You are on page 1of 34

Doosan Heavy Industries

Vietnam

Dung Quat Economic Zone,


Binh Thuan, Binh Son, Quang Ngai,
Vietnam
T +84 55 5618 900
F +84 553 618 950

08.Feb.2011

V.H.PHONG J.Y.JEONG

K.J.LIM

Revised incorporating the comment made by Owner via "Unifier System" on SB1053 dated 23.Jan.12

26.Dec.2011

V.H.PHONG J.Y.JEONG

K.J.LIM

For Information

Rev.

Date

Drawn

Checked

Approved

Details of Revision

Owner :

AES-VCM MONG DUONG POWER


COMPANY LIMITED
Owner's Engineer :

Contractor :

Project :

PC

MONG DUONG II 2 X 560MW (NET) COAL FIRED POWER


PROJECT

Title :

T10206-DD09-POBAU__-14001 Method Statement for


Grounding and Cad welding Works

T10206

UAS :

DD09

Unit :

PO

KKS :

BAU

Reg. No. :14001


Revision :

Drawing No. :

T10206-DD09-POBAU__-14001

Page-No :

1
1 of 34

AES-VCM

METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

INDEX
SI NO.

DESCRIPTION

PAGE NO.

1.0

PURPOSE

2.0

SCOPE

3.0

REFERENCE DOUCMENTS

4.0

MACHINERY AND EQUIPMENT AND TOOL

5.0

RESPONSIBILITIS

6.0

HEALTH AND SAFETY

7.0

PROCEDURE AND SEQUENCE

8.0

QUALITY INSPECTION

13

9.0

EXHIBITS

13

10.0

ACTIVITY FLOW CHART

14

11.0

INSPECTION AND TESTING FORM

15~16

12.0

Attachment

17~34

4~10

11~12

1. Storage Procedure
2. Exothermic Welding system
3. Material safety data sheet

Page 2

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

PURPOSE

1.0

The purpose of this Method Statement is to describe the methodology involved in excavation, installing earthing material
and backfilling works and to details out the steps to be taken in meeting the technical standards and EHS requirements of
Mong Duong II Coal Fired Power Plant.

2.0

SCOPE
The purpose of this method statement is to provide the minimum requirements for the
installation of

above ground Earthing and cad welding. This method statement defines the methods

and processes to be adopted in ensuring that activities regarding the work activities are
done in convenience and accordance to specification.
This documents also describes details of EHS Requirements, Equipments and Methodology Requirements

3.0

Reference Doucments
A. Issued For Construction Drawings
B. Approved Contract Quality Plan
C. Project EHSS Management Plan

4.0

Machinery and Equipment and Tool

.
.
.
.
.
.

Equipment and Tools to be used for Installation and Erection of Grounding (Earthing) and Cad Welding System.
prior to using any machineries / equipment at site ,it will be inspected and certified by qualified person.
periodic preventive Maintenance will by made on all equipment and machineries.
all operators and drivers are to be equipped with valid drivers license/operators license or permit from
concerned government agency.
only authorized drivers and operators are allowed to operate equipment and machinery
only authorized signalman will be assigned together with the driver or operator.
all lifting equipments as well as its accessories such as sling wire, nylon sling, shackles,
chain blocks crane hook and latch shall be inspected periodically.

- Truck 11ton
- Truck 1ton
- Forklift 7ton

- Cable drum Jacks 5ton

- Hand Crimping Tool

- Welding Machine

- Cad Welding Tool for Mould

- Hand Cable Cutter

- Ground Resistance Tester

- Machine Excavators - Hydraulic Crimping Tool

- Electrical hand tools

Page 3

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

5.0

Responsibilities
.
.
.
.
.
.

6.0

It is overall responsibility of Project Manager to organize resources prior to perform construction activities
as per project specification in compliance with the quality, schedule and safety Requirement.
EHS Manager will ensure incoordination with Site Engineer that all measure/construction
taken shall be maintained till completion of job.
It is the responsibility of Construction Manager/Site Engineer that construction activites are executed
According to the relevant project specification in compliance with the quality, schedule and safety requirements.
Doosan will ensure that all works are performed safely according to the attachment.
The relevant Doosan supervisor will ensure that the work is carried out in accordance with this method
Statement and project specification.
The QC inspector will ensure that the work is executed according the requirements
of quality dossier are fulfilled.

Health and Safety


6.1 General
It is the intention of Sub-Contractor that all test inspection procedures are carried out as per Inspection and Test Plan
in a safe manner in accordance with the Health and Safety at Work act and any other relevant legislation.

