finishing on time
It is important that you recognise that working as a team with the Builder is vital to overall
project success, however it must be on the basis that ultimately design and construction
matters must be decided by the Builder and not directed by the School. Directions from the
School that are not in accordance with the Builders obligations under the Contract will
transfer risks back to Government and could lead to cost (and time) overruns which must be
paid for out of the Schools project budget.
It is also important that you recognise that the architect and engineers are reporting to the
Page 1 of 14
work with you to confirm siting of the new building and later to confirm material and
colour selections
investigate and design for site specific issues i.e. electrical requirements, terrain,
demolition, contamination
a little later, work with you to scope the refurbishment works (if applicable)
manage the calling and letting of all subcontractor/trade contracts and manage
subcontractors generally.
Construction Cost
The Builder will submit a Target Construction Sum to DTEI for the Works. The Target
Construction Sum is made up of
for the new building work - a fixed price for the superstructure (all work above ground)
and a target price for the substructure, site works, site services, demolition and
remediation
for the refurbishment work (if applicable) an initial amount nominated by DECS.
The Builder and its design team will commence the process of completing the design of the
new building work with a focus on the site specific elements such as the footings, paving etc.
At a time nominated in the Contract (when the site specific information should be known and
the design is advanced) the Builder must submit a fixed price and program for the project
(the contract sets out the consequences of the submitted price and program not being
acceptable). Assuming all is well, the price and completion date will be approved and from
that point on the Builder has strict obligations to finish on budget and on time.
It is important that you recognise that from the time of approval of the Builders price and
completion date, you must not issue variations to the Builder i.e. ask the Builder to do
additional things or to change the design. The Contract has been structured in this way to
make sure the Builder remains accountable and to control the final cost of your project.
It is also important that you recognise that until the Builders price for new building work is
approved, the cost of your project will not be fully understood and the scope is subject to
variation. If there are risks that the Builder must address at your site (like problems with the
Page 2 of 14
Refurbishment Work
For the reasons outlined above, if your project includes refurbishment work to existing
buildings, the Builder will not start the process of considering the scope of work and the
associated design until after the fixed price and time for new building work is approved.
That will be about 10 weeks into the project. It has been arranged in that way to be sure that
the Builder is only being asked to scope refurbishment work for a verified budget amount,
and importantly to give some time for the School to work out its objectives for the
refurbishment work.
Once the final refurbishment budget is known, the Builder will bring its Consultants as
required to meet with the School and scope the work that must be undertaken in the existing
buildings. It will then submit to DTEI for approval an indicative scope of works and target
price for the refurbishment work (together with supporting information). The Builder must
ensure that the delivery of the indicative scope of works can be achieved within the approved
refurbishment budget and within the fixed completion date.
If the indicative scope of works and target price is approved, the Builder proceeds on to finish
the design and submit it with the associated final price for approval.
This might seem a somewhat complex process, but it has been implemented to ensure that
each School gets good value for its refurbishment works in an environment where the usual
budget and risk controls cannot be implemented.
Page 3 of 14
Geotechnical Report
Site Survey
If the Builder relies on any of the information it is responsible for ensuring its accuracy,
currency or completeness.
work with the Builder and its design team to confirm siting of the new building, material
and colour selection, refurbishment scope etc
ensure the school community provides input into the design process
ensure the Builder is fully briefed on the operational and functional needs of the school
community
work with Asset Services, DECS, to ensure any requirements are implemented on site
Page 4 of 14
ensure approved project parameters for scope, quality, time and cost are adhered to
DTEI will conduct the formal tendering and contract arrangements and will
arrange for cost managers to report on project financials and recommend contract
payments
manage the interface between the Builder and relevant Facilities Manager at completion
Useful Notes
Set out below are notes which it is hoped will assist you as you proceed through working with
your Builder to deliver your BER project.
Communication
Informal communication (information sharing)
The School Representative and the Builders Representative will discuss day-to-day site
management and co-ordination issues. Any community issues related to the school are to
be coordinated through the School Representative.
Formal communication (contractual issues)
DECS Asset Services, DTEI and the Builder will resolve any issues relating to the approved
scope, budget and program for the project, generally with input from the School.
Page 5 of 14
Meetings
All meetings will be arranged by the Builder. Issues to be addressed include:
Design meetings (in the initial weeks)
siting of new facility
site specific issues i.e. access, fire/bushfire, heritage, noise abatement, environmental
material selections
items to be re-used/salvaged
staging/decanting requirements
Site Administration/Management
The following are notes about the administration of the Contract and the management of the
Builders Site:
the School and Builder will agree the Builders construction area and the appropriate
hoarding/fencing
the School will advise the Builder on requirements for reporting and identification for the
Builders team and construction workers
the School will be providing the Builder with access to power and water but not to toilets
the Builder will set up its own office and amenities within its construction site and will
ensure that all necessary storage and bins are provided
Page 6 of 14
the Builder will be responsible for inductions onto the construction area and must have
an OHS&W plan including evacuation procedure and management of hazardous
materials (copy of register to be provided by school to Builder)
if the Builder finds asbestos or other hazardous materials it is accountable for their safe
removal. Note that all asbestos products must be removed outside of normal school
hours when staff, students and the general community (i.e. sporting clubs that may use
school facilities) are not present on site. Key issues for consideration include:
the Builder understands that smoking, alcohol and dogs are not permitted on site
Approvals
When the Builder wants to be paid for the work completed to date, it must make a payment
claim to DTEI. The claim for payment must be accompanied by photographs which clearly
confirm the completion of the work which is the subject of the claim for payment.
