Professional Documents
Culture Documents
The guide has been developed by the Department of Health together with the
NHS and the ProCure21 Supply Chain Partners as a reference for common
practice to be implemented on ProCure21 schemes.
This guide captures the learning the implementation of one of the largest
Public Sector procurement programmes within the UK. It provides practical
guidance on how schemes should be procured under the ProCure21
programme and demonstrates the blend of management techniques that are
required at key stages. Regular reference to the guide will help ensure that
your ProCure21 scheme is on the right track.
The Guide is intended for all those involved in the procurement of ProCure21
schemes, namely;
- NHS Clients
- Professional Advisors
- Principal Supply Chain Partners (PSCPs)
- Primary Supply Chain Members (PSCMs)
NHS Clients new to ProCure21 will find the guide of particular use in gaining
an idea of;
- What ProCure21 is and its advantages
- What the differences are to traditional tender procurement
- Key Stages
- What is expected of them
The Principal Supply Chain Partners (PSCPs) act as ‘solution providers’ and
their services may vary from service strategies, estate strategies and
business planning through to design development, development of the brief
and construction works (both major & minor).
The ProCure21 guide follows the timeline of a scheme. You can either start at
the beginning or pick out areas of interest as you go along. However the
guide is not meant to be used in isolation. Please ensure that you include
your ProCure21 Implementation Advisor when developing your scheme.
If you have a scheme registered you can get access to more detailed
information on our ProCure21 Club SharePoint System. There are links
provided at the appropriate points.
To get access to the ProCure21 Club you must work directly on a ProCure21
scheme. Access is given to;
6.0 Evaluation
Figure 1: The ProCure21 life cycle:
5.0 Delivery
4.0 Scheme
development
Each of these sections is then further subdivided into the contents of the
guide:
1.1 Range of services 2.1 Establishing the P21 team 3.1 Launch workshop
1.2 Benefits of P21 2.2 How to select a PSCP 3.2 Establishing the scheme team
1.3 Application of P21 2.3 Roles & responsibilities 3.3 Developing a joint action plan
1.4 Critical success factors
4.0 Scheme
5.0 Delivery 6.0 Evaluation
development
4.1 Scheme development 5.1 Managing the delivery phase 6.1 Post Project Evaluation
4.2 Management techniques 5.2 Use of the Contract 6.2 Sharing lessons learned
4.3 Use of the Contract 5.3 Management techniques
4.4 Agreeing the GMP
Checklist
Introduction
Getting an intimate knowledge of what ProCure21 is, and what it can do for
you is the best place to start.
This section will help you understand the breadth of the programme, and the
different ways you can engage with it.
ProCure21 provides NHS Clients with the ability to readily appoint accredited
Principal Supply Chain Partners (PSCPs) alongside a pre-agreed commercial
arrangement. This enables the team to immediately focus on the needs of the
NHS Client.
Achieving Excellence
in Construction targets
NB: Recently summarised in the Common
Minimum Standards (CMS) issued by the
Office of Government (OGC)
ProCure21 can respond to challenges within the NHS e.g. changes in clinical
need/ practice.
Their input can vary from assisting the NHS Client with its’ overall strategy to
that of developing a detailed design.
The ProCure21 process (point at which the PSCP is engaged) may begin at
Pre-SOC stage, SOC, OBC or FBC.
“ProCure21 is delivering significant time savings for those schemes that would
otherwise have to be procured via the Official Journal of the European
Communities. Time savings of around nine months, equating to a saving of 3
per cent on scheme costs can be identified for the relatively small number of
schemes completed to date.”
National Audit Office, Improving Public Services Through Better Construction, March 2005
NHS clients that have supported ProCure21 have enabled the programme to
win a number of accolades since the commencement of the national
framework in October 2003:
National Audit Office, Improving Public Services Through Better Construction, March 2005
The key findings published in their report “Improving Public Services Through
Better Construction” (published in March 2005 –
COST SAVINGS
CERTAINTY SHARED
¾ A transparent cost
arrangement
¾ Potential to generate and
share cost savings.