6.2 Risk Assessments


General Hazards

6.3 Site Safety


1) There are various risks associated with working on any site and site
Regulations as laid down by the site owner / operator should be observed
2) PPE The minimum personal protective equipment is as follows:
- Safety helmet
- Ear defenders / earplugs
- Safety footwear
- Eye protection
- Leather apron and arm guards
- Fire blanket
- And any other equipment required by the site operator or deemed necessary by the task.
3) Working in excavation
- Unless absolutely necessary, it is preferable that personnel do not enter any Excavations, regardless of
depth can be dangerous and there is No safe working
depth. If the work cannot be completed without entering the Excavation then must be provide proper ladder certain
area Under no circumstances should a person working alone enter Excavation .There must always be someone
outside the excavation to Raise the alarm in case of emergency

6.4 Safety Precautions


1) Compress gas cylinder shall be kept away from welding location
2) Barricade the working area
3) All safety precautionary signboards must be visibly posted
4) Ensure that only authorized personnel are within the affected area.
5) Daily Toolbox Meeting
Supervisor shall initiate daily toolbox meeting to educate his work crew on
Safety hazards involved in their work and the preventive measures that shall be undertaken .

Page 4

AES-VCM

METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

6.5

Emergency Action Plan


1) Fire & Security Protection / Prevention
Sub-Contractor shall ensure that Fire Watch assigned during the execution of Hot work activity and all of its
employees have given a basis induction Course on fire fighting and aware of the existing safety standards set
forth by Client Fire Department.
2) Sub-Contractor shall ensure that necessary fire preventive measures are being religiously performed by different
level of organizations.
3) Fire fighting equipment such as Extinguisher, Hose and fire blanket are subject to evaluation and approval by
Client Fire Department.
4) All Fire Extinguishers are to be inspected prior to the work period.
5) All fire watchers will be identified.

6.6

Emergency Procedures

Sub-Contractor shall follow clients emergency procedure during the period of work and shall ensure that its staff
and personnel are fully familiar with the use and location of the essential emergency equipment such as BA, Fire
Extinguishers, fire exits, muster points and plant alarms.
- Actions In The Event of Plant Emergency.
1) General and Evacuation alarm.
2) All works must stop and switch off all welding machines and compressor.
3) All personnel must proceed to safe location upwind or across wind to muster stations
4) Use of breathing apparatus if necessary.
5) Sub-Contractor personnel who detected a fire , toxic, flammable or asphyxiating gas leak must initially ensure their own
safety and report immediately to key personnel about the incident.
6) Direct person to person or by messenger by proving pertinent information to the Fire Station.
(location, problem, name and staff position).

6.7

First Aid
1) Sub-Contractor shall use first aid provided by Doosan in the project site.
2) Horseplay is Fools Play :
- There have been some incidents or horseplay on the process plant and the people
involved have been pulled up and warned about their future conduct
- A process plant is not a place for this kind of childish behaviour and can have devastating consequences.
- All employees must ensure that their ACTS and OMISSIONS do not endanger any other person working on site.
They are also responsible for their own safety and must co-operate with the employer and SAFETY at all times.
- Sub-Contractor require that all personnel report UNSAFE ACTS and CONDITIONS. They are also expected to
suggest methods to improve the workplace.

Page 5

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

3)

Safety Awareness :
The underlying cause accidents, injuries and incidents is invariably a lack of Safety Awareness linked with
unsafe behaviour.
Safety awareness is;

Being alert to what you are doing and what is going on around you.
Identifying potential hazards and taking the appropriate precautions to minimise and eradicate the risk.
Something everyone has to learn if he or she is to stay injury free
Part of every employees job, Everyone should carry out a Self Assessment and use Total Observation to;
Think about how you have done similar jobs in the past.
Think about how you are doing or planning to do the job now.
Compare the two operations with how the job should be done safely.
Look at everything that is taking place around you and anything that could pose a hazard to you.
Look above, below, behind and inside. Use the questioning Attitude to ask.
Have any people been injured doing this particular job ?
What injuries could occur if the unexpected happens ?
On, what I am doing will it affect other people ?
Do I have the authority, have I been trained, am I capable of doing the job ?
Do I need to wear or am I wearing the correct Personnel Protective Equipment ?
Eye Injuries :

- There have been a few entries in the accident books that relate to injuries to the eyes.
- Most of these injuries could have been avoided if the operatives had been wearing
goggles as proposed to safety glasses

- With immediate effect, Sub-Contractor Management insists that all personnel working inside the Process Plant wear
Safety Goggles /Glass at all times.
- If the housekeeping at the worksite is poor or if there is a long standing dust hazard
operatives are encouraged to report the matter to their supervisor.
6.8

Personnel Protective Equipment (PPE) :


The minimum standard of Personnel Protective Equipment is

- Head Projection,
The Process Plant is a designated Hard Hat site so safety helmets must be worn in all
the plant area. You must change your helmet if it is damaged in any way.

