Code No: E5206
jnt

R09

JAWAHARLAL NEHRU TECHNOLOGICAL UNIVERSITY HYDERABAD


MBA II Semester Examinations, March/April - 2013
PRODUCTION AND OPERATIONS MANAGEMENT
Time: 3hours
Max. Marks: 60
Answer any five questions
All questions carry equal marks
---

1.a)
b)

Give the overview of Production and Operations Management ( POM).


Explain about various historical milestones in POM.

2.a)
b)

Explain the various steps involved in product development process.


Define value analysis. State its objectives.

3.a)
b)

Explain factors to be considered for selection of location of software industry.


Explain salient features of group technology. Explain the reasons for preferring it.

4.

The Tru-Rainbow company produces a variety of paint products for both


commercial and private use. The demand for paint is highly seasonal, peaking in the third
quarter. Current inventory is 250000 gallons and ending inventory should be 300000
gallons.
Tru-Rainbows manufacturing manger wants to determine the best aggregate plan by
using the following demand requirements and capacity plan. Demands and capacities are
expressed in thousands of gallons. The manger knows that the regular-time cost is Rs.1
per unit, overtime cost is Rs.1.50 per unit, subcontracting cost is Rs.1.90 per unit, and
inventory holding cost is Rs.0.30 per gallon per quarter.
Quarter
Demand capacities
Regular time
Overtime
Subcontracting

1
300
450
90
200

2
850
450
90
200

3
1500
750
150
200

4
350
450
90
200

The following constraint should be taken into while making a plan.


No backorders or stock outs are permitted
5.a)

Professional Image Briefcases is an exclusive producer of handcrafted, stylish cases. The


company assembles each case with care and attention to detail. This work requires the
completion of the six primary work elements listed here.
Work Element
A
B
C
D
E
F

Precedence
A
B
C,D
E

Time (min)
30
15
10
5
10
10
Cont2

www.jntuonline.com

www.onlineQP.com

om

.c
ne
i
l
n
tuo

::2::

jn

b)

i) Draw precedence diagram for the production process.


ii) Determine minimum number of work stations to assembly 50 cases in a 40 hour week
and iii) balance efficiency.
Define Line of balancing problem. State its objectives.

6.

Explain the steps involved in work sampling. State its merits and demerits over stopwatch
time study.

7.a)
b)

Define productivity. Explain about various types of measures of productivity.


Explain about various components of productivity life cycle.

8.a)
b)

Explain about various aspects of economics of quality assurance.


Explain the operating principle of double sampling plan using a flow chart. State its
merits over single sampling plan.

********