You are on page 1of 71

Medium Voltage Distribution

MCset 17.5 kV
Air insulated switchboard
Withdrawable switchgear SF6 or vaccum technology

Installation instruction
January 2009

Contents

General

Glossary
Earthing switch control symbols
Moving part control symbols
Recommendations
Standard tightening torques
List of bags and accessories
Packaging

Dimensions and weights

6
9
10
10

Handling instructions

11

Installation and operation recommendation

13

Floor finishing and cubicle fastening

14

Surface condition
Floor quality
Description of irons and accessories
Placing and adjusting on non earthquake resistant
civil engineering works
Placing and adjusting on earthquake resistant
civil engineering works

11
11
11
12
12

14
14
14
14
16

Installation instructions

18

Installation of a FU equipped with


electromagnetic locking options

63

Steps to be taken for tests and inspection

65

Tests on site

66

Index

67

Unpacking cubicles
Placing cubicles in a switchboard
Coupling of cubicles
Plug-in check
Removing the mobile part transportation devices
Installing the main earth lead
Installing the electric connections of the busbars and MV cables
Installing busbars
Installing busbars between MTP and the MOTORPACT cubicle
Placing MV cables on AD cubicle
Placing MV cables on RHC cubicle
MV cable screen earthing
LV cable routing and connection
Placing the tunnel sheets
Placing the IPX1/IPX2 roofs or anti arc IPX1/IPX2
Placing the tunnel end sheets
Placing end sheets
Installing fans on versions 3600 A / 4000 A

Earthing switch with electromagnetic locking


Plug-in prevention with electromagnetic locking
Prior to installing the front panels
Power frequency dielectric test

Checking and cocking the internal arcing detector

version 05

2
2
3
3
4
4
5

AD, CL-GL, VT cubicles


RHB, RHC cubicles
Cubicle fitted with IPX1/IPX2 roofs
Transition Panel MTP
Land packaging
Ocean shipment packaging
Handling using a sling
Handling by rolling
Storage

07897301EN.indd

18
18
21
23
23
24
26
28
32
35
41
45
46
48
51
57
59
62

63
64
64
65
66

General

Glossary
Note: this document is available for all the units
ordered from the 2nd of April 2009.

UF

Functionnal Unit (cubicle + mobile part + Sepam)

AD

Incomming/outgoing cubicle

CL-GL

Withdrawable line coupling cubicle

TT

Measurement and busbar earthing cubicle

RHB

Connection from the top by bar

RHC

Connection from the top by bar cable

MTP

Connection duct between an MCset cubicle and a


MOTORPACT cubicle

DI

Fuse switch outgoing cubicle

TT

Voltage transformer

TC

Current transformer or current sensor

VPIS

Voltage Presence Indicating System

LV

Low voltage

MV

Voltage class, including levels 7.2 - 12 and 17.5 kV

SMALT

Earthing switch

Mobile part
LF

Withdrawable circuit-breaker with SF6 breaking which is


used in AD and CL cubicles

Rollarc 400

SF6 breaking withdrawable contactor equipping the AD1


cubicle

EVOLIS

Withdrawable circuit-breaker with vacuum breaking which


is used in AD and CL cubicles

CTV1

Vacuum breaking withdrawable contactor equipping


the AD1 cubicle

OED

Rack-in or rack-out and removal tool of the mobile parts


on the ground

Table
dextraction

Extraction or insertion table without the removal tool


of the mobile parts on the ground

Earthing switch control symbols

Plug-in prevention position.


Locking possible.

Plug-in or withdrawal position.

Operation position.

Open earthing switch mechanical indicator


light.

version 05

07897301EN.indd

General

Closed earthing switch mechanical


indicator light.

Position can be locked using paslocks.

Moving part control symbols

Operation position.

Plugged-in position.

Withdrawn position.

Insertion/extraction position.

Recommendations
Installation above the switchboard

All type of equipment installation such as lamp or light are forbidden.

Marking

It is compulsory forbidden to walk


on the parts bearing this marking.

It is compulsory forbidden to remove


the parts bearing this marking when
the equipment is energised.

07897301EN.indd

version 05

General

Standard tightening torques


(Non greased screws and bolts)

Screw

Torque in Nm

13

28

10

50

12

75

14

120

Application methods:
The elastic washers placed on the
external sides of the pads and busbars
ensure better distribution of stress
regarding screws tightened to the
recommended torques.

List of bags and accessories


Switchboard packaging

Package

Contenu

Switchboard end and fixing

- Switchboard end sheets


- Fixing columns
- Bag of screws and bolts
- Wiring collector external closure

Switchboard

- 2 cubicle operation cranks


- 10 mm2 wire
- 1 earth fishplate and seal
- Civil engineering guide
- Installation manual
- Operating manual

Civil engineering

- Cubicle fastening rails


- Expansion pins
- Bag of screws and bolts

Package (Optional)

Content

Tests and inspection

- Manual earthing kit

Spare parts

- Fuses

Optional accessories

- 1 busbar earthing carriage


- 1 phase balance testing device
- 1 I and U test lead
- 1 tunnel closure kit
- 1 mobile part extraction tool
(ERT or extraction table)

version 05

07897301EN.indd

General

Packaging

Content

Cubicle
packaging

Separate
packaging

- Busbar fastening

(1)

- Busbar shims

(1)

- Lock associated with the cubicle

- Lock unit

Screws and bolts for:

- Cubicle fastening on civil engineer. works

- Intercubicle fastening

- Coupling gaskets

Cable fastening (AD cubicle):


- Flange supports

- Flanges

Cable floor:
- Bottom plates

- Cable support sleeves

- Bag of screws and bolts

- Busbar 1250 A

- Cable connection brackets

- Busbar covers

- Zero frequence toroids

- Busbars 2500 A, 3150 A et plus

- Cable compartment

- Fan compartment (FU 3600 A/ 4000 A)

(1) in general.
(2) these parts can sometimes be dispatched in a separate package.

The tank installation drawings can be dispatched:


AD1 : AAV8094101
AD2 : AAV8900201
AD3 : BBV1456801.

07897301EN.indd

version 05

Dimensions and weights

AD, CL-GL, VT cubicles


Cubicles with 1 CT per phase, internal arcing withstand
and Gas Exhaust version (wall-mounted) or no internal arcing

Dimensions

AD1

AD2

AD3

CL1

(2500A)

(3150A)

(3600A)
(4000A)

CL2

CL3
(2500A)

TT1
(3150A)

TT2

DI2

(3600A)
(4000A)

Width (mm) L

570

700

900

900

900

570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570

700

700

Height** (mm) H

2300

2300

2300

2300

2445

2300

2300

2300

2300

2445

2300

2300

2300

Depth (mm) P

1550

1550

1550

1700

1700

1550

1550

1550

1700

1700

1550

1550

1550

Weight* (kg)

850

1000

1300

1700

1760

650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500

550

750

Weight (kg) of VT
compartment

120

130

130

130

130

120

130

130

130

130

130

130

120

* Maximum fully fitted weight.


