You are on page 1of 45

PETROIRAN DEVELOPMENT COMPANY

SALMAN OFFSHORE FACILITIES


(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 1 of 45

SALMAN OFFSHORE FACILITIES EPC-3


AMID CONTRACT NO. SALMAN 127 CONT 001
TECHNIP PROJECT NO. 9068G

JOB SPECIFICATION
SPECIFICATION FOR LAY BARGE
WELDING OF LINE PIPES

This document has completely changed from revision D1 to D2.


D2

11.07.04

RE-ISSUED AS FINAL

H.NOUROZI

S. VENUGOPAL

S. VENUGOPAL

J. BARRON

D1

20.12.03

ISSUED FOR APPROVAL

M.A.MOSTAFA

S. VENUGOPAL

S. VENUGOPAL

J. BARRON

D0

08.11.03

ISSUED FOR COMMENTS

M.A.MOSTAFA

S. VENUGOPAL

S. VENUGOPAL

J. BARRON

REV
NO.

DATE

DESCRIPTION

PREPARED BY

CHECKED BY

APPROVED BY

AUTHORIZED
BY

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

I.O.E.C.

AMIDCO

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 2 of 45

CONTENTS
1.

2.

INTRODUCTION
1.1

Scope

1.2

Definition of Terms

1.3

Quality Assurance System

1.4

Inspection

1.5

Codes and Standards

MATERIAL
2.1

Linepipe

2.2

Equipment

2.3

Welding Consumables

3.

QUALIFICATION OF WELDING PROCEDURE

4.

QUALIFICATION OF WELDING PROCEDURE FOR WELDS CONTAINING FILLERMETAL ADDITIVE


4.1

Welding Procedure Specification

4.2

Essential Variables

4.3

Welding of Test Joints - Butt Welds

4.4

Testing of Welded Joints - Butt Welds

4.5

All Weld Metal Tensile Test

4.6

Macro Examination / Hardness Surveys

4.7

Charpy Impact Testing

4.8

Chemical Analysis

4.9

Crack Tip Opening Displacement Test (CTOD)

4.10

Testing of Welded Joints - Fillet Welds


TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

I.O.E.C.

AMIDCO

4.11
5.

6.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 3 of 45

Performance

QUALIFICATION OF WELDERS AND WELDING OPERATORS


5.1

General

5.2

Welding Inspection and Testing

5.3

Requalification

5.4

Validity of Welder and Welding Operator Qualification Certificates

PRODUCTION WELDING
6.1

General

6.2

Line Pipe End Preparation

6.3

Alignment

6.4

Proximity of Welds

6.5

Tack Welding

6.6

Temporary and Non-Structural Attachments

6.7

Movement of Pipe

6.8

Storage and Handling of Consumables

6.9

Preheating and Interpass Temperatures

6.10

Post-Weld Heat Treatment

6.11

Repair Welding

7.

WELD PROFILE AND SURFACE FINISH

8.

IDENTIFICATION OF WELDS

9.

WEATHER CONDITIONS

10.

INSPECTION AND TESTING


10.1

Visual Inspection

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

10.2

Non-Destructive Testing (NDT)

10.3

Stages of Inspection

10.4

Radiography

10.5

Magnetic Particle Inspection (MPI)

10.6

Ultrasonic Examination

10.7

Acceptance Criteria For Inspection and NDT

10.8

MPI Testing

10.9

Dye Penetrant Testing

Page 4 of 45

10.10 Ultrasonic Testing


10.11 Random Hardness Testing
10.12 Metallic Inclusions
11.

DOCUMENTATION
11.1

Prior to Production Welding

11.2

On Completion of the Work

APPENDIX A

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 5 of 45

1.

INTRODUCTION

1.1

SCOPE

1.1.1

This specification covers field and laybarge welding of pipes for the Salman Oil and
Gas Integrated Development project including the associated risers.
The new pipelines are listed below:

Ten 4 inch lift gas pipelines from new Salman GLP platform to designated tripods.

Eleven 8 and 10 inch oil gathering pipelines from existing designated tripods to a new
Riser Platform PP3 located at the Salman Complex.

Two 20 inch gas gathering pipelines from new 2SKB and 2SKC Platforms to new KPP
platform located at the Dalan Complex.

One 6 inch gas condensate pipeline from Dalan KPP to the new PP3 riser platform
located at the Salman Complex.

One 14 inch associated gas pipeline from the new GLP platform located at the
Salman Complex to Dalan KPP.

One 36 inch Flare gas pipeline with 2 inch piggy back pilot gas between KPP and the
new FPP Flare platform located near Dalan complex.

One 30 inch, 220 km long export gas pipeline from Dalan KPP to AP Mobarak
Platform via Sirri island.

1.1.2

This Specification defines the minimum Company requirements for the Offshore laybarge welding, laying and testing of the pipelines for the Salman Oil and Gas Field
Integrated Development Project. This specification also applies to ancillary pipeline
and riser welding in the field including Contractor fabrication yards.

1.1.3

The scope of this specification covers the welding of carbon steel line pipe including
bends made from material with specified minimum yield strength of 414 MPa (60,000
p.s.i.) and fittings supplied to ASTM or other standards of equivalent strength grades.

1.1.4

The following welding processes are pre-approved for use:

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Gas tungsten Arc Welding (GTAW)-Manual

Shielded Metal Arc Welding (SMAW)- Manual

Submerged arc welding (SAW)

Gas metal arc welding (GMAW)

Page 6 of 45

Root runs in pipe of diameters less than 60mm shall be made using GTAW process.
1.1.5

This specification also applies to pipeline risers and includes shore approach sections
towards landfall points of the export pipeline to AP Mobarak complex.

1.1.6

Welding and inspection activities within the scope of this Specification shall be carried
out in accordance with API 1104, and as amended by this Specification.

1.1.7

This specification shall be used in conjunction with the additional requirements given in
the Purchase requisition for the lay-barge welding of the line pipes.

1.1.8

This specification does not cover the reeling method of pipeline installation.

1.1.9

This specification does not apply to Hyper-baric method of welding.

1.2

DEFINITION OF TERMS

1.2.1

Terminology used within this Specification is defined as follows:

Company

Petro-Iran Development Company (PEDEC) or its authorised


representative.

Contractor

AMID / I.O.E.C or its authorised representative(s)

Supplier

Party(s) designated on the purchase order or contract for supply


of welding material.

Approval indicates prior Approval in writing, by the Company and where required, by
the Certifying Authority.

ASNT

American Society for Non-Destructive Testing

AWS

American Welding Society

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 7 of 45

Basic Describes flux type for welding consumables which has a high soda and lime
content; basic fluxes may be baked to reduce moisture content such that the
electrode depositing weld metal has a controlled amount of diffusible Hydrogen. Low
Hydrogen Electrodes refer to hydrogen content below 10ml/100g of weld metal
deposited.
However, basic fluxes absorb moisture from atmosphere and will then have high
diffusible Hydrogen content.

