You are on page 1of 214

SPACE PROGRAM SAN FRANCISCO GENERAL HOSPITAL MEDICAL CENTER

MAY 31, 2007


City and County of San Francisco
Department of Public Health
Fong & Chan Architects

SPACE PROGRAM SAN FRANCISCO GENERAL HOSPITAL MEDICAL CENTER

Table of Contents
Section 1

Executive Summary
Introduction
Overview
Development Process
Space Program Objectives and Assumptions
Findings
Recommendations
Program Summary

Section 2

Site Review
Introduction
Site Review
Stacking
Floor Plans

Section 3

Space Program Tables


Introduction
Program Summary
Inpatient
Medical/Surgical
ICU/Step-Down
Obstetrics
Pediatrics
NICU
Diagnostic and Treatment
Perioperative
Diagnostic Imaging
Ancillary Services
Emergency
Support
Administration and Public
Auxiliary Support
Plant Services
Program Allocation by Floor

SFGHMC | Space Program May 2007

Section 4

Statement of Probable Construction Cost


(Issued under separate cover)

Section 5

Acknowledgments
Steering Committee
Inpatient
ICU/Step-down
Women & Children
Diagnostic
Emergency
Perioperative
Ancillary Support
DPH Program Management/Administration
DPW Project Management
Fong & Chan Architects
Forell/Elsesser Engineers, inc.
Gayner Engineers
TBD Consultants
Herrero Contractors

Section 6

Appendices
Appendix A Space Program Work Plan
Appendix B Bed Projections
Appendix C Meeting Minutes

SFGHMC | Space Program May 2007

Section 1

Executive Summary
Introduction
This space program report provides the basis for the
development of the design and eventual construction of the
new acute care hospital building at San Francisco General
Hospital Medical Center (SFGHMC).
The report includes a comprehensive written space program
and a preliminary site review.

Overview
In 1994, California Senate Bill (SB) 1953 was passed as an
amendment to and furtherance of the Alfred E. Alquist Hospital
Seismic Safety Act (Alquist Act) enacted in 1973. The intent of
the original act was to ensure that acute care hospitals remain
functional shortly after a major earthquake. The Alquist Act
requires all general acute care hospital buildings to meet
explicit seismic safety standards by either retrofitting existing
buildings or electing the option, provided by SB 1801 (Speier)
adopted in 2000, to rebuild a new hospital building by 2013.

Fig. 1-1

Aerial View of SFGHMC

In 2000, SFDPH commissioned a seismic evaluation study


which concluded that the Main Hospital building at SFGHMC
has significant seismic deficiencies and that it may not be
capable of providing health care services to the public after a
major seismic event.1 The SFGHMC Main Building was
categorized as a Structural Performance Category 1 (SPC-1).
Buildings categorized as a SPC-1 pose a significant risk of
partial or total collapse and a danger to the public.
In 2001 the San Francisco Health Commission adopted
resolution 1-01 supporting the construction of a new general
acute care hospital by 2013.
In May 2005, Mayor Gavin Newsom and Public Health Director
Mitch Katz established a Blue Ribbon Committee to study San
Francisco General Hospitals future location. In October 2005
the Blue Ribbon Committee issued a report to Mayor Newsom
recommending rebuilding the new hospital on the existing
Potrero Campus instead of at the new UCSF Mission Bay
Campus as had been suggested.2 The Blue Ribbon Committee
found that the Mission Bay Campus was not feasible from a
cost, long-term financing or site acquisition perspective. In

SFGHMC | Space Program May 2007

1-1

Section 1 Executive Summary

addition, the Committee found that coordinating care between


the Mission Bay Campus and the Potrero Campus would create
operational challenges not readily overcome.
In the final Blue Ribbon report issued to Mayor Gavin Newson,
two locations within the Potrero Campus were acknowledged as
potential viable sites to build the new acute care hospital. One
option was to locate the new acute care hospital to the north
and abutting the existing hospital, the other option was to
locate the new acute care hospital west of the existing hospital
on the west lawn in between two existing masonry buildings,
the site of a former hospital building demolished in 1972.
Proposed site for west option
Proposed site for north option*
Proposed site for south parking lot
* North option requires the demolition of
Bldg 100 and M-wing

The Blue Ribbon Committee recognized that the option to build


to the north would require the demolition of Building 100 and
M-wing which currently houses the majority of the ambulatory
services and the clinical lab. The option to build to the west
would have significantly less overall impact on the existing
acute care hospital and would not likely require the demolition
of existing structures.
Even though the Blue Ribbon Committee did not consider where
on Potrero Campus the new acute care hospital should be built,
it suggested that the west option should be further examined
as a potential alternative to the more disruptive North option. 3
Of note, prior to the establishment of the Blue Ribbon
committee the option to build the new acute care hospital on
the existing south parking lot adjacent to the existing hospital
was reviewed. This option was rejected by the members of the
Community Advisory Committee due to the sites proximity to
the nearby residential neighborhood, specifically highlighted
were both noise and bulk concerns. In addition, the ongoing
operations of the existing emergency and psychiatric emergency
services would be severely impacted by the construction due to
their direct adjacency to the site. Relocation of these services
was considered not to be a workable or practical option.

Fig. 1-2

Aerial View of SFGHMC showing the


various building site options

In Spring 2006 the San Francisco Department of Public Health


(DPH) commissioned a site feasibility study to determine if a
new hospital building could be constructed on the west lawn.
The site feasibility study prepared by Anshen + Allen and issued
on September 25, 2006 concluded that a compliant 428,003
sq. ft. hospital building could be constructed on the west lawn
without demolishing any buildings. The study also stressed that
the assumed program could be accommodated within the
existing zoning height limits but the bulk limits may be
exceeded.

SFGHMC | Space Program May 2007

1-2

Section 1 Executive Summary

In November 2006, Fong & Chan Architects started the


programming effort to determine the space requirements for
the new acute care hospital and to validate the feasibility of the
west lawn site. The contents of these items are described in
detail in this report.

Development Process
The essential data used to develop the space program was
collected through the implementation of a work plan. This work
plan involved a series of workshops and meetings with hospital
staff and Fong & Chan Architects under the guidance of the
Steering Committee.
Hospital staff participated in seven distinct user groups:
Inpatient, Women & Children, Diagnostic, ICU/Step-down,
Emergency, Perioperative and Ancillary Support representing a
broad cross section of healthcare expertise at SFGHMC.
Refer to Appendix A for a copy of the Work Plan.

Space Program Objectives and Assumptions


In the course of the planning process the Hospital
Administration and the Steering Committee identified the
following space programming objectives and assumptions:
OBJECTIVES

SFGHMC | Space Program May 2007

To develop and submit a space program for a new acute


care Hospital to fit within the West Lawn of San Francisco
General Hospital Medical Center (SFGHMC)

To maximize the number of patient rooms and exam rooms


within the building envelope

To increase the number of ICU/CCU patient rooms to reflect


current demand and to meet future projections

To look for cost saving opportunities throughout the


development of the space program, including balancing the
allocation of space between existing and new Hospitals to
the extent that is practical in accomplishing established
goals

1-3

Section 1 Executive Summary

To maximize facility flexibility by programming multifunctional spaces and flexible step-down nursing units

To update and submit a Statement of Probable Construction


Cost reflecting the findings and conclusions reached in the
space program

Potrero Avenue

ASSUMPTIONS

The building site will be located directly west of the existing


main hospital building, over the West Lawn between
Building 20 and Building 30

Demolition of existing buildings will not be required

The San Francisco Planning Code limits the overall mass of


a building. If required, these bulk limitations can be
exceeded by applying for a conditional use permit

The San Francisco Planning Code also limits the overall


height of a building, however the height of the new acute
care building should not exceed these limits

Allocation of space in the new Hospital will be limited to


those functions that are required to be in a new acute care
hospital and to those functions that are required to meet
operational adjacency requirements

The following major departments (not an complete list) will


not be part of the new hospital program, but will stay in the
existing hospital building:

Fig. 1-3

Site Plan showing building site

Acute Psych
SNF
Clinical Labs (except for the blood bank and specific
functions that by code are required to be in a compliant
acute care facility)
Cafeteria
Kitchen
Rehab
Nuclear Medicine

SFGHMC | Space Program May 2007

Departmental gross square footages (DGSF) will be derived


from the examination and analysis of SFGH census data;
regulatory requirements; best practices in Health Care
design; and suggestions from user groups, administrative
personnel and industry leaders

1-4

Section 1 Executive Summary

Space Program will be developed with the assumption that the


new acute care hospital will begin providing services to the
public in the year 2015.

Findings
This report describes a space program for a 284 bed new acute
care hospital to be located in the west lawn of SFGHMC with an
assumed building massing of 8 stories (including basements)
and an area of 420,260 square feet. The principal findings of
the space program study are as follow:

A code compliant acute care hospital can be built on the


west lawn without demolishing any existing buildings

The assumed building massing as described in this report


can be accommodated within the established zoning height
limits however the portion of the building massing above 65
feet in elevation will likely exceed the bulk limits. A
conditional use permit may be required

The new acute care hospital should be linked to the existing


hospital building by means of a 2nd floor bridge connection
and a basement tunnel connection to improve the
movement of supplies and personnel

The total number of acute care beds can be expanded from


230 to 284 without significantly increasing the total building
gross square footage. The assignable square footage of
each patient room was thoroughly discussed with each
respective user group and the final agreed upon area was
deemed appropriate for a public teaching hospital

Fig. 1-4

Aerial view looking south of building site

SFGHMC | Space Program May 2007

1-5

Section 1 Executive Summary

Recommendations
In the course of the space programming effort the various User
Group Committees and the Steering Committee identified
project goals and objectives to be considered in the design
phase of this project. These committees envisioned the
creation of a modern healthcare facility that embodied the
Hospitals Mission to deliver humanistic, cost-effective, and
culturally competent health services to the residents of the City
and County of San Francisco. The following recommendations
should be used as a foundation for the development of the
design of the new acute care Hospital:

Design a state-of-the-art acute care hospital with safe,


secure, efficient and user-friendly patient and work
environments to promote access to services, quality of care,
patient safety, customer satisfaction, staff morale, resource
management, effective partnership, and academic
excellence

Design flexible and efficient spaces able to handle


technological advances and allow for program changes

Incorporate emerging green building technologies and


sustainable design principles

Consider the architectural context of the existing campus in


the development of the new acute care hospital

Create spaces that support collegial professional


interchange and discussion and promotes educational
interaction

Perform cost management studies such as earn-value


analysis, life-cycle costs analysis and value engineering
throughout the planning and design process to improve the
performance of the new acute care hospital without
exceeding the budget

Degenkolb Engineers/ Structus Inc., SB1953 Seismic Evaluation Report,


December 2000
2 Blue Ribbon Committee on San Francisco General Hospitals Future
Location, October, 2005
3 Blue Ribbon Committee on San Francisco General Hospitals Future
Location, October, 2005
1

SFGHMC | Space Program May 2007

1-6

Section 1 Executive Summary

PROGRAM SUMMARY

Beds/Rm

DGSF

Remarks

Inpatient
Acute Medical
Medical/Surgical
Medical/Surgical - Forensic Unit
ICU/CCU
Step-Down
Obstetrics
Pediatrics
NICU
Subtotal

144
8
40
46
22
12
12
284

72,466
6,744
31,086
27,287
21,427
9,194
7,830
176,032

Perioperative
Surgery
Gastroenterology
Patient Intake and Recovery

15
5
57

23,369
4,158
17,914

Diagnostic Imaging
Cardiology
Radiology

6
8

4,606
15,425

Ancillary Services
Sterile Processing
Pharmacy
Clinical Laboratory
Pulmonary Function
Biomed
Morgue and Autopsy
Subtotal

91

6,774
6,139
2,344
2,071
1,019
1,920
85,738

60

36,668

4 units - each 36 beds


4 units - each 10 beds
20 beds flex up & 26 beds flex down
13 postpartum + 9 LDRP beds

Diagnostic & Treatment


14 OR & 2 IR

Inpatient only
Blood bank + Urinalysis

Emergency
Emergency
Clinical Care

54 exam + 6 trauma rooms

1-7

Section 1 Executive Summary

PROGRAM SUMMARY

Beds/Rm

DGSF

Administration and Public


Entry Area
Admitting
Administration

5,755
2,801
621

Auxiliary Support
Material Management
Messenger/Mailroom
Environmental Services
Information Technology
PBX
Dietary
Subtotal

8,250
2,544
1,294
2,731
719
828
25,544

18%
9%

323,982
58,317
34,407
416,706

Remarks

Support

DGSF Total
Circulation/ Exterior Wall
Plant Services
BGSF Total

Most Dietary Services to remain in Bldg. 5

1-8

Section 2

Site Review
Introduction
San Francisco General Hospital Medical Center is located in the
southeast quadrant of San Francisco, at the junction between
the Mission and Potrero Hill Districts.

101
1

Financial
District

SFGHMC
101
280

Fig. 2-1

Map of San Francisco

Potrero
Hill
Mission
District

SFGHMC

101

208

Fig. 2-2

Enlarged map of San Francisco

SFGHMC | Space Program May 2007

2-1

Section 2 Site Review

EXISTING CAMPUS DESCRIPTION


The hospital campus occupies an area of approximately 24
acres bordered on the west by Potrero Avenue, on the south by
23rd street, and on the east and north by U.S. Highway 101
and Vermont Street. The existing buildings were constructed
throughout the last century.
Dept. of Public Health (Built after 1987)
Dept. of Public Health (Built before 1987)
Dept. of Parking and Traffic
A

Building 90

Service Building

Building 1

Avon Center (Building 4)

Volunteer Center

Building 3

Building 10/20

Building 5 (Main Hospital Building)

Building 100

Building 30/40

Building 9 Trailer

Building 9

Parking Structure

01

y1
wa

Building 80

21st Street

gh
Hi

S.
U.

Behavioral Health Rehabilitation

22nd Street

G
22nd Street

J
L
23rd Street

23rd Street
Vermont Street

San Bruno Avenue

Utah Street

Potrero Avenue

Fig. 2-3

Existing campus

On its north-south axis the campus is approximately 1700 feet


long, and from the east to west about 750 feet wide. Moving
east from Potrero Avenue, the terrain slopes upward by
approximately 20 feet over street level, while the portion of the
site occupied by the main hospital building is relatively level.
Approaching the northeast, the campus continues to slope
upwards, gaining another 25 feet in elevation as it reaches the
freeway.
SFGHMC | Space Program May 2007

2-2

Section 2 Site Review

Site Review
BUILDING SITE
The West Lawn building site was established by SFGHMC prior
to this space program study. The buildable area on this building
site is approximately 72,100 square feet, defined on the west
by Potrero Avenue, on the north by Building 20, on the south by
Building 30 and on the east by Building 5. The buildable area
was determined using planning and building code best
practices.

21st Street
S.
U.
Hi
y1
wa
gh
01

22nd Street

Fig. 2-4

22nd Street

Aerial photo of SFGHMC campus map

West Drive

23rd Street

23rd Street
Vermont Street

San Bruno Avenue

SFGHMC | Space Program May 2007

Utah Street

Buildable area

Potrero Avenue

Fig. 2-5

SFGHMC campus map

2-3

Section 2 Site Review

SETBACKS
The following assumptions were made in determining the
extents of the buildable area:
Along the west the buildable area is defined by a plane created
by the alignment of Buildings 20 and 30.
Along the north/south/east the buildable area is defined by an
assumed property line located 20-feet from existing adjacent
structures to eliminate the need to fire rate the exterior walls
and windows of these existing structures.

Building 20
20'

20'

Building 5

20'

Building 30
Fig. 2-6

Site plan indicating location of assumed


property line
Buildable area
Assumed property line
Alignment plane

SFGHMC | Space Program May 2007

2-4

Section 2 Site Review

Similarly the distance between the assumed property lines and


the new acute care hospital is greater than 20-feet, eliminating
the need to fire rate exterior walls and windows of the new
acute care hospital, except at the first floor along the east side
where the exterior wall is aligned with the assumed property
line.
The first floor east exterior wall will be of 4-hour fire resistive
construction and openings within that wall assembly will not be
allowed.

Building 20
20'
20'

20'

Building 5

20'
20'

Building 30

Fig. 2-6

Site plan indicating location of assumed


property line
Assumed property line
Alignment plane

The below grade basement floors are not limited by setback


requirements and extend to within 21-feet of Building 20, 20feet of Building 5 and 34-feet of Building 30. These distances
were determined by balancing the need to maximize the
program area and the need to protect these existing structures
during construction.
SFGHMC | Space Program May 2007

2-5

Section 2 Site Review

Fig. 2-7

Aerial photo highlighting the 40


separation between the new acute care
hospital and adjacent buildings 20 & 30

Along the first floor the east exterior wall is aligned with the
assumed property line, on the floors above the east exterior
wall shifts 20-feet west to avoid opening protection
requirements due to proximity to assumed property line.

Assumed Property Line Plane

Fig. 2-8

Perspective sketch showing the property


line plane between the new acute care
hospital & the existing hospital

SFGHMC | Space Program May 2007

2-6

Section 2 Site Review

ASSUMED BUILDING MASSING


The assumed building massing derived from the 2006 Site
Feasibility Study was developed to determine the constraints on
the space program resulting from site, planning and code
limitations. The assumed building envelope was exercised with
the space program in an iterative process to validate the
feasibility of the space program assumptions.

The assumed building massing descends one floor and rises


7 floors below and above grade respectively along Potrero
Avenue. Along West Drive, which is at a higher elevation the
building descends 2 floors and rises 6 floors below and
above grade respectively

The designation of first floor was assigned to the floor that is


level with grade along West Drive to match the floor
designation of the existing hospital building. The footprint of
the first floor is 53,092 square feet which represents
approximately 78% of the buildable area

To reduce the bulk of the building massing the footprint of


all floors above the first floor has been further reduced

Fig. 2-9

View of SFGHMC looking northeast

SFGHMC | Space Program May 2007

2-7

Section 2 Site Review

SITE CIRCULATION
The suggested circulation on the SFGHMC campus is shown on
the plan below. In general, ambulance and service vehicle
access is from 22nd Street. Public vehicle access is from 23rd
Street. Pedestrian access is from Potrero Avenue, 22nd Street
and 23rd Street.

21st Street
S.
U.
gh
Hi
01
y1
wa

Fig. 2-10

View of SFGHMC looking northeast

22nd Street

22nd Street

23rd Street

Fig. 2-11

Suggested site circulation


Vermont Street

San Bruno Avenue

Auto for public

Utah Street

Service

Potrero Avenue

Ambulance

Pedestrians
Bus stop

SFGHMC | Space Program May 2007

2-8

Section 2 Site Review

ZONING CONSIDERATION
The SFGHMC campus is zoned as 105 E, this zoning
designation reveals building height and bulk limits. The
height limit for the new acute care hospital is 105 feet
with the following exemptions:

Mechanical equipment and appurtenances necessary


to the operation of the building itself, together with
visual screening, limited to the top 16 feet of any such
features.

Elevator, stair, and mechanical penthouses, fire


towers, and skylights, limited to the top 16 feet of
such features. Further exemptions for elevator
penthouses may be granted if necessary to meet
state or federal laws or regulation.

Unroofed recreation
including tennis and
swimming pools with
and play equipment
feet.

Property line
Grade line
Building height limit
Elevator/mechanical
penthouse height limit
Helipad
New hospital massing
Existing hospital building
Mechanical penthouse

Fig. 2-12

Section showing height of new acute care


hospital massing and existing hospital
building

facilities with open fencing,


basketball courts at roof level,
a maximum height of four feet
with a maximum height of 10

The suggested new acute care hospital massing is within


the prescribed height limit.
NEW HOSPITAL

103'

105'

16'

159'

PLANT SERVICES

PLANT SERVICES

12,000
BGSF

BGSF

CLINIC/PSYCH/SNF

73,272

CLINIC

79,362

CLINIC

78,070

CLINIC

77,597

MED/SURG

43,428

MED/SURG

43,428

ICU/STEP-DOWN

45,588

STEP-DOWN/ MED/SURG FORENSIC UNIT/PHARMACY

45,588

CLINIC

84,432

OBSTETRICS/PEDIATRICS/NICU

47,096

CLINIC LAB/CAFETERIA/SUPPORT

87,804

RADIOLOGY

91,934

NUCLEAR MED/MAT'L MGMT/SUPPORT

82,407

ADMITTING/EMERGENCY

51'

EXISTING HOSPITAL (Building 5)

56' PERIOPERATIVE/CLINICAL LABORATORY


CARDIOLOGY/RADIOLOGY/AUXILIARY SUPPORT/PLANT SERVICES

SFGHMC | Space Program May 2007

69'

53,092
59,547

69'

84'

69,303

2-8

Section 2 Site Review

The E Bulk district designation limits the bulk of the new


acute care hospital above 65 feet in elevation to a
maximum plan dimension of 110 feet in length and a
maximum diagonal dimension of 140 feet in length.

Achievement of a distinctly better design, in both a


public and a private sense, than would be possible
with strict adherence to the bulk limits, avoiding an
unnecessary prescription of building form while
carrying out the intent of the bulk limits and the
principles and policies of the Master Plan.

Development of a building or structure with


widespread public service benefits and significance to
the community at large, where compelling functional
requirements of the specific building or structure
make necessary such a deviation.

Property line
Grade line
Helipad
Building massing above 65
Building massing below 65
Existing hospital building
Mechanical penthouse
Fig. 2-13

Section showing bulk of new acute care


hospital massing and existing hospital
building

PLANT SERVICES

65'

Floor plate above 65

The suggested new acute care hospital massing exceeds


the prescribed bulk limit, however a variance could be
granted based on the exemptions listed above.

NEW HOSPITAL

7 15'-0"
6 15'-0"
5 15'-0"
4 15'-0"
3 15'-0"
2 15'-0"
1 15'-0"
B116'-0"
B216'-0"

Buildable area within bulk limit

Fig. 2-14

Floor plan showing E district bulk limits

EXISTING HOSPITAL (Building 5)

PLANT SERVICES

12,000
BGSF

BGSF

CLINIC/PSYCH/SNF

73,272

CLINIC

79,362

CLINIC

78,070

CLINIC

77,597

MED/SURG

43,428

MED/SURG

43,428

ICU/STEP-DOWN

45,588

STEP-DOWN/ MED/SURG FORENSIC UNIT/PHARMACY

45,588

CLINIC

84,432

OBSTETRICS/PEDIATRICS/NICU

47,096

CLINIC LAB/CAFETERIA/SUPPORT

87,804

ADMITTING/EMERGENCY

53,092

RADIOLOGY

91,934

PERIOPERATIVE/CLINICAL LABORATORY

59,547

NUCLEAR MED/MAT'L MGMT/SUPPORT

82,407

CARDIOLOGY/RADIOLOGY/AUXILIARY SUPPORT/PLANT SERVICES

69,303

SFGHMC | Space Program May 2007

Max 110'

Ma
x1
40
'

Exemptions from the prescribed bulk requirements may be


granted via a variance application under the following
conditions:

8
13'-0" 7
13'-0" 6
13'-0" 5
13'-0" 4
13'-0" 3
15'-0" 2
15'-0" 1
16'-0" B1
13'-0"

2-9

Section 2 Site Review

MEDICAL HELIPAD
SFGHMC is proposing to construct and operate a medical
helipad on the roof of the existing hospital building in
order to provide timely access to and from their Trauma
Center.

500'

500'

250'

Because the helipad's proximity to trauma is critical, the


City will be studying, as part of the SFGHMC Environmental
Impact Report (EIR) effort, whether or not the helipad
should be relocated to the new acute care hospital or
whether it's adequate to just link the two buildings. If a
decision is made to move the helipad to the new acute
care hospital, the original helipad location would be
decommissioned. There will only be one operational
helipad at the SFGHMC Potrero Campus.

Helipad transitional
surfaces
Helipad
New hospital massing
Existing hospital building
Mechanical penthouse
Fig. 2-15

Section showing suggested helipad location

If the helipad is to be relocated to the roof the new acute


care hospital this report suggests locating it along the east
side of the building closer to the center of the campus.
Assuming a north-south approach/departure path it
appears that neither the transitional surface nor the
approach/departure surface will be punctured by nearby
structures.

