Procedure for Power Receiving

PROJECT NAME

: Khabat Thermal Power Plant Units 1&2

DOCUMENT NO.

: KP-00+++-CY712-G0019

TITLE

: Procedure for Power Receiving

OWNER

: Ministry of Electricity (MOE) of


Kurdistan Regional Government

(Including Cover)

Purpose
For Information
For Review
For Approval
For Construction
As-Built

28-08-2015

For Construction

MS

GK

30-07-2015

For Approval

MS

GK

31-05-2015

For Approval

MS

GK

PREPARED

CHECKED

REVIEWED

APPROVED

Rev.
No.

DATE

DESCRIPTION

GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

Owner
Ministry of Electricity (MOE)
of Kurdistan Regional Government

Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.

Main Subcontractor
GAMA POWER SYSTEMS ENGINEERING &
CONTRACTING,INC.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

TABLE OF CONTENTS
1. PURPOSE
2.

EXTENT

3. PRECAUTIONS AND LIMITATIONS


4.

PREREQUISITES

5. TEST AND ENERGIZING OF 132KV AIS


5.1 TEST AND ENERGIZING OF DC SYSTEM
5.2 TEST AND ENERGIZING OF 132KV AIS

2 of 8

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

1.

3 of 8

PURPOSE

The purpose of this document is to establish the power energizing procedure to be performed prior to initial
operation of the electrical systems of KHABAT THERMAL POWER PLANT UNIT 1 & 2 according to the
following schedules,

1) 132KV AIS Power Receiving : Aug. 31, 15 (Official Completion of Power Receiving)

2.

EXTENT

Power receiving shall be carried out after completion of site test of the following equipment in accordance with
each test procedure.

1) 132KV AIS

132kV AIS CB, DS/ES, CT & PT

132kV AIS Protection & Relay Panel

132kV AIS Control Panel

132kV AIS Metering Panel

132kV AIS 400V AC Panel (temporary power supply)

132kV AIS 220V & 48V DC Battery Charger, Battery & DC Distribution Panel
power supply)

132kV AIS Common Signaling Panel

132kV AIS SCADA & Telecom Panel (OPGW is not provided by MOE )

132kV AIS ECS (if not, control panel operation)

132kV AIS Grounding & Lightening Protection System

132kV AIS Lighting System (temporary power supply)

132kV AIS HVAC System (temporary power supply)

132kV AIS Fire Fighting / Alarm System (if not, temporary installation)

3.

PRECAUTIONS AND LIMITATIONS

(temporary

a)
All checks and tests specified in site test plan or commissioning procedure submitted by
manufacturer shall be performed prior to energizing the equipment.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

4 of 8

b)
Provide warning barriers around the equipment to be energized first for the protection of plant
personnel.
c)

Ensure that circuit breakers and disconnecting switches are open and SF6 pressure correct.

d)

Check all panels and electrical equipment are connected to earth.

e)

Check the lighting and HVAC are available (if not, temporary installation).

4.

PREREQUISITES

a)
The main and auxiliary power systems have been turned over to the commissioning team and the
commissioning engineers are to be aware of the electrical distribution system of the plant.
b)

All the factory test report and operation manuals are to be available for review.

c)

All the test equipment shall be prepared to fulfill the complete test and commissioning

d)
400V AC power supplies are available for energizing the 220V DC system and 230V UPS System.
(Temporary power supply).

e)
For 132KV AIS energizing, 132KV Substation should be installed completely, also all preenergizing tests should be done.
Coordinate with MOE for power energizing of 132kV AIS Breaker.
f)

Earthing switches of 132kV AIS, 15.75KV GCB and 6KV switchgear are on correct position

(closed for pre-energizing checks, opened for energizing)


g)

Ensure that all circuit breakers are in power off position initially

h)

All protective relays have been set as per Protective Relay Setting Table prepared.

The Contractor will be responsible for all the safety measure necessary to the taken before, during and after
the commissioning tests. The works will be carried out in accordance with the PLANT HSE PLAN.

