INDEX
CHAPTER I - GENERAL
I.1. Responsibility ............................................................................................... page 05
I.2. Project description ........................................................................................ page 05
I.3. Project scope of work ................................................................................... page 06
CHAPTER II - METHODOLOGIES
II.1. WORK ANALYSIS .................................................................................... page 07
II.1.1. Site survey and considerations ................................................................ page 07
II.1.2. Potential problem and solution ................................................................. page 08
II.2. PREPARATION.......................................................................................... page 10
II.2.1. Equipment, tools, material and consumables ........................................... page 10
II.2.2. Site organization ....................................................................................... page 11
II.2.2.1. Organization chart ................................................................................. page 11
II.2.2.2. Personnels job description ................................................................... page 12
II.3. HORIZONTAL DIRECTIONAL DRILLING (HDD) ............................... page 15
II.3.1. Pilot drilling .............................................................................................. page 15
II.3.2. Drill path and drilled hole size ................................................................. page 16
II.3.3. Drilling fluid ............................................................................................. page 17
II.3.3.1. Drilling fluid function ........................................................................... page 17
II.3.3.2. Mixing procedure .................................................................................. page 17
II.3.3.3. Original ...................................................................................................page 17
II.4. PIPE RAMMING ........................................................................................ page 17
II.4.1. Setting up .................................................................................................. page 17
II.4.2. Pipe ramming technique ........................................................................... page 18
II.4.3. Main parts and functions of pipe ramming hammer system .................... page 21
II.4.3.1. Main parts .............................................................................................. page 21
II.4.3.2. Main functions ....................................................................................... page 22
II.4.3.3. Soil cleaning .......................................................................................... page 23
II.4.3.4. Pneumatic pipe ramming hammer structure.......................................... page 24
II.4.3.5. Pipe ramming hammer selection ........................................................... page 24
II.4.3.6. Requirement for steel product pipe ....................................................... page 25
II.4.3.6.1. Pipe outside cleaning .......................................................................... page 25
II.4.3.6.2. Wall thickness .................................................................................... page 25
II.5. EARTH/FOUNDATION WORK FOR DRILLING EQUIPMENT .......... page 26
II.5.1. Earth work in flat ground ......................................................................... page 26
II.5.2. Earth/foundation work in road shoulder ................................................... page 26
II.6. OVERCOMING ACTIONS WHEN DRILLING/RAMMING PROBLEMpage27
CHAPTER III - WORK PLAN
III.1. SUGGESTED ACTIVITIES ..................................................................... page 28
Crossing No.1 Km0+100, Pk4-ITS008-G-111-D: 44m ...................................... page 28
Crossing No.2 Km0+140, Pk4-ITS008-G-111-D: 45m ...................................... page 29
Crossing No.3 Km0+720, Pk4-ITS008-G-112-D: 18m ...................................... page 30
Crossing No.4 Km4+000, Pk4-ITS008-G-117-D: 33m ...................................... page 31
Crossing No.5 Km6+150, Pk4-ITS008-G-121-D: 19m ...................................... page 32
Prepared by: Deltatech Technical Services JSC
Page 2
Page 3
Page 4
CHAPTER I
GENERAL
I.1. Responsibility
- Employer: Vietnam Expressway Corporation (VEC).
- Contractor: Toshiba & Hitachi & Itochu Joint Venture.
- Drilling sub-contractor: Deltatech JSC.
I.2. Project description
Drilling sub-contractor required to install D200 galv. steel pipes across HCM
Long Thanh Dau Giay expressway at locations as in following table:
No.
Position, reference
drawing
unit
Qty
No.
