Total Questions: 30
Choose one of the best choices available for each question. All questions are mandatory.
1. The customer wants to make a change to the project scope. The BEST thing for the PM to
evaluate is the:
a.
b.
c.
d.
Validated deliverables
Organizational process assets
Accepted deliverables
Change requests
4. A fire has just destroyed a warehouse that was being constructed as part of a large project
you are managing. What would have been the easiest way to ensure that this force
majeure would not significantly impact the cost of the project?
a.
b.
c.
d.
You are in trouble because there are three activities with no float
You have a lot of flexibility because you have activities with float
You do not have enough information to make a decision
Everything is fine because you have an even number of activities with and without float
Activity
Start
B
End
6. All of the following are inputs to the Verify Scope process EXCEPT:
a. WBS
c. WBS dictionary
d. Inspection
b. Bottom-up estimating
d. Control Costs
b. NPV
c. Indirect
d. Fixed
10. All of the following are parts of an effective change management plan EXCEPT:
a. Procedures
b. Standards for reports
c. Meetings
d. Lessons learned
11. Your project is currently scheduled to take 117 months. Based on the chart, you could
crash the project by five months at a cost of US $ 20,000. How long will the project take if
you select this option?
a. 55 months
b. 25 months
c. 112 months
Activity
Original Duration
in months
Crash Duration
in months
Time
Savings
24
22
18
15
23
C
H
Original Cost
in $
d. 117 months
Crash Cost
Extra Cost
$ 100,000
$ 114,000
$ 14,000
$ 117,000
$ 135,000
$ 18,000
19
$ 225,000
$ 245,000
$ 20,000
30
25
$ 114,000
$ 134,000
$ 20,000
25
23
$ 127,000
$ 130,000
$ 3,000
13. A project is over budget to date. Which of the following is not a reason this could have
occurred?
a. More work that planned was accomplished
supplier
c. Work was delayed
14. A project manager has a problem with a team members performance. What is the best
form of communication for addressing this problem?
a. Formal written communication
c. Informal written communication
15. One common way to compute estimate at completion (EAC) is to take the budget at
completion (BAC) and:
a. Divide by SPI
b. Multiply by SPI
c. Multiply by CPI
d. Divide by CPI
20. Two people on the same project team have just found out they are working on the same
work. This situation can be BEST characterized as a lack of:
a. A good WBS
b. A matrix organization
c. Sponsor direction
At this time, we expect the total project to cost 89 percent more than planned
When the project is completed, we will have spent 89 percent more than planned
The project is only progressing at 89 percent of that planned
The project is only getting 89 cents out of every dollar invested
b. Fixed costs
c. Overhead costs
d. Opportunity costs
23. Seven non-random data points that are still within the upper and lower control limit of a
control chart are:
a. Specification limits
plated
b. Out of control
c. In control
d. Gold
24. A manufacturing project has a SPI of 0.89 and a CPI of 0.91. What is the BEST explanation
for why this occurred?
a. The scope was changed
b. A supplier went out of business, and a new one needed to be found
c. Additional equipment needed to be purchased
d. A critical path activity took longer and needed more labor hours to complete
25. In a fixed price contract, which of the following might not be an output of the Administer
Procurements process?
a. Resource approvals
c. Contract changes
b. Payment requests
d. Records collected
26. Which of the following are GENERALLY illustrated BETTER by bar charts than network
diagrams?
a. Logical relationships
c. Resource trade-offs
b. Critical paths
d. Progress or status
28. All of the following are part of the Perform Quality Control process EXCEPT:
a. Pareto charts
b. Control charts
c. Inspection
d. Quality Audits
29. A team manager tells the project manager that her activity will be delayed four weeks. The
project manager investigates and determines that the delay will affect the projects
completion date. Who should approve the change?
a. Change Control Board
c. Team member
b. Project Manager
d. Sponsor
30. If Earned Value (EV) is US $ 300,000, Actual Cost (AC) is US $ 350,000 and Planned Value
(PV) is US $ 375,000. What does the Schedule Performance Index (SPI) indicate?
a. You are only progressing at 86 percent of the rate originally planned
b. You are progressing at 125 percent of the rate originally planned