METHOD STATEMENT FOR ANTI TERMITE

1.0) SCOPE OF WORK


a) Main contractor shall notify pest control operator 24 hours in advance that
anticipates concrete casting into the area to be treated.
b) Before area treated, Main Contractor shall ensure that all loose timber,
wood shaving, loose containing materials be removed from the said
allocation area.
c) Pest control operator shall applied Dynamite EC or Termigard 38.7EC (or
any other applicable / approve with Termicide 38.7 EC) chemical onto
entire ground floor slab area prior to concrete casting.
d) The area surrounding all sides of the column stumps extending to 1 meter
below the soil surfaces of to the top of pile cap.
e) Pest control operator shall apply 2 meter all round the building prior to
concrete of the apron area.
2.0) CHEMICAL PREPARATION AND APPLICATION
Pest control operator shall mixed the solution at site in the present of Site
Supervisor/ Consultant according to 1:40 as manufacturers specification
proposed rate and to apply the mixed solution onto the indicated allocation
area by 4-5 liter to 1m2.
Before soil treatment will be carried out, the ground water table will be
checked. Excavation of trial holes of more than 0.5 meters deep measured
from the level of the soil to be treated will be done. As required by
Environmental Department, no treatment is to be carried out if the ground
water table is 0.5m of less below of soil to be treated.
This chemical preparation shall be carried out within a kerb area under a roof
with no outlet to the lake, open drains or public sewer. The waste water
containing the chemical shall not be discarded into the lake, septic tank or
open drain.
3.0) TIME OF APPLICATION
a) Link concrete shall be laid immediately after chemical has been applied
on the hardcore as to avoid exposure to weather.
b) Application of chemical Dynamite EC or Termigard 38.7EC (or any other
applicable / approve with Termicide 38.7 EC) should spray on hard
surfaces of hardcore or sand blinding prior to concrete casting.
c) After completion of applying chemical, PVC sheet have to provide to cover
up treated area as to avoid exposure to sun heated and rain wash in case
occurred of concreting.

d) Immediately after the soil treatment is completed, the treated soil shall be
securely covered with black polyethylene sheet. The layer of lean
concrete shall be cast on top of the sheet.
e) After completion of applying chemical pest control operator will let the
site supervisor/ Consultant to sign and certify on the job street provided
by pest control operator.
4.0) ALLOCATION EQUIPMENT
Pest control operator must provide full range equipment for the job (Mask,
Eye protector, Latex Glove, etc).
5.0) TEMPORARY DRAINAGE
The provision of temporary drainage will be provided of adequate capacity
around the whole area to be treated within an outlet to a sump.
6.0) SAMPLING
The examination/ quality control sampling (please refer to chemical
manufacturers material safety data sheet, material identification report)
7.0) STORAGE
Pest control operator shall arrange owned transportation and delivery,
storage of material at site is not necessary.
8.0) SUBMITTAL OF MATERIAL
a) Sample of material to be used is ready for submission
b) Material for test shall be done at site at any time
9.0) MATERIAL
a) Dynamite EC or Termigard 38.7EC (or any other applicable / approve
withTermicide 38.7 EC) chemical must be applied uniformly over the area to
be treated at the rate of 4.5 liters to 1m2 or according to manufacturers
specification
b) The area to be chemically treated by Dynamite EC or Termigard 38.7EC (or
any other applicable / approve with Termicide 38.7 EC) onto 2 meters all
round building perimeter prior concreting of the apron area.
10.0)PEST CONTROL OPERATOR
a) Anti Termite Contractor is the operator and chemical importer or supplier
must approve with Termicide 38.7 EC.
b) Pest control operator (company) is not necessary to register with CIDB
(Please refer to CIDB) but our technicians are trained by CIDB and obtained
recognized operators cards issued by CIDB (attached).
c) Poison permit is issued not by Environmental Department but the ministry
of agriculture control the issuing poison permit (please refer to
Environmental Department Guideline). The poison permit issued by the

ministry of agricultural is attached for your perusal.

11.0)WARRANTY
a) Actual warranty is issued by Anti Termite Contractor immediately upon P.R.
request subject to payment fully settled by the main contractor. The
warranty period is 2 years from CPC.
b) The treated subterranean termite be found affected the treated building
within warranty period Anti Termite Contractor undertakes to control by
whatever method the company should deem fit free of charge.
12.0)METHOD OF APPLYING ANTI TERMITE SOIL TREATMENT (4 STAGE)
a) Spraying of surfaces of pile cap and ground beam trenches.
b) Spraying of surfaces below the floor-slab area after laying of hardcore and
prior to the final concreting stage.
c) Spraying of surfaces below apron/ Terraces and area within 2 meters
perimeter beyond the edge of external building wall unless adjoining
structures render this impossible.
d) Power spray at any soil surfaces or areas through which termite infestation
is likely to occur and as directed by the S.O.
13.0)METHOD OF APPLYING ANTI TERMITE SOIL TREATMENT (2 STAGE)
a) Spraying of surfaces below the floor-slab area after laying of hardcore and
prior to the final concreting stage.
b) Spraying of surfaces below apron/ Terraces and area within 2 meters
perimeter beyond the edge of external building wall unless adjoining
structure render this impossible.
c) Power spray at any soil surface of areas through which termite infestation
is likely to occur and as directed by the S.O.

** EC - EMULSIFIABLE CONCENTRATE