Position, reference
drawing
01
Km0+100, Pk4ITS008-G-111-D
44
20
Km34+500, Pk4ITS008-G-326-D
24
02
Km0+140, Pk4ITS008-G-111-D
45
21
Km34+615, Pk4ITS008-G-326-D
28
03
Km0+720, Pk4ITS008-G-112-D
18
22
Km37+200, Pk4ITS008-G-330-D
30
04
Km4+000, Pk4ITS008-G-117-D
33
23
27
05
Km6+150, Pk4ITS008-G-121-D
19
24
29
06
Km10+920, Pk4ITS008-G-128-D
22
25
Km41+360, Pk4ITS008-G-417-D
30
07
Km11+400, Pk4ITS008-G-129-D
30
26
Km43+650, Pk4ITS008-G-421-D
20
08
Km14+500, Pk4ITS008-G-211-D
22
27
Km43+870, Pk4ITS008-G-421-D
20
09
Km22+380, Pk4ITS008-G-222-D
19
28
Km45+250, Pk4ITS008-G-423-D
21
10
Km22+720, Pk4ITS008-G-223-D
16
29
Km49+000, Pk4ITS008-G-429-D
16
11
Km22+800, Pk4-
20
30
Km49+250, Pk4-
19
unit Qty
Page 5
ITS008-G-223-D
ITS008-G-429-D (1)
12
Km23+230, Pk4ITS008-G-224-D
47
31
16
13
Km23+270, Pk4ITS008-G-224-D
40
32
Km52+170, Pk4ITS008-G-434-D
18
14
60
33
18
15
46
34
18
16
Km23+445, Pk4ITS008-G-224-D
24
35
Km54+500, Pk4ITS008-G-438-D
32
17
Km23+790, Pk4ITS008-G-224-D
16
36
Km54+920, Pk4ITS008-G-440-D
19
18
Km24+110, Pk4ITS008-G-311-D
16
37
Km54+980, Pk4ITS008-G-441-D
43
19
Km24+950, Pk4ITS008-G-312-D
21
Page 6
CHAPTER II
METHODOLOGIES
1. Drill length
2. Drill depth
Consideration
Technique shall be applied:
*1st step: Horizontal
directional drilling (HDD)
*2nd step: Pipe ramming
Keep deeper than road layer
3. Ground structure
5. At-site electric
No
No
7. Dumping area
No
Limited
From expressway
No
4. Adjacent
constructions
8. Entrance
9. Accommodation
Page 7
1. For safety:
- Unsafe activities (mobilization/demobilization, walking, moving
tools,) when work across expressway.
- Harming adjacent constructions.
- Unsafe when work in raining time.
2. For work organization:
Potential
problem
Page 8
1. For safety:
- Risk assessment and safety training for all construction personnel.
- Set up and maintain good cooperation with expressway management
authority:
+ Prepare and explain working procedure in details.
+ Understand cooperation procedure for emergency cases in
expressway.
+ Keep contacted with expressway authority at all working time.
- Set up protection when work in raining time or stop work.
2. For work organization:
Solution
Page 9
II.2. PREPARATION
II.2.1. Equipment, tools, material and consumables
In order to get the job done in time, the following shall be prepared and mobilized to
the sites:
No.
Description
Capacity
Unit
Qty
Equipment, tools
115hp
Set
01
5000 lit
Set
02
Digitrak F5 locator
25,9m
Set
01
1500KN
Set
01
Air compressor
0.7MPa,
6m3/min
Set
01
Guide rail
U200 steel
Set
01
Leveling instrument
0.8m long
Set
01
Chain block
3 ton
Set
02
Tensioner
1 ton
Set
02
10
Laser pointer
15w
Set
01
11
Walkie-talkie
5w
Set
02
12
Excavator
0,4m3
Ea.
01
13
Diesel pump
30m3/h
Ea.
01
14
Generator
30KVA
Ea.
01
15
Welding machine
250A
Ea.
02
16
Grinding machine
15kW
Ea.
02
17
Cargo crane
10 tonne
Ea.
01
Page 10
18
Diesel winch
1 tonne
Ea.
01
19
Steel
U200, I700
Ton
20
Wooden pile
D150x3000
Ea.
150
21
2mx3m
Ea.
02
II
Sch40
1000
Bentonite
USA
Ton
10
Additives
USA
Ton
01
Welding consumables
Japan
Ton
0,5
Diesel oil
Litter
2000
Hydraulic oil
Litter
600
Fuel
Litter
400
Shell
SITE MANAGER
LOGISTIC/
ADMIN 1&2
SAFETY
SUPERVISOR 1&2
CONSTRUCTION
SUPERVISOR 1&2
SURVEY
TEAM
DRILLING
TEAM 1&2
EQUIPMENT
TEAM 1&2
GENERAL LABOUR
TEAM 1&2
Page 11
drilling,
and submit
the
Page 12
Page 13
Page 14
Pilot drilling is done by following the directional head from surface with the help of
the transmitter installed inside drill head. Signal from transmitter will be gained by a
receiver, which kept above by a technician and converted into drilling data in the
display. So the depth, direction and slope is known, in order to avoid existing
infrastructure.