** This dimension excludes cable flanges as well as any compartments placed under the cubicle.


version 05

07897301EN.indd

Dimensions and weights

AD, CL-GL, VT cubicles


Cubicles with 1 CT per phase, internal arcing withstand on 4 sides

Compartment for version


3600 A / 4000 A

Dimensions

AD1

AD2

AD3

CL1

(2500A)

(3150A)

(3600A)
(4000A)

CL2

CL3
(2500A)

TT1
(3150A)

TT2

DI2

(3600A)
(4000A)

Width (mm) L

570

700

900

900

900

570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570

700

700

Height** (mm) H

2300

2300

2300

2300

2445

2300

2300

2300

2300

2445

2300

2300

2300

Depth (mm) P

1725

1725

1725

1725

1725

1725

1725

1725

1725

1725

1725

1725

1725

Weight* (kg)

850

1000

1300

1700

1760

650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500

550

800

Weight (kg) of VT
compartment

120

130

130

130

130

120

130

130

130

130

130

130

120

* Maximum fully fitted weight.


** This dimension excludes cable flanges as well as any compartments placed under the cubicle.
07897301EN.indd

version 05

Dimensions and weights

Cubicles with 2 CTs per phase, internal arcing withstand


and Gas Exhaust version (wall-mounted) or no internal arcing

Compartment for version


3600 A / 4000 A

AD3

Dimensions

AD1

AD2

(2500A)

(3150A)

(3600A/4000A)

Width (mm) L

570

700

900

900

900

Height** (mm) H

2300

2300

2300

2300

2445

Depth (mm) P

1700

1700

1700

2000 (RHB3) 2275 (RHC3) 1700

Weight* (kg)

900

1050

1350

1750

1810

130

130

130

130

Weight (kg) of VT compartment 120

* Maximum fully fitted weight.


** This dimension excludes cable flanges as well as any compartments placed under the cubicle.

Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides


(installed in the middle of the room, no wall-mounting)

Compartment for version


3600 A / 4000 A

AD3

Dimensions

AD1

AD2

(2500A)

(3150A)

(3600A/4000A)

Width (mm) L

570

700

900

900

900

Height** (mm) H

2300

2300

2300

2300

2445

Depth (mm) P

1725

1725

1725

1725

1725

Weight* (kg)

950

1110

1400

1800

1800

Weight (kg) of VT compartment

120

130

130

130

130

* Maximum fully fitted weight.


** This dimension excludes cable flanges as well as any compartments placed under the cubicle.


version 05

07897301EN.indd

Dimensions and weights

RHB, RHC cubicles

Compartment for version


3600 A / 4000 A

Cubicles with 1 CT per phase, internal arcing withstand


on 4 sides (installation in the middle of the room, no wall-mounting)

Dimensions

RHB1
RHC1

2 cables max.
per phase

RHC1

3 to 4 cables
per phase

RHB2
RHC2

2 cables max.
per phase

RHC2

3 to 4 cables
per phase

RHB3 (2500A)
RHC3 (2500A) RHC3
2 cables max.
per phase

3 to 4 cables
per phase

RHB3 (3150A) RHB3


RHC3 (3150A)
2 cables max.
per phase

(3600A)
(4000A)

Width (mm) L

570

Height (mm) H

2300

570

700

700

900

900

900

900

2300

2300

2300

2300

2300

2300

2750

Depth (mm) P

2000

2275

2000

2275

2000

2275

2000 (RHB3)
2000
2275 (RHC3)

Weight* (kg)

950

950

1100

1100

1400

1400

1800

1820

Weight (kg) of VT compartment

120

120

130

130

130

130

130

130

* Maximum fully fitted weight.


Compartment for
version 3600 A / 4000 A

Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides


(installation in the middle of the room, no wall-mounting)

Dimensions

RHB1
RHC1

RHC1

RHB2
RHC2

RHC2

RHB3 (2500A)
RHC3 (2500A) RHC3
2 cables max.
per phase

3 to 4 cables
per phase

RHB3 (3150A) RHB3


RHC3 (3150A)
2 cables max.
per phase

(3600A)
(4000A)

Width (mm) L

570

570

700

700

900

900

900

900

Height (mm) H

2300

2300

2300

2300

2300

2300

2300

2750

2 cables max.
per phase

3 to 4 cables
per phase

2 cables max.
per phase

3 to 4 cables
per phase

Depth (mm) P

2000

2275

2000

2275

2000

2275

2000 (RHB3)
2000
2275 (RHC3)

Weight* (kg)

1000

1000

1150

1150

1450

1450

1850

1820

Weight (kg) of VT compartment

120

120

130

130

130

130

130

130

* Maximum fully fitted weight.


07897301EN.indd

version 05

Dimensions and weights

Cubicle fitted with IPX1/IPX2 roofs


(e.g.: AD1 with internal arcing withstand
on 4 sides)

Dimensions

AD1 IPX1

AD1 IPX2

Width (mm) L

570

570

Height (mm) H

2732

2732

Depth (mm) P tunnel

1815

2485

Transition Panel MTP


(Motorpact, vacuum technology,
Transition Panel)
This duct is factory-mounted to the right or left
of an MCset cubicle (depends on switchboard
configuration).
See MOTORPACT civil engineering guide :
46032-700-07A.

Dimensions

10

MTP
1250 A

2500 A

3150 A

Width (mm) L

375

375

375

Height (mm) H

2300

2300

2300

Depth (mm) P

1550

1550

1550

Weight (kg)

240

275

310

version 05

07897301EN.indd

Handling instructions

Land packaging
Functional Unit

Ocean shipment packaging


Functional unit

Cubicles packed by threes

Handling using a sling


FU with circuit-breaker

07897301EN.indd

version 05

11

Handling instructions

Handling by rolling

Storage
Store the devices in their original
packaging, placed on dry ground or on
a material insulating it from humidity.

Prolonged storage

12

After prolonged storage, thoroughly clean insulating parts before operation.

version 05

07897301EN.indd

Installation and operation


recommendation

The switchgears resistance


to ageing in an MV substation
depends on 3 main factors:

1/ The necessity of correct


implementation of connections:
New cold retractable or slip-on
technology offers ease of installation
that favours resistance over time.
Their design allows them to used in
polluted environments with harsh
climatic conditions.
2/ Impact of the relative humidity
factor:
Installing a heating device is essential
in climates with high relative humidity
levels and major temperature
differences.
Ensure that draughts and/or thermal
shocks are avoided in all cubicle
compartments in order to avoid the
creation of dew points (sources of
partial discharges).

Operation and maintenance

In case of dismantling, the elastic


washers must be change and replace
by new ones supplied by Schneider
Electric.