NEW HOSPITAL

PLANT SERVICES

'
00
40

2:1 transitional surface


8:1 approach/departure surface
Helipad
Fig. 2-16

Illustration showing approach/departure surfaces


and transitional surfaces

250'
500'

EXISTING HOSPITAL (Building 5)

PLANT SERVICES

12,000
BGSF

BGSF

CLINIC/PSYCH/SNF

73,272

CLINIC

79,362

CLINIC

78,070

CLINIC

77,597

MED/SURG

43,428

MED/SURG

43,428

ICU/STEP-DOWN

45,588

STEP-DOWN/ MED/SURG FORENSIC UNIT/PHARMACY

45,588

CLINIC

84,432

OBSTETRICS/PEDIATRICS/NICU

47,096

CLINIC LAB/CAFETERIA/SUPPORT

87,804

ADMITTING/EMERGENCY

53,092

RADIOLOGY

91,934

PERIOPERATIVE/CLINICAL LABORATORY

59,547

NUCLEAR MED/MAT'L MGMT/SUPPORT

82,407

CARDIOLOGY/RADIOLOGY/AUXILIARY SUPPORT/PLANT SERVICES

69,303

SFGHMC | Space Program May 2007

2-10

Section 2 Site Review

Stacking

Fig. 2-17

Stacking diagram

SFGHMC | Space Program May 2007

2-12

Section 2 Site Review

Basement 2 Floor Plan


Basement 2 is located one story below grade along Potrero
Avenue and has a footprint of approximately 69,300 square
feet. This floor does not have direct access to grade. The floor
plan below suggests one possible arrangement of the spaces
programmed on basement 2:

Radiology (8 Imaging Rooms Total)


Cardiology
Environmental Services
Material Management
Morgue and Autopsy
Messenger/Mailroom
Plant Services
Sterile Processing
Dietary
Pulmonary Function Lab

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-13

Section 2 Site Review

Basement 1 Floor Plan


Basement 1 is located one story below grade along West Drive
and has a footprint of approximately 59,500 square feet. This
floor has a Potrero Avenue grade level entrance, a tunnel
connection to existing hospital and a small loading dock. The
floor plan below suggests one possible arrangement of the
spaces programmed on basement 1:

Surgery (14 OR Total)


PACU (35 Beds Total)
Gastroenterology Unit (5 Rooms Total)
Pre-OP Unit (22 Beds Total)
Administrative/Staff Areas
Entry Area
Bronchoscopy
Clinical Laboratory
Loading Dock

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-14

Section 2 Site Review

First Floor Plan


First floor is located one story above grade along Potrero Avenue
and has a footprint of approximately 53,100 square feet. This
floor has separate entrances for public, ambulance and loading
to the grade. The floor plan below suggests one possible
arrangement of the spaces programmed on the first floor:

ER - Shared Support Areas


ER - Exam Unit (54 Rooms Total)
ER - Trauma Unit (6 Rooms Total)
Entry Area
Admitting

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-15

Section 2 Site Review

Second Floor Plan


Second floor has a footprint of approximately 47,100 square
feet. This floor has a bridge connection to existing hospital
building 5. The floor plan below suggests one possible
arrangement of the spaces programmed on the second floor:

Obstetrics Unit (22 Beds Total)


Pediatrics Unit (12 Beds Total)
Administrative/Staff Areas
Administration
Public Areas
NICU Unit (12 Bassinets Total)

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-16

Section 2 Site Review

Third Floor Plan


Third floor has a footprint of approximately 45,600 square feet.
The floor plan below suggests one possible arrangement of the
spaces programmed on the third floor:

ICU Step-Down (26 Beds Total)


ICU Step-Down (10 Beds Total)
Information Technology
Inpatient Pharmacy
Med/Surg - Forensic Unit (8 Beds)

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-17

Section 2 Site Review

Fourth Floor Plan


Fourth floor has a footprint of approximately 45,600 square
feet. The floor plan below suggests one possible arrangement of
the spaces programmed on the fourth floor:

ICU/CCU Unit ( 30 Beds Total)


Trauma ICU Unit (10 Beds Total)
Biomed
Public Areas
Administrative/Staff Areas
Step-Down Unit (10 Beds Total)
PBX

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-18

Section 2 Site Review

Fifth and Sixth Floor Plans


Fifth and sixth floors each have a footprint of approximately
43,500 square feet. The floor plan below suggests one possible
arrangement of the spaces programmed on the fifth and sixth
floor:

Med/Surg Unit (36 Beds Total)


Med/Surg Unit (36 Beds Total)
Courtyard
Public Areas

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-19

Section 2 Site Review

Penthouse Floor Plan


Excluding the Helipad the Penthouse floor has a footprint of
approximately 12,000 square feet. The floor plan below
suggests one possible arrangement of the spaces programmed
on the penthouse floor:

Helipad
Plant Services
Elevator Hoistway
Sixth Floor Roof
Courtyard

20'
10'

40'
30'

SFGHMC | Space Program May 2007

2-20

Section 3

Space Program Tables


Introduction
The following space program tables detail the program
requirements for a new acute care hospital at SFGHMC. Each
program space is listed in the table along with the type and
number of rooms and the assignable square footage (ASF)
required. The following definitions are used in these program
tables:
ASF represents the net assignable area measured from inside
of walls and partitions.
Department gross square footage (DGSF) is the sum of the
total department ASF plus the estimated area for
departmental infrastructure, such as interior partitions and
intra-department circulation which are estimated based on a
percentage of the total ASF.
Building gross square footage (BGSF) is the sum of the total
DGSF and estimated building services and building
infrastructure, such as exterior walls and inter-department
circulation which are estimated based on percentages of the
total DGSF

SFGHMC | Space Program May 2007

3-1

Section 3 Space Program

PROGRAM SUMMARY

Beds/Rm

DGSF

Remarks

Inpatient
Acute Medical
Medical/Surgical
Medical/Surgical - Forensic Unit
ICU/CCU
Step-Down
Obstetrics
Pediatrics
NICU
Subtotal

144
8
40
46
22
12
12
284

72,466
6,744
31,086
27,287
21,427
9,194
7,830
176,032

Perioperative
Surgery
Gastroenterology
Patient Intake and Recovery

15
5
57

23,369
4,158
17,914

Diagnostic Imaging
Cardiology
Radiology

6
8

4,606
15,425

Ancillary Services
Sterile Processing
Pharmacy
Clinical Laboratory
Pulmonary Function
Biomed
Morgue and Autopsy
Subtotal

91

6,774
6,139
2,344
2,071
1,019
1,920
85,738

60

36,668

4 units - each 36 beds


4 units - each 10 beds
20 beds flex up & 26 beds flex down
13 postpartum + 9 LDRP beds

Diagnostic & Treatment


14 OR & 2 IR

Inpatient only
Blood bank + Urinalysis

Emergency
Emergency
Clinical Care

54 exam + 6 trauma rooms

3-2

Section 3 Space Program

PROGRAM SUMMARY

Beds/Rm

DGSF

Administration and Public


Entry Area
Admitting
Administration

5,755
2,801
621

Auxiliary Support
Material Management
Messenger/Mailroom
Environmental Services
Information Technology
PBX
Dietary
Subtotal

8,250
2,544
1,294
2,731
719
828
25,544

18%
9%

323,982
58,317
34,407
416,706

Remarks

Support

DGSF Total
Circulation/ Exterior Wall
Plant Services
BGSF Total

Most Dietary Services to remain in Bldg. 5

3-3

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Inpatient - Summary
Acute Medical
Medical/Surgical
Medical/Surgical Unit
Support Areas
Administrative/Staff Areas
Public Areas

144
144

42,280
500
2,080
1,880
46,740
72,466

8
8

3,000
1,350
4,350
6,744

ICU/CCU
ICU/CCU Unit
ICU/CCU Unit
ICU/CCU Unit
Trauma ICU Unit
Shared Support Areas
Administrative/ Staff Area
Public Areas
ASF Total
DGSF

10
10
10
10
40

3,290
3,290
3,290
3,990
2,480
2,510
1,200
20,050
31,086

Step-Down
Step-Down Unit - Flex Up
Step-Down Unit - Flex Up
Step-Down Unit - Flex Down
Support Areas
Administrative/ Staff Areas
Public Areas
ASF Total
DGSF

20
10
26
46

6,760
3,370
6,540
2,000
1,300
1,000
17,600
27,287

ASF Total
DGSF
Medical/Surgical - Forensic Unit
Medical/Surgical - Forensic Unit
Administrative/Staff Areas
ASF Total
DGSF

3-4

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Inpatient - Summary
Acute Medical
Obstetrics
Triage
Post-Partum
LDRP
C-Section
Support Areas
Administrative/Staff Area
Public Areas
ASF Total
DGSF

3
13
9
2
22

650
3,150
3,270
1,420
2,240
2,210
880
13,820
21,427

Pediatrics
Pediatrics Unit
Administrative/Staff Area
Public Areas
ASF Total
DGSF

12
12

4,440
1,030
460
5,930
9,194

NICU
NICU unit
Administrative/Staff Area
Public Areas
ASF Total
DGSF

12
12

3,670
1,260
120
5,050
7,830

DGSF Total

176,032

3-5

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Medical/Surgical
Medical/Surgical Unit
19

180

3,420

Toilet

17

30

510

Toilet - ADA

50

100

280

1,120

Toilet

30

60

Toilet - ADA

50

100

180

1,620

Toilet

50

350

w/ shower

Toilet - ADA

70

140

w/ shower

Anteroom

100

500

Nursing Station

300

300

Auxiliary Nursing Station

150

300

Physician Workroom/Charting

200

200

Medication

120

240

Clean Supply

100

100

Clean Utility

100

100

Nourishment

100

100

Linen

30

60

Equipment/Storage

200

400

Soiled Utility

100

100

Soiled Linen

60

60

Patient Shower - ADA

50

100

Custodian Closet

40

40

Office - Unit Manager

100

100

Office - Head Nurse

100

100

Office - Clinical Nurse Specialist

100

100

Toilet - ADA

50

50

Conference Room

200

200

10,570

250

Patient Room

Patient Room - Double Occupancy

Patient Room - Isolation

3 negative pressure rooms

Wall between two rooms to have an


opening to allow for multiple patient
observation

Support

Automated dispensing units

Administrative/Staff Areas

10,570

Medical/Surgical Unit ASF


Medical/Surgical Unit Total ASF

Exterior window if possible

42,280

Support Areas
Procedure Room
Support Areas ASF

500

1 per Floor

500

3-6

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Medical/Surgical
Administrative/Staff Areas
Office - Social Worker

200

400

Office - Chief Medical Resident

100

100

Medicine Resident Room

250

250

Dayroom

250

250

Staff Lounge

200

400

1 per floor

Women's Locker

120

240

40 Lockers (full height)

Toilet - ADA

50

100

120

240

50

100

Men's Locker
Toilet - ADA

Team based
Common room

40 Lockers (full height)

2,080

Administrative/Staff Areas ASF

Public Areas
Waiting

200

400

1 per floor

Multipurpose Room

200

400

Consultation

120

360

w/ divider-can serve as waiting room/rounds


and as Emergency Response Center

Women's Toilet

180

360

Multi accommodation - 3 fixtures

Men's Toilet

180

360

Multi accommodation - 3 fixtures

1,880

Public Areas ASF

46,740

Total Department ASF


Intra-Department Circulation

36%

16,826

Partition & Structures

14%

8,899

Medical/Surgical DGSF

72,466

3-7

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Medical/Surgical - Forensic (Jail)
Medical/Surgical - Forensic Unit
Patient Room
Toilet
Patient Room
Toilet - ADA
Patient Room - Isolation

180

900

30

150

180

180

50

50

180

360

Toilet - ADA

70

140

Anteroom

100

100

Nursing Station

200

200

Medication

120

120

Physician Workroom/Charting

150

150

Consultation

120

120

Equipment/ Storage

120

120

Linen

30

30

Clean Utility/Supply

120

120

Nourishment

50

50

Soiled Utility

80

80

Soiled Linen

40

40

Patient Shower - ADA

50

50

Custodian Closet

40

w/ shower

Support

Medical/Surgical - Forensic Unit ASF

40
3,000

3-8

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Medical/Surgical - Forensic (Jail)
Administrative/Staff Areas
Office - Head Nurse

100

100

Office - Social Worker

100

100

Office - Sheriff

100

100

Interview Room

80

160

Visiting

60

120

Command Center

150

150

Conference Room

150

150

Toilet - ADA

60

60

Staff Lounge

150

150

Women's Locker

80

80

Toilet - ADA

50

50

80

80

50

Men's Locker
Toilet - ADA

15 Lockers (full height)

50
1,350

Administrative/Staff Areas ASF

Total Department ASF

4,350

Intra-Department Circulation

36%

1,566

Partition & Structures

14%

828

Medical/Surgical - Forensic (Jail) DGSF

15 Lockers (full height)

6,744

3-9

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Step-Down
Step-Down Unit - Flex Up
8

210

1,680

Toilet

30

90

Toilet - ADA

50

50

210

420

Toilet - ADA

70

140

Anteroom

80

80

Patient Room

Patient Room - Isolation

w/ shower

Support
Nursing Station/Charting

300

300

Viewing Alcove

30

30

Medication

120

120

Clean Utility/Supply

120

120

Linen

30

30

Nourishment

50

50

Equipment/Storage

200

200

80

Soiled Utility
Step-Down Unit - Flex Up ASF

80
3,390

Step-Down Unit - Flex Down


Patient Room

12

180

2,160

12

30

360

280

1,120

Toilet

30

60

Toilet - ADA

50

100

180

1,080

Toilet

50

200

w/ shower

Toilet - ADA

70

140

w/ shower

Anteroom

80

240

Toilet
Patient Room - Double Occupancy

Patient Room - Isolation

Sliding glass doors between two


rooms for multiple patient observation

Support
Nursing Station/Charting

300

300

Auxiliary Nursing Station

150

150

Viewing Alcove

30

30

Medication

120

120

Clean Utility/Supply

120

120

Linen

30

30

Nourishment

50

50

Equipment/Storage

200

200

Soiled Utility
Step-Down Unit - Flex Down ASF

80

80
6,540

3-10

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Step-Down
Support Areas
Physician Workroom/Charting

150

300

Medical Equipment

200

200

Mobile Imaging

150

150

Biomed

150

150

Respiratory Therapy

150

300

Pharmacy

150

150

Physical Therapy

150

150

Storage

200

400

Soiled Linen

60

60

Patient Shower - ADA

50

100

Custodian Closet

40

40

w/ 2 PACS stations in each room

2,000

Support Areas ASF

Administrative/ Staff Areas


Office - Unit Manager

100

100

Office - Head Nurse

100

100

Office - Clinical Nurse Specialist

100

100

Office - Social Worker

150

150

Toilet - ADA

50

50

Conference Room

150

150

Staff Lounge

200

200

Locker

Team based
w/ 1 PACS station

250

250

Women's Toilet

70

70

w/ Shower

Men's Toilet

70

70

w/ Shower

Changing Room

30

60

50 Lockers (full height)

1,300

Administrative/ Staff Areas ASF

Public Areas
Waiting

200

400

Consultation

120

240

Women's Toilet

180

180

Multi accommodation - 3 fixtures

Men's Toilet

180

180

Multi accommodation - 3 fixtures

1,000

Public Areas ASF

14,230

Total Department ASF


Intra-Department Circulation

36%

5,123

Partition & Structures

14%

2,709

Step-Down DGSF

22,062
3-11

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
ICU/CCU/Step-Down
ICU/CCU Unit
9

210

1,890

30

150

210

210

Hopper Room

30

30

Anteroom

80

80

Nursing Station/Charting

300

300

Viewing Alcove

30

30

Medication

120

120

Clean Utility/Supply

120

120

Linen

30

30

Nourishment

50

50

Equipment/Storage

200

200

Soiled Utility

80

80

3,290

9,870

280

2,520

Patient Room
Hopper Room
Patient Room - Isolation

1 Negative Pressure Room

Support

3,290

ICU/CCU Unit ASF


ICU/CCU Unit Total ASF

Trauma ICU Unit


Patient Room

30

150

280

280

Hopper Room

30

30

Anteroom

80

80

Nursing Station/Charting

300

300

Viewing Alcove

30

30

Medication

120

120

Clean Utility/Supply

120

120

Linen

30

30

Nourishment

50

50

Equipment/Storage

200

200

Soiled Utility

80

80

Hopper Room
Patient Room - Isolation

1 Negative Pressure Room

Support

Trauma ICU ASF

3,990

3-12

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
ICU/CCU/Step-Down
Step-Down Unit - Flex Up
8

210

1,680

Toilet

30

90

Toilet - ADA

50

50

210

420

Toilet

50

50

w/ shower

Toilet - ADA

70

70

w/ shower

Anteroom

80

80

Nursing Station/Charting

300

300

Viewing Alcove

30

30

Medication

120

120

Clean Utility/Supply

120

120

Linen

30

30

Nourishment

50

50

Equipment/Storage

200

200

Soiled Utility

80

80

Patient Room

Patient Room - Isolation

Support

3,370

Step-Down Unit - Flex Up ASF

Shared Support Areas


Mobile Imaging

150

300

Biomed

150

150

Respiratory Therapy

150

300

Satellite Pharmacy

300

300

Medical Equipment

150

150

Provider Workroom/Charting

150

450

Quiet Room

80

160

Storage

200

400

Soiled Linen

60

120

Patient Shower - ADA

50

50

Custodian Closet

50

100

Shared Support Areas ASF

w/ 2 PACS stations in each room

One cart per ICU unit

2,480

3-13

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
ICU/CCU/Step-Down
Administrative/ Staff Area
Office - Director

100

100

Office - Head Nurse

100

300

Office - Clinical Nurse Specialist

150

150

Toilet - ADA

50

50

On-Call Sleep Room

80

640

Shared

Toilet - ADA

70

280

w/ shower

Conference Room

150

300

w/ 1 PACS station in each room

Staff Lounge

300

300

Locker

250

250

Women's Toilet

70

70

w/ Shower

Men's Toilet

70

70

w/ Shower

Changing Room

30

60

50 Lockers (full height)

2,510

Administrative/Staff Areas ASF

Public Areas
Waiting

200

600

Consultation

120

240

Women's Toilet

180

180

Multi accommodation - 3 fixtures

Men's Toilet

180

180

Multi accommodation - 3 fixtures

1,200

Public Areas ASF

23,420

Total Department ASF


Intra-Department Circulation

36%

8,431

Partition & Structures

14%

4,459

ICU/CCU/Step-Down DGSF

36,310

3-14

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Obstetrics
Triage
3

180

540

Toilet

30

60

Toilet - ADA

50

Patient Room

During high census use Postpartum


rooms

50
650

Triage ASF

Post-Partum
Patient Room
Toilet
Patient Room

180

1,620

50

450

180

360

70

140

180

360

Toilet - ADA

70

140

Anteroom

80

Toilet - ADA
Patient Room - Isolation

w/ shower
w/ shower
w/ shower

80
3,150

Post-Partum ASF

LDRP
Patient Room
Toilet
Patient Room

290

2,030

60

420

290

290

80

80

290

290

Toilet - ADA

80

80

Anteroom

80

80

Toilet - ADA
Patient Room - Isolation

w/ tub
w/ tub
w/ tub

3,270

LDRP ASF

C-Section
Operating Room

400

800

Resuscitation Room

200

200

Sterile Supply

100

100

Clean Supply/Utility

120

120

Sub-Sterile

120

120

Soiled Utility

80

80

C-Section ASF

Included in NICU

1,420

3-15

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Obstetrics
Support Areas
Nursing Station

300

300

Well Baby

400

400

Medication

120

120

Provider Workroom/Charting

200

200

Anesthesia/Respiratory

120

120

Equipment/ Storage

300

600

Linen

30

60

Clean Supply/Utility

120

120

Soiled Utility

80

80

Soiled Linen

90

90

Pantry

100

100

Custodian Closet

50

50

Five bassinets (80 SF per bassinet)

2,240

Support Areas ASF

Administrative/Staff Area
4

80

320

Toilet

40

40

Toilet - ADA

70

70

Office - Clinical Nurse Specialist

100

100

Office - Lactation Specialist

100

100

Office - Nurse Manager

100

100

Conference Room

300

300

Toilet - ADA

50

50

Staff Lounge

400

400

Shared w/ Pediatrics and NICU

Locker

250

250

250 total staff

Women's Toilet

180

180

Multi accommodation - 3 fixtures

Men's Toilet

180

180

Multi accommodation - 3 fixtures

Changing Room

30

120

On-Call Sleep Room

Administrative/Staff Areas ASF

w/ shower

w/ divider

2,210

3-16

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Obstetrics
Public Areas
Waiting

400

400

Consultation

120

120

Women's Toilet

180

180

Multi accommodation - 3 fixtures

Men's Toilet

180

180

Multi accommodation - 3 fixtures

880

Public Areas ASF

13,820

Total Department ASF


Intra-Department Circulation

36%

4,975

Partition & Structures

14%

2,631

Obstetrics DGSF

21,427

3-17

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Pediatrics
Pediatrics Unit
8

180

1,440

Toilet

30

180

Toilet - ADA

50

100

180

360

30

60

Patient Room

Patient Room
Toilet

180

360

Toilet - ADA

70

140

Anteroom

100

100

Nursing Station

300

300

Medication

120

120

Pantry

80

80

Provider Workroom/Charting

200

200

Treatment Room

120

120

Play Room

150

150

Equipment/Storage

300

300

Clean Supply/Utility

100

100

Soiled Utility

80

80

Linen

30

30

Soiled Linen

60

60

Patient Tub/Shower - ADA

60

120

40

Patient Room - Isolation

Sliding glass doors between two


rooms for multiple patient observation
w/ shower

Support

Custodian Closet
Pediatrics Unit ASF

40
4,440

Administrative/Staff Area
On-Call Sleep Room

80

160

70

70

Office - Nurse Manager

100

100

Office - Clinical Nurse Specialist

100

100

Office - Social Worker

150

150

Team based

Conference Room

400

400

w/ divider

Toilet - ADA

50

50

Staff Lounge

Toilet - ADA

Locker w/ Toilets
Administrative/Staff Area ASF

w/ shower

Shared w/ Obstetrics and NICU

Shared w/ Obstetrics and NICU

1,030

3-18

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
Pediatrics
Public Areas
Waiting

Consultation

120

120

Parent Lounge

200

200

70

140

Toilet - ADA
Public Areas ASF

w/ shower

460

Total Department ASF

5,930

Intra-Department Circulation

36%

2,135

Partition & Structures

14%

1,129

Pediatrics DGSF

Shared w/ Obstetrics and NICU

9,194

3-19

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
NICU
NICU unit
Patient Room - Level II

150

1,050

Patient Room - Level III

170

680

Patient Room - Level III Isolation

190

190

100

100

Anteroom

w/ bathing sink and counter

Support
Nursing Station

200

200

Provider Workroom/Charting

200

200

Respiratory Therapy

100

100

Treatment Room

100

100

Medication

120

120

Scrub

60

60

Linen

30

30

Soiled Linen

60

60

Breast Feeding

100

100

Equipment/Storage

400

400

Clean Supply/Utility

120

120

Soiled Utility

120

120

40

40

Custodian Closet
NICU Unit ASF

w/ sink

3,670

Administrative/Staff Area
On-Call Sleep Room

100

200

70

70

Family Sleep Room

100

100

Toilet - ADA

70

70

400

400

Toilet - ADA

Mother Boarding Room

70

70

Office - Nurse Manager

Toilet - ADA

100

100

Office - Clinical Nurse Specialist

100

100

Office - Neonatologist

100

100

Conference Room

Toilet - ADA

50

Staff Lounge

Locker w/ Toilets

Administrative/Staff Area ASF

w/ shower
w/ shower
4 beds with visual separation & sink
w/ shower

Shared w/ Pediatrics

50
-

Shared w/ Obstetrics and Pediatrics

Shared w/ Obstetrics and Pediatrics

1,260

3-20

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Inpatient
Acute Medical
NICU
Public Areas
Waiting

Consultation

120

Toilet

Public Areas ASF

Shared w/ Obstetrics and Pediatrics

120

Total Department ASF

5,050

Intra-Department Circulation

36%

1,818

Partition & Structures

14%

962

NICU DGSF

Shared w/ Obstetrics and Pediatrics

120

7,830

3-21

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Diagnostic and Treatment - Summary


Perioperative
Surgery
Surgery Unit
Interventional Radiology Unit
Shared Support Areas
Administrative/Staff Areas
ASF Total
DGSF

14
1
15

9,130
2,670
3,000
320
15,120
23,369

Gastroenterology
Gastroenterology Unit
Administrative/Staff Areas
ASF Total
DGSF

5
5

2,440
250
2,690
4,158

Patient Intake and Recovery


Pre-OP Unit
PACU
Shared Support Areas
Administrative/Staff Areas
Public Areas
ASF Total
DGSF

22
35
57

2,820
4,220
200
3,230
1,120
11,590
17,914

Cardiology
Cath/EP Lab Unit
Echo Lab Unit
Support Areas
Administrative/Staff Areas
ASF Total
DGSF

1
5
6

730
930
970
350
2,980
4,606

Radiology
X-ray Unit
CT Scan Unit
MRI Unit
Angiography Unit
Ultrasound Unit
Support Areas
Administrative/Staff Areas
ASF Total
DGSF

3
2
1
2
1
9

900
1,180
850
1,310
400
3,680
1,660
9,980
15,425

Diagnostic Imaging

Can accommodate 3 cubicles

3-22

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Diagnostic and Treatment - Summary


Ancillary Services
Sterile Processing
Decontamination Area
Assembly/Sterilization
Administrative/Staff Areas
ASF Total
DGSF

1,270
2,360
850
4,480
6,774

Pharmacy
Storage Areas
Manufacturing Areas
Dispensary
Administrative/Staff Areas
ASF Total
DGSF

640
1,230
970
1,220
4,060
6,139

Clinical Laboratory
DGSF

1,550
2,344

Pulmonary Function Lab


DGSF

4
4

1,340
2,071

Biomed
DGSF

700
1,019

Morgue and Autopsy


Morgue
Autopsy
Administrative/Staff Areas
ASF Total
DGSF

600
400
270
1,270
1,920

DGSF Total

85,738

3-23

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Perioperative
Surgery
Surgery Unit
Operating Room - Large

540

2,160

Operating Room - Medium

500

3,000

Operating Room - Small

420

1,680

Clean Core

1,000

2,000

Scrub

30

40

One OR to be fluro capable

Support

Custodian Closet
Surgery Unit ASF

210
80
9,130

Interventional Radiology Unit


1

550

550

60

60

700

700

60

60

Control

200

400

PACS Viewing

200

200

Workroom

200

200

100

100

IR Operating Room
Computer Storage
IR Operating Room
Computer Storage

w/ CT scan capability

Support

Sterile Supply
Scrub

30

30

Equipment/Tube Storage

250

250

Electrical Room

120

120
2,670

Interventional Radiology Unit ASF

Shared Support Areas


1

350

350

150

150

Anesthesia Induction

220

220

Surgery Control Station

150

150

Satellite Pharmacy

300

300

Graft Freezer

60

60

Frozen Section Lab

100

100

Control/Video Equipment

100

100

Biomed

200

200

Equipment/Storage

250

1,000

Housekeeping Supplies

80

80

Decontamination

200

200

90

90

Anesthesia Workroom
Storage

Soiled Linen
Shared Support Areas ASF

Scheduling

w/ tray-veyor

3,000

3-24

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Perioperative
Surgery
Administrative/Staff Areas
Office - Surgery Manager

100

100

Office - Anesthesia

100

100

60

Toilet - ADA
Administrative/Staff Areas ASF

120
320

Total Department ASF

15,120

Intra-Department Circulation

38%

5,746

Partition & Structures

12%

2,504

Surgery DGSF

23,369

3-25

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Perioperative
Gastroenterology
Gastroenterology Unit
1

350

350

Control Room

80

80

Toilet - ADA

50

50

Endoscopy Room

250

1,000

ERCP Room

Support
pH Monitoring Room

150

150

Linen

30

30

Clean Utility/Supply

120

120

Scope Closet

30

120

Scope Clean Room

80

80

Equipment/ Storage

200

200

Computer Room

80

80

Soiled Utility

80

80

Soiled Linen

60

60

40

Custodian Closet
Gastroenterology Unit ASF

40
2,440

Administrative/Staff Areas
Conference Room
Toilet - ADA
Administrative/Staff Areas ASF

200

50

200
50
250

Total Department ASF

2,690

Intra-Department Circulation

38%

1,022

Partition & Structures

12%

445

Gastroenterology DGSF

4,158

3-26

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Perioperative
Patient Intake and Recovery
Pre-OP Unit
22

80

1,760

Nursing Station

120

240

Provider Workroom/Charting

100

100

Equipment/Storage

200

200

Linen

30

60

Clean Utility/Supply

120

120

Soiled Utility

80

80

Soiled Linen

60

60

Patient Toilet - ADA

50

100

Patient Toilet

30

60

40

40

Holding Cubicle
Support

Custodian Closet
Pre-OP Unit ASF

2,820

PACU
Recovery Cubicle

34

80

2,720

Recovery Patient Room - Isolation

140

140

70

70

Nursing Station

120

240

Provider Workroom/Charting

120

120

Equipment/Storage

200

200

Nourishment

80

80

Medication

120

120

Linen

30

60

Clean Utility/Supply

120

120

Soiled Utility

80

80

Soiled Linen

60

60

Patient Toilet - ADA

50

100

Patient Toilet - ADA

70

70

40

40

Toilet - Accessible

w/ shower

Support

Custodian Closet
PACU ASF

w/ shower

4,220

Shared Support Areas


Stretcher/Wheelchair
Shared Support Areas ASF

100

200
200

3-27

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Perioperative
Patient Intake and Recovery
Administrative/Staff Areas
Office - PACU Manager

