Voltage test at a
test level equal to 64% of the rated lightening impulse withstand level specified in IEC-517.
Three positive and three negative polarity impulses shall be applied.
b.
In case the GIS VTs are not suitable to be used as test transformer; a special voltage
transformer shall be used to perform such tests. GIS VT can only be used as a test
transformer if the manufacturer guarantees its safety and capability to perform such tests
otherwise it shall not be used as a test source.
IV.
Sometime in extension projects due to practical and technical reason of joining new and old GIS together, the
test may be performed at reduced voltage level for an extended duration subject to agreement between SEC
and supplier.
V.
Assessment of Tests
i.
ii.
iii.
iv.
VI.
Test is considered passed if no disruptive discharge occurs during the test period.
If disruptive discharge occurs in solid insulation, the compartment should be opened and
repaired. After fault repair, again, test with full site test voltage.
If disruptive discharge occurs in gas, the test may be repeated and if discharge again takes
place, then compartment should be opened to clean out the compartment.
If the discharge occurs and second time it disappears, it should be considered acceptable
after repeating one test more at full site test voltage mentioned in Table 1.
Test may be repeated several times to listen and locate the location of fault point subject to the agreement
between SEC and Contractor.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
T-PreCom-1000-R0
Page Number:
Page 24 of 96
Table-1 on the next page describes the exact test voltage levels, time and kind of tests to be applied after
erection of GIS at site.
i.
For 132 kV GIS the test voltage shall be 220 kV AC 60 Hz for one minute as per Procedure A
clause 7.107.1.5 of IEC 517- 1990
ii.
For 380 kV GIS and GIBs shall be 416 kV AC 60 Hz for one minute as per procedure A
clause 7.107.1.5 of IEC 517-1990.
iii.
In case of procedure B as per clause 7.107.1.5 of IEC 517-1990 the test voltage for 132 kV
rated GIS shall be 84 kV AC for 5 minutes and followed by 416 kV Impulses of three positive
and three negative polarities.
iv.
In case of procedure B to be applied for high voltage tests on 132 kV GIS special VT should
be used as Test voltage source. GIS VTs shall not be used as HV test voltage source.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 25 of 96
13.8
10 kV for 10
min.
33
22 kV for 15
min.
69
69
110
110
115
115
132
44 kV for 30
min.
84 kV for 30
min.
84 kV for 30
min.
84 kV for 30
min.
30
60 Hz
1 min.
56
60 Hz
1 min.
128
44
220
84
220
60 Hz.
or 10300 Hz.
60 Hz.
60 Hz.
or 10300 Hz.
60 Hz.
60 Hz.
or 10300 Hz.
84
60 Hz.
220
60 Hz.
or 10300 Hz.
1 min.
5 min.
1 min.
5 min.
1 min.
5 min.
1 min.
248 kV
3
positive
3
negative
416 kV
3
positive
3
negative
416 kV
3
positive
3
negative
REMARKS
Partial
Discharge
Measure
No. Of
Impulses
Swing or
Switching.
Impulse level
Time Of
AC Test
Voltage
Freq.
Of Test
Voltage
AC Test
Voltage
kV
Electrical
Conditioning
System Rated
Voltage
KV
Method
No.
Table 1. Test Voltage Levels for Metal-Enclosed Gas Filled Switchgear (GIS)
Leakage
current
< 1000
mA
Leakage
current
< 0.86
mA
At 48 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
At 92 kV
less than
10 pC
Electrical
conditioni
ng is a
cleaning
process
only.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
132
230
142 kV
for 30
min.
230
380
245 kV
for 30 min.
84
316
142
416
60 Hz.
10-300
Hz.
Better
60 Hz.
10-300
Hz.
Better at
60 Hz.
10-300
Hz.
Better at
60 Hz.
Page Number:
Page 26 of 96
5 min.
416 kV
3
positive
3
negative
1 min.
608 kV
3
positive
3
negative
5 min.
1 min.
840 kV
3
positive
3
negative
PD or HF
detection
techniques
to be
applied
Impulse
test is
applied
in
special
cases
only
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
12.0
Page Number:
Page 27 of 96
12.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Inspect enclosures for proper alignment, foundation fixing and
grounding and vermin proofing.
Inspect all covers, panels section and doors for paint work and
proper fit.
Check for smooth and proper movement of racking mechanisms
for alignment, shutters, rollers, rails and guides.
Check for proper alignment of the breaker primary and
secondary contacts.
Check operation of all mechanical interlocks.
Check tightness of all bolted connections (torque wrench
method).
Check bus and supports for defects such as cracked welds,
chipped porcelain, cracked insulation, etc., and free from dust
accumulation.
Check main and riser buses for correct phasing.
Verify that all front panel mounted devices (meters, push
buttons, switches, indicator lamps, mimic buses, etc.) are
installed as per drawings.
Perform mechanical checks and visual inspection on all circuit
breakers.
Perform mechanical checks and visual inspection on all current
transformers.
Perform mechanical checks and visual inspection on all voltage
transformers.
Perform mechanical check and visual inspection on all
disconnect and grounding switches.
Check for correct breaker position indication.
Check for correct spring status indication (spring
charged/discharged).
For air magnetic breakers check the arc chutes for damage and
correct positioning above the interrupter contacts.
For minimum oil breakers, check correct oil level in each pole.
For SF6 breakers, check the correct gas pressure, quality and
leakage where possible.
For SF6 breakers, check the operation of the gas density switch
(alarm and lockout functions).
Perform all specific checks on the breaker and spring operating
mechanism according to the manufactures instructions.
Check that all control wiring is correct according to the approved
drawing and terminal connections are secure.
Check all wiring is correct according to approved drawings.
Check that all phase marking have been installed per
specifications.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
27.
28.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Page 28 of 96
ITEM
1.
2.
3.
4.
Page Number:
Electrical Tests
DESCRIPTION
Insulation resistance test of all circuits in the panels.
Functional test of all controls and interlocks.
Bus continuity and phasing test.
Main Circuit Resistance Test with the switchgear
erected but not yet connected to the cables.
Performed with 10 or 100 Ampere DC by microohmmeter from panel to panel on each phase from
cable spouts with all circuit breakers racked in service
and in the on position.
Check all AC/DC MCBS in the panel for correct
ratings and grading. Trip test by current injection for
one point on curve.
Insulation resistance test at 5 kV DC on all main
circuits between phase to phase and phase to ground
(before HV test).
Perform electrical tests on all component equipment
as per SEC approved procedures:
a.
Circuit breakers.
b.
Current transformers.
c.
Voltage transformers.
d.
Disconnect and grounding switches.
Ensure the cable spouts are included in the high
voltage tests.
Insulation test on all wiring at 500 V DC.
Functional test of all electrical interlocks.
Functional test of trip free and anti pump circuits.
Functional test of local alarm and indications.
Functional test of remote alarm and indications.
Minimum control voltage trip and close operations.
Check and test capacitor trip circuit (if applicable).
Check spring charge time and motor currents at rated
control voltage.
Functional check of thermostat and space heaters,
measure heater current.
Functional check of breaker operation counter.
Timing test open/close using an electronic
oscillograph.
For SF6 breakers, verify electrically the low gas
pressure alarm and lockout functions.
For minimum oil breakers, test insulating oil for
dielectric strength according to ASTM D 877 (with 2.5
mm gap).
Check correct operation of all auxiliary a and b
contacts (for breaker open/closed position).
DONE
REMARKS
500 V DC
The resistance values from panel to
panel should vary no more than 15%.
Compare the measured resistance
values with factory test results, and
shall be within +/- 20% of factory test
results.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
T-PreCom-1000-R0
Page Number:
Page 29 of 96
ii.
For vacuum breakers, test across open contact and live parts to ground. Precautions shall be
taken against emission of X-rays.
For all other breakers. Test in conjunction with breaker racked in the switchgear and in the
closed position.
iii.
Voltage shall be applied on each phase with all other phases and then frame grounded.
Tests shall be performed with the CB in both the closed and open position
In the open position, the cable contacts are to be grounded.
Test voltage levels are given in Table 2 below.
After the high voltage test on main circuit is finished, rack the voltage transformers in service
position and apply a test voltage on the primary side equal to 1.5Un (Un = phase to neutral rated
voltage) on each phase consecutively and measure the secondary output voltage same time during
the test.
Make sure the VTs secondary side MCBs are switched off and any resistor in open delta winding
should have been removed.
Compare the observed ratio with actual ratio.
The HV Test should be repeated with circuit breakers in open position keeping cable spouts in
earthed condition in all panels.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 30 of 96
SWITCHGEAR RATINGS
AC TEST VOLTAGE
TIME PERIOD
11 kV
25 kV 60 Hz
60 Sec
13.8 kV
30 kV 60 Hz
60 Sec
33 and 34.5 kV
56 kV 60 Hz
60 Sec
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
13.0
Page Number:
Page 31 of 96
13.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
DESCRIPTION
Inspect for physical damage or defects.
