Professional Documents
Culture Documents
GEST 88/138
5th Edition
February 2004
GEST 88/138
5th Edition
Euro Chlor
Euro Chlor is the European federation which represents the producers of chlorine
and its primary derivatives.
Euro Chlor is working to:
***********
This document has been produced by the members of Euro Chlor and should not be reproduced in
whole or in part without the prior written consent of Euro Chlor.
It is intended to give only guidelines and recommendations. The information is provided in good
faith and was based on the best information available at the time of publication. The information is
to be relied upon at the users own risk. Euro Chlor and its members make no guarantee and
assume no liability whatsoever for the use and the interpretation of or the reliance on any of the
information provided.
This document was originally prepared in English by our technical experts. For our members
convenience, it may have been translated into other EU languages by translators / Euro Chlor
members. Although every effort was made to ensure that the translations were accurate, Euro Chlor
shall not be liable for any losses of accuracy or information due to the translation process.
Prior to 1990, Euro Chlors technical activities took place under the name BITC (Bureau
International Technique du Chlore). References to BITC documents may be assumed to be to Euro
Chlor documents.
February 2004
Page 2 of 40
GEST 88/138
5th Edition
Chlorine is essential in the chemical industry and consequently there is a need for
chlorine to be produced, stored, transported and used. The chlorine industry has
co-operated over many years to ensure the well-being of its employees, local
communities and the wider environment. This document is one in a series which
the European producers, acting through Euro Chlor, have drawn up to promote
continuous improvement in the general standards of health, safety and the
environment associated with chlorine manufacture in the spirit of Responsible
Care.
The voluntary recommendations, techniques and standards presented in these
documents are based on the experiences and best practices adopted by member
companies of Euro Chlor at their date of issue. They can be taken into account in
full or partly, whenever companies decide it individually, in the operation of existing
processes and in the design of new installations. They are in no way intended as a
substitute for the relevant national or international regulations which should be fully
complied with.
It has been assumed in the preparation of these publications that the users will
ensure that the contents are relevant to the application selected and are correctly
applied by appropriately qualified and experienced people for whose guidance they
have been prepared. The contents are based on the most authoritative information
available at the time of writing and on good engineering, medical or technical
practice but it is essential to take account of appropriate subsequent developments
or legislation. As a result, the text may be modified in the future to incorporate
evolution of these and other factors.
This edition of the document has been drawn up by the Equipment Working Group
to whom all suggestions concerning possible revision should be addressed through
the offices of Euro Chlor.
February 2004
Page 3 of 40
GEST 88/138
5th Edition
Nature
7
Appendix 2
TABLE OF CONTENTS
INTRODUCTION
CONSTRUCTION CODE
12
3.1
Vessel Construction
3.1.1 Minimum Design Temperature
3.1.2 Test Pressure
3.1.3 Minimum Wall Thickness
3.1.4 Material of Construction
3.1.5 Welds
3.2
Accessories
3.2.1 Manhole or Handhole (if any)
3.2.2 Valves
3.2.3 Protection against Mechanical Damage during Transport and Storage
3.2.4 Relief Valves and Fusible Plugs
3.2.5 Thermal Insulation
3.2.6 Handling Consideration
12
12
12
12
12
12
13
13
13
18
18
18
18
18
4.1
Initial Commissioning
4.1.1 Vessel