100

100

Office - Medical Director

100

100

Office - Nursing Director

100

100

Office - IS Clinical Staff

100

100

Office - CNS/Educator

140

140

Toilet - ADA

50

100

On-Call Sleep Room

80

320

Toilet

30

30

Shared

Toilet - ADA

50

50

Shared

80

80

Surgery

Toilet - ADA

50

50

Conference Room

200

400

Staff Lounge - Anesthesia

300

300

Staff Lounge

300

300

Women's Locker

On-Call Sleep Room

Shared
Anesthesia (3 residents, 1 faculty)

300

300

75 Lockers (full height/purse)

Toilet

210

210

Multi accommodation - 3 fixtures w/ shower

Men's Locker

300

300

75 Lockers (full height/purse)

Toilet

210

210

Multi accommodation - 3 fixtures w/ shower

40

40

Custodian Closet
Administrative/Staff Areas ASF

3,230

Public Areas
Reception

120

120

Waiting

200

400

Consultation

120

240

Women's Toilet

180

180

Multi accommodation - 3 fixtures

180

180

Multi accommodation - 3 fixtures

Men's Toilet
Public Areas ASF

1,120

Total Department ASF

11,590

Intra-Department Circulation

38%

4,404

Partition & Structures

12%

1,919

Patient Intake and Recovery DGSF

17,914

3-28

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Diagnostic Imaging
Cardiology
Cath/EP Lab Unit
Cath/EP Lab Room

500

500

Includes POCT

Control Room

150

150

w/ PACS station

80

80

Equipment
Cath/EP Lab Unit ASF

730

Echo Lab Unit


Echo Bays

150

600

Stress Echo Room

250

250

80

Equipment
Cath Lab Unit ASF

w/ treadmill and crash cart

80
930

Support Areas
Imaging Reading/Workroom

300

300

Equipment/Computer Storage

200

200

Stat Lab

100

100

Clean Supply/Utility

100

100

Linen

30

90

Soiled

80

80

Soiled Linen

60

60

Contrast Media Storage

40

40

PACS Workroom
Support Areas ASF

Shared w/ Radiology

970

Administrative/Staff Areas
Office - Cardiology Manager

100

100

Office - Chief Sonographer

100

100

Office - Tech

100

100

Toilet - ADA

50

50

Conference Room

Locker
Administrative/Staff Areas ASF

Shared w/ Radiology

Shared w/ Radiology

350

Total Department ASF

2,980

Intra-Department Circulation

38%

1,132

Partition & Structures

12%

493

Cardiology DGSF

4,606

3-29

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Diagnostic Imaging
Radiology
X-ray Unit
X-ray Room
Control Room
Fluoroscopy Room
Control Room
Toilet
X-ray Unit ASF

250

500

50

50

250

250

50

50

50

50

ADA accessible

900

CT Scan Unit
CT Scan Room

450

450

CT/Angio Scan Room

550

550

180

180

Control Room
CT Scan Unit ASF

1,180

MRI Unit
MRI Room
Control Room
Equipment
MRI Unit ASF

520

520

180

180

150

150
850

Angiography Unit
Angiography Room

500

1,000

Control Room

150

150

80

Equipment
Angiography Unit ASF

160
1,310

Ultrasound Unit
Ultrasound Room
Toilet - ADA
Ultrasound Unit ASF

350

50

350

Three cubicles

50
400

3-30

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Diagnostic Imaging
Radiology
Support Areas
Reading Room

150

Holding/Recovery

1,360

150

Reception

60

60

Waiting

150

150

Changing

40

80

Workroom

500

500

Imaging Control Station

150

150

PACS Workroom

300

300

Linen

30

90

Clean Supply/Utility

100

100

Soiled

80

80

Soiled Linen

60

60

Equipment/Computer Storage

400

400

Contrast Media Storage

60

60

Patient toilet

50

100

Custodian Closet
Support Areas ASF

40

40

1,360

17 Gurneys

Scheduling

ADA accessible

3,680

Administrative/Staff Areas
Office - Imaging Director
Office - Radiology Manager

1
1

100
100

100
100

Office - Tech

100

200

Conference Room

350

350

Toilet - ADA

50

50

Staff Lounge

200

200

Women's Locker

150

150

50 day use Lockers (full height)

Toilet

180

180

Multi accommodation - 3 fixtures

Men's Locker

150

150

50 day use Lockers (full height)

180

180

Multi accommodation - 3 fixtures

Toilet
Administrative/Staff Areas ASF

1,660

Total Department ASF

9,980

Intra-Department Circulation

38%

3,792

Partition & Structures

12%

1,653

Radiology DGSF

w/ divider

15,425

3-31

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Sterile Processing
Decontamination Area
Workroom

800

800

200

200

Cart Wash

120

120

Toilet - ADA

70

70

Supply Closet

50

50

30

30

Soiled Cart Staging area

Custodian Closet
Decontamination Area ASF

w/ shower

1,270

Assembly/Sterilization
Pass Through Sterilizers

150

150

Sterile Supply

400

400

Terminal Sterilizer

180

180

Sterile Storage/Cart Assembly

800

800

Cart Storage

200

200

Wrap and Pack Area

600

600

Custodian Closet

30

30
2,360

Assembly/Sterilization ASF

Administrative/Staff Areas
Office - Manager

100

100

Office - Supervisor

100

100

Conference Room

150

150

Staff Lounge

200

200

Women's Locker

100

100

Toilet - ADA

50

50

100

100

50

50

Men's Locker
Toilet - ADA

20 Lockers (full height)


20 Lockers (full height)

850

Administrative/Staff Areas ASF

Total Department ASF

4,480

Intra-Department Circulation

35%

1,568

Partition & Structures

12%

726

Sterile Processing DGSF

Back to back w/ Staff Lounge

6,774

3-32

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Pharmacy
Storage Areas
Active Storage

400

400

Refrigerated Storage

30

90

Narcotics Vault

150

150
640

Storage Areas ASF

Manufacturing Areas
Bulk Compounding

400

400

2 auto compounders

I.V. Prep Room (Chemo)

300

300

Positive air pressure

Anteroom/Storage

300

300

Walk-in Refrigerator

80

80

Packaging and Labeling

150

150
1,230

Manufacturing Areas ASF

Dispensary
Pick-Up

120

120

Discharge

150

150

Compounding

300

300

Reviewing and Recording

320

320

Cart Staging

80

80

8 Workstations

970

Dispensary ASF

Administrative/Staff Areas
Office - Director

100

100

Office

100

100

Open Office

320

320

Conference Room

200

200

Staff Lounge

200

200

Women's Locker

100

100

Toilet - ADA

50

50

100

100

50

Men's Locker
Toilet - ADA

20 Lockers (full height)


20 Lockers (full height)

50
1,220

Administrative/Staff Areas ASF

Total Department ASF

4,060

Intra-Department Circulation

35%

1,421

Partition & Structures

12%

658

Pharmacy DGSF

4 Workstations

6,139

3-33

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Clinical Laboratory
Clinical Laboratory
Blood Bank

1,200

1,200

Urinalysis Lab

150

150

Office - Senior Supervisor

100

100

Office - Supervisor

100

100
1,550

Clinical Laboratory ASF

Total Department ASF

Code min. 180 SF

1,550

Intra-Department Circulation

35%

543

Partition & Structures

12%

251

Clinical Laboratory DGSF

6" Pneumatic Tube

2,344

3-34

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Pulmonary Function
Pulmonary Function Lab
Procedure Room

Equipment

80

80

200

200

80

Special Procedure Room


Equipment

200

600

80
960

Pulmonary Function Lab ASF

Bronchoscopy
Procedure Room

250

250

Equipment

80

80

Toilet - ADA

50

50

Negative pressure

380

Bronchoscopy ASF

Shared Support Areas


Clean Supply/Utility

Shared w/ Cardiology & GI

Linen

Shared w/ Cardiology & GI

Soiled

Shared w/ Cardiology & GI

Soiled Linen

Shared w/ Cardiology & GI

Support Areas ASF

Administrative/Staff Areas
Toilet

Shared w/ Cardiology & GI

Conference Room

Shared w/ Cardiology & GI

Locker

Shared w/ Cardiology & GI

Administrative/Staff Areas ASF

Total Department ASF

1,340

Intra-Department Circulation

38%

509

Partition & Structures

12%

222

Pulmonary Function DGSF

2,071

3-35

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Biomed
Biomed
Workshop

400

400

Storage

200

200

Office - Manager

100

100
700

Biomed ASF

Total Department ASF

700

Intra-Department Circulation

30%

210

Partition & Structures

12%

109

Biomed DGSF

1,019

3-36

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Diagnostic and Treatment


Ancillary Services
Morgue and Autopsy
Morgue
Viewing Room

200

200

Mortuary Refrigerator

400

400

200

Vestibule

16'x25' can accommodate 6 gurneys

200
600

Morgue ASF

Autopsy
Autopsy
Tissue Storage
Autopsy ASF

300

300

100

100
400

Administrative/Staff Areas
Office - Supervisor

100

100

Locker

80

80

Changing Room

40

40

Toilet - ADA

50

50
270

Administrative/Staff Areas ASF

Total Department ASF

1,270

Intra-Department Circulation

35%

445

Partition & Structures

12%

206

Morgue and Autopsy DGSF

10 Lockers (full height)

1,920

3-37

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Emergency - Summary
Emergency
Clinical Care
Exam Unit

54

10,780

Trauma Unit

3,510

Support Areas

4,305

Administrative/Staff Areas

2,780

Public Areas
ASF Total
DGSF

60

Exam rooms are equipped w/


additional med gas consoles and
are sized to accommodate two
gurneys to handle mass casualty
events

1,600
22,975
36,668

3-38

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Emergency
Emergency
Clinical Care
Exam Unit
Exam Room

46

140

6,440

Exam Room - Behavioral Health

140

560

w/ sound isolation control

Exam Room - RTC

180

180

Adjacent to consultation room

Toilet - ADA

70

70

140

420

Toilet

30

60

Toilet - ADA

50

50

Nursing Station

200

800

Provider Charting

150

600

Medication

120

480

Clean Utility/Supply/Equipment

170

680

Soiled Utility

80

320

Soiled Linen

60

120

Exam Room - Isolation

w/ shower

Support

10,780

Exam Unit ASF

Trauma Unit
6

350

2,100

120

360

Nursing Station

200

200

Provider Charting

250

250

Medication

120

120

Clean Utility/Supply/Equipment

200

200

Soiled Utility

80

80

Soiled Linen

60

60

Consultation/Quiet Room

100

100

40

40

Resuscitation Room
Equipment Storage

w/ X-ray capability

Support

Custodian Closet
Trauma Unit ASF

3,510

3-39

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Emergency
Emergency
Clinical Care
Support Areas
1

350

350

120

240

POCT

100

100

CT Scan Room

450

900

Control Room

150

150

Workroom

100

100

250

500

Control Room

100

100

Satellite Pharmacy

400

400

Equipment/Storage

300

600

Provider Workroom

200

200

Toilet - ADA

50

150

Toilet

35

175

Shower/Decontamination

260

260

40

40

40

Central Triage
Triage Room

X-ray Room

Storage
Custodian Closet

Including reception

ADA accessible w/ washer & dryer

40
4,305

Support Areas ASF

Administrative/Staff Areas
Office - Nursing Director

100

100

Office - Nurse Manager

100

200

Office - CNS

150

150

Shared

Office - Social Worker

150

150

Shared

Admitting/Registration

500

500

6 Workstations

Interview

80

80

Radio Room

80

80

Conference Room

200

400

Toilet - ADA

50

100

Staff Lounge

300

300

Women's Locker

w/ divider to accommodate 20 staff

150

150

50 Lockers (full height)

Toilet

210

210

Multi accommodation - 3 fixtures w/ shower

Men's Locker

150

150

50 Lockers (full height)

Toilet

210

210

Multi accommodation - 3 fixtures w/ shower

40

Custodian Closet
Administrative/ Staff Areas ASF

40
2,780

3-40

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Emergency
Emergency
Clinical Care
Public Areas
Waiting

400

800

Waiting - Pediatrics

200

200

Consultation/Quiet Room

120

240

Women's Toilet

180

180

Multi accommodation - 3 fixtures

180

180

Multi accommodation - 3 fixtures

Men's Toilet
Public Areas ASF

1,600

Total Department ASF

22,975

Intra-Department Circulation

40%

9,190

Partition & Structures

14%

4,503

Clinical Care DGSF

36,668

3-41

Section 3 Space Program

SERVICE

Beds/Rm

ASF

Remarks

Support Services - Summary


Administration and Public
Entry Area
Main Lobby
Lobby
ASF Total
DGSF

3,360
1,000
4,360
5,755

Admitting
DGSF

2,030
2,801

Administration
DGSF

450
621

Material Management
DGSF

6,250
8,250

Messenger/Mailroom
DGSF

1,770
2,544

Environmental Services
DGSF

900
1,294

Information Technology
DGSF

1,900
2,731

PBX
DGSF

500
719

Dietary
DGSF

600
828

Auxiliary Support

DGSF Total

25,544

3-42

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Administration and Public
Entry Area
Main Lobby
Waiting

3,000

3,000

Women's Toilet

180

180

Multi accommodation - 3 fixtures

Men's Toilet

180

180

Multi accommodation - 3 fixtures

Main Lobby ASF

3,360

To be located in First Floor

Lobby
Waiting

1,000

Lobby ASF

1,000
1,000

Total Department ASF

To be located in Ground Floor

4,360

Intra-Department Circulation

20%

872

Partition & Structures

10%

523

Entry Area DGSF

5,755

Administration and Public


Admitting
Administrative/Staff Areas
Interview/ Admitting Room

12

80

960

Reception

250

250

Registration

200

200

Cashiers

300

300

Vault

40

40

Supply

200

200

Toilet

80

80

Custodian Closet

40

40

Administrative/Staff Areas ASF

2,030

Total Department ASF

2,030

Intra-Department Circulation

20%

406

Partition & Structures

15%

365

Admitting DGSF

2,801

3-43

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Administration and Public
Administration
Administrative Offices
Office

200

200

Director of Nursing

Open Office

200

200

Including Reception

Toilet

50

Administrative Offices ASF

50

Total Department ASF

450

Intra-Department Circulation

20%

90

Partition & Structures

15%

81

Administration DGSF

ADA accessible

450

621

3-44

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Auxiliary Support
Material Management
Material Management
Storage

6,000

6,000

Medical Gas Storage

100

200

Toilet - ADA

50

50
6,250

Material Management ASF

Total Department ASF

6,250

Intra-Department Circulation

20%

1,250

Partition & Structures

10%

750

Material Management DGSF

Code Min. 20 SF per Licensed Bed

8,250

3-45

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Auxiliary Support
Messenger/Mailroom
Messenger
Office - Supervisor

100

100

Open Office

600

600

Toilet - ADA

50

100

Changing

40

40

Specimen Storage

80

80

Mailroom

200

200

Clothes Storage

300

300

One Workstation

Gurneys/Wheelchair Storage

350

350

10 Gurneys and 10 Wheelchairs

Two Refrigerators

1,770

Messenger ASF

Total Department ASF

1,770

Intra-Department Circulation

25%

443

Partition & Structures

15%

332

Messenger DGSF

12 Workstations w/ 12 Lockers (half height)

2,544

3-46

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Auxiliary Support
Environmental Services
Environmental Services
Office - Supervisor

100

100

Supply

400

400

Equipment

200

200

Linen

200

200
900

Environmental Services ASF

Total Department ASF

900

Intra-Department Circulation

25%

225

Partition & Structures

15%

169

Environmental Services DGSF

1,294

3-47

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Auxiliary Support
Information Technology
Information Technology
1

800

800

Lab/Test

800

800

Operator

300

Computer Server Room

300
1,900

Information Technology ASF

Total Department ASF

1,900

Intra-Department Circulation

25%

475

Partition & Structures

15%

356

2,731

Information Technology DGSF

Auxiliary Support
PBX
PBX
1

300

350

Office - Supervisor

100

100

Toilet - ADA

50

50

PBX Room

500

PBX ASF

Total Department ASF

500

Intra-Department Circulation

25%

125

Partition & Structures

15%

94

PBX DGSF

719

3-48

Section 3 Space Program

SERVICE

No. of Units ASF/ Unit

ASF

Remarks

Support Services
Auxiliary Support
Dietary
Dietary
Storage
Refrigerator
Freezer
Dietary ASF

500

500

50

50

50

50

Code Min. 2 Cu FT per Licensed Bed

600

Total Department ASF

600

Intra-Department Circulation

20%

120

Partition & Structures

15%

108

Dietary DGSF

Code Min. 400 sf + 1 sf per Licensed Bed


over 200

828

3-49

Section 3 Space Program


BASEMENT -2
Department

BASEMENT -1
Beds/Rm

ASF

Diagnostic Imaging
Cardiology
Cath/EP Lab Unit
Echo Lab Unit
Support Areas
Administrative/Staff Areas
ASF Total
DGSF
Radiology
X-ray Unit
CT Scan Unit
MRI Unit
Angiography Unit
Ultrasound Unit
Support Areas
Administrative/Staff Areas
ASF Total
DGSF

Sterile Processing
Decontamination Area
Assembly/Sterilization
Administrative/Staff Areas
ASF Total
DGSF
Morgue and Autopsy
Morgue
Autopsy
Administrative/Staff Areas
ASF Total
DGSF

FIRST FLOOR
Beds/Rm

ASF

Perioperative
1
5
-

730
930
970
350
2,980
4,606

3
1
1
2
1
-

900
1,180
850
1,310
400
3,680
1,660
9,980
15,425

Ancillary Services
Pulmonary Function Lab
DGSF

Department

960
1,484

1,270
2,360
850
4,480
6,774

Surgery
Surgery Unit
Interventional Radiology Unit
Shared Support Areas
Administrative/Staff Areas
ASF Total
DGSF
Gastroenterology
Gastroenterology Unit
Administrative/Staff Areas
ASF Total
DGSF
Patient Intake and Recovery
Pre-OP Unit
PACU
Shared Support Areas
Administrative/Staff Areas
Public Areas
ASF Total
DGSF

Department

SECOND FLOOR
Beds/Rm

ASF

Emergency
14
1
-

9,130
2,670
3,000
320
15,120
23,369

5
-

2,440
250
2,690
4,158

22
35
-

2,820
4,220
200
3,230
1,120
11,590
17,914

Clinical Care
Exam Unit
Trauma Unit
Support Areas
Administrative/Staff Areas
Public Areas
ASF Total
DGSF

Admitting
DGSF

Plant Services

54
6
-

10,780
3,510
4,305
2,780
1,600
22,975
36,668

3,360
3,360
4,435
2,030
2,801

(For Reference Only)

Plant Services
DGSF

562

Ancillary Services
Bronchoscopy
DGSF
Clinical Laboratory
DGSF

THIRD FLOOR
Beds/Rm

ASF

Acute Medical

Administration and Public


Entry Area
Main Lobby
ASF Total
DGSF

Department
Obstetrics
Triage
Post-Partum
LDRP
C-Section
Support Areas
Administrative/Staff Area
Public Areas
ASF Total
DGSF
Pediatrics
Pediatrics Unit
Administrative/Staff Area
Public Areas
ASF Total
DGSF
NICU
NICU unit
Administrative/Staff Area
Public Areas
ASF Total
DGSF

600
400
270
1,270
1,920

Entry Area
DGSF

Plant Services

Beds

ASF

Acute Medical
3
13
9
2
-

12
-

12
-

650
3,150
3,270
1,420
2,240
2,210
880
13,820
21,427

4,440
1,030
460
5,930
9,194

3,670
1,260
120
5,050
7,830

Step-Down
Step-Down Unit - Flex Up
Step-Down Unit - Flex Down
Support Areas
Administrative/ Staff Areas
Public Areas
ASF Total
DGSF
Medical/Surgical - Forensic Unit
Medical/Surgical - Forensic Unit
Administrative/Staff Areas
ASF Total
DGSF

10
26
-

3,390
6,540
2,000
1,300
1,000
14,230
22,062

8
-

3,000
1,350
4,350
6,744

640
1,230
970
1,220
4,060
6,139

1,900
2,731

Ancillary Services
Pharmacy
Storage Areas
Manufacturing Areas
Dispensary
Administrative/Staff Areas
ASF Total
DGSF

Auxiliary Support

380
587

Administration and Public


Administration
Administrative Offices
ASF Total
DGSF

1,550
2,344

Information Technology
DGSF
-

450
450
621

Administration and Public


-

Department

Plant Services

1,000
1,320

Plant Services

(For Reference Only)

Plant Services
DGSF

562

(For Reference Only)

Plant Services
DGSF

562

(For Reference Only)

Plant Services
DGSF

562

Auxiliary Support
Material Management
DGSF

6,250
8,250

Messenger/Mailroom
DGSF

1,770
2,544

Environmental Services
DGSF

900
1,294

Dietary
DGSF

600
828

Plant Services
Plant Services
Mechanical
Electrical
Miscellaneous
Administrative/ Staff Areas
ASF Total
DGSF
DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)
BGSF Available (For this floor only)
BGSF Available/ Total Delta
BGSF Delta %

(For Reference Only)

7,000
2,800
1,100
610
11,510
15,193
58,318

18%

10,497
68,815

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

69,303
488
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

50,253
18%

9,046
59,299

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

59,749
450
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

44,467
18%

8,004
52,471

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

53,092
621
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

39,633
18%

7,134
46,767

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

47,096
329
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

38,238
18%

6,883
45,121
45,588
467
1%

3-50

Section 3 Space Program


FOURTH FLOOR
Department

FIFTH FLOOR
Beds

ASF

10
10
10
10
10
-

3,290
3,290
3,290
3,990
3,370
2,480
2,510
1,200
23,420
36,310

Medical/Surgical
Medical/Surgical Unit
Medical/Surgical Unit
Support Areas
Administrative/Staff Areas
Public Areas
ASF Total
DGSF

Plant Services

PENTHOUSE

SIXTH FLOOR
Beds

ASF

Acute Medical

Acute Medical
ICU/CCU/Step-Down
ICU/CCU Unit
ICU/CCU Unit
ICU/CCU Unit
Trauma ICU Unit
Step-Down Unit - Flex Up
Shared Support Areas
Administrative/ Staff Area
Public Areas
ASF Total
DGSF

Department

Department

Beds

ASF

Acute Medical
36
36
-

10,570
10,570
250
1,040
940
23,370
36,233

(For Reference Only)

Plant Services
DGSF

562

Medical/Surgical
Medical/Surgical Unit
Medical/Surgical Unit
Support Areas
Administrative/Staff Areas
Public Areas
ASF Total
DGSF

Plant Services

Department

(For Reference Only)

Rooms

ASF

Plant Services
36
36
-

10,570
10,570
250
1,040
940
23,370
36,233

Plant Services
Mechanical
Electrical
Miscellaneous
ASF Total
DGSF

BUILDING 25
Services

Beds

ASF

Inpatient

284

113,540

7,000
300
300
7,600
10,032

Diagnostic and Treatment

10,032
1,806
11,838

DGSF Total
Circulation/ Exterior Wall
Plant Services
BGSF Total

12,000
162
1%

BGSF Available
BGSF Available/ Total Delta
BGSF Delta %

76,096

Support Services

18,760
208,396
323,982

ASF Total
DGSF

(For Reference Only)

Plant Services
DGSF

562

Auxiliary Support
Biomed
DGSF

700
1,019

PBX
DGSF

500
719

Plant Services

(For Reference Only)

Plant Services
DGSF

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)
BGSF Available (For this floor only)
BGSF Available/ Total Delta
BGSF Delta %

562

38,610
18%

6,950
45,560

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

45,588
28
0%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

36,795
18%

6,623
43,418

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

43,922
504
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

36,795
18%

6,623
43,418

DGSF Total
Interdepartmental & Vertical
Circulation/ Exterior Wall
BGSF Total (For this floor only)

43,922
504
1%

BGSF Available (For this floor only)


BGSF Available/ Total Delta
BGSF Delta %

18%

18%
9%

323,982
58,317
34,407
416,706
420,260
3,554
1%

3-51

Section 4

Statement of Probable Construction Cost


A statement of probable construction cost based on this space
program will be issued under separate cover.