Check bus arrangement for conformance with approved
drawings.
Check tightness of all bolted connections (torque wrench
method).
Check that all enclosure grounding is securely connected.
Inspect internal compartments for cleanliness (free from dust
and moisture).
Check for watertight seals at joints including expanding
interface points.
Check bus conductor support insulators for cracked insulation,
chipped porcelain, etc.
Check quality of paint work (inside and outside).
Check that ventilation opening are not blocked, and meet
specified Degree of Protection.
Moisture drain holes available at bottom of enclosure.
Check anti-condensation heaters mounted at the correct
locations (bottom)
13.2
DONE
REMARKS
DONE
REMARKS
Electrical Tests
ITEM
1.
2.
3.
DESCRIPTION
Perform phasing checks. Ensure correct phase identification.
Perform continuity check.
Bus joint resistance test.
4.
5.
6.
Ductor at
100 A DC
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
14.0
Page Number:
Page 32 of 96
14.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect bus and support insulators for physical damage or
defects.
Check bus physical arrangement for conformance with
approved drawings.
Check bus connections for correct phasing and marking of
phases.
Check tightness of all bolted connections (torque wrench
method).
Check for proper phase to phase and phase to ground
clearances.
Ensure that PT, etc., connections are flexible, to prevent
transferring expansion stress from the bus
14.2
ITEM
1.
2.
3.
REMARKS
DONE
REMARKS
Ductor at t 100
A DC.
Electrical Tests
DESCRIPTION
Measure resistance of bus section joints.
Insulation resistance test at 5 kV DC.
HV test (indoor bus work including PTs where applicable, 69 kV
and below).
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
15.0
Page Number:
Page 33 of 96
15.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
DESCRIPTION
Inspect bus for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections (torque wrench
method).
Check all wiring is correct according to approved drawings and
that terminal connections are secure.
Check quality of paintwork.
Check that all grounding cables are securely connected.
Check breaker truck, rails, for proper alignment and smooth
movement.
Check operation of all mechanical interlocks with associated
disconnects, grounding switches, racking truck mechanism,
cubicle doors, etc.
Check for correct breaker position indication (breaker
open/closed).
For minimum oil circuit breakers, check for correct oil level in
each pole.
For SF6 breakers:
a.
Check for correct SF6 pressure in each pole.
b.
Check for gas leakage.
c.
Calibrate SF6 pressure gauge.
d.
Check operation of gas density switch (alarm
and lockout functions).
e.
Verify that all special filling adapters have
been provided.
For motor/spring operation mechanisms:
a.
Check manual spring charge operation.
b.
Verify correct spring status indication (spring
charged/discharged).
c.
Perform all specific checks on the mechanism
according to the manufactures instructions.
For pneumatic operating mechanisms(69KV and above):
a.
Check the compressor, air piping, valves,
pressure gauges, air filter, water trap and
switches for damage, defects or blockage.
b.
Calibrate the air pressure gauges.
c.
Check the setting of air pressure switches
(compressor start/stop, alarm, lockout).
d.
Perform all specific checks on the
compressed air system according to the
manufacturers instructions.
e.
Check for correct direction of compressor
rotation.
f.
Check air-charging time.
g.
Check safety relief valve operating pressure
and resetting pressure.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 34 of 96
h.
14.
15.
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Electrical Tests
DESCRIPTION
Measure resistance of main conducting circuits at 100 A DC.
Insulation resistance test of each breaker pole at 5 kV DC.
Insulation resistance test of all low voltage wiring and cabling.
Functional test of all electrical interlocks.
Functional check of trip free and anti pump circuits.
Functional check of phase disagreement protection circuit
(applicable to breakers whose poles are not mechanically gang
operated).
Functional check of local control, alarm and indications.
Functional check of remote control, alarm and indications.
Minimum control voltage trip and close operation.
Functional check of breaker operation counter.
Functional check of thermostat and space heaters, and
measurement of heater current.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
12.
13.
14.
15.
16.
17.
18.
T-PreCom-1000-R0
Page Number:
Page 35 of 96
ASTM D
877(with
2.5 mm
gap)
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
16.0
Page Number:
Page 36 of 96
16.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections (torque wrench
method).
Check all wiring is correct according to approved drawings and
that terminal connections are secure.
Check quality of paintwork.
Check that all grounding cables are securely connected.
Check for correct breaker position indication (breaker
open/closed).
For SF6 breakers:
a.
Check for correct SF6 pressure in each pole.
b.
Check for gas leakage.
c.
Calibrate SF6 pressure gauge.
d.
Check operation of gas density switch (alarm
and lockout functions).
e.
Check air and moisture content of SF6 gas in
breaker.
For motor/spring operation mechanisms:
a.
Check manual spring charge operation.
b.
Verify correct spring status indication (spring
charged/discharged).
c.
Perform all specific checks on the mechanism
according to the manufactures instructions.
For pneumatic operating mechanisms:
a.
Check the compressor, air piping, valves,
pressure gauges, air filter, water trap and
switches for damage or defects.
b.
Calibrate the air pressure gauges.
c.
Check the setting of air pressure switches
(compressor start/stop, alarm, lockout).
d.
Perform all specific checks on the
compressed air system according to the
manufacturers instructions.
e.
Check for correct direction of compressor
rotation.
f.
Check air-charging time.
g.
Check safety relief valve operating pressure
and resetting pressure.
h.
Measure air consumption for C, O, CO and
OCO operations.
i.
Air storage test, perform as specified, the
following without replenishment: 5X CO, or O
+ CO + 3min. + CO
j.
Air leakage test (pressure drop method over
24 hours, CB closed and open).
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
11.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Page 37 of 96
ITEM
1.
2.
3.
4.
5.
6.
Page Number:
Electrical Tests
DESCRIPTION
Measure resistance of main conducting circuits at 100 A DC.
Insulation resistance test of each breakers pole at 5 kV DC.
Insulation resistance test of all low voltage wiring and cabling.
Functional test of all electrical interlocks.
Functional check of trip free and anti pump circuits.
Functional check of phase disagreement protection circuit
(applicable to breakers whose poles are not mechanically gang
operated).
Functional check of local control, alarm and indications.
Functional check of remote control, alarm and indications.
Minimum control voltage trip and close operation.
Functional check of breaker operation counter.
Functional check of thermostat and space heaters, and
measurement of heater current.
Check correct operation of all auxiliary a and b contacts (for
breaker open/closed positions).
Timing test using an electronic oscillograph.
For SF6 breakers, verify electrically the low gas pressure alarm
and lockout functions.
For minimum oil circuit breakers, test insulating oil for dielectric
strength.
For bulk oil breakers:
a.
Test insulating oil for dielectric strength and
water content.
DONE
REMARKS
ASTM D 877
(with 2.5 mm
gap)
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
i.
17.
18.
19.
20.
21.
T-PreCom-1000-R0
Page Number:
Page 38 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
17.0
Page Number:
Page 39 of 96
17.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check quality of galvanizing (if applicable).
Check tightness of all bolted connections (torque wrench
method).
Check smoothness and ease of operation (both closing and
opening).
Check simultaneity and synchronism of all 3 poles during
closing.
Check for proper contact, fingers spread and contact pressure
in fully closed position.
Check that end of travel stops are correctly adjusted, set and
locked in position.
Check open gap and minimum clearance between phases and
to ground
Check switch opens more than 90 (for horizontally mounted
vertical open disconnects).
Check switch drive linking toggled in both the closed and
opened positions.
Check that switch can be pad locked in both the closed and
opened positions.
Check that all grounding is securely connected.
Check that switch-operating handle is grounded properly as
specified.
Check mechanical interlocks (with grounding switches, CBs,
etc.).
Check that the operators platform is of adequate size and is
properly grounded.
17.2
ITEM
1.
2.
3.
4.
REMARKS
Electrical Tests
DESCRIPTION
Measure resistance of main current path (terminal
to terminal) at 100 A DC.
Functional test of all electrical interlocks.
Check position-signaling contacts (if applicable).
For motor operated mechanisms:
a.
Check mechanism cabinet is
grounded.
b.
Check correct setting of motor limit
switched (open/close).
c.
Check correct operation of all
auxiliary a and b contacts.
d.
Measure switch opening and
closing times and motor current at
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
5.
T-PreCom-1000-R0
Page Number:
Page 40 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
18.0
Page Number:
Page 41 of 96
Circuit Switchers
18.1
ITEM
1.
2.
3.
4.
DESCRIPTION
Perform mechanical checks and inspection of
isolating disconnect, as per Section 3.17.1, above.
Perform mechanical checks and adjustments on
interrupter unit according to the manufacturers
instructions.
Check the low SF6 target at the interrupter units.
Check interrupter position indicator operation.
18.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Resistance of main current path (terminal to
terminal) at 100 Amps DC.
Functional check of all electrical interlocks.
Check position-signaling contacts (if applicable).
