CHANDRAPUR SUPER THERMAL POWER STATION

CHANDRAPUR
ISO 9001- 2000, ISO 14001 and OHSAS 18001 UNIT

A PROJECT REPORT

CAPITAL OVERHAUL JAN - 2016


UNIT # 5
(PERIOD: 27.12.2015 TO 30.01.2016)

SUBMITTED BY

Er. P.V.GOSAVI

Executive Engineer

Er. S.S.BHANSE

Assistant Engineer

Er. P.D.HAJARE

Assistant Engineer

Er. S.S.DHERE

Assistant Engineer

Er. N.S.KSHIRSAGAR

Assistant Engineer

CHANDRAPUR SUPER THERMAL POWER STATION

QUALITY POLICY:
Chandrapur Super Thermal Power Station of Maharashtra State Power Generation CO. Limited
recognizes its prime role in state power grid and is committed to produce economical and reliable
power in an environmentally sustainable manner with continual improvement in effectiveness of quality
management system.
We shall endeavor to upgrade knowledge and skill of our staff and strive for safe working practices
and minimum occupational health hazards.

QUALITY OBJECTIVES:

Increase in station generation.

Increase in plant load factor.

Reduction in auxiliary power consumption.

Reduction in loss of generation due to O&M problem.

Reduction in forced outages factor.

Increase in station availability.

Reduction in total Nos. of tripping.

Reduction in numbers of tripping due to boiler tube leakage.

Reduction in loss of man days due to accidents excluding fatal accidents.

Imparting training for engineers and workers.

ENVIRONMENTAL POLICY:
Chandrapur Super Thermal Power Station of Maharashtra State Power Generation Co.Limited is
committed to produce power to the use modern technology and work practices for prevention of
pollution.

We are committed to:


Carry out with environment legislation and regulation.
Carry out with C. R. E, P. and corporate policy.
Reduction in consumption of natural resources by optimum utilization of coal, oil and water.
Conservation of water by recycling water for ash disposal.
Minimization of pollution by promoting fly ash utilization.
Prevention of pollution by increasing green belt area.
Reduction of SPM level of stack emission.
Continual improvement in effectiveness of environment management system.
The environment al policy will be reviewed for objectives and targets at appropriate time.

OCCUPATIONAL HEALTH AND SAFETY POLICY:


Chandrapur Super Thermal Power Station of Maharashtra State Power Generation Co. Limited is
committed for continual improvement in health and safety performance of all our employees.

We are committed to continually improve the OHSMS by:

Identifying and assessing all types of OHS risk and take proactive step to reduce the significant
risks, in turn reduce occurrences of accidents.

Identifying, updating and Carried outlying with all applicable statutory requirements.

Creating awareness about occupational health and safety amongst all employees, contractors and
contract labors and training them adequately for safe work practices.

Preventing injury, loss of property and controlling occupational health problems, following appropriate
measures in respective areas of work.

CHANDRAPUR SUPER THERMAL POWER STATION


UNIT-V CAPITAL OVERHAUL
PREFACE
CSTPS is a quality conscious, thermal power station. It is the First Power Station in the history of
MSPGCL and first amongst all the State Electricity Board's in INDIA to get prestigious ISO-9002
certification, then ISO-9001 certification And ISO-14000 for its Environmental Management System
and OHSAS 18000.
In order to continuously upgrade and maintain the quality, Capital overhaul of unit-V was declared
W.E.F. 27.12.2015. Boiler validity was up to 03.04.2016.

During this overhaul, major thrust was given on:


1. Replacement/Servicing of passing valves of boiler and turbine side.
2. Removal, servicing, calibration & restoration of SADC Power Cylinder.
3. Overhauling of CCW 5C & BFV seal ring replacement.
4. Work of separation of ACW return line from CCW hot water outlet line.
5. Servicing of APH including basket replacement.
6. Servicing of Burner Tilt including coal compartment assemblies replacement.
7. Seal trough cleaning.
8. Maintenance/Servicing of ESP.
9. Work of repairing /replacement of riser valves of cooling tower.
10. Servicing/ Calibration of Boiler and Turbine side control valves.
11. CONDENSER TUBE CLEANING BY SULPHAMIC ACID.
12. Cleaning of Pent house, Repair of pent house, dog house & cat house.
13. A-type of C/M-A, B, C & H mills.
14. Bottom Ash hopper refractory replacement.
15. Arrest air ingress in the boiler.
16. Complete overhauling of BT mechanism .
17. Repairs of overheated / eroded water wall tubes, SH / RH tubes, LTSH tubes, economizer tubes.
18. Turbine all bearing inspection and LP turbine overhaul.
19. Calibration of various instruments.
20. TDBFP-6B over-haul work.
21. HPT Module servicing work.

THIS OVERHAUL REPORT OF U # 5 IS DISTRIBUTED IN FOUR PARTS.


Part I

: Pre overhaul report, unit history and planned O/H activities.

Part II : Actual overhaul activities.


Part III : Post overhauls activities.

Part IV : Overhaul expenditure.

INDEX

PART-I
PRE OVERHAUL REPORT, UNIT HISTORY AND PLANNED O/H ACTIVITIES :
A. Staff arrangement.
B. Unit History.

C. Set withdrawn activities.


D. Problems faced during operation.
E. Major activities planned.

PART-II
ACTUAL OVERHAUL WORKS CARRIED OUT :
A. Boiler maintenance - II
B. Turbine maintenance - II
C. ODP - II
D. Electric Maintenance - II
E. Instrumentation& Control II
F. Testing II

PART- III
A. LIGHT UP, ROLLING AND SYNCHRONIZATION OF UNIT.
B. POST OVERHAUL ACHIEVEMENTS.
C. POST OVERHAUL PENDING DEFECTS.

PART- IV
A. OVERHAUL EXPENDITURE.

PART - I
PRE OVERHAUL REPORT, UNIT HISTORY AND PLANNED O/H ACTIVITIES:
A.
B.
C.
D.
E.

Staff arrangement.
Unit History.
Set withdrawn activities.
Problems faced during operation.
Major activities planned.

UNIT-5 OPERATION STAFF ARRANGEMENT:

PROJECT MANAGEMENT:
Er. P. V. GOSAVI

Executive Engineer

Er. S.S. BHANSE

Assistant Engineer

Er. N.S. KSHIRSAGAR

Assistant Engineer

Er. S. S. DHERE

Assistant Engineer

Er. P.D. HAJARE

Project Manager

Assistant Engineer

ISOLATION & NORMALIZATION:


Er. A.M. KATHOYE

Executive Engineer

Er. M.H. ALI

Assistant Engineer

Er. S.R.GITE

Assistant Engineer

Er. G.B. NIMKAR

Junior Engineer

Er. V.K.CHAUDHARI

Junior Engineer

Team Manager

TURBINE SIDE ACTIVITIES:


Er. G.S.KULSANGE

Executive Engineer

Er. A.D.MOHOKAR

Dy Executive Engineer

Er. H.S. GHUGE

Assistant Engineer

Er. Y.W.ASAWALE

Junior Engineer

Team Manager

BOILER SIDE ACTIVITIES:


Er. A.V.YELE

Executive Engineer

Er. P.W. RAMTEKE

Addl. Executive Engineer

Team Manager

Er. N.S.KADAM

Addl. Executive Engineer

Er. S.B. KAMBLE

Dy. Executive Engineer

Er. V.B.RAMTEKE

Assistant Engineer

ODP ACTIVITIES:
Er. P.N. WARUDKAR

Executive Engineer

Er. K.Y. UIKE

Dy. Executive Engineer

Er. R.R. KALE

Assistant Engineer

Er. P.P.ROY CHAUDHARY

Assistant Engineer

SHIFT STAFF ARRANGEMENT:


1) Shift In Charge In overhaulPeriod:
Er. J.D. BAWANE

Addl. Executive Engineer

Er. R.S. NAIDU

Addl. Executive Engineer

Er. V.M. JOSHI

Dy. Executive Engineer

Er. D.D. KAMBLE

Dy. Executive Engineer

Er. M.T. BULKUNDE

Dy. Executive Engineer

2) Control Desk Engineer in Shift:


Er. P.P. PATIL
Er. S.K. TETWAR

Dy. Executive Engineer


Assistant Engineer

Er. S.V. MESHRAM

Assistant Engineer

Er. G.S. CHIKANKAR

Assistant Engineer

Er. S.S. THOMBARE

Assistant Engineer

3) Deputation to other section:


A) TURBINE MAINTENANCE:
Er. B.S. PETKAR

Junior Engineer

Team Manager

B) BOILER MAINTENANCE-II:
Er. D.M. CHANDAVALE

Assistant Engineer

C) INSTRUMENT&CONTROL-II:
Er. J.A. DHANGAR

Assistant Engineer

UNIT HISTORY:
M.S.E.B. (Now Maharashtra State Power Generation Co. Limited) has constructed a Coal Based
Thermal Power Station at Chandrapur, in Maharashtra State. This is on the Broad Gauge rail route of
the Central Railway, on Delhi-Chennai trunk route. A site is situated near village Neri and Durgapur on
Chandrapur Tadoba road at a distance of 6-7 km. from Chandrapur. Broad gauge railway siding and all
weather approach road connect the project site.
Chandrapur Super Thermal Power Station of generating capacity of 2340 MW has adequate water
apart from the huge coal reserve in Chanda - Wardha Valley.

STAGE

UNIT

SANCTION

COMMISSIONING

COMMERCIAL
OPERATED

JUL-1976

15/08/1983

01/11/1985

JUL-1976

11/07/1984

16/09/1985

II
III

FEB-1979

03/05/1984

01/04/1986

FEB-1979

08/03/1986

04/11/1986

JUN-1981

22/03/1991

01/12/1992

JUN-1981

11/03/1992

01/12/1993

FEB-1991

01/10/1997

01/03/1998

CLIMATIC CONDITION
The climatic condition of Chandrapur is as followsa)Elevation

192.3 meters above MSL

b)Maximum temperature

50 0C

c) Minimum temperature

6 0C

d)DBT / WBT
Summer

112.5 0F dbt/81.5 0F wbt

Winter

88.2 0F dbt/78.2 0F wbt

e)Annual rainfall

750 millimeters

UNIT DETAILS:
(1) Boiler Registration No :
(2)

MR 11729

Boiler
Type- Controlled Circulation with Rifled Tubing CC+, Radiant Reheat, Dry Bottom, Top
Supported.
Design pressure : 204 kg/cm2
SH outlet : 179 kg/cm2 / 540 0C

(3) Furnace
Type- Balanced Draft Furnace with Fusion Welded Water Walls
Width

: 18034 mm.

Depth

: 15289 mm.

Volume

: 14580 m3

10

Fuel Heat Input : 1225.5 X 106 kcal / hrs.

(4) Turbine
o
o
o
o

Three cylinders reheat condensing Turbine.


Single - flow HP turbine with 18 reaction stages. Type: H30 - 63 - 2
Double - flow IP turbine with 14 reaction stages per flow. Type: M30 - 50
Double - flow LP turbine with 6 reaction stages per flow. Type: N30 - 2x10 2

RATING:
Normal rating

500 MW

TMCR

524.4MW

SPEED:
Rated speed

: 3000 rpm.

Standard over speed trip setting

3330 rpm max.

Generator & Exciter:


Generator Type

THDF 115 / 59

Main Exciter Type

ELR 70 / 90 -30 / 6 -20E5

Pilot Exciter Type

ELP 50 / 42 - 30 / 16 E7

Rated Data & Outputs

TurboGenerator

Main Exciter

Apparent Power

588 MVA

Active power

500MW

3840 kW

Current

16.2kA

6300A

11

Pilot Exciter
65 kVA

195 A

Voltage

211.05 kV

600 V

220 22 V

Speed

50 s -1

50 s -1

50 s -1

Frequency

50 Hz

Power factor

0.85

Inter conn. of Stator winding

YY

H2 Pressure

3.5 Bar

Cont. Perm. Unbalanced Load

8%

400 Hz

GENERATOR VOLUME AND FILLING:


Generator volume (Gas volume):

80 M3

CO2 Filling Quantity: 160 M3 (STP),


H2 Filling Quantity: 480 M3 (STP)

HISTORY OF THE UNIT # 5:


UNIT - 5

Particulars

(500 MW)

Boiler No.

MR-11729

Comms. date

22-03-91

Coal firing

31-03-92

Commr. op

01-12-92

SR.NO.

12

TRIPPED

SYNCHRONISED

DATE & TIME

DATE & TIME

REASONS /
REMARKS

06/07/94 20.15

13/09/94 04.05

CAPITAL OVERHAUL

05/10/96 22.30

22/10/96 13.47

ANNUAL OVERHAUL

01/12/97 22.10

16/12/97 07.40

ANNUAL OVERHAUL

13/06/99 00.45

29/07/99 00.45

CAPITAL OVERHAUL

11/08/00 22.30

19/08/00 16.15

MINI
OVERHAUL
6

18/07/01 00.00

14/08/01 18.40

ANNUAL OVERHAUL

31/07/03 03.20

16/09/03 06.05

CAPITAL OVERHAUL
ANNUAL OVERHAUL

01/07/05 00.00

15/12/06 22.54

( Extended due to
turbine breakdown)
ANNUAL OVERHAUL /

14/08/08 19.30

19/09/08 05.50

LPT & IPT inspn and


Reheater Girdling Loop
& LTSH coil repl'nt.

10

16/04/2010

11

29/12/11 12.13

08/01/12 19.54

MINI OVERHAUL

14/07/2013
12

/02/2014
00:00

13

ANNUAL OVERHAUL

Year wise Generation, PLF, AVF:


Year

GEN

PLF

AVF

(Mus)

(%)

(%)

1991-92

1.224

16.88

1992-93

1035.820

23.65

44.43

1993-94

1877.224

42.86

78.71

1994-95

2130.928

48.65

73.85

1995-96

3194.136

72.73

90.81

1996-97

3383.520

77.25

89.63

1997-98

3279.445

74.87

89.74

1998-99

3115.664

71.13

88.27

99-2000

3049.040

69.42

80.76

2000-01

3428.528

78.28

90.26

2001-02

3376.464

77.09

87.14

2002-03

3493.448

79.76

93.11

2003-04

3335.120

75.94

83.62

2004-05

3734.357

85.26

90.78

2005-06

989.873

22.60

24.20

2006-07

1121.927

25.61

27.45

2007-08

3384.122

77.05

89.81

2008-09

2958.086

67.54

85.44

2009-10

3158.904

72.12

94.31

2010-11

2325.151

53.09

72.46

2011-12

3144.648

71.60

92.26

2012-13

3208.469

73.25

96.19

2013-14

1170.367

26.72

36.17

2014-15

3039.905

69.40

91.07

ANALYSIS OF GENERATION & LOSSES

14

2013-14

2015-16
2014-15

(Aug-13 to Mar-

SR

PARTICULARS

Total
(Till Jan-16)

14)

Mus.

Mus.

Mus.