SFGHMC | Space Program May 2007

4-1

Section 5

Acknowledgments
The following people participated in the development of the
San Francisco General Hospital Medical Center space program
report and provided their labor, time and expertise toward the
preparation of the final document:

Steering Committee
Gene Marie O'Connell, MSN
Roland Pickens
Sue Currin, RN, MS, CNS
Delvecchio Finley, MPP, FACHE
Andre Campbell, MD
Jeff Critchfield, MD
John Luce, MD
Sue Carlisle, MD
Kathy Jung, MPH
Carlos Villalva, RA
Ron Alameida, RA
Mark Primeau
Sharon Kotabe, PharmD

Inpatient
Sue Currin, RN, MS, CNS
Yuhum Digdigan, RN, MS
Ana Sampera, RN, MS
Michael Daly, RN
Lettie Miller, RN
Leslie Dubbin, RN
Sharon Wicher, RN, MS
Piera Wong, RN, MS, CNS
Bill Schecter, MD
Jeff Critchfield, MD
Talmadge King, MD
Kevin Grumbach, MD
Todd May, MD
Elena Fuentes-Afflick, MD
Richard Price, MD
Morris Schambelan, MD
Pat Skala

SFGHMC | Space Program May 2007

5-1

Section 5 Acknowledgments

ICU/Step-down
Sue Currin, RN, MS, CNS
Terry Dentoni, RN
Vivian Curd, RN
Genevieve Farr, RN
Paul Koo, RN, MS, CNS
Leslie Dubbin, RN
Lettie Miller, RN
Sue Carlisle, MD
Jim Marks, MD
John Luce, MD
Shirley Stiver, MD
Sheryl Calson, RN, MS, CNS
Nora Goldschlager, MD
Andre Campbell, MD
Courtney Broaddus, MD
Lisa Chen, MD
Julin Tang, MD
Rochelle Dicker , MD
Cheryl Jay, MD
Sandra Peterson

Women & Children


Nela Ponferrada, RN
Fe Hortinela, RN
Louise Dimattio, RN
Elizabeth Romero, RN
Ocean Berg, RN, MS, CNS
Phil Darney, MD
Lee Learman, MD
Tina Raine, MD
Eleanor Drey, MD
Chris Stewart, MD
Susan Sniderman, MD
Teresa Villela, MD
Ronald Dieckmann, MD
Shannon Thyne, MD
Kathryn Roberts

SFGHMC | Space Program May 2007

5-2

Section 5 Acknowledgments

Diagnostic
Terry Dentoni, RN
Patricia Coggan, RN, MS, CNS
Maggie Rykowski, RN
Terry Lynch, MD
Mark Wilson, MD
Geoff Manley, MD
Claude Hemphill, MD
Ebie Fiebig, MD
Walt Finkbeiner, MD
Hal Yee, MD
Jim Genevro
John Applegarth

Emergency
Bob Sypher, RN
Pat Carr, RN
John Fazio, RN, MS, CNS
Kathryn Fowler, RN
Alan Gelb, MD
Chris Barton, MD
Jeff Tabas, MD
Mark Leary, MD
Eric Isaacs, MD
Mitchell Cohen, MD
Jan Allison, RN

Perioperative
Sue Currin, RN, MS, CNS
Terry Dentoni, RN
Lawrence Nichols, RN
Jane Cino, RN
Patricia Coggan, RN, MS, CNS
Renee Navarro, MD
Bob Mackersie, MD
Sue Carlisle, MD
Rochelle Dicker, MD
Ted Miclau, MD
Jim Marks, MD
John Inadomi, MD
Courtney Broaddus, MD
Winona Mindolovich

SFGHMC | Space Program May 2007

5-3

Section 5 Acknowledgments

Ancillary Support
Sharon Kotabe, PharmD
Paul Cho
Shirley Lee, PharmD
Julie Russell
Fred Hom, PharmD
Eberhard Fiebig, MD
Cora Nunez-Talens
Lawrence Nichols, RN
James Moore
Bob Eggleston
Delvecchio Finley, MPP, FACHE
Johnson Gong
Marijane Pierson

DPH Program Management/Administration


Gene Marie O'Connell, MSN
Kathy Jung, MPH
Mark Primeau
Carlos Villalva, RA
John Hurley
Anson Moon

DPW Project Management


Ron Alameida, RA

Fong & Chan Architects


Chiu Lin Tse-Chan, FAIA, CSI, LEED AP
David Fong, AIA, SARA, LEED AP
Paolo Diaz
Nuno Lopes, AIA
Samina Choudhry
Connie Ma, LEED AP
Jacopo Montalenti

Forell/Elsesser Engineers, inc. (Structural Engineers)


Simin Naaseh, SE
James B. Guthrie, SE

SFGHMC | Space Program May 2007

5-4

Section 5 Acknowledgments

Gayner Engineers (Mechanical/Electrical Engineers)


David Pang, PE, CIPE, MCIBSE

TBD Consultants (Cost Estimator)


Gordon Bevridge

Herrero Contractors (Cost Estimator)


Craig Braccia

SFGHMC | Space Program May 2007

5-5

Section 6

Appendices
The following documents were prepared during the
development of the San Francisco General Hospital Medical
Center space program report and supplement the content of
this report.
Appendix A
Space Program Work Plan
Appendix B
Bed Projections
Appendix C
Meeting Minutes

SFGHMC | Space Program May 2007

6-1

Appendix A

SPACE PROGRAM WORK PLAN


Organizational Chart
STEERING COMMITTEE COMPOSITION

Fig. Exhibit A-1

View of SFGHMC

Executive Hospital Administrator


Chief Nursing Officer
Executive DPH Admin. Representative
SFGH Associate Hospital Administrators
Chief Medical Officer
Chief of Service (current and elect)
SFGH/UCSF Dean
Campus Executive Architect
DPW Project Manager

USER GROUP COMMITTEE COMPOSITION

Chief Nursing Officer


SFGH Associate Hospital Administrators
Department Managers
Inpatient
Ambulatory
Emergency
Facilities
Support Services
Physician Representatives

Activity I: Engagement Initiation (2 Weeks):

SFGHMC | Space Program May 2007

Receive authorization to proceed with work

Identify San Francisco General Hospital Medical Center


(SFGHMC) Objectives and Assumptions

Tour SFGHMC and project site

Compile project data: Institutional Master Plan, site survey,


plot plans (topographic and site utilities), legal site
descriptions, soil reports, EIR documentation, City of San
Francisco planning regulations, City of San Francisco
Master Plan (if applicable), SFGHMC space standards, etc

SFGHMC to provide patient population projections

Develop and present preliminary project schedule


Appendix A-1

Appendix A Space Program Work Plan

Assemble Steering Committee, appoint AChair@ and identify


User Groups for the services to be programmed

Activity II: Develop Draft Space Program (12 Weeks):

Document planning assumptions and space requirements,


including scope of services to be included in the building,
operating systems, functional relationships, organizational
structure and staffing, hours of operation, major
equipment,
major
intraand
inter-departmental
relationships, and anticipated facility or operational
changes

Translate planning assumption and space requirements


into the following service categories:

Forward Draft document to user representatives prior to


meeting

Meet with Steering Committee

Review planning assumptions and space requirements

Workshop #1 with User Groups:

SFGHMC | Space Program May 2007

Inpatient
Diagnostic and Treatment
Emergency
Support
Plant Services

Meet with User Groups


Review patient population projections,
assumptions and space requirements
Review site and building constraints
Review work progress in Activity I
Identify and document outstanding issues

planning

Appendix A-2

Appendix A Space Program Work Plan

Activity III:
Weeks)

Preliminary Draft Space Program (7

Document Draft Space Program based on Workshop #1


input.

Develop site plan and floor plan block diagrams

Workshop #2 with Steering Committee and User Groups:

Meet with Steering Committee and User Groups


Review Draft Space Program
Review site plan and floor plan block diagrams
Review work progress in Activity II
Resolve and document outstanding issues

Activity IV: Refine Draft Space Program (6 Weeks)

Refine Draft Space Program based on Workshop #2 input

Develop general room layouts

Workshop #3 with User Groups:

Meet with User Groups


Review refine Draft Space Program
Review general room layouts
Review work progress in Activity III

Activity V: Review and Refinement of Draft Space


Program
(6 Weeks)

Refine Draft Space Program based on Workshop #3 input


and submit for review

Steering Committee and User Groups to review and


comment on Draft Report

Activity VI: Final Space Program (5 Weeks)

SFGHMC | Space Program May 2007

Make minor revisions and complete final Space Program

Appendix A-3

Appendix B

Bed Projections
Introduction
The number of beds included in this space program have been
derived from the examination and analysis of several
variables: census trends at SFGHMC, current and expected
demands on services, the range of services provided at
SFGHMC, rates of occupancy, and services provided by other
area hospitals now and in the future. There is no prescribed
formulary for establishing bed projections.

Daily Census and Average Daily Census (ADC)


Daily Census for this report includes all acute medical patient
days. The daily census is a snap shot in time taken at
midnight each day. Midnight census is the community
standard for counting patient days.
Excluded from the data provided for this report are normal
newborn nursery days, acute psychiatric patient days, and
skilled nursing patient days. Normal newborns are not
considered acute patients and nursery bassinets are never
included in bed counts.
Acute psychiatric and skilled nursing days are excluded
because these patient care areas will not be relocated into the
new hospital building.
Average Daily Census (ADC) is the average number of patients
in the hospital on a single day. An ADC for the past four years
was calculated for each bed type. The ADC can then be used
as one variable to project future bed needs by multiplying each
bed category by a chosen occupancy rate.
There is no fixed prescribed community standard for
occupancy rates. Each hospital must assess the needs of its
own patient population along with their particular service
capabilities to determine an appropriate rate.
The Society of Critical Care Medicine in their Guidelines for
Intensive Care Unit Design state that The development team
should assess the expected demands on the proposed ICU
based on an evaluation of its sources of patients, admission
and discharge criteria, expected rate of occupancy, and
services provided by other area hospitals. The ability to
provide specific levels of care must be determined by
analyzing physician resources, staff resources (nursing,
SFGHMC | Space Program May 2007

Appendix B-1

Appendix B Bed Projections

respiratory therapy, etc.) and the availability of support


services (laboratory, radiology, pharmacy, etc.) This guidance
is equally applicable to acute care beds.
According to the National Center for Health Statistics the
average occupancy rate for Community Hospitals from 1998
thru 2001 was 64%. SFGHMCs occupancy rate has frequently
gone to nearly 100% of its capacity. You cannot operate
efficiently at that occupancy level. Time is required for the
discharge of patients and the cleaning
of beds by
housekeeping services. Operating at levels that exceed 80%
means patients will often have to wait for beds.
Based on the factors described above and known demands for
services, SFGHMC has applied an occupancy factor of 80% for
all acute patient bed categories and a factor of 70% for
intensive care (adult and neonatal) and step-down beds.
Generally a lower rate is applied when utilization of a particular
service is more unpredictable (in the case of intensive care
and step-down which is closely associated with ICU use).
In terms of services provided by other area hospitals, SFGHMC
is the only designated trauma center (Level 1) serving San
Francisco and northern San Mateo County, SFGHMC is
required to maintain bed capacity for trauma patients. Nontrauma facilities do not have this same level of responsibility.
SFGHMC and St. Lukes Hospital are the only two hospitals
that serve the southern quadrant of the City. There is some
concern that in the near term, St. Lukes will not continue to
provide acute care services.
Other variables that artificially lower the census data and that
skews the actual demand for services include:

SFGHMC | Space Program May 2007

Census is limited by the number of available, staffed beds.

Census does not always reflect the patients that have been
admitted but are being held in the emergency department
or PACU awaiting a bed to become available. Patients are
required to be in a bed at midnight to be counted in the
midnight census.

Appendix B-2

Appendix B Bed Projections

Summary
The bed projections provided in Table have been derived from
an examination of all the above variables. Bed flexibility is
built into the program by the number of planned step-down
beds. Step-down beds can either go from intensive care to
step-down; or step-down to acute care levels of care.

SFGHMC | Space Program May 2007

Appendix B-3

Appendix B Bed Projections

ADC

Daily Census

Projected Bed Needs

CY 02-03

CY 03-04

CY 04-05

CY 05-06

4 Year Total

Over 4 Years

Occupancy rate

Based on
Census Data*

Based on
Actual Needs**

Medical/Surgical

47,469

45,083

49,001

47,687

189,240

129.5

80%

162

144

Medical/Surgical - Forensic

1,939

1,425

1,066

1,031

5,461

3.7

80%

ICU

8,000

7,915

8,167

8,647

32,729

22.4

70%

32

40

Step-Down

6,844

7,679

8,805

12,037

35,365

24.2

70%

35

46

Obstetrics

4,197

4,076

4,119

3,952

16,344

11.2

80%

14

22

Pediatrics

1,069

1,082

991

1,093

4,235

2.9

80%

12

NICU

2,864

2,729

2,707

3,421

11,721

8.0

70%

11

12

Total

72,382

69,989

74,856

77,868

295,095

202.3

262

284

Average Daily Census (ADC)

198.3

191.8

204.5

213.3

202.3

SERVICE

Notes:
Census is limited by the number of beds available. Lack of available beds artificially reduces the census and does not reflect actual demand.
Census numbers do not always reflect the patients that have been admitted but are being held in the emergency department or PACU awaiting a bed to become available. Patients need to be in a bed at midnight to be counted in the midnight census which is the community standard for
establishing daily census numbers.
SFGHMC's occupancy rate has frequently gone to nearly 100% of its capacity. Hospitals cannot operate efficiently at that occupancy rate.
SFGHMC operates beds beyond their budgeted capacity in order to care for as many patients as possible.
SFGHMC is the only trauma center in San Francisco. As a designated trauma center SFGHMC is required to maintain bed availability in ICU for trauma patients.

Appendix B-4

Appendix C

Meeting Minutes
The following meeting minutes will serve as the approved
record of matters discussed and conclusions reached during
the space programming effort for the new acute care hospital
at San Francisco General Hospital Medical Center.

SFGHMC | Space Program May 2007

Appendix C-1

MINUTES OF MEDICAL/ SURGICAL MEETING NO. 1


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 1, 2006
2:00 pm : 4:00 pm

ISSUE DATE:

December 4, 2006

ATTENDEES:

Kathy Jung (KJ)


Sue Currin (SC)
Yuhum Digdigan (YD)
Ana Sampera (AS)
Michael Daly (MD)
Lettie Miller (LM)
Leslie Dubbin (LD)
Sharon Wicher (SW)
Piera Wong (PW)
Jeff Critchfield (JC)
Todd May (TM)
Elena Fuentes-Affl. (EF)
Richard Price (RP)
Pat Skala (PS)
Mark Jacobson (MJ)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH -Nursing Admin
SFGH -Nursing Admin
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Oncology
SFGH -Medicine
SFGH -Family & Comm. Med.
SFGH -Pediatrics
SFGH -Neurology
SFGH -Information System
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Medical/ Surgical User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated December 1, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 1, 2006
7. Med/Surg User Group Questionnaire, dated December 1, 2006

ITEMS DISCUSSED:
Item

Description

Action

NEW BUSINESS:
PROGRAM ISSUES

A.
1.01

Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. NL noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230Page 2 of 7

Due Date

Item

Description

Action

267 beds. Kathy Jung (KJ) of SFGHMC noted that


this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
include the estimated 160 million dollars required for
equipment and furnishings or for any renovation work
of the existing hospital building.
3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
1.02

FCA reviewed some current trends in Med/Surg Nursing Unit


Design per the request of the user group. FCA noted that
some of the major trends that may impact the program of the
Nursing Units include the following:
1. Increased use of technology for patient /asset tracking
and allowing decentralizing of nurses away from a
Central Nurse Station towards auxiliary nurse stations
and in-room charting stations.
2. Greater patient privacy. Rooms provided with more
amenities such as multimedia options to increase
patient comfort.
3. Development of Patient rooms with the same
configuration and orientation. This helps reduce staff
error by standardizing the room layouts.
4. Greater use of mobile equipment to allow exams,
therapies and imaging to take place in patient rooms
rather than transporting patients around the hospital.

1.03

FCA noted that the preliminary space program assumptions


for Med/Surg beds were for a total of 120 beds divided into
2 nursing units per floor with 32 & 28 beds per unit. This
assumption was developed in conjunction with SFGH and is
based on a combination of the census figures and previous
utilization studies commissioned by SFGH.

DEPARTMENTAL ISSUES

B.
1.04

Nuno Lopes (NL) of FCA asked whether the Nursing Units


are specialized or generalized units. The user group noted that
there was a distinction between the medical nursing units and
Page 3 of 7

Due Date

Item

Description

Action

the surgical nursing units that should be maintained.


Otherwise there should be no planned specialization of
Nursing Units for maximum flexibility.
1.05

Elena Fuentes-Affl. (EF) of SFGH noted that the Pediatric


Nursing Unit should be located in a separate unit adjacent to
Obstetrics and noted that separation of the general adult
patient population from the Pediatrics and Obstetrics units as
an important planning consideration.
EF also noted that patient rooms in the Pediatrics Nursing Unit
should be designed to be large enough to accommodate
sleeping facilities for a family member.

1.06

Nuno Lopes (NL) of FCA noted that the Forensic Inpatient


Unit was located with the new Hospital Building but that the
Forensic Psych unit was to remain within the existing
Hospital. The user group noted that while it was desirable to
keep the two units together for operational efficiency, it was
preferable to separate the units in order to increase the overall
number of licensed beds in the new Hospital building.

1.07

Mark Jacobsen (MJ) of SFGH expressed his concern that no


patient beds were currently allocated for the General Clinical
Research Center (GCRC) and noted the importance of the
GCRC within the facility.
Kathy Jung (KJ) of SFGH acknowledged that the GCRC
had not yet been addressed as part of the Space Program and
that it needed to be discussed and evaluated by SFGH in a
separate meeting.
NURSING UNIT ISSUES

C.
1.08

Nuno Lopes (NL) of FCA noted that the current assumptions


were for 2 nursing units per floor with 32-28 beds per unit.
The user group confirmed that this was generally acceptable
and that the workability of the 36 bed unit would depend on
the layout of the unit for workflow efficiency.
The user group generally agreed that either a centralized or
decentralized nursing unit concept would be feasible but that
actual plan layouts would need to be reviewed.
The user group noted that the past patient census is not a good
indication of the actual patient beds required by the Hospital
since occupancy is usually over 100% and there is significant
diversion of patients that takes place. Whatever the maximum
number of beds feasible given the other constraints of space
and cost would be preferred by the User Group. After further
discussion, it was agreed that a maximum of four units of 36
beds for a total of 144 licensed beds would be preferable.
FCA to exercise this option for feasibility within the building
Page 4 of 7

Due Date

Item

Description

Action

envelope
1.09

The user group noted the importance of sufficient storage


space required for printers and other equipment that needs to
be easily accessible. The current storage space in the existing
nursing units have not been sufficient.
NL stated that the storing mobile equipment in alcoves along
the corridor could be provided in the design of the unit.
Currently FCA has allocated 400 square feet per unit for
storage not including the possible additional alcove spaces.

1.10

The user group emphasized the importance of having one (1)


conference and one (1) consultation room within each unit.
The user group would also prefer to have at least one (1) sleep
room within the unit in addition to the on call facilities that
will stay in the existing building.
NL noted that any additions to support and service areas may
reduce the number of patient beds as there is a limited amount
of floor area per nursing unit. The user group agreed that
patient beds are the priority and that the work of the group
would be to find the optimal balance between maximizing bed
capacity and staff / support areas.

1.11

The user group confirmed that a separate medicine room


might not be required as a Pyxis/Omnicell automated system
will probably be provided.
PATIENT ROOM ISSUES

D.
1.12

Nuno Lopes (NL) of FCA confirmed that in the current


programming all patient rooms are single occupancy patient
rooms and asked whether shared patient rooms should be
considered to increase the number of licensed beds.
The user group confirmed that all patient rooms should be
designed as single patient rooms with the exception of two (2)
patient rooms per unit which should be designed for the
possibility of two beds in each room with a sliding door within
the shared wall that can open up the rooms into one large
room. This will allow the rooms to be used for monitoring
purposes and as a mini-ward and will provide the nursing staff
with flexibility for patient care.
NL asked the user groups whether the rooms be reduced in
size to maximize the number of beds in the unit. The user
group noted that patient rooms should be designed for medical
reasons and not to squeeze in the maximum capacity.
Although the number of patient beds is a prime consideration,
Page 5 of 7

Due Date

Item

Description

Action

Due Date

the size, comfort and quality of patient rooms should not be


compromised just to maximize capacity.
1.13

Nuno Lopes (NL) of FCA confirmed that in the current


programming three (3) patient rooms per nursing unit are
ADA accessible units as required by code.
The user group agreed to 3 accessible patient rooms per unit
was acceptable. Paolo Diaz (PD) of FCA noted that these
rooms would also be appropriate for bariatric patients.
SFGH to review their current and projected needs for
bariatric rooms and will provide data to FCA at the next
meeting.

1.14

Nuno Lopes (NL) of FCA confirmed that in the current


programming one (1) patient room per nursing unit is an
isolation room as required by code.
The user group noted that because of the prevalence of TB and
other communicable diseases within the patient population
there is a need for 30-35% of the rooms to be negative
pressure isolation rooms.
FCA clarified that the current isolation rooms within the
hospital were not code compliant isolation rooms which
require an anteroom but rather just negative pressure rooms.

1.15

The user group agreed that two isolation rooms with a shared
anteroom per unit would be acceptable and the remainder of
the required isolation rooms could be negative pressure rooms
without anterooms. The isolation rooms should be equally
distributed among all the nursing units.
Nuno Lopes (NL) of FCA confirmed that in the current
programming each patient room has a private toilet.
The user group agreed that all patient rooms should have
private toilets. Shared bathrooms are not considered to be an
option due to infection issues. A shower for each bathroom is
not required apart from the Obstetrics unit. Shared showers on
each unit (2 showers per unit) are sufficient.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc
Page 6 of 7

MINUTES OF MEDICAL/ SURGICAL MEETING NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 1, 2006
2:00 pm : 4:00 pm

ISSUE DATE:

December 4, 2006

ATTENDEES:

Kathy Jung (KJ)


Sue Currin (SC)
Yuhum Digdigan (YD)
Ana Sampera (AS)
Michael Daly (MD)
Lettie Miller (LM)
Leslie Dubbin (LD)
Sharon Wicher (SW)
Piera Wong (PW)
Jeff Critchfield (JC)
Todd May (TM)
Elena Fuentes-Affl. (EF)
Richard Price (RP)
Pat Skala (PS)
Mark Jacobson (MJ)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH -Nursing Admin
SFGH -Nursing Admin
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Nursing Admin.
SFGH -Oncology
SFGH -Medicine
SFGH -Family & Comm. Med.
SFGH -Pediatrics
SFGH -Neurology
SFGH -Information System
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Medical/ Surgical User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated December 1, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 1, 2006
7. Med/Surg User Group Questionnaire, dated December 1, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
PROGRAM ISSUES

A.

1.01

Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. NL noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230Page 2 of 7

Due Date

Item

Description

Action

Due Date

the size, comfort and quality of patient rooms should not be


compromised just to maximize capacity.
1.13

Nuno Lopes (NL) of FCA confirmed that in the current


programming three (3) patient rooms per nursing unit are
ADA accessible units as required by code.
The user group agreed to 3 accessible patient rooms per unit
was acceptable. Paolo Diaz (PD) of FCA noted that these
rooms would also be appropriate for bariatric patients.
SFGH to review their current and projected needs for
bariatric rooms and will provide data to FCA at the next
meeting.

1.14

Nuno Lopes (NL) of FCA confirmed that in the current


programming one (1) patient room per nursing unit is an
isolation room as required by code.
The user group noted that because of the prevalence of TB and
other communicable diseases within the patient population
there is a need for 30-35% of the rooms to be negative
pressure isolation rooms.
FCA clarified that the current isolation rooms within the
hospital were not code compliant isolation rooms which
require an anteroom but rather just negative pressure rooms.

1.15

The user group agreed that two isolation rooms with a shared
anteroom per unit would be acceptable and the remainder of
the required isolation rooms could be negative pressure rooms
without anterooms. The isolation rooms should be equally
distributed among all the nursing units.
Nuno Lopes (NL) of FCA confirmed that in the current
programming each patient room has a private toilet.
The user group agreed that all patient rooms should have
private toilets. Shared bathrooms are not considered to be an
option due to infection issues. A shower for each bathroom is
not required apart from the Obstetrics unit. Shared showers on
each unit (2 showers per unit) are sufficient.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc
Page 6 of 7

Item

Description

Action

267 beds. Kathy Jung (KJ) of SFGHMC noted that


this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
include the estimated 160 million dollars required for
equipment and furnishings or for any renovation work
of the existing hospital building.
3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
1.02

FCA reviewed some current trends in Med/Surg Nursing Unit


Design per the request of the user group. FCA noted that
some of the major trends that may impact the program of the
Nursing Units include the following:
1. Increased use of technology for patient /asset tracking
and allowing decentralizing of nurses away from a
Central Nurse Station towards auxiliary nurse stations
and in-room charting stations.
2. Greater patient privacy. Rooms provided with more
amenities such as multimedia options to increase
patient comfort.
3. Development of Patient rooms with the same
configuration and orientation. This helps reduce staff
error by standardizing the room layouts.
4. Greater use of mobile equipment to allow exams,
therapies and imaging to take place in patient rooms
rather than transporting patients around the hospital.

1.03

FCA noted that the preliminary space program assumptions


for Med/Surg beds were for a total of 120 beds divided into
2 nursing units per floor with 32 & 28 beds per unit. This
assumption was developed in conjunction with SFGH and is
based on a combination of the census figures and previous
utilization studies commissioned by SFGH.

DEPARTMENTAL ISSUES

B.
1.04

Nuno Lopes (NL) of FCA asked whether the Nursing Units


are specialized or generalized units. The user group noted that
there was a distinction between the medical nursing units and
Page 3 of 7

Due Date

Item

Description

Action

the surgical nursing units that should be maintained.


Otherwise there should be no planned specialization of
Nursing Units for maximum flexibility.
1.05

Elena Fuentes-Affl. (EF) of SFGH noted that the Pediatric


Nursing Unit should be located in a separate unit adjacent to
Obstetrics and noted that separation of the general adult
patient population from the Pediatrics and Obstetrics units as
an important planning consideration.
EF also noted that patient rooms in the Pediatrics Nursing Unit
should be designed to be large enough to accommodate
sleeping facilities for a family member.

1.06

Nuno Lopes (NL) of FCA noted that the Forensic Inpatient


Unit was located with the new Hospital Building but that the
Forensic Psych unit was to remain within the existing
Hospital. The user group noted that while it was desirable to
keep the two units together for operational efficiency, it was
preferable to separate the units in order to increase the overall
number of licensed beds in the new Hospital building.

1.07

Mark Jacobsen (MJ) of SFGH expressed his concern that no


patient beds were currently allocated for the General Clinical
Research Center (GCRC) and noted the importance of the
GCRC within the facility.
Kathy Jung (KJ) of SFGH acknowledged that the GCRC
had not yet been addressed as part of the Space Program and
that it needed to be discussed and evaluated by SFGH in a
separate meeting.
NURSING UNIT ISSUES

C.
1.08

Nuno Lopes (NL) of FCA noted that the current assumptions


were for 2 nursing units per floor with 32-28 beds per unit.
The user group confirmed that this was generally acceptable
and that the workability of the 36 bed unit would depend on
the layout of the unit for workflow efficiency.
The user group generally agreed that either a centralized or
decentralized nursing unit concept would be feasible but that
actual plan layouts would need to be reviewed.
The user group noted that the past patient census is not a good
indication of the actual patient beds required by the Hospital
since occupancy is usually over 100% and there is significant
diversion of patients that takes place. Whatever the maximum
number of beds feasible given the other constraints of space
and cost would be preferred by the User Group. After further
discussion, it was agreed that a maximum of four units of 36
beds for a total of 144 licensed beds would be preferable.
FCA to exercise this option for feasibility within the building
Page 4 of 7

Due Date

Item

Description

Action

envelope
1.09

The user group noted the importance of sufficient storage


space required for printers and other equipment that needs to
be easily accessible. The current storage space in the existing
nursing units have not been sufficient.
NL stated that the storing mobile equipment in alcoves along
the corridor could be provided in the design of the unit.
Currently FCA has allocated 400 square feet per unit for
storage not including the possible additional alcove spaces.

1.10

The user group emphasized the importance of having one (1)


conference and one (1) consultation room within each unit.
The user group would also prefer to have at least one (1) sleep
room within the unit in addition to the on call facilities that
will stay in the existing building.
NL noted that any additions to support and service areas may
reduce the number of patient beds as there is a limited amount
of floor area per nursing unit. The user group agreed that
patient beds are the priority and that the work of the group
would be to find the optimal balance between maximizing bed
capacity and staff / support areas.

