NOVEMBER2015

REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Contents
1.

INFORMATION....................................................................................................... 3
1.1 Background Information.................................................................................... 3
1.1.1. General...................................................................................................... 3
1.1.2.

Project Location and site Plan..................................................................3

1.1.3.

Project Description................................................................................... 3

1.1.4.

Workloads of the project..........................................................................3

1.2 Contract Data.................................................................................................... 4


1.2.1 Basic Data................................................................................................... 4
1.2.2 Contract Time Data..................................................................................... 4
1.2.3 Contract Cost Data...................................................................................... 6
2.0 CONSTRUCTION SUPERVISION & QUALITY CONTROL............................................9
2.1.1. Construction supervision activities.............................................................9
2.2. QUALITY CONTROL......................................................................................... 10
2.2.1 Material Tests Conducted..........................................................................10
2.3 Material and Work quality Problem..................................................................11
3.0. CONTRACT ADMINISTRATION............................................................................. 12
3.1 Performance Bond and Advance Guarantee Bond...........................................12
3.2 Instructions made on this month.....................................................................12
3.3 Summary of Claims......................................................................................... 12
3.4 Summary of Disputes...................................................................................... 12
3.5 PROGRESS OF WORKS..................................................................................... 13
3.5.1 WORK SCHEDULE...................................................................................... 13
3.5.2 WORK PLANNED VS EXECUTED.................................................................13
3.6 SUMMARY OF PROJECT CONTRACT ISSUES......................................................13
3.6.1 PROJECT PROGRESS..................................................................................13
3.6.2 PROJECT COST........................................................................................... 15

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

3.7 CRITICAL PROBLEMS ON PROGRSS & COST.....................................................16


3.8 QUALIFICATION OF CONTRACTORS TECHNICAL STAFFS.................................16
4.0 PROJECTS PROBLEMS, CRITICAL ISSUES, ACTIONS TAKEN & PROPOSED
SOLUTIONS............................................................................................................... 17
5.0 SUPERVISION AND MONITORING........................................................................18
5.1 Narrative Report.............................................................................................. 18
5.2 Consultants Staf............................................................................................ 18
5.3 Site Meeting.................................................................................................... 18
5.4 Site Visit.......................................................................................................... 18
5.5 Key Correspondences...................................................................................... 19
APPENDIX A Site Snapshots...................................................................................... 20
APPENDIX B.............................................................................................................. 24
Material test Results................................................................................................. 24
APPENDIX C.............................................................................................................. 25
Work executed Vs. Planned...................................................................................... 25
APPENDIX D.............................................................................................................. 28
Materials Issued to date........................................................................................... 28
APPENDIX E.............................................................................................................. 29
Payment Certified to date......................................................................................... 29
APPENDIX F.............................................................................................................. 31
Contractors Staf..................................................................................................... 31
APPENDIX G.............................................................................................................. 32
Consultants Staf..................................................................................................... 32
APPENDIX H.............................................................................................................. 34
Meeting Minute......................................................................................................... 34
APPENDIX I Key......................................................................................................... 35
Correspondences...................................................................................................... 35

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

1. INFORMATION
1.1 Background Information
1.1.1. General
Mekelle University, as part of its Endeavour to step up the quality and coverage of
education, has sourced out a project to procure a consultative service for
CONSTRUCTION SUPERVISION, CONTRACT ADMINISTRATION AND DESIGN REVIEW
OF MUSS 32 [Construction of Mekelle University Liaison Office at Addis Ababa
(MUBP-90), Construction of Expansion of new Cafeteria & Renovation of old
Cafeteria at Adihaki Campus (MUBP-91) and Construction of G+4 Class Room
Building at Mekelle Hospital (MUBP-92)].
1.1.2.Project Location and site Plan
The project site is located MUBP 90 in Addis Ababa, MUBP 91 in Adihaqi campus and
MUBP 92 in Mekelle Hospital.
1.1.3.Project Description
The Projects are Construction of liaison office at Addis Ababa site, Construction of
Expansion of new Cafeteria & Renovation of old Cafeteria at Adihaki Campus and
Construction of G+4 Class Room Building at Mekelle Hospital.
1.1.4.Workloads of the project
As per the original contract of the project and the bill of quantities prepared,
the estimated cost of the projects to execute all project work load including
supplementary agreement is 46,128,466.08 Birr including all taxes.