TP

Third Party Inspection Authority appointed by the Company

CTOD

Crack Tip Opening Displacement

DAC

Distance Amplitude Correction

FCAW

Flux Cored Arc Welding (Includes FCAW (G) Gas shielded Flux
Cored Arc Welding and FCAW(S) Self Shielded Flux Cored Arc
Welding)

GMAW

Gas Metal Arc Welding

GTAW

Gas Tungsten Arc Welding

HAZ

Heat Affected Zone

IIW

International Institute for Welding

ISO

International Standards Organisation

IQI

Image Quality Indicators (Penetrameters)

May

indicates a possible course of action

MPI

Magnetic Particle Inspection

NDE (NDT)

Non Destructive Examination

PCN

Personnel Certification in Non-Destructive Testing

PWHT

Post Weld Heat Treatment

pWPS

Provisional Welding Procedure Specification

RE (RT)

Radiographic Examination

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 8 of 45

SAW

Submerged Arc Welding

Shall

indicates a mandatory requirement

Shapes

any structural section except plate and tubulars

Should

indicates a recommended course of action

SMAW

Shielded Metal Arc Welding

UE (UT)

Ultrasonic Examination

Welder

Welder, including welding operator using automatic equipment

WPQ

Welding Procedure Qualification validating a WPS

WPQR

Welding Procedure Qualification Record of a WPQ

WPS

Welding Procedure Specification qualified by a WPQ

1.3

QUALITY ASSURANCE SYSTEM

1.3.1

The Contractor shall operate a Quality Assurance System (QAS) within his
organisation, which will ensure that the requirements of this Specification will be fully
achieved.

1.3.2

The Contractors quality system shall be based on ISO 9001 (or an approved
equivalent) and shall be described in a quality manual. The manual shall provide
details for the preparation of a quality plan, which shall include provisions for the
QA/QC of all welding consumables, weld procedures, line pipe welding equipment,
testing and final inspection. The quality plan shall ensure that all quality related
requirements are determined prior to commencement of the works and subsequently
satisfied throughout all phases of construction and inspection. Where changes are
made to the Contractors quality system/manual after Approval and commencement of
the works, these shall be submitted to Company for approval prior to their
implementation.

1.3.3

The effectiveness of implementation of the Contractor quality system may be subject


to monitoring by Company or its nominated representative and, may be audited
following an agreed period of notice.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 9 of 45

1.4

INSPECTION

1.4.1

Company reserves the right to inspect and reject the work at any and all stages of
construction.

1.4.2

The Contractor shall take still photographs of the pipeline on request by Company at
any stage of fabrication.

1.4.3

All nominated representatives of Company shall be allowed free access to all parts of
the laybarge where field welding of the pipeline, and associated operations as
described in this specification, will be performed.

1.4.4

The Contractor shall telex Company giving appropriate notice (Period to be agreed at
Bid Stage) prior to the start of pipe lay operations to enable TP inspection
arrangements to be made.

1.5

CODES AND STANDARDS

1.5.1

Fabrication of the pipeline under this specification shall comply with the latest edition
including all current addenda of the following specifications, and all referenced
publications within this specification:
Reference Codes & Standards
The following codes and specifications are referenced in this specification:
API Spec 5L

Specification for Linepipe

API 5LD

Specification for CRA clad or lined line pipe

API Spec 1104

Welding of Pipelines and Related Facilities

ASNT SNT-TC-1A Guidelines for Personnel Qualification and Certification in NonDestructive Testing
ASTM A320

Alloy Steel Bolting Materials for Low Temperature Service

ASTM A370

Standard Test Methods and Definitions for Mechanical Testing of


Steel Products

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 10 of 45

ASTM A563

Carbon and Alloy Steel Nuts

ASTM A578

Specification for Straight Beam Ultrasonic Examination of Plain


and Clad Steel Plates

ASTM B568

Test Method for Measurement of Coating Thickness By X-Ray


Spectrometry

ASTM B695

Coatings of Zinc Mechanically Deposited on Iron and Steel

ASTM E747

Design, Manufacture and material Grouping Classification of Wire


Image quality Indicators (IQI) Used for Radiology

ASTM F436

Hardened Steel Washers

ASTM F568

Carbon and Alloy Steel Externally Threaded Metric Fasteners

ASTM F844

Washers, Steel, Plain (Flat), Unhardened for General Use

AWS A5

Filler Metal Specifications

AWS B1.11

Guide for the Visual Inspection of Welds

ASME B 31.4

Liquid Transportation Systems for Hydrocarbons

ASME B 31.8

Gas Transmission and Distribution Piping Systems

AWS C5.3-91

Recommended Practices for Carbon Arc air Gouging and cutting.

AWS QC1

Standard and Guide for Qualification and Certification of Welding


Inspectors

BS 4515

Welding of Steel Pipelines on Land and Offshore

BS 7448

Fracture Mechanics Toughness Tests - Method for Determination


of K1C, Critical CTOD and Critical J Values of Metallic Materials

BS 7910

Guide On Methods for Assessing the Acceptability of Flaws in


Metallic Structures

DNV OS-F-101

Submarine Pipeline Systems 2000

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 11 of 45

EN 287

Approval Testing Of Welders - Fusion Welding

EN 288

Specification and Approval of Welding Procedures for Metallic


Materials

EN 462

Non-Destructive Testing - Image Quality Of Radiographs - Image


Quality Indicators

ISO 262

General Purpose ISO Metric Screw Threads

ISO 2553

Welded, Brazed and Soldered Joints - Symbolic Representation


on Drawings.

ISO 6520-1

Welding and Allied Processes- Classification of Geometric


Imperfections in Metallic Materials; Part 1 Fusion Welding, 1998.

ISO 9001

Quality Management Systems - Requirements

ISO 9001:2000 supersedes both ISO 9001:1994 AND ISO 9002:1994. The
requirements of both former standards are covered by the new ISO 9001.

1.5.2

ISO 9712

Non-Destructive Testing - Qualification and Certification of NDT


Personnel

ISO 3834

Quality Requirements for Welding: Fusion Welding of Metallic


Materials

ISO 10474

Steel and Steel Products - Inspection Documents

Company Specification
SL430-0000-SP-PL-1502

Specification for Seamless Line pipe

SL430-0000-SP-PL-1503

Specification for Longitudinally Welded Line pipe

SL430-0000-SP-PL-1504

Specification for Heat Induction Bends

SL430-0000-SP-PL-1508

Specification for Asphalt Enamel and Fusion Bonded


Epoxy Coating of Line pipe

SL430-0000-SP-PL-1509

Specification for Concrete Weight Coating

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

1.5.3

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 12 of 45

Contract Document
All codes and Standards shall be in the editions stated above and with all published
amendments to latest editions. Where the Contractor is proposing to work to another
edition this shall be clearly stated by the Contractor in his bid.
The Contractor shall be in possession of all the above referenced Codes, Standards
and Specifications before commencement of welding fabrication. All such documents
shall be made readily available to personnel involved in executing the work, including
Company personnel.
The Contractor shall obtain written approval from the Company for any deviations from
the requirements of this Specification, referenced codes and Standards, contract
drawings or accompanying purchase order.
The requirements of this Specification shall take precedence over the referenced
Codes and Standards. Where this Specification does not stipulate any overriding
requirements, the referenced Codes and Standards shall apply in full.