1.11

The user group confirmed that a separate medicine room


might not be required as a Pyxis/Omnicell automated system
will probably be provided.
PATIENT ROOM ISSUES

D.
1.12

Nuno Lopes (NL) of FCA confirmed that in the current


programming all patient rooms are single occupancy patient
rooms and asked whether shared patient rooms should be
considered to increase the number of licensed beds.
The user group confirmed that all patient rooms should be
designed as single patient rooms with the exception of two (2)
patient rooms per unit which should be designed for the
possibility of two beds in each room with a sliding door within
the shared wall that can open up the rooms into one large
room. This will allow the rooms to be used for monitoring
purposes and as a mini-ward and will provide the nursing staff
with flexibility for patient care.
NL asked the user groups whether the rooms be reduced in
size to maximize the number of beds in the unit. The user
group noted that patient rooms should be designed for medical
reasons and not to squeeze in the maximum capacity.
Although the number of patient beds is a prime consideration,
Page 5 of 7

Due Date

MINUTES OF OBSTETRIC/ PEDIATRIC MEETING NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 5, 2006
2:00 pm : 4:00 pm

ISSUE DATE:

January 5, 2007

ATTENDEES:

Kathy Jung (KJ)


Ocean Berg (OB)
Jon Barash (JB)
Holly Cost (HC)
Ronald Dieckmann (RD)
Alma Martinez (AM)
Nela Ponferrada (NP)
Tina Raine-Bennett
(TRB)
Kathryn Roberts (KR)
Elisabeth Romero (ER)
Susan Sniderman (SS)
William Taeusch (WT)
Juan Vargas (JV)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Women & Children User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated December 1, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 1, 2006
7. Women & Children Program Questionnaire, dated December 5, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
PROGRAM ISSUES

A.
1.01

Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. NL noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230267 beds. Kathy Jung (KJ) of SFGHMC noted that
this maximum target includes construction costs only
and is what has been determined to be politically
Page 2 of 5

Due Date

Item

Description

Action

feasible as a bond measure. This figure does not


include the estimated 160 million dollars required for
equipment and furnishings or for any renovation work
of the existing hospital building.
3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
1.02

FCA reviewed some current trends in OB/GYN Nursing Unit


Design per the request of the User Group. FCA noted that
some of the major trends that may impact the program of the
Nursing Units include the following:
1. Increased use of technology for patient /asset tracking
and allowing decentralizing of nurses away from a
Central Nurse Station towards auxiliary nurse stations
and in-room charting stations.
2. Greater patient privacy. Rooms provided with more
amenities such as multimedia options to increase
patient comfort.
3. Development of Patient rooms with the same
configuration and orientation. This helps reduce staff
error by standardizing the room layouts.
4. Greater use of mobile equipment to allow exams,
therapies and imaging to take place in patient rooms
rather than transporting patients around the hospital.

1.03

KJ confirmed that the time limit for a new hospital is 2013. An


extension for the planning of the new hospital has been
approved; an additional extension while the hospital is in
construction will be necessary.

1.04

The User Group raised the question if the planning of the


OB/GYN and PED departments is considering a move to
Mission Bay.
KJ noted that the decision to move OB/GYN and PED
departments to Mission Bay is outside the mandate of this
programming effort. For now the programming effort will
assume the OB/GYN and PED departments will remain in the
Potrero Campus.

B.

DEPARTMENTAL ISSUES
Page 3 of 5

Due Date

Item

Description

Action

1.05

The User Group requested the programming effort to address


pediatric patient needs in the Emergency and ICU
departments.

1.06

The User Group agreed that a total of three Triage rooms are
necessary. The Triage rooms should be the same size as the
Postpartum rooms. The User Group also commented that if
necessary during high census the postpartum rooms could also
be used for triage.

1.07

The User Group agreed that the current and future philosophy
is to follow the LDRP model- the mother and child stay in one
room during labor, delivery, recovery and postpartum
(LDRP). The average duration for a patient in a LDRP room is
2 days, in case of a C-Section patient the average duration
increases to 4 days.
The User Group confirmed there are currently:
7 LDRP
12 Postpartum
The User Group requested:
9 LDRP rooms
13 Postpartum rooms, which includes 9 single rooms, 2
ADA rooms, 2 isolation (ADA).
1 well baby nursery with 5 well baby bassinets
1 Procedure / Treatment room

1.08

The User Group noted that providing a movable partition


between 2 single patient rooms to allow for observation of two
patients by a single nurse was acceptable.

1.10

All LDRP rooms should have a toilet with a birthing tub.


All Postpartum rooms should have a toilet with a shower.

1.11

The User Group requested four on-call sleep rooms to


accommodate Obstetrics.
They emphasized that the on-call sleep rooms should be on
the same floor as the Obstetrics unit, preferably within the
unit.
The User Group agreed that 2 on-call sleep rooms for
Pediatrics could be located in the existing hospital
preferably on the same floor with a bridge connection.

1.12

The User Group requested 2 C-Section rooms sized similarly


to an operating room with a resuscitation room in between.
This is similar to the current layout, which has proven to work
well.

1.13

The User Group stated their preference to locate


approximately 12 GYN Med/ Surg beds in the same floor as
Page 4 of 5

Due Date

Item

Description

Action

Due Date

Obstetrics. FCA noted that due to space constraints this


would likely not be possible. FCA also noted that staffing
issues would have to be addressed if a partial Med/ Surg unit
was to be programmed on a separate floor.
STAFF ISSUES

C.
1.14

The User Group requested the following revisions from the


original program:
Delete office for social worker.
Increase size of the staff lounge from 300 sf to 400 sf.
Provide only one 400 sf waiting room for Obstetrics,
Pediatrics and NICU.

1.15

The User Group requested lockers for a total of 125 staff (75
female and 50 male)

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc

Page 5 of 5

ICU / STEP-DOWN NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 8, 2006
2:00 pm : 4:00 pm

ISSUE DATE:

January 11, 2007

ATTENDEES:

Kathy Jung (KJ)


Courtney Broaddus (CB)
Andre Campbell (AC)
Vivian Curd (VC)
Terry Dentoni (TD)
Leslie Dubbin (LD)
Genevieve Farr (GF)
Nora Goldschlager (NG)
Cheryl Jay (CJ)
Paul Koo (PK)
John Luce (JL)
Jim Marks (JM)
Lettie Miller (LM)
Sandy Peterson (SP)
Shirley Stiver (SS)
Julin Tang (JT)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Medical/ Surgical User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated December 1, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 8, 2006
7. ICU / Stepdown User Group Questionnaire, dated December 8, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

1.01

General
Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital to be designated as Building 25. The
new Acute Care Hospital is to be constructed on the West
Lawn of the Campus and will not require the demolition of
any of the existing buildings currently on the Campus. NL
noted that there were several major constraints and drivers that
would direct the development of the Space Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230Page 2 of 6

Due Date

Item

Description

Action

267 beds. Kathy Jung (KJ) of SFGHMC noted that


this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
include the estimated 160 million dollars required for
equipment and furnishings or for any renovation work
of the existing hospital building (Building No. 5).
3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
1.02

Building Connections
NL noted the current assumption is that Building 25 and the
old Hospital Building (Building No. 5) will be connected on
three levels; at basement level through a tunnel, at street level
and with a bridge connection at Level 2.
KJ confirmed that connections between all levels will not be
possible since it would be too costly.

1.03

Helipad
Currently the proposed location for a new helipad is the C
wing of Building 5. The feasibility of relocating the helipad
to the top of Building 25 will be studied as part of the Building
Design.

1.04

Building 5 Envelope Limitations


John Luce (JL) and Andre Campbell (AC) of SFGH explained
that the space available in the established envelope is limited
and cannot be increased. They both emphasized the important
goal is to achieve the maximum efficiency within the
established envelope.
JL noted that the assumptions made for the new hospital are
based on previously proposed space programming figures that
were not considering any building envelope limitations.
Now that the decision regarding the site to be on the existing
campus between buildings 20 and 30 is made, the current
space programming is more precise and represents a realistic
possible scenario.
FCA noted that there will be a net overall increase in program
areas because Building 5 will be retained for outpatient, clinic
and support functions. There may be limitations in the size of
inpatient, diagnostic and treatment functions because of the
limitations of the new building envelope, but the overall
available space will be increased.
Page 3 of 6

Due Date

Item

Description

Action

B.

DEPARTMENTAL ISSUES

1.05

Space Adjacencies
The user group noted the following spaces are desirable to be
adjacent to the ICU unit::
Post Anesthesia Care Unit (PACU)
Operating Rooms (OR)
Cath Lab
Given the building limitations, it was agreed that it will not be
possible to locate all related departments on the same floor.
Dedicated elevators assigned to connect these spaces was
considered an acceptable solution to address adjacency
requirements.
The user group agreed that the final layout will depend on the
optimal allocation within the building envelope.

1.06

Location of Operating Rooms


The user group expressed concern that the Operating Rooms
were located in the basement and did not have any natural
daylight. FCA explained that the Patient rooms are required
by code and practice to have access to natural daylight and
that they are given priority in their location above grade.
Other departments, such as Emergency are required to be
located at grade level. This limitations lead to the location of
the Peri-Operative Services and Imaging Department in the
basement levels. The user group generally agreed with this
approach and understood the rationale.

1.07

On-Call Sleep Rooms


The user group expressed concern about the initial proposal to
locate all the on-call sleep and conference rooms in Building
No. 5.
FCA noted that this was done to maximize the amount of
space for patient bedrooms and support services but agreed
that a minimum number of sleep and conference rooms per
unit are required for the operational efficiency of the
ICU/CCU in the new building.

1.08

Quantity of Isolation Rooms


The user group expressed concern that one (1) isolation room
per unit would not be sufficient to meet operational needs.
FCA clarified that an isolation room built to the current code
has an anteroom and specific requirements and is not
comparable to what is currently designated as isolation rooms
in the existing hospital, which generally only have negative
pressure systems.
It was agreed that one (1) isolation room per unit would be
provided and one (1) negative-pressure room.

Page 4 of 6

Due Date

Item

Description

1.09

Support & Staff Area


The user group requested the following support and staff areas
to be included in the ICU department:

1.10

Action

3 Nurse manager offices


1 ICU director office
2 Workrooms
2 Consultation rooms. (100 square feet (sf) each)
Staff lounge (does not need to be located within the
unit, can be located in Building No. 5.)
Staff lockers (50 male / 50 female)

Patient Rooms
The user group confirmed that the 2005/06 census has been
extremely high. More beds for the ICU and Step-down are
currently needed. These numbers are also expected to increase
in the future. The increase in patient number is dependent on
the development of the citys health care policies and are
unpredictable.
The user group agreed that the programming should provide
the maximum flexibility possible regarding the current and
future use of the units.
The number of ICU/Step-down was discussed.
The user group agreed to the following ICU/Step-down bed
breakdown:

40 licensed ICU beds in 4 units.

10 licensed ICU beds in one unit that will also


function as a Step-Down Unit.

One 32-36 bed Med/Surg Unit that will also function


as a Step-Down Unit.

Subsequent to this meeting, the Emergency Department user


group noted that it was desirable that one ICU unit be
designated as a Trauma ICU unit.
1.11

Patient Room Toilets


The user group confirmed that the ICU Patient rooms do not
need separate toilets.
Step-down rooms need separate or shared toilet facilities.

Page 5 of 6

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc

Page 6 of 6

MINUTES OF DIAGNOSTIC MEETING NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 12, 2006


2:00 pm : 4:00 pm

ISSUE DATE:

January 15, 2007

ATTENDEES:

Kathy Jung (KJ)


Patricia Coggan (PG)
Doug Eckman (DE)
Genevieve Farr (GF)
Walt Finkbeiner (WF)
Jim Genevro (JG)
Claude Hemphill (CH)
Richard
Hollingsworth
(RH)
Gene OConnell (GOC)
Roland Pickens (RP)
Hal Yee (HY)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH, Executive Administrator
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Diagnostic User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Space Programming Objectives and Assumptions, dated December 1, 2006
2. Project Schedule dated November 20, 2006
3. SFGHMC Rebuild Program Subcommittee Focus Groups,
4. Average Daily Census FY 00-01 FY 04-05
5. Preliminary Summary Space Program, dated December 1, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

1.01

General
Paolo Diaz (PD) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. PD noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs PD noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230267 beds. Kathy Jung (KJ) of SFGHMC noted that
this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
include the estimated 160 million dollars required for
Page 2 of 6

Due Date

Item

Description

Action

equipment and furnishings or for any renovation work


of the existing Hospital Building.
3. Site Limitations- PD noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
B.

DEPARTMENTAL ISSUES

1.02

Radiology & Endoscopy Rooms


The user group noted that the use of diagnostic imaging in the
future is anticipated to increase with a focus on a wider use of
CT scanning and MRI scanning facilities.
It was noted that there is a need to increase the current number
of Endoscopy procedure rooms.
The user group agreed to the following numbers of rooms:
2 X-Ray Rooms
1 Fluoroscopy Room
1 Interventional Radiology Room (adjacent to ORs)
3 CT Scans (1 CT Scan for Emergency, 2 CT Scans for
Diagnostic Imaging)
2 MRI
2 Angiography Rooms
2 Ultrasound

1.03

Location - Inpatient Imaging


The user group agreed to locate the Inpatient Imaging in the
basement of the new hospital with dedicated elevators
connecting the department to the surgery and emergency.

1.04

Outpatient/Inpatient Split Radiology & Endoscopy (GI)


Paolo Diaz (PD) of FCA asked whether the Endoscopy
Procedure Rooms should be separated between outpatient
radiology located in the existing Hospital Building (Building
No. 5) and inpatient radiology located in the new hospital
building (Building No. 25).
The user group raised concerns that splitting the Endoscopy
procedures between Outpatient and Inpatient would result in
additional staff required in 2 different locations.
The user group agreed that each nursing unit floors should
have either a procedure room or a larger patient room where
Endoscopies could be performed. Outpatient Endoscopies
would remain in the existing Hospital Building. This solution
would increase the availability of Endoscopy procedure rooms
Page 3 of 6

Due Date

Item

Description

Action

and would reduce the amount of intra-hospital transportation


for the patient. The comfort of the patient is an important
concern.
The user group agreed that the GI department and the
Outpatient Imaging should be maintained in the existing
Hospital Building. (Building No. 5). It was understood that
there will be additional operational costs in separating
Outpatient and Inpatient Imaging.
1.05

Adjacencies
The user group noted that ideally the ICU/CCU should be
located closer to the Diagnostic Imaging department but that it
was acceptable to have a dedicated elevator provide access
between the departments.
The user group agreed that the IR rooms should be located
adjacent to the Operating Rooms as a swing room to be
accessible for both Diagnostic Imaging and Perioperative
departments.
Subsequent to this meeting, Dr. Andre Campbell also noted
that a wall mounted Fluoroscopy unit be provided in one of
the OR rooms for use during Trauma Surgery.

1.06

Cardiology
The user group noted that an Angiography Room is not
required within the Cath Lab. 2 Angiography Rooms in the
Inpatient Radiology department will be sufficient.
The user group agreed that one (1) Cath lab in the new
hospital building will be sufficient and that all other
Diagnostic Cardiology functions can be kept in the existing
Hospital Building (Building No.5).
The user group recommended four (4) Echo/EKG rooms and
two (2) Stress Testing Rooms.

1.07

Mammography
The user group confirmed there is no need for Mammography
in the new building. These services are provided in the Avon
Breast Center.

1.08

Nuclear Med.
The user group confirmed that the Nuclear Med. Department
should remain in the existing Hospital Building (Building
No. 5).

1.09

Further Departments located in Old Hospital


FCA confirmed that the following departments remain in the
existing Hospital Building:
Page 4 of 6

Due Date

Item

Description

1.10

Action

Cardio Echo
Rehab
Dialysis
Respiratory
Bronchoscopy
Main storage
Psych
SNF

Pathology- Morgue
The user group recommended that the Pathology department
should be relocated from Building No. 3 into the existing
Hospital Building. This will move it adjacent to the clinical
labs.
FCA confirmed that there is a frozen section room within the
OR area. The user group noted that this was acceptable.
The user group requested one centralized morgue for the
SFGHMC to be located with the new Hospital Building.
Size of the morgue facility to be determined.
The user group recommended that an autopsy area be provided
next to the morgue that can also be used for tissue transplant.
The user group agreed that pathology offices and faculty
rooms do not need to be next to the morgue and autopsy
facilities in the new Hospital Building. They can be located in
a separate location.

1.11

Clinical Lab
The user group agreed that the main clinical labs and blood
bank could stay in the existing hospital building if each unit is
supplied with the necessary equipment and rooms to perform
point of care testing. Satellite labs in each department/unit
need to be connected to the clinical labs in the existing
Hospital Building through a new 6 inch pneumatic tube
system that can accommodate IV bags.
The user group confirmed that point of care testing can also be
used in the ICU/CCU and Emergency.
FCA confirmed that a Building Code requires a minimum
amount of Clinical Lab space to be located within the new
Hospital Building as part of the critical facilities. FCA to
provide the exact requirements.
Subsequent to this meeting, FCA clarified that the following
Clinical Lab functions need to be available within the new
Hospital Building to meet minimum code requirements.
420A.17 Clinical Laboratory Service Space.
Page 5 of 6

Due Date

Item

Description

Action

Due Date

420A.17.1 General requirements. All hospitals shall provide


space and equipment to perform urinalysis, complete blood
counts, hemoglobin blood typing and cross matching. If laboratory facilities for bacteriological, serological, pathological and
additional hematological procedures are not available in the community, then space, equipment and supplies for such procedures
shall be provided.
420A.17.2 Size. The minimum clinical laboratory area shall be
180 square feet (16.7 m2).
420A.17.3 Blood storage. Blood storage facilities shall be provided.

1.12

Storage Space
The user group is concerned about sufficient and appropriate
storage space for diagnostic equipment and addressed the
importance for it to be accessible at all times.
FCA confirmed that the storage in the basement is for general
storage purposes and that there will be additional storage
space allocated for each department. A detailed breakdown of
the programming will be presented in the next meeting.

1.13

Mobile Imaging Equipment


The user group noted that it was desirable to provide
provisions for Mobile Imaging equipment on each nursing
unit.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc

Page 6 of 6

MINUTES OF PERI-OPERATIVE MEETING NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 15, 2006


2:00 pm : 4:00 pm

ISSUE DATE:

January 17, 2007

ATTENDEES:

Kathy Jung (KJ)


Andre Campbell (AC)
Jane Cino (JC)
Sue Currin (SC)
Terry Dentoni (TD)
Renee Navarro (RN)
Lawrence Nichols (LN)
Winona
Mindolovich
(WM)
Gene OConnell (GOC)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH, Executive Administrator
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Peri-Operative User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated November, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 15, 2006
7. Peri-Operative User Group Questionnaire, dated December 15, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

1.01

General
Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. NL noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230267 beds. Kathy Jung (KJ) of SFGHMC noted that
this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
include the estimated 160 million dollars required for
equipment and furnishings or for any renovation work
Page 2 of 5

Due Date

Item

Description

Action

of the existing hospital building.


3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
1.02

A.
1.03

NL encouraged all attendees to hold separate internal space


program discussions and forward any comments and/or
questions to KJ prior to the next Peri-Operative User Group
meeting . NL also noted that the high census of 05/06 will
be taken into account with the space program once those
figures are made available.

DEPARTMENTAL ISSUES
Outpatient/Inpatient Split Peri-Operative
The feasibility of locating Inpatient Peri-Operative services in
the new hospital building and Outpatient Peri-Operative
services in the existing hospital building was discussed.
Paolo Diaz (PD) of FCA described the following 2 possible
programming scenarios to be studied.
1. Entire Peri-Operative Department to be located in
the new hospital building Sixteen (16) OR/IR
rooms with adjacent sterile processing facility.
2. Inpatient Peri-Operative Services to be located in
the new hospital building - Outpatient PeriOperative Services to remain in the existing
hospital building Ten (10) OR/IR rooms with
adjacent satellite sterile processing facility in the new
hospital building. The main sterile processing and
Outpatient Surgery services to use existing spaces.
The user group preferred the option of having the entire PeriOperative Department in the new hospital building. The
consensus was that splitting the Outpatient and Inpatient PeriOperative services was not desirable as this would have
significant impact on operational costs.

1.04

Sterile Processing & Distribution


Dr. Andre Campbell (AC) of SFGH noted that ideally the
Sterile Processing & Distribution (SPD) should be located
adjacent to the OR to keep crucial transportation time of
Page 3 of 5

Due Date

Item

Description

Action

required surgery items during surgery to a minimum.


1.05

Quantity & Size of Operating Rooms (OR)


Nuno Lopes (NL) of FCA noted that currently there are ten
(10) ORs in the existing hospital building. The OR room size
varies between 380sf- 550sf.
The user group confirmed that the number of ORs definitely
needed to be increased.
The user group discussed whether it is better to pursue an
increased number of medium/small (450-480sf) sized OR
rooms rather than working with a smaller number of large OR
rooms (550-650sf).
Dr. Andre Campbell (AC) of SFGH questioned the need for
very large OR rooms and noted that the small OR rooms (450480sf) are sufficient for the majority of operations if operation
equipment is installed within the OR; if mobile equipment is
shared between OR s, bigger OR rooms are better. He also
noted that it would be better if all OR rooms are the same size.
The user group concluded that the program should include:
Sixteen (16) OR rooms in total, including 2 IR room for
Surgery. All OR rooms to be around 520sf in size.
If it is not possible to accommodate the large sized OR rooms
within the given floor plan, the room size and number should
be reduced to only:
Ten (10) large OR rooms (520sf)
Four (4) smaller OR rooms (minimum 400sf)
Two (2) IR rooms (520-600 sf) including Fluoroscopy
equipment for Surgery
The user group confirmed that orthopedic surgery rooms need
to be the larger OR Rooms and require a laminar flow
mechanical system.
Subsequent to this meeting, Dr. Andre Campbell also noted
that a wall mounted Fluoroscopy unit be provided in one of
the large OR rooms for use during Trauma Surgery.

1.06

Inpatient Bed Ratio


Gene OConnell (GOC) of SFGH inquired about data
showing the relation between the amount of surgeries
performed to the amount of inpatient beds required and
questioned if there were sufficient inpatient beds to
accommodate the amount of surgeries performed in the OR.
FCA noted that the number of ICU beds has been increased
from 40 to 50 licensed ICU/CCU beds and that an additional
Page 4 of 5

Due Date

Item

Description

Action

Due Date

10 Step-down beds are considered as flex up ICU/CCU


beds, which gives a total of 60 ICU/CCU beds.
1.08

Lockers
The user group requested for locker space for a total of One
Hundred and Fifty (150) staff members. Surgery and
Anesthesia can share the locker rooms.
Female- male ratio is 50-50.
The user group agreed that the small personal lockers for
individuals and shared full-height day-use lockers be
provided.

1.09

On-Call Sleep Rooms


The Anesthesia users requested 4 separate sleep rooms, 2
rooms with separate toilets and 2 rooms sharing a toilet.
The Surgery user group noted to confirm detailed
requirements in the next meeting. FCA to provide one (1)
sleep room for Surgery until the requirements can be
confirmed.

1.10

Miscellaneous
The user group noted the following items:
Viewing rooms are not required
Provide Anesthesia Workroom with 350sf and 100sf
storage
Provide One (1) Isolation room in the PACU Recovery
Area
Pantry area needs more space
One (1) shower is sufficient in the PACU Recovery Area
There should be 1 OR Staff lounge and 1 Anesthesia
lounge. The anesthesia lounge could be used as a
conference room as well.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc

Page 5 of 5

MINUTES OF EMERGENCY MEETING NO. 1

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

December 18, 2006


2:00 pm : 4:00 pm

ISSUE DATE:

January 22, 2007

ATTENDEES:

Kathy Jung (KJ)


April Clock (AC)
Mitchell Cohen (MC)
Rochelle Dicker (RD)
John Fazio (JF)
Kathryn Fowler (KF)
Angela Hackenschmidt
(AH)
Michelle Lin (ML)
Gene OConnell (GOC)
Kristan
Staudenmayer
(KS)
Bob Sypher (BS)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH, Executive Administrator
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA

Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Emergency User Group. The
following is a record of the items discussed.

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

FCA presented and discussed the following attached documents:


1. Agenda of Meeting
2. Space Programming Objectives and Assumptions, dated November, 2006
3. Project Schedule dated November 20, 2006
4. SFGHMC Rebuild Program Subcommittee Focus Groups,
5. Average Daily Census FY 00-01 FY 04-05
6. Preliminary Summary Space Program, dated December 18, 2006
7. Med/Surg User Group Questionnaire, dated December 18, 2006

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

1.01

General
Nuno Lopes (NL) of FCA noted that the primary goal of this
effort was to develop a Detailed Space Program for the new
Acute Care Hospital. The new Acute Care Hospital is to be
built on the West Lawn of the Campus and will not require the
demolition of any of the existing buildings currently on the
Campus. NL noted that there were several major constraints
and drivers that would direct the development of the Space
Program.
1. Operations The User Groups and the Leadership
committee need to provide input to help develop a
space program that will adequately meet the
operational needs of SFGHMC for the foreseeable
future.
2. Costs NL noted that a Site Feasibility Study was
recently completed which validated the feasibility of
the West Lawn site and set some parameters and costs
for the project. FCA has been instructed to assume a
preliminary construction cost budget of 622 million
dollars for a new building with approximately 230267 beds. Kathy Jung (KJ) of SFGHMC noted that
this maximum target includes construction costs only
and is what has been determined to be politically
feasible as a bond measure. This figure does not
Page 2 of 6

Due Date

Item

Description

Action

include the estimated 160 million dollars required for


equipment and furnishings or for any renovation work
of the existing hospital building.
3. Site Limitations- NL noted that the Site Feasibility
Study established parameters for the maximum size of
the new building. Code and Planning requirements
have determined the maximum area for each floor and
the maximum number of floors for the new facility.
All new required program elements need to be
accommodated within this envelope.
B.
1.02

DEPARTMENTAL ISSUES
Emergency Rooms
The user group commented that the current number of 25
exam rooms is inadequate.
The user group requested 40 exam beds to be programmed in
the new hospital with the following breakdown
27 private exam rooms
3 private isolation exam rooms
One open space exam area capable of holding 10 beds.
The user group also inquired whether additional space in the
corridor would be available to accommodate additional
gurneys in case of a catastrophic event. KJ noted that gurneys
in hallways should be avoided.
David Fong (DF) of FCA noted that each of the 27 private
exam rooms, currently programmed at 120 sf, are capable of
holding two beds in case of a rapid patient surge. DF however
cautioned that this approach is not ideal and would likely not
be acceptable as a means to address normal daily patient
fluctuations.

1.03

Trauma Rooms
The user group requested 6 trauma rooms and noted that when
considering work flow an open floor plan layout for the
trauma rooms is preferred.
NL noted that from an acoustical, turnover and infectious
control standpoint an open floor plan layout for the trauma
rooms may not be desirable. These issues could be partially
mitigated if an opening in the partition separating the trauma
rooms is provided. The User Group agreed to this approach.
The user group also requested 3 equipment storage rooms.

