You are on page 1of 3

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

PROJECT SCHEDULE

LSTK- SAVAIR ENERGY LTD.

CLIENT- ONGC-URAN
Activity ID

Activity Name

Duration Start

Finish

2016
Nov

INSTALLATION OF STANDBY FGRU


MILESTONES

458d

09-Nov-15

08-Feb-17

38d

09-Nov-15

16-Dec-15

Receipt of LOI

0d

09-Nov-15

A1010

Kick off Meeting

0d

08-Dec-15

08-Dec-15

A1020

Submission and Approval of DCI

8d

08-Dec-15

15-Dec-15

A1030

Submission of WCP/Insurance

1d

16-Dec-15

16-Dec-15

A1040

Contract Signing

1d

08-Dec-15

08-Dec-15

114d

08-Dec-15

30-Mar-16

A1050

Submission and approval of Overall Plot plan

15d

08-Dec-15

22-Dec-15

A1060

Submission and approval of Soil report

15d

06-Jan-16

20-Jan-16

A1070

Submission and approval of design mix

15d

21-Jan-16

04-Feb-16

A1080

Submission and approval of Foundation drawing of


Compressor Shed

15d

05-Feb-16

19-Feb-16

A1090

Submission and approval of Shed Structure drawing

21d

23-Feb-16

14-Mar-16

A1100

Submission and approval of Process design basis

10d

20-Dec-15

29-Dec-15

A1110

Submission and approval of PFD

10d

30-Dec-15

08-Jan-16

A1120

Submission and Approval of P&ID of the Package

10d

05-Jan-16

14-Jan-16

A1130

Submission and Approval of Process datasheet of


Compressor

31d

15-Jan-16

14-Feb-16

A1140

Submission and Approval of Mechanical datasheet of


Compressor

31d

15-Jan-16

14-Feb-16

A1150

Submission and Approval of datasheet of Motor

31d

15-Jan-16

14-Feb-16

A1160

Foundation drawing & design calculation for Standby Flare


Gas Compressor

15d

17-Feb-16

02-Mar-16

A1170

Submission and approval of datasheet of EOT crane

10d

09-Mar-16

18-Mar-16

A1180

Submission and Approval of PMS

10d

16-Dec-15

25-Dec-15

A1190

Submission and Approval of VMS

10d

16-Dec-15

25-Dec-15

A1200

Submission and Approval of Process datasheet of Cooler

21d

15-Feb-16

06-Mar-16

A1210

Submission and Approval of Process datasheet of


Compressor KODs

15d

26-Jan-16

09-Feb-16

A1220

Submission and approval of Foundation drawing of


Compressor auxillaries(Lube oil cooler, KODs etc)

15d

10-Feb-16

24-Feb-16

A1230
A1240

Submission and approval of Layout of OWS line


Submission and approval of datasheet of Field Instruments

21d
15d

07-Jan-16
20-Feb-16

27-Jan-16
05-Mar-16

A1250
A1260

Submission and approval of datasheet of MOV


Submission and approval of Datasheet of ESDV

15d
15d

15-Feb-16
15-Feb-16

29-Feb-16
29-Feb-16

A1270

Submission and approval of Electrical design basis

10d

15-Feb-16

24-Feb-16

A1280

Submission and approval of Electrical load list

10d

25-Feb-16

05-Mar-16

A1290

Submission and approval of SLD

10d

06-Mar-16

15-Mar-16

A1300

Submission and approval of Electrical & Instrumentation Cable layout


15d

16-Mar-16

30-Mar-16

A1310

Submission and approval of electrical cable sizing

15d

16-Mar-16

30-Mar-16

A1330

Submission and approval of Instrument index

15d

25-Jan-16

08-Feb-16

A1340

Submission and approval of I/O list

10d

09-Feb-16

18-Feb-16

A1350

Submission and approval of Instrument cable schedule

15d

19-Feb-16

04-Mar-16

A1360

Submission and approval of F&G layout & datasheet

15d

08-Mar-16

22-Mar-16

A1370

Submission and approval of PLC based panel

15d

19-Feb-16

04-Mar-16

A1380

Submission and approval of Piping GAD

21d

28-Jan-16

17-Feb-16

A1390

Submission and approval of Equipment layout

15d

22-Feb-16

07-Mar-16

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Jan

Feb

Mar

Apr

May

Jun

2017
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb Mar
08-Feb-17, INSTALLATION OF

16-Dec-15, MILESTONES
Receipt of LOI

A1000

ENGINEERING

Dec

30-Mar-16, ENGINEERING

Page 1 of 3

TASK filter: All Activities


Primavera Systems, Inc.

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

PROJECT SCHEDULE

LSTK- SAVAIR ENERGY LTD.