¾ Free VAT recovery advice
DISTILLS
THE BEST
OPTIMUM
OF EARLIER BEST
ENVIRONMENT
DESIGNS VFM
NHS Clients can choose to engage the services of the PSCP (and thus begin
the P21 process) at any of the following stages:
• Pre-SOC,
• SOC,
• OBC, or;
• FBC.
Figure 5 illustrates the potential ‘entry points’ of the PSCP dependant upon
the needs and required services of the NHS Client.
5.0 Delivery
4.0 Scheme
development
C
FB
C
OB /
ts
C in
SO po
c t ry
3.0 Scheme Launch
e - so en
Pr P
PSC e21
l r
2.0 Team selection t ia
o Cu
n
te f Pr
Po o
1.0 Defining how se
P21 is applied U
The appropriate time to engage a PSCP will depend on the dynamics of the
scheme. The following illustration emphasises the benefits realised by a
number of NHS Clients through early PSCP appointment.
£
Reducing opportunity to add value
Time
As fundamental decisions about the build are taken (e.g. site, footprint of the
building, room adjacencies, components etc) the commitment to construction
cost rises. To go back and change an earlier decision becomes more costly.
As the NHS Client ‘manages’ the extent of use of the PSCP during the SOC,
OBC and FBC phases then many NHS Clients find that controlled and timely
input from the PSCP at early stages adds most value. NHS Clients need to
manage the input from PSCPs to ensure that only services that add value are
provided.
The format of the following blank matrix may be of use to NHS Clients to help
stimulate thoughts and ideas about the most appropriate time for selection:
SOC
OBC
FBC
For example, if there are no ‘potential added value’ items noted at SOC stage,
it may suggest that the most appropriate stage to appoint the PSCP is at
OBC.
Having established the most appropriate point to select the PSCP (and
engage the ProCure21 process) it is also important to appreciate the critical
success factors behind ProCure21.
The ‘critical success factors’ of ProCure21 form the chapters of this guide.
It is important that each stage is comprehensively addressed in order that the
full potential of ProCure21 is attained:
Section checklist:
Team Selection
Checklist
Introduction
Getting the right team around you is one of the most important parts of a
ProCure21 scheme. The degree to which you able to work together will
determine your success.
This chapter identifies the key roles on the project team and their
responsibilities. It also gives detailed guidance on the PSCP selection
process.
Project Director
Professional Advisor
Supply Chain
Member Implementation
Advisor
Stakeholder
• Project Directors
• Project Managers
• Cost Advisors
• Implementation Advisors (part of the P21 team)
• Supervisors
• ProCure21 team
ProCure21 does not run itself – it requires commitment, leadership and good
team working.
Personal effectiveness
Knowledge of ProCure21
Project Directors
Project Managers
Implementation
Advisors
Supervisors
ProCure21 team
The above illustration highlights the level of typical involvement of the client
team (including support) on ProCure21 schemes. This merely provides
indicative levels of management effort rather than a precise number of hours.
Project Director
The leads the whole process from the outset of the scheme. They provide the
strategic direction, leadership and ensure that the business case reflects the
views of all stakeholders. They should initiate contact with P21
Implementation Advisors and build a team around them with adequate skills
and experience to match the scheme. The Project Director should hand over
the delivery function to the Project Manager (although this could be the same
person on smaller schemes).
Project Manager
The Project Manager takes over the delivery function from the Project
Director. This is ideally just before the FBC is completed so that they gain an
appreciation of the schemes strategic intent and can begin to integrate with
the team. The Project Manager is a named individual within the Engineering
and Construction Contract (ECC) used under ProCure21 and assumes a
number of defined duties. The Project Manager should report to the Project
Supply side
Supply side
Client side
Client side
Project
Manager
On some schemes (typically those that are lower in value) the Project Director
and Project Manager roles may be undertaken by the same individual. On the
larger, higher value schemes the roles may be separated.
Both the Project Director and Project Manager will need to ‘add value’ to the
ProCure21 process by applying a variety of management techniques (e.g.
Value Management, Risk Management and the principles of collaborative
working).
Many of these techniques are new to healthcare and will therefore require
additional training or external support at key stages.
