INSPECTION REQUEST

PROJECT:

Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO:

Job-230

CLIENT:

M/s Osool Gulf Investment Co.

REQUEST NO:

ISSUED TO:

UNIQUE CONTRACTING CO L.L.C

DATE:

CONSULTANT:

Al Saqf Engineering Consultancy

DISCIPLINE:

J-230/ AM - 001

29.06.2015
POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):


WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work of Upper Basement floor slab - Pour 5
X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT
LOCATION : Upper Basement Floor Slab - POUR 5 ( Location Drawing Attached )

Requested By :

Sohail Khan (Site Incharge)

Ready for Inspection at

Date: 30.06.2015 10:00 AM


Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida


MAIN CONTRACTOR REMARKS

Approved

Approved as noted

Revise & Resubmit

Rejected

Signed for and on behalf of the Consultant Resident Engineer

Date

Signed for and on behalf of the Consultabt MEP Engineer


Notes:
1. A minimum of 24 hours notice is required prior to inspection time
2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Date

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0

Date: 29th June 2015

Document # AM-101

Page 1 of 1

INSPECTION REQUEST
PROJECT:

Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO:

Job-230

CLIENT:

M/s Osool Gulf Investment Co.

REQUEST NO:

ISSUED TO:

UNIQUE CONTRACTING CO L.L.C

DATE:

CONSULTANT:

Al Saqf Engineering Consultancy

DISCIPLINE:

J-230/ AM - 002

6th July, 2015


POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):


WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 6 & Pour 7
X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT
LOCATION : Upper Basement Floor Slab - POUR 6 & POUR 7 ( Location Drawing Attached )

Requested By :

Sohail Khan (Site Incharge)

Ready for Inspection at

Date: 7th July, 2015 10:00 AM


Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida


MAIN CONTRACTOR REMARKS

Approved

Approved as noted

Revise & Resubmit

Rejected

Signed for and on behalf of the Consultant Resident Engineer

Date

Signed for and on behalf of the Consultabt MEP Engineer


Notes:
1. A minimum of 24 hours notice is required prior to inspection time
2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Date

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0

Date: 6th July, 2015

Document # AM-002

Page 1 of 1

INSPECTION REQUEST
PROJECT:

Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO:

Job-230

CLIENT:

M/s Osool Gulf Investment Co.

REQUEST NO:

ISSUED TO:

UNIQUE CONTRACTING CO L.L.C

DATE:

CONSULTANT:

Al Saqf Engineering Consultancy

DISCIPLINE:

J-230/ AM - 003

22th July, 2015


POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):


WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 4
X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT
LOCATION : Upper Basement Floor Slab - POUR 4( Location Drawing Attached )

Requested By :

Sohail Khan (Site Incharge)

Ready for Inspection at

Date: 23th July, 2015 10:00 AM


Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida


MAIN CONTRACTOR REMARKS

Approved

Approved as noted

Revise & Resubmit

Rejected

Signed for and on behalf of the Consultant Resident Engineer

Date

Signed for and on behalf of the Consultabt MEP Engineer


Notes:
1. A minimum of 24 hours notice is required prior to inspection time
2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Date

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C

Revison-0

Date: 7th July, 2015

Document # AM-003

Page 1 of 1

INSPECTION REQUEST
PROJECT:

Construction of Nawras Commercial Center at Al Kuwair on Plot No. 41, 17/3

PROJECT NO:

Job-230

CLIENT:

M/s Osool Gulf Investment Co.

REQUEST NO:

ISSUED TO:

UNIQUE CONTRACTING CO L.L.C

DATE:

CONSULTANT:

Al Saqf Engineering Consultancy

DISCIPLINE:

J-230/ AM - 004

8th Aug, 2015


POST TENSIONING

Sr. PROJECT MANAGER (UNIQUE):


WE REQUEST THE INSPECTION OF THE FOLLOWING WORK:

We hereby request you to kindly inspect the Stressing work forUpper Basement floor slab - Pour 2
X' DIRECTION CABLE LAYOUT & 'Y' DIRECTION CABLE LAYOUT
LOCATION : Upper Basement Floor Slab - POUR 4( Location Drawing Attached )

Requested By :

Sohail Khan (Site Incharge)

Ready for Inspection at

Date: 9th Aug, 2015 10:00 AM


Signature of Sub-contractor (As applicable)

Signed for and on behalf of Al Azaem Al Muttahida


MAIN CONTRACTOR REMARKS

Approved

Approved as noted

Revise & Resubmit

Rejected

Signed for and on behalf of the Consultant Resident Engineer

Date

Signed for and on behalf of the Consultabt MEP Engineer


Notes:
1. A minimum of 24 hours notice is required prior to inspection time
2. Contractor / Subcontractor to confirm compliance with the contract documents if applicable.

Date

Encl: Dwg.Ref. : UNQ/J-230/PT/CL-3A&3C