Mus.
10224.00

Possible generation

2544.000

100.00

4380.000

100.00

3300.000

100.00

Actual generation

361.369

14.20

3039.905

69.40

2178.224

66.01

5579.498

54.57

Loss of generation

2182.631

85.80

1340.093

30.60

1121.776

33.99

4644.500

45.43

A] Unit overhauls

0.000

0.00

0.000

0.00

50.583

1.53

50.583

0.49

B] External factors

72.699

2.86

707.706

16.16

477.202

14.46

1257.607

12.30

i) Low system demand

20.764

0.82

147.846

3.38

239.454

7.26

408.064

3.99

ii) Poor coal receipt

0.000

0.00

232.341

5.30

0.000

0.00

232.341

2.27

iii) Poor coal quality

51.935

2.04

276.127

6.30

201.250

6.10

529.312

5.18

iv) Wet coal problems

0.000

0.00

16.084

0.37

36.368

1.10

52.452

0.51

0.000

0.00

35.308

0.81

0.130

0.00

35.438

0.35

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

C] Op. & Mt factors

2109.932

82.94

632.387

14.44

593.991

18.00

3336.310

32.63

1) Boiler tube leakage

26.840

1.06

167.141

3.82

236.101

7.15

430.082

4.21

2) Pr.parts/pipes/valves

0.000

0.00

78.798

1.80

0.000

0.00

78.798

0.77

0.115

0.00

2.120

0.05

2.753

0.08

4.988

0.05

0.000

0.00

10.936

0.25

1.392

0.04

12.328

0.12

0.000

0.00

0.000

0.00

1.308

0.04

1.308

0.01

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

27.166

0.62

0.000

0.00

27.166

0.27

v) System problem
vi) Water Shortage
problems
vii) Excessive Rains

3) Coal mills
4) ID/FD/PA fan
5) Flame fail/Furnace
pr
6) Drum level
157) Governing problem
8) Turbine
Rotor/Brg./CV/BG

100

16

TRIPPING REPORT FOR UNIT-V THE PERIOD: 20/02/2014 TO 09/06/2015 :

UNIT-5 TRIPPING OH TO OH

SR.

TRIPPED DATE

SYNCHRONISED

& TIME

DATE & TIME

20/02/14 20.51

21/02/14 03.56

REASONS / REMARKS

Unit tripped on Gen. H2 cold gas temp.


After cooler very high. (Other Problem)
Unit withdrawn to attend Boiler Tube
Leakage

28/02/14 18.37

03/03/14 13.39

(Zone - Steam Cooled Wall). The


synchronization delayed due to Barring
gear jamming problem. (Turbine
misc/others - 6.825 Mus)
Unit tripped on "Condenser pressure
very very high" due to tripping of all
CEP's. CEP-5C R-Phase lug detached
and cable touched to body, due to
sulfation effect. CEP-5B R-phase earth.

05/05/14 00.40

08/05/14 06.20

CEP-5A R/C valve stuck up due to


positioner failure. Turbine barring stalled
on 05-05-2014 @ 08:20 hrs. (Electrical
Problem - 11.667 Mus, Turbine
Brg./CV/rotor/bal - 27.166 Mus from
00:00 hrs of 06-05-2014.)
Unit Withdrawn to attend hot spot at

17/05/14 23.20

18/05/14 11.00

GTR Y phase. The work is carried out


by MSETCL 400 KV R/S. (System
Problem)

17

21/05/14 12.46

25/05/14 14.37

Unit withdrawn due to Boiler tube


Leakage (Zone : Economizer)

12/06/14 10.05

12/06/14 12.38

Unit tripped due to generator rotor E/F


relay 64F tripped.(Electrical Problem)
Unit withdrawn due to Boiler tube

12/06/14 19.14

16/06/14 12.25

Leakage
(Zone : Super heater)

23/06/14 22.00

24/06/14 06.05

01/08/14 11.48

04/08/14 16.12

10

04/08/14 23.19

05/08/14 04.23

11

05/08/14 05.17

05/08/14 18.02

12

06/09/14 18.30

Unit withdrawn due to abnormal sound


in Primary Air-Heater-B.
Unit withdrawn due to Boiler Tube
Leakage at Steam Cooled Wall.
Unit Withdrawn due to condenser
vacuum very low.
Unit Withdrawn due to Primary Water
Temp. very High.

Unit withdrawn to attend HPH FD-41


08/09/14 00.10

Valve problem

Unit withdrawn to attend HPH FD-41


13

09/09/14 05.15

14/09/14 12.51

Valve problem & due to critical coal


stock

14

14/09/14 21.02

15/09/14 10.58

15

19/09/14 19.13

20/09/14 01.25

16

05/12/14 14.58

05/12/14 22.28

18

Unit Withdrawn due to PA Fan problem

Unit withdrawn due to PAH-5B rotor


stopped
Unit withdrawn for GTR B Phase jumper
work by MSETCL. (System problem)

17

18/12/14 11.01

18/12/14 14.02

18

22/02/15 11.36

25/02/15 18.44

19

26/02/15 21.39

03/03/15 14.27

20

26/03/15 16.44

27/03/15 14.03

21

12/04/15 14.38

14/04/15 19.18

Unit tripped on "Loss of fuel indication"


(T&IC problem)
Unit withdrawn due to condenser tube
leakage.
Unit withdrawn due to BTL. (Zone Super heater)
Unit Tripped due to Starting Device Card
Failure
Unit withdrawn due to BTL. (Zone Economizer)
Unit withdrawn to jamming of SAH-5A
due to dislocation of one no of grating, 1

22

29/04/15 08.07

30/04/15 09.39

basket fall down on GD & 1 basket


entrapped in rotor & sector plate . (AirPreheater)

23

01/05/15 04.30

10/05/15 17.25

24

04/06/15 01.01

04/06/15 05.45

Unit withdrawn due to SAH-5B roter


jam.(Air heater Problem)
Unit tripped due to malfunctioning of
FSSS card (T&IC Problem)
Unit tripped on cold gas temp high due

25

04/06/15 06.05

04/06/15 08.43

to closing of H2 temp control valve.


(Others Problem)

26

24/06/15 01.23

26/06/15 02.02

27

11/07/15 04.43

14/07/15 12.51

19

Unit withdrawn due to BTL. (Zone Economizer )


Unit withdrawn due to BTL. (Zone Economizer )

28

25/09/15 21.40

28/09/15 22.02

29

30/09/15 17.36

05/10/15 05.07

30

15/10/15 18.00

19/10/15 23.55

Unit Withdrawn due to BTL (Zone - WW


&Economizer)

Unit Withdrawn due to BTL (Zone - RH)

Unit Withdrawn due to BTL (Zone Water Wall)


Unit tripped as EHG got zero due to

31

03/11/15 03.28

03/11/15 09.45

malfunctioning of EHG control final


output card. (T&IC Problem)
Unit tripped on Condenser Pressure

32

17/11/15 21.13

18/11/15 05.34

very High as all running CCW Pumps


tripped due to DC control supply failure
(Electrical Problem)
Unit tripped as EHG got zero due to

33

18/11/15 06.35

18/11/15 09.23

malfunctioning of EHG control final


output card. (T&IC Problem)

34

17/12/15 17.18

17/12/15 19.55

35

21/12/15 23.47

22/12/15 05.15

C. SET WITHDRAWAL ACTIVITIES:

20

Unit tripped on Flame Failure

Unit tripped on Condenser vacuum very


low

a) OPERATIONAL ACTIVITIES:
TG Set withdrawn on 27/12/2015 at 18:55Hrs.forcapital overhaul work.
Before withdrawing TA set was sharing 371.01 MW load.
And following were the unit parameters at 13.58hrs.on 26/12/2015.
BOILER

GENERATOR

TURBINE

TUR THR PR

HPT TOP / BOT TEMP.

Gen. Voltage

515 / 518 0C

21.00 KV

126.01 Kg/cm2.

G
E
N

MS TEMP

IPT TOP / BOT TEMP

Gen phase current

525.770C

326 / 3410C

R- 10.1, Y- 10.3, B-10.3 K Amp

E
R

HRH PR.
31.51Kg/cm2.
HRH Temp- 5280C

HPT FIRST STG PR.

Exciter field current

125 Kg/cm2.

1942 AMP

T
O

MAX. TG BRG VIBR.

GEN FREQ. 50.10 Hz MVA

23.71 MIC (BRG NO. 07)

7.13MVAR

MAX. SHAFT VIBR.


GEN FREQ. 50.10 Hz
61 MIC.( No. 01)
Condenser Vacuum
MAX GEN. SLOT TEMP 72.510C
-8630 MMWCL
MAX CORE TEMP 51.100C
NEG. PHASE SEQ CURRENT 0.5 %

TRANSFORMER PARAMETERS AS ON 26/12/2015 AT 19:15.00HRS


Sr No

21

PARAMETER

GTR-R

GTR-Y

GTR-B

OIL TEMP (Deg. C)

43

47

47

WDG TEMP (Deg. C)

48

52

52

OIL PUMP RUNNING

1&3

1&3

1&3

OIL LEVEL

50 %

40 %

40 %

SILICA COLOR

BLUE

BLUE

BLUE

TAP POSITION

ESP PARAMETERS ON DT: 18/12/2015:

PASS A FIELD VOLTAGES IN KV & CURRENT IN mA :


FIELD

1A1

1A2

2A1

2A2

3A1

3A2

4A1

4A2

5A1

5A2

6A1

6A2

VOLT

30

U/V

U/V

36

40

53

42

U/V

42

44

39

42

mA

237

U/V

U/V

221

352

00

278

U/V

590

41

426

65

PASS B FIELD VOLTAGES IN KV & CURRENT IN mA :


FIELD

1B1

1B2

2B1

2B2

3B1

3B2

4B1

4B2

5B1

5B2

6B1

6B2

VOLT

30

35

36

28

55

33

42

44

37

41

28

32

mA

32

65

172

82

08

16

04

90

00

123

24

467

PASS C FIELD VOLTAGES IN KV & CURRENT IN mA :


FIEL

1C1

1C2

2C1

2C2

3C1

3C2

4C1

4C2

5C1

5C2

6C1

6C2

VOLT

16

16

22

45

U/V

32

34

42

U/V

U/V

54

51

mA

00

00

00

82

U/V

24

442

574

U/V

U/V

24

73

6D1

6D2

PASS D - FIELD VOLTAGES IN KV & CURRENT IN mA :


FIELD

1D1

1D2

2D1

2D2

3D1

VOLT

36

34

U/V

26

mA

98

205

U/V

32

22

3D2

4D1

4D2

5D1

5D2

04

37

39

34

35

36

39

35

728

303

328

295

295

426

221

418

TURBINE BEARING AND SHAFT VIBRATIONS IN MICRONS ON DT: 18/12/2015,AT: 23.09 HRS.
ABSOLUTE BEARING

SHAFT

Time
1

HPT F

HPT R

IPT R

LPT R

GEN F

GEN R

EXC R

HPT F

HPT R

IPTR

IPT R

EXC

4.83

3.46

6.70

5.8

25.09

3.89

16.1

70.91

36.31

50.72

58.5

24.4

HRS

23.09

FOLLOWING ACTIVITIES WERE CARRIED OUT AFTER TRIPPING OF TA SET :


BOILER SIDE ACTIVITIES :
1. Boiler draining started on 28/12/2015 at 14:20Hrs.at drum metal temp top/bottom-78/740C.
2. Furnace pressurasation test was carried out on dated 29/12/2015 from 10:45 Hrs. to 12:30 Hrs. at
1424 T/Hr air flow and +52 mmwcl furnace draftwith 2 I.D.fan and 2 F.D. fan in service and leakages
observed were marked with paint.
3. CAVT was carried out in second pass of boiler with 3 I.D.fan and 2 F.D. fan in service on dtd.
29/12/2015 from 14:00 to 18:00 Hrs. at air flow 1436 T/Hr. and -5.9 mmwcl furnace draft.

TURBINE SIDE ACTIVITIES :


A. ACW, CCW system :
1. CCW sump make up stopped on dated 30/12/2015 at 14:30Hrs.& level was 190.300 MSL.
2. CCW sump level low alarm not appeared even if sump level drop down to 191.300MSL (Alarm setting
191.300 MSL). And CCW pump has to stop manually as no pump was tripped even if sump level drops
down to 190.300 MSL.

23

3. ACW-5C withdrawn at 10:00 AM on 30.12.2015.ACW-B TRIPPED at 23:30 on 31.12.2015. Sump level


very low (189.600 MSL).
4. MOT coolers, seal oil coolers, IA Compressor & SA Compressor, F/F water supply was provided for
cooling purpose during above period.

B. HYDROGEN PURGING :
1. On dated 27/12/2015 at 18:58 Hrs. unit withdrawn for Capital overhaul work.
2. H2 purging started (at pr.3.1 kg/cm 2) at 10:07hrs.on29/12/2015 by opening H2 purging valve from
turbine basement.
3. CO2 filling started at (0.2kg/cm2)13:20Hrs. on Dated 29/12/2015
4.

CO2 purity 100.0% achieved on dtd 30.12.2015. Total CO2 cylinders consumed 65Nos.

5. Dry instrument air filling started at 00:50hrs, Dated 31/12/2015 and stopped at 08:15hrs. On
31/12/2015and CO2 purity obtained 0% and air pressure boost-up to 3 kg/cm2 at 08:15hrs.
6. Generator leak test and depressurization of air started dated 01/01/2016 from 09:15hrsand air
pressure kept 0.5 kg/cm2, on dated 01/01/16 at 12.20 hrs.
7. Turbine Barring stopped at 02:45 hrs. On 01/01/2016.HPT top/bottom casing temperatures were
109/110oC.

HPT COOLING CURVE:


HPT CASING COOLING CURVE

Set withdrawn on Dt. 27/12/2015 AT 18:50Hrs.Barring stop on dt.01/01/2016, AT 02:45Hrs.Average


rate of cooling 3.20C per hour.

24

500
450
400
350
300
250

HPT TOP
HPT BOTTOM

200
150
100
50
0

HPT Casing top / bottom cooling temp (0C) :


Sr.No.

Hrs.

TOP

Bottom

Sr. No

Hrs.

Top

Bottom

463

448

19

36

293

260

451

434

20

38

284

252

438

420

21

40

277

244

25

426

404

22

42

270

237

417

385

23

44

262

230

10

409

374

24

46

255

223

12

400

363

25

48

248

217

14

391

352

26

50

241

211

16

383

347

27

52

234

204

10

18

375

338

28

54

227

198

11

20

367

329

12

22

358

320

13

24

349

311

14

26

341

302

15

28

332

293

16

30

321

288

17

32

314

276

18

34

307

268

PROBLEMS FACED DURING OPERATION:

TURBINE SIDE :
1) SAC-5A, DIS NRV PASSING
2) SAC-5B, SAFETY VLV LEVER NOT AVALABLE
3) SAC-5C, BELTS LOOSE
4) IAC-5A OIL LEAKAGE FROM FIY WHEEL SHAFT
5) IAC-5B,SOUND FROM NRV
6) AIR WASHER -1A, SAFETY GUARD N.A.
7) ALL COMPR ACW VLV REQ LUBRICATION
8) AIR DRYER BLOWER NO-2,HAVING VIBRATION & ABNORMAL SOUND
9) BOILER FILLING PUMP U5 & U6 HAVING GLAND LEAKAGE
10) COMPR SV -3 AIR LEKAGE FROM PLUNGER
11) AIR DRYER 4WAY VLV REQ SERVICING
12) MDBFP-5C,R/C VLV BONET LEAKAGE

26

13) MDBFP-5C,BOOSTER PUMP MECH SEAL STEAM ,WATER LEAKAGE


14) MDBFP-5C,BOOSTER PUMP END DROP BY DROP OIL LEAKAGE
15) MDBFP-5C R/H & S/H SPRAY NRV PASSING
16) CEP-5B, HAVING STUFFING BOX LEAKAGE
17) MAIN CRH LINE,IMPULSE LINEABOVE MAL STATION HAVING LEAKAGE
18) EX-32,VLV SEAL WATER LEAKAGE FROM ACTUATOR
19) CEP-5A,5B,5C SUCTION LINE DRAIN TO BE MODIFIED
20) VACCUME PUMP -5A SEPERATOR TANK VENTGUARD N.A.
21) GTR B PH ,ACW I/L STRAINER HOLE OBSERVED
22) MOT COOLER NO-2,HAVING DROPWISE LEAKAGE FROM FLANGE
23) MS ATMOSHERIC DRAINS VLV 3NOS PASSING
24) ALL MAL STATION ISOL VLV & MOTORISED VLV NEED SERVICING
25) CD-31 & 34 VLV DROPWISE LEAKAGE FROM BONET
26) MDBFP-5D ,WORKING COOLER CHOCK UP
27) PRIMARY WATER PUMP STN RASIN TANK I/L VLV PASSING ,NOT ISOLATES WHILE RASIN
CHANGEING
28) G.D. PUMP NO-1,DIS VLV LEAKAGE
29) G.D.PUMP NO-1.DIS LINE LEAKGE NEAR FLANGE
30) MOT COOLER I/L & O/L ACW LINE VENT VLV NEED REPLACEMENT
31) MD BFP-5C,SH SPRAY LINE DRAIN VLV PASSING
32) MDBFP-5C,HAVING LEAKAGE FROM MAIN PUMP BODY FLANGE
33) MDBFP-5D,MECH SEAL COOLER CHOCKUP
34) EX- 10 VLV IN OPERATIVE
35) EX 6 VLV IN OPERATIVE
36) TDBFP-5B,MAIN PUMP HAVING HIGH VIBRATIONS AS PER CMC REPORT
37) PROVISION OF FIRE FIGHTING WATER FOR U5 COMPR OPERATION

ODP-II SIDE DEFECT:


1)
2)
3)
4)
5)
6)

CCW PUMP SUMP MAKEUP VLV (OLD) NOT WORKING


CCWPH PNEUMATIC MAKEUP VLV JAM
ACW PUMP R/C, DIS VLV HAMMERNG SOUND
CCW-5B PUMP, DIS BFV NOT OPENING ON AUTO MODE
COOLING TOWER -5A & 5B RISER VLV JAM
CCW-5C PUMP GLAND FOLLOWER DAMAGE.

