You are on page 1of 5

JOB METHOD STATEMENT

PROJECT TITLE : KARIANGAU CFSPP 2 X 15 MW

CONTRACT NO:

LOCATION / FACILITY : TURBINE AREA

DATE :

NAME OF CLIENT : PT KARIANGAU POWER


NAME OF SUBCONTRACTOR (S) : PT DUTA JASA KONSTRUKSI
JOB / ACTIVITIY :

S.
No

ACTIVITY

PREPARATION
FOR
INSTALLATION

EQUIPMENTS /
TOOLS
REQUIRED

SAFETY
PRECAUTIONS

WORK
SEQUENCE

PROCEDURE
1.
2.
3.
1.
2.
3.
4.
5.
6.
1.
2.
3.
1.
2.
3.
4.

DETAIL WORK
SECOND
SHIPMENT

REMARKS

Cleaning location area project


Preparation equipment scaffolding
Preparation of materials that will be done
Scaffolding
Body harness
Stairs for level working
Helmet
Safety shoes
Glasses
Perform safety talk before doing the work
Using of body harnes for working level
Use of safety shoes to avoid because of the nails and slippery
conditions
leveling and compacting the soil at the location of turbines
Installation of peri material to be used as support of form work
Instalation of rebar work column and beam concrete work be done
before casting
Do the work of casting concrete the columns and beams

DETAILED WORK SEQUENCE

PT AE MATERIAL HANDLING SYSTEMS

Ref: AE-JMS-001
Page 1 of 5

JOB METHOD STATEMENT


PROJECT TITLE : KARIANGAU CFSPP 2 X 15 MW
LOCATION / FACILITY : TURBINE AREA

CONTRACT NO:
DATE :

NAME OF CLIENT : PT KARIANGAU POWER


NAME OF SUBCONTRACTOR (S) : PT DUTA JASA KONSTRUKSI
JOB / ACTIVITIY :

1. Column Work :
Fabrication of steel formwork concrete column and the binding rebar
site prior to work around the turbine installation.
Installation of rebar steel column assemblies that have been created
and then removed using a crane mobile to the location of the turbine
to be installed.
After reinforcement steel columns installed then do the work
formwork column removal using crane mobile to do the work
strengthened formwork column.
After work steel rebar and column formwork is installed and then do
the job done checking the column casting.
2. Beam Work :
The first work is done prior to installation of scafolding and working
steel rebar form work beam.
Second step after the completion of the working is the installation of
scafolding that serves as a peri formwork beam support of the
turbine.
Assembly of steel rebar beams carried on top of the column, so do
safety by using a body harness in doing the steel rebar working on
the turbine installation to prevent falls from height at the location of
the turbine.
Implementation of the beam and floor molding using a hanging
concrete basket to a crane of capacity 50 ton.

PT AE MATERIAL HANDLING SYSTEMS

Ref: AE-JMS-001
Page 2 of 5

JOB METHOD STATEMENT


PROJECT TITLE : KARIANGAU CFSPP 2 X 15 MW
LOCATION / FACILITY : TURBINE AREA

CONTRACT NO:
DATE :

NAME OF CLIENT : PT KARIANGAU POWER


NAME OF SUBCONTRACTOR (S) : PT DUTA JASA KONSTRUKSI
JOB / ACTIVITIY :

PT AE MATERIAL HANDLING SYSTEMS

Ref: AE-JMS-001
Page 3 of 5

JOB METHOD STATEMENT


PROJECT TITLE : KARIANGAU CFSPP 2 X 15 MW
LOCATION / FACILITY : TURBINE AREA

CONTRACT NO:
DATE :

NAME OF CLIENT : PT KARIANGAU POWER


NAME OF SUBCONTRACTOR (S) : PT DUTA JASA KONSTRUKSI
JOB / ACTIVITIY :

PT AE MATERIAL HANDLING SYSTEMS

Ref: AE-JMS-001
Page 4 of 5

JOB METHOD STATEMENT


PROJECT TITLE : KARIANGAU CFSPP 2 X 15 MW

CONTRACT NO:

LOCATION / FACILITY : TURBINE AREA

DATE :

NAME OF CLIENT : PT KARIANGAU POWER


NAME OF SUBCONTRACTOR (S) : PT DUTA JASA KONSTRUKSI
JOB / ACTIVITIY :

Prepared By: PT AE MHS

Reviewed By : PT AE MHS

Approved By :

Signature

Signature

Signature

Name

Name

Name

Date

Date

Date
Reviewed By :
Signature
Name
Date
Reviewed By :
Signature
Name
Date
Reviewed By :
Signature
Name
Date

PT AE MATERIAL HANDLING SYSTEMS

Ref: AE-JMS-001
Page 5 of 5

You might also like