1.04

Imaging
Contrary to the existing condition, the user group confirmed
Page 3 of 6

Due Date

Item

Description

Action

that a dedicated x-ray room for each trauma room is not


required.
Instead the user group requested a separate imaging suite
consisting of 2 CT scan rooms and 2 X-ray rooms, located
within the Emergency department preferably adjacent to the
trauma suite.
Subsequent to this meeting, the Steering Committee
questioned this approach and requested this issue be
reconfirmed in the next Emergency user group meeting.
1.05

Department Adjacencies
The user group expressed some concern regarding the
distance between the Radiology and Emergency departments
and noted that ideally Emergency, Surgery and Radiology
departments should all be collocated on the same floor.
NL noted that given the site constraints collocating all three
departments in the same floor is not possible, however each
department is currently programmed to be located directly
above or below each other, vertically linked with dedicated
service only elevators. NL explained that currently
Radiology is located in the Basement Floor, Surgery is
located in the Ground Floor and Emergency is located in the
First Floor.
Kathy Jung (KJ) also pointed out that the Emergency
department will be equipped with two X-ray rooms and two
CT scan rooms to handle any urgent imaging needs.
Given the limited size of each floor area, the user group
confirmed that the proposed concept would be operationally
feasible.

1.06

Storage
The user group expressed concern that an 8-6 corridor would
not provide adequate storage space for equipment.
NL noted that currently two 300 sf storage rooms have been
programmed and that during the building design phase the
user group could request alcoves within the corridor to provide
for additional storage areas. The user group conquered with
this approach.

1.07

Medication Room
The user group requested larger medication rooms to facilitate
4 automated medication machines. The user group noted that a
decision needs to be made whether all 4 machines should be
located centrally in 1 room or in 4 separate rooms distributed
within the department depending on the floor plan layout.
Page 4 of 6

Due Date

Item

Description

Action

1.08

Meeting and Consultation Area


NL noted that 2 conference rooms of 200 sf each and 2
consultation rooms of 120 sf each for staff meetings and
patient consultations have been programmed. The user
group conquered with the proposed space allocation.

1.09

Stat. Lab
The user group requested a small 100 SF Stat. Lab to be
located in the Emergency department.

1.10

Centralized Monitoring Area


The user group noted that a centralized monitoring area is
not desirable, since that would require additional dedicated
nursing staff. Nursing stations should be sized to
accommodate all necessary monitoring equipment.

1.11

Custodian Closets
The user group requested 1 custodian closet inside the
Trauma suite and two additional custodian closets to service
the remaining Emergency department.

1.12

Linen
The user group mentioned that in the existing Emergency
department the accumulation of soiled linen has become an
issue and requested a dedicated 800 sf soiled linen room.

1.13

Manager/Director Offices
The user group requested separate offices for the manager
and director positions.

1.14

Security Staff Area


The user group pointed out that a dedicated security room
adjacent to the emergency lobby area is not desirable. The
user group preferred to allocate space for a workstation
inside the Emergency Entry lobby to increase the visibility
of security personnel.

1.15

EMS Dispatch
The user group confirmed that the EMS Dispatch can be
reduced to 80 sf.

1.16

On-Call Sleep Rooms


The user group agreed that the residents do not require a
sleep room in the Emergency department.

1.17

Viewing Room
The user group confirmed that a separate viewing room for
family members to view a deceased patient before taken to
the morgue is not required.

Page 5 of 6

Due Date

Item

Description

Action

1.18

Lockers
The user group requested a mix of medium and large sized
lockers to be shared with a total of 160 staff members.

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Emergency\Minutes_06.12.18_001 Emergency.doc

Page 6 of 6

MINUTES OF MEDICAL/ SURGICAL MEETING NO. 2

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 5, 2007
2:00 pm : 4:00 pm

ISSUE DATE:

February 5, 2007

ATTENDEES:

Kathy Jung (KJ)


Ronald Alameida
Iran Blanco
Sue Currin
Elena- Fuentes-Afflick
Kevin Grumbach
Fred Hom
Sharon Kwong
Todd May
Katie Murphy
Ana Sampera
Morris Schambelan
Chris Stewart
Bill Taeusch
Sharon Wicher
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
Bureau of Architecture, Project Manager
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to review the programming effort with the Medical/ Surgical User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 5, 2007
3. Preliminary Summary Space Program, dated January 5, 2007
4. New Hospital Space Program, dated January 5, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

2.01

Building Bulk & Clearances


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that the distance at the first and second
floor levels to the existing hospital building is 25 and to the
adjacent brick buildings 20 and 30 is 40. The floors above the
second floor have additional setbacks to address planning and
exterior wall fire rating concerns. The distance at the basement
1 and 2 to the existing hospital building is 14 and to the
adjacent brick buildings 20 and 30 is 12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the designated
site. It does not represent any design features. The final layout,
building and faade design are to be determined at a later
stage.

B.

DEPARTMENTAL ISSUES

2.02

Forensic Unit
The user group requested if it was possible to configure the
Forensic unit to allow it to be used as a regular Med/Surg unit
during low census of forensic patients.
Currently the existing forensic unit cannot accept non-forensic
patients and is required to shut down if the number of patients
is lower than 3. The average census for forensic beds was 2.3
last year, 3.4 this year.
NL commented that a Forensic Unit has unique security
Page 2 of 4

Due Date

Item

Description

Action

requirements and may not be possible to convert to a regular


Med/Surg unit.
NL and PD noted that a meeting with the forensic group will
determine the requirements and possibilities for a flexible
Forensic MedSurg unit.
2.03

New and Existing Bed Capacity


NL introduced the revised space program and confirmed that a
total of 4 Med/Surg units each with 36 beds have been
programmed for the 5th and 6th floors.
The following distribution of patient rooms was proposed and
agreed by the user group.
19 Patient Rooms - Single Occupancy
4 Patient Rooms - Double Occupancy
9 Patient Isolation Rooms
The user group expressed concerns that the total number of
patient beds currently being proposed is too low.
The user group estimated that currently 186-196 beds are
being used.
The user group requested if an additional Med/Surg unit could
be added in the currently allocated shell space on the 3rd floor.
NL noted that FCA would analyze the available space on the
third floor and confirm whether an additional Med/Surg unit
could be accommodated.

2.04

Pharmacy - Medication Room


The user group explained that the medication room needs to
accommodate 9 nurses per Med/Surg unit.
Currently one 80sf medication room per Med/Surg unit has
been programmed.
The user group requested FCA to program two 120sf
medication rooms per Med/Surg unit.

2.05

Lockers
The user group expressed concerns that the number of
lockers might not be sufficient.
KJ confirmed a shared day-use policy for the lockers has been
agreed for the new hospital.

2.06

Conference Rooms - Teaching Rooms - Rounds


The user group mentioned the importance of providing
sufficient space for conference/consultation rooms,
predominantly to be used for:
Patient rounds and teaching
Seminars / lectures
Page 3 of 4

Due Date

Item

Description

Action

Due Date

The user group agreed that seminars/lectures could take


place in existing conferences rooms in Building 5, but all
patient rounds and teaching should be conducted in
conference/consultation rooms located on the same floor as
the Med/Surg unit.
2.07

Isolation
The user group requested 30% to 35% of all patient rooms
to be isolation rooms.
NL confirmed that the current available space only allows
for 25% of all patient rooms to be true isolation rooms, but
additional negative pressure rooms, which are similar to
isolation rooms minus the anteroom, would be programmed
to make up the difference.

2.08

Computer Terminals in Corridors


The user group requested that sufficient space be provided
within the corridors for computer terminals, so that they are
easily accessible and evenly distributed.
CLTC noted that details such as computer terminal locations
in the corridor layout are going to be addressed at a later
design stage. The floor layout currently shown is only
representing one of many layouts possible to demonstrate
that the planned space program fits into the designated
square footage of the building envelope.

2.09

Social Worker Offices


The user group confirmed that one 200sf office per floor
would be required to accommodate 2-4 social workers.

2.10

Summary
NL summarized the following points at the end of the
meeting:
Any feedback regarding the space program spreadsheet
should be forwarded to FCA to be addressed in further
planning.
There is no more available space for additional program on
the 5th and 6th floors. Any additional program on these
floors will have to replace space that has already been
allocated.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc
Page 4 of 4

MINUTES OF OBSTETRIC/ PEDIATRIC MEETING NO. 2


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 9, 2006
1:45 pm : 4:00 pm

ISSUE DATE:

February 8, 2007

ATTENDEES:

Kathy Jung (KJ)


Beg Ocean
Sue Carlisle
Phil Darney
Louise Dimattio
Fe Hortinela
Colin Partridge
Nela Ponferrada
Tina Raine-Bennett
Kathryn Roberts
Chris Stewart
Cathryn Thurow
Cam Tran
Teresa Villela
Juan Vargas
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 9, 2007
3. Preliminary Summary Space Program, dated January 9, 2007
4. New Hospital Space Program, dated January 9, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

BUILDING ISSUES

2.01

Relocation to Mission Bay


The user group raised the question whether the
Obstetric/Pediatric (Ob/Peds) department is going to be
relocated to Mission Bay.
KJ noted that the program effort should continue with the
assumption that Ob/Peds is going to remain in the Potrero
campus.

2.02

Building Bulk & Clearances


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that in order to address planning and
exterior wall fire rating concerns specific distances to the
existing buildings need to be kept on all levels.
The distance at the first and second floor levels between the
existing and new hospital building is 25. The distance
between the new hospital building and the adjacent brick
buildings 20 and 30 is 40.
The floors above the second floor have additional setbacks to
address planning concerns and to eliminate the need to have
fire rated walls and windows along the east facade.
The distance at the basement 1 and 2 to the existing hospital
building is 14 and to the adjacent brick buildings 20 and 30 is
12.
NL emphasized that the bulk study is only an exercise to
Page 2 of 6

Due Date

Item

Description

Action

examine the maximum mass possible within the designated


site. It does not represent any design features. The final layout,
building and faade design are to be determined in the
subsequent design phases.
B.

PROGRAM ISSUES

2.03

OB/PEDS Location
NL noted that the Ob/Peds department is currently
programmed to be located on the 2nd Floor of the new hospital
building.
The user group raised concerns with collocating the OB/Peds
department on the same floor as the bridge connection to the
existing building, since this may result in higher than usual
human traffic which could pose a security concern given the
patient population of the department.
FCA discussed several options ranging from either relocating
the Ob/Peds department or the bridge connection to the 3rd
floor or to layout the floor plan in a way that provides a direct
and dedicated connection from the elevators to the bridge
connection without passing through the OB/Peds department.
It was agreed that a final decision will be made after
examining and reconsidering the floor plans and program.

2.04

Quantity & Size of Rooms


The user group agreed to the following number of patient
rooms in Obstetrics, Pediatrics and NICU:
Obstetrics

3 Triage Rooms @ 180 sf


13 Post Partum Rooms @ 180 sf
9 LDPR Rooms @ 250 sf
Pediatrics

12 Patient Rooms @ 180 sf


NICU

1 Level II Patient Room @ 720 sf (6 bassinets)


1 Level III Patient Room @ 900 sf (6 bassinets)
The user group noted that the layout of the patient rooms in
Pediatrics should accommodate a sleeping area for family
members.
The user group commented that unlike the current Pediatric
Department the new Pediatrics Department should be family
friendly in terms of its program and layout.

Page 3 of 6

Due Date

Item

Description

Action

2.05

Triage Rooms
The user group questioned if the current number of triage
rooms being programmed is sufficient.
FCA noted that currently 3 triage rooms have been
programmed. FCA added that during high census post partum
rooms and LDRP rooms can serve as additional triage rooms.
The user group agreed to the above arrangement. KJ also
added that how the rooms are going to be utilized is an
internal discussion dealing with operational issues to be
addressed at a later point.

2.06

C-Section / Resuscitation
The user group noted that the C-Section and Resuscitation
rooms are not adequately sized.
FCA proposed to increase the size of the C-Section room to
400 sf and the Resuscitation room to 200sf.
FCA to review the impacts the additional space will have on
the program.

2.07

Patient Toilets
Obstetric

NL confirmed that toilets in LDPR rooms are equipped with


bath tubs.
Pediatric

The user group requested Pediatrics patient rooms to be sized


similarly to Med/Surg patient rooms in order to provide for
future flexibility and be equipped with showers.
FCA confirmed that Pediatrics patient rooms, including the
toilets are sized similarly to Med/Surge patient rooms. FCA
however noted that like Med/Surg patient rooms, Pediatric
patient rooms are not equipped with showers, instead several
patient shower rooms are provided throughout the unit.
The user group agreed to this concept and requested 2 shared
patient showers to be programmed in the Pediatric
Department.
2.08

ICU and Emergency services for Pediatric patients


The user group noted that provisions for pediatric patients in
the ICU and Emergency Departments need to be provided.
The user group noted that in the Pediatric Department certain
high acuity pediatric patients require direct visual monitoring.
To increase nurse efficiency FCA proposed to provide a
sliding door between 2 Pediatric patient rooms to allow for
Page 4 of 6

Due Date

Item

Description

Action

the visual monitoring of two patients by a single nurse. The


user group agreed to this approach.
2.09

Isolation
FCA noted that currently 25% of the Med/Surg patient rooms
are isolation rooms and inquired if the Ob/Peds departments
would want the same isolation room ratio.
The user group confirmed the following isolation room
distribution:
Obstetrics

2 Post Partum Isolation patient rooms


1 LDPR isolation room
Pediatrics

2 Isolation patient room


2.10

Anesthesia Workroom
The user group requested one 120 sf Anesthesia/Respiratory
workroom and one adjacent 300 sf storage room.
FCA to review the impacts the additional space will have on
the program.

2.11

Equipment Storage
Pediatrics

The user group noted that more space is required for


equipment storage room in Pediatrics, since this is a major
shortcoming in the current department. The user group
requested the Equipment storage to increase to 300 sf.
FCA to review the impacts the additional space will have on
the program.
NICU

The user group requested the NICU storage room to be


increased to 400 sf and requested a separate 100 sf storage
room for Respiratory Therapy.
FCA to review the impacts the additional space will have on
the program.
2.12

Lockers
KJ noted that a policy needs to be established by the hospital
and should be applied to all departments.
The user group would be agreeable to a concept of providing
small personalized lockers for personal belongings and shared
day-use lockers for coats and larger items.
Page 5 of 6

Due Date

Item

Description

Action

Due Date

The user group also suggested that if necessary additional


lockers could be provided in the existing hospital.
The user group pointed out that the majority of nursing staff
are female and agreed to the idea of having unisex locker
rooms with separate adjacent changing rooms.
2.13

Social Worker Office


The user group confirmed that only one 150 sf social worker
office be provided in the Pediatric department to service
OB/Peds Departments.

2.14

On-Call Rooms
The user group revised the number of on-call rooms as
follows:

2 On-call rooms for Peds


3 On-call rooms for OB
1 On-call room for Medical Nurse
1 On-call room for Family Attending
1 On-call room for Anesthesiologist

FCA to review the impacts the additional space will have on


the program.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Obstetrics - Pediatrics - Nursery\MIN.02_ObGynPed.doc

Page 6 of 6

`.
MINUTES OF ANCILLARY-CLINICAL LAB MEETING NO. 1
PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Cafeteria Conference Room 3

MEETING
DATE:

January 10, 2007


3:00 pm : 4:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Eberhard Fiebig (EF)
Chiu
Lin
Tse-Chan
(CLTC)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH, Clinical Labs
Fong & Chan Architects (FCA)
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Ancillary-Clinical Lab User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Space Programming Objectives and Assumptions, dated November, 2006
2. Project Schedule dated November 20, 2006
3. Preliminary Detail Space Program, dated January 10, 2007
4. Preliminary Summary Space Program, dated January 10, 2007
5. New Hospital Space Program, dated January 10, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

ITEMS DISCUSSED:

Item

Description

Action

Due Date

NEW BUSINESS:
B.

DEPARTMENTAL ISSUES

1.01

Clinical Lab Location


The user group confirmed that the Clinical Lab Department
will remain in the existing hospital building with the exception
of the Blood Bank and any other space required by code to be
located in a compliant acute care hospital .

1.02

Space Program
FCA proposed the following spaces to be included in the
space program:

Blood Bank 1200 sf


Urinalysis Lab 150 sf
Office Senior Supervisor 100 sf
Office Supervisor 100 sf

The user group agreed to the proposed space program


revisions and added that the Blood Bank should be located in
close proximity to the Resuscitation rooms and the Operating
Rooms to facilitate the immediate delivery of blood supplies.
The user group also requested the Blood Bank to have direct
access to a shipping and receiving area to facilitate the
distribution of blood products.
1.03

Point of Care Testing (POCT)


The user group requested a 80 sf POCT room with a sink,
bench space, storage for supplies and a location for a specimen
refrigerator in the Emergency Department.

1.04

Pneumatic Tube System


The user group requested a 6 pneumatic tube system be
provided with a direct connection to the Emergency
Department.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Ancillary - Auxiliary\MIN.01_Ancillary-Clinical Lab.doc
Page 2 of 2

`.
MINUTES OF ANCILLARY- PHARMACY MEETING NO. 1
PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Cafeteria Conference Room 3

MEETING
DATE:

January 10, 2007


2:00 pm : 3:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Sharon Kotabe (SK)
Paul Cho (PC)
Shirley Lee (SL)
Julie Russel (JR)
Fred Hom (FH)
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH, Pharmacy
SFGH, Materials Management/Purchasing
SFGH, Pharmacy
SFGH, Pharmacy
SFGH, Pharmacy
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Ancillary-Pharmacy User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Space Programming Objectives and Assumptions, dated November, 2006
2. Project Schedule dated November 20, 2006
3. Preliminary Detail Space Program, dated January 10, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

4. Preliminary Summary Space Program, dated January 10, 2007


5. New Hospital Space Program, dated January 10, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
B.

DEPARTMENTAL ISSUES

1.01

Pharmacy Location
The user group confirmed that the Pharmacy Department will
remain in the existing hospital building with the exception of
the Inpatient Pharmacy and any other space required by code
to be located in a compliant acute care hospital.
The user group confirmed that the Inpatient Pharmacy does
not require to be adjacent to any specific department.

1.02

Satellite Pharmacy
The user group requested a Satellite Pharmacy in the
following departments:
Emergency Department (400 sf)
Operating Rooms (300 sf)
ICU (300 sf)

1.04

Shipment and Receiving Area


The user group requested that a shipment and receiving area
be provided in the new hospital building, principally to
accommodate smaller pharmaceutical deliveries.
KJ agreed that a shipment and receiving area will be required
as using the main public entrance for deliveries would not be
acceptable.
NL acknowledged that a shipment and receiving area would
be advantageous and would identify possible locations in the
new hospital building.

1.05

Receiving Logistics
The user group agreed to receive and unpack most pharmacy
deliveries in the existing hospital building and use the tunnel
and elevator connections for distribution of goods to supply
the inpatient and satellite pharmacies.

Page 2 of 4

Due Date

Item

Description

1.06

Pharmacy Equipment

Action

Robotic Processing
Chiu Lin Tse-Chan (CLTC) of FCA recommended to consider
robotic processing equipment for the new inpatient pharmacy
because it saves space and reduces human errors. It has
become the current trend in pharmacy design.
PD also noted that storage capacity can be improved by using
vertical storage systems.
Compounders
The user group requested the inpatient pharmacy area to be
able to accommodate 2 compounders.
Automated Dispensing
The user group confirmed that the automated pharmacy
dispensing system (Sure-Med) cannot be located in the nurse
stations because licensing requires dispensers to be located in
a lockable room.
Subsequent to the meeting during a pharmacy walk- through
(1/23/07) FH and SK requested the impatient pharmacy to be
able to accommodate 2 automated carrousel dispensing
machines.
1.08

Dispensary
The user group requested the Reviewing and Recording room
to accommodate 6-8 workstations (40 sf each).
Each workstation should consist of a countertop work surface
large enough to accommodate a computer, a fax and a
scanner.

1.09

Medication Room
The user group requested one medication room per nursing
unit and 2 medication rooms for each 36-bed Med/Surg
Nursing Unit (120 sf each).

1.10

Narcotics Vault
The user group requested the area assign to Narcotics Vault to
increase to 150 sf.

1.11

Staff Lounge
The user group requested a staff lounge in the inpatient
pharmacy.
NL confirmed that currently a 200 sf staff lounge has been
programmed. The user group agreed to the proposed staff
lounge size.

Page 3 of 4

Due Date

Item

Description

Action

1.12

Lockers
The user group confirmed that lockers for inpatient pharmacy
staff can remain in the existing hospital.

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\Minutes_06.12.01_Medical - Surgical.doc

Page 4 of 4

ICU / STEP-DOWN NO. 2

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 12, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

February 12, 2007

ATTENDEES:

Kathy Jung (KJ)


Andre Campbell
Sue Carlisle
Lisa Chen
Sue Currin
Terry Dentoni
Leslie Dubbin
Genevieve Farr
Cheryl Jay
Paul Koo
John Luce
Sandy Peterson
Shirley Stiver
Ron Alameida
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to initiate the programming effort with the ICU / Step-down User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 12, 2007
3. Preliminary Summary Space Program, dated January 12, 2007
4. New Hospital Space Program, dated January 12, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

BUILDING ISSUES

2.01

Building Bulk - Clearances & Height


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that in order to address planning and
exterior wall fire rating concerns specific distances to the
existing buildings need to be kept on all levels.
The distance at the first and second floor levels between the
existing and new hospital building is 25. The distance
between the new hospital building and the adjacent brick
buildings 20 and 30 is 40.
The floors above the second floor have additional setbacks
to address planning concerns and to eliminate the need to
have fire rated walls and windows along the east facade.
The distance at the basement 1 and 2 to the existing hospital
building is 14 and to the adjacent brick buildings 20 and 30
is 12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the designated
site. It does not represent any design features. The final
layout, building and faade design are to be determined in
the subsequent design phases.

B.

PROGRAMM ISSUES

2.02

Number of ICU and Step-Down Beds


NL reviewed the total number and distribution of ICU and
Page 2 of 4

Due Date

Item

Description

Action

Step/down beds based on the previous meeting:


Fourth Floor:

3 ICU units (10 beds each)


1 Trauma ICU unit (10 beds)
1 Step-down unit flex up (10 beds)
Fifth Floor:

1 Step-down unit flex down (36 beds)


The user group noted that the presented number of ICU and
Step-down beds will not be sufficient to meet the future
needs of the hospital.
After discussing several different options the user group
agreed to the following number and distribution of ICU and
Step-down beds:
Third Floor:

1 Step-down unit flex up (10 beds)


1 Step-down unit flex down (26 beds)
Fourth Floor:

3 ICU units (10 beds each)


1 Trauma ICU unit (10 beds)
1 Step-down unit flex up (10 beds)
Fifth Floor:

Med/Surg units only


The user group acknowledged that the hospital needs to
examine whether financial resources would be available to
operate 86 ICU and Step/ down beds.
2.03

Procedure Rooms
Paulo Diaz (PD) of FCA asked if a procedure room is
required in the ICU floor.
The user group confirmed that a dedicated procedure room
is not required because procedures can be performed in the
proposed 270 sf Trauma patient rooms.
The user group however requested one Trauma patient room
to be equipped with wall led protection to accommodate
fluoroscopic procedures.

2.04

Showers
The user group confirmed that showers are not required in
the ICU patient rooms.

2.05

Waiting Room
Given the potential for rival gang members to be in the ICU
Page 3 of 4

Due Date

Item

Description

Action

Due Date

and Step-down floors at the same time, the user group


requested two separate waiting rooms to be programmed in
each floor.
The user group also suggested to provide glass windows in
the waiting rooms to provide for greater transparency and
improve security.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\ICU - Step-Down\MIN.02_ICU-Step-Down.doc

Page 4 of 4

MINUTES OF DIAGNOSTIC MEETING NO. 2

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 16, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

February 15, 2007

ATTENDEES:

Kathy Jung (KJ)


Sue Carlisle
Mary Clancy
Pierre-Alaine Cohen
Terry Dentoni
Doug Eckman
Genevieve Farr
Eberhard Fiebig
Walt Finkbeiner
Rafael Ibarra
Roland Pickens
Hal Yee
Ronald Alameida
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
DPW
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Diagnostic User Group. The
following is a record of the items discussed.

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

FCA presented and discussed the following attached documents:


1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 16, 2007
3. Preliminary Summary Space Program, dated January 16, 2007
4. New Hospital Space Program, dated January 16, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

BUILDING ISSUES

2.01

Building Bulk - Clearances & Height


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that in order to address planning and
exterior wall fire rating concerns specific distances to the
existing buildings need to be kept on all levels.
The distance at the first and second floor levels between the
existing and new hospital building is 25. The distance
between the new hospital building and the adjacent brick
buildings 20 and 30 is 40.
The floors above the second floor have additional setbacks to
address planning concerns and to eliminate the need to have
fire rated walls and windows along the east facade.
The distance at the basement 1 and 2 to the existing hospital
building is 14 and to the adjacent brick buildings 20 and 30 is
12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the designated
site. It does not represent any design features. The final layout,
building and faade design are to be determined in the
subsequent design phases.

Page 2 of 5

Due Date

Item

Description

Action

2.02

Building Connections
NL confirmed the program currently assumes the following
three connections between the existing and new Hospital
buildings:
Tunnel connection at the basement level
Street connection at the 1st floor
Bridge connection at the 2nd floor

B.

PROGRAM ISSUES

2.03

Gastroenterology
NL noted that currently the programming assumption is for the
Gastroenterology department to remain in the existing
Hospital building. NL explained that endoscopic procedures in
the new Hospital could be performed in patient rooms on the
ICU/ Step-down floors and in procedure rooms in the
Med/Surg floors. Additional storage space for equipment has
also been programmed in the ICU/ Step-down and Med./Surg
floors.
The user group agreed with this approach, however stated that
the Gastroenterology department in the existing Hospital
would also require to be modernized and expanded.
KJ emphasized that funds from the upcoming bond measure
could only be used for work related to the new Hospital.
Funds to modernize and/or expand departments in the existing
Hospital would have to come from a different source. KJ
reiterated that the programming effort should not assume
funding to modernize and/or expand departments in the
existing Hospital will be available.
The user group commented that a lack of guaranteed funding
warrants a reassessment of the current approach.
Subsequent to the meeting the Perioperative user group
confirmed that while the Gastroenterology department could
remain in the existing Hospital an Endoscopy Suite with the
following spaces should be included in the new Hospital
Program:

2.04

4 Endoscopy Procedure Rooms


1 ECRP Room
1 Monitoring Room
Required Ancillary Space
10 patient intake and recovery beds

Percentage of Inpatient procedures in the GI Unit


CLTC noted that if the percentage of inpatient procedures in
the GI unit is less than 20%, then these services could remain
in the existing Hospital. The user group agreed to verify this
Page 3 of 5

Due Date

Item

Description

Action

information.
Subsequent to the meeting the Mr. Hal Yee confirmed in an
email that the percentage of inpatient procedures performed
in the GI unit is predicated to be less than 20%.
2.05

Emergency Evacuation
The user group expressed some concerns with the proposed 4th
& 3rd floor locations of the ICU/ Step-down units. The user
group commented that in the event patients require to be
evacuated following a major catastrophe and elevators are
decommissioned, hospital staff would have to physically
transport these patients down several flights of stairs. The user
group predicted that this scenario would result in a high
number of a patient casualties.
Subsequent to the meeting, this issue was raised with the
Steering Committee and the consensus was that from an
operational standpoint it was important to locate the
Emergency Department at grade level and given the limited
footprint of the building it would not be possible to collocate
two large departments on the same floor. The Steering
committee also noted that an emergency evacuation
procedure plan would have to be developed since
transporting patients in the ICU and Step-down floors and
perhaps certain Med/Surg patients down several flights of
stairs would not be a viable option.

