You are on page 1of 4

1 of 4

DEVELOPMENT CONSULTANTS
PRIVATE LIMITED
Reviewed for general conformance with Contract
drawings and specifications.
ACTION :

1 Approved

BGR ENERGY SYSTEMS LIMITED

Disapproved.

Approved except as
noted. Forward final
drawing.

For information/reference
only.

Approved except as
noted. Resubmission
required.

Information category with


comments. Resubmission
required.

Approval of Contract documents by the Consultant shall


not relieve the Seller of his responsibility for any errors
and fulfilment of Contract requirements.

POWER PROJECTS DIVISION

Digitally signed by Shouvik


Patari
DN: cn=Shouvik Patari,
o=DCPL, ou=DCPL,
email=shouvikp@in.dclgroup.
com, c=IN
Date: 2015.01.28 12:06:04
+05'30'

PROJECT : 2 X 660 MW IB TPS, JHARSUGUDA


FIELD INSPECTION AND TEST PLAN & CHECK LIST
FOR
EARTHING SYSTEMS

PREPARED BY

REVIEWED BY

D.ARUN BHARATH

APPROVED BY

K.SUBRAMANIAN

K.KALYANARAMAN

P - Perform

IR-Inspection Report

GRN-Goods receipt note

H-Hold

W - Witness

S- Surveillance

TR- Test Report

LB-Log Book

V - Verification

SR - Site register

P.O - Purchase Order

IMIR - Inward Material Inspection Report

R - Review

S - Surveillance

D.C - Delivery Challan

IRN - Inspection Release Note

RW-Random Witness PR-Protocol

TR-Test report

FITP - Field Inspection And Test Plan

A - An Activity checked & Cleared by Owner QA/QC /


BGRESL QA/QC

C - An Activity checked & Cleared by BGRESL Execution / Sub Contractor

B - An Activity checked & Cleared by Owner Executive Group / BGRESL Execution

DOCUMENT NO

: BGR/PPD/208/EL/FQP/0553

REVISION

: 00

DATE

: 13.01.2015

2 of 4

FIELD INSPECTION AND TEST PLAN & CHECK LIST


Package : EARTHING SYSTEM

S.NO

Item/Component & Operation

Doc No

:BGR/PPD/208/EL/FQP/0553

Rev No

: 00

Date

: 13.01.2015

Class of
Check

Type of check

PROJECT: 2X660 MW IB THERMAL POWER STATION

CUSTOMER: ODISHA POWER GENERATION CORPORATION


LIMITED

Inspecting Agency

Quantum/
Frequency
of check

Ref documents &


Acceptance std

Format of
Record

Remarks
SUB
Contractor

BGRESL

OPGCL

1.0

Receipt

1.1

Verify MDCC issued by BGR/OPGC(If


applicable), BGR&OPGC verified test
reports,Dispatch documents (LR & packing List
etc )

Visual

100%

PO,MDCC & LR/All the


documents shall be
available

IMIR

1.2

Veirfy the Dimesions of the Earthing


Conductors & Down conductors (MS Rods,
Galvanised MS Flats, Etc)

Measurement

Random (3
samples /lot)

PO,MDCC,IRN/ Material
shall confirm to IRN

IMIR

1.3

Verify the toatal Quantity in Kg/Mtons in


weighing Bridge with truck and tally with
packing list

Meaurement

100%

MDCC,IRN

IMIR

1.4

Veirfy the materials such as welding electrodes


and anti corrossion paints

Visual

100%

PO,MDCC/ IRN

IMIR

2.0

STORAGE

2.1

Ensure that Earthing Conductors are stored in


a covered space/outdoor in a well-drained &
raised area with firm surface

Visual

100%

FITP

,,,

2.2

Ensure that the storage area is free from


water logging.

Visual

100%

FITP

,,,

2.3

Ensure that the material is stored seperately


as per the type and dimensions and not mixed
up

Visual

100%

FITP

,,,

2.4

Consumables such as welding electrodes and


Anti corrosive painst shall be stored well
ventilated dry indoor area

100%

FITP

,,,

3 of 4

FIELD INSPECTION AND TEST PLAN & CHECK LIST


Package : EARTHING SYSTEM

S.NO

Item/Component & Operation

PROJECT: 2X660 MW IB THERMAL POWER STATION

Doc No

:BGR/PPD/208/EL/FQP/0553

Rev No

: 00

Date

: 12.01.2015

CUSTOMER: ODISHA POWER GENERATION CORPORATION


LIMITED

Class of
Check

Type of check

Quantum/
Frequency
of check

Ref documents &


Acceptance std

Format of
Record

Inspecting Agency
SUB
Contractor

BGRESL

OPGCL

3.0

ERECTION /INSTALLATION

3.1

Ensure the availability of approved Earthing


layouts of the respective area

Visual

100%

Check List

3.2

Ensure that the approved materials(type and


diemensions) are mobilized

Visual

Random Check

Check List

3.3

Ensure the availability of "Work permit" for the


respective area

Visual

100%

Check List

3.4

Ensure that the ground grid of the respective


area is installed at a depth of not less than
1000mm below finished grade during
installation

Measurement

100%

Check List

RW

3.5

verify the installation of Earth


Electrodes(auxiliary) during installation & pits
after installation at specifed points

Visual

100%

Check List

RW

3.6

Ensure that the Ground conductors welded


joints above and below ground(Before back
filling) are coated with 2 coats of anti
corrosive paintings

Visual

Random

Check List

3.7

Ensure the availability of riser projecting 300


mm above ground at specified points

Measurement

100%

Check List

3.8

Ensure the availability of two risers for each


floor and two distinctive earth terminals for
each equipments

Visual

100%

Check List

3.9

Ensure the connection of internconnected


earth flats above ground with risers

Visual

100%

Check List

3.10

Ensure the availabilty of grid extension for


connecting to the main plant grid

Visual

100%

Check List

EF -02

EF -03

Appd Drg /Method


Statement

4.0

TESTING OF INSTALLATION

4.1

Measurement of Earth pit resistance with and


without grid

Testing

100%

4.2

Verification of Earthing system continuity

Testing

100%

Appd Drg /Method


Statement

Remarks

OPGC Witness is
only for earth pits

4 of 4

FIELD CHECK LIST FOR EARTHING SYSTEM


AREA

DATE

ELEVATION

REPORT NO

DRAWING NO
SL.No

Description of Check

Verify the availability of approved Earthing layouts of the respective area

Check that the approved materials(type and diemensions) are mobilized

Verify the availability of "Work permit" for the respective area

Check that the ground grid of the respective area is installed at a depth of not less
than 1000mm below finished grade during installation

verify the installation of Earth Electrodes during installation & pits after installation at
specifed points

Verify that the Ground conductors welded joints above and below ground(Before back
filling) are coated with 2 coats of anti corrosive paintings

Check the availability of riser projecting 300 mm above ground at specified points

Check the availability of two risers for each floor and two distinctive earth terminals for each
equipments

Verify the connection of internconnected earth flats above ground with risers

10

Verify the availabilty of grid extension for connecting to the main plant grid

11

Measurement of Earth pit resistance with and without grid (Test report shall be
enclosed)

12

Verification of Earthing system continuity (Test report shall be enclosed)

BGRESL

OBSERVATION

Remarks

/ NA

OPGCL

You might also like