4.1.2 Valves
4.1.3 Drying
4.1.4 Leak Testing
4.2
Maintenance of the Vessel
4.3
Filling
4.3.1 Handling the Containers
4.3.2 Weight Control
4.3.3 Procedure
4.3.4 Safety Measures in the Factory
4.4
Taking out of Service for Maintenance
18
18
19
19
19
19
20
20
20
22
22
22
22
TRANSPORT
5.1
Specific Precautions for Transport
5.1.1 Cylinders
5.1.2 Drums
5.1.3 Spheres
5.1.4 Drums and Spheres Loading and Unloading
February 2004
22
22
22
24
24
Page 4 of 40
GEST 88/138
5th Edition
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
24
24
26
28
28
28
30
30
31
31
7.1
Breathing Apparatus with Filter
7.1.1 The Filter
7.1.2 Filter Saturation
7.1.3 Storage of Filters
7.2
Self-Contained Breathing Apparatus - SCBA
32
32
32
33
34
34
REPORTING OF ACCIDENTS
35
10 EMERGENCY ORGANISATION
35
11 REFERENCES
35
36
37
Principle:
Equipment:
st
1 Example: Air at 0C Saturated with Moisture in the Barrel
nd
2 Example: Air at 20C Saturated with Moisture Contained in the Barrel
37
37
38
39
TABLE OF FIGURES
FIGURE 1: CYLINDER TYPICAL DRAWING
FIGURE 2: DRUM TYPICAL DRAWING FIRST EXAMPLE
FIGURE 3: DRUM TYPICAL DRAWING SECOND EXAMPLE
FIGURE 4: DRUM TYPICAL DRAWING THIRD EXAMPLE
FIGURE 5: CHLORINE CONTAINER - SAFRAP TYPE
FIGURE 6: CHLORINE CONTAINER - SPHERE TYPE
FIGURE 7: SCHEMATIC VIEW OF A VALVE
FIGURE 8: TYPICAL CYLINDER VALVE
FIGURE 9: TYPICAL DRUM VALVE
FIGURE 10: TYPICAL SPHERE VALVE
FIGURE 11: MANUAL ISOLATING VALVE PV)
FIGURE 12: EXAMPLE OF A TYPICAL INSTALLATION
February 2004
7
7
8
8
10
11
14
15
16
17
24
25
Page 5 of 40
GEST 88/138
5th Edition
1 INTRODUCTION
The recommendations given in this code represent the various measures
taken by the member companies of Euro Chlor for the construction and
handling of liquid chlorine drums, cylinders and spheres.
Study of chlorine accidents shows that small containers contribute to a
relatively frequent number of minor accidents. Euro Chlor, aware of the
continuing necessity to improve safety, has drawn up this guide.
This recommendation does not replace the national or international regulations
in force, such as the ADR, European Agreement concerning the international
carriage of dangerous goods by road, which should be universally respected
as standard practice (See GEST 74/31 - Tank Containers for the Transport
of Liquid Chlorine under Pressure). In general, they reinforce the
international codes and regulations by adding to them the experience gained
by the chlorine producers of the different countries.
February 2004
Page 6 of 40
GEST 88/138
5th Edition
Drums have a capacity between 500 and 3,000 kg. They are horizontal
cylinders. Typical examples are shown in figures 2, 3, and 4. The ends are
either convex or concave. The valves are either protruding or fully protected by
the container itself. In both cases, the valves are protected by a cover.
Figure 2: Drum Typical Drawing First Example
February 2004
Page 7 of 40
GEST 88/138
5th Edition
convex ends, 1 cover plate with two openings for the valves, 1 valve protection
cover. Total protection of both ends. Robust construction.
2 welded heads, 2 concave ends, 1 cover plate with 2 openings for the valves, 1
protection cover.
The sharp angles between ends and cylinder need particular attention for cleaning
and drying.
Figure 4: Drum Typical Drawing Third Example
February 2004
Page 8 of 40
GEST 88/138
5th Edition
Totally forged robust construction. Convex ends, removable end plate allowing for
easy inspection, valves on this concave plate protected with a cover; excellent
protection of the valves.
Typical dimensions
Capacity kg Cl
500
600
850
1000
2100
3000
Tare kg
265
450
650
650
830
1500
Diameter of the
vessel, mm
700 - 712
720
880
750 - 830
1150
1270
Total length
mm
1350 - 1400
1600
1650
2000 - 2200
2160
2500
Spheres
This category includes vertically standing vessels with valves on a manhole at
the top of the container, normally not in contact with liquid chlorine.
