PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
DOC NO:
Page 1 of 12
Rev : 1
HYDROTEST PROCEDURE
PRODUCTION FACILITY BANGKO CRESTAL 0-W1-57A
SR NO. 1259049 01 04770 000
SLO N
MARCH 2015
DESCRIPTION
BP3
DATE
RW
PREPARED BY
REVIEWED BY
CPI
APPROVED BY
WORK PROCEDURE
PQP NO:
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
Page 2 of 12
Rev : 0
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
DOC NO:
Page 3 of 12
Rev : 1
GENERAL
1.1 Scope
This specification covers the requirements of Hydrostatic Test
1.2 Codes and Standards
This specification supplements or modifies the requirements of :
1.2.1.RW / CPI Related Specifications and Procedures
SP-PI-PP-001
General Piping System
SP-PI-PP-002
Piping Specification
PP-PI-PP-008
Piping Fabrication, Erection, Inspection, and Testing
Spec.
PP-SC-GG-001 Piping Pressure Test Procedure
SWP-IM-II-001 Rev.0 Standard Working Procedure Hydrostatic Test
for Piping
1.2.2.Relevant Code and Standard
ASME B31.4
1.3 Units
The metric unit shall be applied as the measurement system in documents
as the measurement system in documents and drawings.
1.4 Material, Tool and Equipment
a. Press.& Temp. Recorder ITT Barton, Range Press. 0 1000 psig, Range
Temp. 0 1000C,Range Press .0 2000 psig,Range Tem. 0 - 100 0C,dan
Range Press. 0 3000 Psig,Range Temp 0 - 300 0C.
b. Pressure Gauge
c. Temperature Gauge
d. High Pressure hose connection 6000 psig
e. Fill Pump Alcon, Flow Rate 300 L/m, max. press. 150 psig
f. Spiral Hose Discharge 1 , Suction 3
g. Tool & Connection
h. Blind Flange (see Table 2)
i. Skillet (see Table 3)
j. Non asbestos Gasket
k. High
Pressure
Pump
2
units,
flow
rate
30
L/m,
max.
press.3625.96psigdan 5076.34 psig
2. GENERAL REQUIREMENT
2.1
General
2.1.1
2.1.2
For painted or insulated lines, the pipe joints that will be leak tested
shall not be painted or insulated or covered until the test has been
successfully completed.
2.1.3
2.1.4
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
PQP NO:
Page 4 of 12
Rev : 0
2.1.6
2.1.7
2.1.8
Fitting Rating
Test Pressure
(Psig)
#150
360
#300
925
#600
1850
#900
2775
3. EXECUTION OF TEST
3.1
General
3.1.1
3.1.2
3.1.3
Install the permanent pipe guide and pipe anchor before hydro test.
3.1.4
The highest point of line is the expansion loop and vent valve will be
installed on this point
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
DOC NO:
3.1.5
Page 5 of 12
Rev : 1
At least two (2) pressure gauges shall be provided for each test:
a. One (1) pressure gauge shall be installed in the piping system
near of pressure sources.
b. One (1) pressure gauge shall be installed in the piping system at
the highest point.
c. Pressure gauge range shall be between 1.5 3.0 times the test
pressure.
3.1.6. For isolation at a flanged joint willuse the skillet with the minimum
thickness is .. mm.
3.1.7. For the blind flange thickness should refer to ASME B16.5 Ed. 2003
(see Table 2). No handmade blind is allowed.
3.1.8. Care shall be taken to avoid over loading any parts of the supporting
structures.
3.2
Hydrostatic Test
3.2.1
and
road
crossing
g. Check all mechanical joint (flanges connection) using the leak test
solution and examination of full piping system under test shall be
carried out with particular attention to joints.
h. For piping system,increase pressure at each steps by 10%from100
% TP (test pressure)
i.
j.
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
PQP NO:
l.
Page 6 of 12
Rev : 0
Test pressure must never allowedto exceed 1.6 times the design
pressure.
3.2.3
3.2.4
The step release of the pressure for piping system shall be not more
than 10 % of the test pressure and especially to road crossing is
20%.
3.2.5
3.2.6
3.2.7
The water will be drain to temporary pit and then to canal around
the location.
4. ACCEPTANCE CRITERIA
4.1
Acceptance Criteria
No Leaks shall be observed as acceptance criteria for the piping system
except in the following cases:
a.Any leaks form gland packing such as valves at test pressure shall be
accepted subject to no leaks at normal operating pressure.
5. POST TEST
a. All equipment shall be completely drained after hydrostatic test. Draining
shall only be started after it is has been made sure that the vents are open
otherwise a partial vacuum or partial vacuum occurring.
b. The rate of drainage from equipment shall be controlled in respect to the
inflow of air to the equipment to prevent a vacuum or partial vacuum
occurring.
c. Spades, blinds and other equipment installed for testing are to be removed
on completion of testing.
d. Flushing shall take place before the piping system is reinstated.
e. Ring joints or gaskets must be renewed whenever a flanged joint is broken
after testing.
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
DOC NO:
f.
Page 7 of 12
Rev : 1
6. TEST RECORDS
a. Before commencing the hydrostatic test the following records shall be
completed and approved by RW / CPI and Subcont. These compiled record
will form the test pack.
b. Test packs will be compiled in two sections.
Section one will contain the information for the test and will contains the
following:
The test certificates which is used to sign off all documentation and
give the go ahead for the test and sign off for final acceptance of the
test.
WORK PROCEDURE
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
PQP NO:
Rev : 0
Page 8 of 12
D
e
s
TT
i
P
g
n
P MTP
r
e
s
s
u
r
e
90 %
90 %
80 %
80 %
70 %
70 %
60 %
60 %
50 %
50 %
J
Time
TTP
MTP
A
B
C
D
E
F
G
H
I
J
K
WORK PROCEDURE
DOC NO:
TABEL
PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
1. TEST PRESSURE FOR HYDROSTATIC TEST
Page 9 of 12
Rev : 1
WORK PROCEDURE
PQP NO:
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
Page 10 of 12
Rev : 0
WORK PROCEDURE
DOC NO:
PRODUCTION FACILITY
BANGKO CRESTAL 0-W1-57A
Page 11 of 12
Rev : 1
WORK PROCEDURE
PQP NO:
PRODUCTION FACILITY
BANGKO CRESTAL 0-0-82A
Page 12 of 12
Rev : 0