Pilot drilling head can be changed according to the ground formation. Drilling is done
by rotation, directional drilling is done by head.
Page 15
A remote display set up in drilling machine will show drilling data to help operator
knows about drill path.
The F Series Display (FSD) lets you see drilling
information at the drill and can receive telemetry
signals from the F5, F2, SE, Eclipse, Mark III,
and Mark V locating systems. The FSD remote
display is equipped with externally mounted antenna.
Additional antenna options available upon request for
increased telemetry range.
Page 16
Page 17
A trench will be dug in the equipment side for guide rail setting up.
In case of setting up in a road shoulder, a foundation with sand bag, steel frame will
be done so that rammers frame can run in a stable direction.
Another trench will be dug in the destination side to get D200 steel pipe end.
II.4.2. Pipe ramming technique
Refer links:
https://www.youtube.com/embed/WRCvMo2Rqg?rel=0&wmode=transparent
https://www.youtube.com/watch?v=hdc63KY9dyw
Prepared by: Deltatech Technical Services JSC
Page 18
Page 19
Page 20
After complete pushing a pipe, a new pipe will be lined up and welded. When the
weld cooled down enough, rammer will lined up, secured and operated to continue
pushing.
A good ramming will be done with following a procedure, which carefully considered
basing on knowing ground structure. Drilling fluid kept inside drilled hole before
ramming will help to maintain D200 steel pipe direction and avoid wall collapse,
especially ramming through sand.
BH190 pneumatic pipe-ramming hammer
Pipe ramming hammer is a low frequency pneumatic impacting tool with large impact
power. It take compressed air as power source to drive cylinder punch hammer to beat
on hammering block, then the steel pipe directly rammer inside the stratum along the
rail track. When working, pipe ramming hammer produce larger impact force; this
force directly acts on the pipe end and passing through the pipe delivered to the front
pipe boots, cutting soil, the cut soil enter into the steel pipe, once pipes reach the
target pit, excluding the soil core, pipeline laying is completed.
Pipe ramming hammer is mainly used for steel pipe trenchless laying, also it can be
used for pipe shed construction, gold mining exploration, cast-in-place pile, steel pipe
pile and profiled steel sheet pile engineering and so on.
BH190 pneumatic pipe-rammer have very good application to the ground, easy
operating, suitable for small size pipe.
II.4.3. Main parts and functions of pipe ramming hammer system
II.4.3.1. Main parts
Pneumatic pipe-rammer is insist of pipe hammer, high pressure hose, oil injecting
system, lubricating system and other parts, the follow picture is the main structure.
Page 21
1. Soil layer
2. Cutting heads
3. Steel pipe
4. Padding wood
5. Soil extractor
7. Pipe hammer
22. Tensioner
8. Pulley
9. Hooks
Page 22
- Air compressor: providing compressed air to the rammer and sweep away soil
core of steel pipe;
- Pipe ramming head: preventing steel pipe month expanding or damage after
hammering;
- Adjusting taper sleeve: let the pipe ramming head, soil excavating tool and pipe
ramming hammers matching with steel pipe diameter;
- The grouting pipe: convey the mud or lubricating liquid to front end of the pipe,
rear channel of the pipe boot;
- Grouting system: consist of slurry storage tank, grouting pipe, air tube, control
valve, it can mud jack to the internal and external wall of steel pipe to reduce the
frictional resistance; in most cases the using effect of grouting system is not too
good because of grouting pipe breakage and lose efficacy, so it is not often used.
II.4.3.3. Soil cleaning
When the pipe going into the ground by impacting force, soil core enter in the steel
pipe, a soil cleaner powered by compressed air will be used for pushing out the soil
core inside pipes until ramming work is completed.
In hard ground conditions need high pressure water shall be used for soil cleaning.