For motor operating mechanisms:
a. Check mechanism cabinet properly
grounded.
b. Check correct setting of motor limit
switched (open/close).
c. Check correct operation of all auxiliary
a and b contacts.
d. Measure switch opening and closing
times and motor current at rated
voltage (for fast acting disconnects
and grounding switches, perform a
timing test with an electronic
oscillograph).
e. Minimum voltage operation (close and
open) at 90V DC.
f.
Functional check of thermostat and
space heaters. Measure heater
current.
g. Insulation test all control and power
wiring/cables at 500V DC
h. Check that in the manual mode,
insertion of the operating handle
automatically disconnects the motor
DC supply.
Check shunt trip device operation.
Verify proper operation sequence of interrupters
and disconnects.
Insulation power factor test of the interrupters.
Timing test of the interrupter contacts with electronic
oscillograph.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
19.0
Page Number:
Page 42 of 96
LV Switchgear (110/220 V)
19.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
Main circuits Continuity Test for tightness of joints
and bolts.
Main circuit insulation resistance measurement
by 2.5 kV Megger or 2 kV AC HV test for one
minute.
Phasing check.
Check and verify for all MCCBs ratings as per
requirement and Trip Test by current injection.
All ammeters and volt meters shall be calibrated.
Insulation Test on all secondary wiring and
cables.
Tests on changeover schemes as per approved
drawings if applicable.
Confirm the neutral cable coming from auxiliary
transformer is grounded in the LV distribution
board.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
20.0
Page Number:
Page 43 of 96
20.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque
wrench method).
Check for proper cable bolted connections.
Check for proper cable support, clamping, trays,
blocking.
Check cable bends to ensure that bending radius is
equal to or greater than the minimum bending radius
specified.
Link box tightness check.
Verify that shields are terminated as specified
(through link box or directly grounded).
Verification of exact route length from termination to
termination as per approved drawings.
Check that all grounding points are securely
connected to ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power
transformer and switchgear shall be single point
earthed at switchgear side and at floating side SVL
(sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter
as per approved design.
Check cable entry path trench as ducts are to be
properly sealed.
For accessories (sealing terminations, instrument
panels and link boxes), check the following as
applicable:
a.
Nameplates installed and data is
correct.
b.
Condition of paint work.
c.
All bolted connections.
20.2
ITEM
1.
2.
3.
4.
5.
REMARKS
Electrical Tests
DESCRIPTION
Phase checking for conductor and sheath
bonding in every link box.
Conductor resistance, capacitance and
inductance measurement test.
Sheath DC high voltage test (10 kV for 1 minute)
and 5 kV DC insulation tester before and after
high voltage test.
Anti corrosion sheath test.
Measure the ground resistance at all link box
DONE
REMARKS
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
6.
7.
8.
9.
10.
11.
12.
13.
14.
positions.
Zero and positive sequence impedance
measurement.
SVL (sheath voltage limiter) test with 2.5 kV DC
insulation tester.
Insulation resistance test of cable by 5 kV DC.
Cross bonding verification test.
Contact resistance test on link boxes (less than
20 ).
Metallic sheath continuity test (if applicable).
Cable jacket test.
Cable profile test.
AC High voltage test.
T-PreCom-1000-R0
Page Number:
Page 44 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
21.0
Page Number:
Page 45 of 96
21.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque
wrench method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is
equal to or greater than the minimum bending radius
specified.
Check for proper cable support, clamping, trays and
blocking.
Verify that shields are terminated as specified
(through link box or directly grounded).
Verification of exact route length as per approved
drawings from termination to termination.
Check that all grounding points are securely
connected to ground grid as specified.
Pressure test of all associated oil piping.
Check that phases are identified and color coded.
Single core cable connected between power
transformer and switchgear shall be single point
earthed at switchgear side and at floating side SVL
(sheath voltage limiter) should be installed.
Availability of oil sampling facility valve arrangement.
Check single point or both ends, via voltage limiter
as per approved design.
Check cable entry path trench as ducts are to be
properly sealed.
Oil flow test.
Impregnation test.
RGP test and DGA tests.
For accessories (sealing terminations, pressure
tank, gauges, instrument panels and link boxes),
cheek the following as applicable:
a. Nameplates installed and data is
correct.
b. All valve positions according to
design (open/closed).
c. Calibrate pressure gauges and
pressure switches.
d. Oil pressure.
e. No oil leaks.
f.
Condition of paint work.
g. All bolted connections.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
21.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Page Number:
Page 46 of 96
Electrical Tests
DESCRIPTION
Check Phasing for conductor and sheath bonding
in every link box
Conductor resistance, capacitance and
inductance measurement test.
Sheath DC high voltage test (10 kV for 1 minute)
and 5 kV DC insulation tester before and after
high voltage.
SVL (surge voltage limiter)test by 2.5 kV DC
insulation tester.
Anti corrosion sheath test.
Measure the ground resistance at all link box
positions (less than 10 ).
Zero and positive sequence impedance
measurement.
Insulation resistance test for conductor.
Cross bonding verification test.
Contact resistance test on link boxes.
Oil pressure gauge function test.
Shield continuity test.
Cable Jacket test.
Cable profile test.
Insulation oil dielectric breakdown test and water
content test.
AC High voltage test.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
22.0
Page Number:
Page 47 of 96
22.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque
wrench method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is
equal to or greater than the minimum bending radius
specified.
Check for proper cable support, clamping, trays,
blocking.
Link box tightness check.
Verify that shields are terminated as specified
(through link box or directly grounded).
Verification of exact route length as per approved
drawings from termination to termination.
Check that all grounding points are securely
connected to ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power
transformer and switchgear shall be single point
earthed at switchgear side and at floating side SVL
(sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter
as per approved design.
Inspection of label inside link boxes and water
proofing test.
Check cable entry path trench as ducts are to be
properly sealed.
For accessories (sealing terminations, instrument
panels and link boxes), cheek the following as
applicable:
a.
Nameplates installed and data is
correct.
b.
Condition of paint work
c.
All bolted connections
22.2
ITEM
1.
2.
3.
REMARKS
Electrical Tests
DESCRIPTION
Check phasing for conductor and sheath bonding
in every link box.
Sheath DC high voltage test and 5 kV DC
insulation tester before and after high voltage
test.
Conductor resistance, capacitance and
inductance measurement test.
DONE
REMARKS
10 kV for 1 minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
T-PreCom-1000-R0
Page Number:
Page 48 of 96
Sheath Current < 3 %
less than 10
less than 20
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
23.0
Page Number:
Page 49 of 96
(Standard Reference is IEC 60141-1, -2, -3 and relevant SEC Transmission Specifications)
23.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque
wrench method).
Check for proper cable bolted connections.
Check for proper cable support, clamping ,trays,
blocking.
Check cable bends to ensure that bending radius is
equal to or greater than the minimum bending radius
specified.
Verify that shields are terminated as specified
(through link box or directly grounded).
Verification of exact route length as per approved
drawings from termination to termination.
Check that all grounding points are securely
connected to ground grid as specified.
Pressure test of all associated oil piping.
Check that phases are identified and color coded.
Single core cable connected between power
transformer and switchgear shall be single point
earthed at switchgear side and at floating side SVL
(sheath voltage limiter) should be installed.
Availability of oil sampling facility valve arrangement.
Check single point or both ends, via voltage limiter
as per approved design.
Oil flow test.
Impregnation test.
RGP test and DGA test.
Check cable entry path trench as ducts are to be
properly sealed.
For accessories (sealing terminations, pressure
tank, gauges, instrument panels and link boxes),
check the following as applicable:
a.
Nameplates installed and data is
correct.
b.
All valve positions according to
design (open/closed).
c.
Calibrate pressure gauges and
pressure switches.
d.
Oil pressure.
e.
No oil leaks.
f.
Condition of paint work.
g.
All bolted connections.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
23.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Page Number:
Page 50 of 96
Electrical Tests
DESCRIPTION
Check phasing for conductor and sheath bonding
in every link box
Sheath DC high voltage test with 5 kV DC
insulation test before and after high voltage test.
Conductor resistance, capacitance and
inductance measurement.
Conductor insulation resistance test.
Cross bonding verification test.
Link box tightness check.
SVL (sheath voltage limiter) test with 2.5 kV DC
insulation tester.
Inspection of label inside link boxes and water
proofing test.
Measure the ground resistance at all link box
positions.
Contact resistance test on link boxes.
Oil pressure gauge function test.
Shield continuity test.
Cable Jacket test.
Cable profile test.
Insulation oil dielectric breakdown test and water
content test.
AC high voltage test.
DONE
REMARKS
10 kV for 1 minute
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
24.0
Page Number:
Page 51 of 96
24.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
DESCRIPTION
Inspect for physical damage or defects.
Check tightness of all bolted connections (torque
wrench method).
Check for proper cable bolted connections.
Check cable bends to ensure that bending radius is
equal to or greater than the minimum bending radius
specified.
Check for proper cable support, clamping, trays,
blocking.