2.06

Size of Imaging Rooms


NL reviewed the following imaging room sizes with the user
group.

Radiology X-ray Rooms


CT Scan Rooms
MRI Room
IR
with 2 adjacent storage rooms each
Angiography Room
Ultrasound Room
Cath Lab Room
Cath Lab Control Room

250 sf
450 sf
520 sf
600 sf
60 sf
500 sf
150 sf
500 sf
150 sf

The user group took no exceptions.


2.07

Cardiology
The user group requested a point of care testing area within
the Cardiology department. The point of care testing area
should include a workbench with a sink and some storage
space.

Page 4 of 5

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Diagnostic\MIN.02_Diagnostic.doc

Page 5 of 5

MINUTES OF STEERING MEETING NO. 1


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 18, 2007


12:00 pm : 2:00 pm

ISSUE DATE:

February 28, 2007

ATTENDEES:

Kathy Jung (KJ)


Ronald Alameida
Andre Campbell
Sue Carlisle
Jeff Critchfield
Sue Currin
Gene OConnell
Delvecchio Finley
Sharon Kotabe
John Hurley
John Luce
Roland Pickens
Mark Primeau
Carlos Villalva
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
Bureau of Architecture, Project Manager
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to present, discuss and validate the space programming process for the new

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

hospital building at San Francisco General Hospital Medical Campus. The following is the list of
items to be discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Hospital Comparison Chart, dated January 18, 2007
3. Preliminary Summary Space Program, dated January 18, 2007
4. New Hospital Space Program, dated January 18, 2007

ITEMS DISCUSSED:

Item

Description

NEW
BUSINESS:
A.

BUILDING ISSUES
1.01

Actio
n

Clearances to Existing Buildings


Nuno Lopes (NL) of FCA introduced the bulk of the
new building and noted that in order to address planning
and exterior wall fire rating concerns specific distances
to the existing buildings need to be kept on all levels.
The distance at the first and second floor levels between
the existing and new hospital building is 25. The
distance between the new hospital building and the
adjacent brick buildings 20 and 30 is 40.
The floors above the second floor have additional
setbacks to address planning concerns and to eliminate
the need to have fire rated walls and windows along the
east facade.
The distance at the basement 1 and 2 to the existing
hospital building is 14 and to the adjacent brick
buildings 20 and 30 is 12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the
designated site. It does not represent any design features.
The final layout, building and faade design are to be
determined in subsequent design phases.

1.02

Bulk
Dr. Andre Campbell (AC) questioned the need to reduce
available floor area on the upper levels.
Page 2 of 6

Due
Date

Item

Description

Actio
n

FCA responded that the San Francisco Planning


Department would likely not approve a building where
the maximum floor area is maintained on every floor,
such building would be considered bulky. FCA assumed
a 15% reduction of the maximum floor area on the upper
floors to address this concern, however this is still well
short of the prescribed Planning Department bulk
requirements, which would require an 80% reduction.
The user group agreed to the proposed floor area
reduction in the upper floors.
1.03

Building Cost
KJ explained that the $622 Million probable
construction cost estimate in the Site Feasibility study is
for a 230 bed 385,000 sf hospital building, however the
consensus was that additional beds would be required.
NL noted that after meeting with all the user groups the
total number of beds has increased to 284 beds and the
new hospital square footage has increase to 405,000 sf.
NL noted that even though the total number of beds has
increased by 23% the overall square footage of the
building has only increased by 5%. This is due in part
with our initial assumption to reduce the spacing of each
column bay from 29x 29 to 26x 29, to note each
column bay can accommodate 2 patient rooms. This
adjustment resulted in the addition of an entire row of
column bays without increasing the size of the building.
CLTC also explained that using code concepts such as
horizontal exits and suites the net to gross ratio could be
further reduced, resulting in a more compact and
efficient building.
CLTC concluded that since the overall square footage of
the building has only increased by 5%, and since healthy
cost contingencies were assumed in the probable
construction cost estimate, the overall project cost
should not substantially increase.

1.04

Bridge Connection
NL noted that in the space program the following floors
in the existing and new hospital buildings are assumed
to be connected:
Basement Floor - Tunnel connection
1st floor - Street level connection
2nd floor - Bridge connection
KJ noted that the Ob/Peds/NICU departments have
Page 3 of 6

Due
Date

Item

Description

Actio
n

expressed concerns with the proposed second floor


bridge connection.
They are concerned that the
additional pedestrian traffic induced by the bridge
connection will make Ob/ NICU less secure.
The user group suggested examining the possibility of
relocating Ob/Peds/NICU departments to another floor
or relocating the bridge to another floor. FCA to
investigate.
Subsequent to this meeting the Women & Children
user group agreed that the preferred solution was to
keep both the Ob/Peds/NICU departments and the
bridge connection on the second floor provided a
layout with a dedicated pathway from the elevator core
to the bridge connection and a single point of entry
into these departments could be devised.
1.05

Loading Dock
The lack of a loading dock in the new hospital building
was discussed. The user group agreed that due to site
constraints an appropriately sized loading dock for the
new hospital would not be possible.
The user group concluded that the existing loading dock
could be used to facilitate the movement of materials for
both existing and new hospital buildings.
FCA noted that the Auxiliary user group requested at a
minimum a small loading dock be provided to facilitate
the movement of blood into the Blood Bank and
cadavers from the Morgue. The user group requested
FCA to review site conditions and to propose locations
where a small loading dock could be incorporated into
the building design.
DEPARTMENTAL ISSUES

B.
1.06

Distribution of Patient Beds


FCA presented the following patient bed distribution:
6th Floor 5th Floor 4th Floor -

2 x 36 bed unit - Med/Surg


2 x 36 bed unit - Med/Surg
3 x 10 bed unit - ICU
1 x 10 bed unit - Trauma ICU
1 x 10 bed unit - Step-Down-Flex Up
rd
3 Floor - 1 x 10 bed unit - Step-Down-Flex Up
1 x 26 bed unit - Step-Down-Flex Down
8 bed unit - Med/Surg Forensic
2nd Floor 22 bed unit -Obstetric (excl. 3 Triage
Rooms)
12 bed unit - Pediatric
Page 4 of 6

Due
Date

Item

Description

Actio
n
12 bed unit - NICU

Total of

284 beds

The user group agreed with the proposed quantity and


distribution of patient beds.
1.07

Morgue
NL noted that due to several unresolved operational
concerns the final location of the Morgue has not yet
been determined. Currently the Morgue has been
programmed in Basement 1 in close proximity to the
tunnel connection.
The user group agreed to review this issue internally and
provide FCA with direction in the next user group
meeting.

1.08

Resuscitation Rooms
NL noted that contrary to the existing condition, the
Emergency user group had confirmed that a dedicated xray room for each Resuscitation room was not required.
The user group questioned this approach and requested
this issue be reconfirmed in the next Emergency user
group meeting.
Subsequent to this meeting the Emergency user group
requested X-ray capability in each Resuscitation room
and two X-ray rooms inside the Emergency
Department.

1.09

Patient Rooms
NL noted that in the space program all patient rooms are
assumed to be single handed rooms. FCA explained that
this layout concept has proven to minimize nursing
errors.
NL also noted that in the space program 25% of all
patient rooms are assumed to be true isolation rooms
with an anteroom.
The user group took no exceptions.

1.10

Linen
NL explained that the Auxiliary user group requested
alcoves for clean linen and dedicated rooms for soil
linen.
The user group took no exceptions.

1.11

Dietary
Page 5 of 6

Due
Date

Item

Description

Actio
n

Due
Date

NL explained that in the space program dietary services


are assumed to remain in the existing hospital building,
however a dietary storage room has been programmed in
the new hospital to meet minimum code requirements.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Steering\MIN.01_Steering.doc

Page 6 of 6

MINUTES OF PERI-OPERATIVE MEETING NO. 2

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 19, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

January 20, 2007

ATTENDEES:

Kathy Jung (KJ)


Terry Dentoni
Jim Marks
John Inadomi
Ronald Alameida
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
DPW
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Diagnostic User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 19, 2007
3. Preliminary Summary Space Program, dated January 19, 2007
4. New Hospital Space Program, dated January 19, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

BUILDING ISSUES

2.01

Building Bulk - Clearances & Height


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that in order to address planning and
exterior wall fire rating concerns specific distances to the
existing buildings need to be kept on all levels.
The distance at the first and second floor levels between the
existing and new hospital building is 25. The distance
between the new hospital building and the adjacent brick
buildings 20 and 30 is 40.
The floors above the second floor have additional setbacks to
address planning concerns and to eliminate the need to have
fire rated walls and windows along the east facade.
The distance at the basement 1 and 2 to the existing hospital
building is 14 and to the adjacent brick buildings 20 and 30 is
12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the designated
site. It does not represent any design features. The final layout,
building and faade design are to be determined in the
subsequent design phases.

2.02

Building Connections
NL confirmed the program currently assumes the following
three connections between the existing and new Hospital
buildings:
Tunnel connection at the basement level
Street connection at the 1st floor
Bridge connection at the 2nd floor

B.

PROGRAM ISSUES

2.03

Gastroenterology
NL noted that currently the programming assumption is for the
Gastroenterology department to remain in the existing
Hospital building. NL explained that endoscopic procedures in
the new Hospital could be performed in patient rooms on the
ICU/ Step-down floors and in procedure rooms in the
Page 2 of 4

Due Date

Item

Description

Action

Med/Surg floors. Additional storage space for equipment has


also been programmed in the ICU/ Step-down and Med./Surg
floors.
The user group suggested that the proposed approach may
reduce patient care efficiency and increase operational costs.
The user group also stated that in a prior Diagnostic user
group meeting it was noted that funding to make the necessary
improvements in the existing building to modernize and
expand the GI department may not be available.
Based on the above discussion the user group determined that
while the Gastroenterology department could remain in the
existing Hospital an Endoscopy Suite with the following
spaces should be included in the new Hospital Program:

2.04

4 Endoscopy Procedure Rooms


1 ECRP Room
1 Monitoring Room
Required Ancillary Space
10 patient intake and recovery beds

Patient Intake and Recovery


NL stated the following number of patient holding and
recovery beds currently programmed:
Holding - 24 beds
Recovery - 32 beds (including 1 isolation)
The user group determined that the proposed number of beds
is generous. However the user group highlighted that 10 beds
had been requested to accommodate the Endoscopy suite. In
view of that the user group decided that only 5 additional beds
should be added to the proposed total number of patient
holding and recovery beds.
The number of patient holding and recovery beds were revised
as follows:
Holding - 26 beds
Recovery - 35 beds (including 1 isolation)

2.05

Soiled & Clean Linen/Equipment


The user group noted that space needs to be programmed to
accommodate 2 carts for clean linen supply within each unit.
The user group requested to provide separate rooms for soiled
linen and soiled equipment.
NL noted that detailed information for soiled/clean linen pick
up and delivery areas will be discussed during the next
Material Management user group meeting.
Page 3 of 4

Due Date

Item

Description

2.06

On-Call Sleep Rooms


The user group confirmed the following arrangements for oncall sleep rooms to be within immediate adjacency to the OR:
For Anesthesia:
3 rooms for residents
1 room for faculty
For Surgery:

2.07

Action

Due Date

1 room (final requirements to be


confirmed by the Surgery user group
at next meeting)

Lounge
The user group requested a separate lounge for the anesthesia
staff.
FCA programmed a total of 2 staff lounges, each 300 sf.

2.08

Trauma Waiting Room


Given the potential for rival gang members to be in the
Trauma floor at the same time, the user group requested two
separate waiting rooms to be programmed for security reasons.
The user group also suggested to provide glass windows in the
waiting rooms to provide for greater transparency and
improved security.

2.09

Morgue
NL noted that due to several unresolved operational concerns
the final location of the Morgue has not yet been determined.
Currently the Morgue has been located on the ground floor in
close proximity to the tunnel connection.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Perioperative\MIN.02_Perioperative.doc

Page 4 of 4

MINUTES OF EMERGENCY MEETING NO. 2

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

January 23, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

February 23, 2007

ATTENDEES:

Kathy Jung (KJ)


Pat Carr (PC)
Kathryn Fowler KF)
Alan Gelb (AG)
Eric Isaacs (EI)
Bob Sypher (BS)
April Clock (AC)
Ron Alameida (RA)
Chiu
Lin
Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
DPW
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Diagnostic User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 23, 2007
3. Preliminary Summary Space Program, dated January 23, 2007
4. New Hospital Space Program, dated January 23, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

BUILDING ISSUES

2.01

Building Bulk - Clearances & Height


Nuno Lopes (NL) of FCA introduced the bulk of the new
building and noted that in order to address planning and
exterior wall fire rating concerns specific distances to the
existing buildings need to be kept on all levels.
The distance at the first and second floor levels between the
existing and new hospital building is 25. The distance
between the new hospital building and the adjacent brick
buildings 20 and 30 is 40.
The floors above the second floor have additional setbacks to
address planning concerns and to eliminate the need to have
fire rated walls and windows along the east facade.
The distance at the basement 1 and 2 to the existing hospital
building is 14 and to the adjacent brick buildings 20 and 30 is
12.
NL emphasized that the bulk study is only an exercise to
examine the maximum mass possible within the designated
site. It does not represent any design features. The final layout,
building and faade design are to be determined in the
subsequent design phases.

B.

PROGRAM ISSUES

2.02

Program Assumptions
NL clarified that initial program assumption have been
derived from SFGHMC current and past census figures,
previous SFGHMC commissioned studies and comparative
data from other hospitals.
The user group explained that this past year the Emergency
Page 2 of 4

Due Date

Item

Description

Action

Department has experienced higher than usual census and


believed this trend will continue in subsequent years. The User
group also noted that a needs assessment study would be
helpful in determining the size of the Emergency Department
in relation to other Hospital services.
PD noted that needs assessment studies are typically
performed during the Design Development phase where
program and building information is more reliable and can
take up to 6-9 months to complete. Currently a needs
assessment study is not being considered during the
programming phase.
The user group agreed to clarify the goals, requirements and
operational issues for the Emergency department in an internal
meeting and provide FCA with updated information at the
next user group meeting.
C.

DEPARTMENTAL ISSUES

2.03

Exam Rooms
NL presented the following distribution of exam rooms:
27 Exam Rooms
3 Isolation Exam Room
1 Semi Private Room with 10 beds
The user group agreed with the following exam room
distribution however theyve request that one of the exam
rooms be designated as a SART exam room. The SART Exam
room should be sized to accommodate all required equipment
and have a dedicated toilet with a shower.

2.04

Urgent Care
KJ confirmed that Urgent Care is remaining in the existing
hospital.

2.05

X-ray Rooms
The user group requested X-ray capability in each
Resuscitation room and two X-ray rooms inside the
Emergency Department.

2.06

Meeting Rooms
NL confirmed the following number of meeting rooms:
3 Consultation/ Quiet Rooms
2 Conference Rooms
The user group requested a space capable of accommodating
20 staff members for patient rounds. NL proposed to locate the
two conference rooms next to each other separated by a
movable partition that can be opened to provide 400 sf of
Page 3 of 4

Due Date

Item

Description

Action

Due Date

space. The user group agreed to this proposal.


2.07

Resuscitation Rooms
The user group requested the Resuscitation rooms to be
located near the ambulance entrance and service elevators.

2.08

CT Scan Rooms
The user group requested the CT Scan rooms to be located
adjacent to the Resuscitation rooms with access from the
corridors as well as from a Resuscitation room.

2.09

Pediatric Emergency
The user group discussed the need for a dedicated Pediatric
Emergency area with a separate waiting area. A final
conclusion was not made.

2.10

Toilets
The user group requested additional toilets in the Emergency
Department. The user group agreed to the following
distribution:
6 private patient toilets (incl. 2 ADA)
2 private ADA staff toilets
2 multi-accommodation public toilets (3 fixtures each)
NL noted that in addition staff toilets have been programmed
in the staff locker area.

2.11

Social Worker Office


The user group requested one social worker office to be shared
by two social workers.
FCA added one 150 sf social worker office.

2.12

Security
The user group confirmed that security does not need a
dedicated enclosed space inside the Emergency department. A
visible workstation near the emergency entrance is preferred.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Emergency\MIN.02_ Emergency.doc

Page 4 of 4

MINUTES OF AUXILLARY-SUPPORT MEETING NO. 1


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Cafeteria Conference Room 3A, Surgery

MEETING
DATE:

January 26, 2007


300 pm : 400 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


James Moore
Bob Eggleston
Delvecchio Finley
Johnson Gong
Marijane Pierson
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH Messenger/Mailroom/Laundry
SFGH Food Services
SFGH - Support Services
SFGH - Environmental Services
SFGH - Material Management
Fong & Chan Architects (FCA)
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Ancillary-Sterile Processing User
Group. The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 26, 2007
3. Preliminary Summary Space Program, dated January 26, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

4. New Hospital Space Program, dated January 26, 2007


ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
B.

DEPARTMENTAL ISSUES

2.01

Messenger/Mail Services
The user group noted that Messenger services should be
located in the new acute care hospital building since most of
their work is related to inpatients services. They also added
that since Mail services is staffed by the same personnel as
Messenger services Mail services should also be located in the
new acute care hospital.
FCA revised the space program to include the following
spaces:
Supervisor Office
@ 100 sf
Open Space Office
@ 600 sf
(12 workstations and 12 half height lockers)
Womens Toilet
@ 50 sf
Mens Toilet
@ 50 sf
Changing room
@ 40 sf
Specimen Storage
@ 80 sf
(incl. 2 commercial grade refrigerators)
Storage Area
@ 350 sf
(10 gurneys and 10 wheelchairs)
Clothes Storage
@ 300 sf
Mailroom
@ 200 sf

2.02

Material Management
The Receiving and Administrative areas were discussed. The
user group noted that since the main loading dock will remain
in the existing hospital the Receiving and Administrative areas
should also remain in the existing hospital.
The user group did request to increase the material
management Storage area in the new acute care hospital from
5000 sf to 6000 sf .

2.03

Dietary
NL explained that dry and refrigerated storage space for
emergency supplies is required by code to be included in the
new acute care hospital.
The user group acknowledged this code requirement however
confirmed that the supervisors office included in the Dietary
storage area is not required.
Page 2 of 4

Due Date

Item

Description

Action

2.05

Custodian Closets
The user group commented that based on the programmed
area in general two 40 sf custodian closets on each floor would
be required.
The user group agreed to the following custodian closet
arrangement for each department:
Med/Surg

4 closets @ 40 sf. (2 per floor)


Med/Surg - Forensic

1 closet @ 40 sf.
ICU

2 closets @ 50 sf (to accommodate a total of 5 carts, one


per ICU unit)
OB/GYN

1 closet @ 50 sf
Peds

1 closet @ 40 sf.
NICU

1 closet @ 40 sf.
Surgery

3 closet @ 40 sf.
Gastroenterology

1 closet @ 40 sf.
Pre-Op

1 closet @ 40 sf.
PACU

1 closet @ 40 sf.
Emergency

3 closets @ 40 sf.
2.06

Linen
The user group noted that in general one 30 sf alcove for a
clean linen cart and one 60 sf room for two soiled linen carts is
required for each inpatient unit.
The user group also commented that the Emergency
Department needs three soiled linen rooms.

Page 3 of 4

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Ancillary - Auxiliary\MIN.01_Auxillary Support.doc

Page 4 of 4

MINUTES OF ANCILLARY- STERILE PROCESSING MEETING NO. 1


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Cafeteria Conference Room 3A, Surgery

MEETING
DATE:

January 26, 2007


2:00 pm : 3:00 pm

ISSUE DATE:

May 25 2007

ATTENDEES:

Kathy Jung (KJ)


Cora Nunez-Talens
Lawrence Nichols
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Ancillary-Sterile Processing User
Group. The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated January 26, 2007
3. Preliminary Summary Space Program, dated January 26, 2007
4. New Hospital Space Program, dated January 26, 2007
ITEMS DISCUSSED:

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

Item

Description

Action

NEW BUSINESS:
B.

DEPARTMENTAL ISSUES

2.01

Sterile Processing
FCA proposed to locate the entire Sterile Processing (SP)
in the new acute care hospital. SP would sterilize all
equipment for both existing and new hospitals and
distribute sterile equipment directly to the ORs.
The user group concurred with the proposed arrangement,
noting that the current breakdown of SP services to the
various departments is as follows:
5% Clinics (existing hospital)
5% ER (new acute care hospital)
70% OR (new acute care hospital)
20% Labor & Delivery (new acute care hospital)
The user group also noted that operating and maintaining
two separate SPs would be inefficient and costly.

2.02

Central Processing and Distribution


FCA suggested keeping most of Central Processing and
Distribution (CPD) in the existing hospital and only
included approximately 5,000 sf of storage in the new
acute care hospital. CPD would be responsible for the
distribution of supplies and sterile equipment for both
existing and new hospital with the exception of sterile
equipment to the ORs, which would be managed by SP.
The user group agreed to the proposed arrangement,
however suggested increasing the Material Management
storage in the new acute care hospital from 5,000 sf to
6,000 sf.

2.03

Dumbwaiter
FCA proposed locating SP directly below the ORs and to
receive and distribute clean and soiled equipment by way of
dumbwaiters.
The user group agreed to this arrangement however
requested that in addition to providing separate clean and
soiled dumbwaiters a third dumbwaiter should be provided
as backup.

2.04

Decontamination room
The user group requested a Decontamination room to be
included in the OR suite off the peripheral corridor (patient
corridor). The soiled dumbwaiter should be located in the
Decontamination room.
Page 2 of 3

Due Date

Item

Description

Action

2.05

Soiled Cart Staging Area


The user group noted that the soiled staging area should be
large enough to accommodate a total of 18 carts. Assuming
each cart is approximately 48x30 the Soiled Cart Staging
Area should be increased to 200 sf.

2.06

Decontamination Area
The user group requested a toilet with shower to be included
inside the Decontamination Area.

2.07

Sterile Supply
The user group requested to increase Sterile Supply from
250 sf to 400 sf.

2.08

Offices
FCA included in the space program three offices. An office
for a supervisor to be located in the Assembly/Sterilization
Area and two additional offices in the Administration and
Staff Areas.

Due Date

The user group requested to locate the office for the


supervisor in the Administrative and Staff Areas and to only
provide one additional office for a manager.
FCA to revise the space program to include two offices one
for a manager and one for a supervisor in the Administrative
and Staff Areas.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Ancillary - Support\MIN.02_Ancillary-Sterile Proc..doc

Page 3 of 3

MINUTES OF MEDICAL/ SURGICAL MEETING NO. 3

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 6, 2007
2:00 pm : 4:00 pm

ISSUE DATE:

February xxx, 2007

ATTENDEES:

Kathy Jung (KJ)


Ronald Alameida
Todd May
Susan Sniderman
Sue Carlisle
Morris Schambelan
Edgar Pierluissi
Yuhum Digdigan
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
Bureau of Architecture, Project Manager
SFGH - Family Medicine
SFGH - Pediatrics
SFGH - Deans Office
SFGH
SFGH
SFGH - Nursing Admin
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to review the programming effort with the Medical/ Surgical User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

2. Preliminary Detail Space Program, dated February 6, 2007


3. Preliminary Summary Space Program, dated February 6, 2007
4. New Hospital Space Program, dated February 6, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

3.01

Patient Room Size Validation


FCA presented several images of a three dimensional
computer model and floor plans of a possible Med/Surg
patient room to confirm that the proposed 180 Assignable
Square Footage (ASF) was adequate.
The user group commented that the size of the exterior
window should be maximized but agree that the proposed 180
ASF for the Med/Surg patient room was adequate.

3.02

Same-Hand Room Designs for Private Patient Rooms


The user group agreed that same-hand room designs for all
private Med/Surg patient rooms should be assumed in the
space program report.
CLTC noted same-hand room designs will increasing material
and installation costs since unlike mirror-reverse patient room
designs the plumbing chase and oxygen and gas drops cannot
be shared.
The user group noted that if conclusive evidence supports the
argument that same-hand room designs are safer than mirror
room designs the additional costs are justified.

3.03

Charting Work Areas


The user group discussed the benefits of charting inside
patient rooms vs. in the corridor.
The user group agreed that creating a charting work area
inside each patient room was beneficial in fostering better
communications between patient and nurse/physician.
However the user group agree that charting inside the room is
not always beneficial and requested that in each unit three
charting work areas be programmed in the corridor.

Page 2 of 4

Due Date

Item

Description

Action

3.04

Nursing Station
Instead of programming a centralized nursing station, the user
group suggested to split the nursing station into nursing pods
to improve workflow.
FCA noted that a primary nursing station is required by code,
but stated that currently two additional auxiliary nursing
station have been programmed. The user group agreed to this
arrangement.

3.05

Nursing Lounge
The size of the nursing lounge was discussed. The user
group requested one 200 sf staff lounge per floor to serve
two Med/Surg units.

3.06

Meeting Rooms
The user group noted that during morning rounds, 7 teams
approximately 6-8 members each would require a private
space to meet on each floor.
FCA noted that currently 12 meeting rooms in total on 2
floors have been programmed.
The user group acknowledged that the number of meeting
rooms currently programmed is an improvement to the
current existing condition and requested that these meeting
rooms not be eliminated.

3.07

Forensic Beds
NL confirmed that Forensic Med/Surg patients are required
to be treated in a compliant acute care hospital.
The user group discussed whether it would be more efficient
to treat forensic patients in the Med/Surg units rather than
creating a dedicated Forensic Med/Surg unit.
KJ noted that this concept would require security guards to
monitor each forensic patient outside their room, which
during high census would significantly increased the total
number of security guards required. KJ commented that this
concept needs to be discussed with the sheriffs department.

3.08

Public Toilets in Waiting Rooms


The user group noted that the existing lockable single
accommodation public toilets in waiting rooms have
encouraged drug and other inappropriate use and requested
multi-accommodation public toilets be provided in all
waiting rooms.

Page 3 of 4

Due Date

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Medical-Surgical\MIN.03_MedSurg.doc

Page 4 of 4

MINUTES OF OBSTETRIC/ PEDIATRIC MEETING NO. 3


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 9, 2007
2:00 pm : 4:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Cathy Duran
Alma Martinez
Colin Partridge
Susan Sniderman
Elisabeth Romero
Ronald Alameida
Eleanor Drey
Abner Korn
Cathryn Thurow
Fe Hortinela
Louise Dimattio
Bill Tausch
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

FCA presented and discussed the following attached documents:


1. Agenda of Meeting
2. Preliminary Detail Space Program, dated February 9, 2007
3. Preliminary Summary Space Program, dated February 9, 2007
4. New Hospital Space Program, dated February 9, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

3.01

Patient Room Size Validation


FCA presented several images of three dimensional computer
models and floor plans of possible LDRP and Postpartum
patient rooms to confirm that the proposed Assignable Square
Footages (ASF) were adequate. The following room sizes
were depicted in the images presented.
LDRP patient room 290sf
Postpartum patient room 180sf

The user group agreed to the proposed patient room sizes.