Outside normal conditions of use,


(between -5C and 40C , absence
of dust, corrosive gas, etc.), it is
recommended to
examine, with our Schneider Electric
services centre, the steps to be
taken, in order to ensure correct
functioning of the installation.

Our service centre is at your


disposal at any time:
b to undergo an installation diagnostic,
b to offer you, if need be, suitable
maintenance operations,
b to offer you maintenance contracts,
b to offer you adaptations.

Version 3600 A / 4000 A:


We strongly recommend that you
clean the ventilation grids A and B
regularly (every 2 years):
A: standard grids
B: grids only on RHB version.

A fan monitoring system must be


installed with the cubicle control
and monitoring devices.
Permanent operation of the
following must be guaranteed:
Cubicles types

version 05

3/ Electrical room ventilation control:


Grid size must be suited to the power
dissipated in the substation. These
grids must be placed exclusively
in the vicinity of the transformer, in
order to avoid air circulation on the LV
switchboard.

It is strongly advised to periodically


carry out, (minimun every 2 years
approximately), a few operation
cycles on operating devices.

After 6 to 12 month operations, we


recommend you to check the busbars
and MV cable connection tightening.
It should be done with a calibrated
torque spanner, adjust to lower torque
compare to values indicated in page 4.
If no problems are detected and if the
busbars and cable connections havent
been modified, it will not necessary to
do again this check.

07897301EN.indd

The equipment must be installed


in conformity with the relevant IEC
standard.
Outside of these normal usage
conditions, we recommend contacting
Schneider Electric to determine the
operations to be carried out as well as
their frequency according to the actual
service conditions.

An MCset 17.5 kV Maintenance


and Services guide is available.
It gives practical information on:
b maintaining the equipment in good
operating order,
b ensuring that the equipment is safe
during all installation, repair and
servicing operations.
DEAI03EN/ART833121
DEAI03FR/ART833120

Fans quantity
3600 A

4000 A

AD3, CL3

RHB3

13

Floor finishing
and cubicle fastening

Surface condition

Floor evenness is such that a 2 meter ruler moved over all surfaces and in all
directions, does not display a difference of more than 5 mm.

Floor quality

For the rolling of mobile part extraction tools without degrading the floor, it must
have acompression withstand u 33 MPa.

Description of irons
and accessories
Cubicle fastening

Take this equipment from


the civil engineering package
of the switchboard packaging.
Standard civil engineering:
- 1 iron section A (length 2m)
- 4 expansion pins B
- 2 fastening shims C.

Earthquake resistant civil


engineering:
- 2 iron sections A (length 2m)
- 8 expansion pins B
- 4 fastening shims C.

Place and fix the irons to the floor using


the supplied expansion pins, screws
and washers.

Note: in the case of a switchboard with


only cubicles AD3-CL3 leave a 40 mm
space for natural ventilation.

Placing and adjusting on non


earthquake resistant civil
engineering works
Preparation
Drill a hole in the floor and irons.

Placing the irons

Cut the last iron to the required length.

14

version 05

07897301EN.indd

Floor finishing
and cubicle fastening

Tightening irons

Do not bend the iron on installation.

Longitudinal adjustment:
using a the water level and using shims before
tightening the screws.

Transversal adjustment:
using a the spirit level and using shims before
tightening the screws.

For the correct installation of


cubicles, it is advised to comply with
a tolerance of 0.2 cm/m and a max.
gap of 10 mm/10m on the length of
the switchboard.

07897301EN.indd

version 05

15

Floor finishing
and cubicle fastening

Placing and adjusting on


earthquake resistant civil
engineering works
Preparation
Drill a hole in the floor and irons.

Placing the irons


Place and fix the irons to the floor using the supplied
expansion pins, screws and washers.
Cut the last iron to the required length.

Note: in the case of a switchboard with


only cubicles AD3-CL3, leave a 40 mm
space for natural ventilation.

16

version 05

07897301EN.indd

Floor finishing
and cubicle fastening

Tightening irons

Do not bend the iron on installation.

Longitudinal adjustment:
using a the water level and using shims before
tightening the screws.

The irons must be very smooth,


because adjustment using actuators
is not possible.

Transversal adjustment:
using a the spirit level and using shims before
tightening the screws.

For the correct installation of


cubicles, it is advised to comply with
a tolerance of 0.2 cm/m and a max.
gap of 10 mm/10m on the length of
the switchboard.

07897301EN.indd

version 05

17

Installation instructions

Unpacking cubicles
The preparation of cubicles must be carried out
on the premises where they will be installed.

To avoid damaging the FU


front panel components,
leave the protection
foam in place until the
switchboard is in
the operation phase.

Remove the 4 handling lugs (1 and 2).


The circuit-breakers are delivered in cubicles in a
withdrawn position.
Unpack the functional unit by removing the wooden
columns (8 screws), then the plastic cover.
Remove the cubicle packaging.

Placing cubicles in a switchboard


Assembling, adjusting and fastening

Note: place switchboard cubicles


according to front panel drawings and
the single-line diagram.
Start by placing the cubicle located in
the middle of the switchboard (except in
the case of an extension of the existing
switchboard) then position the cubicles
on either side of it, according to the Civil
Engineering Guide indications.

Depending on the type of civil


engineering, take the following from
packages:

1 bag of non earthquake resistant


civil engineering screws and bolts
n 51236072F0:
Rear adjustment accessories:
A: 4 x HM12 nuts
B: 2 quick cage nuts
C: 5 flat washers
D: 4 x (HM12x70) screws
E: 2 support irons.
Front fastening accessories:
F: 2 hook head bolts
G: 2 fastening shims
H: rubber anti-vibration plate.

1 bag of earthquake resistant civil


engineering screws and bolts
n 51236075F0:

Cubicle X must not impede cubicle


X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.

18

Rear fastening accessories:


H: 2 hook head bolts
K: 2 fastening shims.
Front fastening accessories:
H: 2 hook head bolts
J: 2 fastening shims.

version 05

07897301EN.indd

Installation instructions

Placing on maintenance space

Do not dismantle any part


of the cubicle.

Note: placing can be carried out by lifting or rolling.

Handling of the cubicle by rolling.

Adjusting cubicles on standard civil


engineering works
The operations described here after, must only be
carried out once the cubicle is positioned on civil
engineering works.

Position the support irons A and the


rubber anti-vibration plates B at the
rear of the cubicle by gaining access
through the maintenance space.

Place the 2 quick cage nuts C at the


rear of the cubicle, by gaining access
underneath the cubicle.

Screw the lock nut D on each actuator


E, place washer F, then screw the
actuators in the quick cage nuts C.

Lift the rear of the cubicle by screwing


the 2 actuators to level the cubicle

Cubicle X must not impede cubicle


X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.

07897301EN.indd

version 05

19

Installation instructions

Fastening to the floor on standard civil


engineering works
Note: remove the front panel if the cubicle is fitted
with VT, it is first necessary to remove them, refer
to the operating manual (07897302), the chapter
on Instructions for access to the interior of a
cubicle.

