Professional Documents
Culture Documents
Education (DepEd) Basic Education Information System (BEIS) will be used and compared
in the reports for the various components of the project. Specifically, the objectives of the
results-oriented M&E are to:
Enhance learning and development- lessons from experience will provide
information on what work and not and thus serve as basis to adjust the approaches
or redesign if necessary;
Ensure informed decision-making quantitative and qualitative data will have to be
established as baseline and updated periodically for policy development;
Support substantive accountability responsibility for ensuring value for money, cost
efficiency and transparency in the implementation
Model for DepEd-ARMM and Civil Society Partners to enhance and build capacities
in the delivery and monitoring of ADM project
3. GUIDING PRINCIPLES AND APPROACHES
This BEAM-ARMM ADM M&E framework is developed consistently following the guiding
principles and approaches of BRAC Education Model on M&E, the Quality Assurance and
Accountability Framework of DepEd and the results-based monitoring and evaluation
system.
3.1 Managing for Results
As indicated in the project log frame, outcome monitoring will be the major emphasis of the
M&E activities. There will be a continual and systematic collection and analysis of data to
measure the performance of interventions towards the achievement of the defined outcomes
of the BEAM-ARMM ADM. It is not time-bounded activity; outcome monitoring must be
periodic so that change can be ascertained. Project components will accumulate information
on progress against the target outcome, which will then be periodically compared against
baseline. This will be carried out by tracking the outputs of each of the 4 Project
Components and measure their contributions towards the achievement of target outcomes
by assessing the change from baseline conditions. Relevance of the interventions- whether
the BEAM-ARMM ADM intervention contributes to the achievement of key outcomes;
supports the DepED ARMM priorities and targets appropriate groups, will have to be
assessed periodically. In order to conduct effective outcome monitoring, the Project will need
to establish baseline data, select outcome indicators of performance, and design
mechanisms that include planned actions such as filed visits, stakeholders meetings and
systematic analysis or reports.
Outcome monitoring is not the same as implementation monitoring. However, it is expected
that the project will still monitor the implementation of activities such as collection of inputs,
activities, and immediate outputs and systematically report this to provide information on
administrative, implementation and management issues that will have an impact to the
achievement of desired results. This monitoring should be planned and integrated with
outcome monitoring to avoid duplication and to lower transaction cost latter
3.2 Evidence based
Outcome evaluation will assess and validate what results were achieved, how and why they
were or were not achieved. Periodic and in-depth assessment will be undertaken to obtain
evidence of the actual impact of the project strategies focusing on improving access and
quality to basic education of students in target communities. The assessment will be done
cooperatively among the various implementing partners such as BRAC, the Facility NGO,
provincial based Civil Society Organizations and DepEd-ARMM. The assessment will also
look at the partnership strategies purposely to establish impact working with such partners in
a conflict environment like ARMM. Evidences will be gathered through the periodic reporting
formats, research and evaluation activities and most significant change stories. All data will
be gender disagreggated to allow analysis of the progress on addressing performance
disparity between boys and girls.
3.3 Analysis, learning and accountability
In order to maximize the impact of the project, it is critical that effective learning process and
analysis are nurtured so that innovations can be shared and applied. The results of both the
outcome monitoring and outcome evaluations will provide understanding of why the
change is or is not taking place. The analysis will help improve the implementation
processes and overall project strategy. This framework will also fulfill its responsibility for
being accountable to stakeholders for project expenditures, activities, outcome and impacts.
Reflecting the critical role of analysis, learning and accountability in monitoring and
evaluation, the framework allows stakeholders to: understand what changes are needed to
improve results and performance; identify lessons learned for future projects and programs,
and establish the success of the implementation ie assess whether project activities should
be expanded.
The M&E system will need to provide performance and impact information to stakeholders to
inform project management decision making and enable stakeholders to: assess progress
against schedules and targets; allocate the necessary resources and funds for effective
implementation; compare use of inputs and expenditure against resource schedules and
budgets; assess the quality of implementation. BRAC, DepED-ARMM along with all
implementing NGO partners will be involved in planning and review of the M&E system, as
well as analysis on the effectiveness of the innovations and approaches.
3.4 Gender Equity
This principle meant to promote and ensure that gender and development (GAD) goals are
integrated in various aspects of the projects operations and M&E. The BEAM-ARMM ADM
ensures that education opportunities are equally accessible to marginalized boys and girls.