Percentage distribution of each major items of work is as shown below


N
o

Block
Code

Name

Uni
t

No
Bloc
k

Per Block

Total
Amount

%
tage
Weigh
t

MUBP 90

liaison office Birr

17,174,256.
07

17,174,256.0
7

37.23

MUBP 91

Cafeteria &
old
Cafeteria

3,829,912.7
6

9,439,083.76

20.46

Birr

5,609,171

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

MUBP 92

G+4 Class
Room

Birr

PROJECT TOTAL

19,515,126.
25

Bir
r

19,515,126.2
5

42.31

46,128,466
.08

1.2 Contract Data


1.2.1 Basic Data
Project Title

Construction of liaison office, Construction of Expansion


of new Cafeteria & Renovation of old Cafeteria and

Project Location

Construction of G+4 Class Room Building


at addis Ababa site, at Adihaki Campus and at Mekelle

Employer

Hospital
Mekelle University

Contractor

Mokenen G/kidan Building Contractor, Tadelle Berhe


Building Contractor and Asfewasen Gugsa Building

Consultant

contractor
Yohannes Abay Consulting Architecture & Engineers

Type of Contract
Consultant

Plc.
Admeasurements Contract
Gebru Abay

Representative

1.2.2 Contract Time Data


A. For Liaison office at Addis Ababa site
Construction contract signed
Site Hand Over Date

18 12 - 2004 E.C (24 08 - 2012 G.C)


17 08 2005 E.C (25 04 2013

Construction Commencement Date

G.C)
02 09 2005 E.C (10 05 2013

Mobilization Contract Period


Construction contract Period

G.C)
15 days from site Hand over
360 Calendar days

Completion Date
Defects liability period
Supervision contract signed

02 09 2006 E.C (10 04 -2014 G.C)


365 Calendar days

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Supervision commencement Date

B. For Construction of Expansion of new Cafeteria & Renovation of old


Cafeteria at Adihaki Campus
Construction contract signed
Site Hand Over Date

20 06 - 2004 E.C (27 06 - 2012 G.C)


22 02 2005 E.C (01 11 2012

Construction Commencement Date

G.C)
07 03 2005 E.C (16 11 2012

Mobilization Contract Period


Construction contract Period

G.C)
15 days from site Hand over
360 Calendar days

Completion Date
Defects liability period
Supervision contract signed
Supervision commencement Date

07 03 2006 E.C (16 11 -2013 G.C)


365 Calendar days

C. For the Construction of G+4 Class Room Building at Mekelle Hospital


Construction contract signed
Site Hand Over Date

19 10 - 2004 E.C (26 06 - 2012 G.C)


07 08 2005 E.C (15 04 2013

Construction Commencement Date

G.C)
22 08 2005 E.C (30 11 2012

Mobilization Contract Period


Construction contract Period

G.C)
15 days from site Hand over
360 Calendar days

Completion Date
Defects liability period
Supervision contract signed
Supervision commencement Date

22 08 2006 E.C (30 04 -2014 G.C)


365 Calendar days

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

1.2.3 Contract Cost Data


A. For Liaison office at Addis Ababa site
Original Contract
Supplementary Agreement
Net Variation Amount
Total Project Amount to Date
Currency of Payment
Maximum Amount of Advance

17,174,256.07
126,672.79
17,300,928.86
Ethiopian Birr
30% of the contract price including VAT

Payment
Start of Advance Recovery

Repaid by deducting proportionate


amount from each Interim payment
certificate
Monthly Advance Payment Recovery 30% of Interim payment certificate and to
be fully repaid when the total of interim
payment reaches 70% of the total
contract amount
Minimum Amount of Interim
% of the contract amount
Payment
Retention
Maximum Amount of Retention
Limit of Liquidation Damage
Interest Rate
Amount of performance Security
Price Escalation
Source of Fund
Settlement of Dispute