Detailed attention must be given to:

Surrounding of the testing area shall be cordoned off and access restricted to authorized person.
Safety warning sign boards shall be provided.

certified.

Ensure that all the testing equipment and tools are in good handling conditions, calibrated and

Fill in formats the test results and forward them to competent authorities.

A restricted area is appointed and indicated by a partition.

The display of a dangerous place.

The door of a control panel and the board is locked.

Fence for 132KV AIS is completed.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

Communication with MOE is available.

5.

TEST AND ENERGIZING OF 132KV AIS

5 of 8

5.1 TEST AND ENERGIZING OF DC SYSTEM

5.1.1
1)

220V/48V DC system
Complete the pre-energizing checks of 220V/48V DC systems as per the test plan and procedure of
manufacturer.

Battery charger unit (DC 220V, 48V)

DC 220V & DC 48V switchboard

Battery bank (DC 220V, 48V)

2)

Initial energizing of 220V/48V DC power supply system

Temporary install and check the 400V AC power supply to the battery chargers

Verify that all breakers are open

Energize the battery chargers and place the mode selector switch in the floating charge mode. Adjust
the float charge voltage as per manufacturer recommendations

Note : After the batteries are fully charged, the DC power systems are available to supply power to the
connected loads
-

Upon completion of initial charge, measure and record individual cell voltages and ambient
temperature as per manufacturers field test plan and procedure.

Energize DC 220V/48V switchboard

5.2

TEST AND ENERGIZING OF 132KV AIS

5.2.1 Prerequisites
1)

132KV CB, DS/ES, CT & PT

Verify that the factory test data is available for review

Verify all CB, DS open

Verify all equipment are grounded properly.

Verify all function test completed

Verify all local indications are correct

Check SF6 gas pressure

Verify all lightening protections are correct

Verify 220V DC control circuits have been checked out and they are functional.

Perform pre-energizing checks in accordance with field test plan and procedure.

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

2)

132KV Protection relay panels, Control Panels, Metering Panels, Common Signal Panels, SCADA
Panels, ECS and Telecom Panels

Verify that the factory test data is available for review

Verify all equipment are installed correctly

Verify all equipment are grounded properly.

Verify all protection relay settings are correct and tests completed

Verify all function test completed

Verify all interlock, inter-trip test completed

Verify all indications are correct

Verify all communication are correct with MOE

Perform pre-energizing checks in accordance with field test plan and procedure.

3)

132KV Lighting, HVAC & Fire Fighting /Alarm System

Verify all equipment are installed correctly

Verify all equipment are grounded properly.

Verify all function test completed

Verify all indications are correct

Perform pre-energizing checks in accordance with field test plan and procedure.

If permanent facilities are not available, temporary solutions will be applied.

5.2.2

Initial energizing of 132KV AIS

6 of 8

Excepting CB/DS of feeder for west Erbil T/L #1 all other CBs and DSs should be open, so this status
must be confirmed again before energizing.

Energize feeder for west Erbil T/L #1 by MOE

Check incoming voltage and phase rotation of 132KV at metering panel

Check incoming voltage and phase rotation of 132KV at metering panel

Close DS Q15 of bus #1 PT

Close DS Q9 of feeder for west Erbil T/L #1

Close DS Q1 of feeder for west Erbil T/L #1

Close CB Q0 of feeder for west Erbil T/L #1

Check voltage and phase rotation of 132KV busbar #1 at metering panel

Check status of the all indication values and protection relay

Check graphic display status at ECS (if available)

Check communication status with MOE

Check status of all outdoor equipment (CB, DS, ES, CT and PT)

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

5.2.3

De energizing of 132KV AIS

Open CB Q0 of feeder for west Erbil T/L #1

Check voltage and phase rotation of 132KV busbar #1 at metering panel

Open DS Q9 of feeder for west Erbil T/L #1

Open DS Q1 of feeder for west Erbil T/L #1

Attachment
#1: Check Sheet for Energizing

7 of 8

KHABAT TPP UNITS 1&2

Doc. No

KP-00+++-CY712-G0019

Procedure for Power Receiving

Rev. No.

Page

8 of 8