3.02

NICU Bassinets
The user group noted that in 2006 the average daily census for
NICU was between 7-11. They also commented that in 2006 a
total of ten days the daily census for NICU was between 1517.
Based on this information the user group requested to increase
the NICU area to accommodate 5 additional bassinets, with
the following distribution:
10 Level II bassinets
6 Level III bassinets
1 Level III isolation bassinet
Medication Room

A Medication room was requested and added to the NICU.


Mother Boarding Room

The user group noted that a sink with counter will be required
for the Mother boarding room. FCA acknowledged the
Page 2 of 4

Due Date

Item

Description

Action

requirements in the program.


Showers

Showers for the NICU were requested and added to the on-call
sleep rooms, family sleep room and the mother boarding
room.
3.02

Provider Workroom/Charting
The user group requested to increase
Workroom/Charting in the NICU to 200 sf.

the

Provider

3.02

Medication Room
The user group requested to add a 120 sf Medication room in
the NICU.

3.02

Mother Boarding Room


The user group requested a counter with sink to be included in
the Mother Boarding room.

3.02

Toilet Room Showers


The user group requested the following Toilet rooms to be
equipped with showers:

At least one On-call room Toilet per department


Toilet in Family Sleep room
Toilet in Mother Boarding room

3.03

Alcove for Resuscitation Equipment in LDRP


The user group requested an alcove to accommodate
resuscitation equipment within the LDPR patient rooms.

3.04

Adjacency Requirement between LDRP and C-Section


The user group requested LDPR rooms to be located in close
proximity to C-Section operating rooms to insure immediate
patient transfer during emergencies.

3.04

Lactation Room
The user group noted that the Lactation room currently
programmed is not required and can be eliminated.

3.06

Conference Rooms
The user group noted that the proposed 200 sf conference
rooms for Pediatrics and NICU are too small to
accommodate large gatherings.
FCA suggested combining both the Pediatrics and NICU
Conference rooms into one large 400 sf Conference room
separated by a movable room divider. This arrangement can
accommodate large gatherings and preserve the same
number of meeting spaces.
The user group agreed to the above arrangement and
Page 3 of 4

Due Date

Item

Description

Action

Due Date

suggested to also include a movable room divider in the


Obstetric Conference room.
3.07

Lockers
The user group requested to combine separate male and
female Locker rooms into one unisex Locker room with
multiple toilet and changing facilities as indicated below:
1 Unisex Locker room 250 sf
2 multi-accommodation separate male and female Toilet

rooms 180 sf
4 Changing rooms 30 sf

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Obstetrics - Pediatrics\MIN.03_ObPeds.doc

Page 4 of 4

ICU / STEP-DOWN NO. 3

PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 13, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

February xx, 2007

ATTENDEES:

Kathy Jung (KJ)


Andre Campbell
Cheryl Jay
Sheryl Calrson
Genevieve Farr
Terry Dentoni
Vivian Curd
Charlotte Bobek
Shirley Stiver
Ron Alameida
Nuno Lopes (NL)
Paolo Diaz (PD)
David Fong (DF)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the ICU / Step-down User Group. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

2. Preliminary Detail Space Program, dated February 13, 2007


3. Preliminary Summary Space Program, dated February 13, 2007
4. New Hospital Space Program, dated February 13, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

3.01

Patient Room Size Validation


FCA presented several images of three dimensional
computer models and floor plans of possible ICU/CCU and
Step-down patient rooms to confirm that the proposed
programmed Assignable Square Footages (ASF) were
adequate. The following room sizes were depicted in the
images presented.

ICU/CCU trauma patient room 280sf


ICU/CCU patient room 210sf
Step-down patient room (flex up) 210sf
Step-down patient room (flex down) 180sf

The user group agreed to the proposed patient room sizes.


3.02

Nourishment/Clean Supply
The user group requested separate Nourishment and Clean
Supply rooms.
FCA proposed programming 50 sf for a Nourishment room
and 120 sf for a Clean Supply room. The user group agreed
to the proposed space allocation.

3.03

On-Call Sleep Rooms


The user group requested 4 private On-call sleep rooms to be
located in the same floor as the ICU units.

3.04

Physical Therapy
The user group confirmed the proposed 150 sf Physical
Therapy room is not required in the ICU floor, instead the
user group requested FCA to program a Medical
Equipment room of equal size.

3.05

PACS Viewing Stations


The user group requested that all patient care units be
Page 2 of 3

Due Date

Item

Description

Action

Due Date

provided with PACS viewing stations.


The user group requested 2 PACS viewing stations in each
Provider Workroom/Charting, 1 PACS viewing station in
each Conference room and 1 PACS viewing station inside
each ICU/CCU and Step-down unit.
FCA confirmed that a total of 20 PACS viewing stations
have been added.
3.06

Public Toilets in Waiting Rooms


Based on user group comments made in previous meetings
FCA suggested changing all lockable single
accommodation public toilets in Waiting Rooms to multiaccommodation public toilets to discourage drug and other
inappropriate use.
The user group agreed to the proposed suggestion.

3.07

Lockers
The user group requested to combine separate male and
female Locker rooms into one unisex Locker room with
multiple toilet and changing facilities as indicated below:
1 Unisex Locker room 250 sf
2 single accommodation Toilet rooms w/ shower 70 sf
2 Changing rooms 30 sf

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\ICU - Step-Down\MIN.03_ICU-Step-Down.doc

Page 3 of 3

MINUTES OF DIAGNOSTIC MEETING NO. 3


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 16, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Nora Goldschlager
Dough Eckman
Richard Hollingsworth
Hal Yee
Eberhard Fiebig
Jeff Critchfield
Terry Lynch
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated February 16, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

3. Preliminary Summary Space Program, dated February 16, 2007


4. New Hospital Space Program, dated February 16, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

DEPARTMENTAL ISSUES

3.01

Cardiology
NL noted that currently only the Cath Lab is located in the
new hospital building. The user group emphasized that with
the exception of EKG and Dialysis the Cardiology Department
should be located in the new hospital building since 50% of
the services provided are inpatient services.
The user group requested the additional following spaces to be
included in the space program:
4 Echo bays
1 Stress Test

3.02

Pulmonary Function
The user group requested the following Pulmonary Function
rooms to be included in the space program:
Pulmonary Function Lab
Special Procedures
Bronchoscopy

3.03

@ 150 sf each
@ 250 sf

600 sf
220 sf
230 sf

Holding/Recovery
The user group requested to increase the number of bays in the
Holding/Recovery room to accommodate a total of 17
gurneys, with the following distribution:
Radiology
Cardiology

15 gurneys
2 gurneys

3.04

Equipment/Computer Storage
FCA noted that a large Equipment/Computer Storage room for
Cardiology and Radiology has been programmed and inquired
if multiple smaller rooms are more practical. The user group
confirmed that one large Equipment/Computer Storage room
for each department is preferred.

3.05

Linen
Page 2 of 3

Due Date

Item

Description

Action

Due Date

The user group requested Cardiology and Radiology to have


dedicated alcoves capable of accommodating 3 linen carts
each.
3.06

Contrast Media Room


The user group requested Cardiology and Radiology to have
separate Contrast Media Rooms. FCA made the following
revisions to the space program:
Radiology 1 Contrast Media Room 60 sf
Cardiology 1 Contrast Media Room 40 sf

3.07

Resuscitation Rooms X-Ray


The user group reiterated that x-ray equipment in the
Resuscitation rooms should be hard wired. They explained
that mobile x-ray equipment requires frequent charging of
batteries and is not suitable for use in Emergency situations.

3.08

Elevators
The user group noted that the service elevators should be
equipped with double acting doors.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Diagnostic\MIN.03_Diagnostic.doc

Page 3 of 3

MINUTES OF PERIOPERATIVE MEETING NO. 3


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 20, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Bill Chun
Ted Miclau
Sue Carlisle
Jens Krombach
Jane Cino
Terry Dentoni
Andre Campbell
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated February 20, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

3. Preliminary Summary Space Program, dated February 20, 2007


4. New Hospital Space Program, dated February 20, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

DEPARTMENTAL ISSUES

3.01

Operating Rooms (ORs)


The number and square footage of OR was discussed. FCA
noted that currently the following is currently programmed:
10 OR (large) @ 520 sf
4 OR (small) @ 420 sf
2 IR
The user group agreed to make the following revisions to the
space program:

3.02

4 OR (large) @ 540 sf
6 OR (medium) @ 500 sf
4 OR (small) @ 420 sf
2 IR

Clean Core
FCA stated that the existing ORs were designed around a
clean core room and bounded by a peripheral corridor. FCA
proposed to program the new OR suite using a similar
approach, however given the total number of OR rooms
currently programmed two surgical suites rather than one large
surgical suite maybe more practical.
The user group agreed to the proposed surgical suite
arrangement.

3.03

IR Room
FCA noted that 550 sf has been programmed for each IR room
and 60 sf for associated computer/equipment storage,
matching the size of the existing IR room.
The user group noted that the existing IR room did not provide
enough space at the end of the patient table for the
anesthesiologist and the required anesthesia equipment.
FCA confirmed that the current IR room proportions were not
Page 2 of 4

Due Date

Item

Description

Action

ideal, however recently FCA has successfully designed 550 sf


IR rooms using more efficient proportions.
The user group agreed to keep the square footage of the IR
rooms at 550 sf but stated that they will re-examine the size of
the IR room once a room layout and IR equipment is known.
3.04

Anesthesia Induction Room


The addition of an Anesthesia Induction room was discussed.
The user group commented that certain anesthesia induction
procedures could last up to 2-hours before a patient is ready
for surgery. Administering these procedures in the ORs would
be inefficient. The user group also mentioned that certain
anesthesia induction procedures should not be administered in
a Pre-Op Unit cubicle, citing privacy, noise and safety
concerns.
FCA suggested adding one 220 sf Anesthesia Induction room
to the space program to accommodate longer procedures and
those requiring special equipment. The user group agreed to
this proposal.

3.05

Toilets in Pre-Op Unit


FCA stated that 2 ADA toilets are currently programmed in
the Pre-Op unit. The user group pointed out that since the GI
department has been recently added to the space program
additional toilets should be added to accommodate GI patients
in the Pre-Op unit.
FCA revised the space program to include two additional
toilets in the Pre-Op unit.

3.06

Lockers
The size of both womens and mens Locker rooms were
discussed. The user group noted that the current locker room
setup is not adequate. FCA confirmed that the existing mens
locker room was divided into two rooms measuring
approximately 260 sf and 130sf and the womens locker room
was approximately 320 sf.
FCA noted that the lockers in the rooms were poorly layout
creating an inefficient and uncomfortable space. FCA
reintegrated that a well layout 300 sf locker room could easily
accommodate a combination of 75 full height and purse
lockers and still offer a comfortable space for changing.
Certain members of the user group were still concern with the
proposed locker room size, however they agreed to defer their
opinion until theyve had the opportunity to review a detail
locker room layout.

Page 3 of 4

Due Date

Item

Description

Action

3.07

OR with Fluoroscopy Capability


The user group requested 1 large OR to have fluoroscopy
capability.

Due Date

FCA to add note in space program to address this request.


3.08

Office
The user group requested to replace the Material Management
office with a IS Clinical Staff office.
FCA to revise the space program as requested.

3.09

Scope Clean Room


The user group requested to add a 80 sf scope clean room.
FCA to revise the space program as requested.

3.10

Square Footage Revisions


The user group agreed to revise the square footage of the
following spaces:

Clean Core
Equipment/Tube Storage
Biomed
Housekeeping Supplies
ECRP
Endo
Holding
(from 26 to 22 cubicles)

from 1400 sf
from 300 sf
from 250 sf
from 120 sf
from 400 sf
from 280 sf
from 2080 sf

to 1000 sf
to 250 sf
to 200 sf
to 100 sf
to 350 sf
to 250 sf
to 1760 sf

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Perioperative\MIN.03_Perioperative.doc

Page 4 of 4

MINUTES OF EMERGENCY MEETING NO. 3


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

February 23, 2007


2:00 pm : 4:00 pm

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Alan Gelb
Eric Isaacs
Bob Sypher
Angela Hackenschmidt
April Clock
Linda Garcia
Ron Alameida
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated February 23, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

3. Preliminary Summary Space Program, dated February 23, 2007


4. New Hospital Space Program, dated February 23, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

DEPARTMENTAL ISSUES

3.01

Exam Rooms
Number of exam rooms

The number of exam rooms was discussed. The user group


stated that the proposed 40 exam rooms would not be
sufficient. The user group argued that not enough inpatient
beds were being programmed to accommodate the total
volume of patients requiring admissions, resulting in an
average length of stay similar to what is currently being
observed in the existing ED. Given those parameters the user
group presented the following statistics:
The average ED census in January and February 2007, at

midnight was 50 patients.


During that period on two occasions the midnight census

was over 60 patients.


The average length of stay was 4-6 hours
Waiting time for a transfer to Step-down was 12 hours
Waiting time for a transfer to a Med/Surg bed was 10 hours

In addition the user group commented that the number of ED


visits will increase by the time the new hospital is built due
primarily to San Franciscos growing aging population and the
likely closure of St. Lukes ED.
FCA proposed to increase the number of exam rooms to 54,
the user group agreed. They noted however that they wanted
to continue to evaluate all known data and would reconfirm
the final number of exam rooms.
Subsequent to the meeting Dr. Alan Gelb distributed an
email requesting at least 60 private exam rooms.
Size of exam rooms

The size of exam rooms was discussed. FCA noted that 140 sf
exam rooms are currently programmed. The user group noted
that preferably the dimensions for exam rooms in a teaching
Page 2 of 4

Due Date

Item

Description

Action

hospital should be 11-6 x 14 (161 sf). The increased area


would better accommodate the multiple staff and students
common in teaching hospitals.
Further the user group
highlighted that the trend is to let friends and family members
stay with the patients in the exam rooms.
FCA explained that the First Floor where the ED is currently
programmed can not accommodate both an increase in the
number and square footage of exam rooms.
The user group recognized these limitations and
acknowledged that their priority was to increase the number of
exam rooms.
Subsequent to the meeting Dr. Alan Gelb distributed an
email clarifying that ED exam rooms should be 160 square
feet.
Behavioral Health

The user group requested 4 exam rooms with sound control


for chemically restraint patients to be included in the program.
Rape Treatment Center Room (RTC)

The user group requested 1 exam room with shower for RTC
patients to be included in the program. The RTC room should
be located in close proximity to a Consultation room.
Summary

During the meeting the following exam room revisions to the


space program were agreed to:

3.02

46 Exam Rooms
4 Exam Rooms Behavioral Health
1 Exam Room RTC
3 Exam Rooms Isolation

@ 140 sf
@ 140 sf
@ 180 sf
@ 140 sf

Exam Room Pods


The user group suggested dividing the total number of exam
rooms into 4 pods each servicing around 13 exam rooms with
separate Nursing Station, Provider Charting, Clean
Utility/Supply, Soiled Utility, Soiled Linen and Medication
rooms.
The user also noted that in addition to the above support
spaces the Resuscitation rooms also require a Consultation
room and a dedicated Custodial closet.

3.03

Resuscitation Rooms
Open Space Layout

The user group confirmed that an open space layout for the
resuscitation rooms is not desirable citing infection control,
Page 3 of 4

Due Date

Item

Description

Action

Due Date

patient privacy and noise concerns.


Preferred Layout

The user group noted that a layout incorporating an anteroom


that leads to the resuscitation room is preferred to a layout
where a separate equipment storage room is provided at the
rear of the resuscitation room.
The anteroom would provide the necessary space for storage
and preparation of equipment, allowing staff to get prepared
before entering the resuscitation room and reducing inefficient
circulation.
FCA noted that the layout of the resuscitation rooms will be
discussed during the design phase but enough area has been
programmed for either an Equipment Storage room or a
Vestibule/Equipment room.
Location

The user group requested the resuscitation rooms to be in


close proximity to the service elevators as well as the
emergency entrance.
3.04

Pediatric Waiting Room


The user group requested a separate waiting room for Pediatric
patients and family members.
The user group agreed to the following distribution of waiting
rooms in the ED:
2 Waiting Rooms
1 Waiting Rooms Pediatrics

@ 400 sf each
@ 200 sf

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Emergency\MIN.03_ Emergency.doc

Page 4 of 4

MINUTES OF STEERING COMMITTEE MEETING NO. 3


PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Room 2A6

MEETING
DATE:

March 5, 2007
9:00 am : 11:00 am

ISSUE DATE:

April 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Ronald Alameida
Andre Campbell
Sue Carlisle
Jeff Critchfield (JC)
Sue Currin
Gene OConnell (GOC)
Delvecchio Finley
Sharon Kotabe
John Hurley
John Luce
Roland Pickens
Mark Primeau
Carlos Villalva
Chiu Lin Tse-Chan
(CLTC)
David Fong (DF)
Paolo Diaz (PD)
Nuno Lopes (NL)
Samina Choudhry (SC)
Connie Ma (CM)

DISTRIBUTION:

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SF Bureau of Architecture
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
SFGH
Department of Public Health (DPH)
SFGH
Fong & Chan Architects (FCA)
FCA
FCA
FCA
FCA
FCA

All Attendees

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

This meeting was held to review the overall programming effort with the Steering Committee. The
following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Summary Space Program, dated March 2, 2007
3. New Hospital Space Program, dated March 2, 2007

ITEMS DISCUSSED:

Item

Description

Action

NEW BUSINESS:
A.

PROGRAM ISSUES

2.01

Nuno Lopes (NL) of FCA noted that after meeting with all
user groups the overall program has increased 20% compared
to the initially proposed program. This will cause an increase
in cost. A revised cost estimate is being prepared to determine
whether the overall building construction budget is acceptable
or if program areas need to be reduced to meet the budget.
NL noted that the construction budget would not increase
linearly with the increase of the program areas.

B.

DEPARTMENTAL ISSUES
Overview of Current Space Program
NL presented the currently proposed space program for each
floor of the new hospital building as follows. Items in bold
italics are areas that were added since the previous Steering
Committee meeting:
Basement 2

Cardiology
Radiology
Sterile Processing
Morgue and Autopsy
Material Management
Messenger/Mailroom
Environmental Services

Basement 1

Surgery
Gastroenterology
Patient Intake and Recovery
Entry Area
Page 2 of 6

Due Date

Item

Description

Action

First Floor

Entry Area
Clinical Care Emergency
Admitting
Second Floor

Obstetrics
Pediatrics
NICU
Third Floor

Step-Down
Medical / Surgical Forensic Unit
Pharmacy
Information Technology

Fourth Floor

ICU/CCU/Step-Down
Administration
Dietary
Biomed

Fifth Floor

Medical / Surgical / Step-Down


Sixth Floor

Medical / Surgical
2.02

Additions and Changes to the Space Program


NL noted that the input from meetings with all user groups
have resulted in the following additions and changes been
made since the previous steering committee meeting:
Cardiology

FCA noted that the Cath/EP Lab, Echo Lab and Pulmonary
Function have been included in the basement 2 level of the
new hospital.
The steering committee agreed to the proposed arrangement
however noted that if cuts need to be made the Pulmonary
Function could remain in the existing building.
Morgue and Autopsy

FCA noted that the morgue and autopsy in the basement 2


level of the new hospital has moved to the north side of the
new hospital building. This location would allow for a small
delivery and pick up area requested by the user groups to
service the morgue as well as the blood bank and pharmacy.

Page 3 of 6

Due Date

Item

Description

Action

FCA suggested examining the possibility of providing a


dedicated elevator to directly connect the morgue with the
loading area.
The steering committee agreed with the proposed arrangement
and welcomed the option of a delivery and pick up area
dedicated to the new hospital.
Messenger / Mailroom

FCA noted that the messenger and mailroom departments


have been included in the basement 2 level of the new
hospital.
The steering committee agreed to the above arrangement.
Gastroenterology

FCA noted that the Gastroenterology (GI) department has


been included in the new hospital.
The steering committee agreed to the above arrangement.
It was noted that Bronchoscopy should be located adjacent to
the GI department.
Emergency

FCA and the steering committee discussed the Emergency


user groups request to increase the total number of exam
rooms from 40 to 60, each room preferably to be sized at 160
sf in order to accommodate family members and teaching
staff.
FCA suggested the following 3 options:
Increase the number of exam rooms from 40 to 56 @ 140 sf
each. Area dedicated to admitting would remain in the First
Floor level as programmed.
Increase the number of exam rooms from 40 to 47 @ 160 sf
each. Area dedicated to admitting would remain in the First
Floor level as programmed.
Increase the number of exam rooms from 40 to 60 @ 160 sf
each. Area dedicated to admitting would move elsewhere in
the building.
The steering committee discussed different admitting
procedures options such as splitting the department onto
different floors however they concluded that relocating
admitting from the First Floor either partially or completely is
not desirable.
The steering committee decided to increase from 40 to 56
exam rooms @ 140 sf each and to keep the space dedicated to
Page 4 of 6

Due Date

Item

Description

Action

admitting on the First Floor as programmed.


NICU

FCA noted that the Women & Children user group has
requested the number of NICU bassinets to increase from 12
to 17.
Gene OConnell (GOC) of SFGH noted that currently the
NICU is budgeted for only 8 bassinets.
2.03

Med/Surg Forensic
The steering committee and FCA discussed whether the
Med/Surg Forensic beds could be used as regular Med/Surg
beds instead of having to close down the Med/Surg Forensic
unit during times of low census.
FCA noted that converting a Forensic Med/Surg unit to a
regular Med/Surg unit is not recommended, and advised
against it.
The steering committee noted that forensic beds could be
integrated into the Med/Surg unit if dedicated security guards
are assigned to each forensic patient room. This option
however needs to be discussed with the sheriff department.
GOC noted that a meeting with the sheriff department needs to
be established during the design phase to discuss the issues for
this area.

2.04

Med/Surg Conference Rooms


JC asked if sufficient space has been provided in the
Med/Surg unit to accommodate meeting rounds.
FCA noted that the following number of meeting rooms per
floor are currently programmed:
2 Consultation Rooms
2 Conference Rooms
2 Physician Workrooms
Jeff Critchfield (JC) of SFGH noted that given the proposed
Med/Surg floor configuration there will be 8 medicine teams
with 7 members each meeting in the mornings from 10am12am and noted that additional space to accommodate this
arrangement would be needed.
FCA noted that currently 2 waiting rooms are programmed per
floor, and suggested to convert one of the waiting rooms into a
multi purpose room with dividers to be used as meeting rooms
in the morning and as waiting room later in the day.

Page 5 of 6

Due Date

Item

Description

Action

Due Date

This would provide the following distribution per floor:

2 Conference Room
2 Consultation Rooms
2 Physician Workrooms
1 Multi-purpose Room (can be divided into 2 meeting
rooms during morning hours)

The steering committee agreed to the above arrangement.


Subsequent to this meeting NL, KJ and JC agreed to reduce
the total number of consultation rooms on the 5th and 6th
floors from 4 consultation rooms to 3 (120 sf each), to
reduce the physician workroom/charting from 300 sf to 200
sf and to reduce the waiting room from 250 sf to 200 sf.
These reductions afforded the following rooms to be added:
1 Office Chief Medical Resident
1 Medical Resident Room
1 Dayroom

@ 120 sf
@ 250 sf
@ 250 sf

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Steering\MIN.02_Steering.doc

Page 6 of 6

MINUTES OF DIAGNOSTIC MEETING NO. 4


RADIOLOGY
PROJECT:

San Francisco General Hospital


1001 Potrero Avenue
San Francisco, CA 94110

MEETING
LOCATION:

San Francisco General Hospital, Radiology Library

MEETING
DATE:

March 8, 2007
9:00 am : 10:30 am

ISSUE DATE:

May 25, 2007

ATTENDEES:

Kathy Jung (KJ)


Mark Wilson
Roland Pickens
Richard Hollingsworth
Chiu Lin Tse-Chan
(CLTC)
Nuno Lopes (NL)
Samina Choudhry (SC)

DISTRIBUTION:

All Attendees
Gene OConnell
Mark Primeau

San Francisco General Hospital (SFGH),


Facilities/ Support Services
SFGH
SFGH
SFGH
Fong & Chan Architects (FCA)
FCA
FCA

SFGH, Executive Administrator


Department of Public Health (DPH)

This meeting was held to initiate the programming effort with the Obstetric/Pediatric User Group.
The following is a record of the items discussed.
FCA presented and discussed the following attached documents:
1. Agenda of Meeting
2. Preliminary Detail Space Program, dated March 7, 2007
3. Preliminary Summary Space Program, dated March 7, 2007
4. New Hospital Space Program, dated March 7, 2007

FCA
FONG & CHAN ARCHITECTS

ARCHITECTURE PLANNING INTERIOR DESIGN


1361 BUSH STREET, SAN FRANCISCO, CALIFORNIA 94109 TEL: (415) 931-8600 FAX: 9415) 931-4601 E-MAIL fca@fca-arch.com

ITEMS DISCUSSED:

Item

Description

Action

Due Date

NEW BUSINESS:
A.

DEPARTMENTAL ISSUES

4.01

Interventional Radiology (IR)


NL noted that 2 IR rooms have been currently programmed in
the Surgery Department. The IR room in the existing hospital
building will remain and be used for outpatient services.
The user group requested the imaging equipment in one of the
IR rooms to have integrated CT scanning capability. FCA
increased one of the IR rooms to 700 sf to accommodate
integrated CT scanning capability.

4.02

Ultrasound
In lieu of two ultrasound rooms the user group requested one
large room with 3 separate bays and one dedicated toilet.
FCA revised the space program to include one 350 sf
ultrasound room with one 50 sf toilet.

4.03

Reading Rooms
The number of Reading rooms was discussed. FCA confirmed
that separate Reading rooms for Cardiology (300 sf) and
Radiology (150 sf) have been programmed. In addition FCA
confirmed that a shared 300 sf PACS room was also included
in the space program.
The user group expressed some concern that not enough space
was being provided for image reading. FCA suggested
increasing the shared Conference room from 200 sf to 350 sf
and adding a movable partition allowing the room to be
divided in half. This flexible Conference room could be used
as additional image reading or meeting room depending on the
user needs. The user group agreed to the proposed approach.

FONG & CHAN ARCHITECTS will rely on these minutes as the approved record of matters discussed
and conclusions reached. Should there be a different understanding of the issues described in the meeting
notes, a written notice should be sent to Fong & Chan Architects within five working days of receipt of
these minutes.
Prepared by Nuno Lopes of Fong & Chan Architects
F:\Proj338\Doc\Minutes\Diagnostic\MIN.04_Diagnostic.doc
Page 2 of 2

You might also like