You are on page 1of 6

s.no.

sor no

item description
Granular Sub-base with Close Graded Material (Table:- 400-1)
Plant Mix Method (Construction of granular sub-base by providing
close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform
layers with motor grader on prepared surface and compacting
with vibratory power roller to achieve the desired density,
complete as per clause 401)
(i) for grading- I Material

1
Dry Lean Cement Concrete Sub- base (Construction of dry lean
cement concrete Sub base over a prepared sub-grade with
coarse and fine aggregate conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm, aggregate cement ratio
not to exceed 15:1, aggregate gradation after blending to be as
per table 600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial length
construction,
concrete strength not to be less than 10 Mpa at 7 days, mixed in
a batching plant, transported to site, laid with a paver with
electronic sensor, compacting with 8-10 tonnes vibratory roller,
finishing and curing.)
2
Cement Concrete Pavement (Construction of un-reinforced,
dowel jointed, plain cement concrete pavement M-40 grade
concrete over a prepared sub base with cement , coarse and fine
aggregate conforming to IS 383, maximum size of coarse
aggregate not exceeding 25 mm, mixed in a batching and mixing
plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints, joint
filler, separation membrane, sealant primer, joint sealant,
debonding strip, admixtures as approved, curing compound,
finishing to lines and grades as per drawing as per IRC 15 2011
and as per relevant clauses of section 602 of specifications
complete but excluding cost of steel in dowel bar and tie rods
etc.)
3

Add extra in item no.3 for the cost of steel in dowel bar including
cradle, laps etc, complete required as per design for Mild Steel
Add extra in item no.3 for the cost of steel in tie rod including
cradle, laps etc, complete required as per design for TOR Steel

Construction of Shoulders with approved material/selected soil i/c


excavation all lifts & leads i/c grading to required slope & camber
of 4% and compacting using vibratory roller of 80 to 100 kN
static weight to meet requirement as per relevant clause of 400.
Hard Shoulders (CBR value > 12)
Retro- reflectorised Traffic signs (Providing and fixing of retroreflectorised cautionary, mandatory and informatory sign as per
IRC :67 made of encapsulated lens type reflective sheeting vide
clause 801.3, fixed over aluminium sheeting, 1.5 mm thick
supported on a mild steel angle iron post 75 mm x 75 mm x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 cm x 45 cm x 60
cm, 60 cm below ground level as per approved drawing) (ii) 60
cm equilateral triangle
Direction and Place Identification signs up to 0.9 sqm size board.
(Providing and erecting direction and place identification retroreflectorised sign as per IRC:67 made of encapsulated lens type
reflective sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm supported
on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed
to the ground by means of properly designed foundation with
M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below
ground level as per approved drawing)

Cable Duct Across the Road (Providing and laying of a reinforced


cement concrete pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and toe of
slope to toe of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and sides
of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of
granular material free of rock pieces, outer to outer distance of
pipe at least half dia of pipe subject to minimum 450 mm in case
of double and triple row ducts, joints to be made leak proof,
invert level of duct to be above higher than ground level to
prevent entry of water and dirt, all as per IRC: 98 - 1997 and
approved drawings.) for single row

Cable Duct Across the Road (Providing and laying of a reinforced


cement concrete pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and toe of
slope to toe of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and sides
of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of
granular material free of rock pieces, outer to outer distance of
pipe at least half dia of pipe subject to minimum 450 mm in case
of double and triple row ducts, joints to be made leak proof,
invert level of duct to be above higher than ground level to
prevent entry of water and dirt, all as per IRC: 98 - 1997 and
approved drawings.)
Double Row for two utility services

unit

qty

rate

You might also like