Activities and strategies in this new education alternative delivery modality are congruent
with the gender equality goals and the results that the project is expected to attain- enable
young children-boys especially- to attend school at the same time help their families earn a
living; make better school facilities accessible to rural boys and girls; greater access of rural
boys and girls to good quality education; longer stay in school of boys, where male drop-out
is particularly high in ARMM; improved school performance of boy and girl students.
Likewise, project monitors and evaluators will be guided by GAD checklist for education in
their assessment for the gender responsiveness of the ADM project. This checklist will be
drafted by the Managing NGO using the harmonized Gender and Development Guidelines
developed and produced by National Economic Development Authority (NEDA), in
collaboration with the National Commission on the Role of Filipino Women (NCRFW) and
the ODA-Gender and Development Network. Collection of sex-disaggregated data, gender
specific information and conduct of research studies to further analyze gender issues/gaps
of education in ARMM shall be undertaken. The research findings will inform the detailed
implementation of activities to ensure gender-fair teaching and learning processes.
3.5 Simplicity
This principle underpins the BRAC Education Program M&E which is also adopted in the
development of this framework. BEAM-ARMM ADM M&E System is simply constructed yet
capable of producing detailed information. It is designed to track results and record activities
implemented using select limited set of Key Performance Indicators (KPIs).
With the view to obtain consistency in the data management, it is essential that indicators
and data collection methods be simple and clear, and the number of indicators to be
collected be kept to an absolute minimum. It is much better to have complete and accurate
data on a small number of useful measures than to have a comprehensive set of measures
for which the integrity and completeness of the data is uncertain.
Reflecting the simplicity principle, the framework consists of three key elements: tracking
inputs and outputs of project activities; organizing regular discussions with key stakeholders
on progress and problems with implementation; and annual review on critical performance
questions as the basis for the annual plan
As required, the monitoring and evaluation framework may expand and grow in complexity to
reflect changing needs and as insights for improvement are gained from experience.
3.6 Ethics
Monitoring and evaluation of BEAM-ARMM ADM activities are designed to comply with the
Australian Evaluation Society (AES) Code of Ethics. In brief, the code requires
systematic, data-based inquiry
competence of evaluators
integrity and honesty
respect for the security, dignity and self-worth of target groups, clients and other
stakeholders
careful consideration of the potential risks or harm to the client, target groups or staff
of the project
articulation and consideration of the diversity of interests and values that may be
related to the public welfare
Moreover, the implementing NGO partners and staff will be trained on the Do No Harm
(DNH) analysis as part of their annual planning and M&E work. This will include a more
detailed examination of how specific activities will engage (or are engaging) the communities
and the possible (or actual) positive and negative impacts these may have.
3.7 Modeling and Capacity building
Consistent with the overarching objective of the M&E is to model BRAC best practices on
M&E and build the capacity of DepEd-ARMM and CSO partners in ADM Project delivery and
monitoring. DepEd-ARMM and NGO partners will significantly learn from the intensive BRAC
M&E practices and experience developed over the years. For the BEAM-ARMM ADM,
outcome indicators will come from the Unified Basic Education Information System (UBEIS)
of DepEd-ARMM. Specific baseline outcome indicators will have to be shared and gathered
to serve as the basis in measuring the direct impact of the intervention. Improvement of
UBEIS as well as DepED ARMMs M&E capacity will have to be enhanced through trainings
and systems improvement. Key elements of the capacity building approach will be
established to support communities of practice in project evaluation and to promote a
learning culture so that evaluation findings will inform future actions. The M&E/Quality
Assurance Unit of DepEd-ARMM will also be capacitated.
M&E Responsibilities
Support the
institutionalization of
national education
innovation in ARMM
through technical
assistance and capacity
building for DepED
ARMM
Support the scale-up of
successful education
innovations in ARMM to
other regions of the
Philippines
Develop the M&E tools
Train all stakeholders on
M&E
Reporting and
communicating the
progress and outcomes
2. BRAC, Managing
NGO, Implementing,
NGOs, DepEd-ARMM
and other Implementing
Information Needs
Development plans or
concepts for muslim
education innovations
Lessons learned and
best practices
Results of RAMSE test
Partners
3. ARMM Regional
Planning Office
4. DepED ARMM
6. Local Government
Units, School
Management, Committee,
Parents
to all stakeholders
Conduct of in-depth
research
Harmonize the M&E
tools and reports across
various Donors in
ARMM
Disseminate program
results
Initiate Policy Dialogue
with national and field
level offices
Maintain an updated
BEIS database
Support the Divisions,
Districts and Schools on
planning and monitoring
Operationalize the M&E
framework
Use data and analysis
for policy development,
budgeting process
Prepare BEIS reports
on school and student
data
Share school
performance data with
community
Gather activity specific
data
Data on pupils,
teachers, school
physical facilities in
accordance with BRAC
reporting requirements
Actual interventions,
support received from
the project
Feedback on activities
from pupils, parents
Progress and impact of
implementation
Issues and problems in
the LGU affecting
implementation such as
security, right of way
Counterpart
requirements
based reporting format. Tools and forms will help ensure that each Key Performance
Indicator will be gathered in a systematic way.
