You are on page 1of 3

Doosan Heavy Industries

Vietnam

Dung Quat Economic Zone,


Binh Thuan, Binh Son, Quang Ngai,
Vietnam
T +84 55 5618 900
F +84 553 618 950

02.Dec.11

V.H.PHONG

J.Y.Jeong

K.J. Lim

For Information

14.Nov.11

V.H.PHONG

J.Y.Jeong

K.J. Lim

For Information

Rev.

Date

Drawn

Checked

Approved

Details of Revision

Owner :

AES-VCM MONG DUONG POWER


COMPANY LIMITED
Owner's Engineer :

Contractor :

Project :

PC

MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER


PROJECT

Title :

UAS :

QE01

Unit :

P0

T10206-QE01-P0BAU__-040201 Inspection and KKS :


Test Plan for Grounding and CAD Welding Reg. No. :
System
Revision :

Drawing No. :

T10206-QE01-P0BAU__-040201

T10206

Page-No :

BAU
040201
0

ITP for Grounding


and Cadwelding work

Doc. No.

T10206-QE01-P0BAU__-040201

Rev. 0

Contractor

DOOSAN

2 of 3

AES-VCM

This note is only applicable for AES-VCM Mong Duong

Detailed Legend

Surveillance Point / DOOSAN / Subcontractor does not send a notification to AES-VCM Mong Duong
except for the first or last operation on the basis of each process. AES-VCM Mong Duong
could check the operation, if he is present at the site during the inspection by Doosan.

Report Review Point / DOOSAN / Subcontractor is required to prepare a certificate or document


attesting to the satisfactory performance of the related test or inspection for review by
AES-VCM Mong Duong.

Witness Point / DOOSAN / Subcontractor shall submit request for inspection to AES-VCM to
decide whether they will attend such inspection or not.

Hold Point / Downstream construction and other activities shall not proceed
without attendance or any written approval of AES-VCM Mong Duong.

NOTE : The Site ITP and all of the abovementioned reports will be kept available by
DOOSAN at anytime for control and or review by AES-VCM Mong Duong.

Page 2

ITP for GROUNDING AND CAD WELDING


SYSTEM

Item Name

Oper. No.

KKS Description

Abbreviation :
Note :

Doc. No.

T10206-QE01-P0BAU__-040201

Rev. 0

Contractor

DOOSAN

Page 3

AES-VCM

Inspection & Test Activities


Applicable Code &
Subcontractor DOOSAN
AES-VCM
Standard Documentation
A
Sign
A
Sign
A
Sign

Inspection Process

Verification Document

1.0

Material Approval
Approval of earthing wire, earthing rod, terminal, cad weld
and other materials to be used in earthing system

Project Specification

2.0

Verify installed location


Verify the completed section of the excavation with depth
and width as per construction drawings.

Construction Drawing

3.0

Earthing work and connection

Construction Drawing

Inspection Sheet

4.0

Testing

Design Drawing

Testing Sheet

S: Surveillance

R: Report Review

W: Witness Inspection

H: Hold Inspection

All inspection shall be performed in accordance with the approved Site Inspection and Test Plans/Project Specifications