EM-II SIDE DEFECTS :


1)
2)
3)
4)
5)
6)

5CWXA & 5CTXA TRANSFORMER OIL GAGE FAULTY (LVL NOT SEEN)
5CWXA TRANSFORMER TAP CHANGER TANK OIL LVL NOT SEEN
COOLING TOWER TRANSFORMER AREA POOR LIGHTING
COMPR BKR PANEL (ALL) LOCK KEY JAM
BUS DUCT DRYER TOWER HEATER NOT WORKING
ALL GTR,UAT,STN TRANSFORMER GAGE GLASS NEEDS CLEANING

I&C-II SIDE DEFECTS :


1) BRG DE SIDE TEMP GAGE FAULTY
2) CCW-5A, 5B COLD AIR TEMP GAGE N.A.

27

3) ALL IAC & SAC DIS PRESS GAGE REQ CALIBRATION


4) SERVICE AIR CCW-5B,MOTOR RECIVER TANK PRESS GAGE FAULTY
5) CONDENSER I/L & O/L TEMP & PRESS GAGES REQ REPLACEMENT
6) BUS DUCT DRYER TEMP & PRESS GAGES NEED CALIBRATION
7) GD PUMP DIS LINE PNEUMATIC VLV NOT OPERATING ON AUTO
8) H2 PRESS GAGE AT LOCAL REQ CALIBRATION
9) HOT WELL TEMP GAGE RHS NEED CALIBRATION
10) EX-10 VLV , NOT WORKING ON AUTO
11) MAIN TG EHG HAVING HUNTING

ET-II SIDE DEFECTS


1)
2)
3)
4)

IAC-A SAC-A, ANNOUNSATION N.A.


GT-5, CW FLOW LOW ALARM FAULTY YET PERSIST ON CUP-19
GT COOLER TROUBLE FAULTY ALARM ON CUP-19
BUS DUCT DRYER HEATER NOT WORKING

CM SIDE DEFECTS :
1) 5CTXA AND 6CWXC TRANSFORMER SLAB LEAKAGE ABOVE DUCT
2) ACW & CCW PUMP HOUSE TERES LEAKAGE
3) TERES DRAIN PIPE NEAR H2 ROOM ,HEAVY LEAKAGE ON LIGHING PANEL

F/F SIDE DEFECTS :


1) F/F VLV ABOVE HOTWELL MAKEUP STATION HEAVY LEAKAGE.

BOILER SIDE :
1. A-4 PIPE FROM FURNANCE HEAVY LEAKAGE AND FLAME COMING OUTSIDE.( SPARK)
2. WIND BOX DUCT LEAKAGES AT RHS/LHS. ALL CORNOR EXP.JOINTBOILER INSULATIONS
DAMAGED AT CORNERS, ESPECIALLY AT 23 MTRS UNIT #6 SIDE AND AT OVERFIRED
DAMPERS (ALL CORNERS), CONTINEOUS ASH COMING OUT OF FURNACE AND GETTING
ACCUMULATED AT CORNERS.
3. ESP HOPPER D31 FOREIGN MATERIAL.
4. DRUM VENT LINE PUNCTURE
5. DRUM VENT B-56, B-72 JAM / INOPERATIVE.
6. SH DRAIN STATION DRAIN V/V GLAND LEAKAGES 3 NOS.
7. SOOT BLOWER FALNGE JOINT GASKET HEAVY LEAKAGES 29,31,64.
8. SOOT BLOWER FALNGE JOINT GASKET LEAKAGES 23,51,54,55,61,69,85,88,103
9. ESP FIELD 4D2. 2A1, 1D2, 4B1, 1A1, 1A2 NEED INTERNAL INSPECTION
10. CRM 1A SHAFT SHIFTED/JAM
11. CBD V/V AT 23 MTRS GLAND LEAKAGE
12. PAH 5A & 5B HOT AIR LEAKAGE FROM MANHOLES & EXPANSION JOINTS
13. OIL GUN AB3 STEAM ISOLATING V/V BONET LEAKAGE
14. ISO V/V TO SH SPRAY V/V SS12 BODY LEAKAGE
15. FO STATION ATOM STEAM TRACING LINE V/V GLAND LEAKAGE

28

16. BCW PUMP NO.1 COOLING LINE V/V GLAND LEAKAGE


17. ISO V/V TO RH SPRAY V/V R11 BODY LEAKAGE
18. ALL CLINKER GRINDERS NEED INTERNAL INSPECTION
19. SEAL TROUGH HAVING LEAKAGE ABOVE C/G 1B, 2A & 2B
20. C/A TANK NO. 1 & 2 WALKING GRILL BROKEN
21. C/A FLUE GAS HOPPER NO 3 & 4 - RAILING & GRILL BROKEN
22. C/A TANK NO. 1 - TEALEPIECE CHOKEUP.
23. BV C/A TANK NO. 1 - TEALEPIECE CHOKEUP.
24. ALL COLD AIR DAMPERS TO BE PROVIDED WITH CHAIN & HANDLE & MAKE THEM FREE
25. ALL B/ASH MANUAL HYJECTOR V/V NEED TO MADE FREE
26. C/M 5E LOP OIL SEAL LEAKAGE. C/M 5A & 5B HAVE MINOR LOP LEAKAGE.
27. C/M 5B J2 ASSY SHAFT SEAL LEAKAGE
28. BOILER FILLING STATION ALL V/V NEED SERVICING
29. SLURRY TRENCH STRAINER NEEDS TO BE REPLACED
30. ID FAN A,B,C,D ACW LINE VALVE INOPERATIVE
31. ID FAN A DUCT LEAKAGE AT LOWER SIDE NEAR INSPECTION DOOR
32. ID FAN D DUCT LEAKAGE AT UPPER SIDE NEAR INSPECTION DOOR
33. ID FAN A LOP II OIL LEAKAGE THROUGH INSPECTION GLASS
34. ID FAN C OIL LEAKAGE THROUGH OIL LEVEL GAUGE
35. ALL ID FAN INSPECTION DOOR ROPE NEEDS TO BE REPLACED
36. SUMP SELECTION VALVE FOR BOTTOM ASH, FLY ASH NOT FREE
37. BOTTOM ASH, FLY ASH SUMP SELECTION VALVE A,B,C SERIES NEEDS SERVICING
38. ASH WATER MAKE UP VALVE PASSING
39. ESP HOPPER C-11,C-21 HOPPER ASH LEAKAGE ANS INPEC. DOOR CHECKING REQ.
40. SIDE HEAVY LEAKAGE AND HEATER BELOW LINE STEAM AND OIL LEAKAGE
41. LDO/HFO TANK SCALE PATTY PROPER FITTING . SCREW FITTING REQ.
42. TANK HEATING MAIN AND TANK HEATING INDIV. V/V PASSING REPL. AND CHECKING REQ.
43. FD FAN-A/B, PA FAN-A/B ACW LINE PRESSURE AND TEMP. GUAGE ISO. V/V NOT
OPEN/CLOSE/JAM ALL PUMP ACW INLET AND OUTLET V/V SERVICING REQ.
44. SUPER HEATER ALL DRAIN V/V JAM SERVICING REQ. AND MAKE FREE
45. PAH-5A/5B,SAH-5A/5B ACW LINE TEMP.AND PRESSURE ISO. JAM AND REPL. REQ. AND AIR
HEATER ALL ACW INLET AND OUTLET AND DRAIN V/V JAM NOT OPEN/CLOSE REPL. REQ
46. GD-6A1/6A2,6B1/6B2,6C1/6C2,6D1/6D2 AND 7A/7B/7C/7D SERVICING REQ.
47. NEW FITTING DUCT HOPPER NOT INOPERATIVE I&C=II U=5 HEAD TOLD NO INFORMATION
AND NOT DONE PROTOCAL
48. SUPER HEATER SPRAY DRAINS V/V ARE PASSING AND NOT OPEN/CLOSE JAM AND REPL.
REQ.
49. C/M-5A TO 5H HOT AIR GATE SEAL PASSING AND DUCT LEAKAGE, C/M 5B - HOT AIR DUCT
RUPTURED.
50. ALL ID FAN ACW LINE DRAINS V/V AND INLET AND OUTLET V/VS ARE JAM AND THREAD
DAMAGED SERVICING AND REPL. REQ.
51. GH ELEVATION GH-2/3 OIL GUN NO PROPER SPACE TO BE FIT OIL GUN AND RAILLING CUT
REQ.
52. ALL DRUM VENT AND STARTUP VENT SERVICING REQ.
53. F.O HEATING U=5 MAIN V/V AND INTER CONNECTION V/V AT OHP JAM MAKE FREE
54. PAH-5A/5B SAH-5A/5B AIR HEATER FLUSHING LINE ALL V/VS ARE JAM NOT OPEN/CLOSE
AND SAH-5A FLUSHING LINE HEAVY LEAKAGE NEAR AIR HEATER

29

55. GAS DAMPER GD-4B2 UNDER PERMIT ABOVE ONE YEAR GD-4A1,4A2,4B1 FULL NOT OPEN
CLOSE FROM LOCAL AND LEVER NOT ENGAGE SERVING REQ.
56. BSWBOOSTER PUMP-5A NRV PASSING AND SERVING REQ.
57. PRI GAS INLET DAMPER GD1A - INOPERATIVE FROM DESK
58. C/M 5D & 5F HAVE ONLY ONE LUB OIL COOLER
59. BOTTOM RING HEADER INSULATION ESP SIDE - SHEETS HANGING
60. HFO PUMP 5C - STEAM LEAKAGE NEAR SUCTION V/V
61. IMPULSE LINE OF ECONOMISER FEED LINE HEAVY LEAKAGE
62. ID FAN A,B,C,D - DROP BY DROP OIL LEAKAGE FROM PRESSURE GAUGES
63. BCW PUMP 5A/5B/5C ITS ACW COOLER INLET AND OUTLET V/V JAM SERVICING REQ.
64. PAH-5A/5B SAH-5A/5B ITS PRESSURE GUAGE AND TEMP. GUAGES LOP CALIBRATION REQ.
65. ACW FD-5A/5B PA FAN-5A/5B PRESSURE AND TEMP. GUAGES FAULTY AND CALIBRATION
REQ.
66. C/M-5A TO 5H MOTOR TEMP. GUAGES ARE FAULTY AND CALIBRATION REQ.
67. ESP PASS -A/B/C/D FIELD AND CRM/ERM PANEL BOX DISPLACED AND GROUND
POSITIONCALIBRATION AND REPL. REQ.

LIST OF THE MAJOR WORKS PLANNED DURINGANNUAL OVERHAUL:


BOILER MAINTENANCE SECTION :
1) BOILER PRESSURE PARTS:
a) Repairs of Water Wall:
1. Tubes with more than 25% erosion will be replaced.
2. Tubes with more than 25% erosion will be replaced.
3.
4.
5.
6.
7.
8.

Sacrificial S.S. shields are put in coal/Air Carried out and also at 9 M level.
Welding of trapezoidal wear bar between two tubes of side wall near neck tubes.
Repair of Z panel hangers in cat house
Attending air ingress through Z panel scallop bar
Replacement of damaged insulation in SB and pent house area
Metallurgical analysis of WW tubes for deposit analysis.

b) Wall RH :
1. Eroded RH Bends and liners will be replaced.
2. Alignment of wall RH tubes near div. Panel will be done.

30

c) Repairs of Div.Panels :
1. Replacement of eroded S.C. spacer tube.
2. Fitting of flexible connectors.
3. Replacement of distorted girdling loops and fitting of flexible connectors.

d) Repairs of PSH :
1.
2.
3.
4.
5.

Radiography of site welding joints in ckt no 1 of thick 9.5 mm


Replacement of eroded and distorted tubes.
Refitting of damaged flexible connectors
Replacement of SC spacer
Welding of SS pads.

e) Repairs of RH (rear) :
1. Position of mechanical binders in rear RH will be changed to avoid further fretting
2. Visual Inspection of RH outlet header stubs for overheating
3. Alignment of coils no 41 to 46 without cutting the tubes

f) Repairs of RH (Front) :
1. Inspection steam cooled spacer tube and its connectors for fretting

g) Repairs of screen tube :


1. Replacement of eroded tubes and bends at bottom and top.

h) Repairs of LTSH :
1. Lifting of assay no 1,3,56 and 58 for inspection in upper LTSH.
2. Eroded tubes and bends at inlet and terminal will be replaced as per thickness report.

i) Repairs of ECO (upper) :


1. Lifting of assy no 1,3,63,65 for inspection
2. Lifting of coils with misaligned tubes
3. Eroded tubes and bends will be replaced.
4. Inspection of eroded 90 deg. bends near header of coil no 1, 2, 3, 128, 129, 130

31

j) Repairs of ECO (middle and lower) :


1. Lifting of coils with misaligned tubes
2. Eroded tubes and bends will be replaced.
3. Repairs of cassette baffles

h) Repairs of steam cooled wall :


1. Inspection of bends of manholes and LRSB openings and replacement of eroded bends

2) Other :
a) Inspection of drum :
1. Inspection and cleaning of drum internally.
2. Checking of phosphate dozing line, feed line for any damage.

b) Inspection of bottom ring header :


1. Inspection of orifices from bottom ring header, after blowing air and after hydraulic test for any
blockage.

c) Repairs in pent house :


1. DP and MPI testing of all stub welding of Pl. S.H. inlet header will be carried out.
2. Sealing ropes of peep holes and manholes will be replaced.
3. Replacement of gaskets of peep holes and manholes
4. Leakages through skin welding of roof will be attended by replacing warped skin plate.
5. Cleaning of Sky climber rope opening in pent house.
d) BCW Pumps :
1. Cleaning of coolers- 3 nos
e) Servicing of safety valve :
1. Servicing of Drum, SH, RH, PRDS, SB safety valves
2. In-site seat cutting if required

32

3. Pressure testing of safety valves

f) Servicing of HP valves :
1. Servicing of SH spray Isol. Valves- 8 nos
2. Servicing of RH spray Isol. Valves- 8 nos
3. Servicing of SH drain valves at 26 m- 16 nos
4. Servicing of drum vents, SH vents, RH vents, Boiler drain valves at 0 m
5. Servicing of PRDS inlet isol. Valve, NRV and ASP16
6. Replacement of gland packing of 2" valves- 50 nos
7. Replacement of gland packing of 1" valves- 50 nos

g)
1.