Link box tightness check.
Verify that shields are terminated as specified
(through link box or directly grounded).
Verification of exact route length as per approved
drawings from termination to termination.
Check that all grounding points are securely
connected to ground grid as specified.
Check that phases are identified and color coded.
Single core cable connected between power
transformer and switchgear shall be single point
earthed at switchgear side and at floating side SVL
(sheath voltage limiter) should be installed.
Check single point or both ends, via voltage limiter
as per approved design.
Check cable entry path trench as ducts are to be
properly sealed.
For accessories (sealing terminations, instrument
panels and link boxes), cheek the following as
applicable:
a.
Nameplates installed and data is
correct.
b.
Condition of paint work.
c.
All bolted connections.
24.2
ITEM
1.
2.
3.
4.
5.
REMARKS
Electrical Tests
DESCRIPTION
Check phasing for conductor and sheath bonding
in every link box.
Conductor resistance, capacitance and
inductance measurement test.
SVL (sheath voltage limiter) test with 2.5 kV DC
insulation tester.
Anti corrosion sheath test.
Measure the ground resistance at all link box
positions.
DONE
REMARKS
less than 10
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
6.
7.
8.
9.
10.
11.
12.
13.
14.
T-PreCom-1000-R0
Page Number:
Page 52 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
25.0
Page Number:
Page 53 of 96
25.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
DESCRIPTION
Inspect for physical damage or defects. Check irregularities of
outer jacket caused by non-uniform shield wire distribution.
Verify all cable connections as per drawing.
Check for proper cable support, clamping, trays, blocking.
Check cable bends to ensure that the bending radius is equal to
or greater than the minimum bending radius specified.
Verify shield grounding as per design (single point, both ends,
via voltage limiters, etc.
Check tightness of all bolted connections (torque wrench
method).
Single core cable connected between power transformer and
switchgear shall be single point earthed at switchgear side and
at floating side SVL (sheath voltage limiter) should be installed.
Check that phases are identified and color coded.
Check cable entry path trench as ducts are to be properly
sealed.
Verification of exact route length as per approved drawings from
termination to termination.
Check for proper cable arrangement in the path (RYB) in order
to prevent circulating current.
25.2
ITEM
1.
2.
3.
4.
5.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Sheath armor continuity test.
Sheath insulation resistance test.
Main conductors insulation resistance test (5KV DC insulation
tester) before and after HV Test.
Phasing and continuity test of main conductor
AC- high voltage test
a.
For new XLPE power cables, AC HV test
voltages should be applied up to 2 Uo for one
hour or by VLF at 0.1 Hz at test voltage level
of 3 Uo for one hour can be performed.
b.
For mixed new and old cables, the test
voltage shall depend upon the service life of
the old cable.
c.
At least It should be tested at normal working
voltage phase to neutral (Uo).
d.
Mixed new and old cables should not be
tested by DC test voltage at any condition
except by AC or VLF methods.
e.
Where cables are connected to switchgear,
the AC HV test time should be reduced to 5
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
f.
T-PreCom-1000-R0
Page Number:
Page 54 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 55 of 96
26.0 LV Cables
(Standard Reference is IEC 60227-2 and relevant SEC Transmission Specifications)
26.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage or defects.
Check for proper cable support, clamping, trays,
blocking.
Verify all cable connections as per approved
drawing.
Verify that all cables and cores are labeled
correctly.
Check tightness of terminals and confirm the
cables are secured.
Check that all cable trays are secure and
correctly grounded.
Check cable entry path trench as ducts are to be
properly sealed.
Visual Insulation, size and rating confirmation.
Check cable size against rating required.
26.2
ITEM
1.
2.
3.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Phasing and continuity check.
AC HV Test at 2 kV 60 Hz for 1 minute between
core to core and core to grounded armor.
Insulation Resistance Test with 2.5 kV DC
insulation tester.
>=100 M
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
27.0
Page Number:
Page 56 of 96
Control Cable
27.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
DESCRIPTION
Inspect for physical damage/defects.
Verify all cable connections as per approved drawing.
Verify that all cables and cores are labeled correctly.
Check for proper cable duct, support, clamping, trays, blocking.
Check tightness of terminals, ferrule numbering and confirm the
cables are secured.
Check that all cable trays are secure and correctly grounded.
Check all cables are securely supported throughout.
Visual inspection, size and rating confirmation.
Size checking against rating required.
27.2
ITEM
1.
2.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Phasing and continuity check.
Insulation Resistance Test with 1 kV DC insulation tester.
IR > 100
Megohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
28.0
Page Number:
Page 57 of 96
Pilot Cables
28.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for physical damage or defects.
Verify all cable connections as per approved
drawing.
Verify that all cables and cores are labeled
correctly.
Check for proper cable support, clamping, trays,
blocking, etc.
Check tightness of terminals, ferrules, wiring
identification and confirm the cables are secured.
Check that all cable trays are secure and
correctly grounded.
Check all cables are securely supported
throughout.
Visual inspection, size and rating confirmation.
Size checking against rating required.
Verification of exact route length as per approved
drawings from termination to termination.
28.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Conductor loop resistance test for all pairs.
Core Identification for each core between two
ends.
Insulation Resistance for sheath armor to ground
by 500V DC insulation tester for each section
before jointing.
Insulation Resistance for sheath armor to ground
with a 500 V DC insulation tester after all joints
are completed and before termination in the pilot
boxes (if applicable).
Capacitance measurement for all cores.
Insulation resistance test between core to core
and core to ground with a 5 kV DC insulation
tester.
Frequency response test.
End to end terminal and pair matching.
Noise Level Measurement.
Cross-talk and coupling test between pairs.
High voltage test for protection and control core
by 15 kV DC for 1 minute.
IR > 10 megohms
IR > 10 megohms
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 58 of 96
PRE-COMMISSIONING SITE
TEST LEVEL
TIME PERIOD
(MINUTES)
2Uo = 16 kV AC
or
VLF test level = 3Uo = 24 kV
2Uo = 38 kV AC
or
VLF test level = 3Uo = 57 kV
2Uo = 80 kV AC
or
VLF test level = 3Uo = 120 kV
60
60
60
60
60
60
2Uo = 128 kV AC
60
2Uo = 152 kV AC
60
230 kV XLPE/LPOF
POWER CABLES
2Uo = 265 kV AC
60
380 kV XLPE/LPOF
POWER CABLE
2Uo = 438 kV AC
60
REFERENCES
AC HV Test: Recommendation by KEMA Research Laboratory (Netherlands).
VLF Test:
Recommendation by High Voltage Corporation (USA) and Seba-Dynatronic (GERMANY) as a
Manufacturer of VLF Test Sets.
Test Voltage levels for LV Cables, Control Cable and Pilot Cables
SYSTEM RATED
VOLTAGE (KV)
PRE-COMMISSIONING SITE
TEST LEVEL
TIME PERIOD
(MINUTES)
LV Cables
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
29.0
Page Number:
Page 59 of 96
Overhead Lines
29.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
DESCRIPTION
Inspect that the access roads and structure pads are to
specification (locations, widths, depth of base, cover material
properly compacted, etc.).
Check that sand stabilization has been done per specification
(if applicable).
Check the right of way to ensure that there is no construction
or agricultural encroachment.
Check that the ground profile allows water run-off from the
structures.
Check that grounding connection is made properly with steel
structure and protective coating is applied on the concrete cap
(if specified). There shall be no cracks, and the concrete cap
shall slope away from the stub angle.
Check that crash barrier and/or flood protection are being
done as per specification (if applicable).
For wooden pole structures, ensure that pole types and sizes
are the correct specification and have been installed correctly
(depth and plumb). Ensure that the depth indication tags are
on each pole.
For wooden pole structures, check structure guy wire, cross
braces, and other framing work have been done correctly.
Check that all wood structures have been identified correctly
and that the identification plates are to specification. For
double circuit structures, ensure that each circuit is correctly
identified.
For steel structures, ensure that type is as per specification /
drawings.
Check galvanizing quality and thickness (rust is not
acceptable).
Check bolt types and tightness (torque wrench method).
Ensure anti-climbing guards are correctly installed (if
applicable).
Check step bolt tightness.
For porcelain insulators, check insulators for chips, cracks,
etc. Ensure correct number of insulators have been installed
in each string. Ensure that cotter keys have been properly
installed.
For composite insulators, perform close elevated inspection on
each structure to check that the insulator sheaths and sheds
are not cracked, damaged or torn. The inner fiberglass rod
should not be exposed at any location.
Check that all line hardware (insulators, corona rings, vibration
dampers, spacers, conductor clamps, warning spheres,
warning lights, armor rods, counter weights, flag socket/keys,
etc.) is installed correctly and in correct locations as per
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
3.
4.
5.
Page 60 of 96
ITEM
1.
2.
Page Number:
Electrical Tests
DESCRIPTION
Perform phase sequence/rotation check.
Perform sequence impedance and susceptance
tests and mutual impedances (both zero and
positive sequence for double circuit lines.
