Professional Documents
Culture Documents
I. INTRODUCTION
VCB
MCB
L
external
grid
Z()
RL choke
MV
cable
MV/LV
transformer
L
C
AC
DC CB
DC
PV
MV
cable
external 2nd
grid
MCB
4th
AC
1st
3rd
PV
DC
MV/LV
transformer
2nd
external
3rd
grid
MV
cable
MCB
AC
1st
MV/LV
transformer
DC
PV
MV
cable
MCB
1st
AC
4th
2nd
external 3rd
grid
PV
DC
MV/LV
transformer
external 2nd
grid
MV
cable
MCB
1st
MV/LV 3-f
transformer
AC
DC
PV
(2)
where:
A Rate of Rise of Dielectric Strength (RRDS),
B initial dielectric withstand,
t0 opening time instant
Each time, when the dielectric withstand exceeds the TRV,
the current is chopped again. This process is referred to as
multiple arc re-ignitions and it continues until the dielectric
withstand of the gap exceeds the crest TRV value. Transient
effects during transformer energization are also related to the
dielectric withstand, which decreases from its maximum
value to zero during contacts closing. Multiple arc pre-strikes
can be recorded when contacts are very close to each other.
Mainly this effect results in fast charging of the primary
winding capacitance.
It has to be added that various circuits can be subjected to
switching operations. Most typically those are formed out of
MV cables and distribution/arc furnace/motor transformers.
6/0.4 kV kV
LC filter
L
1 m wire
MV cable
C
20 kVA
MV supply
50
100
200
t [ms]
300
400
B. PSCAD simulations
Based on the measurement results a PSCAD model was
prepared, which allowed to perform further studies. Its
equivalent circuit is presented in Fig. 10.
VCB
#2
50 [ohm]
#1
200 [uH]
#1
cable_ 85_m
#2
0.1 [ohm]
0.1 [mH]
1 [nF]
-1 0
-1 5
-2 0
t [m s ]
25 [uF]
1.8 [nF]
R=0
0.2 [nF]
40
0.2 [nF]
U [kV]
30
t [ms]
0.2 [nF]
0
-5
20
3 [nF]
10
3 [nF]
1 0
0.1 [ohm]
1 5
-10
4.8 [nF]
-5
25 [uF]
Value
6 kV
MV supply
0.25 %
(from 250 kVA transformer)
4.5 %
6 kV / 0.4 kV
4.23 %
4.3 %
20 kVA transformer
Cp_g = 3 nF
winding
Cp_ph_ph = 0.2 nF
capacitances
Cp_s = 1 nF
rated voltage
12 kV
VCB
chopping current
3 Ap
1 m wire
inductance
1 H
length
85 m
MV cable
impedance Z
50
inductance L
200 H
inverter output LC filter
capacitance C
25 F
Cp_g capacitance between primary winding and ground
Cp_ph_ph capacitance between phases of primary winding
Cp_s capacitance between primary and secondary winding
U [kV]
Parameter
UN
I0
uk%
UP/US
I0
uk%
25 [uF]
Component
I[
A
]
TABLE I
COMPONENTS OF LABORATORY TEST STAND
15.0
10.0
10.0
5.0
5.0
U [ kVp]
0.0
U [ kVp]
-5.0
0.0
-5.0
-10.0
-10.0
-15.0
-15.0
-20.0
-20.0
t [s]
0.0460
0.0470
0.0480
0.0490
0.0500
t [s]
0.0510
0.0700
0.0725
0.0750
0.0775
0.0800
0.0825
0.0850
0.0875
0.0900
10.0
15.0
5.0
U [ kVp]
10.0
5.0
U [ kVp]
0.0
-5.0
0.0
-5.0
-10.0
-15.0
-10.0
sec 0.040
0.050
0.060
0.070
0.080
-20.0
0.090
t [s]
0.076900
0.076910
0.076920
0.076930
0.076940
0.076950
0.80
0.60
15.0
0.40
10.0
0.00
5.0
[A ]
0.20
U [ kVp]
-0.20
-0.40
-0.60
0.000
0.0
-5.0
-10.0
-0.80
sec
0.050
0.100
0.150
0.200
0.250
0.300
0.350
-15.0
0.400
-20.0
0.0700
0.0720
0.0740
0.0760
0.0780
0.0800
0.0820
0.0840
0.0860
0.0880
0.0900
15.0
10.0
5.0
U [ kVp]
t [s]
0.0
-5.0
-10.0
-15.0
-20.0
t [s]
0.077330
0.077335
0.077340
0.077345
0.077350
Current at MV side
30
20
10
I [A]
0
-10
-20
-30
-40
t [s]
0.020
0.030
0.040
0.050
0.060
0.070
40
30
20
U [ kVp]
10
0
-10
-20
-30
-40
sec
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
40
VI. SUMMARY
Research presented in herein paper covers studies of
transient states which can occur in photovoltaic power plants.
The following most important findings can be pointed out:
1) switching sequences for operation of PV power plants were
identified and presented,
2) laboratory measurement of transformer energization and
de-energization at no-load state were conducted,
3) based on recorded voltage waveforms, PSCAD model was
prepared and fitted in order to accurately reflect the
laboratory set-up, developed PSCAD model served for further
simulations analyses of inrush current breaking and
interruption of transformer short-circuited at LV side was
conducted,
4) it was found that significant overvoltages are possible in
two states mentioned above due to the fact that interrupted
current is higher than during no-load state, higher chopping
current (3 Ap maximum) results in higher energy that causes
oscillations of TRV,
5) it was shown that RL chokes installed before the MV cable
can decrease the overvoltage steepness, also some high
frequency components were filtered out.
VII. REFERENCES
[1]
30
20
U [ kVp]
10
[2]
[3]
[4]
0
-10
-20
-30
-40
sec
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]