5% of the interim payment


5% of the contract price
10% of the contract price
Prevailing bank loan Interest
10% of the contract price
None

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

B. For Construction of Expansion of new Cafeteria & Renovation of old


Cafeteria at Adihaki Campus
Original Contract
Supplementary Agreement
Net Variation Amount
Total Project Amount to Date
Currency of Payment
Maximum Amount of Advance

9,439,083.76
2,389,410.02
11,828,493.28
Ethiopian Birr
30% of the contract price including VAT

Payment
Start of Advance Recovery

Repaid by deducting proportionate


amount from each Interim payment
certificate
Monthly Advance Payment Recovery 30% of Interim payment certificate and to
be fully repaid when the total of interim
payment reaches 70% of the total
contract amount
Minimum Amount of Interim
% of the contract amount
Payment
Retention
Maximum Amount of Retention
Limit of Liquidation Damage
Interest Rate
Amount of performance Security
Price Escalation
Source of Fund
Settlement of Dispute

5% of the interim payment


5% of the contract price
10% of the contract price
Prevailing bank loan Interest
10% of the contract price
None

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

C. For the Construction of G+4 Class Room Building at Mekelle Hospital


Original Contract
Supplementary Agreement
Net Variation Amount
Total Project Amount to Date
Currency of Payment
Maximum Amount of Advance

19,515,126.25
77,561.26
19,593,687.51
Ethiopian Birr
30% of the contract price including VAT

Payment
Start of Advance Recovery

Repaid by deducting proportionate


amount from each Interim payment
certificate
Monthly Advance Payment Recovery 30% of Interim payment certificate and to
be fully repaid when the total of interim
payment reaches 70% of the total
contract amount
Minimum Amount of Interim
% of the contract amount
Payment
Retention
Maximum Amount of Retention
Limit of Liquidation Damage
Interest Rate
Amount of performance Security
Price Escalation
Source of Fund
Settlement of Dispute

5% of the interim payment


5% of the contract price
10% of the contract price
Prevailing bank loan Interest
10% of the contract price
None

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

2.0 CONSTRUCTION SUPERVISION & QUALITY CONTROL


2.1.1. Construction supervision activities
Works of the project executed until the end of this reporting period were the
following (see site snapshots Appendix A):
No.
1
2

Description
Liaison office at Addis Ababa
site
Expansion of new Cafeteria &
Renovation of old Cafeteria at
Adihaki Campus
G+4 Class Room Building at
Mekelle Hospital

Work Under Progress


No work at this reporting month
Curtain
Carpet work &
Completion work

Plastering work
Painting
Flooring work
Hand rail work

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

2.2. QUALITY CONTROL


The quality of local and industrial materials is assured through testing and/or approval of submitted samples
with required standards.

2.2.1 Material Tests Conducted


As per requirement of the contract document for quality identification purpose, the following tests were
conducted in this report month and test results are attached in Appendix B.
No. Types
of
materi
als

uni
t

Batc
h
qua
ntity

Material
source

Test type

Date
Test
ordered

Result
expected

Testing
organiz
ation

Results
of
test(fai
led/pas
sed)

Remark

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

2.2.2 Material samples Requested for Approval


No.

Types of Materials

Material submitted
date

Result date

Result of
approval/Rejected

Remark

1
2
3

2.3 Material and Work quality Problem


No.