The Managing NGO will coordinate with implementing NGOs and DepED ARMM on
establishing the baseline data for the outcome indicators. Once the baseline has been
gathered, it will serve as a guide to all implementing NGO partners for periodic reports.
In selecting information gathering methods, due consideration will be given to the cost,
reliability of data, skill needed, ability to quantify results and the richness of information
generated. This will also require some capacity building for those responsible for collecting,
analyzing and reporting evidence based data. See page __ for details of the table below that
is linked to the Monitoring and Evaluation Plan (to be drafted by the Managing NGO).
Table 2 Sample of data gathering and evidence based reporting that is linked to M&E
Plan
Method of data gathering
Findings to be
Performance Indicators
Presented in (Monthly
(Tools/forms)
report (MR); Quarterly
Report (QR); Annual
Report (AR))
Component 1
E.g Number, by gender,
Site visit and interview with
MR
children ages 4-5 attending beneficiaries
BEAM-CLC pre-school
classes
BEAM-ARMM ADM Monitoring
Form Report on Newly Opened
School (see annex X
Forms/Tools)
4.3 Plan for Milestone Review and Critical Reflection Events and Processes
In this component systematic planning time for reflection and analysis will help ensure that
data are transformed into valuable knowledge. By doing this, project management decisions
will likely build on the lessons learned as the project progresses. Likewise, M&E working
group can plan routine reflection events in order to validate project information coming from
observations, monitoring data and project visits; analysze the findings; and then use these
findings to inform project decision-making.
Critical reflection events should be held frequently during the project implementation.
Regular project review meetings maybe held monthly, quarterly, semi-annual or as deemed
necessary by the project. Periodic events maybe scheduled, such as a learning review
following a major training event or a lessons-learned workshop following a project
evaluation. Formal critical reflection and milestone review can occur at meetings of the
Project Management Unit, Senior Management Group and Steering Committee where a
decision can be made to proceed or not or scale up the project.
4.4 Plan for Quality Communication and Reporting
In this aspect of M&E it is important to think about when information is needed to make
critical management decisions with partners and key project stakeholders. Communicating
M&E findings is very important. Primarily, there are two fundamental reasons for quality
communication and reporting: 1.) for accountability purposes, and 2.) to maximize impact by
sharing information on project successes and shortcomings if there are any.
For primary stakeholders, they have an interest and right to know how the project is
progressing and provide them feedback to ensure the accuracy of the results. For AusAID,
BRAC, DepEd-ARMM, and MINDA it is important to account for the investment in project
inputs, progress toward goals and contribution to impacting on the quality of and access to
basic education in ARMM as well as to understand the challenges faced to make good
decisions. Communication and reporting is also a key element of the managing for impact
or results-based approach of BEAM-ARMM ADM. In particular M&E findings generate
knowledge of what works, what doesnt and why under certain conditions which needs to be
recorded and shared through formal and informal means to maximize its impact.
Sine M&E information is very important to inform project management decision, creating an
M&E Calendar will help ensure that information is available at the time required by those
who need it to inform management decision. The timely provision of information will enhance
the likelihood that it will be used. Further, an M&E Calendar establishes critical deadlines for
reporting. Please see below reporting M&E calendar.