1.5.4

Conflicting Requirements
The applicable specifications, standards, codes, and requirements for design,
construction and fabrication shall apply according to the following priority:
a)

Purchase order and Approved variations.

b)

Requisition and Data Sheets.

c)

This Specification.

2.

MATERIAL

2.1

LINEPIPE
The line pipe in seamless and SAW forms will be API 5L grade X 60 for the 30 export
pipeline, the 36 flare pipeline and the in-field pipelines.
The line pipe materials will be supplied conforming to the requirements of NACE MR
01-75 and this requirement shall also apply to the qualified welding procedures to be
used for this project.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

2.2

2.3

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 13 of 45

EQUIPMENT

All welding shall be performed using reliable equipment suitable for the work being
done.

The contractor shall establish a procedure to check and demonstrate to the Company
or its authorized representative that all welding machines are properly grounded to
avoid the occurrence of stray arcing.

Contractor shall provide the procedures for calibration of all welding equipment and
gauges and confirmation of calibration date.

Ammeters and voltmeters shall be fitted to all GMAW, SAW and FCAW equipment.
Portable Voltmeters and Ammeters shall also be available at the welding stations.

The contractor shall provide internal clamps of an approved design and employ only
insulated electrode holders and/or leads.

All electrical equipment shall be calibrated immediately prior to commencement of


production welding in accordance with agreed calibration procedures.

All production welding equipment shall be of the same type and model that will be
used for the qualification of automatic welding procedures.

WELDING CONSUMABLES
Filler metals used in fabrication welding shall be certified as conforming to AWS
Standard A-5.2.
All filler metals proposed to be used in welding fabrication shall be subject to individual
approval by the Company.
The yield strength of the deposited weld metal shall meet the upper quartile value for
the line pipe steel used. The maximum weld metal tensile strength shall not exceed the
line pipe specified minimum UTS plus 30%.

2.3.1

Batch Testing of Filler Metals


Batch testing is not required if Electrode / Filler Wires are supplied with EN 10204
3.1.C certificate.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 14 of 45

The following tests shall be made by the Supplier on the weld metal deposit in
accordance with Section 4.4:

Charpy V-notch impact test (weld centreline only)

All weld metal tensile

Hardness survey (Weld only)

Where a consumable is used for the welding of root pass only, weld metal chemical
analysis as well as hardness survey shall be carried out.
The certificate for the flux shall be 3.1C or 3.1B as verified by TP.

3.

QUALIFICATION OF WELDING PROCEDURE

3.1

The Contractor shall submit preliminary welding procedure specification (pWPS)


including preheating proposals for each welding procedure to be qualified using the
project material for review and approval by Company.

3.2

Welding procedure specifications shall also be proposed and qualified for all weld
repair configurations including half depth excavation followed by re-welding. (See
Figure 3)

3.3

Where a semi-automatic and or an automatic welding procedure will be used during


pipe laying, a manual back up weld procedure shall also be qualified. This weld
procedure shall be subjected to all the NDT and mechanical tests including SSC tests
(if required) as for the automatic welding procedures.

3.4

Separate weld procedure qualification tests are required for the welding of flanges,
valves and fittings. The contractor shall establish, by examination the relevant material
test certificates the need for qualification of additional welding procedures.

3.5

The SMAW welding of fittings shall be carried out using the uphill weld progression
technique and basic, low hydrogen electrodes. The butt welds on all fittings and fillet
welds in contact with the production fluids shall be subject to PWHT in accordance
with ASME B31.8.

3.6

The tie-in welds and butt welds for the riser pipes shall be made with basic low
hydrogen electrodes using the uphill technique.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

3.7

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 15 of 45

Longitudinal Seam Orientation


Two consecutive longitudinal seams (if any) shall be radially offset by 30 approx. and
positioned on the upper quarter of the line (i.e. +/- 45 from the vertical axis).

3.8

Internal Run Order


Internal root sealing runs shall not be permitted except on pipe to fitting welds where
PWHT will be carried out. Where internal welding is used as an integral part of a
mechanised GMAW process, the contractor shall furnish documented evidence that
the completed weld is resistant to Sulphide Stress Cracking.
Internal weld repairs shall not be permitted except on pipe to fitting welds where
PWHT is to be applied. However for GMAW process, it is allowed if misfire defect
length was less than 10mm and frequency of one misfire for every one hour operation.
Double-sided SAW girth welding shall not be allowed.

3.9

Application of Post Weld Heat Treatment


Welds in all materials not in accordance with the line pipe Specifications and having
CE value higher than allowed by that specification shall be subject to post weld heat
treatment. The holding temperature shall be 640C + 10C unless otherwise agreed
but should in no case be lower than 580C.

3.10

Sour Service Requirements

3.10.1

Hydrogen Induced Cracking Tests (Line Pipe)


The pipelines will be exposed to wet sour service conditions throughout the design life,
therefore, the welding procedures shall comply with NACE MR 01-75 requirements.
The welding procedures shall be qualified by hydrogen induced cracking (HIC) testing
as follows:
HIC tests shall be conducted on samples from each of the weld procedures proposed
to be qualified for the welding of line pipe on the lay barge. Testing shall be performed
in accordance with NACE TM02-84 using Solution A, as per NACE TM 01-77
The acceptance criteria for all tests (NACE solution A) shall be:
CSR = 1.5%

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 16 of 45

CLR = 10%
CTR = 1.5%
3.10.2

Hardness test survey carried out 1.5mm from the outer and inner surfaces of a macrosection through the welded joint shall sample the parent material, HAZ, and the weld
deposit. The maximum hardness anywhere on the macro-section shall not exceed 248
Hv10.

3.10.3

Sulphide Stress Corrosion (SSC) Tests


SSC tests as per Appendix A shall be performed on girth welded joints representing
each type of welding procedure qualified for pipeline welding on the lay barge.

4.

QUALIFICATION OF WELDING PROCEDURE FOR WELDS CONTAINING FILLERMETAL ADDITIVE

4.1

WELDING PROCEDURE SPECIFICATION


The welding procedure specification proposed for qualification by the Fabrication
Contractor shall include all the information listed in Table 1 of this specification.
TABLE 1 - Welding Procedure Details and Changes Affecting Approval

Item

Welding procedure specification


details

Changes affecting approval (essential


variables)

Welding Process

The specific arc welding process (or


combination)

A change from one arc welding process to


another

Base Material
Specification

Specified standard and grade

Any change

Manufacturer (and plate steel mill for


SAW pipe)

Any change

Heat Treatment Condition

Any change

Composition (Note 1)

For line pipe - any change outside range


contractually agreed with the line pipe
manufacturer. For fittings - Any change greater
than that permitted by Table 2

Nominal outside diameter, D, of pipe

For mechanised GMAW - any change

Diameter

For other processes -Change in excess of 0.5

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Item

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Welding procedure specification


details

Page 17 of 45

Changes affecting approval (essential


variables)
to 1.5D

Thickness

Nominal wall thickness t of pipe

A change outside the range 0.75t to 1.5 t

Joint configuration

Type of bevel

Any change

Angle of bevel

Any change outside approved tolerances (Note


2)

Size of root face

Any change outside approved tolerances (Note


2)

Width of root gap

Any change outside approved tolerances (Note


2)

Any use of (temporary) backing rings

Any addition or deletion, or change in material

Dimensions of fillet weld

Not essential variable

Electrode or wire

The following information is needed for each run:


Nominal diameter of electrode or wire

Any change for the capping layer or the first


two layers
Any increase for other runs

Trade name

Not Essential Variable

Classification

Any change

Any drying or pre-treatment for hydrogencontrolled electrodes

Any relaxation

Number of wires for each run

Any change

Number of runs
and number of
sides welded

Number of runs from each side

Any change from single to multi-run or vice


versa

Sides welded first and last (double sided


welds only)

Any change

Shielding gas or

Shielding gas

Change in gas selected

Flux

Composition of any gas mixture

A change exceeding 10% of the nominal


addition in a mixture.