CLIENT- ONGC-URAN
Activity ID

Activity Name

Duration Start

Finish

2016
Nov

A1400

Submission and approval of Piping Isometrics

15d

12-Mar-16

26-Mar-16

A1410

Submission and approval of Flexibility analysis

15d

12-Mar-16

26-Mar-16

A1420

Submission and approval of Torsional analysis

10d

15-Mar-16

24-Mar-16

349d

08-Dec-15

20-Nov-16

PROCUREMENT
A1430

Placement of order for Soil Investigation

5d

23-Dec-15

27-Dec-15

A1440

Placement of Order for Screw Compressor package

10d

08-Dec-15

17-Dec-15

A1450

Placement of Order for EOT crane

20d

15-Feb-16

05-Mar-16

A1460

Reciept of EOT crane at site

140d

06-Mar-16

23-Jul-16

A1470

Placement of order of Piping items

10d

12-Mar-16

21-Mar-16

A1480

Reciept of Piping items at Ambernath

84d

22-Mar-16

13-Jun-16

A1490

Placement of order of Valves

15d

26-Dec-15

09-Jan-16

A1500

Placement of order of Control valves

25d

06-Mar-16

30-Mar-16

A1510

Reciept of valves at site

140d

10-Jan-16

28-May-16

A1520

Reciept of Control valves at site

196d

31-Mar-16

12-Oct-16

A1525

Placement of order of PLC panel

216d

05-Mar-16

06-Oct-16

A1530

Placement of order of ESDV

25d

01-Mar-16

25-Mar-16

A1535

Receipt of PLC panel at site

7d

07-Oct-16

13-Oct-16

A1540

Reciept of ESDV at site

196d

26-Mar-16

07-Oct-16

A1550

Placement of order of PSV

10d

06-Mar-16

15-Mar-16

A1560

Reciept of PSV at site

140d

16-Mar-16

02-Aug-16

A1570

Placement of Order for Fire detection items

15d

14-Aug-16*

28-Aug-16

A1580

Reciept of Fire detection item at site

84d

29-Aug-16

20-Nov-16

A1590

Placement of order of RMC/Cement & TMT bar

2d

23-Feb-16

24-Feb-16

A1600

Receipt of RMC/Cement & TMT bar at site

2d

25-Feb-16

26-Feb-16

A1610

Placement of order of instruments & Fittings

20d

23-Mar-16

11-Apr-16

A1620

Placement of order of Instrument and electrical Cables

20d

05-Mar-16

24-Mar-16

A1630

Receipt of Cables, JBs at site

70d

25-Mar-16

02-Jun-16

A1640

Placement of order of JBs

7d

05-Mar-16

11-Mar-16

A1650

Receipt of Instruments & Fittings at site

70d

12-Apr-16

20-Jun-16

A1660

Receipt of compressor package

336d

18-Dec-15

17-Nov-16

458d

09-Nov-15

08-Feb-17

CONSTRUCTION
A1670

Site mobilization for soil Investigation

2d

04-Jan-16

05-Jan-16

A1680

Starting Soil grading activity at site

15d

30-Dec-15

13-Jan-16

A1690

Pre fabrication of Structural shed at Ambernath works

35d

17-Mar-16

20-Apr-16

A1700

Pre fabrication of spools at ambernath works

80d

14-Jun-16

01-Sep-16

A1710

Pre fabrication of pipe support at ambernath works

35d

02-Sep-16

06-Oct-16

A1720

Site Mobilization for Civil and Structural works

1d

22-Feb-16

22-Feb-16

A1730

Tapping of Suction & Discharge line

20d

22-Feb-16

12-Mar-16

A1740

Compressor Shed Foundation casting work

30d

23-Feb-16

23-Mar-16

A1750

Erection of Compressor house shed

60d

21-Apr-16

19-Jun-16

A1760

Installation of EOT crane

10d

20-Jun-16

29-Jun-16

A1765

Lighting

12d

03-Jul-16

14-Jul-16

A1770

Commissioning of crane

2d

30-Jun-16

01-Jul-16

A1780

Raft & pedestal foundation work for Cooler, Oil seperators

40d

26-Mar-16

04-May-16

A1790

Underground piping work for OWS line

60d

15-Apr-16

13-Jun-16

A1800

Erection of Compressor auxillaries at its location

28d

04-Oct-16

31-Oct-16

A1805

Earthing

15d

04-Oct-16

18-Oct-16

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Dec

Jan

Feb

Mar

Apr

May

Jun

2017
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb Mar

20-Nov-16, PROCUREMENT

08-Feb-17, CONSTRUCTION

Page 2 of 3

TASK filter: All Activities


Primavera Systems, Inc.

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

PROJECT SCHEDULE

LSTK- SAVAIR ENERGY LTD.

CLIENT- ONGC-URAN
Activity ID

Activity Name

Duration Start

Finish

2016
Nov

A1810

Raft & Pedestal foundation casting of Compressor & Motor

40d

07-May-16

15-Jun-16

A1820

Erection of Compressor package

20d

25-Nov-16

14-Dec-16

A1825

Feeder Modification

12d

06-Dec-16

17-Dec-16

A1830

Installation of Pipe supports at site

15d

04-Oct-16

18-Oct-16

A1835

Hot Tapping

20d

09-Oct-16

28-Oct-16

A1840

Interconnection piping work

20d

15-Dec-16

03-Jan-17

A1850

Cleaning & Flushing

3d

04-Jan-17

06-Jan-17

A1860

Hydrotesting

4d

07-Jan-17

10-Jan-17

A1870

Installation and calibration of Instruments

21d

11-Jan-17

31-Jan-17

A1880

Laying of cable trays

40d

10-Sep-16*

19-Oct-16

A1885

Panel Erection and commisioning

7d

10-Sep-16

16-Sep-16

A1890

Laying and termination of Cables

40d

20-Oct-16

28-Nov-16

A1900

Loop checking of Instrument cables

6d

29-Nov-16

04-Dec-16

A1910

DCS modification

21d

09-Nov-15

29-Nov-15

A1920

Precommissioning

7d

11-Jan-17

17-Jan-17

A1930

Commissioning & PGTR

3d

18-Jan-17

20-Jan-17

A1940

Punch points

10d

21-Jan-17

30-Jan-17

A1950

Handing over

9d

31-Jan-17

08-Feb-17

Actual Work

Critical Remaining Work

Remaining Work

Milestone

Summary

Dec

Jan

Feb

Page 3 of 3

Mar

Apr

May

Jun

2017
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb Mar

TASK filter: All Activities


Primavera Systems, Inc.

You might also like