Provisional sum
A provisional sum is an allowance, usually estimated by the cost consultant, that is inserted into
tender documents for a specific element of the works that is not yet defined in enough detail for

Home / news

Site info / tools

Create an article

Share

Follow

Related articles

tenderers to price. This, together with a brief description, allows tenderers to apply mark up and

Architects instruction.

attendance costs within their overall tender price and make allowance for the work in the contract

Attendance.

programme.

Bill of quantities.
Construction contract.

An example of a situation where a provisional sum might be appropriate is when work is required
below an existing structure, where the ground conditions cannot be determined until the existing
structure is demolished and the ground opened up.

Contract sum.
Contract sum analysis.
Equipment.

Provisional sums can be 'defined' or 'undefined':


Defined provisional sums are considered to have been accounted for within the contractor's
price and programme. In effect the contractor is taking the risk that their estimate will be
sufficient.
Undefined provisional sums are not accounted for in the contractor's price and programme.
This means that the client is taking the risk for the works and the contractor may be entitled
to an extension of time and additional payments.

Extension of time.

Featured articles
Central Activities Zone

Provisional sums are provided for in different ways in different forms of contract, and some forms
of contract can be a little vague about how provisional sums should be handled, in particular
regarding adjustments to the programme.

GLA publish supplementary planning guidance


for Londons commercial heartland.

Provisional sums place either the contractor or the client at risk of unexpected costs or delays.
Agreeing the cost of such work or extensions of time that might be claimed can result in tension

Skills gap

between the contractor and client. For this reason, they should only be used as a last resort,
they should not be an easy fall-back position for consultants (who are not bearing any of the risk)
when designs are incomplete or information is difficult to obtain. The risks are significant enough
that the NEC Engineering and Construction Contract (NEC3) does not have any allowance for
provisional sums.

Provisional sums should not be confused with prime cost sums, which are allowances for the
supply of work or materials to be provided by a contractor or supplier nominated by the client.
Prime cost sums might include items that have already been purchased by the client, such as
equipment, or a specific installation by a company with a strong existing relationship with a client
organisation.

Find out more

Related articles on Designing Buildings Wiki

BRE Academy skills gap survey finds key BIM


and management skills are lacking in
individuals, organisations and the wider
industry.

Government Construction Strategy

Architects instruction.
Attendance.
Bill of quantities.
Construction contract.
Contract sum.
Contract sum analysis.
Equipment.

http://www.designingbuildings.co.uk/wiki/Provisional_sum

1/4

3/28/2016

Provisional sum - Designing Buildings Wiki

Extension of time.
Final account.
Named subcontractor.
NEC3
Preliminaries.
Prime cost sum.
Project programme.
Tender.
Tender documents.
External references
Practical Law Company: Ask the team, what are provisional sums?
(http://construction.practicallaw.com/blog/construction/plc/?p=402)
Expressway Ltd v Carillion Construction Ltd 2006
(http://www.casecheck.co.uk/CaseLaw.aspx?EntryID=12992) - the meaning of provisional
sum.

Share

Add a comment

Send us feedback

The governments new construction strategy


moves towards BIM level 3, but sets
unambitious efficiency targets compared with
its predecessor.

Building of the week - Florence Cathedral

Comments

To start a discussion about this article, click 'Add a comment' above and add your thoughts to
this discussion page.

View comments history

140 years in the making, the masterpiece of


Renaissance Florence and the world's largest
masonry dome.

Cohousing

A new type of communal living that is growing


in popularity around the UK.

National Infrastructure Delivery Plan 2016-21

http://www.designingbuildings.co.uk/wiki/Provisional_sum

2/4

3/28/2016

Provisional sum - Designing Buildings Wiki

Government publishes their spending strategy


for infrastructure projects together with a
commitment to make efficiency savings.

Development House, Shoreditch

Architects unveil plans for innovative all-timber


structure in London's Shoreditch.

Unusual building design of the week

Peter Cook's Kunsthaus Graz modern art


museum in Austria, a landmark piece of
'blobitecture'.

Buildings in film

http://www.designingbuildings.co.uk/wiki/Provisional_sum

3/4

3/28/2016

Provisional sum - Designing Buildings Wiki

With 'High-Rise' in the cinemas, here is a


selection of famous buildings that have played
important film roles.

For more news, go to the home page.

Designing Buildings Ltd. 2016

About

Help

http://www.designingbuildings.co.uk/wiki/Provisional_sum

Privacy Policy

T&Cs

Contact

Feed

Report Abuse

Press

4/4

You might also like