Diameter
Total height
Capacity
Tare
Safrap type
1100 mm
1720 mm
1250 dm
750 kg
Sphere type
1900 mm
2300 mm
3600 dm
1300 kg
February 2004
Page 9 of 40
GEST 88/138
5th Edition
February 2004
Page 10 of 40
GEST 88/138
5th Edition
550
500
30
2220
2000
560
50
Unit: mm
February 2004
5800 kg
1300 kg
3,6 m
4500 kg
4250 kg
15 kg/cm
25 kg/cm
Page 11 of 40
GEST 88/138
5th Edition
3 CONSTRUCTION CODE
3.1
Vessel Construction
The transport vessels should be designed according to international
regulations, ADR, and other national regulations as appropriate. The aim of
this text is to indicate the principal usual rules and the further constraints
which are imposed by the chlorine producers by way of additional safety
measures.
February 2004
Page 12 of 40
GEST 88/138
5th Edition
3.2
Accessories
February 2004
Page 13 of 40
GEST 88/138
5th Edition
February 2004
Page 14 of 40
GEST 88/138
5th Edition
Reference
1b
2
3
4
5
6
7
8
9
10
11
12
13
14
15
February 2004
DESCRIPTION
Body
Insert Seat
Stem
Packing Ring
Gland Follower
Handwheel
Cover nut (Outlet cap)
Gasket
Gland Packing
Bush
Stem Nut (Left hand
thread)
Short chain
Split ring
Circlip
Washer
Page 15 of 40
GEST 88/138
5th Edition
Reference
1
2
3
4
5
6
February 2004
DESCRIPTION
Body
Disc
Outside seal
device
Ring
Gasket
Internal screwed
ring
Reference
7
8
9
DESCRIPTION
Screwed bonnet
Hand wheel
Washer
10
11
12
Page 16 of 40
GEST 88/138
5th Edition
Reference
1
2
3
4
5
6
7
8
9
10
11
February 2004
DESCRIPTION
Screw stem
Screw key
Bearing
Stop ring
Handwheel
Packing nut
Packing ring
Packing gland
Outlet gasket
Outlet screwed cap
Stem
Reference
12
13
14
15
16
17
18
19
20
21
22
DESCRIPTION
Body
Gasket
Spring washer
Internal check body
Spring
Support nipple
Ball
Inlet dip tube
Bolt
Stud bolt
Nut
Page 17 of 40
GEST 88/138
5th Edition
Initial Commissioning
Chlorine producers receiving a vessel from the manufacturer or from repair
work should carry out a general inspection of the vessel and of the fittings.
These operations can be carried out either by the chlorine producer or by a
specialist organisation acting on their behalf and under their responsibility.
They should proceed to the following inspection:
4.1.1 Vessel
Examination of the internal surfaces. The following should be excluded:
February 2004
Page 18 of 40
GEST 88/138
5th Edition
February 2004
Page 19 of 40
GEST 88/138
5th Edition
4.3
Filling
The container should be filled at a filling installation which generally meets the
requirements laid down in chapter 6 of this recommendation.
February 2004
Page 20 of 40
GEST 88/138
5th Edition
Not OK
External visual
examination
DEGASSING AND
PURGING
NEUTRALISATION
OK
Ask supervisor
Abnormal
WEIGHING
CLEANING
DEPRESSURIZING
TESTING
Not OK
OK
Normal
WEIGHING
EMPTYING
Yes
>2% OVER
TARE
SCRAP
DRYING
WEIGHING
No
PERIODIC
RETESTING
No
>2% UNDER
TARE
No
FILLING AND
WEIGHING
CHECK WEIGHING
LABELLING
STORAGE
February 2004
Page 21 of 40
GEST 88/138
5th Edition
4.3.3 Procedure
The safety of the filling operation should be ensured by handling of the
returned containers with a written procedure and a check-list which may
easily be controlled.