Cost Advisors
Cost Advisors provide support to the Project Director and Project Manager
throughout the life of the scheme. The PSCP’s also employ Cost Advisors for
commercial assistance. At the SOC, OBC and FBC stages the Cost Advisor
will be assisting in the compilation of the business case. They also play a key
role at FBC stage when the GMP is formulated and agreed. This requires an
in depth understanding of the ProCure21 target setting process and of the
PSCP’s costings. During construction they will be undertaking open book
audits, advising on payments and controlling expenditure. It is important that
appointed Cost Advisors display the attributes referred to in figure 9. A
collaborative approach and detailed understanding of ProCure21 are both
Implementation Advisors
The P21 Implementation Advisors typically provide the next level of input to
the scheme. The Implementation Advisor role is to implement the principles
of ProCure21 – they provide a free service as part of the ProCure21 team. It
is important that they are engaged at the outset of the scheme and remain as
a source of guidance and support throughout. They will help to ensure that
the required ProCure21 principles and procedures are adhered to and that the
scheme is implemented successfully. Providing the scheme is running
smoothly their input will be minimal during construction but they will be
interested in capturing any lessons learned at the end of the scheme (when
the Review Workshop is undertaken).
Supervisors
Supervisors are also named individuals within the Contract (NEC2, Option C).
Under ProCure21, their role requires greater involvement at the design
development phase as opposed to checking on site.
ProCure21 team
Recruitment:
It is inevitable that some NHS Clients will not have sufficient in-house
resource to manage ProCure21 schemes or perhaps are lacking experience
Average
Step 5 NHS client selects a shortlist of PSCP’s timescale
& invites them to an Open Day
– 3 weeks
These criteria may be altered by the NHS Client and weighted accordingly.
They also need to be aware how ProCure21 may affect them, the input they
will need to provide and key areas of responsibility.
- The need to ensure that realistic aspirations, budgets and timescales are
set.
- The need to ensure that the right resource and expertise exists and is
available to represent the NHS client.
- The need to ensure that they are engaged in all key decisions.
- The need to engage the P21 VAT recovery process prior to construction.
- Consider training to ensure that all key staff have the appropriate
levels of awareness and skills – further guidance can be provided by
the ProCure21 Implementation Advisor.
- Ensure that the Estates department has adequate resource and skills
in place – ideally with an accredited Project Director.
- Attendance at workshops and meetings to ensure that the facility is fit for
purpose.
- Ensure that all appropriate clinical staff, end users, stakeholders and
patient user groups are involved during the design development phase.
- Consider internal training/ joint training with the PSCP and supply chain to
ensure that all key staff have the appropriate levels of awareness and skills –
further guidance can be provided by the ProCure21 Implementation
Advisors.
- Ensure that senior personnel are aware of the impact e.g. cash flow on the
Finance Directorate and more proactive involvement of user groups.
- Ensure that all personnel are clear about their roles and responsibilities –
further guidance is contained in section 2.3.
For detailed guidance on the roles and responsibilities of the Project Manager
and Cost Advisor. Follow the link below
The role of the Project Director is recognised as being vital to the success of
ProCure21. Effective Project Directors will not only need to lead the process
and ensure that the scheme complements NHS Client strategy they will also
need to add value to the design process.
New skills and techniques are required in order to maximise the success of
ProCure21. A number of courses have been specifically designed to ensure
that Project Directors are equipped with the appropriate skills.
- Consider training to ensure that all key staff have the appropriate levels
of awareness and skills e.g. Cost Advisor knowledge of the Target
Setting process – further guidance can be provided by the ProCure21
Implementation Advisors.
For detailed guidance on the roles and responsibilities of the Project Manager
and Cost Advisor. Follow the link below
Section checklist:
Scheme Launch
The Launch workshop serves as a formal start to the scheme and, very
importantly, the relationship between all those involved in its development and
delivery.
Launch workshop - Child & Mental Health Scheme (CAMHS), St. Nicholas
Hospital, January 2005 – Photograph of team developing the scheme Charter.
The Launch Workshop is a formal launch to the scheme. All parties involved
in the scheme are involved in a one day workshop. The workshop allows the
team to build relationships and develop mutual objectives for the scheme.
Project Board
Principals Group
(strategic focus)
Core Group
(delivery focus) Task team
Task team
Core Group
The Core Group are focussed on delivery and the day-to-day management of
the contract. They will be constantly reviewing the programme, cost
projections and ensuring that their decisions are well founded. They are
supported by a number of Task Teams who perform functional duties e.g.
design development, end users, commercial management, commissioning
and infection control.