Check tower foot earth resistance as per company
standard.
Check the aircraft warning lights are properly
functioning (if applicable).
Perform continuity and conductivity test.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
30.0
Page Number:
Page 61 of 96
(Standard Reference is SEC Transmission Standard Procedures and relevant Manufacturers Recommendations)
30.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for defects and physical damage from shipping and
handling.
Prior to opening any case or panel, confirm that the equipment
will not be contaminated by dust, excessive humidity or other
pollutants.
Ensure that there is no foreign material, moisture, dust, etc.,
inside panels and device cases.
Check all installed equipment nameplate information for
compliance to approved drawings and equipment/material
lists.
Ensure that all relays, relay covers, meters, controls and test
facilities are properly identified as per the approved drawings
and relevant SEC standards and that the identification does
not obscure information displays.
Ensure the mimic bus provides an accurate representation
and that all switchgear identification is accurate and as
assigned by Systems Operations Department.
Confirm that each panel has been properly secured to the
floor in its final service location.
Confirm that panels are constructed and wired as per SEC
relevant specification.
For all internal and external panel wiring, confirm that all
screw terminations are tight and that crimp connectors are
firmly secured to the wire and to the termination point. Ensure
that no part of the wire is bent at the termination point.
Check that panel equipment is mounted securely and
protected against mal operation due to vibration, shock, etc.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
30.2
ITEM
1.
2.
Page Number:
Page 62 of 96
DESCRIPTION
Wiring Test / Confirmation
a.
The equipment is safe to work on and free of
construction activities.
b.
Ensure that the approved drawings, relevant
specification, protection requirement,
manufacturers manuals, factory test results,
site test procedures, etc., are available at site.
c.
All necessary tools and equipment with their
valid calibration certificates are available.
d.
Stable auxiliary power supplies at the rated
voltages are available.
e.
Prior to conducting panel checks, open all
supply breakers, remove all fuses and ensure
that all DC (including alarm, SOE, SCADA,
etc.), AC, VT and CT circuits are properly
isolated.
f.
Confirm all DC circuits are ungrounded.
g.
Check CT and VT circuits to confirm the
presence of a ground. Temporarily isolate the
ground point on each circuit individually and
retest to confirm that each CT and VT circuit
is grounded at a single point.
h.
Check the burden of each DC circuit with an
ohmmeter to confirm absence of short circuits.
i.
Check auxiliary power supply polarity and
magnitude at the supply side of all circuit
breakers/fuses to be correct as per
schematics and relay/meter ratings.
j.
All wiring including CT, VT, AC, control, alarm
and earthing shall be confirmed terminal to
terminal and wire by wire using an ohmmeter.
k.
Operate all switches and relay contacts
confirming connection terminal numbers and
contact status using an ohmmeter.
l.
Confirmed wiring is to be highlighted in yellow
on the schematic diagram.
Corrections/changes in the schematics shall
be marked up using red pencil for additions
and green for deletions.
m.
For all MCBs, confirm ratings as per approved
drawings; operate several times by hand.
Inject 150% of rated current and record the
timing for trip operation.
n.
Confirm that each internal and external wire is
properly ferruled at termination points.
CT Circuit Confirmation
a.
Inject AC current at about 50% of the rated
current into one phase to neutral of the
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
3.
4.
T-PreCom-1000-R0
Page Number:
Page 63 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
Page Number:
Page 64 of 96
30.3
Cable testing requires at least two personnel with a means of communication between the
cable/wiring ends. Spare cores shall be clearly identified and of sufficient length to be
terminated at the farthest terminal in the panel.
CAUTION: Before conducting any external wiring or cable tests, ensure that all sources of
supply to the circuits involved have been de-energized or disconnected.
ITEM
1.
2.
3.
DESCRIPTION
REMARKS
Continuity Checks
Cables and external wiring insulation shall be tested as for
panel internal wiring, Section 3.30.2. All control cables shall
be tested using a low ohms reading ohmmeter to check each
wire separately to ground (CT and VT circuits must have
their normal grounding point isolated during this test). The
technician at one end shall ground one core at a time in
communication with the technician at the other end who shall
use an ohmmeter to monitor the cores.
CT Cable Checks
A final check of each CT circuit shall be conducted by
current injection at the source end while measuring
magnitude and phase angle in the downstream circuit test
facilities.
VT Cable Checks
A final check of each VT circuit shall be conducted by
voltage injection at the source end while measuring
magnitude and phase angle in the downstream circuit test
facilities.
30.4
ITEM
1.
DONE
DESCRIPTION
Each panel device shall be mechanically inspected
prior to testing.
CAUTION: When working with electronic devices,
never remove modules with the DC supply energized.
Use precautions to prevent static discharge damage to
the modules. Grounded wrist strap, anti-static work
surface and electrically conductive storage bags should
be used.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
a.
2.
T-PreCom-1000-R0
Page Number:
Page 65 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
3.
4.
nominal voltage.
iv.
Time delay relays
shall be tested at 0%,
set point and 100%
delay.
h. Use of red and green tags for tested
relays, meters, etc.
i.
All the relays and meters which have
been tested and found acceptable
shall have green tags.
j.
The relays and meters found
defective during tests shall be tagged
red.
Metering Tests
Panel metering calibration shall be tested via front
panel mounted test facilities. The following represent
the minimum test points required.
a.
Maximum demand indicator (MDI)
meters shall be tested at 10% and
100% of full scale.
b.
Current and voltage metering and
transducers calibration shall be tested
at 0, 25, 50 and 100% of scale.
c.
Watt and VAR metering and
transducer calibration shall be tested
at (+/- when bi-directional) 0, 25, 50
and 100% of rated load and with rated
voltage and current at angles of 0,
45,180, 2270 and 315 degrees.
d.
KWH and KVARH metering
calibration shall be tested at 10% and
100% of rated current at angles of 0,
45, 90, 180, 225, 270 and 315
degrees.
e.
Frequency metering and transducers
calibration shall be tested at
minimum, nominal, and maximum
rated scale.
f.
Power Factor metering and
transducer calibration shall be tested
at rated voltage and at 50% lead,
unity, 50% lag power factors at 10, 50
and 100% of rated current.
g.
Tap position indicators shall be
checked and confirmed for the entire
range of transformer tap positions.
Annunciator Tests
a.
Confirm dual supply operation by
disabling primary and backup supplies
one at a time.
b.
Confirm operation of Acknowledge,
Reset and Lamp Test push buttons.
i.
Alarm indication lamp
T-PreCom-1000-R0
Page Number:
Page 66 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
5.
Page 67 of 96
flashes on receipt of
alarm.
ii.
Pressing
Acknowledge does
not reset the alarm
points.
iii.
Alarm does not reset
until Reset is
pressed.
c.
Confirm Annunciator Failure alarm to
SCADA.
d.
Check operation of each alarm point
one at a time by simulating input at
the marshalling panel.
e.
Confirm individual alarm identification
for each point during functional testing
of remote panels output contacts.
Digital Disturbance (DDR) Tests
a.
DDR shall be inspected and
calibrated as recommended by the
manufacturer.
b.
Calibration of voltage and current
channels shall be confirmed by
secondary injection.
c.
Each digital input shall be confirmed
by operation of the associated
auxiliary contact in the remote panel.
d.
Program and electrically confirm
trigger levels and initiating contacts.
e.
All alarm/SOE/SCADA outputs shall
be tested and confirmed.
f.
Verify accuracy of all channel
descriptions.
g.
Verify operation to the local printer if
available.
h.
Verify proper communication and
software
i.
Update/installation at all concerned
locations by establishing
communications with each unit and
downloading event data.
30.5
ITEM
1.
Page Number:
Functional Checks
DESCRIPTION
Test to Local Auxiliaries
With all tripping isolating switches opened, operate
the protective relays by secondary injection to test
all functions to the panel auxiliaries. Check and
confirm correct operation of all trip, alarm, SOE and
SCADA auxiliaries in the panel as well as initiation
outputs to DFR, breaker failure, etc.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
2.
3.
4.
5.
6.
T-PreCom-1000-R0
Page Number:
Page 68 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
7.
8.
9.
T-PreCom-1000-R0
Page Number:
Page 69 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
10.
11.
T-PreCom-1000-R0
Page Number:
Page 70 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
30.6
ITEM
1.
2.
3.
Page Number:
Page 71 of 96
Energization
DESCRIPTION
First Time Energization Testing-Checks Prior to Energization
a.
All in service CT circuit shorting is removed.
b.
All VT circuits MCBs closed, fuses in place.
c.
All supplies to protection, control, switchgear,
etc., are normal.
d.
No abnormal relay targets, alarms, SCADA
SOE indications.
e.
All relays have approved settings applied and
have been fully tested and are in service.
f.
All switchgear and other power equipment
testing is completed.
g.
All protection equipment is properly labeled.
h.
All fire/smoke alarm systems are fully tested
and in service.
i.
