Professional Documents
Culture Documents
PGP-CM-MODULE-01
ASSIGNMENT NO: 01
COURSE TITLE:
PRINCIPLES AND
PRACTICES OF
MANAGEMENT
COURSE CODE PGCM11
DATE OF DISPATCH: 25/11/2015
LAST DATE OF RECEIPT: 30/11/2015
ASSIGNMENT TASK
PROJECT
Documents:
The project execution plan is on of a number of documents that
define the project and describe how the project will be delivered.
These documents are supported by management plans, policies
and procedures.
Documents under this project:
Scope of work
Approved budget
Approved schedule
Project execution plan
Design basis report
Technical specification and drawings for all works
Scope of work:
Completing civil work, MEP works and interior fit out works.
Internal roads and landscaping work is also forms the part of
works.
Project and site specific:
The wet/dry season cycle that imposes access, safety and
workability constraints on progress of the work.
Project Organization:
Clients
Contractor
Consultant and owners engineer
Architect, interior designer
The selection of personnel will be lean and is done by the
contractor and the project manager is a full-time worker. The
contractors personnel can be full-time or part-time workers. The
project employees will be available at their particular work
places.
Construction Team:
Champions the project.
Ensures relevant management plans are prepared and
implemented.
Oversees and reviews progress of the work on daily basis.
Manage and reviews safety and environmental performance on
a daily basis.
Manage contractual issues.
Manage industrial issues on the project site.
Negotiation and purchase of materials according to the
requirement of the clients.
Trains the personnel under his/her control in order to complete
the task.
Ensures the work is being completed in time according to the
schedule provided by the planning department.
Project Coordinator:
Leading the project team and coordinating the project.
Implementing the agreed action plan to the agreed standards
and deadlines.
Prepare project organization and communication charts.
Ensuring the effective preparation and delivery of all project
events and meetings and production of all necessary
documentation.
Maintain contract execution tracking log.
Track & manage contemplated change notices and change
orders in the database.
Prepare substantial completion certificates and ensure all
required project close out documents are obtained.
Keep the Project Manager (PM) and others informed about
project status and issues that may impact client relations.
Effectively and accurately communicate relevant project
information to the client and project team.
Quantity Surveyors:
Estimation of control cost.
Cost planning and cost controlling.
Preparation of bills of quantities for inviting tenders including
schedules of materials, labour, equipments and transport
requirements.
Interpretation and use of standard contract forms.
Management of contracts, billing and valuation of variations.
Assessment of interim and final payments, settlement of claims
and disputes.
Site Engineers:
Setting out the works in accordance with the drawings and
specifications.
Observance of safety requirements.
Resolving technical issues with employers representatives
Checking materials and work in progress for compliance with
the specified requirements.
Liaising with the company or project purchasing department
to ensure that purchase orders adequately define the
specified requirements.
Measurement and valuation ( in collaboration with the
quantity surveyor where appropriate).
Providing data in respect of variation orders and site
instructions.
Preparing record drawings, technical reports and site diary.
Job review of subordinate staff.
Supervisors:
Accomplishes construction human resource objectives by
selecting, orienting, training , assigning, scheduling,
coaching, counselling and disciplining employees;
communicating job expectations; planning, monitoring,
appraising job contributions, recommending compensation
actions; adhering to policies and procedures.
Meets construction budget by monitoring project
expenditures; identifying variances; implementing corrective
actions; providing non project annual operating and capital
budget information.
Approves construction projects by conducting inspections at
critical phases; obtaining approval from buyers.
Prevents fines and interruptions by complying with and
enforcing codes.
Maintains safe secure and healthy work environment by
following and enforcing standards and procedures complying
with legal standards.
Updates job knowledge by tracking and understanding
emerging construction practices and standards participating
in educational opportunities; reading professional
publications; maintaining personal networks; participating in
professional organisations.
Project Management:
Project Administration
Project systems developer
Inspection and auditing of work
Resource management
Safety management
Environmental management
Project Administration:
General correspondence
Site communications
Security
Filing
Site meetings
Receipt of drawing and documentation
Site purchase orders
Minor contract
Material control
Request for information register
Project systems developer:
Data migration.
Interfaces with other systems
Reporting configuration and deployment
Set up maintenance and security rights and access
permissions.
Contributing to technical strategy, policy and
procedure.
Development and operation of technical testing
programmes.
Production of technical documentation to agreed
quality standards.
Reporting on progress/issues to management and
users.
Inspection and auditing of work:
Inspection and test plans
Inspection reports
Non-conformance reports
Resource management:
Resource planning and allocation
Equipment maintenance
Equipment servicing
Equipment register
Inspection
Safety management:
Work permits
Operation procedures
Training
Operation competency
Inductions
Auditing
Incident investigation and reporting
Planning:
Level I Project Milestone Schedule: The level I schedule shall
include the most significant events in the project and planned
dates for the accomplishment of each. This will be developed at
the beginning of the project by the project scheduler and
maintained by the project controls engineer.