Date of
occurrence

Quality defect/Problem description

Cause of quality defect/problem

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

3.0. CONTRACT ADMINISTRATION


3.1 Performance Bond and Advance Guarantee Bond
No

Bond

Performan
ce bond
Advance
payment

Name of
bank/insurance

Date of
provisio
n

Date
of
expiry

Type
of
Bond

Type
of
Bond

Statu
s

3.2 Instructions made on this month


No Instruction
Design change
Variation work
Suspension
Material Change
Rectification
Others

Date

Reference

3.3 Summary of Claims


No Claim statement

Reference

Status

3.4 Summary of Disputes


Disputes addressed to our office concerning any issue during this reporting
month
No Claim statement
Reference
Status

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

3.5 PROGRESS OF WORKS


3.5.1 WORK SCHEDULE
Date of
Status of
submission/revision of
approval
Work schedule
(Yes/No)

Date of
Approval/revision of
Work schedule

Remark

3.5.2 WORK PLANNED VS EXECUTED


During the reporting period, the average construction executed work
progress of MUSS 32 reached 66.70 %.

3.6 SUMMARY OF PROJECT CONTRACT ISSUES


3.6.1 PROJECT PROGRESS
Here is the project status summary apart from the actual activity
accomplishments:
a. For Liaison office at Addis Ababa site
No.
Description
Quantity
In percentage
Completion Date
02 09 2006 E.C
(10 04 2014
G.C)
Total Contract time
360 Cal. days
Extension time approved
0
Revised completion date
02 09 2006 E.C
(10 04 2014
G.C)
Time elapsed (Cal. Days)
950
263.89%
Work planned during this
0
month
Work Executed during this
0
month
Work planned to date
0
Work executed to date
1.64%
Slippage during this month
Slippage to date
262.25%

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

b. Expansion of new Cafeteria & Renovation of old Cafeteria at Adihaki


Campus

No.

Description
Completion Date
Total Contract time
Extension time approved
Revised completion date
Time elapsed (Cal. Days)
Work planned during this
month
Work Executed during this
month
Work planned to date
Work executed to date
Slippage during this month
Slippage to date

Quantity
07 07 2006 E.C
(17 11 2013
G.C)
360 Cal. days
458
11 07 2007 E.C
(20 03 2015
G.C)
1065

In percentage

103.10%

76,620

0.74%

10,207,624.30

99,.24%
Project is
completed on
October 30,
2015

c. G+4 Class Room Building at Mekelle Hospital

No.

Description
Completion Date
Total Contract time
Extension time approved
Revised completion date
Time elapsed (Cal. Days)
Work planned during this
month

Quantity
22 08 2006 E.C
(30 04 2014
G.C)
360 Cal. days
342 days
04 08 2007 E.C
(12 04 2015
G.C)
938
0

In percentage

108.31%

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Work Executed during this


month
Work planned to date
Work executed to date
Slippage during this month
Slippage to date

92,321.25

0.54%

0
16,903,635.0

99.22%

3.6.2 PROJECT COST


a. For Liaison office at Addis Ababa site
Original Contract Price
17,174,256.07
Supplementary Agreement
Net Variation amount to
126,672.79
date
Revised Project amount to
17,300,928.86
date
Work Executed to date
Payment certified to date

9.10%

0.73%

1.64%
0

b. Expansion of new Cafeteria & Renovation of old Cafeteria at Adihaki


Campus

Original Contract Price


Supplementary Agreement
Net Variation amount to
date
Revised Project amount to
date
Work Executed to date
Payment certified to date

9,439,083.76
2,389,410.02
11,828,493.28
10,207,624.30
7,211,597.30

99.24%
70.14%

c. G+4 Class Room Building at Mekelle Hospital

Original Contract Price


Supplementary Agreement

19,515,126.25

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Net Variation amount to


date
Revised Project amount to
date
Work Executed to date
Payment certified to date

77,561.25
19,593,687.51
16,903,635.0
16,271,654.09

99.22%
95.51%

3.7 CRITICAL PROBLEMS ON PROGRSS & COST


The critical issues which afect the progress and cost of the project are
summarized as follows:
No Critical Issues
1

The liaison office project is


suspended for long time due to the
permission from AA administration

Yes/N
o
Yes

If Yes, list out


Site is suspended long
time

3.8 QUALIFICATION OF CONTRACTORS TECHNICAL STAFFS


Please see Appendix F

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

4.0 PROJECTS PROBLEMS, CRITICAL ISSUES, ACTIONS TAKEN & PROPOSED


SOLUTIONS
No

a) Major difficulties

b) Critical
c) Action
d) Proposed
issues
taken
solutions
QUALITY CONTROL & CONSTRUCTION SUPERVISION