To be retrieved from the bag of screws


and bolts.

Place the fastening screws at the front


of the cubicle and tighten them.

To be retrieved from the two bags of


screws and bolts H and K.

Place the fastening screws at the rear


of the cubicle and tighten them.

To be retrieved from the two bags of


screws and bolts J and H.

Place the fastening screws at the front


of the cubicle and tighten them.

Fastening to the floor one earthquake


resistant civil engineering works
Note: remove the front panel if the cubicle is fitted
with VT, it is first necessary to remove them, refer
to the operating manual (07897302), the chapter
on Instructions for access to the interior of a
cubicle.

Cubicle X must not impede cubicle


X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.

20

version 05

07897301EN.indd

Installation instructions

Coupling of cubicles
Installing the inter cubicle gasket
Note: for a first generation switchboard extension,
consult the installation manual (07897302) First
generation switchboard extension.

Place the self-adhesive inter cubicle


gasket along the entire top part of the
right side of the cubicle, except on the
high end of the cubicle.
This operation is not necessary for
the cubicle on the far right side of the
switchboard.
Install the second cubicleby proceeding
in the same way as the first one and
tighten the actuators. Assemble the 2
cubicles together (10 fastening points).
Access to the fastening points:
- Refer to chapter on Instructions for
access to the interior of a cubicle in
the operating manual (07897302).
- See page 23 Removing the mobile
part transportation devices.

Assembling cubicles

The lifting rings and its nuts cages


associated must be removed.

A: assembly of HM8 x 30 screws + M8 washers


and HM8 nut.
B: assembly of HM8 x 16 screws + M8 washers
and M8 cage nuts.

C: assembly of HM6 x 16 screws + M6 washers and


HM6 nut + M6 washers.

Internal arc : 4 sides option.


For every square hole (nb : 6/side) on the side
of backplate, it shall be screwed to the one
located on its side with:
Screw : VAM HM8x30
Washer : Was. CS 8x18x1.4
Nut : HM8.

07897301EN.indd

version 05

21

Installation instructions

Assembling a MOTORPACT cubicle /


MTP transition panel
Left-hand fastening

Right-hand fastening

Implementation:
1: disassemble the transition panel (E) front and rear
panel sheets
2: open the front doors of the MOTORPACT top and
bottom compartments
3: disassemble the central front panel D of
MOTORPACT by withdrawing the 4 screws
4: disassemble the rear sheets of the MOTORPACT
compartments:
see manual (46032-700-08B), Installation guide
5: install screws (A), nuts (B) and washers (C) as
shown opposite.

22

version 05

07897301EN.indd

Installation instructions

Plug-in check

Each time a cubicle is coupled, check,


using the mobile part, that plug-in and
locking is correctly carried out at the
end of travel.

Removing the mobile part


transportation devices

To extract the mobile part and door closure, refer to operating manual
in the chapter on Operating instructions.
The operations described here after, must only be carried out once the cubicle
has been positioned on civil engineering works.

For the insertion and plug-in of the


mobile part as well as door closure,
refer to the operating manual
(07897302) in the chapter on
Operating instructions.

Do not handle the mobile parts before removing the wedges.

On circuit-breaker LF
1: remove the 2 transportation reinforcements
(3 screws per reinforcement)
2: place the 4 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:

On a ROLLARC/ CTV1 contactor


1: Remove the 2 transportation reinforcements
(3 screws per reinforcement)
2: place the 4 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:

On an EVOLIS circuit-breaker
1: remove the front panel screws
2: extract the circuit-breaker (out of the cubicle)
3: remove the top wedge with access
via the LV compartment
4: remove the wedge positioned on the circuit-breaker.
Tightening torque: 8.5 Nm.
5: on the first operation, remove the label:

07897301EN.indd

version 05

23

Installation instructions

On an EVOLIS LF circuit-breaker
1: remove the 3 transportation reinforcements
(3 screws for the lower reinforcement and 3 screws
for the upper reinforcement)
2: place the 6 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:

Installing the main earth lead


From the switchboard to the buildings
earth
Note: when the end sheets are placed, remove the
punch-outs from the sheets.
For a switchboard with a MOTORPACT cubicle at the
end, refer to MOTORPACT installation manual ref.
46032-700-08.

Connect the earth bar to the buildings earth at the end of the switchboard, on the
right and on the left, place the special fishplate by positioning the oblong hole on
the inside of the cubicle.
Tighten with a torque of 28 Nm (the fishplates for the end of the switchboard are
in the switchboard package)

24

version 05

07897301EN.indd

Installation instructions

Inter-cubicles MCset - MCset


and MCset - Transition Panel MTP
Note: this connection can be done during the
installation of each cubicle or at the end of
switchboard assembly.

The connection is located at the base of


the cubicle

Retrieve the self-adhesive seal in the


bag of screws and bolts.
Position this seal around the fishplate.

Install the fishplate by sliding it from


cubicle 2 to cubicle 1.

Put back and lock in place the fastening


screws. Use only screws HM8x30.
28 Nm tightening torque.
Stick the seal onto the cubicle sheet as
shown in A.

Inter-cubicles
Transition Panel MTP - Motorpact

The connection is located in the middle of the cubicle.


The MTP duct earth bar fish plate is installed at the factory.
When coupling it to the Motorpact, simply screw the MTP duct fish plate onto
the earth bar inside the Motorpact.

07897301EN.indd

version 05

25

Installation instructions

Installing the electric connections


of the busbars and MV cables
General information

Assemblies with bolts for MV and LV


internal equipment.
Screws and bolts to be used:
Class 8.8 according to standard
NF E 27 005, i.e. an elastic limit,
Re 630 Nm / mm.

Connection maintenance:
During downtime, check clamping of
connections with a torque wrench.
In the case of dismantling, change the
elastic washers.
Note: to carry out the following
preliminary switchboard operations see
chapter Instructions for access to
the interior of a cubicle.

Cubicle AD and CL without VT

Preliminary operations
to be carried out

Placing
busbars

Placing MV
cables

Extraction of the mobile part


(Optional)
Close the earthing switch
Remove the front panel
protective cover plates
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.

(Optional)

Remove the busbar access sheet


Remove the manhole sheet

Cubicle AD and CL with fixed VT

Placing
busbars

Preliminary operations
to be carried out

Placing MV
cables

Extraction of the mobile part


(Optional)
Close the earthing switch
Remove the front panel protective
cover plates
Remove the fixed VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.

(Optional)

Remove the busbar access sheet


Remove the manhole sheet

26

version 05

07897301EN.indd

Installation instructions

Cubicle AD and CL with withdrawable VT

Preliminary operations
to be carried out

Placing
busbars

Placing MV
cables

Extraction of the mobile par


(Optional)
Withdraw the VT fuses
Close the earthing switch
Remove the front panel protective
cover plates
Remove the withdrawable VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.