All necessary fire fighting equipment is on site
and accessible without obstruction.
j.
Confirm all men and tools are clear of
equipment to be energized and that all
personnel are aware of the pending
energization.
Phasing Checks
Before paralleling two sources, phasing shall be
absolutely proven by selectively energizing a common
three phase VT set from the two sources one at a time
and checking the phasing (voltage and phase angle) of
the VT set to a reference potential whose source shall
remain unchanged for the duration of the test.
For example, if one new incoming line to an existing
station is to be energized, use the existing incoming line
A phase to neutral potential as a reference and measure
and record the new line VT secondary three phase voltage
and phase angles when energized from the remote end
only. Then after opening the remote end of the new line,
energize the new line from the local station only and
repeat the voltage and phase angle measurements, the
results of the two tests should be identical (within a few
degrees) if phasing is correct. Where possible, phasing
sticks can be used.
In Service Checks
a.
Immediately after energization, in-service/onload checks should be taken and recorded by
measuring the magnitude and phase of all
voltage and current circuits to a common
reference at all of the test points available to
prove VT and CT connection, ratio and
polarity.
b.
Check and record all panel meter readings to
compare with CT/VT measurements in the
control circuits.
As soon as sufficient load is available, all
c.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
d.
e.
f.
g.
h.
i.
T-PreCom-1000-R0
Page Number:
Page 72 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
31.0
Page Number:
Page 73 of 96
Station Batteries
(Standard Reference is IEC 60623, clause 4 and relevant SEC Transmission Specifications)
31.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness as per standards.
Check tightness of all external wiring and cabling connections.
Verify all panel mounted devices (meters, switches, push
buttons, indicator lamps, etc.) are supplied and installed
according to approved drawings.
Make sure all battery connections are clean and free from
corrosion.
Verify system configuration and capacity with contract
specification.
Check that all cells are properly numbered.
Check protective covers installed.
Check that all battery maintenance tools and accessories
(hydrometer, wall mounted thermometer, insulated torque
wrench, rubber gloves, apron, face shield) have been provided
per specifications. Ensure that all maintenance equipment is
stored in a wall mounted lockable cabinet.
Check that the room ventilation, exhaust fan, etc., are to
specification.
Check installation of safety equipment (eyewash, showers, No
smoking and Warning Caustic/Acid signs).
For flooded lead acid batteries, check for correct specific gravity
and liquid level.
Check that all battery racks are correctly and securely
grounded.
Check that the battery bank is provided with an isolating
disconnect switch.
Check that the Valve Regulated Lead Acid (VRLA) battery bank
has an ammeter provided for monitoring the float charge
current.
31.2
ITEM
1.
2.
3.
4.
REMARKS
Electrical Tests
DESCRIPTION
For valve Regulated lead Acid Batteries, check the open circuit
voltage of each cell.
Perform initial charging of the battery (equalize voltage,
charging rate and charging time according to the manufacturers
instructions).
Record individual cell voltage electrolyte specific gravity and cell
temperatures at the end of charge cycle.
Battery discharge test:
a.
The battery must not have been discharged
within last 7 days before test is performed.
b.
While battery on float, read and record the
DONE
REMARKS
Room
temperature
shall be
between 25
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
5.
T-PreCom-1000-R0
Page Number:
Page 74 of 96
and 30 C.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
32.0
Page Number:
Page 75 of 96
Battery Chargers
(Standard Reference is IEC 60623, clause 4 and relevant SEC Transmission Specifications)
32.1
ITEM
1.
2.
3.
4.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness as per standards.
Check tightness of all external wiring and cabling connections,
labeling, drawing pocket shall be checked.
Verify all panel mounted devices (meters, switches, push
buttons, indicator lamps, fuses, etc.) are supplied and installed
according to approved drawings.
32.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Insulation test for all external wiring.
Battery charger test by simulation of variable load to check for
correct charger current output response to different values of
load.
Check the adjustment range of output float and equalize
voltage. Note that the adjustment of float and equalize voltage
should be independent of each other.
Functional check of the following:
a.
High and low output voltages alarm/shutdown.
b.
Ground monitoring/ground detector for +ve
and ve alarms.
c.
All other protective alarm/shutdown.
d.
All devices (switches, push buttons, timers,
indicating lamps, etc.).
e.
Current limits.
f.
Soft start.
g.
Impedance monitors (if applicable).
h.
Silicon droppers (if applicable).
Check output voltage ripple content (battery disconnected).
Check regulation at 0%, 50% and 100% of full load.
Measure AC input and DC output voltages and currents and
calculate efficiency at 50% and 100% of rated output current.
Calibrate voltmeters and ammeters.
If applicable measure the following and verify that they are
compatible with and meet the requirements of the
communications equipment:
a.
Voice band noise voltage.
b.
Wideband noise voltage.
Check load sharing operation for parallel chargers.
Ensure that the settings of adjusted control, shutdown, alarm
voltage, etc., have been reset to the final operational values as
specified by SEC.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
33.0
Page Number:
Page 76 of 96
AC Distribution Panels
33.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage or defects including of quality of
paint work.
Verify circuit layout for conformance with breaker directory
drawing.
Verify correct rating of each circuit breaker per design drawings.
Check tightness of all bolted connections.
Verify that all front panel mounted devices (meters, selector
switches, push buttons, timers, indication lamps, etc.) are
installed per layout drawing and are correctly labeled.
Check for proper grounding connection (torque wrench
method).
33.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
REMARKS
Electrical Tests
DESCRIPTION
Insulation test of all buses and wiring.
Phasing check.
Functional check of main power contactor (or breaker).
Functional check of each branch breaker.
Calibrate voltmeters, ammeters and wattmeters.
Functional check of meters and phase selector switches.
Functional check of all auxiliary devices including individual,
group and main circuit breaker alarms.
Functional check of under voltage protection/alarm circuits.
Functional check of ground fault circuit interrupter (if applicable).
Check all MCBs for their ratings and alarms.
DONE
REMARKS
2.5 kV for one
minute
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
34.0
Page Number:
Page 77 of 96
DC Distribution Panels
34.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage or defects including of quality of
paint work.
Verify circuit layouts for conformance with breaker directory
drawing.
Verify correct rating of each circuit breaker per design drawings.
Check tightness of all bolted connections.
Verify that all front panel mounted devices (meters, selector
switches, push buttons, timers, indication lamps, etc.) are
installed per layout drawing and are correctly labeled.
Check for proper grounding connection (torque wrench
method).
34.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
REMARKS
DONE
REMARKS
2.5 kV for one
minute
Electrical Tests
DESCRIPTION
Insulation test for all buses and wiring.
Polarity check.
Functional check of main breaker.
Functional check of each branch breaker.
Calibrate voltmeters, ammeters and wattcmeters.
Functional check of meters.
Functional check of all auxiliary devices including individual,
group and main circuit breaker alarms.
Functional check of under voltage protection and alarm circuits.
Functional check of DC transfer switches and interlocks.
Functional check of positive and/or negative ground alarm
(calibrate resistors for proper detection sensitivity earth fault
relay setting shall be checked).
Check all MCBs for their ratings and alarms.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
35.0
Page Number:
Page 78 of 96
LV AC Auto-Transfer Schemes/Switches
35.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage or defects.
Check that all front panel mounted devices are supplied and
arranged according to approved drawings.
Check that all devices and cables are properly identified and
labeled.
Check tightness of all bolted connections (torque wrench
method).
Check that all grounding is correct and securely connected
(including neutral bus).
Check mechanical/electrical interlocks.
35.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Phasing check of incomers and transfer switch connections.
Calibrate under voltage relays and time delays.
Calibrate voltmeter and ammeters.
Functional check of meters and selector switches.
Functional check of electrical and mechanical interlocks.
Functional check of preferred source selector switch.
Check transfer motor fuses.
Functional check of transfer operation (simulate loss of one
source) and retransfer on re-establishment of preferred source
voltage. Check with each source as the preferred source.
Ensure the sources are from two separate buses.
Set under voltage relay and time delay per manufacturers
instructions.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
36.0
Page Number:
Page 79 of 96
Grounding Systems
36.1
ITEM
1.
2.
3.
4.
DESCRIPTION
Inspect the grounding system(s) for conformance with approved
design drawings and specification.
Inspect the mechanical integrity and quality of all bolted and/or
thermite welded grounding joints and connection.
Inspect and verify the size and type of conductors conform to
standard requirements.
Check that all metal parts in the substation are grounded.
36.2
ITEM
1.
2.
3.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Measure the ground grid system resistance by the fall of
potential method.
Measure the contact resistance at 100 A DC of all bolted and/or
thermite-welded joints at the grounding conductor between the
equipment to be grounded and the grounding mesh. Note that
bolted below grade connections are not permitted.
Measure the electrical resistance between each major electrical
equipment grounding point, grounded neutral points and the
substation main grounding system by the millivolt drop
method.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
37.0
Page Number:
Page 80 of 96
37.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
DESCRIPTION
Inspect for physical damage or defects.