Summary Schedule: The summary schedule is a time sequence
network of summary activities and their associated planned
dates. It is done by the project scheduler by summarizing the
level III schedule and provides and overview of all phases of the
project for the periodic corporate management.
Level III Control Schedule: The level III schedule will be
prepared by the project scheduler utilizing the precedence
critical path method covering all phases of the project and
incorporating milestones and other key events defined in the
level I schedule. Activities included in the CS cover the
permitting, conceptual and detailed design, procurement,
construction, and start-up. Interfaces between all activities are
included which assures integration of all phases of the project.
The construction and start-up portions of the CS will be
developed in sufficient detail to logically complete the project
and to focus engineering and procurement with early need
dates. The CS will be utilized by the project team to monitor
and analyze construction and start-up activities and progress of
the engineering and sub contractors.
Estimating:
The estimate will be based upon preliminary engineering.
Architecture and interior designer fit out work. It will be based
on a well defined site plot plan, general arrangement drawings,
and preliminary drawings.
Risk Management:
Risk management for the project will be responsibility of all the
clients project management staff. It is expected that lessons
learned from previous projects and excellent planning will avoid
many of risks present on this type of project.
Selection of appropriate expertise, based on knowledge and
experience, will be fundamental in addition to the requirement
of good communications between the owner and each
contractor.
Quality:
A planned and systematic approach to the quality management
will be adopted for the project that will focus on delivering
project outcomes that are fit for purpose and meet or exceed
project requirements.
Quality Assurance:
The quality system used on the project will comply with the
requirements of AS/NZ ISO 9001:2000. A quality management
plan will be developed for the project by the project manager in
collaboration with the construction manager.
The management plan will include the following.
Responsibilities
Best practice
Continuous improvement
Procedures
Standard and codes
Audit and review
Correlative actions
Communications
Quality Control:
All construction work will be controlled through a site based
quality control plan. The key elements of the plan will be.
Conformance to the scope of work
Compliance with the specifications
Inspection and testing
The quality control plan will be developed by the construction
manager in collaboration with the project manager. The plan is
a controlled document and will be reviewed as required.
Environment:
A project specific environmental plan will be developed for the
project by the contractor in collaboration with the project
manager and coordinator.
The management plan will define the issues and process for
environment protection on the site and may utilize existing
procedures where appropriate. The management plan will
include the following.
Responsibilities
Targets and license conditions
Training and inductions
Communications
Procedures and mitigation strategies
Emergency response
Incident investigation and reporting
Waste management
Surface water
Air quality
Project Execution:
The site offices shall be prefabricated modular units
manufactured by the contractor and erected on the site and
shall be in compliance with local regulations.
The site offices will be fully furnished and well equipped with all
requirements of power, communications, sanitary and janitorial
services to make them fully operational with adequate
provisions of safety and security.
The offices will be maintained in the appropriate condition in line
with the contractual requirements and the international industry
standards.
Specific and detailed plans will be submitted to OE during
execution of the project for approval.
A camp with all facilities to accommodate for the manpower
required for this project is also readily available with all
messing, power, utilities and canteen services made available.
Engineering:
Understanding the nature, complexity and technicality of the
work to be carried out is of the utmost importance.
All data sheets will be prepared and submitted to local
authority for approval prior to release of purchase orders.
All drawings and technical data will be performed
electronically; distribution in the field will be hard copy. The
technical team will also be responsible for maintaining as
built documentation.
Engineering Execution Plan:
Detailed Engineering activities will be carried out at our
Engineering Office. Given the nature of the project, our
Engineering shall depute Engineering Coordinator and discipline
personnel viz. Electrical, & Civil for the period of 1 to 4 weeks at
the beginning of the project, for site basic survey, data
collection of existing facilities with respective tender
Corrective Maintenance:
Urgent reported faults.
Non urgent reported faults.
Non urgent faults reclassified as urgent due to the failure of
another element of the system.
A reclassified fault shall be a non-urgent fault, which due to
further faults or circumstances results in non-operation.
Faults shall be reported and logged as outlined in the
specification.
Problem Reporting, tracking and fixing Procedures:
24 Hour Fault Service with fault registration service, to which
the MSEB can report service faults that is manned or otherwise
actively monitored all the time.
Replacement of spare parts:
All replacement parts and consumables which are necessary for
the services shall be arranged. The list of the spare parts
needed shall be prepared along with the vendor so that the
replacement can be done easily.
Project completion:
Practical completion will be reached when the project works are
completed in accordance with the scope and performance
criteria and are functionally ready.