(Optional)

Remove the busbar access sheet


Remove the manhole sheet

TT cubicle with fixed VTs




Preliminary operations
to be carried out

Placing
busbars

Placing MV
cables

Remove the front panel


protective cover plates
Remove the fixed VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.

(Optional)

Remove the busbar access sheet


Remove the manhole sheet

TT cubicle with withdrawable VT

Preliminary operations
to be carried out

Placing
busbars

Placing MV
cables

Withdraw VT fuses
Close the earthing switch
Remove the front panel
protective cover plates
Remove withdrawable VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.

(Optional)

Remove the busbar access sheet


Remove the manhole sheet

07897301EN.indd

version 05

27

Installation instructions

Installing busbars

This connection is done during


the installation of each cubicle.
Access the busbars through the cubicle
side.
Retrieve;
- In package of the cubicle packaging,
the busbars
- In package of the cubicle packaging,
any busbar shims (if they exist).
If this is not possible, access through
the interior of the cubicle (refer to
chapter on Instructions for access to
the interior of a cubicle).

Place the busbar between the 2


previously assembled cubicles
(refer to chapter on Principle of
assembling busbars).
Block the fastening screws by
tightening on the side of the screw
heads.
50 Nm tightening torque.
Repeat these operations each time a
switchboard cubicle is placed.

Principle of assembling busbars


1250 A busbars
Bag of 1250 A busbars: 03407033F0.

A: top view of busbars


B: 1 x (100 x 8) bar per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 40 screws.

28

version 05

07897301EN.indd

Installation instructions

Evolis HP 2500 A busbars

A: top view of busbarss


B: 3 riser busbars
C: 2 x (100 x 8) per phase
D: nut

E: an type lock washer


F: flat washer
G: M10 x 55 screws
H: 3 hole shim.

A: top view of busbarss


B: 2 x (100 x 8) per phase
C: nut
D: fan type lock washer

E: flat washer
F: M10 x 55 screws
G: 3 hole shim
H: 6 hole shim.

2500 A busbars
Bag of 2500 A busbars: 03407034F0.

07897301EN.indd

version 05

29

Installation instructions

Evolis HP 3150 A busbars

A: top view of busbarss


B: 4 riser busbars
C: 3 x (100 x 8) per phase
D: nut

E: an type lock washer


F: flat washer
G: M10 x 55 screws.

A: top view of busbarss


B: 3 x (100 x 8) per phase
C: nut
D: fan type lock washer

E: flat washer
F: M10 x 70 screws
G: 3 hole shim
H: 6 hole shim.

3150 A busbars
Bag of 3150 A busbars: 03407035F0.

30

version 05

07897301EN.indd

Installation instructions

Evolis HP 4000 A busbars

A: top view of busbarss


B: 4 riser busbars
C: 4 x (100 x 8) per phase
D: nut

E: an type lock washer


F: flat washer
G: M10 x 55 screws.

4000 A busbars
Bag of 4000 A busbars: 51237530F0.

A: top view of busbars


B: 4 x (100 x 8) per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 85 screws (special)
G: 3 hole shim
H: 6 hole shim.

07897301EN.indd

version 05

31

Installation instructions

Cover mounting principle


(depending on needs)
Mounting the covers with clips

Retrieve: from package of the cubicle packaging, the covers.

Note: for mounting the covers with rings,


see page 34.

Position the half-covers on the


connection pads.

Close the covers on the bars.

MOTORPACT
to the right

MOTORPACT
to the left

Installing busbars between MTP


and the MOTORPACT cubicle
1250 A busbars
A: nut
B: contact washer
C: flat washer
D: M10 x 40 screws
E: 1 x (76 x 9,5) per phase
F: 2 holes shim
G: M10 x 60 screws
H: 1 hole shim.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.

32

version 05

07897301EN.indd

Installation instructions

2500 A busbars

MOTORPACT
to the right

MOTORPACT
to the left

MOTORPACT
to the right

MOTORPACT
to the left

A: nut
B: contact washer
C: flat washer
D: M10 x 55 screws
E: 2 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 70 screws.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.

3150 A busbars
A: nut
B: contact washer
C: flat washer
D: M10 x 70 screws
E: 3 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 80 screws.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.

07897301EN.indd

version 05

33

Installation instructions

Optional insulated busbars

MTP - Top views

Mounting the covers:


A: install a ring around the busbar, inside the cover
(allow to clamp the cover in position)
B: close the cover with rings
C: close the cover with clips
D: fit the entire cover assembly with clips.

For cover mounting, refer to the chapter Cover


mounting principle.

Mounting the covers with rings

Position the half-covers on the


connection pads.

34

version 05

Close the covers on the bars by


tightening the rings in the notches.

07897301EN.indd

Installation instructions

Placing MV cables on AD cubicle


General information
An explanation is given for all types of cables.
Retrieve: from package of the cubicle packaging,
back plates, flanges and fastenings.

A: 3 single-pole cables
B: 1 three-pole cable.
To access the interior of a cubicle (refer to the
operating manual chapter on Instructions for
access to the interior of a cubicle )

Cut cable bushings according


to the number and diameter of cables.

Install them on the cables.

Position the cable and its grommet


correctly between the sheets (A).

Fix and press the flange support


against the cable under the cubicle
floor.

To produce cable ends, refer to


accessories for manufacturer
instructions.

MV cable maintenance on AD cubicle


Successively assemble, after having installed a row
of cables:
- Flange support
- Flanges
- Back plates.

Fix the flange support under the floor,


after placing the cables vertical to
their attachment bracket.

Block the cables with half-flanges.

Reassemble bottom plates.


Fill in the openings that have not been
used with uncut cable bushing.

07897301EN.indd

version 05

35

Installation instructions

Height of cable insulation replacement

Type of cubicle

Configuration

AD1 - AD2

630 A

LV toroids

621

1 set of 3 CTs

454

2 sets of 3 CTs

438

LV toroids

621

1 set of 3 CTs

454

2 sets of 3 CTs

438

1 set of 3 CTs

477

2 sets of 3 CTs

459

1 set of 3 CTs

428

2 sets of 3 CTs

428

3150 A

1 set of 3 CTs

404

3600 A/ 4000 A

1 set of 3 CTs

653

1250 A

AD3

H (mm)

1250 A

2500 A

Surge arrester
Removing
In the case of an AD1 or AD2 cubicle
fitted with a surge arrester, access to
the cable compartment through the front
requires removal of the surge arrester
assembly.
1: remove the busbar surge arrester connection
2: remove the insulator support.

Placing
To place back into operation, carry out the operations
in the reverse order of removal.
Tightening torque
B: 50 Nm
E: 20 Nm.

36

version 05

07897301EN.indd

Installation instructions

Single-pole or three-pole cable without


toroid TC

Drill a hole in bracket A according


to the cable head to be connected.
Place and fix bracket A.

AD1 and AD2, 1, 2 or 3 cables per phase


An explanation is given for a phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.

