1. Follow the SAP menu as shown, or type the transaction code CS03 in the command field.
Page 1 of 5
Business Process
End User
Procedures
Plant: Plant in which this BOM is used, enter plant number (Plant 3000 is the default plant
for SPX PE Rochester Operation). Production BOMs are plant-specific.
**** Use pull down menu for other plants****
BOM Usage: The area in which this BOM is to be used (Production, Cost, Engineering, etc.).
Enter BOM usage category. Typical entry is 3 Universal.
**** Use pull down menu for other BOM usage categories****
Alternative BOM: Enter an alternative BOM number if one exists to display the BOM.
Change Number: Enter Change Number if required. If required continue to enter data in
the fields within this section.
Page 2 of 5
Business Process
Valid From: Date from which change is effective. The system will use the current date as
the default date. Overridden by Change number date if ECM (Engineering Change
Management) is active.
3.
End User
Procedures
ECM: Data record that contains all the information required for managing a change.
Revision Level: The link between a material with the change and a specific change
number. The system determines the valid-from date from the change master record.
No entry required
Result: The Display material BOM: General Item Overview screen displays.
Page 3 of 5
Business Process
End User
Procedures
5. If display is required to the BOM header-level data, bring up the BOM header or key the Header
key as show below:
Page 4 of 5
Business Process
End User
Procedures
5. Display the header-level data such as Base Quantity, BOM status or BOM and Alternate Text
may be performed here as desired to complete the BOM change.
6. Click the Back button
Page 5 of 5