DCG5243 ENGINEERING SURVEYING 3

FIELDWORK REPORT
CONSTRUCTION SURVEY

NAME: MUHAMAD AMEENURRASHID BIN ISMAIL


REG NUM: 01DGU14F1038
CLASS: DGU4A
LECTURER NAME: MOHD ZAHIRUDIN B. MOHAMMED NA'AIM

POLITEKNIK UNGKU OMAR

Page 1

REPORT CONTENT
Content

Page

COVER

REPORT CONTENT

APPRECIATION

1.0 INTRODUCTION OF CONSTRUCTION SURVEY

1.2 OUTLINE OF EQUIPMENT


1.3 OBJECTIVE OF SETTING OUT BUILDING
1.4 PROCEDURE OF FIELD WORK

5-6
7
8-15

1.5 ANALYSIS

16

1.6 RESULT

17

1.7 CONCLUSION

18

POLITEKNIK UNGKU OMAR

Page 2

PRE-PHASE

I would like to express our greatest appreciation to all the people who have help one
way or another in the report of Construction Survey in Engineering Surveying 3 subject.
First of all, I would like to thank our lecturer Sir Mohd Zahirudin Bin Mohammed
Naaim for the contribution either directly or indirectly to complete this report such as lecture
and practical on site even out of time earnestly. For sure without them I cant finish our report
base on instruments application and measurement completely. Actually, we are facing for
new experience that we were not imagined before.
A special thanks to the Geomatic lab assistant Mr Jamil because without him, I cant
get permission to takeout construction survey equipment to our survey site.
I confident this report will be a valuables resource for the upcoming students to
archive more knowledge about construction survey work. To all the group members,
congratulation and thank you for a job well done.

Thank you.

POLITEKNIK UNGKU OMAR

Page 3

1.0 INTRODUCTION OF CONSTRUCTION SURVEY

DIAGRAM 1.0
Setting out is the process of transferring the distance from the plan which was already prepared
to the ground before the beginning of construction. The plan was designed and prepared to give a
correct position of setting-out on the ground. Setting out also means the provision of marks, levels,
profiles and other information which will enable other members of the construction team to carry
out their works, so that the result is a true interpretation of the contract documents in the terms of
position, size, shape and level. It involves marks and control for any form of new construction,
including excavation, filling, tunneling, building, bridging and marine works.
The surveyor must ensure that the structure is located in the correct position in accordance with
the plan. The structure must be corrected in all the dimensions both relatively and absolutely. It
must be of the correct size, positioned correctly and at the correct level. The important that we must
to know is the skill in a successful execution of setting out job. The skill required is in angular and
linear measurement, ability to solve ordinary or simple mathematic problems, ability to read and
understanding drawings and ability to provide independent checking for the jobs

POLITEKNIK UNGKU OMAR

Page 4

1.2 OUTLINE OF EQUIPMENTS


1) Total station
Display and calculate coordinate data .
Picture:

DIAGRAM 1.2.1
2) Tripod.
Fix and make temporary adjustment for level instrument, total station and prism.
Picture:

DIAGRAM 1.2.2

POLITEKNIK UNGKU OMAR

Page 5

3) Prism
Used for reflect the electromagnetic wave from EDM to get distance reading.
Picture:

DIAGRAM 1.2.3
4) Hammer
To install pegs at site
Picture:

DIAGRAM 1.2.4
5) Pegs
Mark at site
Picture:

DIAGRAM 1.2.5

POLITEKNIK UNGKU OMAR

Page 6

1.3 OBJECTIVE OF SETTING OUT BUILDING

To understand the concept of setting-out survey


To setup a simple setting out of point on the ground
Carry out accurate setting out.
Carry out all the necessary calculations to establish the setting-out points.
Work as a team in order to execute a large scale surveying work.
Produce and present an engineering report on an engineering survey work.

POLITEKNIK UNGKU OMAR

Page 7

1.4 PROCEDURE OF FIELD WORK (install simple pegs at site)

DIAGRAM 1.4
i.
ii.
iii.
iv.

First at all, calculate assume coordinate like diagram 1.4.


Using 4 control point and 15 pegs total in site
Next step is key in all coordinate in total station
Open total station and press menu then select memory manager

DIAGRAM 1.4.4

POLITEKNIK UNGKU OMAR

Page 8

v.

Select SEARCH

DIAGRAM 1.4.5

vi.

Identify the right file and press enter

DIAGRAM 1.4.6

vii.

Select F1

DIAGRAM 1.4.7

POLITEKNIK UNGKU OMAR

Page 9

viii.

Type recent point and press enter

DIAGRAM 1.4.8
ix.

Insert instrument height and press enter

DIAGRAM 1.4.9
x.

Press F2

DIAGRAM 1.4.10

POLITEKNIK UNGKU OMAR

Page 10

xi.

Insert prism height and press enter

DIAGRAM 1.4.11
xii.

Press F3

DIAGRAM 1.4.12
xiii.

Press NEZ

DIAGRAM 1.4.13

POLITEKNIK UNGKU OMAR

Page 11

xiv.

Select point (CP) to start work and press enter

DIAGRAM 1.4.14
xv.

Press enter

DIAGRAM 1.4.15
xvi.

Press layout and search peg number and press enter

DIAGRAM 1.4.16

POLITEKNIK UNGKU OMAR

Page 12

xvii.

Press angle

DIAGRAM 1.4.17
xviii.

Adjust Total Station until bearing is 0 degree and press distance

DIAGRAM 1.4.18
xix.

Shoot total station at prism, and measure distance until the distance is 0

DIAGRAM 1.4.19
xx.

Repeat all step for another point

POLITEKNIK UNGKU OMAR

Page 13

INSERT COORDINATE IN TOTAL STATION


1) Open memory manager and take coordinate input

2) Select file and press enter

3) Select NEZ

4) Type point number and press enter

POLITEKNIK UNGKU OMAR

Page 14

5) Insert northing, easting and height coordinate station and press enter

6) Then, repeat all step for another point

POLITEKNIK UNGKU OMAR

Page 15

1.5 ANALYSIS

DIAGRAM 1.6

Using assume coordinate starting point 1000N, 1000E, calculate all control point.
At east of first point, add 2 metre, and then add 8 metre to get another control for east
coordinate (like diagram above)
At west of first point, let it be because northing is not changed.
So, another control point coordinate is 1000N,1010E
Repeat all step to get another control point and all pegs(1,2,3,4,5,6,7,8,9,10,11,12,13,14,15)

POLITEKNIK UNGKU OMAR

Page 16

1.6 RESULT

POLITEKNIK UNGKU OMAR

Page 17

1.7 CONCLUSION OF THIS FIELDWORK


For conclusion, I found that setting out is important in civil engineering work. Setting out is
add on from construction survey because with this method, I can found any opened space by looking
at the construction plan. After the setting out is finish, I can determine the point and the area for the
purposed structure. After all the works finish, I can learn the setting out process and how to get the
bearing, distance, and coordinate as in objective and we can apply it in the future work

POLITEKNIK UNGKU OMAR