1. Soil layer
6. Seal ring
2. Soil core
7. Stop level
3. Steel pipe
Soil cleaner includes soil cleaning ball and seal cover plate. Outer wall of the soil
cleaning ball cling to the steel pipe wall, and thus it will form a piston in the steel
pipe, the effect of compressed air is making it go forward inside the steel pipe, then
Prepared by: Deltatech Technical Services JSC
Page 23
the soil core inside the steel pipes will be pushed out from the steel pipe. The seal
cover plate is used for plugging the nozzle at the steel pipe end.
II.4.3.4. Pneumatic pipe rammer structure
1. Hammering block
2. Impact hammer
3. Cylinder
6. Damper
7. Hose
Page 24
pipe diameter
wall thickness
pipe diameter
wall thickness
100mm
4mm
500800mm
9mm
100180mm
5mm
8001000mm
10mm
Page 25
180250mm
6mm
10001200mm
12mm
250350mm
7mm
12001500mm
15mm
350500mm
8mm
15002000mm
19mm
Earth work to make working trench for guide rail, hammer setting up in flat ground.
After digging trench, protection work will be done, such as: cover arrangement, water
pump arrangement,
II.5.2. Earth/foundation work in road shoulder
In case of arranging drilling equipment in road shoulder, earth work and foundation
work shall be done to get a stable working base.
Earth work includes following steps:
- Clean up ground from water, rubbish, trees,
- Level up by sand bags, soil to desired level so that can get drill path -2m from
road surface.
Foundation work includes following steps:
Prepared by: Deltatech Technical Services JSC
Page 26
- Pile up by wooden piles so that a secured frame can be made to protect sand
bags, soil from collapse, especially in raining time.
- Steel work to make a strong frame for drilling machines working base. Frame
shall be made by welding or joining up by bolts and nuts depending on safety
requirements.
- Secure drilling machine into steel frame.
- Secure rammers frame into steel frame after drilling work.
Drilling equipment reinforcement help to keep machine stable so that desired drill
path can be done in 1 time pilot drilling without interruption for adjustment.
Good reinforcement also help to protect machine from slipping or falling down from
working base.
Earth/foundation work shall be done before mobilization, avoiding wasting time for
waiting.
II.6. OVERCOMING ACTIONS WHEN DRILLING/RAMMING PROBLEM
When drill head hit a hard object, the following steps must be done:
- Check back ground structure reports to estimate object with type, size.
- Try to go through the object place, if can.
- Calculate a substituted action.
- Take back drill head and change direction without moving drilling machine.
- Move drilling machine to more suitable place and start a new drilling.
- Report to Employer/Contractor.
When rammed pipe hit a hard object, the following steps must be done:
- Check back ground structure reports or drilling report to estimate object with
type, size.
- Try to go through the object place, if can.
- Take back pipe and try another ramming.
- Move pipe and hammer more suitable place and start a new drilling.
- Report to Employer/Contractor.
Page 27
CHAPTER III
WORK PLAN
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 28
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 29
Site condition
1. Site entrance: in expressway.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Page 30
Site condition
1. Site entrance: in expressway.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Page 31
Site condition
Suggested activities
Page 32
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 33
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 34
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 35
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 36
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 37
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 38
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 39
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 40
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 41
Site condition
1. Site entrance: in ramp way.
Suggested activities
- Mobilization done at night time to avoid
traffic problem.
- Safety signs, fence, barricade will be set
up.
Technique: drilling.
Page 42
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 43
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 44
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 45
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 46
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 47
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 48
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 49
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 50
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 51
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 52
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 53
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 54
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 55
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 56
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 57
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 58
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 59
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 60
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Foundation work done to extend work
space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 61
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 62
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 63
Site condition
Suggested activities
- Mobilization done in off-peak time to
avoid traffic problem.
- Safety signs, fence, barricade shall be set
up.
- Earth work done to extend work space.
- D200 pipe must be cut short when doing
pipe ramming.
Page 64
Page 65
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
No.
Responsibility
Activities
Manpower
Equipment
/Tools to be
used
Time
(estimated)
Safety
Report
PREPARATION
Action: Deltatech
Supervision:
Employer/Contractor
II
Drawing
/Document
* Work
permit
* Approved
drawings
* Approved
procedures
/regulations
from
Employer
/Contractor
Site Manager
Safety
supervisor
Logistic/Ad.