Check labeling and marking according to the approved
drawings.
Check tightness of bolts on direct drive and base-mounted
equipment.
Check oil level and leakage and air compressor main
components, air receiver tank design and specification.
Check hour meter, safety relief valve, pressure switch and
gauges.
Check air lines piping according to the approved materials.
Check that the exposed airlines protected against rupture
damage.
Check that all piping runs parallel to flooring or walls and is
clamped properly by u-bolts or metal clamps supported on at
least 6 foot intervals or less.
Check that all piping has sufficient spacing so that each line can
be accessed without disturbing the rest of the piping.
Check that all pipes are supported on steel benches on the floor
of the trench.
Check that all piping fitting connections to be used shall be flare
cup type nuts with sleeve.
Check that air compressors are fitted with:
a.
Automatic drain valve.
b.
Manual drain valve.
c.
Pressure relief valve.
d.
Oil level sight glass.
Check that the receiver tank provided with inlet and outlet stop
valves, manual drain valve, pressure relief valve and pressure
gauge.
37.2
ITEM
1.
2.
3.
4.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Check that the motor for air compressor designed for operation
on 220 V, 3 phase 60 Hz including magnetic contactors, relays
and accessories.
Check that circuit breaker, isolating switch wires and conduit
sizes are suitable for load requirement of the system.
Check that all wiring shall be in rigid steel conduit, wire ducts or
flexible conduit; wires shall be standard type THW and color
coded.
Check that all wiring splices shall be made with wire connector
or terminal bed connectors of approved type and insulated with
two layers of rubber, covered with friction tape to protect the
rubber.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
5.
6.
7.
T-PreCom-1000-R0
Page Number:
Page 81 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
38.0
Page Number:
Page 82 of 96
HVAC Systems
38.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
DESCRIPTION
Inspect for physical damage or defects.
Check labeling and marking is according to the drawings.
Check tightness of bolts on direct drive and base-mounted
equipment.
Check for adequate access to the equipment.
Check that ducts exposed to weather are properly insulated and
wrapped with weather proofing materials, e.g., wrapped with
aluminum sheet.
Check that the space clearance around the duct shall be
properly sealed to prevent the passage of rain water or any
other foreign matter.
Check that all panels such as control panel, compressor panel,
motor blower panels shall be provided with left and right
handles.
Check that air conditioning essential components, electrical
controls, breaker, etc., is properly labeled or marked.
Check that all exposed refrigerant suction lines are properly
insulated and wrapped with aluminum sheet and suitably
protected from rupture damage.
Check that the exposed refrigerant liquid line is painted with
liquid refrigerant gas color code paint and fitted with liquid sight
glass, solenoid valves expansion valves and strainer if required.
If semi-hermetic reciprocating compressor with nominal cap of
20 tons and above is used, check that the size of receiver tank
is able to contain all refrigerant charged into the system plus
20% excess volume for gas expansion.
Check that receiver is provided with inlet and outlet shut off
valves, relief valves, purge cock, liquid level sight glass and oil
drain.
Check that the refrigerant compressor is a sealed hermetic type
or semi-hermetic reciprocating type.
Check that the compressor is provided with the following:
For sealed type hermetic compressors:
a.
Suction and discharge service valves with
charge plug fitting connection.
b.
Crank case heater.
c.
High and low pressure cut-out manual reset.
For semi-hermetic reciprocating compressors:
a.
Suction and discharge service valves with
charge plug fitting connection.
b.
Oil level sight glass.
c.
Suction, discharge and oil pressure gauges.
d.
Crank case heater.
e.
Oil pressure protective switch to stop
compressor operation in case of lubrication
failure.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
15.
16.
17.
18.
19.
Electrical Tests
ITEM
DESCRIPTION
1.
3.
4.
5.
6.
7.
8.
9.
Page 83 of 96
f.
High and low pressure cut-out manual reset.
g.
Suction line strainer with service valves.
Check that thermostat control with temperature indicator is
provided and suitable to operate the system automatically.
Check that the thermostat is equipped with independent switch
to operate the air supply fan continuously if required.
Check that the thermostat control is protected by a clear plastic
transparent guard cover with standard lock and key.
Check that the belt driven blower and fan motors are protected
by a belt guard cover.
Check that the air filters are easily removable from unit and
washable type and check that the frame is 18 gauge galvanized
iron with welded or screw type corners.
38.2
2.
Page Number:
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
39.0
Page Number:
Page 84 of 96
39.1
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
Inspect for physical damage/defects (cracks, chips, etc., of the
cast resin).
Check nameplate for correctness.
Check tightness of all bolted connections (torque wrench
method.
Check that all grounding is securely connected, including star
point neutral.
Perform all specific checks per manufacturer instructions.
Check proper operation of all auxiliary devices (as applicable).
39.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Insulation resistance and Polarization Index (PI) test.
Turns ratio all (taps) test.
Polarity and vector relationship test.
Winding resistance measurement (all taps).
Excitation current test (at nominal tap).
Back energization test (at rated voltage for 15 minutes).
Check the off load tap changer is set at the rated voltage tap.
Functional test of all auxiliary devices (if applicable).
Control and protective circuit functional tests.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
40.0
T-PreCom-1000-R0
Page Number:
Page 85 of 96
Loss Prevention Department is responsible for fire detection and suppression systems, but
transmission witnessing personnel shall check the alarms and trip signals (if applicable) which affect
the main equipment such as power transformer, GIS, etc.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
41.0
T-PreCom-1000-R0
Page Number:
Page 86 of 96
Civil Work
Witnessing of civil work is the responsibility of the Civil Department to witness the work of the civil
contractor. Transmission witnessing personnel shall check the accesses and ventilation that affects
the main equipment.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
42.0
Page Number:
Page 87 of 96
42.1
ITEM
1.
2.
3.
4.
5.
6.
7.
DESCRIPTION
Get the sanction for test document.
Check the safety documents for entering the capacitor bank
area.
Check the safety documents for entering the TCR area.
Check the safety document for touching the capacitor banks
and TCRs.
Check the anti-static instruction prior to handling the electronic
devices.
Never touch the components of electronic cards without antistatic wrist strap.
Check your safety shoes, helmet, goggles and industrial
uniform.
42.2
DONE
REMARKS
(Standard Reference is IEEE 1303-1994, IEEE Guide for Static VAR Compensator Field Tests and relevant SEC
Transmission Specifications)
42.3.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check leakage.
Check deformation.
Check tightness of the bolts according to specifications.
Check that all grounding cables are securely connected.
Check for any damaged paint.
Check earthing switch.
Capacitor bushing tightness check.
Check for bushing cracks.
Check for proper termination.
Check CT locations physically.
42.3.2
ITEM
1.
2.
3.
4.
REMARKS
DONE
REMARKS
Electrical Tests
DESCRIPTION
Check of test and measuring instruments calibration certificates.
Check of condition of battery cells of the T&M instruments.
Check individual insulation resistances.
Measure each individual capacitance.
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
5.
6.
7.
8.
9.
10.
11.
12.
Page Number:
Page 88 of 96
(Standard Reference is IEEE 1303-1994, IEEE Guide for Static VAR Compensator Field Tests and relevant SEC
Transmission Specifications)
42.4.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check for overall body deformation.
Check tightness of the bolts according to specifications.
Check that all grounding cables are securely connected.
Check for any damaged paint.
Check of foreign particles between the layers of the reactor
coils.
Check of any insulation cracks.
Check for proper termination.
Check CT locations physically.
42.4.2
ITEM
1.
2.
3.
4.
5.
DONE
REMARKS
Electrical Tests
DESCRIPTION
Check of condition of battery cells of the T&M instruments
Check main current path connection contact resistance.
Temperature measurement at different joints after energization.
Check the insulation resistance.
Inductance measurement between different cores.
42.5
DONE
(Standard Reference is IEEE 1303-1994, IEEE Guide for Static VAR Compensator Field Tests and relevant SEC
Transmission Specifications)
42.5.1
ITEM
1.
2.
3.
4.
5.
DESCRIPTION
Inspect for physical damage or defects for entire system.
Check nameplate information for correctness and installation of
the cooling network according to the drawings.
Check for the redundancy of the fluid circulating pumps in the
cooling system.
Check pressure holding test on the expansion vessel/reservoir.
Check the pressure release valve and its operation on the
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
expansion vessel/reservoir.
Check the availability of nitrogen regulating system on the
expansion tank and ensure no leakage.
Check the Motor and pump for leveling and alignment.
Check tightness of all joints and couplings of the coolant circuit
(torque wrench method).
Check all pipe network and cooling system to stand test
pressure and operating pressure.
Check the unobstructed coolant circuits in all parallel paths.
Check the provision of control valve for inlet and outlet for all
parallel paths.
Check the provision of control valve for all equipment in the
cooling system for replacing or repairing without any interruption
to the cooling system.
Check the availability of pressure regulating valves at the outlet
of the pumps.