1
CONTRACT ADMINISTRATION
1

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

5.0 SUPERVISION AND MONITORING


5.1 Narrative Report
All the permanent staf of the consultants has been assigned in the project
during this reporting month and participated in the construction supervision
and monitoring of activities in accordance to the contract document. These
activities include inspection of construction activities, inspection and
sampling of construction materials, monitoring laboratory tests, contract
administration works and other related duties to control the accomplishment
of the project within the time bound and budget in accordance with the
General and particular Conditions of Contract and Technical Specifications.

5.2 Consultants Staf


As per the contract agreement the consultant has assigned all stafs required
for the construction supervision of the project starting from the
commencement date of the project (Appendix G)

5.3 Site Meeting


5.4 Site Visit

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

5.5 Key Correspondences


The key correspondences between three parties made in this reporting
month are summarized in the table. Copies of some of the correspondences
are enclosed in the Appendix I of this report.
No
.
1
2
3

Date
Nov. 03/2015
Nov. 06/2015
Nov. 06//2015

Nov. 13/2015

Nov. 13/2015

Subject
Monthly Progress report
Budget Plan for MUBP 92
Interim payment No. 6 for MUBP
91
Interim Payment No 4 for MUBP
92
Provisional acceptance request
for MUBP 91

Remark
To MU
To MU
To MU
To MU
To MU

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX A Site Snapshots

Snapshot of Renovation of new cafeteria

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Stage curtain of Old cafe

Curtail & Wall Sound insulation work of Old caf

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Theater seat of Old cafe

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Snapshot of Old cafeteria external wall painting

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Snapshot of Mekelle Hospital status

Mekelle hospital External painting & masonry work

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Snapshot of G+4 Class Room @ Mekelle Hospital

APPENDIX B
Material test Results

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX C
Work executed Vs. Planned

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

G+4 CLASS ROOM (MUBP 92)


VALU E AS % OF
TOTAL WORK
DESCRIPTIO
No.
N
M.CONTRA
ADD %
CT

PLANNED AND EXCUTED AS % OF THE TOTAL


VALUE OF WORK
THIS MONTH
TOTAL TO
DATE
PLA
EXCUTE
PLAN EXCUTED
N
D
%
%
0.00
0.00
683,500.2 4.01
9

EXCAVATION AND
EARTH WORK

585,300.00

3.44

CONCRETE WORK

49.11

0.00

0.00

MASONRY WORK

10.78

0.00

0.00

Roof work

8,366,630.0
0
1,836,800.0
0
346,200.00

2.03

0.00
-

5
6

Carpentry &
Joinery work

652,660.00

Metal Work

925,240.00

3.83

0.00

5.43

0.00
-

Plastering &
pointing

1,151,890.0
0

6.76

Floor & Wall finish

1,651,900.0
0

9.70

Painting

360,395.00

2.12

62,935.0
5
29,386.2
0

60.8
9
8.09
2.18

371,388.0
0

10,373,07
3.64
1,378,832

0.37
0.17
0.00

Yohannes Abbay Consulting Architects & Engineers

2.05
348,917.7
2
924595.0 5.43
0
5.77
982,967.2
6
7.94
1,352,692
.20
1.78
303,578.8
0

Page 4

NOVEMBER2015
REPORT No: 37

10
11
12
13

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Glazing
Sanitary
installation
Electrical
Installation
Variation for
demolishing
TOTAL

392,000.00
106,500.00

2.30
0.63

0.00
0.00

0.00
0.57

97,144.80

594,160.00

3.49

0.00

67,444.57

0.40

0.00 0.00

17,037,119.
57

100.00

92,321.2
5

0.00

0.00
0.51

0.5
4

0.00

86,945.71
16,903,6
35.00

99.
22

EXPANSION OF NEW & RENOVATION OF OLD CAF (MUBP 91)