Format
Key Messages
E.g. Progress
Monthly Report
Electronic
narrative
Microsoft word
A4
Bi-monthly
Monitoring
Report
Electronic
narrative
Microsoft word
A4
Yearly Progress
Report
Electronic
narrative
Microsoft word
A4
Achievements:
Facilitators
trainings
conducted,
parents forum
undertaken
Pedagogic
issues which
includes the
subject-based
teachinglearning issues
Achievements:
Summary of
outputs,
progress 4
major
components and
initial project
results (if theres
any; evidencebased)
Prepared by
BRAC and
Managing NGO
10th of every month
Submission to
AusAID and
DepEd-ARMM
15th of every
month
5th of the
following month
The key staff and partners with M&E responsibilities will be ensured to have the knowledge,
skills, tools and support to carry out their respective tasks. A well functioning M&E System
requires human resources, training as well as materials and financial resources.
The Managing NGO will lead the orientation on the M&E Plan/System to ensure that
Implementing NGOs, DepEd-ARMM and other key partners are familiar and have the
necessary skills on how to implement the M&E plan so they can effectively use the system to
record, store and analyze data as well as produce the necessary reports to inform decisionmaking. The project will also endeavor to investing project staff time in building capacities
within the project to integrate GAD or promote gender equality into the M&E.
Table 4: Example of Capacity Building Required for Stakeholders with M&E
Responsibilities
Stakeholders with M&E
Responsibilities
BRAC, Managing NGO
through its M&E Unit
M&E Responsibilities
Develop the M&E tools
Train all stakeholders on M&E
Reporting and communicating the
progress and outcomes to all
stakeholders
Conduct of in-depth research
Resources &
Capacities Required
Review of
existing
BRAC M&E
tools and
enhance/deve
lop tools
suitable for
BEAM-ARMM
ADM Project
5. SCOPE OF M&E
The scope of M&E activities is informed by the project strategy as documented in the Project
Design Document (PDD) and further defined in the Work Plan (to work on by Managing
NGO & Implementing NGO). The changing context and new understanding gained from
experience demands that the project strategy be adapted from time to time to maximize the
impact on improving the quality of, and access to, basic education in ARMM.
5.1 Project strategy
In determining the scope of the M&E framework, the first step was to review the logical
framework (logframe) incorporating outputs and activities defined in the work plan and cost
schedule of the Project Design Document. In addition, the LogFrame (Annex X) provides a
single project description against which to monitor progress and assess impacts and
services delivered. It is also reflected in the detailed activity schedule (Gantt Chart-to be
further refined by Managing NGO), resource schedule and cost schedule to better manage
project implementation and monitor project performance.
5.2 Annual plan
Translating a project strategy as outlined in the LogFrame into an annual plan that is clear to
the staff of Managing and Implementing NGOs and partner organizations transforms ideas
into action. Accordingly, activities listed in the Work Plan (to work on by Managing NGO
and Implementing NGO partners) are included in the M&E system. The Project
Management Unit will periodically review the project LogFrame and Work Plan in close
consultation with primary stakeholders to monitor changes in the planned activities.
10
Project Goal: Improved access to and quality of basic education for Out of School Boys and
Girls thereby contributing to the over-all improvement of basic education performance in
ARMM
Project Purpose: To provide opportunity for Out of School Boys and Girls in selected
communities in ARMM acquire pre-school and elementary education through the BRAC-like
alternative delivery model (ADM).
Strategic Objectives:
1.
2.
3.
4.
Increased access, participation and completion rates of boys and girls in basic
education
Improved learning achievements of boys and girls in elementary education
Engaged communities in basic education delivery through an alternative delivery
model
Capacitated DepEd-ARMM and NGO Partners in basic education delivery through
an alternative delivery model
Table 5: Milestones
Outputs
Component 1.Curriculum, Materials and Assessment
1.1. Preschool education curriculum and instructional materials
1.2. Primary education curriculum and Instructional materials
1.3. Student assessment tools
Component 2. Community Learning Centers
2.1. Preschools Learning Centers established
2.2. Primary education Learning Centers established
2.3. Preschool education completers
2.4. Primary education completers
Component 3. Capacity Building
3.1. Trained Managers (ARMM)
3.2. Trained Managers (Other regions)
3.3. Trained Supervisors and Trainers (ARMM)
3.4 Trained Supervisors and Trainers (Other regions)
3.5. Trained Project Coordinators and Organizers
3.6. Trained CLC Learning Facilitators
3.7. Trained parents and community leaders
Component 4. Management, Monitoring and Evaluation
4.1. Steering Committee organized
4.2. Provincial Steering/Advisory Committee organized
4.3.Project Management Unit established
4.4. Local NGOs engaged and capacitated
4.5. Provincial Field Offices established
4.6. Project Design for BRAC- ADM Philippines
Total
1 set
1 set
1 set
1,128
299
33,840
8,970
20
12
170
25
200
1,128
40,000
1
5
1
15
5
1
11
7. INFORMATION GATHERING
7.1 Data collection methods
Based on the output, outcome and impact indicators to be measured and evaluated,
consideration has been given to how data is to be collected, specifically:
moving from data collection to explaining successes and failures, deriving
understanding from various issues with stakeholders and making decisions
the reliability of data collected. In many cases triangulation of data generated from
different methods is proposed and validation of the results.