- Body Protection.
Protective clothing that is the right size, suitable for the job and properly maintained
must be worn all time at the Process Plant. Overalls must be made from 100% cotton.

- Safety Footwear
Safety Footwear must be worn at all times in all plant areas. The most common type of safety footwear is the safety
boot or shoe. It is recommended that they are fitted with at least a 200 joule toe-cap.

- Eye and face Protection (Note : eye injuries)


The wearing of eye protection is mandatory on all Process areas, workshops, Fabrication
yards and fire training ground. Eye protection is also recommended on roadways adjacent to process units.
Face shields or visors and/or specialist equipment (such as air-fed welding hoods) must be worn depending on the
application or as dictated by Client Operation/Work Permit..

Page 6

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

- Hearing Protection
Adequate hearing protection must be worn at all times in the designated high noise areas.
Audits are finding lots of people not wearing ear defends in the high noise areas. There are two types of ear defenders
available for use i.e muffs fitted to the helmet and ear plugs which fit inside the ear canal.
- Hand Protection
Personnel working on site are likely to be expose to a number of hazards i.e. thermal, mechanical, chemical and vibration.
Where there is a risk of contact with one or more of these hazards then the appropriate protective gloves must be worn.
- Good Housekeeping.
Poor housekeeping and untidy working is a MAJOR source of accidents and injuries.
Sub-contractor is expected to clean up and debris created and after every job. Stop work and tidy up if the work area
is becoming cluttered and ensure that you take time out at the end of every work period to do some housekeeping.
Persistent untidy workers cannot be tolerated.
Housekeeping audits are being conducted on a daily basis by both Sub-contractor and CLIENT management
and the auditors will be looking at the following area.

- Hose and cable discipline i.e. trailing hoses and cables that do not restrict access egress, passage ways or roadways.
- Oil and process spill. Any liquid should be contained in dams or soaked up with proprietary absorbent materials such
as Spillsorb or soak-up before disposal in the approved manner. Solids and dusts should be either dampened
down or vacuumed up as soon as possible.
- Insulation and scaffolding debris. This material should be removed as soon as possible and disposed of in the approved
area.

- Engineering and General Debris. To be removed as soon as possible and disposed of the approved area, meanwhile, it
must be stored in a tidy manner.

- Elevated platforms, stairways, and access ways free from debris and/or obstruction. Tools and equipment must be positioned
so that they cannot be fall onto people working below.

Page 7

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

Emergency Flow Chart

Sub - Contractor
First Finder
Site Manager

Sub-contrator
Project Manager

Doosan
site Manager

AES-VCM
Safety Manager

Police Station

Sub - Contractor
Safety Manager

Doosan

Sub-contrator
Admin Manager

Labour Office

Safety Manager

AES-VCM
Social Security
Safety

Site First aid

Hospital

Page 8

Fire Dept,

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

Risk Assessment

Task/ Job Step

A. Survey

List all Known Hazard

1.1 Instrument falling down and

1. Survey Instrument

Type of
Damage

Injury

BASE RISK
(without
controls)
L

Risk

Mitigating Control

1.1 Area where the

hit the workmen.

RESIDUAL RISK
(with controls)
L

Risk

instrument is to be set must


be well compaction

1.2 Camera dropping to ground by accident Breaking

1.2 Be concentrate all time


during work execution

B. Erection Work

1.1 Saw injure hand/fingers on cutting.

1. Preparation

1.2 Dust from timers injure eyes.


1.3 Person injure from work

2. Installation

Injury

1.1 Worn leather gloves


1.2 Worn safety glass.
1.3 Work in a correct and way precaution

Injury

2.1 Hand/Fingers trapping between work

Injury

2.1 Worn leather gloves

2.2 Work injure feet on sliding down

Injury

2.2 Worn safety shoes

2.3 Person injure from turning overwork

Injury

2.3 Support withstands to strengthen

2.4 Tripping and falling

Injury

2.4 Housekeeping area and concentrate work

Breaking

2.5 Worn leather gloves

2.6 Persons falling from height

Injury

2.6 Always worn safety full body harness.

3.1 Fire Occure

Burn

3.1 Area where the welding is to be set

2.5 Rough surfacing work and support


injure hand.

3. Welding

Injury

watchman & Extinguisher


3.2 Spark

Burn

3.2 Are where the welding point is to be set


Asbestos.