VALU E AS % OF
TOTAL WORK
No

THIS MONTH

DESCRIPTION
M.COUNT

CONCRETE WORK

MASONARY WORKS

PLANNED AND EXCUTED AS % OF THE TOTAL


VALUE OF WORK

ROOF WATER
PROOFING

411,42
6.75
356,23
1.10
18,692
.00

ADD %
5.01

PLAN
N
-

4.34

EXCUTE
D

%
0.00

0.00
0.23

0.00
-

Yohannes Abbay Consulting Architects & Engineers

TOTAL TO
DATE
PLA EXCUTE
N
D
%
335,150. 4.08
25
132,153. 1.61
00
24,800.0 0.30
0

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32
3.15

11. PLASTER & POINTING


1

258,83
7.00
243,75
0.00
402,20
2.86
28,086
.00
486,14
1.71

11. FLOOR & WALL


2 FINISHING

417,02
1.12

5.08

12

123,06
9.03

1.50

50,263
.35

0.61

SANITARY
INSTALLATION

114,04
0.00

1.39

ELECTRICAL
INSTALLATION

420,59
8.00

5.12

7
9
10

13
14
15

ROOF &WALL
CLADDING
CARPENTERY
STRUCTURESTEEL
WORK
METAL WORKS

PAINTING
GALAZING

0.00

0.00

2.97

4.90

0.00

0.00

0.34

0.00

0.00

5.92

0.00

0.00
-

0.00

1.83

3.48

0.68
55,962.9
0

0.00

1.23
100,800.
00

0.00

0.60
49,044.0
0

0.00

6.47
531,362.
59

0.00
-

4.91

285,761.
22

40.58

2.36

2.39

2.43
199,819.
84
2,907,01 35.42
0.96

3,330,35

3.04

195,761.
8

Other additional
TOTAL NEW CAF

249,843.
70
193,712.
72
402,658.
92
150,180.
00

0.00

0.00

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

RENOVATION OF OLD CAF

TOTAL

8.92
4,877,54
0.00
10,285,6
46.8

0.00

6,927,578.
52
10,207,6
24.3

0.00
%

Yohannes Abbay Consulting Architects & Engineers

Page 4

99.60
99.24

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX D
Materials Issued to date

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX E
Payment Certified to date

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Project: Construction of Liaison office at AA, Expansion of New cafeteria &


Renovation of Old cafeteria at Adihaki Campus and G+4 Class Room
at Mekelle hospital
Location: At Addis Ababa, at Adihaki Campus and Mekelle hospital
Client: Mekelle University
Consultant: Yohannes Abay Consulting Architectures & Engineers
Contractor: Mekonen G/kidan B.C, Tadelle Berhe B.C & Asfewosen Gugsa B.C

N
o

Paymen
t
Certific
ate No.

Ty
po
lo
gy

U
n
i
t

Certified

Previous
month
16,271,654.09

9,017,431.60

This
month

Remark

To date

Yohannes Abbay Consulting Architects & Engineers

G+4
Class
room
New &
old cafe

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX F
Contractors Staf

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX G
Consultants Staf

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

CONSULTANT'S MAN POWER


No.

Position

Qualification

Input(staff month)

1 Project manager

Architect

2 Resident Engineer

Civil Engineer

3 Site Engineer (Site Inspector)

Civil Engineer

SUMMARY OF MAN POWER FOR OFFICE WORK AND DESIGN REVIEW MUSS 32
No.

Position

Qualification

Input(staff month)

Project manager

Architect

Structural engineer

Civil Engineer

Electrical engineer

Electrical Engineer

Sanitary Engineer

Civil Engineer

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX H
Meeting Minute

Yohannes Abbay Consulting Architects & Engineers

Page 4

NOVEMBER2015
REPORT No: 37

MONTHLY CONSTRUCTION PROGRESS REPORT

PROJECT: MUSS 32

APPENDIX I Key
Correspondences

Yohannes Abbay Consulting Architects & Engineers

Page 4