Servicing of burner tilt :


Servicing of burner tilt

2. Synchronization of all coal and air tips will be ensured.


3. Freeness of burner tilt operation for 30 degree will be ensured.

h) Servicing of APH :
1. Inspection of guide bearing in position.
2. Inspection of support bearings in position
3. Replacement of all radial and bypass seals.
4. Replacement of axial seals
5. Cleaning of all baskets by hydro jetting
6. Replacement of rotor angle, T-bar, support grills

i) Servicing of dampers / gates :


1. Repair of APH inlet and outlet gas dampers
2. Servicing of APH inlet and outlet air dampers

33

3. Servicing of actuators-16 nos

j)

Servicing of ID,PA,FD Fans

1. Inspection of bearings.
2. Checking bearing clearances.
3. Servicing of IGV.
4. Replacement of PA Fan-A both bearings along with housing.
5. Servicing of PA/FD discharge dampers/gate

3) ESP:
a) Repairs of Bottom Ash Hopper :
1

Inspection& repairs of damaged refractory.

2. Inspection & repairs of SS wire mesh.


3. Inspection & repairs of SS seal plates.
4. Inspection & repairs of refractory cooling water system.
5. Inspection & repairs of hopper flushing nozzles.
6. Repairs of bottom ash hopper by welding.

b) Servicing of ash feed gates, bottom ash hyjectors& HP / LP Water Valves .


1.
2.
3.
4.
5.

Inspection & repairs of ash feed gate.


Overhaul of bottom ash hyjectors.
Overhaul of SG roll clinker grinder.
Servicing of HP & LP water valves.
Replacement of damaged HP & LP water pipe lines.

c) Servicing / Repairing of Corse Ash Evacuation System


1.
2.
3.
4.
5.
6.

Servicing of feeder ejectors.


Gland 6 mm:
Valve plates:
Consumable set:
Jet pump spares
MSERW Pipes 200, 100, 80 NB

d) Servicing / Repairing of Fly ash Evacuation System :

34

1. Servicing of feeder ejectors assembly.


2.
3.
4.
5.
6.

Servicing of feeder ejectors


Gland 6 mm
Valve plates
Consumable set:
Replacement of damaged HP water Pipe lines.

e) Repairs of Flue Gas duct from Eco outlet to ESP inlet area (LHS & RHS). Removal of
ash & debris from duct & stack hopper :
1. MS plates 3.15 to 12 mm thick
2. Bracing pipes of various Dia.

f) Overhauling / Repairs of complete Electrostatic Precipitator:


1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.

CRM shafts
CRM Hammers
ERM shafts (V/H): Sets each.
ERM hammers
Set ring
Shock bar guide angle
Shock bar assembly
Inner arms
Plain brgs
Bush bearings
Thrust bearing
Cup Washers
Sleeve Tube 50mm.
Sleeve Tube 40 mm.
GD Screens.

g) CFD of flue gas & hot gas duct & rectication thereoff :
i)

Diversion plates, chemical bonded refractory.

h)

Replacement of Metallic Expansion Joints of flue gas duct :

1. Eco O/L, PAH Horizantal duct, ESP I/L duct

i) Replacement of Fabric Expansion Joints of flue gas duct :


1. APH vertical duct, PAH Horizantal duct, APH O/L horizantal duct
j)

Replacement of Worn out coal pipes and bends :

1. Proper scaffolding for replacement of pipes and bends.


2. Replacement of coupling rubber gaskets

35

k)
1.
2.
3.
4.

Servicing & replacement of classifier vanes:

l)

Servicing of coal mill drive air system :

Proper scaffolding
Inspection of vanes
Replacement of vanes
Servicing of vanes

1. Removal of bowl hub skirt.


2. Check the gap between inner ring and outer ring and fitment as per requirement.
3. MDV flap

m) Servicing / Repairing HAG/CAD/ actuators /CF gates / seal air fan filters 1. Servicing / repairing of hot air gates and dampers.
2. Servicing / repairing of cold air gates and dampers.
3. Servicing / repairing of CF inlet and bunker outlet gates.
4. Cleaning of seal air fan filters.

4) CAPITAL OH of coal mill & coal feeder of 5A/5B/5C/5F


TURBINE MAINTENANCE SECTION
1) HP TURBINE OVERHAUL:
1. Removal of Spray Insulation & Piping
2. Dismantling of HP module .
3. Re-Assembly
4. Steam Flow Path Clearance Checking
5. Assembly Checks and Correction

2) IP TURBINE OVERHAUL:
1. Removal of Spray Insulation & Piping
2. Dismantling of IP Module & Dismantling checks
3. Alumina Blast Cleaning of Rotor and casing
4. IP Gland seal clearance checking & setting.
5. Steam Flow Path checking

36

6. Inspection of Blades and Fact Finding


7. Assembly checks and correction
8. Assembly of IP module & Restoring of piping.
9. Checking & Correction of Pipe Pull in HRH pipes.

3) LP TURBINE OVERHAUL :
1. Dismantling of LP & Dismantling Checks
2. Removal of rotor, inspection & Alumina Blasting
3. DPT & MPI of Free Standing Blades of LP
4. NFT of Free Standing Blades of LP
5.Casing Alumina Blasting
6. Inner-Inner casing Ovality & Steam Flow Path Check
7. Placement of Rotor in Position, checking of clearance
8. Box up of LPT turbine
9. LP Gland Box Clearance adjustment of Labyrinth
10. Hot well inspection

4. GENERATOR & EXCITER :


1. Generator Rotor Thread out .
2. Leakages test of Hydrogen System
3. Inspection of Seal Bearing
5.
1.
2.
3.
4.

TURBINE VALVES

:
HP Stop & Control Valve
IP Stop & Control Valve
LP Bypass Stop & Control Valves
CRH & Exraction FCNRV's

6. HP BYPASS VALVE SERVICING :


1. Valves Servicing and Internal inspection
7. GOVERNING SYSTEM :
1. Setting of Governing System Charecterstics
2. All Accumalators N2 Pressure Checking & Filling
8.
1.
2.
3.
4.
5.
6.
7.

BEARING (7 NOS ) :
Dimensional checks of journal /bearings/keys etc
Bearing UT & DPT, Bearing Bedding Inspection
Oil Catcher Fins Renewal
Replacemnt of Jacking Oil Hoses
Bottom Saddle & Torus piece checking & correction
Bearing no. 5 ,6 & 7 -IR cheaking of bearing insulation
Check Labyrinth Rings and replace seal strips

9. LUB OIL SYSTEM :


1. Bucket strainer cleaning & Lub Oil filter cleaning

37

2. JOP ilter Cleaning / Replacement.


10. MOT COOLER :
1. Cooler Cleaning.

11.
1.
2.
3.

MAIN OIL PUMP (MOP) :


Inspection and Overahuling of MOP.
Checking of various parts of MOP for clearance.
Checking of Bearing and matching

12. COOLERS :
1. H2 cooler Cleaning & Hydraulic testing.
2. Exiter Coolers Cleaning & Hydraulic testing.
13. HPT/IPT & VALVES :
1. Spray insulation of HPT/IPT & Valves
14. HRH / MS STRAINER :
1. Inspection & Bonnet Seal Replacement
15. COOLERS CLEANING & HYDRAULIC TEST:
1. MDBFP Coolers ( 8 Nos. )
2. TDBFP Coolers ( 4 Nos. )
3. Vaccum Pump Coolers ( 2 Nos. )
4. Primary Water Coolers( 3 nos. )
5. Seal oil Coolers ( H2+ Air Side ) 4 Nos
6. GTR Coolers ( 6 Nos. )
7. FRF Coolers( 2 Nos. )
16. CONDENSER TUBE CLEANING :
1. Cleaning By Bullet Shot
2. Gravity Test

17. HP VALVES / NRV INSPECTION & SERVICING :


1. MS & HRH strainer drain valves (MS-502, 504, 506 & 508 HR - 113, 502, 504, 506 & 508 , MAL
2.
3.
4.
5.
6.

11,12,13,14, 22,26,28,34,54,65,66) ,MS 104.


HP Heater Extraction Valves ( EX : 1A & 2A) & EX-1,2,3,4,5,
BD ( Iso.), BPE-1 & 2, HPB 101 & 102 FD : 56 & 58.
AS-2, 3, 4, 9, 10, 11 & 12.
TDBFP Valve EX27,28,29,30, 31 & 32.
Passing Valves as per defect list.

18. ACW LINE VALVES SERVICING :


1. H2 Cooler I/L & O/L ( 8 + 1 nos. )
2. Exciter cooler I/L & O/L ( 4 nos. )

38

3. Vacuum Pump Coolers I/L & O/L ( 4 Nos. )


4. MOT coolers I/L & O/L ( 4 nos. )
5. TDBFP A & B coolers ( 16 nos. )
6. MDBFP C & D coolers main I/L & O/L (4nos. )
7. Seal Oil Coolers ( H2 + Air ) 8 nos.
8. SAC / IAC ( 21 nos )
9. LPBP Water Injection ( 5 nos. )
10. FRF coolers ( 4 + 1 nos. )
11. PW Coolers ( 6 + 1 nos. )
12. GTR R-Y-B I/L ( 9 nos. )
19. FEED STORAGE TANK ,DEAERATOR INSPECTION:
1. Inspection and cleaning of FST & Deaerator
2. Checking of Deaerator Nozzle and replacement

20. HP & LP HEATERS :


1. Internal inspection, Conducting Tube leakage test
21. CEP -5A :
1. Pump Overhaul
22. CEP RC VALVES :
1. Recirculation Valve Internal Inspection
23. ALL BFP'S VALVE SERVICING :
1. Suction Valve
2. Superheater Spray Valve
3. R/H Spray Valve
4. TDBFP-5A & 5B RC valve replacement
5. TDBFP-5BMain
6. Pump Cartridge Replacement

24. VACUUM PUMP 5A :


1. Pump Overhaul

25. TDBFP A & B :


1. Tank Cleaning
2. All AOP & JOP Filter Cleaning

OUT DOOR PLANT MAINTENANCE


A. VALVE REPLACEMENT/SERVICING:
1. A, B Series suction KGV servicing /Replacement work
2. Fly ash Sump Selection Valve replacement/servicing.
3. Bottom ash Sump Selection Valve servicing/replacement.
4. RAW water inlet valve 500 NB servicing/replacement.

39

5. RAW water inlet valve 350NB servicing


6. ETP v/v servicing
7. Series drain Valve replacement/ servicing work
8. Seal water line, cooling water line valves replacement/ servicing work
a) HPAWP/LPAWP Inlet & outlet valve servicing work
b) HPSWP/LPSWP Inlet& outlet valve servicing work

B. CLEANING WORK :
1. Ash water Tank cleaning work
2. Seal water Tank cleaning work
3. Drain sump Cleaning Work
4. Ash Surry sump cleaning work

C. FLUSHING NOZZLE REPLACEMENT :


1. Bottom Ash sump, Fly Ash Sump, A, B, C sump, flushing nozzle And its line replacement work

D. STRAINER AND NRV SERVICING:


1. HPAWP/LPAWP NRV & strainer servicing work.
E. GRATING AND SUPPORT REPLACEMENT:
1. A, B, C sump damaged grating replacement work
2. Bottom ash & Fly ash trench grating Replacement work
3. Various Pipe support replacement/ strengthening work

F. PIPES REPLACEMENT:
1. 5A line- sump suction bends checking, suction pipe replacement, ASDP-3 expander to bend & bend to
reducer replacement, ASDP-4 bend to bend repl.
2. 5B line- sump suction bend checking, sump suction pipe replacement, BSDP-1 HP repl, BSDP-2 HP &
VP repl, BSDP-3 expander to bend, bend to reducer repl, BSDP-4 bend to bend repl.
3. 5C line-sump suction bend checking, sump suction pipe replacement, CSDP-1 HP & VP repl, CSDP-2
HP & VP repl, CSDP-3 expander to bend, bend to bend, bend to reducer repl, CSDP-4 expander to
bend, bend to bend repl.

40

4. Seal water pump eroded line replacement work


5. Seal water, cooling Water, air system rusted line replacement work

G.CT FAN O/H:


1. CT FAN O/H
2. CT FAN GB O/H

H. CT POND:
1. Work of cleaning of CT pond area, outlet strainer of CT Pond Repairing.
2. Work of both side nozzle replacement which are missing & nozzle cleaning of tower 5A & 5B
3. Overhauling of CCW 5A
4. ACW Pumps Thrust bearing oil replacement 5A, B, C
5. CCW Pumps Thrust bearing oil replacement 5B, C, D
6. CCW Pumps gland replacement 5B, C, D
7. ACW Pumps gland replacement 5A, B, C
8. CCW Pump Butterfly valve Hydraulic system servicing & power pack oil replacement 5B, C, D
9. ACW/CCW pumps suction strainer repairing & fitting work
10. ACW/CCW SUMP CLEANING WORK and hydro cone checking

I. VALVE SERVICING/REPLACEMANTWORK:
1. Work of ACW recirculation / outlet line's valves, discharge line valves, vent valve checking,
repairing/replacement
2. Work of repairing /replacement of riser valves of cooling tower 5A & 5B
3. Work of checking, repairing/replacement of Blow down valves of CT 5A & 5B
4. CCW pump butterfly v/v seal ring replacement

J. SUPPORT AND APPROACH PROVIDING:


1. Work of CT fan cells approach way railing & gear box protection cage railing repairing work
2. Drift eliminator cleaning
3. CT Fan foundation frame replacement/ reconditioning CT Fan
4. Hot water asbestos cement (broken) pipe replacement
5. Hot water pipe Header painting & riser v/v painting

41

6. Work of cleaning of Hot water Basin of cooling tower Unit-5 at cstps, Chandrapur.

ELECTRICAL MAINTENANCE
1.

GENERATOR / GEN. EXCITER:


Preventive Maintenance of Generator PT cubicle & NGR.
PMG & Pilot excitor
Diode wheel assemble
Preventive Mainenance of Generator PT cubicle & NCR"

2. BATTERY MAINTENANCE:
P/M & Capacity Test of +/- 24V G1/G2 Battery sets.
P/M & Capacity Test of Station Battery set for battery set1&2 and UPS Battery set.

3. HT TRANSFORMERS:
A. 400KV Connections :
400KV side HV bushing & LA connection tightness of GTR-5R/5Y/5B.

B. Internal inspection of GTR 5Y, UAT-5B & 5D :

Complete draining of oil.


Internal inspection through inspection window carried out& attending defect if any found.
Replacement of MOG along with float, gauge glass, PRV.
Replacement of gasket & activated alumina if required.
Oil Filteration work.
Assistance in cooler testing if required.
External cleaning of surface,Applying first coat of red oxideand two coat of epoxy paint, writing

identification/name plate.
Replacement of rubber bellow if required.

C. Oil filteration of GTR-5R, UAT-5A,5C,SAT-3B:

Oil folteration arrangement and filteration of oil to be carry out.


Leakage attending or attending defect if any found.
Oil Filteration
Assistance in cooler testing if required.
External cleaning of surface.
Replacement of rubber bellow if required.