Task Teams
The Task Teams provide technical support and opinion to the Core Group and
typically provide update reports on a monthly basis. The Core Group, in turn,
reports overall progress to the Principals Group. The reporting from Core
Group to Principals Group will typically focus on strategic issues (the main
focus of the Principals Group) and raise any key risks to overall delivery e.g.
lack of funds or time.
The names of the groups may vary or be altered but the mechanism remains
the same (e.g. the Core Group is sometimes referred to as a Delivery Team).
This integrated team structure ensures that all key parties (namely Estates,
the PSCP and clinical/ end user representatives) work effectively, are
empowered to make decisions and work under a defined structure.
Scheme Board
The dotted line to the Scheme Board (or NHS Client Board) shows how some
NHS Clients have developed this further and may still require a further tier
consisting solely of NHS Client representatives. The Scheme Board may be
responsible for a number of capital schemes but recognise the need for an
integrated team structure for ProCure21 below its own level.
This integrated team approach also helps support the use of the Contract
(NEC2, Option C) – dealing with Early Warnings and agreeing the impact of
Compensation Events in a timely manner (explained further in section 4.3).
Project Board
Principals Group
(strategic focus)
The Task Teams may still be aligned to a single Core Group or may, to
maximise resource, provide technical support across a number of Core
Groups.
The focus of the Principals Group then shifts from one of managing a single
Core Group to that of a multiple Core Groups. Issues such as the sharing of
best practice and consistency of service tend to feature more heavily on the
multiple ProCure21 schemes.
The purpose of this ‘joint action plan’ is to take the team from the
current position to the point where the Contract (NEC2, Option C) can be
signed. This should be as soon as practically possible.
Once in place, the ‘joint action plan’ can be monitored. Progress is typically
reported by the Core Group to the Principals Group. If there are risks or
slippages in the ‘joint action plan’ then remedial actions will be required.
It is important that the team deliver this short term action plan and move into
the ‘scheme development’ phase as soon as practically possible.
Section checklist:
Scheme Development
Introduction
The style of ProCure21 and the ‘scheme contract’ promotes the use of
contemporary management techniques. These are also applied to formulate
the Guaranteed Maximum Price (GMP). The GMP needs to be validated to
ensure that costs are in line with expected norms (Departmental Cost
Allowance Guides - DCAGS) and represent value for money.
The extent of ‘scheme development’ with the PSCP will therefore depend on
when the NHS client has selected the PSCP. This could range from Pre-SOC
or as late as FBC. The timing of PSCP selection should be determined at the
outset of the process (as explained in section 1.3 of the ProCure21 Guide).
5.0 Delivery
4.0 Scheme
development
C
FB
C
OB /
ts
C in
SO po
c t ry
3.0 Scheme Launch
e - so en
Pr P
PSC e21
l r
2.0 Team selection t ia
o Cu
n
te f Pr
Po o
1.0 Defining how se
P21 is applied U
It is important to note that the NHS Client will still need to conform to the
recognised approval gateways for managing capital schemes – the Capital
Investment Manual (CIM).
Whilst it is not the purpose of the ProCure21 Guide to explain these in detail a
summary of the gateways is contained overleaf and web address provided
with further guidance.
• Stakeholder approval
• Appointed:
Prerequisites:
¾ Project Director
¾ Project Team
¾ Clinical working groups
• Outline planning approval
• Levels of delegated authority
• Project Initiation Document (PID)
The use of the Contract (NEC2, Option C) conforms with the aforementioned
approval gateways (SOC, OBC and FBC) and, as such, provides control
mechanisms to the NHS Client.
Figure 18 below illustrates the ‘phases’ of the contract and how these relate to
the approval gateways. As a condition of entry into each ‘phase’ of the
contract a detailed list of aims and deliverables is agreed with the PSCP these
are identified in a critical path programme for continuous monitoring.
The commercial rates and profit levels for these duties are predetermined as
part of the framework agreement.