4.3.4 Safety Measures in the Factory
The chlorine containers should be stored in a location which is isolated and
protected, that is to say sheltered from risks of collision or of fire or
explosion.
4.4
5 TRANSPORT
5.1
5.1.1 Cylinders
Care must be taken to ensure that cylinders are securely anchored for
transport.
Vertical loading has the advantage that the valve is in the gaseous phase,
which reduces the emission in case of a gaseous leak. However, because of
the shape of the cylinders, special provisions are necessary for anchoring
them.
Cylinders may be strapped or chained to rings securely attached to the
vehicle. Palletisation of cylinders is also widely used where the proper
loading and unloading equipment is available.
5.1.2 Drums
The preferred methods of securing drums are to use fixed chocks or
purpose made cradles. These can be used where the customer has suitable
lifting equipment or with self-unloading trucks.
If there is a need to roll the container to the rear of the truck for offloading, a
recommended method of containment in transit is to use chains with front
and rear blocking. Straps should be limited to securing individual ton
containers.
February 2004
Page 22 of 40
GEST 88/138
5th Edition
February 2004
Page 23 of 40
GEST 88/138
5th Edition
Types of Installation
The containers may be used in various types of application:
a) Single cylinder or drum arranged to deliver gas.
This type of installation is physically capable of only a low steady rate of
supply or very occasional short periods of high supply rate. A manual
isolating (auxiliary) valve mounted very close to the container is
recommended to prevent moisture ingress when disconnected. See figure
11.
Figure 11: Manual Isolating Valve PV)
PV
PI
Point of Use
Air
Flexible Connection
February 2004
Page 24 of 40
GEST 88/138
5th Edition
PV
Absorption
unit
Gas
PDSL
PS
Hot
water
Gas under
pressure
PS
PS
E
Air
Liquid
Point of
use
Vaporiser
TI
TA
Separator
Flexible connection
LEGEND
TI
TA
Liquid storage
Temperature
indicator
Temperature alarm
PS
PI
Pressure switch
Pressure indicator
Flexible
connection
PDSL Pressure difference switch low
PV
Pressure valve
February 2004
Page 25 of 40
GEST 88/138
5th Edition
6.2
February 2004
Page 26 of 40
GEST 88/138
5th Edition
February 2004
Page 27 of 40
GEST 88/138
5th Edition
Leak Detection
Chlorine detectors and alarms should be provided in unmanned buildings
housing chlorine drums or vaporisers, and should be considered for cylinder
installations.
Their value outdoors depends on the size of the installation and the manning
levels and response times achievable. Recommended alarm actions are a
distinct local audible alarm and a warning light outside the building.
The detector system should activate the alarm at 3-5 ppm chlorine. Lower
settings are liable to activate the system at every cylinder or drum change
and lead to mistrust in the alarm when it gives a real warning of a
malfunction.
6.4
Pipework
Pipework for lines carrying liquid chlorine or gaseous chlorine under pressure
should be constructed generally in accordance with Euro Chlor GEST 79/81
Dry Liquid Chlorine Piping Systems Located Inside Producer's or
Consumer's Plants. Pipe runs should be kept short and protected against
impact. Plastic pipes should not be used.
February 2004
Page 28 of 40
GEST 88/138
5th Edition
February 2004
Page 29 of 40
GEST 88/138
5th Edition
After any exposure to moisture the pipework should be thoroughly dried; the
joint rings should be changed after any hydraulic test.
For gaseous chlorine at atmospheric pressure or slightly below, plastic
pipeworks (preferably reinforced) may be considered when there is a risk of
moisture. Advice should be sought from the chlorine suppliers on suitable
materials.
All packings, gaskets and diaphragms, and all components of pipes, valves
and fittings should be resistant to the action of chlorine between the
foreseeable extremes of operating temperature and pressure. Gaskets should
never be used for liquid chlorine service.
Flexible connector pipes are often made from copper or alloys which are
subject to work hardening. They should be inspected at each cylinder
change, periodically heat treated and replaced if necessary.