Note:

3.3 Injure hand (skin burn)

Burn

3.3 Worn welding gloves

3.4 Injure eye then spark

Burn

3.4 Worn welding glasses

L (Low)
5 : Almost Certain
4 : Likely
3 : Probable
2 : Occational
1 : Unlikely

S (Serious)
4 : High
3 : Moderate
2 : Low
1 : Very Low

Risk
S : 10~15
M : 6~9
T : 3~5
A : 1~2

Page 9

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

JOB SAFETY ANALYSIS


MONG DUONG II 2 x 560MW (NET) COAL FIRED POWER PROJECT

(Developing a habit of analyzing methods to identify hazards & unsafe practices than developing hazards.
solutions that control, minimize or eliminating)
Task : Grounding Work(Electric Work)
Prepared by :

Reviewed by :

Approved by :

Original Dated :

Revised by:

Revision Date :

Revision : A

Goggles

Gloves

Face

Barricade

Lock out No

Needed YES

Tack out No

YES
Safety

YES
Long

Harness

YES

Shield

YES

Hearing

Sleeves

YES

Ground Fault

Protection

YES

Interrupter

Others:

Other safety Equipment Required :


Remarks :
Describe Job on General: Survey, Panel Local Electrical devices Cable Tray, Conduit ,Cable/ground cable Installation, work
splice & Termination, Grounding work .Support work.
List of All Job Steps
A. Survey
1. Survey Instrument

List all Known Hazard

How to eliminate Hazards

1.1 Instrument falling down and

1.1 Area where the

hit the workmen.

instrument is to be set must


be well compaction

1.2 Camera dropping to ground by accident

1.2 Be concentrate all time

B. Erection Work

1.1 Saw injure hand/fingers on cutting.

1.1 Worn leather gloves

1. Preparation

1.2 Dust from timers injure eyes.

1.2 Worn helmet mounted face sheild

1.3 Person injure from work

1.3 Work in a correct and way precaution.

2.1 Hand/Fingers trapping between work

2.1 Worn leather gloves

2.2 Work injure feet on sliding down

2.2 Worn safety shoes

2.3 Person injure from turning overwork

2.3 Support withstands to strengthen

2.4 Tripping and falling

2.4 Housekeeping area and concentrate work

2.5 Rough surfacing work and support

2.5 Worn leather gloves

during work execution

2. Installation

injure hand.
2.6 Underground live cables

2.6 Get the clearence from the client regarding the


location of the cable and apply LOTO procedure while
working in the area.

3. Welding

3.1 Fire Occure

3.1 Area where the welding is to be set


watchman & Extinguisher

3.2 Spark

3.2 Use fire retardant blankets where is welding work


is to be done.

3.3 Injure hand (skin burn)

3.3 Worn welding gloves

3.4 Injure eye because of welding fumes

3.4 Worn welding glasses

Page 10

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

7.0

Procedure and Sequence


7.1 Storage Procedure
The storage procedure must be followed the manufacture procedure (Samsung E&L co.,ltd)
please see attachment procedure.
7.2 Preparation work
1) All existing facilities, which are within the construction area to obstruct any work activities shall be removed or be provided
with protection against damage, dust and dirt.
2) The safety and integrity of the excavation and elevation work shall be thoroughly checked before commence the work.
3) Prepare, check and submit the verified construction drawing of installation area to be attached in addition to this method
statement. These information to be distributed to all consumed parties as required.
4) The tool is suitable and safe to use.
5) Suitable fire extinguishers are available in the area.
6) Restrict inventory of materials in the point of installation to one-day supply. This will assist with housekeeping and
reduce the risk of damage and loss of products.

7.3 Underground Earthing system Installation Procedure Summary


1) Confirmation of the location where the underground earthing system is to be installed. Visit the site where the
underground earthing cable is to be installed and confirm the site condition if is ready for the said installation.
If there is any problem which interrupts underground earthing system installation at site, inform to DOOSAN engineer
or supervisor.
2) Preparation of Underground Earthing system Material and tool shall be confirm size, type, etc. of earthing system to be
installation by drawing and prepare required material.
3) Installation and Connection of underground earthing system Rods, Bare, Plates and Wires. To confirm installation earthing
system material at level as required drawings and before connect all bare copper surface must be cleaned to bright surface and
and to confirm when connect earthing system material by thermit or compression type connector as per drawing
indication.
4) Installation the grounding wire
According to design, the earthing gird will be 1 m in depth. The excavator will be used to excavate with the depth of 1.1m
the hole will be made with sufficient slope (the width is 1.2m). See below figure

1.2 m

GL

1m

1.1 m
Earthing wire

1m
Excavation work for earthing wire

Page 11

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

5) Installation the grounding rod


Excavate with 2m in depth and 3m in width and then the earthing rod will be driven to earth by harmer with more 2m.
If the soil is too hard, the more excavation shall be made in order to dirve the earthing rod properly. See below figure

3m
GL

1.1m
2m

3m

2m
7.4 Cad Welding Work
1) Qualified Cadwelder resume should be submitted to Onwer for review
2) Cadweld work process should be strictly followed the manufacture's instruction (Welding manual). Please see attachment.
3) In addition to project safety requirement, more safety precaution should be provided depend on the location and the
nature of the job, such as
- Fire bucket/extinguisher (if working near flammable materials)
- Heat resistant board.
4) Sample Cadweld should be done and tested by qualified welder and should be approved by Onwer's team
5) Cadweld material should not mix with different material.
6) The inspection must be carried out before backfilling the soil.
7) Test instrument should have valid calibration date prior to use
Instrument test certificate shouldbe enclosed with the report.