Gas flow rate

Any change exceeding 10%

Trade name and type of flux

Not Essential Variable

Electrical
characteristics

Current (ac or dc) and polarity

Any change.

Welding

Electrical stick-out (SAW, GMAW, FCAW)

Any change 5mm

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Item

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Welding procedure specification


details

Page 18 of 45

Changes affecting approval (essential


variables)

Arc Voltage

Any change 10%

Welding current

Any change 10%

Wire feed speed

Any change 10%

Travel speed

Any change 10%

Calculated value of heat input

No separate restriction

Welding Position

Angle of pipe axis to horizontal

Any change exceeding 25

Direction of
Welding

Vertical up or vertical down

Any change

Welding technique

Maximum amplitude of any mechanised


weave

Any Change

Frequency of any mechanised weave

Any Change

Dwell time at the side of any mechanised


weave

Any change outside approved tolerances (Note


2)

Number of welders

Number of root run and of second run


welders

Any reduction

Time lapse
between runs

For cellulosic electrodes only: Time lapse


between start of the root run and the start
of the second run;

Any increase

Partially completed
joint

Number of runs before cooling to ambient

Any reduction

Line up clamp

Internal, external or alternative method

A change from internal to external, or from


internal clamp to alternative.

Number or runs before removal of clamp

Any reduction

Lowering off (on


land) or Barge
move-up (offshore)

Number of runs before this activity


commences

Any reduction

Preheating

Preheat temperature

Any reduction, or an increase exceeding 50C

Method of applying heat

Not Essential Variable

Method of controlling temperature

Not Essential Variable

Method of measuring temperature

Not Essential Variable

Maximum and minimum interpass


temperature for each layer

Any change

Method of applying heat

Any change

Parameters

Post-weld heat

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Item

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Welding procedure specification


details

treatment

Repair welds

Page 19 of 45

Changes affecting approval (essential


variables)

Soaking temperature

Any change

Soaking time (specified as time/


thickness)

Any change

Welding procedure details for repair


welding

Any of the changes affecting approval listed


above

Welding procedure details for the weld to


be repaired

Any change affecting the approval of the


procedure for the weld on which the repair
welding procedure was qualified

Note 1 - CE calculated as per IIWValue tested 0.06% to + 0.03%.


Note 2 - To be agreed with Company after qualification of the welding procedure.

4.2

ESSENTIAL VARIABLES
The essential variables shall be as listed in Table 1 of this specification with the
following additional restriction for the welding of line pipe.

4.3

For mechanised GMAW, any change in diameter of wire.

WELDING OF TEST JOINTS - BUTT WELDS


The welding of test joints shall be made using either using the same welding, heating
clamping and support equipment, that is to be used in production or equipment
identical to it.
Welding shall be carried out using pipe nipples of sufficient length to properly
demonstrate the clamping, support and preheating method and in no case shall be
less than 3 meters in length.
The test joint material shall be selected from material of the highest carbon equivalent
(CE(IIW)) available at the time of welding. Table 1 Note (1) provides guidance for requalification of weld procedures with change in CE of line pipe material.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

4.4

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 20 of 45

TESTING OF WELDED JOINTS - BUTT WELDS


After welding, the test joint shall be allowed to cool for 12 hours. It shall then be
subject to 100% radiographic examination prior to sectioning for mechanical tests.
In addition to radiography, welds made by GMAW (manual or mechanised) shall be
subject to 100% volumetric ultrasonic examination.
Non-destructive examination methods shall be in accordance with Sec.10, with the
exception that radiography shall be carried out using lead screens.
Acceptance criteria shall be as for production welds.
Table 2
Outside Diameter. 4 - 12 (Note 1)
Test Type

Outside Diameter > 12

Number of
Tests/Specimens

Clock Position of
Specimens

Number of
Tests/Specimens

Clock Position of
Specimens

2, 8

2, 4, 8, 10

All weld tensile

1 (where possible)

Not specified

Not Specified

Macro/hardness

12, 3, 6

12, 3, 6

1
(Note 2)

9 to 12
(Note 3)

2
(Note 2)

9 to 10, 4 to 6
(Note 3)

Weldmetal Chem.
Analysis

Not Specified

Not Specified

CTOD test

As specified in
Purchase Order

N/A

Transweld Tensile

Charpy Impact Tests

Full Ring stress


Corrosion Test

If Required

N/A

If Required

N/A

Note 1: Tests for pipe under 4 OD to consist of 2 macro/ hardness test specimens taken at the
3 and 6 oclock positions and one transweld tensile test
Note 2: A Charpy impact test consists of 4 sets of three specimens (Weld, FL, FL+2mm and
FL+5mm ) for pipe wall up to and including 20 mm thick and 5 sets of three specimens
(Weld [Root and Cap], FL, FL+2mm and FL + 5mm) for pipe wall greater than 20mm
thickness. See Fig 2.
Note 3: The positions given for the Charpy impact test are approximate. They may be adjusted
to allow removal of tensile and macro specimens from their indicated positions

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 21 of 45

General Note:

Nick break and bend specimens are required by this specification for procedure
qualification since they also demonstrate the welders capability of making sound
welds using the parameters specified in the Contractors pWPS.

4.5

ALL WELD METAL TENSILE TEST

4.5.1

Method
The test specimen shall be taken within the weld deposit over the full gauge length.
Specimen dimensions and testing shall be in accordance with ASTM A370

4.5.2

Requirements
The yield strength and ultimate tensile strength values obtained shall be higher than
the minimum specified values (SMYS) for the parent material.

4.6

MACRO EXAMINATION / HARDNESS SURVEYS

4.6.1

Method
Sections shall be ground to, as a minimum 600 grit finish and etched for macro
examination. Examination at a magnification of x5 shall be made using a hand lens or
stereoscopic microscope.
Hardness survey shall be carried out by Vickers hardness test method using a 10Kg
load for welds made using SMAW process. For butt welds made using GMAW process
a 5Kg load shall be used. The position of the hardness impressions is given in Figure
1a.

4.6.2

Requirements
Each section shall show full penetration, be free from lack of fusion and cracks. Any
cavities or inclusions shall not exceed 5% of the surface area on each section.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 22 of 45

The maximum permitted value is 248 Hv10 for hardness impressions adjacent to the
internal surface and at mid thickness and 275 Hv10 for hardness impressions adjacent
to within 1.5mm of the cap reinforcement area.