Connect the cables.


Standard tightening torque corresponding to
of the bolts.

B: 50 Nm tightening torque.
Note: how the bracket fastening screws
are assembled:
1: M10 x 30 screws
2: M10 washer

After having installed a row of cables, then assemble


the support flange (see chapter on MV cable
maintenance on AD cubicle).

3: M10 nuts.
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.

Place and fix brackets A, C and D.


B: 50 Nm tightening torque.
Connect the cables.
Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on AD cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.

AD3, 1 to 4 cables per phase

Remove the bars.

07897301EN.indd

version 05

Drill a hole in the bars according to the


cable heads to be connected.

37

Installation instructions

Put back the bars with new washers.


Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.

Dielectric tests must be carried


out before connecting the surge
arresters.
Fix the surge arrester connections if
they exist.
Tightening torque:
B: 50 Nm
E: 20 Nm.

AD3 3150 A/ 4000 A up to 8 cables


per phase

38

Remove the bars.

Drill a hole in the bars according to the


cable heads to be connected.

Put back the bars with new washers.


Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.

Dielectric tests must be carried


out before connecting the surge
arresters.

A: screw
B: washer
C: nut
D: lug.

Tightening torque:
B: 50 Nm
E: 20 Nm.

version 05

Fix the surge arrester connections if


they exist.

07897301EN.indd

Installation instructions

Single-pole cable with toroid CT


on cubicle AD1 and AD2
AD1 and AD2, 1 or 2 cables per phase
The explanation is given for one phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
pads A and screws and bolts.

Drill a hole in pads A according to the


cable head to be connected.

Place and fix pads A.


50 Nm tightening torque.
Note: how the fastening screws
of the pads are assembled:
1: M10 x 30 screws
2: M10 washers
3: M10 nuts.

AD1 1 cable per phase

Place phase 2 cable in the toroid.

The explanation is given for one phase.


Do the same for the two other phases.

Note: how the cable head fastening screws are


assembled:
1: M10 x 30 screws
2: M10 washers
3: M10 nuts.

Standard tightening torque


corresponding to of the bolts.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).

AD2 1 cable per phase

07897301EN.indd

Connect the cables on the pads.

Place the cables in the toroids.

version 05

39

Installation instructions

Note: how the cable head fastening screws are


assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.

Connect the cables.


Standard tightening torque
corresponding to of the bolts.
Dielectric tests must be carried
out before connecting the surge
arresters.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).

AD2 2 cables per phase


AD3 2 cables per phase

Place the cables in the toroids.

Note: how the cable head fastening screws are


assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.

Connect the cables.


Standard tightening torque
corresponding to of the bolts.
Dielectric tests must be carried
out before connecting the surge
arresters.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).

40

version 05

07897301EN.indd

Installation instructions

Placing MV cables on RHC cubicle


General information
An explanation is given for all types of cables.
Retrieve: from package of the cubicle packaging,
back plates, flanges and fastenings.

A: 3 single-pole cables
B: 1 single-pole cable.
To access the interior of a cubicle (refer to the
operating manual chapter on Instructions for
access to the interior of a cubicle )

Cut cable bushings according


to the number and diameter of cables.

Install them on the cables.


To produce cable ends, refer to
accessories for manufacturer
instructions.

MV cable maintenance on RHC cubicle


Successively assemble, after having installed a row
of cables:
- Flange support
- Flanges
- Cables bushing plates.

Fix the flange support onto the cables


bushing plates, after placing
the cables vertical to their attachment
bracket.

07897301EN.indd

version 05

See chapter on MV cable maintenance on AD cubicle) for installation


instructions.

41

Installation instructions

Single-pole or three-pole cable without


toroid TC
RHC3 1250 A, RHC1 and RHC2 1, 2 or 3
cables per phase

Drill a hole in bracket A according


to the cable head to be connected.
Place and fix bracket A.

An explanation is given for a phase.


Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.

Place and fix brackets A and C.


B: 50 Nm tightening torque.

Note: how the bracket fastening screws


are assembled:
1: M10 x 30 screws

Connect the cables.


Standard tightening torque corresponding to of
the bolts.

2: M10 washer
3: M10 nuts.

After having installed a row of cables, then assemble


the support flange (see chapter on MV cable
maintenance on RHC cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.

RHC3 1250 A and RHC2 4 cables per


phase

Drill a hole in bracket A according


to the cable head to be connected.
Place and fix bracket A.

An explanation is given for a phase.


Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.

Place and fix brackets A.


B: 50 Nm tightening torque.

Note: how the bracket fastening screws


are assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.

Connect the cables.


Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on RHC cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.

42

version 05

07897301EN.indd

Installation instructions

RHC3 2500 A 4 cables per phase

Remove the bars.

Drill a hole in the bars according to the


cable heads to be connected.

Put back the bars with new washers.


Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.

RHC3 3150 A up to 8 cables per phase

Remove the bars.

Drill a hole in the bars according to the


cable heads to be connected.

Put back the bars with new washers.


Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.

07897301EN.indd

version 05

43

Installation instructions

Single-pole cable with toroid TC


RHC1 1or 2 cables per phase

Drill a hole in bracket A according


to the cable head to be connected.

An explanation is given for a phase.

Place and fix bracket A.

Do the same for the two other phases.


Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.

Note: how the bracket fastening screws


are assembled:
1: M10 x 30 screws

Place and fix brackets A.


B: 50 Nm tightening torque.

2: M10 washer
3: M10 nuts.

Connect the cables.


Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on RHC cubicle).

There are three ways of installing the toroids


(according to the width of the cubicles):
1: 1 single-pole cable
2: 1 single-pole cable
3: 2 single-pole cables.

Dielectric tests must be carried out before


connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.

44

version 05

07897301EN.indd

Installation instructions

MV cable screen earthing


On single-pole or two-pole toroid CT

The braid connection is done under the


cubicle.

In all cases, the insulated MV cable


screen braids must pass through
the toroids before connection to the
switchboard main earth lead.

In all cases, the MV cable screen braids


must be insulated and pass through the
zero frequence toroid before connection
to the switchboards earth.

The braid connection is done on


the switchboard earth bars in the
maintenance space.
Example: one cable per phase, 3 braids
to be connected. Two cables per phase,
6 braids to be connected.

On zero frequence toroid


Example of cable leadthrough:
A: 1 three-pole cable
1 cable per phase
3 earthing braids
B: 2 three-pole cables
2 cables per phase
6 earthing braids
C: 3 single-pole cables
1 cable per phase
3 earthing braids
D: 6 single-pole cables
2 cables per phase
6 earthing braids.

07897301EN.indd

version 05

45

Installation instructions

LV cable routing and connection


Incoming cables at the end
of the switchboard

Remove the roofing sheet on each


cubicle (6 screws).

Remove the cubicle cable troughs.

Place the strand and the feed wires.


