Professional Documents
Culture Documents
CONSTRUCTABILITY REVIEW
By the time that the design has reached the bid document stage there are few
opportunities to make improvements or changes without causing added design cost and
delay the project. It is not too late to correct errors, which would cause defective bidding
or result in costly change orders to the work. Addendums can be issued during the
bidding phase, but they do complicate the process of getting bids, since the bidders must
read through several documents in addition to the original bid set. Sometimes they dont
fully understand the final requirements and the bids suffer accordingly.
As the Construction Manager you are probably seeing these plans for the first time. The
user and architect have been working on this project for months, while you only have a
few days to perform the Constructability Review before bidding commences.
The following guidelines are provided to help you perform this review in a timely, but
accurate manner:
1. Visualize the project first. (Dont just start reading page one like a novel).
a. Read Summary of Work.
b. See site plan and drawing index.
c. Look at floor plans and architectural elevations.
i. What are the principal materials of construction for:
1. Floor
2. Wall
3. Roof
ii. Where are the exterior items:
1. Parking lot/roads
2. HVAC units
3. Transformer
d. Scan Division 1 for:
i. Time for completion
ii. Owner provided items (utilities, material)
iii. Salvage material
iv. Safety
v. Quality control plans
vi. Schedules required
vii. Progress meetings
2. Detailed study of plans: (make notes on plans in color as you go, if more than one
person reviewing then use different colors for each person.)
a. Find utility connections to existing:
i. Water, sewer, electricity, storm water, telephone, gas (cut off
valves for all? Or outages later)
b. Locate limits of construction
i. Close existing parking or roads?
ii. Close walkways?
iii. Fence required (what type? Screen fabric?)
c. Scan other drawings to see:
12-1
12-2
13-1
C.
D.
E.
F.
G.
Now that you have assembled all of these documents, and created the contract what do
you do when different sections of the contract contradict other sections? The legal
implications of confusion and contradiction are going to cost you more money to resolve,
unless there is an orderly process to eliminate the confusion. Step one is to determine the
correct technical solution to the irregularity, then decide if it is a change order or not.
This is not an automatic process, since the meaning of a single word could cost one of the
parties to the contract substantial sums. Usually the material typed specifically for your
project will govern over preprinted standard clauses. This means that you should spend
more time reviewing the nonstandard clauses.
It is generally accepted that the precedence of the contract documents is as follows:
Table 2
Precedence of Contract Documents
1. Change orders issued after award.
2. The Agreement (signed form with administrative clauses,
such as time for completion, total price, and also references
the specs and drawings to include them in the contract.)
3. Addenda (those with a later date have precedence over
earlier versions).
4. Supplementary Conditions (included in the Specification
package, they vary for each project)
5. General Conditions (preprinted fine print clauses that dont
vary for each project)
6. Division 1 of the Specifications (Administrative)
13-2
13-3