D.

P/M of X'mers , M. B. & NGRs of GTR-5R/ 5Y/ 5B, UAT-5A /5B/ 5C/5D, Stn-3, SAT 3A/B:
Tightness checking of HV / LV connections
Silica gel replacement.
Oil topping up , if required

42

E.

Oil lekage attending , if any


Rubber bellow replacement , if required
NGRs / MBs Preventive maintainance.
Painting of GTR-5R,5Y,5B:
Cleaning of transformer .
Painting of transforrmer as per scope of work.

F. Preventive Maintenance of Generator & UAT Bus Duct and painting of Generator and
UAT bus duct outside A-axis:

Opening and closing of inspection window covers.


Checking & cleaning of insulators, rubber bellows and replacement if required.
Sealing of unwanted openings using sealant.
External & internal cleaning of bus duct.
Cleaning and painting of outer surface with one coat red oxide and two coat of paint

G.

Work of replacement of black metal of GTR-5R,5Y,5B;UAT-5A,5B,5C,5D; ST-3;SAT-3A,3B


Removing of old black metal
Cleaning of surafce , removing of bush tree
Spreading of new black metal of existing size.
Dumping of removed black metal as per instruction of site incharge.

H.

P/M of Dry Type Transformer 5XA, 5XB, OXA1, OXA2 LXA1, LXA2 :

4.
A.

HT MOTORS:
Overhauling of HT motors ID fan 5A,5D ; PA FAN 5A ; FD FAN 5B :

Opening of doors of the X'mer


Cleaning of X'mer with air
Tightness checking of HV / LV connections
including tap changer
Rubber bellow replacement, if required
NGRs / MBs Prev. Maint.
IR measurement

Removal of power cable, earthing connections, control cables etc


Shifting of motor to repair bay.
Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.

43

Box up of motor completely


Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.
Coal mill motors 5A, 5B, 5F.

B. P/M of HT Motors :COAL MILL- 5C,5D,5E, 5G, 5H; BCW-5A, 5B, 5C; CEP-5A/5B/5C;

MDBFP 5C,5D; ID 5B, 5C:


Cleaning & Connection Tightness checking at motor and switchgear end& rectification, if required.
IR value measurement
Silica gel replacement of power JB .
C.

Cooler Cleaning of HT motors, PA-5A, 5B; MDBFP-5C, 5D:


Dismantling of I/L & O/L pipelines.
Removal of coolers with Hydra or EOT crane.
Cleaning of coolers with brush, cleaning agent.
Hydraulic testing of cooler.
Restoration of cooler along with pipelines.

5. LT MOTORS
A. Overhauling of critical LT motors SAF-5A,5B; Vaccum pump-5A; AC scanner fan;
control fluid-5A,5B; AC-JOP; Main Turbine AOP-1,2; SOP-1,2; PAH 5A/5B 1,2; SAH5A/5B
1,2; TDBFP AOP 5A/5B 1,2:

Shifting of motor to repair bay.


Removal of power cable, earthing
connections, control cables etc
Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.
Box up of motor completely
Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.

B. Coal Feeder motor overhauling works along with DE side pinion hrading and check nut
provision:
Removal of power cable, earthing
connections, control cables etc

44

Shifting of motor to repair bay.


Dismentalling of motor completely
Replacement of bearings, if required.
Stator & rotor varnishing.
DE side pinion check nut provision works.
Box up of motor completely
Shifting of motor to the location.
Alignment of motor with the gear box
Normalization of motor & trial.

C. Preventive Maintenance of LT Motors of unit # 5:


Cleaning & Connection Tightness checking at motor and switchgear end & rectification , if required.

6.
A.

HT/LT SWITCH-GEARS:
P/M of Unit Board 5A, 5B,5C, 5D,5E:
Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty component.
IR measurement.

B. PM of 5PA , 5MA , 5MB, 5MC, 5MD, 5EMPA , 5ME, 5MG, Soot blower Boards:

Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty components.
IR measurement.

C. PM of DCDBbs ODA, ODB Boards

Cleaning of panels & Power Connection Tightness checking and rectification, if required.
Servicing of Breakers.
Replacement of faulty components.
IR measurement.

7.
A.

AHP/ESP MAINTENANCE:

Maintenance of ESP A Pass, B Pass, C Pass, D Pass:


Prev.Maint.of 5EPPA,5EPPB,5EPPC,5EPPD/ ACP panels
Prev.Maint.of ESP A-Pass/B-Pass/C-Pass/D-pass
fields,hopper heaters / support & shaft

insulators heaters
Prev.Maint.of all ERM / CRM of A-Pass/B-Pass/C-Pass/D-Pass
Prev. Main. of 5EPXA X'mer/5EPXB X'mer/5EPXC X'mer/5 EPXD X'mer.
B. Retrofitting of 3.3 KV HV Breaker by HT contactor :

45

Retroffiting work as per order.

C. Maintenance of AHP:
P/M of 5AHS 3.3 KV BOARD
P/M OF 5AHPA 415 VOLTS BOARD.

D. Preventive maintenance of rectiformer:

Checking of power connection & rectify if found defective.


Oil leakge arresting by tightening of gasket.
Replacement of HV bushing oil if found leakage .
Through Cleaning of rectiformers.

E. PM of ESP Heater along with replacement if required & preventive maintenance of


ERM/CRM motors:
Checking of all ESP heater and replacement if required.
Cleaning of Insulator.
PM of all CRM/ERM motor and replacement if required.

8. COMPRESSOR ROOM :
A. Preventive Maintenance of DG set:
Cleaning of panels & Power Connection Tightness checking and rectification, if required
Servicing of Breakers.

9. LIGHTING / WELDING SUPPLY:


Electrical supply to various Agencies woking for capital O/H of the unit.

INSTRUMENTATION & CONTROLS


A. Removal, Servicing and Normalization of 16 Nos. of HEA Igniters with Power Cylinder, Limit
Switches and Igniter Transformer.
Removal and restoration of 16Nos. HEA spark rod assemblies after Servicing, Repairing if Reqd,
Testing Healthiness of Spark Tip, HT Cable with Transformer & Limit Switches with remote Trials.

B. Removal, Servicing, cleaning, checking, calibration and Normalization of 28 Nos. of Flame


scanners.
Removal, Servicing, cleaning, replacement of PCBs, sensing glass etc., checking healthiness of flame
sensitivity, calibration and Normalization of 28 Nos. of Flame scanners.

46

C. Servicing of SADC Power Cylinder.


Removal & restoration of 64 nos. SADC power cylinders after servicing of Positioners, Pilot assembly,
painting Stroke Calibration with remote joint trial.
8 nos. of air line filter regulators servicing & restoration ( 2nos. in each corner)

D. Mill O/L Temp. T/Cs checking, Thermo well checking , replacement if found faulty and both
point availability/checking.
Removal , Cleaning , Re-mounting, Connection normalization of Mill O/L T/Cs with T/WS.
Cable laying for T/C 2nd point.

E. Flushing of 100 nos. Impulse Line.


Disconnection of instrument impulse pipe , Flushing & re-connection with Teflon tape.

F. Servicing of Bottom Ash / Burner Tilt / PA Fan guide vane power cylinder.
De-linking, Removal, Dismantling, Servicing of Power Cylinder, Seal replacement, Assembling ,
Testing for Zero leakages with full air pressure.
G. TRBs / TRTs / JBs cleaning, Painting Sealing, connections tightening & Broken TBs
replacement.
Cleaning and Painting of TRBs / JBs
Broken T.Bs replacement
connection tightening after rail cleaning.
H. Removal and Restoration of all corner solenoid/C/M HAG & reject gate solenoid along with
tubing & leak isolating valve checking/ replacement.
Removal, cleaning and restoration of all solenoid valves along tubing of all corner-56nos.
Removal, cleaning and restoration of all solenoid valves along tubing of C/M HAG-8no.
Removal, cleaning and restoration of all solenoid valves along tubing of C/M RG sol-16no
All leak/passing instrument isolating valves checking/ replacement.-100nos

I.

Servicing of C/Ms HAG/ all corner solenoid, Limit Switches & air line, oil filter cleaning and oil
top up.
Removal, cleaning & contact functional checking of L/S(16 no)
Filter element removal, cleaning & fresh oil top up.
All corner solenoid- 56nos.

J. Servicing/ Calibration of Boiler and Turbine side control valves- 75 nos.


Removal, Servicing , Remounting, Calibration of Stroke with PFT.
servicing/cleaning and calibration of E/P converters, Air lock relays, Air filter regulators

47

K.

1.

1.
2.

Calibration of
Servicing of Positioners, pilot assemblies, an lock relays, E/P converters, Air line regulators.
C/MS CAD/HAD 16nos.
Calibration of stroke with PFT& remote trial.
Burner tilt.
PA Fan vane

L. Servicing and calibration of ID/FD/PA/BCWP/ CWBP all instruments & protection trial.
Removal, Servicing, Calibration.
Re-mounting as per B/M ,T/M & E/M Schedule

M.

(a)

(b)

Removal / Calibration & Re-mounting of


Removal, Cleaning, Calibration
PA Hdr Press. Switches.
Re-mounting after impulse line flushing
Furnace Press. Switches.
Connections normalization & isolating manifold valve position normalization

N. Servicing of C/Ms Seal air valve power cylinders with Solenoids & Limit Switches
Removal, Servicing Testing of Power Cylinders
Servicing & Testing of Solenoids and Limit Switches
O. Removal & Normali-sation of Boiler side Instruments as per B/M II , E/M II requirement .
Removal of Connections/ Instruments
Normalization after clearance

P.

Internal Inspection of O2 Probe & Replacement of guide pipes & V guards.


O2 LHS/RHS disconnection removal, inspection.
Replacement of Protective tube & V guard strengthening.
Calibration

Q.

Removal & Restoration of all elevation pressure gauges.


Removal of all corners press gauges.
Cleaning of all gauges.
Calibration of all Gauges.

R. Removal, mounting, laying, dressing & checking of SH/RH metal temp thermo-couples as per
BM-II schedule.
Removing of T/C as per BM-II.

48

Checking and Replacement if found faulty.


Restoration after BM-II clearance
Connection cleaning, tightening, signal checking upto panel.

S.

Attending of all S/D defects /Modifications:Calibration of critical and Non-critical Instruments as per List / Schedules 200 nos.
Confirm validity of MCAL/ SMCAL
Removal; of Instrument & Cleaning
Calibration & ISO Tagging
Remounting & Normalization

T. Removal of ESP / Coarse Ash / FGDH / Economizer A/V & W/V Solenoid after B/M II clearance
B/M II Clearance & removal of Solenoids.

U.

Removal, Servicing and painting of ESP/Coarse ash power cylinder.


Servicing & Testing of Solenoids
Removal cleaning, servicing, checking and painting of power cylinder.
Re- installation of Solenoids after B/M II clearance
Local Remote Joint Trial.
ESP all rows air filter regulators servicing & accumulator oil level top up.

V. Removal / Servicing & Remounting of AHP Ash water make up valves, series sump make
valves, ETP valves, RC valves, suction valves solenoids as per ODP II schedules.
Removal, cleaning / Servicing of Solenoids.
Remounting & joint trial

W. AHP A/B/C Series & HP Ash water tank Level controller testing after Sensor Cable & bolt
replacement
Removal of Old cables with bolts & replacement by new.
Ckt testing & Protection trial
Calibration of all series seal Water Press Switches, HP Ash Water Disch. Press. Switches

X.

Calibration of Bottom ash/PAH/SAH/FGDH/Economizer/ESP/AHP all instrument.


Removal &cleaning of press. gauges.
Calibration & tagging.
Remounting & connection normalization.

Y. Calibration of Boiler drum press. Gauges.


Removal, Cleaning & Calibration.

49

Z. ID/FD/PA/BCWP protection Trials

AA. Boiler protection Trial.

AB. Replacement/ Retrofitting of MOT and FRF tank Level Amplifiers with Cali-bration.
Removal, Cleaning, Calibration of probe with amplifier units & tagging.

AC. Removal, Servicing/ Testing & restoration of HPT/ITP top/bottom & TSE thermocouples with
T/W.
Removal, Cleaning & testing of T/CS with T/WS & Tagging.
Restoration after T/M-II clearance.
AD. Removal, Cleaning, testing & restoration of LPT exhaust Hood T/CS & RTD.
Removal, Cleaning, testing, tagging & restoration after T/M-II Clearance.

AE. Disconnection of HP/IP stop & Control valves Limit switches & PFTS.
Disconnection of HP/IP stop & Cvs LS & PFTs
Restoration after T/M-II Clearance.

AF.Disconnection & removed of HP/IP ATT valves motors.


Disconnection & Removal of ATT motors.
Restoration after T/M-II clearance.
AG. Disconnection & removal of LPBP 1 & 2 stop control & water Injection Limit switches &
PFTS.
Disconnection & Removal of Limit switches & PFTS.
Cleaning, testing & restoration after T/M-II clearence.

AH. I.P. inner casing TSE T/C 4 Nos.


Removal, testing and replacement Removal of T/CS & replacement by new terted T/Cs.

AI. Removal,Calibration and normalisation ,Retrofit-ting of main turbine turbovisory instru-ments


and EHG unit.
Removal of existing instrument.
Installation of new instruments.
Made such facility so that Signal of instruments available upto panel.

50

AJ.Disconnection, removal, servicing of HPBP1, HPBP2, FOD-1 & 2, BPE1, BPE2, BD valve servo &
Blocking element, both tank & suction filter cleaning.
Depressurization, disconnection of hoses & removal of servo/blocking element, servicing line & micro
filter
Line filters removal & line flushing.
Fresh oil top up, valves Calibration after T/M-II clearance & servo/ blocking unit restoration.

AK. Seal /leak off steam valve sump, Filter & Servo-unit Cleaning, Calibration, and Normalization.
Sump oil removal, cleaning.
Filter cleaning.
Servo unit cleaning
New oil top up
Stroke with PFT calibration.
Remote trial.

AL.Removal and Normalization of Turbine side instru-ments as per TM-II & EMII requirement
Supply isolation, connec-tion removal and cleaning.
Restoration & trial after TM-II/EM-II Clearance.

AM.Removal, Cleaning, Calibration of HOT & Cold gas Primary water RTDS/ Temp. Switches &
Acw I/L/OL RTDS
Supply isolation, dis-connection & instruments removal
Cleaning, Calibration
Restoration after T/M-II Clearance.
AN. Disconnection, Removal & restoration of Generator seal oil TE & EE RTDS, Prechamber
Level Probe Gas Cooler I/L & O/L RTDS.
Supply isolation, dis-connection & instruments removal
Cleaning, checking & Calibration
Restoration after T/M-II Clearance.
AO. Main Exciter Hot/Cold air instruments removal, Calibration & restoration as per TM-II
schedule.
Supply isolation, dis-connection & instruments removal
Cleaning, checking & Calibration
Restoration after T/M-II Clearance.

AP.Removal & Servicing of CRH NRVs Limit switches assemblies LHS & RHS.
Dis-connection & removal of LS assemblies.
Servicing & testing
Restoration after T/M-II Clearance.

51

AQ. Removal, Cleaning, Calibration of all Press. Switches, Press. Gauges,Temp. switches temp.
gauges, transmitters, RTDs of Dis-connection, removal Cleaning, checking & Calibration
i) Lub. Oil& Turbine drain oil system.
Repair / Replacement of defective instruments
ii) Control Fluid system.
Restoration after T/M-II Clearance.
i.
Governing racks
ii.
LP bypass system
iii.
HP bypass system
iv.
Primary water system
v.
Gas system
vi.
Seal Oil system inclusive of new ckt.