existing data gathering systems/tools from BRAC shall be utilized. Particular
consideration has been given to how these systems can be used and strengthened
where needed to meet the requirements of stakeholders
providing precise, scientifically verifiable data to measure the status or change of a
specific indicator and rich qualitative information on peoples experiences and
opinions
Having considered the input of stakeholders and assessed existing capacity, a range of
data collection methods have been identified in the M&E framework including:
12
Process or event
E.g Monthly
Progress review
Purpose &
Description
Review project
progress against
targets defined in the
Annual Plan, plan of
activities for
subsequent six
months
Whom to Involve
Timing
Monthly
13
14
describe the issue in full, and identify the proposed remedial action, its likely impact,
and the responsibility and timing for implementing it.
9.2 Frequency of reporting
The following reports and or studies shall be prepared during the project implementation.
Table 6: Example of Reports to be produced for various M&E Users
Type of Report
Contents
Responsibility
Recipients
Monthly Report
Quarterly Progress
Report
Completion Report
Research and
Special Studies
Advisers/Consultants
Reports
10. MANAGEMENT INFORMATION SYSTEM
The development of Management Information System (MIS) is very vital to effectively and
efficiently handle complex data, store and transform them into useful information and
knowledge. The MIS itself comprises of a number of different related systems development
for the various outputs and components of the project. Wherever possible basic packages
such as Microsoft Office products (including MS Excel and MS Access) are used to minimize
the recurrent cost of software licenses and avoid the large costs of developing and
maintaining customized software. The key elements of the MIS for the BEAM-CLC include
the following:
10.1 Training database
A user-friendly and flexible training database shall be developed and utilized during the
BEAM-ARMM ADM Project. A consultation shall be undertaken among NGO Implementing
partners to identify the information needed and ensuring that the data entered is of high
quality by using inputs, limiting lists and making key fields compulsory so that the reports
produced are accurate and reliable. The database allows results to be disaggregated and
analysed by gender, special needs groups (e.g. Lumads, Learning Facilitators, Parents),
and calculate absolute training numbers and the percentage of the target population that has
received training.
10.2 Student Tracking SystemEstablish student tracking system to monitor and assess progress and attainment of learning
competency of each pupil during project implementation. It shall also provide vital
information about status of pupils after completion in BRAC-like school especially those who
will enter in the public elementary and secondary schools. Collection and analysis of sexdisaggregated data are an important requirement of this system.
10.3 NAT and RAMSE
A simple MS Access database to allow easy input of NAT and RAMSE test results across
different sites, compilation of results and basic analysis which also interfaces with more
advanced analysis packages. This system serves as a resource for all PMU staff and
15
primary stakeholders in evaluating the impact of initiatives to improve the quality of basic
education. Collection of sex-disaggregated data is an important requirement in the analysis
of NAT and RAMSE results.
10.4 Quality and Financial management systemEstablish chart of accounts to be used in the BEAM-ARMM ADM Project reflect outputs
during the project implementation. The financial management system can generate reports
of reimbursable expenditure grouped as training, procurement and other costs at component
level. Similarly financial reports on expenditure covering fixed management fees and
milestone payments can also be produced.
16
Partly
yes*
Yes
Result
1. Involvement of women
and men in project
conceptualization and
design (max score: 2)
1.5
17
Partly
yes*
Yes
Result
1.5
2.0
2.0
1.5
Gender analysis is
included in the projects
design document. To
reduce gender disparity is
one of the primary foci of
the project and this is
18
Partly
yes*
Yes
Result
2.0
2.0
Research to determine
and address other gender
issues will also be
conducted.
9. Commitment of resources to
address gender issues (max
score: 2)
1.80
19
Partly
yes*
Yes
Result
18.30
*As evident from the scores in Boxes 5 and 6 and the sector-specific checklists, the summary score for
a partly yes for an element or requirement can range from 0.1 to 1.99.
20