6.6
Prevention of Suckback
Precautions must be taken to avoid damage to cylinders and drums due to
suckback of water or other chemicals present in the reaction or absorption
system.
6.7
February 2004
Page 30 of 40
GEST 88/138
5th Edition
Where the installation is shut down for a long period, it has to be fully purged
with dry air or dry nitrogen.
Tightness has to be periodically tested with diluted ammonia bottle.
Use always a correct gasket material and never use the same gasket twice.
See GEST 94/216 Experience of Non-Asbestos Gaskets on Chlorine.
If a valve does not open easily, never use too much force.
Do not use too long a key on drums and spheres. Do not use keys for
cylinders. If you cannot open the valve without too much forces, return the
cylinder to the supplier.
Use key recommended by the supplier.
Never use naked flames in the chlorine area.
The valves should always be either full open or closed.
6.8
Vaporisers
Vaporisers (also known as evaporators) are discussed in a separate GEST
75/47 Chlorine Vaporisers.
February 2004
Page 31 of 40
GEST 88/138
5th Edition
The user of a breathing apparatus shall be trained and tested for lung
function.
There are two main types of equipment:
breathing apparatus with filters,
self-contained breathing apparatus.
Both groups use a device: the mask (which is different for non-pressurised
and pressurised systems).
7.1
February 2004
Page 32 of 40
GEST 88/138
5th Edition
February 2004
Page 33 of 40
GEST 88/138
5th Edition
Any unused filter which has been opened must be replaced within six
months unless the mask has been stored in an airtight container.
7.2
February 2004
Page 34 of 40
GEST 88/138
5th Edition
9 REPORTING OF ACCIDENTS
Any accident or other incident involving liquid chlorine should be the subject of
a proper report, even when no liquid chlorine leak results. These reports
should be made out on the standard form provided by Euro Chlor for this
purpose (see GST Form
10 EMERGENCY ORGANISATION
The European chlorine producers have set up an international security
organisation to take account of any accident in which liquid chlorine is
involved. Emergency vehicles are permanently available for going out to the
scene of an accident, and personnel specifically trained in dealing with such
emergencies are available at the request of local authorities. The geographical
layout of the emergency system should be listed amongst the documents in
the possession of the driver, as well as the initial steps to be taken in the event
of an accident whilst waiting for assistance.
The driver should be trained in the application of these emergency plans in
order to be able to call for their application by the competent authorities.
The emergency vehicles must be equipped with the special material needed
for all kind of chlorine containers used in their geographic zone. The
emergency team has to be aware of the existence of special devices to isolate
a leaking valve or even to totally enclose a leaking cylinder.
11 REFERENCES
Following documents were largely used for the preparation of present
recommendation
a)
b)
c)
d)
February 2004
Page 35 of 40
GEST 88/138
5th Edition
12 REFERENCES
TO
RECOMMENDATIONS
EURO
CHLOR
GEST
February 2004
Page 36 of 40
February 2004
Page 37 of 40
=
=
4,868
0,702
5,570
=
=
0,7957
0,702
1,4977
=
=
0,2129
0,702
0,9149
February 2004
Page 38 of 40
2nd Example: Air at 20C Saturated with Moisture Contained in the Barrel
Pressure supplied by a compressor at 7 bar(a)
1st purge
For 1 m of air at 20C, i;e; a water content of 17,148 g/m,. 6 Nm of dry air
(0,86 m at 7 bar(a) pressure), with a dewpoint of minus 40C, containing
0,117g of water per Nm are discharged into the barrel giving 7 Nm of gas
mixture at atmospheric pressure , or 1m at a pressure of 7 bar(a).
The water content of the mixture is:
1 m * 17,148
6 m * 0,117
Total
=
=
17,148
0,702
17,850
=
=
2,55
0,702
3,252
=
=
0,464
0,702
1,166
February 2004
Page 39 of 40
GEST 88/138
5th Edition
February 2004
Page 40 of 40