Page 12

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

8.0

Quality Inspection
The Site Inspection and Test plan (ITP) for this work summarizes various characteristics to be checked. the concerned
Site Engineer/Foreman will be responsible to ensure stage wise compliance for these operation and the Site QA/QC
Engineer/Inspector will carry-out quality control checks and report the inspection results

9.0

Exhibits
Exhibit A-INSPECTION & TEST REPORT FOR GROUND SYSTEM
(See sample Next Page)

Page 13

AES-VCM
METHOD STATEMENT FOR GROUNDING (EARTHING) AND CAD WELDING WORKS

10.0

Activity Flow Chart

(1) Excavation by Electrical

(2) Doosan Eng, S/V : Incharge of Grounding Work

(3) Sub - Contrator : Incharge of Grounding Work

Installation
(4) Direct Worker (Incharge Foreman)

(5) Sub - Contrator : Incharge of Grounding Work

(6) Doosan Eng, or S/V : Incharge of Grounding Work or


Doosan QA/QC of Electrical

(7) Sub - Contrator S/V : Incharge of Grounding Work

(8) Client : AES-VCM One Incharge Person

(9) Back Fill By Electrical

Page 14

AES-VCM

Inspection Check List


Project
Drawing No.
Specific Location

:
:
:

Earthing System

Ref. No.
Date :
CHECK ITEM

No

Verification & Approval


Yes
No N/A

Inspection elements

Material Check

Excavation work

Check Earthing Cable Size, Earthing Rod and Type correct

Earthing wire and Earthing Rod installed with designed depth and
location

Electrode inspection pits satisfactory

Check earthing connected to equipment, steel structure, frame, etc.


satisfactory

Checked by : (Subcontractor)
Name & Signature
Position
Date

DOOSAN QA/QC Dept.


DOOSAN Electrical Dept.
Name & Signature
Name & Signature
Position
Position
Date
Date

Page 15

Observed
Result
/ Remarks

AES-VCM
Name & Signature
Position
Date

AES-VCM

Testing Sheet
Project
:
Drawing No.
:
Specific Location :
Cadwelder Person :
Test Person
:
Test Equipment
:

Earthing System

Ref. No.
Date :

CHECK ITEM
No

Location

Earthing resistance

8
Checked by : (Subcontractor)DOOSAN Electrical Dept.
Name & Signature
Name & Signature
Position
Position
Date
Date

DOOSAN QA/QC Dept.


AES-VCM
Name & Signature
Name & Signature
Position
Position
Date
Date

Page 16

Observed
Result
/ Remarks

STORAGE PROCEDURE

ITEM NAME :

1 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

Storage Procedure

Title
()

PROJECT NAME :

PAGE

( )

MONG DUONG
CONDUIT & ACCESSORIES
EARTHING & LIGHTNING MATERIALS

0.0

2011.03.28

First Issue

Rev.
No.

DATE
()

DESCRIPTION
()

ENL-Q-005 Rev 0.0

SAMSUNG E&L CO.,LTD

S.H.PARK

K.H.LEE

K.M.LEE

PREPARED
BY

REVIEWED
BY

APPROVED
BY

A4 ( 210 * 297 )

STORAGE PROCEDURE

PAGE

2 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

- Contents ( ) 1. Scope ( )
2. Purpose ( )
3. Storage ( )

Attachment 1 ( 1 : ) - 5 page
Attachment 1 ( 1 : ) - 6 page

ENL-Q-004 Rev 1.0

SAMSUNG E&L CO.,LTD

A4 ( 210 * 297 )

STORAGE PROCEDURE

PAGE

3 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

1. Scope ( )
This procedure shall be applied to storage methods of electric conduit, grounding and lightning products.
, .

2. Purpose ( )
This procedures describes storage methods to prevent supplied equipment and materials from corrosion,
chemical damage or any effect of deteriorating quality.
,
.

3. Storage ( )
Every product shall be classified into indoor or outdoor storage and stored according to detailed storage
method based on its material and characteristics of use structure.
( Outdoor storage refers to that with canopy or equivalent to prevent exposure to the rainwater. )
For the concerned storage, perform the sorage method on the basis of contents on Attachment 1.
, ,
.
( . )
, 1 .

3.1

Shall be stored by designating location so as to be identified from and not to be mixed


with other items.
.