Construction
supervisor
Drilling team
Equip. team
General Labor
7-seat car
15 ton cargo
crane
* Work
permit
* Approved
drawings
* Approved
procedures
/regulations
from
Employer
/Contractor
Site Manager
Safety
supervisor
Logistic/Ad.
Construction
supervisor
Drilling team
Equip. team
General Labor
D24x26 drilling
machine
Digitrak F5
locator
Bentonite
mixing tank
BH190
ramming
hammer
Welding
machine
2-3 days
*Daily
work.
report.
*Safety
reports.
*Daily
report.
*Safety
reports.
*Drilling
/ramming
reports.
DRILLING/RAMMING WORK
Action: Deltatech
5. Pilot drilling.
6. D200 pipe ramming.
7. Welding work to join up pipes
until complete ramming.
8. Cleaning up pipe inside.
Supervision:
Employer/Contractor
2 days for
drilling / 2
days for
ramming
Page 66
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
III
Action: Deltatech
Supervision:
Employer/Contractor
* Work
permit
* Approved
drawings
* Approved
procedures
/regulations
from
Employer
/Contractor
Site Manager
Safety
supervisor
Logistic/Ad.
Construction
supervisor
Drilling team
Equip. team
General Labor
7-seat car
15 ton cargo
crane
1 day
*Daily
report.
*Drilling
/ramming
reports.
*As-built
documen
ts.
*Handover
documen
ts.
Page 67
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
Steps of work
Time (week)
1 2
10
11
12 13 14 15 16 17 18
General preparation
Construction
Crossing No.1
Crossing No.2
Crossing No.3
Crossing No.4
Crossing No.5
Crossing No.6
Crossing No.7
Crossing No.8
Crossing No.9
Crossing No.10
Crossing No.11
Crossing No.12
Crossing No.13
Crossing No.14
Crossing No.15
Crossing No.16
Crossing No.17
Crossing No.18
Crossing No.19
Crossing No.20
Crossing No.21
Page 68
19
20
21 22
23 24 25
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
III
Crossing No.22
Crossing No.23
Crossing No.24
Crossing No.25
Crossing No.26
Crossing No.27
Crossing No.28
Crossing No.29
Crossing No.30
Crossing No.31
Crossing No.32
Crossing No.33
Crossing No.34
Crossing No.35
Crossing No.36
Crossing No.37
FINAL CHECK, HAND
OVER, DEMOBILIZATION
Page 69
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
CHAPTER IV
SAFETY CONTROL
All the factors in construction activities must be checked for safety carefully before and
during work. Checking is to find out inadequate matters, potential risks for preventive
actions or repair.
Checking procedure shall be done in various ways:
-
Check for secure system. All parts in foundation must be secured each
other strong enough.
Page 70
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
Check for failures can cause crack, break in material during work.
Activities:
o When mobilization, transportation vehicles stay near expressway safety
fence and off load equipment/tools, material.
o During work, workers move tools, material across expressway.
Page 71
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
Activities:
o When drilling, drill rods and its carrier moving forward/backward,
rotating by operators actions.
o When feeding rod, workers take a rod in by hand.
o Working with hydraulic system in drilling machine.
o When drilling machine working on foundation vibrating force makes
machine moving.
Activities:
o When ramming, the hammer moves forward by pressurized air.
o When feeding pipe, workers take a pipe in by hand for welding.
o When continue ramming, workers take hammer in and line up with pipe
by crane and hand.
Activities:
o When ramming, the rammer moves forward by pressurized air.
o When feeding pipe, workers take a pipe in by hand for welding.
o When continue ramming, workers take rammer in and line up with pipe
by crane and hand.
Page 72
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
Page 73
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
CHAPTER V
QUALITY CONTROL
Construction quality will be achieved when the processes: making product pipeline, pilot
drilling, pipe ramming are controlled.
The whole quality control consists of following steps:
-
Document control.
Material/consumable control.
Equipment/tools control.
Welding test.
Check data reports to make sure that drill path done as required, especially
the drill depth.
Storage.
Substitution, if any.
Page 74
METHOD STATEMENT D200 EXPRESSWAY CROSSING BY HDD AND PIPE RAMMING TECHNIQUE
Visual check for all weld, take measure to control weld dimensions.
Page 75