As each Phase of the contract is agreed, the PSCP is then duty bound to
deliver the agreed list of duties in accordance with an agreed programme and
Phase 4
Construction phase
It is important that the team develops a joint action plan, broken down into the
sequential phases, to ensure that scheme development is controlled and
monitored.
Close liaison with clinicians and end users is vital during scheme
development.
An accepted universal contract has been adopted for use as the basis of all
ProCure21 scheme specific contract documents. It is in general use in the
construction industry by many major public and private sector clients.
The current version of the Benchmarking Toolkit has been developed in close
liaison with the Office of Government Commerce (OGC).
The format of the toolkit is easy to follow and navigate. It is provided in Excel
format with hyperlinks to guide users through the various sections.
Explanation:
Best Client - evaluates the PSCP’s feedback on the NHS Client.
Design Quality - evaluates the design at defined stages of development
using AEDET (Achieving Excellence Design Evaluation Toolkit).
Environment - evaluates the environmental impact at defined stages of
development using NEAT (NHS Environmental Assessment Toolkit).
Client Satisfaction - evaluates the NHS Client’s satisfaction with the process
and product.
Cost - analyses the capital cost of the scheme at GMP using a
template based on a standard industry format.
Safety – evaluates the safety record of the PSCP.
ProCure21 Guide 45 Version 5.0, January 2007
Defects - scores the level of defects at handover.
Cost/Time Certainty - evaluates the cost/time outcome.
Completed
Best
at Stage
Client
Cost/Time Design FBC/GMP
Certainty Quality
CONSTRUCTION
Continuous
Defects Improvement
Environment
Client
HANDOVER
Safety
Satisfaction
Cost
Analysis
PPE
The instructions page of the toolkit is illustrated below. This provides straight
forward guidance on how to use the toolkit. ‘Grey’ cells are to be completed
by the PSCP and, ‘yellow’ cells, by the NHS Client.
The timeline highlights the three main stages when the toolkit requires
updating:
The safety records, however, need updating quarterly during the construction
phase.
The timeline acts as the ‘hub’ of the toolkit. Links are provided to the timeline
on each page to ease navigation throughout the toolkit.
Benchmarking Spreadsheet
Review Workshops
Review Workshops typically involve the same parties that attended the
Launch Workshop (clinicians, supply chain and Estates etc) and, in an open
environment, capture what has worked well and what could be improved
upon. Even the most successful schemes can find areas of improvement so it
is important that effort is devoted at key stages to ensure ongoing
improvement. It is also important that the outcomes of the reviews are fed
back to the ProCure21 team so that they may share them with other NHS
Clients.
Separate engagements are entered into for each of the business development
stages SOC, OBC, FBC and delivery. These are referred to as Phases 1-4
respectively.
- Easy to understand,
- Written in plain English, and;
- Well structured.
- Early Warning notices – to deal with problems as they arise and avoid
additional costs if possible,
- A resource led programme which should be kept current at all times,
- Early agreement of variations (referred to as Compensation Events).
Cost Advisors should be well versed in the application of the Contract (NEC2,
Option C) and provide guidance on both its completion and use.
For detailed guidance on the roles and responsibilities of the Project Manager
and Cost Advisor. Follow the link below
1. It is important that PSCP’s and NHS Clients enter into the relevant stage of
the contract (i.e. 1, 2, 3 or 4) as soon as practicable.
The Guaranteed Maximum Price (GMP) is the agreed price between the NHS
Client and the PSCP for the construction works. This section explains how
the GMP is agreed. The explanation is broken down into two halves:
The GMP should be agreed under ProCure21 as part of the Phase 3 duties
i.e. at FBC. This is based on the premise that a more accurate GMP will be
established if it is based upon a substantially complete design.
Please note: This does not prevent enabling works being undertaken as they
can be defined as part of the Phase 3 duties.
Good practice also suggests that a number of activities need to occur before
the GMP can be successfully agreed:
- All innovation needs to be incorporated into the GMP (this ensures that the
NHS Client obtains value-for-money)
The NHS Client’s business case figures are initially shared with the PSCP and
worked on jointly. Over time, this hopefully sees a reduction in scheme cost
as the design develops and risks are managed out.
The overhead and profit levels of the PSCP and key supply chain members
have already been agreed as part of the framework selection process. This
allows the team to focus on the scheme in hand rather than deal with
commercial issues.