AR. TDBFP A/B, MDBFP C/D , CEP A/B/C instruments checking, calibration and protection trials.

AS. Provision of PVC tubes for condenser hydraulic test & Hot-well level switches functional
checking.
PVC tube to be provided as per requirements.
AT. LPH -1/2/3, GSC Level switches functional testing with Protocol with operation and TM-II

AU. TDBFP A & B Governing Characteristics & protection trial

AV.Governing Characteristics through EHC & Hydraulic with TM-II & operation

AW. LP bypass stop & CVs with water injection valves remote trials.

AX. Turbine Protection trial.


CPU all valves solenoid checking, trial & replacement if necessary.
CPU bypass valve & DP transmitter calibration & interlock checking .

AY. CPU instrument air valves checking & replacement if necessary.

52

AZ.SWAS room pH & conductivity meters sensors cleaning & ensuring availability of these
signals on DCS.

BA.All air heaters flue gas inlet thermocouple guide pipe provision

BB.Sample isolating valves & blow down needle valves(Whitey make) replacement

TESTING SECTION
A.

Generator relay testing by secondary injection & CT/PT resistance checking.


Current relay testing
Voltage Relay Testing
Power Relay & frequency relay Testing
Impedance Relay Testing
PT fuse replacement and connection tightening
CT/PT Resistance measurement & connections Checking
Annunciations and SOE points checking

B.

Generator Testing a Stator


Rotor
Main & pilot execitor
diode and fuses
GCB Trial and Dynamic Testing of Generator

C.

D.

HT Switch gear Relays testing a Unit Board A


Unit Board B
Unit Board C
Unit Board D
Compressor Switch gear
Station Switch gear(11KV)
AHP switchgear
HT Circuit Breaker operation time & contact resistance measurement and connection

tightening ( Unit Boards)


Unit Board A & B
Unit Board C & D
BTS A/B/C/D Trial
E.

LT Switchgear Relay testing PA/EMPA board relay testing


MA/ME/MD Board relay testing
AHP LT board relay Testing
mics works of HT/LT switchgear

53

PA/EMPA Auto changeover trial and DG set auto pick up trial


F.

GTR / UAT Transformer testing, OTI/WTI calibration and. Protection trials.


GTR R/Y/B Testing
UAT A/B/C/D Testing
SAT 4A/4B Testing
OTI/WTI calibration,and Mech.Protection trials
GTR WATER FLOW , oil pump trial
GTR Bushing

G.

Checking of Battery Chargers.


220 V chargers
24 V chargers
UPS
Misc. works of Transformer side
Motorised valves
Bottom Ash panel/Air compressor panel
Services to operation and other sections and Misc. works

H.

ODP WORKS
CCW transformer testing
CTPA Relay Testing and connection tightening and reguler running work of ODP
CTFAN Panel checking and control room control panel checking/connection tightening
ODP RELAY TESTING WORKS
Regular and other ODP works

PART II
ACTUAL OVERHAUL ACTIVITIES
WORKS CARRIED OUT DURING ANNUAL OVERHAUL OF UNIT # 5

BOILER MAINTENANCE
FURNACE
1. Ring headers orifices checking carried out. Screen fitting work carried out.
2. Drum internal inspection carried out.
a) FIRST PASS :
1. Hydrojetting in WW, Divisional panel , wall reheater, PSH, RH, carried out.
2. Thickness survey at all elevation Water wall, Repeater (RHS) Repeater (LHS), Super heater (RHS)
Super heater (LHS) carried out. Damaged & eroded tubes cuttng and welding at all elevations of WSB
carried out.
3. Burner corner bend welding carried out.
4. DP & PSH repair work carried out.

54

5. Ash removal work in Pent House carried out.


6. Cat house and Dog house cleaning is carried out.
b) SECOND PASS :
1. Screen tubes inspection completed.
2. Economizer upper assy. repair work carried out

As per thickness survey conducted Furnace various tubes marking, Radiography, Repairs/replacement
carried out as follows
JOINT STATUS IS AS BELOWZONE

AGENCY

EX.JONT

MRKD

JT. COMPL

JONT
WATER WALL

SHEL

1500

SHEL

878

878

587

587

587

60

60

60

48

48

48

23

23

23

47

47

47

50

600

548

520

474

532

532

481

50

ADORE
PSH

SHEL

250

ADORE
RE HEATER

SHEL

50

ADORE
SCREEN TUBE

BCC

878

ADORE
DIV PANEL

RADIOGRAPH

VK
ECO(UPPER

BCC

ADDNL)

VK

55

RAPAIR

LTSH

BCC

500

536

536

536

440

440

440

14

14

14

100

83

82

82

3150

3808

3779

3682

VK
ECO (MIDD
&LOW REP.
SH VERT. SP.
ASSY REP.
STEAM

BCC

COOLED WALL

VK

RLA

SHEL

TOTAL

50

c) ID FAN 5A, 5B, 5C & 5D :


1. Lube oil tank, filter and cooler cleaning work carried out.
2. DE & NDE side bearing inspection work completed. Bearing boxed up.
3. Cooler cleaning completed.
4. Impeller cleaning done.

d) FD FAN - 5A, 5B :
1. FD Fan 5B bearing inspection work completed.
2. FD Fan 5A DE side bearing replacement work completed.
3. Duct and Impeller cleaning done.

e) PA FAN -5A, 5B :
1. Bearing inspection work completed.
2. Impeller and IGV gate cleaning done.
3. Gate servicing done.

f) BURNER TILT:
1. Corner No. 1

56

Power cylinder servicing and wind box cleaning done.


All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.

2. Corner no. 2
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.

3. Corner no. 3 Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.
Tie rod servicing completed.
Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.

4. Corner no. 4
Power cylinder servicing and wind box cleaning done.
All air buckets cleaned.

57

Tie rod servicing completed.


Burner compartment repairing work completed.
08 New coal nozzle assy. positioning done. Alignment completed.
Inner cover plate fitted.

g) AIR HEATERS :

1. Air Preheater-5A:
I.

Primary:

All old baskets replaced with new basket


Support and guide bearing inspection work carried out.
Support bearing replacement work completed.
Rotor and sector plate leveling completed.
Guide and Support bearing cooler cleaning done.
Gearbox insp. carried out. Hot & cold end radial seal setting done

II.

Secondary :
All old baskets replaced with new basket
Support and guide bearing inspection work carried out.
Rotor and sector plate leveling completed.
Guide and Support bearing cooler cleaning done.
Gearbox insp. carried out. Hot & cold end radial seal setting done

2. Air Preheater-5B:

58

I.

Primary :

All old baskets replaced with new basket.


Hot& Cold end side sector plates repairs works carried out.
Grating repairs work carried out.
Support and guide bearing inspection completed.
Guide and Support bearing cooler cleaning work completed.
Rotor and sector plate leveling completed.
Seal fitting work is in progress.

II.

Secondary :
All old baskets replaced with new basket.
Hot& Cold end side sector plates repairs works carried out.
Grating repairs work carried out.
Support and guide bearing inspection completed.
Guide and Support bearing cooler cleaning work completed.
Rotor and sector plate leveling completed.
Seal fitting work is in progress.

h) AIR / GAS DAMPERS:

GD-1A, GD-1B servicing done.


GD-2A, 2B servicing done.
GD-3A, 3B servicing done.
GD-4A1, 4A2 replaced by new one.
GD-4B1,4B2 servicing done.

59

i)

HP VALVES :
Following V/Vs servicing / repairing / replacement carried out
High Pressure valves% completed
Sr

Valve
descriptions

Qty

dismantling

Machining

Lapping

Box up HANDOVER
TO
I&C / TEST

MS VALVE

SH Spray
control v/v

RH Spray
control v/v

SH MANUAL
ISO V/V

SH drain valve

10

10

10

10

Safety valve

16

16

16

Zero meter
drain valve

RH MANUAL
ISO V/V

RH SPRAY MOT
ISO. VALVE

10

DRUM VENT

11

STARTUP VENT

60

12

PRDS STATION
VALVE

13

SH SPRAY MOT
ISO. VALVE

14

SB moto, man &


CV

80

77

77

58

15
TOTAL
j)

BCW PUMPS :

1. BCW pump cooler cleaning done

k) COAL MILLS :
I.

COAL MILL A :

1. Type-A overhaul carried out.


2. Air port assembly replaced
3. Air deflectors and vane wheel segment welding carried out.
4. Extension ring top plated welding carried out.
5. Inner seal air ring replaced.
6. Gear box side coupling replaced.
7. Hot air damper close/zero position done.
8. PA duct cleaning done.
9. Scrapper area cleaned.

II.

COAL FEEDER - 5A:


1. Internal inspection carried out.
2. Bunker outlet gate and C/F inlet gate servicing done.
3. Rubber skirt fitting done.
4. Modification of COC base plate done.
5. Belt, pulley, bearings replaced.

61

14

6. G/B oil seal and stud plate modification work carried out.

III.

COAL PIPE A:
1. Pipe and bend 2A1 replaced.
2. 4.5 mtr. pipe on duct and bend 45 degree replaced.
3. Centre pipe replaced, MOE A3, A2 and A4 replaced.
4. 4th corner second bend 2A4 and pipe 2m and 1 m long after and before respect replaced.

I.

COAL MILL B :

1. Type-A overhaul carried out.


2. Center pipe replaced.
3. Ventury joint patch welding done.
4. PA duct cleaning done.
5. Scrapper area cleaned.
6. 5 Nos. of ICP replaced.
7. Coal Mill Lube oil cooler cleaning done.
8. MOE B3 and MOE B2 replaced.
9. HAG/CAG servicing/ calibration done.

II.

COAL FEEDER - B
1. Internal inspection carried out.
2. Bunker outlet gate/inlet gate and C/F inlet gate servicing done.
3. Rubber skirt fitting done.
4. Bunker outlet gate all stud roller replaced.

III.

COAL PIPE - B:
1. Fire corner 1B2 pipe replaced.
2. Send pipe second corner after MOE 4.55 mtr. replaced.
3. 3ed pipe 3ed corner after MOE 1.900 mtr replaced.

62

4. 4th pipe 4th corner after MOE 6.700 mtr replaced.


5. 3ed corner 6th B3 pipe and 2 coupling and 3B3 bend at 9mtr level and 2B2 bend and pipe on duct
replaced.
6. MOE B2 replaced
7. 3ed corner on 9 mtr level 5.5 mtr pipe 6.2 mtr pipe and bend replaced.

I.

COAL MILL C :

1. Type-A overhaul carried out.


2. CAD seal replaced.
3. Centre pipe replaced.
4. MOE C1 and MOE C3 replaced.
5. Inner seal ring replaced.
6. PA duct cleaning done.
7. Scrapper area cleaned.
8. Lop cooler cleaning done
9. Inner coal leakages and ventury patching done.

II.

COAL FEEDER - 5C :
1. Internal inspection carried out.
2. C/F inlet and bunker O/L gate servicing done.
3. Rubber skirt fitting done
4. BOG/FOG bearing and sprocket shaft replaced.
5. COC base plate modification done.
6. Inlet skirt, side skirt, LH-RH 2 nos. extended skirt plate replaced.
7. Rubber belt with 2 nos. bearings replaced.
8. Gear box servicing done.

III.

COAL PIPE C:

63

1. Centre pipe replaced.


2. C1 post pipe replaced
3. MOE C1, C4 and C3 replaced
4. 3ed pipe 3ed corner after MOE 1.700 mtr replaced.
5. Pipe on duct replaced.
6. C1 post pipe 2.7mtr replaced.
7. 1st corner 6.17mtr pipe replaced.
I.

COAL MILL D :

1. Type-A overhaul carried out.


2. PA duct cleaning carried out.
3. Scrapper area cleaned.
4. Center pipe replaced.
5. MOE D3 replaced.
6. 1 nos. inner seal replaced.
7. Bowl hub skirt replaced.
8. Inner cone checked, found fallen in cone same was refitted.
9. Lop cooler cleaning done

II.

COAL FEEDER D :
1. Internal inspection carried out.
2. C/F inlet and bunker o/l gate servicing done.
3. Rubber skirt fitting done.
4. Belt replaced.

III.

COAL PIPE D:
1. Center pipe replaced.
2. MOE D3replacd
3. 2nd bend 2D2 and 2nd pipe after 2D2 bend 1mtr replaced.

64

4. 4th pipe 4th corner 9.00mtr replaced.


5. 3ed corner 45 degree bend and 2.3mtr pipe (over mill) replaced.

I.

COAL MILL E :

1. Type-C overhaul carried out.


2. Bull ring segment replaced.
3. J/A-J2 and J3 replaced.
4. Vane wheel top plate clamping hard facing done.
5. Bowl hub cover top plate welding done.
6. Lop cooler cleaning done
7. PA duct cleaning done.
8. Scrapper area cleaned.
9. Door liner replaced
10. Inner cone and ventury checked found worn out, patching and welding done.

II.

COAL FEEDER - 5E :
1. Internal inspection carried out.
2. Belt replaced.
3. C/F inlet and bunker o/l gate servicing done.
4. Rubber skirt fitting done
5. COC base plate modification done.
6. Center skirt plate (inlet) replaced.
7. Support roller bearing and gear box oil replaced.

III.

COAL PIPE E:

65

1. 1st pipe 1st corner after MOE 5.5 mtr. replaced.


2. 3ed corner after MOE 1.500mtr replaced.
3. 3ed corner 2E3 pipe and bend 30degree and 1.5mtr pipe replaced
4. 4th corner 1E4 replaced.
5. 1st corner MOE replaced.
6. 4th corner 4.2mtr pipe replaced.
7. 3ed corner 1.4 mtr pipe and 30 degree bend replaced.
8. MDV flap E1, E4 replaced.
I.

COAL MILL F :

1. Type-A overhaul carried out.


2. Scrapper liner replaced.
3. Lop cooler cleaning done
4. PA duct cleaning done.
5. Scrapper area cleaned

II.

COAL FEEDER F :
1. Internal inspection carried out.
2. C/F inlet and bunker o/l gate servicing done.
3. Rubber skirt fitting done.
4. Belt replaced
5. COC base plate modification done.
6. Center skirt plate (inlet) and side skirt plate with rubber and extended skirt replaced.
7. Support roller bearing and support rollers replaced.

III.

COAL PIPE F:
1. pipe 1st corner after MOE 2.400mtr replaced.
2. 1st corner 1.2mtr pipe after MOE and MOV replaced.
3. MDV flaps F1, F2, F3 replaced.

I.

COAL MILL G :

1. J1 AND J2 OIL REPLACED.

66

2. PA duct cleaning done.


3. Scrapper area cleaned.
4. Lube oil cooler cleaning done.
5. MDV flap G1 and G3 replaced.
II.

COAL FEEDER - G
1. Internal inspection carried out.
2. C/F inlet and bunker O/L and I/L gate servicing done.
3. Rubber skirt fitting done.
4. COC base plate modification done
5. Skirt plate center, LH-RH, extended modification done.
6. G/B servicing done

III.

COAL PIPE G:
1. 2nd pipe 1G2 2nd corner 3.00mtr replaced.
2. 1st corner 2.4 mtr pipe and 30 degree bend after MOV replaced.
3. MDV flaps G1, G4 replaced.

I.

COAL MILL H :

1. Type-A overhaul carried out.


2. MDV flap H3 and H4 replaced.
3. LOP filter and breather cleaning done.
4. Lop cooler cleaning done
5. PA duct cleaning done.
6. Scrapper area cleaned.

II.