Check the availability of shut off valve at the inlet and outlet of
the pumps.
Check provision of replacing the pump while system is on line.
Check the provision of air bleeding valve at the top of all parallel
paths and at the ion exchanger/ deionizer.
Check the provision of leak-water collection (drainage) on the
floors.
Check the provision to replace the resin while system is on line.
Check the provision to replace filters/strainer while system is on
line.
Check the availability of the filters at the inlet and out let of the
deionizer.
Check the availability of the strainers at the outlet of the
deionizer and at the inlet of the valves with bypass circuit.
Check the availability of the control valves at the inlet and outlet
of each heat exchanger.
Ensure the outdoor piping network is stainless steel.
Ensure unobstructed ventilation for all heat exchangers.
Ensure the availability of vibration shocks for the all heat
exchangers.
Check, calibrate and functional test of the all temperature
gauges.
Check and calibrate all pressure gauges, flow switches,
differential pressure gauges and liquid level switches.
All the cooling system should be flushed over several hours,
including all branches, heat exchangers, deionizers, etc.
Verify no leakage in the cooling system.
Test the coolant for purity, proper percentage of anti freezing
and anti algae before filling the cooling system.
Check the rotation of pumps and cooling fans.
Run the pumps on and off repeatedly, until no more particles
accumulate in the filters.
Vibration check of cooling network.
Sound level check.
Check the auto operation of ion exchanger/bypass valves with
the conductivity meter (if applicable).
T-PreCom-1000-R0
Page Number:
Page 89 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
42.5.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
Page Number:
Page 90 of 96
Electrical Tests
DESCRIPTION
Check of condition of battery of the T&M instruments.
Visual check of electrical panel.
Insulation resistance test of motors.
Winding resistance measurement of motors.
Check the proper rating of the motor protection breakers and
perform the functional trip test by current injection, under
voltage, and phase reversal.
Verification of current, overload, thermal, under voltage, and
phase reversal settings of motor protection.
Check the operation of the pumps from local pump station PLC,
and SCADA. Ensure the alarm signal when pump is on local
mode.
Record the power supply input voltage and phase rotation.
Record starting and running motor current.
Check the redundancy of auxiliary power supply and operate
the pumps one by one by both power sources.
Check the alarm and status by simulating the breaker open/
loss of auxiliary power sources.
Verify overload trip time of all motors by artificial single phasing
of all three-phase motors.
Simulate the operation of pumps by loss of power, pump failure,
differential pressure and running hours completion cycle and
ensure automatic changeover.
Ensure automatic changeover time is coordinated with loss of
cooling alarm time.
Verify start-up of standby pump on loss of supply to running
pump and record the time.
Check PLC of cooling system for measurement of pressure,
temperatures, Levels, resistively and status of pumps, heat
exchanger fans and valves.
Check to see that monitoring signals show correct values or
correctly indicate alarms.
Check the alarm/trip signal on loss of input voltage, pump
failure, low coolant level, high and low resistivity, pressure,
fellow, and temperature from all gauges, sensors and meters.
Check the cooling fans auto-changeover and auto operation by
temperature.
Check the cooling fans operation from Manual and Auto from
PLC control panel.
Check the cooling fans minimum run time, and on-off
hysteresis.
Check the simulated operation of all electrical operated valves.
Ensure the full cooling capacity is available with one cooler
failed or out of service.
Display messages check for alarms and trips.
PLC internal battery check if present and note the date of
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
26.
27.
28.
29.
Page Number:
Page 91 of 96
replacement.
Check Automatic operation of de-ionizer by resistivity. Check
the conductivity measurement of the coolant to see that it drops
below alarm level when new water is circulated, if applicable.
Check the deionizer time for recovering the resistivity, if
applicable.
Check the minimum activation time of deionizer, if applicable.
Ensure that liquid coolant is electrically grounded.
42.6
(Standard Reference is IEEE 1303-1994, IEEE Guide for Static VAR Compensator Field Tests and relevant SEC
Transmission Specifications)
42.6.1
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that the connection does not transfer stress to the
connection terminal.
Check operation of the cooling fan.
Check that the filters for the cooling fan are not dirty..
All input and output cables are secure.
Fiber optics cables are secure without squeezing and without
severe bends.
All modules are properly labeled.
Check the panels are well ventilated with dust filter.
Check that the connection ports which are under use have dust
covers and all other unused ports should be sealed off.
Check that the connections ports are clearly and correctly
identified.
Check that the ferrules are properly marked.
Card locations are clearly numbered.
Sequence event recorder panel check.
Annunciator panel check.
Check the labeling on thyristor towers.
Check of proper extractor tool.
Panel lighting is operating properly.
Check that the panel heaters are not installed.
Check that the terminals are furnished with isolator links.
Check that the wire terminals have banana sockets for the
testing purposes.
Check that all grounding cables are securely connected.
Verification against drawings and contract specification.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
42.6.2
ITEM
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
Page Number:
Page 92 of 96
Electrical Tests
DESCRIPTION
Check of Test and Measuring instruments calibration
certificates.
Check of condition of battery cells of the T&M instruments.
Check of hardware.
Check of software.
Hardware jumpers check.
Micro console and PC with software check.
Check of user program loading.
Input and output operation check.
Test of light guides passing from controller to TCR towers.
Firing pulses tests to thyristors simulation.
Snubber circuit testing.
DC functional tests.
Complete wiring checking.
Cooling system alarm checks from controller.
All alarms and trips initiation checks.
Trouble shooting guide verification with initiation of alarms.
Check of disconnects and low voltage switchgear by control
panel operation.
Check of print-out on the printer and alarm on the annunciator.
Check of alarms and trips to controller, annunciator and to even
recorder.
Check of cooling system ready.
Check of temperature normal.
Check of SVC ready.
Check of alarms at controller due to alarms of the transformer.
Check of all controller cards.
Low voltage tests for SVC with different firing angles, i.e., B=0
to B=90 (LIMAX=0 TO 1.0.
Stability test of differential protection thyristor bypass switch
closed.
Emergency trip operation check.
SCADA point list testing.
Check of thyristor monitoring software operation.
Check of CB fail to close and fail to open alarm.
Controller over current protection level-1 tests, if applicable.
Controller over current protection level-2 tests, if applicable.
Secondary under voltage level 70% protection for immediate
trip, if applicable.
Primary under voltage 30% protection for 100 msec and no
trip, if more the system to trip, if applicable.
Primary under voltage 0.6 p.u. for more than 1 sec. CB trips.
Secondary under voltage 0.6 p.u., TCR blocks if more than 1
sec. then CB trips.
UPS operation time to be checked if ac is off to the UPS.
UPS alarm and trip level tests.
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
T-PreCom-1000-R0
CHECK LIST
S/S Name/No:.
Bay No:
39.
40.
41.
42.
43.
44.
Page Number:
Page 93 of 96
42.7.1
ITEM
1.
2.
3.
4.
DESCRIPTION
Inspect for physical damage or defects.
Check nameplate information for correctness.
Check tightness of all bolted connections.
Check that the connection does not transfer stress to the
connection terminal
42.7.2
ITEM
1.
2.
3.
4.
5.
6.
7.
DONE
REMARKS
Electrical Tests
DESCRIPTION
Check of Test and Measuring instruments calibration
certificates.
Check of condition of battery cells of the T&M instruments.
Test the protection relays related to transformer.
Test the protection relays related to HV CB.
Test the protections related to TCR and Harmonic Filters.
Check and test the modified schemes.
Check of alarms from the SVC local panel, and remote alarm in
the control panel and corresponding alarm to the Control
Center.
42.8
DONE
Electrical Tests
(Standard References are manufacturers instruction manual and SEC relevant Transmission Standard))
ITEM
1.
2.
3.
4.
5.
6.
DESCRIPTION
SVC pre-energization check list.
Check the SVC energization list.
Confirm the final settings.
Operation division shall issue caution for energization process.
Check and follow the switching program.
Check that the operating division has issued a warning to the
DONE
REMARKS
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
T-PreCom-1000-R0
Page Number:
Page 94 of 96
This is to
avoid
damage to
the
thyristors in
case of mis
synchronism
between the
firing pulses
and voltage
across the
thyristor
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
T-PreCom-1000-R0
Page Number:
Page 95 of 96
TRANSMISSION
PRE-COMMISSIONING TEST PROCEDURE
PART II
Title:
Index Number:
CHECK LIST
S/S Name/No:.
Bay No:
42.9
T-PreCom-1000-R0
Page Number:
Page 96 of 96
Air-Conditioning Systems
The reliability of air-conditioning is very important for the SVC controller, so this part of the equipment should
be tested thoroughly. For details of its pre-commissioning please refer to Section 3.38, HVAC Systems.
42.10
The reliability of fire detection and suppression systems is very important for the SVC System, like any other
substation component. This equipment should be thoroughly tested. For details of its pre-commissioning
please refer to Section 3.40, Fire Detection and Suppression Systems