3.2

Shall be stored and handled considering packing volume and frequency of carry-in/out.
.

3.3 Keep clean in the storage area and do not store the products under tough corrosive environments.
, .

ENL-Q-004 Rev 1.0

SAMSUNG E&L CO.,LTD

A4 ( 210 * 297 )

STORAGE PROCEDURE

PAGE

4 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

3.4 Thinner, paints and other inflammable hazrdous materials shall be stored on the separately designated
place , and avoid the storage place around fire and explosion hazrds scattered.
, ,
.

3.5 Every threaded products shall be treated with anticorrosive process first to prevent corrosion on the
thread, and the related products shall be stored on dry place without moisture so as to prevent
re-corrosion.
,
.

3.6 Those products packed within carton box may be stacked to the extent that the lower box shall not
be sunken, but periodic checkup is required.
box box box
.

ENL-Q-004 Rev 1.0

SAMSUNG E&L CO.,LTD

A4 ( 210 * 297 )

PAGE

5 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

Class

Indoor

Outdoor

As original Material

Steel

Electro-Galvanizing

Carbon steel

Hot-Dip Galvanized

Hot-Dip Galvanized / Threaded product

Zinc Alloy

Electro-Galvanizing

Galvanized steel plate

As original Material

As original Material

Chromate Plating

Nickel Plating

Bronze

As original Material

SUS304

As original Material

SUS316

As original Material

As original Material

Tinned Coating

Hot-Dip Galvanized

Hot-Dip Galvanized / Threaded product

Aluminum

As original Material

PVC

As original Material

Concrete

As original Material

Graphite Compressive

As original Material

Inflammable

As original Material

Adhesives

As original Material

paint/Thinner

As original Material

STORAGE PROCEDURE
ATTACHMENT 1.
Materials

Brass

Copper

Cast Iron

Plating Specification

Storage Class
A
B
C
D
E

Materials vulnerable to oxidation (rust) that shall be stored indoor and avoided storage under
high humid area as possible.
Hot dip galvanized products available for outdoor storage ( However, white rust shall not be
regarded as quality defect. )
Products without deterioration from oxidation (rust), available for outdoor storage.
Products without deterioration from oxidation (rust). However, as their deflection may occur,
excessive stacking shall be avoided.
Inflammable materials or other explosive materials that shall be isolated indoor and avoid
the storage place around fire and explosion hazrds scattered.

ENL-Q-004 Rev 1
1.0
0

SAMSUNG E&L CO
CO.,LTD
LTD

A4 ( 210 * 297 )

PAGE

6 OF 6

Rev. No.

0.0

Doc. No.

ENL-SP-0001

(SUS304)

(SUS316)

PVC

STORAGE PROCEDURE
ATTACHMENT 1.

() , .

. (, . )

() .

D
E

() ,
.
,
.

ENL-Q-004 Rev 1
1.0
0

SAMSUNG E&L CO
CO.,LTD
LTD

A4 ( 210 * 297 )

MATERIAL SAFETY DATA SHEET


HMIS HAZARD RATINGS

OSHA - Meets 29 CFR 1910.1200 Standards

HEALTH
1
FLAMMABILITY
0
PHYSICAL HAZARD 0

SUPERWELD

* = Chronic Health Hazard


0 = INSIGNIFICANT
1 = SLIGHT

2 = MODERATE
3 = HIGH
4 = EXTREME

TRANSPORTATION INFORMATION
PROPER SHIPPING NAME: Not Regulated
HAZARD CLASS / PKG GRP: Not regulated
IDENTIFICATION NUMBER: None

REF: Not Applicable


LABEL: None Required

SECTION 1 - PRODUCT / COMPANY IDENTIFICATION


IDENTITY (AS USED ON LABEL AND LIST)

Rail Weld Metal

Page 1 of 3

MANUFACTURER'S NAME

34-6622-03 Rev. A
EMERGENCY TELEPHONE NUMBER

Superweld

Infotrac (031) 542-8381

ADDRESS (NUMBER, STREET, P.O. BOX)

TELEPHONE NUMBER FOR INFORMATION

#210 MooBong-ri Soheul-Eup

(031) 542-8381

(CITY, STATE AND ZIP CODE)

DATE PREPARED: February 12, 2008

Pochun-Si, Kyungki-Do

SUPERSEDES: November 22, 2004

SECTION 2 - HAZARDOUS INGREDIENTS / IDENTITY INFORMATION


HAZARDOUS COMPONENTS
(PECIFIC CHEMICAL IDENTITY; COMMON NAME(S))

CAS #

%
(OPTIONAL)

OSHA PEL
PPM

MG/M3

ACGIH TWA
PPM

MG/M3

SARA

RQ

TITLE III

LBS

Cuprous oxide (a)

1317-39-1

65~75

Copper (a,b)