Conduct the wiring cubicle by cubicle,
by passing wires through the cable
bushing of the cable troughs.
Reassemble the cable troughs.

Carry out connections to the terminal


blocks.

Remove the cable leadthrough sheet


located on the roofs of the cubicles (4
screws), as well as the roofing sheets(6
screws).

Cut the cable leadthrough sheets


according to the wires to be installed.

Reassemble the roofing sheets


(6 screws per sheet).

Incoming cables through the top,


cubicle by cubicle

46

version 05

Install the glands on these sheets and


pass the wires through.

07897301EN.indd

Installation instructions

Replace the sheet (4 screws).


Connect the wires to the terminal blocks
and fix the roofing sheet (6 screws).

Incoming cables from below,


cubicle by cubicle

Remove the cable trough.


Cut according to the number and the
diameter of the cables.

(maximum 5 diameters 20 mm) at the


base of the cable trough.

Remove the roofing sheets,and any


the cable leadthroughsheets (6 and 4
screws).

Thread the wiring as well as feeder


cables up to the cubicle roof.
Place the cable trough.
Place the wires on the terminal blocks,
then connect them.
Reassemble the roofing sheets (6 and
4 screws per sheet).

07897301EN.indd

version 05

47

Installation instructions

Placing the tunnel sheets


Wall-mounted anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).

4 side anti arc tunnel


A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle using four
screws (B) for MCset 1 and 6 screws (B) for
MCset 2 and MCset 3.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.

48

version 05

07897301EN.indd

Installation instructions

Wall-mounted anti arc tunnel for


versions 3600 A / 4000 A
Wall-mounted anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).

4 side anti arc tunnel for versions


3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the ventilation
compartment using four screws (B) for MCset 1
and 6 screws (B) for MCset 2 and MCset 3.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.

07897301EN.indd

version 05

49

Installation instructions

Installing a tunnel on a MTP transition


panel
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first.
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.

50

version 05

07897301EN.indd

Installation instructions

Placing the IPX1/IPX2 roofs


or anti arc IPX1/IPX2
Wall-mounted cubicle IPX1 roof
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).

Non wall-mounted cubicle IPX1 roof


A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the cubicle using four
screws (B) for MCset 1 and six screws (B) for
MCset 2 and MCset 3 for each sheet.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
3/ Fit the tunnel with each other using 5 screws
according to the vue (D).

07897301EN.indd

version 05

51

Installation instructions

Wall-mounted cubicle IPX1 roof for


versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).

Non wall-mounted cubicle IPX1 roof


for versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the ventilation
compartment using four screws (B) for MCset 1
and six screws (B) for MCset 2 and MCset 3
for each sheet.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
3/ Fit the tunnel with each other using 5 screws
according to the vue (D).

52

version 05

07897301EN.indd

Installation instructions

IPX1 roof on a MTP transition panel


The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first.
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.

Wall-mounted cubicle IPX2 roof


A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Fit the feet (4) onto the cubicle using two screws
(B).
4/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the feet (4) using two screws
(C) and on the angle bracket (2) using two screws
(C).
6/ Fit the tunnel with each other using 5 screws
according to the vue (D).

07897301EN.indd

version 05

53

Installation instructions

Non wall-mounted cubicle IPX2 roof


A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the cubicle using four
screws (B) for MCset 1 and six screws (B) for
MCset 2 and MCset 3 for each sheet.
2/ Fit the feet (4) onto the cubicle using two screws
(B).
3/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (2) on the feet (4) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).

Wall-mounted cubicle IPX2 roof for


versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Fit the feet (4) onto the cubicle using two screws
(B).
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the feet (4) using two screws
(C) and on the angle bracket (2) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).

54

version 05

07897301EN.indd

Installation instructions

Non wall-mounted cubicle IPX2 roof


for versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the ventilation
compartment using four screws (B) for MCset 1
and six screws (B) for MCset 2 and MCset 3
for each sheet.
2/ Fit the feet (3) onto the cubicle using two screws
(B).
3/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (2) on the feet (4) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).

IPX2 roof on a MTP transition panel


The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first and the feet (5).
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.

07897301EN.indd

version 05

55

Installation instructions

Tunnel sheets or IPX1/IPX2 roofs


for RHB cubicle
1/ Mount first the support sheets (1) furthest to the
rear of the cubicle continuing up to those positioned
at the front and the feet (3c)
2/ Mount the sheets (2) on the RHB duct part
3/ Mount the tunnel roof (3a) or the IPX1 roof (3b)
or the IPX2 roof (3c).
4/ Position the sheets of the adjacent cubicles,
installing the components in the order described
above.
5/ Fasten the support sheets of the two cubicles
to one another.
6/ Fasten the roofs of the two cubicles to one another.

* Ventilation compartments for version 3600 A / 4000 A.

Tunnel sheets or IPX1/IPX2 roofs


for RHC cubicle
1/ Mount first the support sheets (1) furthest to the
rear of the cubicle continuing up to those positioned
at the front and the feet (3c)
2/ Mount the access sheets (4).
3/ Mount the tunnel roof (3a) or the IPX1 roof (3b)
or the IPX2 roof (3c).
4/ Position the sheets of the adjacent cubicles,
installing the components in the order described
above.
5/ Fasten the support sheets of the two cubicles
to one another.
6/ Fasten the roofs of the two cubicles to one another.

56

version 05

07897301EN.indd

Installation instructions

Placing the tunnel end sheets


On anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle with
the screws (C)
2/ Fit the sheet (1) onto the tunnel with the screws (C).

On anti arc tunnel for version


3600 A/ 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle with
the screws (C)
2/ Fit the sheet (1) onto the tunnel with the screws (C).

07897301EN.indd

version 05

57

Installation instructions

On IPX2 tunnel
A: front of the cubicle
B: rear of the cubicle
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination.
1/ Fit the sheet (1) onto the cubicle and onto
the tunnel
2/ Fit the sheet (2) onto the tunnel feet on the front
face
3/ Fit the sheet (3) onto the cubicle, the tunnel
and the sheet (1)
4/ Fit the sheet (4) onto the sheet (1).

58

version 05

07897301EN.indd

Installation instructions

Placing end sheets


On the left end cubicle, place the cage nuts on the
sides.
Note: operations are identical for the right or left ends
of the switchboard.

Make sure that the busbar end cover


is assembled before mounting
the switchboards end covers.

On the left and right end cubicles, place and screw


(M8 screw) the 4 fastening columns of the end sheets
(right and left end of the switchboard).

Assembling cover panels of cubicle ends


Remove the punch-outsat the bottom of panels
to allow the main earth lead to pass through
(1 per panel).

07897301EN.indd

version 05

59

Installation instructions

On the right end cubicle, place the cage nuts on the


sides.

Assemble the end cover panels 1 and 2 (right and left


end of the switchboard).
A: HM8 screws+ M8 washers
B: HM6 screws+ M6 washers
D: assembly of HM8 x 30 screws + M8 washers
and HM8 nut + M8 washers.