Formal techniques such as Value and Risk Management are employed at this
stage and help define the brief for the scheme and allocate risk in an
equitable manner.
£
Shared savings
GMP
Ethos continues:
- Value Engineering
- Joint working
GMP build-up
Professional fees
GMP
Phases 1-3
Fee %
PSCP Risk
Site On Cost
Own work
Sub/c 6
Sub/c 5
Sub/c 4
Sub/c 3
Sub/c 2
Sub/c 1
- The amounts due and incurred in Phases 1-3 (SOC, OBC & FBC)
The GMP represents the maximum price that the NHS Client will pay for the
works unless:
‘The GMP must be analysed and presented in the same format as the
economic cost models, clearly distinguishing between departmental and on-
cost areas’.
NHS Cost Advisors will need to undertake this exercise in conjunction with the
PSCP.
Section checklist:
2. Compliance with the NHS approval Gateways (SOC, OBC & FBC)
8. An agreed GMP
Delivery
Introduction
The Contract (NEC2, Option C) will be used throughout the process. If the
previous Phases (1-3) have been completed successfully then the parameters
of scheme delivery should be clearly defined and measurable. The contract
contains detailed procedures for dealing with any likely risks and managing
change.
The parameters of the scheme should be clearly established and these should
form the cornerstone of project management on the scheme.
Irrespective of the events that occur after signing the GMP, the use of the
Contract (NEC2, Option C) should remain the focus for the delivery team.
The risk management, programming and change management procedures
will ensure that issues are dealt with in a timely and equitable manner.
Effective use of the NEC pro-forma’s will also ensure that an audit trail is
maintained and that administration costs are kept to a minimum.
Practical use of the contract is supported by using the NEC pro-forma’s. For a
copy of these please click the link below
Cost control
Managing the ‘gain share’
Open-book audit
Cost Control:
The GMP (broken down into an Activity Schedule) may therefore be easily
aligned to the detailed resource plan (further broken down into labour, plant
and materials) and a ‘cumulative value’ curve established (highlighted in blue
on the diagram).
GMP
Cumulative value
(breakdown of the GMP)
Pay cumulative
cost (lesser of the
£
two)
Cumulative cost
Pay cumulative
value (lesser of
the two)
Valuation 2 Valuation 8
Time
The ‘cumulative value’ is then plotted against the ‘cumulative cost’ curve to
track commercial progress (in this case predicting a ‘gain share’ at Final
Account stage).
Under ProCure21 if the ‘cumulative cost’ exceeds the ‘cumulative value’ then
only the ‘cumulative value’ is paid by the NHS Client (example given at
Valuation 2).
Conversely, if the ‘cumulative cost’ is less than the ‘cumulative value’ then
only the ‘cumulative cost’ is paid (example given at Valuation 8).
In both cases the NHS Client pays the lesser of the two. It is important that an
equitable breakdown of the GMP is agreed. If the breakdown is inaccurate
then the PSCP will be disadvantaged and/or the NHS Client will have
unpredictable cash flow.
A graphical representation of the finances (as outlined above) will also prove
invaluable to the team in order to help track and control expenditure. This
The PSCP is paid actual cost plus Fee % (i.e. labour, plant, materials and
subcontract work) but only up to the ceiling price of the GMP.
If savings are generated against the GMP then these are shared on a 50/50
basis. There is provision in the contract so that the NHS Client may reinvest
these savings back into the scheme e.g. to improve staff facilities or
furnishings.
If the amount of savings exceeds 20% of the GMP at completion the gain
share is only calculated on the 20% saving e.g. 10% maximum gain share to
the PSCP. The remaining saving reverts to the NHS Client (although to have
savings of this magnitude is extremely rare and suggests that the original
target was set poorly).
Figure 23 illustrates the relationship between the final GMP and the audited
final cost. The GMP will alter throughout the course of the contract to account
for variations (Compensation Events). At final account stage the final GMP is
then compared against the audited cost and the ‘pain/ gain’ share calculated.
The amended GMP (left hand column) is compared against the audited actual
cost. The middle and far right hand columns represent two Final Account
scenarios. The middle column reflects a ‘gain share’ where actual cost is less
than the GMP – any gain is shared on a 50/50 basis. However if the gain
exceeds a 20% cost saving then the NHS Client will retain the extra (this is
unlikely to occur and would suggest an inaccurate GMP).