COAL FEEDER H :
1. Coal Feeder internal inspection done.
2. C/F inlet and bunker O/L gate servicing done.
3. Rubber skirt fitting done

67

4. COC base plate modification done.


5. Skirt plate with rubber replaced.
6. Rubber belt with support roller bearing replaced.
III.

COAL PIPE H:
1. 1st corner 2.9mtr pipe and 1B1 bend, 2.4mtr pipe replaced.
2. MDV flaps H3 and H4 replacd.

l)

CAG / CAD :

1. All mills CAG servicing done.


2. All CAD made free.

m) SEAL AIR FANS 5A & 5B :


1. Bearing internal inspection of both fans done.
2. Fan brg. Greasing done.
3. Suction filter cleaning carried out.
4. Damper servicing done.

n)

ESP PASS - A, B, C, D :

1. Water washing carried out.


2. Inlet GD screen replacement work done.
3. All fields internal inspection done.
4. All fields damaged/worn out collecting plates, ERM / CRM top & bottom hammers, bearings, shock
bars, guide angles, pads & pin wheels repairs/replacement work carried out.

68

U = 5 E.S.P. PASS REPAIRED AND REPLACEMENT REPORT1. E.S.P. A PASS :


S.NO.

WORK

1A1

2A1

3A1

4A1

5A1

6A1

DISCRIPTION

1A2

2A2

3A2

4A2

5A2

6A2

57

57

20

15

11

09

230

Replaced

12

12

12

12

45

Replaced

C.R.M.

TOTAL REMARK

Hammer
C.R.M.

Bearings
3

Shock Pads

13

16

12

13

38

Replaced

Shock Bars

12

14

13

Repaired

Replaced

Alignment

C.R.M.

Shafts
C.R.M.

Shafts
7

Guide Angles

10

30

10

78

Replaced

Guide Angles

12

12

52

Alignment

Repaired

56

56

13

20

17

18

233

Replaced

29

24

18

12

12

12

98

Replaced

10

Replaced

Alignment

Hoppers Gas

Screens

10

E.R.M.
Hammers

11

E.R.M.
Bearings

12

E.R.M.
Shafts

13

E.R.M.
Shafts

14

Pin Wheel Big

17

Repaired

15

Pin Wheel Small

19

Repaired

16

Bush Bearings

22

Replaced

17

Vertical Shafts

Replaced

18

Notching Of Plates

18

24

21

10

10

80

Repaired

69

19
20

Collecting Plates

36

150

Repaired

94

Replaced

150

Replaced

40

Replaced

128

Replaced

72

G.D.

128

Screens
23

94

"U"
Clamps

22

E.R.M.
Electrodes

21

60

Deflector Plates

2. E.S.P. B PASS :
S.NO

WORK

1B1

2B1

3B1

4B1

5B1

6B1

DISCRIPTION

1B2

2B2

3B2

4B2

5B2

6B2

57

57

31

27

23

204

Replaced

12

12

14

12

56

Replaced

TOTAL REMARK

C.R.M.
1
Hammer
C.R.M.
2
Bearings
3

Shock Pads

13

12

51

Replaced

Shock Bars

13

11

07

48

Repaired

Replaced

Alignment

C.R.M.
5
Shafts
C.R.M.
6
Shafts
7

Guide Angles

10

10

10

10

10

57

Replaced

Guide Angles

Alignment

50

50

Repaired

56

56

56

31

32

21

202

Replaced

24

24

24

11

12

12

107

Replaced

Hoppers Gas

Screens
E.R.M.

10
Hammers
E.R.M.
11
Bearings

70

E.R.M.
12

10

Replaced

16

14

17

63

Alignment

Shafts
E.R.M.
13
Shafts
14

Pin Wheel Big

18

Repaired

15

Pin Wheel Small

18

Repaired

16

Bush Bearings

40

Replaced

17

Vertical Shafts

26

Replaced

18

Notching Of Plates

11

11

13

10

60

Repaired

19

Collecting Plates

10

30

Repaired

48

Replaced

100

Replaced

45

Replaced

128

Replaced

E.R.M.
20
21

Electrodes

48

"U"

100

Clamps
22

45

G.D.

128

Screens
23

Deflector Plates

3. E.S.P. C PASS
WORK

1C1

2C1

3C1

4C1

5C1

6C1

DISCRIPTION

1C2

2C2

3C2

4C2

5C2

6C2

57

57

57

21

12

211

Replaced

12

12

22

12

65

Replaced

S.NO.

TOTAL REMARK

C.R.M.
1
Hammer
C.R.M.
2
Bearings

71

Shock Pads

15

14

12

10

66

Replaced

Shock Bars

14

10

12

40

Repaired

12

12

Replaced

Alignment

C.R.M.
5
Shafts
C.R.M.
6
Shafts
7

Guide Angles

10

10

10

10

10

50

Replaced

Guide Angles

Alignment

50

50

Repaired

56

56

37

32

24

23

228

Replaced

24

24

24

24

12

12

120

Replaced

16

16

12

12

62

Replaced

12

40

Alignment

Hoppers Gas

Screens
E.R.M.

10
Hammers
E.R.M.
11
Bearings
E.R.M.
12
Shafts
E.R.M.
13
Shafts
14

Pin Wheel Big

24

Repaired

15

Pin Wheel Small

24

Repaired

16

Bush Bearings

48

Replaced

17

Vertical Shafts

32

Replaced

18

Notching Of Plates

11

11

52

Repaired

19

Collecting Plates

24

Repaired

E.R.M.
20
21

Electrodes

25

"U"

100

Clamps
22

G.D.
Screens

23

72

Deflector Plates

25
100

50
100

50
100

4. E.S.P. D PASS
S.NO

WORK

1D1

2D1

3D1

4D1

5D1

6D1

DISCRIPTION

1D2

2D2

3D2

4D2

5D2

6D2

57

57

40

11

183

Replaced

12

12

12

46

Replaced

TOTAL REMARK

C.R.M.
1
Hammer
C.R.M.
2
Bearings
3

Shock Pads

19

10

18

74

Replaced

Shock Bars

10

10

13

49

Repaired

Replaced

Alignment

C.R.M.
5
Shafts
C.R.M.
6
Shafts
7

Guide Angles

10

10

10

10

10

10

60

Replaced

Guide Angles

Alignment

160

160

Repaired

56

56

56

20

21

12

212

Replaced

24

24

24

12

12

12

108

Replaced

Replaced

34

Alignment

Hoppers Gas

Screens
E.R.M.

10
Hammers
E.R.M.
11
Bearings
E.R.M.
12
Shafts
E.R.M.
13
Shafts
14

Pin Wheel Big

24

Repaired

15

Pin Wheel Small

48

Repaired

16

Bush Bearings

48

Replaced

17

Vertical Shafts

48

Replaced

73

18

Notching Of Plates

39

Repaired

19

Collecting Plates

22

Repaired

E.R.M.
20
21

Electrodes

400

"U"

150

Clamps
22

150

160

G.D.

160

39

Screens
23

400

Deflector Plates

39

U = 5 E.S.P. PASS REPAIRED AND REPLACEMENT REPORT:


S.NO.
1
2

WORK
DISCRIPTION
C.R.M.
Hammer
C.R.M.
Bearings

E.S.P. A
PASS

E.S.P. B
PASS

E.S.P. C
PASS

E.S.P. D
PASS

TOTAL
CONSUME

REMARK

230

204

211

183

828

Replaced

45

56

65

46

212

Replaced

Shock Pads

38

51

66

74

229

Replaced

Shock Bars

13

48

40

49

150

Repaired

12

17

Replaced

23

Alignment

5
6

C.R.M.
Shafts
C.R.M.
Shafts

Guide Angles

78

57

50

60

245

Replaced

Guide Angles

52

55

Alignment

Hoppers Gas
Screens

50

50

160

262

Repaired

233

202

228

212

875

Replaced

98

107

120

108

433

Replaced

10
11

74

E.R.M.
Hammers
E.R.M.
Bearings

12
13

E.R.M.
Shafts
E.R.M.
Shafts

10

62

72

Replaced

63

40

34

143

Alignment

14

Pin Wheel Big

17

18

24

24

83

Repaired

15

Pin Wheel Small

19

18

24

48

109

Repaired

16

Bush Bearings

22

40

48

48

158

Replaced

17

Vertical Shafts

26

32

48

106

Replaced

18

Notching Of
Plates

80

60

52

39

231

Repaired

19

Collecting
Plates

30

24

22

78

Repaired

94

48

25

400

567

Replaced

150

100

100

150

500

Replaced

40

45

50

160

295

Replaced

128

128

100

39

395

Replaced

20
21
22
23

E.R.M.
Electrodes
"U"
Clamps
G.D.
Screens
Deflector Plates

o) BOTTOM ASH HOPPER:


1. Seal trough cleaning done.
2. Seal trough corner and center C/M side leakage attended.
3. Seal trough inner side plate repaired.
4. Bottom ash hopper cleaning done.
5. Bottom ash hopper strengthening done.
6. Dome repairing done.
7. 50 N.B. line seal trough line and inspection glass flushing line replaced.
8. 100 N.B. seal trough filling header at seal trough header level and bottom ash flushing line 90 m and 9
m bend fabricated.
9. Damaged LP ash water pipe line 150NB replaced.

75

10. 200 N.B HP line 17 m and 5 bend replaced.


11. 178 tons refractory gun netting done.
12. 4 No. of surge box repaired.
13. Refractory cooling water line, hopper flushing line 100 NB replaced, 02Nos.bendfabricated.
14. Bottom ash refractory replacement works carried out.
15. 210 RMT M.S. welding done.

p) CLINKER GRINDERS AND ASH GATES:


1. C/G-1A and 1B, 2Ahyjector manual valve servicing done.
2. C/G-2B hyjector manual valve replaced.
3. C/G -1A, 1B, 2A, 2B ash feed gate repairing done.
4. C/G -1A, 1B, 2A, 2B feed chute hopper repair and welding done.
5. C/G -1A, 1B, 2A, 2B ash gate shaft gland replaced.
6. Flushing water valve 100 N.B. 02 replaced.
7. Feed Chute hard facing carried out.
8. All C/G ash feed gate indicating rod box repaired.
9. Discharge line, ground level up to bend replacement work carried out.
10. 200 N.B.3 valve replaced and 13 valve servicing done.
11. 100 N.B.3 valve replaced and 3 valve servicing done.
12. Seal water line 4 no of valve servicing done.
13. 4 no. of man door servicing done.

q) FLUE GAS DUCT :


1. All duct cleaning done.`
2. Ash &debris removed from duct.
3. Flue gas path damaged bracing replacement carried out.

76

4. Hot air duct damaged bracing replaced.


5. Worn out MS plates replacement done.
6. Cover plates of expansion joint replaced.
7. Damaged expansion joints at ESP outlets repairing work carried out.
8. Flue gas duct hoppers repairing work carried out.
9. Diversion plates at ESP inlet replaced.
10. PAH vertical duct has hole at 27 m level and hot air duct U # 5 side in front of ECO duct its corner
expansion joint bottom leaf found damaged same attended by patch welding
r) COARSE ASH EVACUATION SYSTEM :
1. All eco hoppers, duct hoppers cleaning carried out.
2. ECO hopper common discharge pipe 200 N.B.8 m replaced.
3. ECO hopper common vertical pipe 200 N.B.60 m replaced.
4. ECO hopper h. p. line damage pipe replaced.
5. All course ash distance piece fitting done.
6. Course ash hopper feeder ejector 22 no. servicing done.
7. 44 no. of air heater chain valve servicing and jamming removal done.
8. 18 no. of servicing water 100 N.B. done.
9.

20 no. of servicing water 150 N.B. done.

10. 12 no. of servicing water 200 N.B. done.


11. 2 no. of servicing of hyjector of C/A tank done.
12. 400 m2 hopper structure and pipe painting done.
13. 2 no. of course ash tank cleaning done.
14. Course ash hopper both side common slurry tank strengthening done.
15. 12 no. feeder ejector nozzle set replaced.
16. All eco hoppers, duct hoppers ash / chain v/v servicing carried out.
17. Eco hoppers trench repairs carried out.

s) FLY ASH EVACUATION SYSTEM :

77

1. Feeder ejector servicing done -72 no.


2. Ash valve and chain valve servicing done -144 no.
3. ESP all hoppers choke up removal done 1 no.
4. Total welding done 200 RMT
5. Replacement of pipe line 150 NB- 112 m
6. Servicing of water valve 350 NB - 4 no.
7. Servicing of water valve 250 NB - 48 no.
8. Servicing of water valve 100 NB - 72 no.

t) ESP INLET AND OUTLET GATE:


1) ESP A, B, C, D passes inlet gate both side gear box servicing done. Old oil replaced by fresh oil.
2) ESP A, B, C, D pass inlet gate support welding done.
3) ESP inlet gate 6A1, 6A2, 6B1, 6B2, 6C1, 6C2, 6D1, 6D2 manual trial found ok.
4) ESP outlet gate 7A, 7B, 7C, 7D manual trail taken found ok.

78

TURBINE MAINTENANCE
A) MAIN TG:
1)
2)
3)
4)

Seal oil Bearing DPT taken.


Generator Pressurization test completed at 6kg/cm2, leakage found in Bushing.
MOP bearing clearance correction done.
Governing- Hydraulic convertor, EHG Convertor servicing was done no abnormality seen.

a) HPT :
1) HPT Horn drop, Swing check, Roll check, CRO test, Bump test completed.
2) Alumina blasting carried out
3) HP rotor MPI Completed
4) Inner Casing quality taken.
5) HP rotor flow path taken

b)
1)
2)
3)
4)

IPT:
IP-LP CRO Completed. Roll check taken.
Rotor Flow path completed
Rotor Alumina blasting completed
IPT rotor MPI was Completed

c)
1)
2)
3)
4)
5)
6)
7)

LPT:
LPT-Gen CRO completed. Roll check taken.
LPT flow path checking completed.
Alumina blasting done.
Free standing blades all MPI completed.
blade No 34 from 2L was found defective. Replaced with new blades.
NFT of free standing blades taken.
Inlet bellow found defective, replace with new bellow.

d)
1)
2)
3)
4)
5)
6)
7)

GENERATOR/EXCITER :
CRO & Swing check of Exciter & Generator Coupling taken.
Exciter rotor leak test taken.
Compressor assembly Blade rings inspection done.
CC Bolt found leakage. Same was attended.
Conical filters cleaning done.
Pressurization of stator was carried out.
Primary water magnetic filter cleaned.

79

B) TANK CLEANING:
1) Control fluid tank bucket strainer cleaning done.
2) Main Turbine MOT tank cleaning carried out.
3) 3 TDBFP-6A and 6B tank cleaned.
B) HP /LP VALVES:
1) HPCV 3 & 4 seat found damage.
2) HPBP valve 1 & 2 servicing done.
3) HPBP 1 & 2 servo motor servicing done.
4) LPBP-1, 2 valve servicing done.
5) LPBP spray valve V1, V2, V3, V4 servicing carried out.
6) BPE-1 &BPE-2 valve servicing done.
7) BPE 1 & 2 servo motor servicing done.
8) BD valve servicing done
9) BD isolating valve servicing done.
C) CONDENSER :
1) Cleaning work completed.
2) Installation of Cathodic protection completed.
3) End Plate coating work completed.
4) Condenser gravity test completed

D) BOILER FEED PUMPS:


a) TDBFP 5B
1) Turbine overhaul done.
2) Rotor sand blasting done.
3) Cartridge replacement done.
E) CEP -5A:
1) Mechanical Seal servicing completed.
G) HP HEATERS:
1) HPH 5A, 5B, 6A & 6B internal inspection Carried out and air leak test taken.
H)
1)
2)
I)
1.
2.