7440-50-8

10~20

1.0

1.0

Yes

Aluminum (fume or dust) (a)

7429-90-5

10~20

15

10

Yes

Iron oxide, black (c)

1317-61-9

1~3

10

Mixture

1~3

Calcium Silicon

Yes
9600

(a) A "Yes" in the SARA TITLE III column in Section 2 indicates a toxic chemical subject to annual reporting requirements of Section 313 of the Emergency
Planning and Community Right-To-Know Act of 1986 and of 40 CFR 372.
(b) The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) has notification requirements for releases or spills to the
environment of the Reportable Quantity (RQ for this mixture > 24000 lbs) or greater amounts, if < 4 diameter, according to 40 CFR 302.
(c) The exposure limits of this product, when allowed to enter the environment as dust particulate, are covered under the rules of 29 CFR 1910.1000, Table Z 3, "All inert or nuisance dusts, whether mineral, inorganic or organic."

SECTION 3 - HEALTH HAZARD DATA


ROUTES OF ENTRY - SIGNS AND SYMPTOMS OF EXPOSURE

INHALATION: Breathing airborne particles or dust from mixing, spraying,


sanding, grinding, etc. may cause irritation to respiratory tract. Contains
substances which are considered nuisance dusts which require a NIOSH
approved respirator when airborne particulate exceeds maximum allowable limit.

EMERGENCY AND FIRST AID PROCEDURES

Remove affected person to fresh air; if symptoms persist seek medical


attention.

SKIN: None expected, however, prolonged contact may cause irritation.

Remove contaminated clothing; wash affected area with soap and water;
launder contaminated clothing before reuse; if irritation persists, seek medical
attention.

EYES: Contact with eyes may cause irritation.

Remove contact lenses. Flush eyes with clear running water for 15 minutes
while holding eyelids open; if irritation persists, seek medical attention.

INGESTION: May cause gastric distress, stomach pains, vomiting and diarrhea.

Give two glasses of water for dilution; induce vomiting as directed by medical
personnel; never give anything by mouth to an unconscious person; seek
medical attention.

CARCINOGENICITY
NTP?
No
IARC MONOGRAPHS? No
OSHA REGULATED? No
California Prop 65, Safe Drinking Water and Toxic Enforcement Act of 1986 - there are no reportable chemicals present known to the state to cause cancer or
reproductive toxicity.
MEDICAL CONDITIONS GENERALLY AGGRAVATED BY EXPOSURE: Preexisting skin, eye, or respiratory disorders may become aggravated through
prolonged exposure.

MATERIAL SAFETY DATA SHEET


IDENTITY (AS USED ON LABEL AND LIST)

Page 2 of 3

Rail Weld Metal

34-6622-03 Rev. A

Date:

October 20, 2009

SECTION 4 - FIRE FIGHTING MEASURES


FLASH POINT (METHOD USED)

NFPA RATING

FLAMMABLE LIMITS

Not applicable

None

LEL: Not applicable

UEL: Not applicable

EXTINGUISHING MEDIA
Use dry sand, graphite, dolomite, sodium chloride, water spray or chemical foam.
SPECIAL FIRE FIGHTING PROCEDURES
Firefighters must wear full facepiece self - contained breathing apparatus in positive pressure mode.
UNUSUAL FIRE AND EXPLOSION HAZARDS: Thermoweld copper base welding/joining materials are exothermic mixtures, which when reacted, produce hot
molten materials with temperatures in excess of 4000 F and a localized release of smoke. The materials are not explosive, ignition temperatures are in excess of
850 F for starting material and 1750 F for base material. They are not shock sensitive, nor are they subject to spontaneous ignition. Should the material be
accidentally ignited, the immediate and direct application of large volumes of water will effectively retard the spread of fire and control it. Large amounts of dense,
dusty smoke will be liberated during an accidental fire.

SECTION 5 - ACCIDENTAL RELEASE MEASURES


STEPS TO BE TAKEN IN CASE MATERIAL IS RELEASED OR SPILLED: Confine and segregate product for reuse; place material into approved containers for
disposal; for spills in excess of allowable limits (RQ) notify the National Response Center refer to CERCLA 40 CFR 302 for detailed instructions; refer to SARA
Title III, Section 313, 40 CFR 372 for reporting requirements. Do not discharge into lakes, ponds, streams or public waters.

SECTION 6 - HANDLING AND STORAGE


PRECAUTIONS TO BE TAKEN IN HANDLING AND STORAGE: Storage of Thermoweld Exothermic materials should be in a clean dry area and restricted to
access by authorized personnel only. Do not subject to rough handling or physical damage, nor excessive vibration. Store in accordance with "This Side Up"
labels. Protect from weather and moisture. DO NOT USE PRODUCTS THAT HAVE BEEN EXPOSED TO MOISTURE. Before using Thermoweld Exothermic
Process, personnel should be trained by a Thermoweld representative. Read and understand the instruction sheet packaged with the mold, and observe all
general and safety instructions.