60

version 05

07897301EN.indd

Installation instructions

Note: panel 3 is only assembled in the case


of a wall-mounted switchboard.
D: assembly of HM8 x 30 screws + M8 washers
and HM8 nut + M8 washers.

Place the cable sheet 4.


Place the two screws for fitting the cable sheet.

Store the cranks in the front end panel

07897301EN.indd

version 05

61

Installation instructions

Installing fans on versions


3600 A / 4000 A

Top view

Fasten the box using 10 screws A.


Connect the wiring in compartment B of the cubicle.

RHB

Maintenance procedures for vents and insulating


materials in the MCset 17.5 kV Maintenance and
Services Guide now available DEAI03F/ART833120.

62

version 05

07897301EN.indd

Installation of a FU equipped with


electromagnetic locking options

Earthing switch with


electromagnetic locking

For circuit-breaker plug-in and draw-out


operations, the earthing switch must be
operated.

FU delivered with the earthing switch


closed

As electromagnetic locking is not


supplied on installation of the FU, it
must be manually released in order to
operate the earthing switch.
Initial status:
- The earthing switch is closed,
- Selector 4 is in the locked closed
position.

Opening the earthing switch


without auxiliary supply

07897301EN.indd

version 05

Disassemble the VPIS without


disconnecting the wiring.

Insert a screwdriver via the box hole.

Push back and hold in place


the electromagnet (A) using the
screwdriver, then pull towards you
and turn the selector to the right in the
operation position.

Open the earthing switch, inserting


the crank in reference 5 until the
mechanical indicator light changes
status.

Position selector 4 in the locked open


position.

Put back the VPIS.

63

Installation of a FU equipped with


electromagnetic locking options

Plug-in prevention with


electromagnetic locking
Initial status:
- The circuit-breaker is in the withdrawn position.
- The earthing switch is closed.
- The front panel is disassembled to access cable
connections.

To access the cable connection compartment, circuit-breaker plug-in must be


prevented.
As electromagnetic locking is not supplied on installation of the FU, it must be
manually released in order to position the front panel when the operations are
complete.

The locking system is accessible as per the arrow in


the drawing opposite.

Prior to installing the front panels


If lever (A) is positioned as per figure 1, locking is
active and prevents installation of the front panel.
To deactivate the locking, insert a tool (screwdriver)
into the hole placed under the box support and push
the electromagnet rod (B).
Push the lever (A) to position it as per figure 2.
The system is released and the front panel can then
be put back.

Figure 1

Figure 2

64

version 05

07897301EN.indd

Steps to be taken
for tests and inspection

Power frequency dielectric test

This test must be performed by


authorised people.

This test can be carried out in one


single operation.

This preparation requires locking to be


forced.

All circuit-breakers must be plugged-in,


closed, with FU doors open.

It is essential to follow the sequences


here after.

All the TTs must be disconnected during


this test.

The insulation level of the switchgear


can be tested on site. The test voltage
shall be 80 % of the rated shortduration power-frequency withstand
voltage of the switchgear as specified
in clause 7.105 of IEC 62271-1.

More over, one of the outgoing FUs


must have its lower panel open for the
test cable
connection to the injection pin.

Locking forced

Carry out the circuit-breaker plugin operation (refer to the operating


manual).

On FUs not connected to the generator

Remove the shim.

Place the circuit-breaker in the test position,


with the door open.

Raise and block the door lock rod using


a 55 mm U shim.

Surge arrester connection

Press the pushbutton I to close the


circuit-breaker

This operation must only be carried out after dielectric tests,


and before the connection of medium voltage cables to the FU.
Place and fix the connection of each surge arrester.
Refer to the chapter on MV cable connection.

07897301EN.indd

version 05

65

Tests on site

Checking and cocking the


internal arcing detector(1)
This operation has to be made during assembly of the
tunnels (option) or during operation on the roof of the
cubicle.

The internal arcing detector is located


on the roof of the cubicle.
To be operational, it must be in cocking
position.

(1) The internal arcing detector is mounted according


to the internal arcing withstand characteristics of the
cubicle.
Cocking the internal arcing detector:
- Push the metal rod (1) in direction of
the bottom of the cubicle,
- Hang up the rod (1) on the support (2).

1: metal rod,
2: support.

66

version 05

07897301EN.indd

Index

AD, CL-GL, VT cubicles

C
Checking and cocking the internal arcing detector
Coupling of cubicles
Cubicle fitted with IPX1/IPX2 roofs

66
21
10

Description of irons and accessories

Earthing switch control symbols


Earthing switch with electromagnetic locking

Floor quality

Glossary

Handling by rolling
Handling using a sling

Installing busbars
Installing busbars between MTP and the MOTORPACT cubicle
Installing fans on versions 3600 A / 4000 A
Installing the main earth lead
Installing the electric connections of the busbars and MV cables

Land packaging
List of bags and accessories
LV cable routing and connection

Moving part control symbols


MV cable screen earthing

Ocean shipment packaging

Packaging
Placing and adjusting on non earthquake resistant civil engineering works
Placing and adjusting on earthquake resistant civil engineering works
Placing cubicles in a switchboard
Placing end sheets
Placing MV cables on AD cubicle
Placing MV cables on RHC cubicle
Placing the tunnel sheets
Placing the IPX1/IPX2 roofs or anti arc IPX1/IPX2
Placing the tunnel end sheets
Plug-in check
Plug-in prevention with electromagnetic locking
Power frequency dielectric test
Prior to installing the front panels

Recommendations
Removing the mobile part transportation devices
RHB, RHC cubicles

Standard tightening torques


Storage
Surface condition

Transition Panel MTP

Unpacking cubicles
07897301EN.indd

version 05

14
2
63
14
2
12
11
28
32
62
24
26
11
4
46
3
45
11
5
14
16
18
59
35
41
48
51
57
23
64
65
64
3
23
9
4
12
14
10
18
67

68

version 05

07897301EN.indd

Schneider Electric group service centers are there to provide:


- engineering and technical assistance,
- commissioning,
- training,
- preventive and corrective maintenance,
- adaptation work,
- spare parts.

07897301EN - REV. 05 a Schneider Electric Industries SAS All rights reserved.

Call your sales representative who will put you in touch with your nearest
Schneider Electric group service center or directly call the following telephone
number: +33 (0)4 76 57 60 60 Grenoble France.

Schneider Electric Industries S.A.S

As standards, specifications and designs change from time to time, please ask for confirmation
of the information given in this publication.


This document has been printed

on ecological paper.

954 503 439 RCS Nanterre


Capital social : 896 313 776

Publishing: Schneider Electric Industries SAS.


Design: Profil.
Printing:

35 rue Joseph Monier


CS 30323
92506 Rueil Malmaison Cedex
www.schneider-electric.com

07897301EN - REV. 05

01/2009

You might also like