4.7

CHARPY IMPACT TESTING

4.7.1

Method
For welds in pipe up to and including 20mm wall thickness, each test (as indicated in
Table 3, above) shall consist of three sets of four, transverse specimens notched at
weld centreline, fusion line (i.e. with the mid point of the notch intersecting the fusion
line) f.l. + 2mm and f.l. + 5mm (i.e. with the midpoint of the notch intersecting a line
5mm from, and parallel to, the fusion line). These specimens shall be taken from the
mid-thickness area of the section through the weld.
However, for welds in pipe over 20mm in thickness, additional impact test specimens
shall be taken from the root area and the specimen locations shall be as shown in
Figure 2.
Specimen preparation and testing shall be in accordance with ASTM A370.
Impact Test temperature shall be in accordance with Table 3
Design Temperature

Wall Thickness t (mm)

Test Temperature (C)

0C or above

t 20

-10

20 < t 30

-20

t > 30

-30

T 20

T 10

20 < t 30

T 20

t > 30

T 30

T C (Less than 0C)

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

4.7.2

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 23 of 45

Requirements
The minimum required energy for all impact tests shall be as follows:
Table 4
Specimen Size (mm)
(Note 1)

Average per Set of


Three (Joules) min.

Individual value min.


(Joules)

10 x 10

42

35

10 x 7.5

38

32

10 x 5

26

22

Note 1: Only specimens of the sizes stated in Table 4 above shall be tested.
Note 2: Line pipe materials with SMYS < 414 MPa see Table 6-3 Sec.6 of DNV-2000.

4.8

CHEMICAL ANALYSIS

4.8.1

Method
Chemical analysis shall be performed on a section of weld metal. Analysis shall be in
accordance with ASTM A370. The elements listed in the relevant line pipe
specification shall be analysed.

4.8.2

Requirements
The analysis shall confirm the manufactures stated limits for the chemical composition
of the weld metal. The results of analysis for other elements are for information.

4.9

CRACK TIP OPENING DISPLACEMENT TEST (CTOD)

4.9.1

Method
CTOD tests shall be conducted at the minimum design temperature for all pipeline
welding procedures and representative weld repair procedures. Each test shall consist
of three (3) specimens. CTOD testing will not be required for pipe to fitting welding
procedures.
TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 24 of 45

Testing will be on preferred geometry (Bx2B) type specimens in accordance with BS


7448 Part 2.
4.9.2

Requirements
The results are for Company information.

4.10

TESTING OF WELDED JOINTS - FILLET WELDS

4.10.1

Preparation
Fillet weld test joints shall be allowed to cool to ambient temperature and then be
subject to 100% magnetic particle examination (Refer Section 10.5), prior to
sectioning.
Four weld sections shall be taken from the 12, 3, 6 and 9 oclock positions of the test
weld. For test welds other than full circumference welds the four sections shall be
equally spaced.

4.10.2

Method
Sections shall be ground to, as a minimum, 600 grit finish and etched for macro
examination. Examination shall be made using a hand lens or stereoscopic
microscope at a magnification of x5.
On two of the sections a hardness survey is to be carried out by Vickers hardness test
using a 10Kg load. The position of the impressions is given in Figure 1b.

4.10.3

Requirements
Cracks or other planar defects detected by magnetic particle examination shall be
unacceptable.
Each section shall show full penetration, be free from lack of fusion and cracks. Any
cavities or inclusions shall not exceed 5% of the surface area on each section.
The maximum permitted hardness for external fillet welds is 275 HV10 and 248 HV10
for internal fillet welds (i.e. those in contact with the sour production fluids.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

4.11

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 25 of 45

PERFORMANCE
Should a test weld fail any of the required tests or the permitted retests, the cause of
the failure shall be established and rectified and the complete procedure test shall be
repeated.
No lay barge field welding shall commence until the appropriate welding and repair
procedures have been qualified and approved by the Company.
Should a qualified procedure show poor production performance the causes for the
poor performance shall be assessed and a modified welding procedure shall be
qualified and submitted to the Company for approval.

5.

QUALIFICATION OF WELDERS AND WELDING OPERATORS

5.1

GENERAL
All welders and welding operators shall be qualified in accordance with API 1104 and
this Specification.
Welders or operators shall be qualified for this project prior to the start of production
welding by making a complete test butt weld using the qualified welding procedure.
The test weld shall be made with the pipe in the same positions as for production
welding. Tests shall be conducted on the same material as that to be used in
production, and welding of test joints shall be carried out on the lay barge.
All welders qualified to work on this project will be provided with identity badges.

5.2

WELDING INSPECTION AND TESTING


Each test weld shall be subject to both visual and non-destructive inspection. Nondestructive inspection shall be in accordance with Section 10.0 of this Specification.
If the test weld is visually acceptable it shall be subject to mechanical testing as
detailed earlier.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

5.3

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 26 of 45

REQUALIFICATION
Re-qualification of welders or welding operators for lay barge operation is required if
any change is made to the welding procedure which necessitates re-qualification of
the welding procedure.

5.4

VALIDITY OF
CERTIFICATES

WELDER

AND

WELDING

OPERATOR

QUALIFICATION

5.4.1

Re-qualification of welders and welding operators is required if any change is made to


the welding procedure that necessitates its re-qualification.

5.4.2

Renewal of a qualification certificate is required whenever a welder or welding operator


has not used the appropriate welding process for a period of more than three months
or whenever there is a reason to question the performance of production welding.
Validity of the certificate is maintained as long as acceptable performance of welding
fabrication is documented with regular non-destructive testing during lay barge
operations and the Contractor keeps records of periods of time and type of work for
each certified welder and welding operator.

6.

PRODUCTION WELDING

6.1

GENERAL
All production welding equipment shall be suitable for the job and capable of producing
welds of the specified quality.
All equipment shall be maintained in a good working order and any unsuitable
equipment shall be replaced immediately.
All welding shall be performed by qualified welders. They shall use qualified welding
procedures and welding consumables. Welding fluxes and gases shall be properly
identifiable and acceptance within the contractor's QA/QC control.

6.2

LINE PIPE END PREPARATION


Pipe lengths will be supplied with machined bevels specified in Company
specifications as appropriate. Should the Contractor elect to use a different groove,

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 27 of 45

prior approval shall be obtained from the Company and incorporated in the procedure
and welder qualifications. For pipe-to-pipe fittings, pipe-to-flange, or pipe-to-pipe
welds where wall thickness changes are involved, the proposed joint design shall be
submitted for Company approval prior to use. In the event the bevel configuration is
changed from that supplied by the line pipe manufacturer the re-machined bevel faces
shall be 100% examined by wet MPI. However this test may be reduced to 20% upon
the Company approval based on satisfactory test result.
Details of end preparation machines shall be forwarded to Company for approval.
Any pipe bevel showing evidence of end area lamination shall be cut back until the
laminated section is removed and rebevelled. After rebevelling the pipe end shall be
ultrasonically inspected in accordance with ASTM A578. Any discontinuity (e.g.
lamination) causing a reflection echo > 50% DAC and accompanied by a 50% loss of
back wall reflection shall be cause for rejection when the discontinuity area is greater
than 30 mm2.
Pipe Bevels shall be cleaned by power tools to a bright finish prior to lining up the pipe
for welding.