SECTION 7 - EXPOSURE CONTROLS / PERSONAL PROTECTION

RESPIRATORY PROTECTION (SPECIFY TYPE): NIOSH approved respirator designed to remove airborne particulate present in excess of maximum allowable
concentrations due to secondary operations such as mixing, spraying, sanding, buffing, etc. Refer to 29 CFR 1910.134 or European Standard EN 149 for
regulations.
VENTILATION
LOCAL EXHAUST:
Recommended
SPECIAL: None
MECHANICAL (GENERAL):

Yes

OTHER: None

PROTECTIVE GLOVES: Neoprene or rubber gloves.

EYE PROTECTION: Protective eyeglasses or chemical safety goggles.

OTHER PROTECTIVE CLOTHING OR EQUIPMENT: Safety eyebath nearby


WORK / HYGIENIC PRACTICES: Practice safe workplace habits. Minimize body contact with this, as well as all chemicals in general.

SECTION 8 - PHYSICAL / CHEMICAL PROPERTIES


BOILING POINT
Not applicable
VAPOR PRESSURE (MM Hg)
Not applicable
VAPOR DENSITY (AIR = 1)
Not applicable
SOLUBILITY IN WATER
Insoluble
APPEARANCE AND ODOR
Gray / silver granules, characteristic odor

SPECIFIC GRAVITY (WATER = 1)


Approximately 6.0
pH
Not applicable
EVAPORATION RATE (WATER = 1)
Not applicable
% VOLATILE (BY WEIGHT )
None

SECTION 9 - STABILITY AND REACTIVITY


STABILITY

UNSTABLE:
STABLE:

CONDITIONS TO AVOID: Avoid generating airborne dust


X

INCOMPATIBILITY (MATERIALS TO AVOID): Strong oxidizers, strong acids


HAZARDOUS DECOMPOSITION OR BYPRODUCTS: Decomposition will not occur if handled and stored properly. In case of fire, smoke, oxides of carbon;
fumes of copper and aluminum. Small amounts of fluoride fume or hydrofluoric fume may be released under ignition.
HAZARDOUS POLYMERIZATION

MAY OCCUR:
WILL NOT OCCUR:

CONDITIONS TO AVOID: None


X

SECTION 10 - DISPOSAL CONSIDERATIONS


WASTE DISPOSAL METHOD: Dispose of in accordance with Local, State, and Federal Regulations. Do not flush to sanitary sewer or waterway. Refer to "40
CFR Protection of Environment Parts 260 - 299" for complete waste disposal regulations. Consult your local, state, or Federal Environmental Protection Agency
before disposing of any chemicals.
The information contained herein is believed to be accurate but is not warranted to be so. Data and calculations are based on information furnished by the manufacturer of the
product and manufacturers of the components of the product. Users are advised to confirm in advance of need that information is current, applicable and suited to the
circumstances of use. Vendor assumes no responsibility for injury to vendee or third persons proximately caused by the material if reasonable safety procedures are not adhered
to as stipulated in the data sheet. Furthermore, vendor assumes no responsibility for injury caused by abnormal use of this material even if reasonable safety procedures are
followed. Any questions regarding this product should be directed to the manufacturer of the product as described in Section 1.

MATERIAL SAFETY DATA SHEET


SECTION 11 - TOXICOLOGICAL DATA
Toxicity :

Non Toxic

Page 2 of 3

SECTION 12 - ECOLOGICAL DATA


If powder should enter a water course or sewer , it is non toxic and non polluting.

SECTION 13 - DISPOSAL DATA


Waste from residues and unused products :

Can be land filled when in compliance with local reaulatiions

Contaminated packaging :

Empty containers can be land filled when in compliance with local regulations

SECTION 14 - TRANSPORTATION DATA


UN 30890 Metal power , flammable , N.O.S 4.1 ; Packing Group II
Hazard Class :

4.1

Flammable Solid Inorganic NOS


Packaging Group :

II

SECTION 15 - INSTRUCTIONS
None

SECTION 16 - MISCELLANEOUS
Recommended Use :

For forming exothermic copper to copper and copper to steel joints

Further Information :

Contact the Superweld Technical Department

Please ensure that it is passed to the appropriate person(s) in your company , who are capable of acting on the infirmation.
The information given in this safety data sheet is based on current knowledge and experience and is intended to describe the products in
terms of their health and safety requirements. it should not therefore be construed as guaranteeing specific properties.
This data is based on our present knowledge. however it shall not constitute a guarantee for any specigic product features and shall not
establish a legally valid contractual relationship.

You might also like