The School Representative will be requested by the Builder to verify that the photographs are
a true record of the progress on Site. The verification is in general terms and the School
Representative will not be requested to verify technical or construction detailing progress.
trained and inducted the School and Facilities Manager on the use of facilities and
equipment
agreed protocols for you to report any defects to the Builder during the next six weeks.
Completion
There is a six week period after Practical Completion until the works will be reassessed for
completion so that the Builder can request that the security money be returned and all
payments on the project can be finalised.
You can expect that at Completion the Builder has
Page 7 of 14
completed all outstanding items of work and corrected any defects identified to that time
removed all amenities, hoarding etc, left the site clean and removed the site sign
reaffirmed protocols for you to report any defects to the Builder during the 12 month
defects liability period.
Information
DTEI has established a contract information hotline if you have any enquiries relating to
design or construction matters. Please don't hesitate to ring the number at (08) 8207 7122
and our person will be able to either assist you personally or direct you to a DTEI person who
can.
Page 8 of 14
Appendix 1
1.1
Compliance statements that the Works are in accordance with the Principals Project
Requirements at the following milestones:
(a)
substructure complete
(b)
(c)
first fix
(d)
second fix
(e)
commissioning
(f)
practical completion
(g)
final completion.
1.2
Statement of approval where materials, products or finishes are substituted for those in the
reference documents
1.3
Statement that samples submitted are in accordance with the intent of the Principals Reference
Design or are an approved substitution.
1.4
Statement that tests required under the Contract have been undertaken and have passed.
1.5
1.6
1.7
1.8
Collection and retention of Quality Control documents including the above statements,
inspection reports, submission approvals, test results, planning approval, building rules
certification, site contamination assessment, geotechnical report, correspondence and notes of
meetings with authorities, authority approvals, warranties and warranty schedule,
commissioning reports, waste management plan etc. for a period of three (3) years or the
warranty period, whichever is greater.
2.
Architectural Consultant
The following services shall be provided by a recognised professional in the discipline of architecture,
with preference for an architect (registered).
2.1
2.2
(b)
(c)
(d)
Orientation
(e)
(f)
Selection of materials and finishes that integrate with the schools context and
Page 9 of 14
3.
(b)
(c)
Heritage considerations
(d)
Noise abatement
(e)
Environment (arid, coastal etc - corrosion & material specification issues etc)
3.1
3.2
4.
Design of Structure
(a)
Calculations for the superstructure design taking into account site specific conditions
such as wind loading and corrosive environment.
(b)
(b)
Contamination management
(c)
(d)
Earthworks design
(e)
(f)
(g)
Design for access (accessible pathways and thresholds in accordance with AS1428
and the Disability Discrimination Act - 1992)
4.1
(b)
(c)
Compliance statements that the Works are in accordance with the approved
Refurbishment design and documentation, DECS and DTEI Guidelines, at the following
milestones:
(a)
demolition complete
(b)
(c)
Page 10 of 14
(e)
commissioning
(f)
practical completion
(g)
final completion
1.2
Statement that the Refurbishment Work is in accordance with the Principals Project
Requirements.
1.3
1.4
1.5
1.6
Collection and retention of Quality Control documents including the above statements,
inspection reports, submission approvals, test results, planning approval, building rules
certification, correspondence and notes of meetings with authorities, authority approvals,
warranties and warranty schedule, commissioning reports, waste management plan etc. for a
period of three (3) years or the warranty period, whichever is greater.
2.
Architectural Consultant
The following services shall be provided by a recognised professional in the discipline of architecture,
with preference for an architect (registered).
2.1
2.2
meetings with the nominated School Representative to determine the extent of work
that provides the best value-for-money educational outcome
(b)
(c)
(d)
creating new building base plans where necessary and supplying them to other
Consultants
(e)
(f)
undertaking preliminary design and documentation for submission to the Principal for
approval
(g)
(h)
2.3
Selection of materials and finishes that integrate with the schools context and
environment.
(b)
(c)
Heritage considerations
(d)
Noise abatement
(e)
Environment (arid, coastal etc - corrosion & material specification issues etc)
Page 11 of 14
3.1
3.2
4.
Design of Structure
(a)
(b)
Inspection and determination of the existing buildings structure and its condition,
(c)
(d)
(e)
Liaison and supply of documents and estimates to the Principals Cost Manager to
enable an agreement on the scope of Refurbishment work for the nominated Upper
Limit Prime Cost Sum.
(f)
(b)
Liaison and supply of documents and estimates to the Principals Cost Manager to
enable an agreement on the scope of Refurbishment work for the nominated Upper
Limit Prime Cost Sum.
(b)
Inspection and determination of the existing services, their type, layout and condition
(c)
(d)
(e)
(f)
(g)
(h)
Liaison and supply of documents and estimates to the Principals Cost Manager to
enable an agreement on the scope of Refurbishment work for the nominated Upper
Limit Prime Cost Sum
(i)
Page 12 of 14
Appendix 2
Page 13 of 14
Appendix 3
Plan delivery
Facilitation
Builder
Professional
services
SCHOOL
Minister for
Infrastructure/DTEI
Contracts
Information
DECS
Consultants
Page 14 of 14