6.3

ALIGNMENT

6.3.1

Details of line up clamps shall be forwarded to the Company for approval prior to
commencement of welding. For pipe welding internal line-up clamps shall be
mandatory unless otherwise agreed by the Company. End preparation machines and
line up clamps shall not damage the pipe or coatings. Line up clamps shall ensure
that pipe bores are aligned to the tolerances of BS 4515. Line up clamps shall not be
removed until both root and hot passes have been completed.

6.3.2

For the welding of fittings and flanges the line-up procedure shall be approved by the
Company. It shall conform to the requirements of BS 4515 and this specification.

6.3.3

Hammering or heating shall not be used for correction of misalignment. Spacer tools
are to be used to check final fit-up.

6.4

PROXIMITY OF WELDS
Girth welds shall be separated by a minimum distance of one pipe diameter. The
minimum distance between nozzle welds and between nozzle and girth welds shall be
4 times the nominal wall thickness of the run pipe. Distances shall be measured weld
toe to weld toe.
TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

6.5

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 28 of 45

TACK WELDING
Bar tacks are preferred, i.e. welds to bridging pieces within the weld bevel, not
affecting the root area and totally removed prior to completion of the final weld.
Where root tacks are to be used they must be at least 50mm long and must be at least
four in number for pipe over 4 in diameter. Root tacks incorporated into the final weld
must be welded to the same procedure, by a welder qualified for that procedure and
shall be ground to a feather edge at each end to ensure adequate fusion into the root
pass.

6.6

TEMPORARY AND NON-STRUCTURAL ATTACHMENTS


Temporary or non-structural attachments to the linepipe or pipelines are not permitted
without the written approval of the Company. The written request shall include details
of proposed welding procedures and controls on their location and methods of
removal.
The Contractor shall prepare a procedure for welding the doubler plates onto those
pipe lengths intended to carry anodes and for CAD welding the anode bonding strap
onto the doubler plate.

6.7

MOVEMENT OF PIPE
The pipes on both sides of the weld joint shall not be moved until both the root and hot
passes have been completed.
In the case of offshore pipe laying the barge shall not be moved until the root and
second pass have been completed.

6.8

STORAGE AND HANDLING OF CONSUMABLES

6.8.1

As a minimum the storage and handling of welding consumables shall conform to the
recommendations of the consumable manufacturer. A detailed storage and handling
procedure shall be submitted by the Contractor for approval by the Company.

6.8.2

Special care shall be taken to ensure that basic coated low hydrogen electrodes are
stored in a warm dry environment. Prior to use low hydrogen electrodes shall be baked
in accordance with the manufacturer's recommendations to achieve a hydrogen

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 29 of 45

content of less than 10ml/100g of weld metal. In the absence of written


recommendations the electrodes shall be baked for two hours at 300C. After baking
the electrodes shall be transferred to a holding oven operating at 150C then issued
from the oven to heated quivers at 70C for use. Any low hydrogen electrode
remaining unused after 2 hours in a quiver shall be returned to the baking oven and redried for 2 hours at 300C before being returned to the holding ovens and re-issued.
No electrode shall be redried more than 2 times.

6.9

PREHEATING AND INTERPASS TEMPERATURES

6.9.1

Preheat shall be applied under the following conditions:


a)

When specified in the approved welding procedure, related to the carbon


equivalent (CE or Pcm) of the pipe.

b)

When required to ensure dryness in the joint.

c)

When the ambient temperature measured on the pipe is below that established
during the procedure qualification.

6.9.2

The requirements for preheat and the temperatures shall be formalised during welding
procedure qualification, taking into account pipe wall thickness, carbon equivalent and
welding process including weldability data available from line pipe manufacturer.

6.9.3

Preheat shall be applied in a uniform manner preferably by using gas ring or electrical
heating. However hand held gas torch heating is permitted if minimum of two torch
used for preheating of pipe sizes up to 14" and four for upper pipe sizes.

6.9.4

The preheat temperature shall be established over minimum distance of 75mm on


each side of the weld and shall be measured using a calibrated thermocouple or
melting indicator crayon. The actual preheat temperature shall not exceed the
specified temperature by more than 50C.

6.9.5

The minimum preheat temperature for repairs shall be 50C higher than that specified
for the original welding, up to a maximum of 150C.

6.9.6

The minimum preheat temperature for welding of fittings to line pipe and at tie-ins shall
be 150C.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 30 of 45

6.9.7

If, notwithstanding the above requirements, HAZ hydrogen cracking is found, then the
whole weld procedure together with the level of preheat and the consumable handling
procedure shall be reviewed and reassessed.

6.10

POST-WELD HEAT TREATMENT


Post-weld heat treatment shall be used when so specified in the qualified welding
procedure. Only electrical methods shall be used for heating. Measurement of post
weld heat treatment temperatures shall be in accordance with ASME VIII part 1. Postweld heat treatment, when specified, shall be performed in accordance with a written
procedure approved by the Company.

6.11

REPAIR WELDING

6.11.1

General

6.11.2

No weld shall be repaired without informing and consent of the Company.

Only one attempt at a repair shall be made. Any further repair attempt shall require
prior approval by the Company.

Should the weld be removed (cut-out), re-bevelling performed shall ensure removal of
the prior heat affected zone material.

Repair Procedure
Weld repair procedures shall be qualified in the same manner, and at the same time,
as production welding procedures are qualified. In addition to the details of the
procedure qualification the repair welding procedure presented shall also include full
details of the following:

Method of defect removal;

Preparation of weld area;

Non-destructive inspection method for confirmation of defect removal;

Maximum and minimum repair cavity sizes;

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 31 of 45

Repair procedures which include the above requirements shall be subject to approval
by the Company.
The qualification test specified covers the typical weld repair situation. Company
reserves the right to require additional testing for very shallow or very deep repair
situations.
6.11.3

Defect Removal
Weld defects shall be removed by grinding, machining or air-arc gouging. If air arc
gouging is used then the defect area shall be subsequently cleaned by grinding. The
cut-out portion shall be sufficiently deep and long to remove the defect. At the ends
and side of the cut there shall be a gradual taper from the base of the cut to the
surface of the weld metal. The width and profile of the cut shall be such that adequate
access for re-welding is provided.
External defects such as undercuts and pin holes shall be repaired by re-capping the
weld for a minimum distance of 40mm past both ends of the defect. This distance
shall be measured parallel to the length of the weld. Re-capping shall only be
accepted if the maximum hardness is shown by procedure qualification to be within the
acceptance limits of this Specification.

7.

WELD PROFILE AND SURFACE FINISH

7.1

Welds shall meet the appearance criteria of BS 4515 Table 5. Welds shall be left aswelded for initial inspection and shall not be doctored with a torch or by mechanical
means to alter their appearance.
Grinding or mechanical dressing shall be permitted only when specified on the
Contract Drawings or after approval by the Company.

7.2

For coated pipes the Contractor shall arrange for the coating to be applied in the weld
area in accordance with Company Specifications after the weld has been inspected
and accepted. The Contractor shall also arrange for the repair of any damaged
coating.