If the cost exceeds the GMP without legitimate reason then the PSCP absorbs
any overspend (right hand column). Again, this would typically infer an
inaccurate GMP or inefficient working by the PSCP (e.g. putting right defective
work or inefficient management of resources).
Professional fees
Fee %
PSCP Risk
100% of further
Site On Cost
savings retained by
the NHS client
Own work
Actual Cost
Sub/c 6
Sub/c 4
Sub/c 3
Sub/c 2
Sub/c 1
Open-book audit:
A central audit of the PSCP’s has already been undertaken by the ProCure21
team. This covers the organisations internal company procedures.
ProCure21 Audit
Local NHS Client audits will still be required to ensure that the amounts paid
to the PSCP are accurate. This is a role typically undertaken by the Cost
Advisor on a monthly basis.
The open book principles under ProCure21 are not just restricted to the
financial aspects – the ethos is carried through to all areas of PSCP working
e.g. subcontractor procurement and risk management.
If undertaken properly these will assist the team in improving performance and
ensuring that the scheme remains on track.
Section checklist
Evaluation
Introduction
The evaluation section of the ProCure21 Guide is relatively short in length but,
nevertheless, a vital stage in the ProCure21 life cycle.
This section of the guide reinforces then need to use the Benchmarking
Toolkit and also to consider the use of Review Workshops.
Despite being the last section within the ProCure21 Guide the ethos of
continuous review and the search for improvements in delivery should be
present throughout the entire process.
Benchmarking Toolkit:
The timing and representation of these reviews should be included within the
agreed delivery plan for the scheme.
It is important that this data is completed as it not only provides the team with
closure on the success of the scheme but also provides invaluable feedback
to the ProCure21 team.
Updated GMP:
This provides essential data to the ProCure21 team and enables comparisons
to be made against other methods of procurement and trends within
ProCure21.
Review workshops:
Members of the team are about to start another scheme and would
benefit from a review of current performance.
The ProCure21 team hold regular events/ conferences and chair a Best
Practice Club. The aim of these forums is to learn from live schemes and to
share experiences.
The ProCure21 team should be the first point of contact should the team
consider that their own experience is worthwhile sharing. An appropriate
forum/ mechanism for capturing this can then be determined.
If you have something that you would like to share with the other ProCure21
schemes then you can add it into the ProCure21 Best Practice Database.
Follow the link below to the database, where there are further instructions on
its use.
Section checklist:
Term Explanation
AEDET (Achieving Excellence in Part of the Benchmarking toolkit that evaluates
Design Evaluation Toolkit) design quality against a range of factors
Charter A non-legally binding document which records the
partnering intentions of the parties. It incorporates
a mission statement, mutually agreed objectives,
together with the signatures and logos of all the
parties
Core Group Part of the integrated scheme team focussed on
delivery
KPI (Key Performance Indicator) Key measure of success
NEAT (NHS Environmental Part of the Benchmarking toolkit that evaluates the
Assessment Toolkit) environmental impact of a scheme
Implementation Advisor Representative of the ProCure21 team responsible
for the correct implementation of ProCure21
PSCM (Primary Supply Chain Second tier supply chain member – a strategic
Member) partner of the PSCP e.g. architectural practice/
Mechanical contractor
Principals Group Part of the integrated scheme team focused on
strategic outcomes
ProCure21 ProCure21 is a procurement initiative aimed at
delivering better quality healthcare buildings and
improved value for money.
Professional Advisor Covers any specialist advice typically provided by
Cost Advisors, Engineers, Architects and Specialist
Procurement Advisors etc.
Project Director Director responsible for the overall delivery of the
scheme.
Project Manager Named individual within the Contract (NEC2,
Option C) that has overall responsibility for
administrating the contract.
PSCP (Principal Supply Chain Principal member of the supply chain
Partner)
SCM (Supply Chain Member) Members of the supply chain
Supervisor Named individual within the Contract (NEC2,
Option C) that is responsible for supervising the
works
Task team Part of the integrated scheme team focussed on
functional delivery e.g. design development,
commercial