7.3

Surface Imperfections
Prior to completion and field joint coating the Contractor shall remove all burrs, scars
and marks made by welding during fabrication.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 32 of 45

Surface imperfections such as gouges, grooves, shallow surface cracks, laps, slivers
and arc strikes may be removed by grinding to a smooth profile provided that the
resulting wall thickness is within the tolerances allowed by Company Specifications as
appropriate. Repair welding on the body of the pipe shall not be attempted.
Where defects that penetrate to the extent that after grinding the remaining wall
thickness will be below the minimum wall thickness the damaged portion shall be cut
out as a cylinder, and replaced to the requirements of this Specification.
Arc strikes are not permitted on pipe body during welding. Arc strikes, inadvertently
caused may be removed by grinding provided the remaining wall thickness is above
the minimum wall thickness required by line pipe specification. The ground surfaces
shall be examined by magnetic particle inspection to demonstrate removal of defect to
the satisfaction of the Company.
7.4

Dents
Unacceptable dents (as defined in the appropriate Company Specification) shall be
removed by cutting the pipe as a cylinder and replacing it to the requirements of this
Specification.

8.

IDENTIFICATION OF WELDS
Each welder shall mark in waterproof crayon that section of weld on which he has
worked with his code No. If different welders work on different sides a separate set of
numbers shall be put on each side. The root welder shall put his number at the top,
with each subsequent welder marking below it, in sequence. These numbers shall not
be removed until the weld is cleared by NDT.
Contractor shall submit detailed procedures for identification and marking of welds
including NDE for Company review and approval prior to mobilisation of welding
personnel on the lay barge.

9.

WEATHER CONDITIONS
All welding shall be performed in areas where prevailing weather conditions can have
no influence on weld quality.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

10.

INSPECTION AND TESTING

10.1

VISUAL INSPECTION

Page 33 of 45

The Company shall have the right of inspection and/or rejection at all times during the
welding and after the weld has been completed.

10.2

NON-DESTRUCTIVE TESTING (NDT)

10.2.1

Butt welds shall be 100% visually inspected 100% inspected using X-ray Radiography
for permanent film methods. Any approved fillet welds shall be 100% inspected by
magnetic particle inspection.
The Company reserves the right to require all suspect areas to be re-examined by
ultrasonic examinations for the purpose of clarifying acceptability or otherwise. The
Contractor shall have available suitably qualified technicians to ASNT level II.
Where welding is conducted using a gas shielded welding (GMAW) process the first
three production welds per day shall be examined by ultrasonic. The Company reserve
the right to increase this if lack of fusion or cracks are found which escape detection by
radiography. In case of using (GMAW) for only root pass and (SMAW) for the other
runs, ultrasonic test is not required.

10.2.2

The qualifications and competence of NDT Personnel used by the Contractor shall be
subject to approval by the Company.
NDT Supervisors shall have full knowledge or all Specification requirements and the
applicable codes and standards. Current copies of all pertinent documentation such
as this Specification and approved welding procedures shall be at the disposal of all
relevant personnel during all welding and associated operations.

10.3

STAGES OF INSPECTION

10.3.1

As a minimum, the inspection stages employed by the Contractor for welded joints
shall be as follows:
a)

Fit-up prior to first pass.

b)

Following root pass.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

c)

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 34 of 45

Following completion of weld (after PWHT where appropriate).

Inspection of stage (a) will be visual and dimensional.


Inspection of stage (b) will normally be visual only.
Inspection at stage (c) will be visual and, as required by this Specification, using the
methods listed in Section 10.4 or 10.6 of this Specification.
10.3.2

Marking
The Contractor's quality control personnel shall clearly identify with a distinguishing
mark all parts or joints that have been inspected and accepted. The system of
marking shall be submitted to the Company for approval.

10.4

RADIOGRAPHY

10.4.1

General
Prior to the start of production radiography the Contractor shall submit a detailed
radiographic procedure for approval by the Company. As a minimum the procedures
shall include the details specified in BS EN 1435.
The radiation source shall consist of X-ray unless otherwise approved by the
Company. Tie-in weld radiography can be done by means of using - ray provided on
using D4 or equivalent films.
Wire type image quality indicators shall be used.
Only fine grain film shall be used. The use of fluoro-metallic intensifying screens shall
be permitted subject to satisfactory procedure qualification. Damaged screens shall
not be used.

10.4.2

Procedure Radiographs
Three radiographs shall be made of each welding procedure qualification weld. It is
the intent of this Specification to establish these radiographs as the quality level for all
production welding. Welding Procedures shall not be deemed Qualified unless these
radiographs have been accepted and approved by the Company. Should any variables

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 35 of 45

in the welding procedure specification change, the radiographic procedure shall be


requalified.
For procedure qualification image quality indicators are to be placed on both the
source side and the film side of the weld. IQI sensitivity shall be:
Source side

better than 1.8%

Film side

better than 1.6%

Film density shall be a minimum of 2.5.


10.4.3

Production Radiography
Production radiography shall be in accordance with the approved radiographic
procedure, with image quality indicators on the film side only. When a circumferential
weld is carried out in a single shot four IQI's shall be used - one per quadrant.
Otherwise two shall be used per film length.
Interpretation of radiographs will be conducted by the Company.

10.4.4

Radiation Protection
The Contractor shall be responsible for the protection and monitoring of radiographic
personnel and shall ensure that work is carried out in accordance with the relevant
Health and Safety Regulations.

10.4.5

Qualification of Radiographers
Radiographers shall be qualified in accordance with the requirements of ASNT level II
or an approved equivalent.

10.4.6

Film Identification
As a minimum, the film identification shall include:

Company Name

Line number/spool No./Line size

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Weld Number

Date

Location of the film on the weld (Clock Positions)

10 cm divisions around the pipe

An indication of weld status. i.e. original, repair, re-repair etc.

Page 36 of 45

The zero datum shall be at the top of the pipe. Divisions for location of weld defects
shall run clockwise in ascending order viewed in the direction of pipelay.
10.4.7

Film Processing
Film shall be processed on site in such a way as to allow storage for up to 5 years
without deterioration. The Contractor shall submit a procedure for ensuring that film
processing chemicals have been removed prior to storage of the radiographs. The film
handling and storage procedure shall be subject to approval by the Company.

10.4.8

Film Storage
All unexposed film shall be stored in a clean dry place where surrounding conditions
will not be detrimental to the emulsion. If deemed necessary by the Company
unexposed film will be developed and the extent of fogging shall produce a density of
less than 0.3. The processed films shall be kept in an Air Conditioned room.

10.5

MAGNETIC PARTICLE INSPECTION (MPI)


The Contractor shall submit his MPI procedure to the Company for approval.
The Contractor's procedure shall be in accordance with BS 6072 or approved
equivalent using a wet particle method. The yoke method shall be used in preference
for all magnetic particle inspection, the use of the prod method shall be subject to
Company approval. Magnetic particle operators shall be qualified to ASNT-Level II or
approved equivalent.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

10.6

ULTRASONIC EXAMINATION

10.6.1

General

Page 37 of 45

The Contractor shall have facilities available for ultrasonic examination of welds in
accordance with Section 12.5 of BS 4515.
The Contractor shall submit his detailed procedure and technique sheets for ultrasonic
examination to the Company for approval prior to the start of production. The
Procedure shall include for the ultrasonic examination of welds between pipes of equal
and unequal wall thickness and between pipes and fittings where the wall thickness
differs.
10.6.2

Qualification of Ultrasonic Technicians


Ultrasonic Technicians shall be qualified to the appropriate level of ASNT-Level II or
approved equivalent scheme.

10.7

ACCEPTANCE CRITERIA FOR INSPECTION AND NDT


The acceptance criteria shall be as stated in Clause 13.1 and Table 5 of BS 4515 and
the following additional requirements:

10.7.1

Radiographic Testing
The diameter of any, individual gas pore shall not exceed 2mm or 20% of the nominal
wall thickness, whichever is the smaller.
All cracks are unacceptable.
Root Penetration
The weld root excess penetration at any point shall not exceed 3mm.
Centre-line Shrinkage in GMAW Welds
Centreline shrinkage (hot cracking) in mechanised GMAW welds is unacceptable.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

10.8

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 38 of 45

MPI TESTING
No additional requirements.

10.9

DYE PENETRANT TESTING


No additional requirements.

10.10

ULTRASONIC TESTING
Where ultrasonic testing is used to compliment radiographic inspection the acceptance
criteria shall be as for Section 10.7.1
Where automated ultrasonic inspection is used as the primary means of weld
inspection then acceptance criteria are to be agreed with the Company.

10.11

RANDOM HARDNESS TESTING


Random hardness tests shall be carried out on the first 50 completed girth welds in
order to ensure compliance with NACE MR 01-75 hardness (248 Hv10) requirement.
This shall consist of hardness testing the weld cap of the finished girth welds at three
equidistant positions around the circumference. Subject to compliance with the
acceptance criteria the testing frequency may be reduced to 1 in 10 welded joints.

10.12

METALLIC INCLUSIONS
The largest dimension of any tungsten inclusion shall not exceed 2mm or 20% of the
nominal wall thickness, whichever is the smaller. Adjacent inclusions shall be
separated by at least 50mm and there shall not be more than four inclusions in any
300mm length.
Copper inclusions are unacceptable and shall be excavated followed by re-welding
using the qualified repair weld procedure.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

11.

DOCUMENTATION

11.1

PRIOR TO PRODUCTION WELDING

Page 39 of 45

Copies of the following documents shall be supplied to the Company prior to


commencement of production welding:

Welding Procedure Specifications

Welding Procedure Qualification and Test Reports

Repair Welding Procedure and Test Reports

Welder Qualification Records

11.2

Non-destructive Inspection Procedures and Qualification Reports.

Quality Plan

ON COMPLETION OF THE WORK


On completion of the work, the Contractor shall submit the following documentation to
the Company.

Non-destructive Examination Reports for all welds, including repair welds, carried out.

List of Certified Welders.

Weld radiographs.

Pipe number / Joint number / Pipe location.

Welding Procedure Proposals.

Welding Procedure Specifications.

Welding Procedure Qualifications.

Welder Approval Qualifications.

NDE Operator Qualifications.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

NDE Procedures.

Records relating pipe number to welder, NDE, PWHT (if applicable)

Chemical analysis and other tests required by the specification.

Heat treatment records (if applicable).

Page 40 of 45

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 41 of 45

FIG. 1 POSITION OF HARDNESS SURVEYS

Hardness Traverse
1.5mm from outer
surface

1.5mm
Specimen
centre line

Hardness traverse
root side
1.5m
m

FIG 1a: Butt Welds and Full Depth Repair Welds


Traverse through fillet cap

Traverse through fillet


root

FIG1b: Hardnesss Traverse on Fillet Welds

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 42 of 45

Fig 2. Charpy Specimen Locations for Welding Procedure Qualification Tests

NOTES:
1. Charpy specimens to be etched to ensure correct notch location
2. Fusion line charpy should be taken from the steeper face if weld is not symmetrical
Centre Line of specimen intersects Centre Line of notch on fusion line for fl Specimens

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 43 of 45

Figure 3. Charpy Test Locations for Partial Repair Weld Procedure

NOTES
1. Charpy Specimens to be etched to ensure correct notch location
2. Centre Line of specimen intersects Centre Line of notch on fusion line for fl specimens

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 44 of 45

APPENDIX-A
Method Statement for HIC and SSC Tests
A.1

General
This procedure describes the testing of both the base material, the circumferential and
longitudinal (SAW) welds of line pipe to be exposed to wet sour gas or multiphase
fluids. The testing procedure forms part of the lay barge welding procedure
qualification requirement.

A.3

Welding Requirements
Welding shall be carried out by the Fabrication Contractor using the Company
approved welding procedure specification to be used on the pipe laying barge, utilising
the same make of electrodes (manual welding) or welding wire (automatic welding).
The girth weld shall be made on pipe sections from a selected heat representing the
highest carbon equivalent (CE) of the heats produced by the line pipe manufacturer
and as used for the conventional weldability tests.
Welding shall be performed in the 5G position.
The pipe sections shall be stamped by the Inspector and marked with:
a.

Heat number

b.

Unique pipe number

The top of the pipe shall be marked with a line and stamped TOP at each end at the
time of welding.
A.4

Specimen Preparation
Number, Location, Orientation and size of the specimens shall be based on NACE TM
0284-96.

A.5

Test Details
Test method shall be based on NACE TM 0284-96 for HIC and NACE TM 0177 for
SSC tests.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

PETROIRAN DEVELOPMENT COMPANY


SALMAN OFFSHORE FACILITIES
(EPC-3)

NIOC

PROJECT DOCUMENT NO.

AMIDCO

A.6

I.O.E.C.

Project

Facility

Document

Discipline

Sequence

Revision

SL-430

0000

SP

PL

1512

D2

Page 45 of 45

Specimen Examination
Prior to testing, the complete test section shall be fully examined by ultrasonic testing.
UT examination will be repeated after 7 days exposure and at regular intervals
thereafter to determine initiation and or extension of any cracks. The test shall be
terminated following final UT examination after 30 day test period or earlier if ultrasonic
testing indicates excessive crack extension such that failure could occur.
The decision for early termination of the test based on the results of ultrasonic
indications will be subject to agreement between the Company and the Test house.
At the completion of testing period the internal weld surfaces will be examined by wet
magnetic particle examination (MPI). Any crack like or other surface indications found
by MPI or by UT examination during testing will be characterised by metallographic
examination of the relevant areas and reported with photomicrographs of
representative features found.

A.7

Acceptance Criteria.
a. No stress corrosion cracks greater than 1mm.
c. No HIC cracking greater than 1mm.
Crack area value < 3% based on results of ultrasonic indications and selected
metallography.
No delamination cracks greater than 5mm.

A.8

Reporting
Any test ring failure occurring within the 30 day test period shall be reported to
Company.
Following the completion of testing the Testing Contractor shall prepare and submit a
draft report within seven (7) working days for discussion of results. Following the
meeting the report shall be finalised and three (3) copies submitted to Company.

TECHNIP Project No.

TECHNIP Document No.

9068G

9068G-000-JSS-3520-512

/var/www/apps/conversion/tmp/scratch_1/299087385.doc

You might also like