LP HEATERS :
LPH 1, 2 & 3 internal inspections carried out.
LPH 2&3 Air leak test Carried out & found normal. No leakage found.
MS AND HRH STRAINERS :
All MS strainer servicing done. Bonnet seal ring replaced by new one.
All HRH strainer servicing done. Bonnet seal ring replaced by new one.

J) DEAERATOR AND FST :


1. Deaerator & FST internal insp. carried out.
2. Damaged nozzles replaced with new.
K)
1.
2.
3.

COOLERS :
Exciter cooler (2 Nos.) Cleaning / brushing / flushing / cleaning done.
Exciter cooler (4 Nos.) ACW valve internal inspection & servicing done.
Hydrogen coolers (4 Nos.): Acid / brushing / flushing / cleaning done.

80

4. H2 coolers- 4 Nos. of ACW outlet valve & 2 Nos. of inlet valve servicing done.
5. H2 cooler temperature control valve servicing done.
6. Primary water cooler- 3 Nos. of valves internal inspection & servicing done.
7. Primary water cooler- 3 Nos. Cleaning/ brushing /flushing carried out.
8. Primary water cooler temp. Control valve servicing done.
9. Seal oil cooler both air side &hydrogen side cleaning/ brushing /flushing carried out.
10. Seal oil rack ACW VALVE servicing done.
11. GTR R Y B Phases both coolers cleaning/ brushing /flushing Carried out.
12. GTR R Y B Phases coolers ACW valve servicing work Carried out.
13. GTR R Y B Phases ACW strainers cleaning done.
14. MOT coolers brushing / flushing / cleaning done. Air test taken at 6.0 kg/cm2.
15. Both MOT coolers ACW Inlet & Outlet valve servicing done.
16. FRF both coolers cleaning carried out both cooler gasket replaced.
17. FRF cooler temp control v/v servicing done
18. TDBFP 6A & 6B - Both oil coolers cleaning/ brushing /flushing carried out.
19. TDBFP6A And 6B Both oil coolers ACW Inlet & Outlet valve servicing done
20. MDBFP-6C, Lub oil coolers and working oil cooler ACW Inlet & Outlet valve servicing done.
21. MDBFP-6C, Lub oil & Working oil cooler brushing / flushing done.
22. MDBFP-6D, Lub oil coolers ACW Inlet & Outlet valve servicing done.
23. MDBFP-6D, Lub oil & Working oil cooler cleaning / brushing / flushing done.

STATUS OF COOLER ACW VALVES


STATUS OF HP VALVES
1
1
1

TDBFP 5A S/H iso

TDBFP 5A R/H iso

TDBFP 5B S/H iso

Valves Details

Remark
Boxup done.

Valve
Gate
Valve
Gate

Boxup done.

Valve
Gate
Valve
Gate

Boxup done.

Valve
Gate
Valve
NRV

Boxup done.

NRV

Boxup done.

NRV
MDBFP 5D S/H
NRV
MDBFP 5D R/H

NRV

Boxup done.

NRV

Boxup done.

NRV
TDBFP 5A R/H
NRV
TDBFP 5A S/H NRV

NRV

Boxup done.

NRV

Boxup done.

MDBFP 5C S/H iso

MDBFP 5C R/H iso

MDBFP 5D R/H iso

MDBFP 5D S/H iso

MDBFP 5C R/H
NRV
MDBFP 5C S/H

3
1
4

Replacement of
valves

Boxup done.

TDBFP 5B R/H iso

1
1
2
1

Valves
for

Valve
Gate
Valve
Gate

1
0
1

Categor
y
Gate

81

Boxup done.
Boxup done.
Boxup done.
Boxup done.

1
5
1

TDBFP 5B R/H
NRV
TDBFP 5B S/H

NRV

Boxup done.

NRV

Boxup done.

6
1
7
1

NRV
TDBFP 5A Suction

Boxup done.

8
1
9
2

MDBFP 5C Suction

Gate
Valve
Gate
Valve
Gate

Boxup done.

0
2
1
2

TDBFP 5B
Discharge
TDBFP 5BIso

Valve
Gate
Valve
Gate
Valve
NRV

Boxup done.

2
2
3
2

Discharge
BPE1 NRVNRV

NRV

Boxup done.

BPE2 NRV

NRV

Boxup done.

4
2
5
2

CD 22

Globe

Boxup done.

BD Isolating Valve

Gate

Boxup done.

6
2
7
2

CD 17

Globe

Boxup done.

EX 02

Gate

Boxup done

8
2
9
3

EX 01

Gate

Boxup done

EX 03

Gate

Boxup done.

0
3
1
3

EX 05

Gate

Boxup done

EX 04

Gate

Boxup done

2
3
3
3

EX 06

Gate

Boxup done.

EX 07

Gate

Boxup done.

4
3
5
3

AS 13

Gate

Boxup done.

EX 13

Gate

Boxup done.

6
3
7
3

DR 11

Globe

Boxup done.

DR 27

Globe

Boxup done.

8
3
9
4

Mal 11

Globe

Boxup done.

Mal 12

Globe

Boxup done.

0
4
1
4

Mal 13

Globe

Boxup done.

Mal 14

Globe

Boxup done.

2
4
3
4

Mal 22

Globe

Boxup done.

Mal 26

Globe

Boxup done.

4
4
5

Mal 28

Globe

Boxup done.

TDBFP 5B Suction
MDBFP 5D Suction

82

Boxup done.
Boxup done.
Boxup done.

4
6
4

Mal 65

Globe

Boxup done.

Mal 66

Globe

Boxup done.

7
4
8
4

HR 115

Globe

Boxup done.

HR 113

Globe

Boxup done.

9
5
0
5

MS 104

Globe

Boxup done.

MS 502

Globe

Boxup done.

1
5
2
5

MS 504

Globe

Boxup done.

MS 506

Globe

Boxup done.

3
5
4
5

MS 508

Globe

Boxup done.

HR 502

Globe

Boxup done

5
5
6
5

HR 504

Globe

Boxup done.

HR 506

Globe

Boxup done.

7
5
8

HR 508

Gloe

Boxup done.

Operating Mode

Quantity

Completed

Motorized

23

23

Manual

23

16

Pneumatically

Hydraulically

NRV

11

11

Total

58

53

DEPARTMENTAL
1. DR 17,25 Bonnet leakage attended
2. All BFP RC line NRV Servicing completed.
3. Vacuum pump A & B Gland replacement done.
4. DR 32 Valve servicing completed.
5. EX 31 & 32 Diaphragm replaced& Seal inspection is in progress.
6. CEP RC Valves inspection.
7.

HPBP Bladder replacement work.

83

ODP SECTION
A. AHP :
1. HP-LP ASH WATER PUMP VALVE SERVICING completed.
2. Line A 500NB B/F SERVICING completed.
3. Line B 500NB B/F SERVICING completed.
4. Tank inlet- 350NB B/F SERVICING completed.
5. Tank inlet- 500NB B/F SERVICING completed.
6. Sump make up main isolating Valve servicing completed.
7. B/A & F/A Sump selection valve servicing completed.
8. Seal water line B-series replacement completed.
9. Seal water line A-series replacement completed.
10. Seal water suction header replacement completed.
11. Flushing line to A, B & C sump adding completed.
12. HPSWP-1,2 & LPSWP-1,2 Preventive maint. completed.
13. HPAWP-2 O/H completed.
14. 5CSDP-1 O/H completed.
15. 5ASDP-1 OH WIP.
16. Raw water tank cleaning.
17. Ash water tank cleaning completed.

B. SUMP CLEANING WORK :


1. 5B Sump cleaning completed.
2. 5A sump cleaning completed.
3. 5C sump cleaning completed.
C. OIL COOLER CLEANING:
1. B SERIES completed.
2. A SERIES completed.
D. ADL:
1. 5BSDP-4 bend to bend pipe replaced.
2. 5BSDP-4 bend to bend no.1 pipe replaced.
3. 5BSDP-3 expander to bend pipe replaced.
4. Pipe rotation done from CP. -4 to CP. 19.
5. Slope pipe replaced at CP. 21.
6. 5BSDP-2 horizontal pipe replaced.
7. 5B pipe replacement from CP.422 backward to CP.419 completed.
8. 5BSDP-2 vertical pipe replacement completed.
9. 5B slope pipe replacement at CP.-33 completed.
10. 5BSDP-4 discharge pipe replaced.
11. 5B sump suction pipe & suction bend replacement completed.
12. 5B pipe replacement from CP.414 to CP.419 completed.
13. 5B pipe replacement from CP.414 to CP.408 completed.
14. 5B pipe replacement from CP.93 to CP.99 completed.
15. 5B pipe replacement in pump house -pump s/c valve to reducer completed.
16. 5B pipe replacement from CP.440 to CP.441 completed.

84

17. 5B pipe replacement from CP.456 to CP.462 completed.


18. 5BSDP-2 vertical & horizontal pipe replacement completed.
19. 5B pipe replacement from CP.86 to CP.94 completed.
20. 5B pipe replacement from CP.462 to CP.467 completed.
21. 5B pipe replacement from CP.468 to CP.472 completed.
22. 5A suction pipe replacement completed.
23. 5A suction bend re-irection completed.
24. 5A pipe rotation from CP 90 to CP 95 completed.
25. 5C suction pipe at sump replacement completed.
26. 5B pipe replacement from CP.323 to CP.330 completed.
27. 5B pipe replacement from CP.472to CP.477 completed.
28. 5A & 5B pipe replacement -44 to -43 completed.
29. 5C suction pipe replacement completed.
30. 5C suction bend re-irection completed.
31. 5A ASDP-2 horizontal pipe repl. completed.
32. 5C suction valve to reducer pipe repl. completed.
33. 5A pipe replacement CP -40 to CP -38 completed.
34. 5B pipe replacement CP -30 to CP -23 completed.
35. 5B pipe replacement CP 319 to CP 313 completed.
36. 5B pipe replacement CP.593 to CP.595 completed.
E. CT FAN:
1. CT Fan 5A/1, 5A/5, 5B/1, 5B/6-O/H completed. 5B/1 trial pending.
2. CT Fan 5B/5- Blade repl. (5A/7, 5B/5, 5B/8 completed).
3. CT 5A nozzle cleaning completed.
5. CT 5B nozzle cleaning completed. (5B/1, 5B/2, 5B/3, 5B/4, 5B/5 completed)
6. CT 5A- Hot water basin Cleaning completed.
7. CT 5B- Hot water basin Cleaning Completed.
8. Riser valve sericing / repl. completed. (5A/1,2,3,4 Padmapur side & 5A/1, 3, 4, 6, 7, 8
chandrapur completed.) (Valve servicing completed.)
9. CT 5B-Riser valve sericing / repl. completed. (5B/2,4,7 Chandrapur side & 5B/4, 5, 6
Padmapur side repl. completed)
10. CT Fan 5A fan splash bar cleaning .(Padmapur & chandrapur side completed)
11. CT Fan 5B fan splash bar cleaning complted .
12. CT Fan 5A- broken hot water pipe replacement completed.
13. CT Fan 5B- broken hot water pipe repl. completed.
F.
1.
2.
3.

ACW / CCW PUMP :


ACW /CCW sump cleaning completed & strainer repairing / cleaning completed.
CCW-5C column pipe inspection & BFV servicing completed.
CCW-5D column pipe inspection completed. BFV servicing completed. Expansion joint repl.

4.
5.
6.
7.
8.
9.

completed.
CCW-5B BFV servicing completed.
CCW, ACW-thrust bearing oil replacement completed.
ACW-gland repl. completed.
CCW-5A, 5B gland repl. completed.
CCW-power pack oil replacement completed.
ACW line separation from CCW hot water line-completed.

85

10. Interconnection of existing CCW pipeline to CT 5C-completed


11. ACW underground line leakage-Attended.

G.
1.
2.
3.
4.
5.

SUMP MAKE UP, ACW, CCW, R-C VALVE SERVICING WORK


ACW air vent valve on disch. side servicing completed.
CCW air vent valve on disch. side servicing completed) bend replaced.
ACW R/C valve servicing 4nos. completed.
ACW return line drain valve 2 nos. servicing completed.
Sump make valve 2 no. servicing completed.

ELECTRICAL MAINTENANCE II
A) GENERATOR:
1. Exciter current carring bolt found leakage,same leakage attended.
2. Stator weidge tightness works done. Rotor wedge tightning carried out. Hydrogen compressor hub ir
value checked
3. Genertor stator winding hydraulic test along with bushings and phase connectors carried out. Leakage
at B phase bushing and stator inlet pressure valve found, leakage rate was 2 kg/cm2 per 24 hours,
same was attaneded. Generator stator IR value taken. IR value is in the range of 280 to 300 kohms.
4. Exciter rotor leakage test taken after attending c.c. Bolts leakage. 0.5 kg/cm2 n2 pressure drop
observed in 6 hrs.
5. Exciter air gaps checked

B) BATTERY CAPACITY TEST DURING COH-2015:


Sr.

Battery Set

No.

Name

1
2
3

Battery Set
No. 1
Battery Set
No. 2
UPS Battery
Set

Work Carried out


Start

Stop

Voltage

Sp. Gravity

Battery

(After Test)

(After Test)

Capacity
>100%

01.01.16

02.01.16

246 Volts

1220 -1230

04.01.16

07.01.16

246 Volts

1220 -1230

12.01.16

19.01.16

243 Volts

1220 -1230

28 Volts1

200-1205

>100%
>100%

G1 Battery Set
4

+24 V G1 Set
23.01.16
-24 V G1 Set

86

24.01.16

>100%

1 Damage cell found as per EXIDE battery, no capacity test was taken

G2 Battery Set
+24 V G2 Set
17.01.16
5

18.01.16

28 Volts1

200-1205

>100%

-24 V G2 Set
Cleaning carried out, desulphation done, and battery charged

C) LT TRANSFORMERs COH-2015:
Sr.No.

NAME OF

DATE OF P/M

TRANSFORMER
1

LXB1

20.01.2016

LXA2

21.01.2016

XA

20.01.2016

XB

15.01.2016

OXA1

20.01.2016

OXA2

21.01.2016

D) HT TRANSFORMER WORK DURING COH-2015:


1. GTR 5R:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
2. GTR 5Y:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
3. GTR 6B:- Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
4. UAT 5A:-Transformer testing and oil filtration, oil leakage attending, cleaning and painting.

87

5. UAT -5B:-transformer internal inspection, gasket and oil seal replacement, testing, cleaning and
painting carried out.
6. UAT 5C:-Transformer testing and oil filtration, oil leakage attending, cleaning and painting.
7. UAT 5D:- transformer internal inspection, gasket and oil seal replacement, testing, cleaning and
painting carried out
8. SAT 3A:-Transformer oil filtration, testing carried out.
9. SAT 3B :-Transformer oil filtration, testing carried out.

E) BUSDUCT INSPECTION COH-2015


Sr.No.

NAME OF BUS

BUS OF UNIT BOARD 5A TO STN. BOARD SE 13

BUS OF UNIT BOARD 5A TO UAT A

BUS OF UNIT BOARD 5B TO STN. BOARD SE 15

BUS OF UNIT BOARD 5B TO UAT B

PT CUBICAL(GENERATOR)

BUS OF UNIT BOARD 5D TO UAT D

BUS OF UNIT BOARD 5D TO STN. BOARD SE 12/2

BUS OF UNIT BOARD 5C TO UAT C

All above bus cleaning work carried out as a preventive measure. Also 21KV Bus duct inspection
carried out during COH-2015, No abnormality found.

F) PREVENTIVE MAINTENANCE OF HT MOTOR COH U # 5:

88

Sr.No.

NAME OF HT MOTOR

OVERHAUL / P/M

ID FAN-5A

Overhaul

ID FAN-5B

PM

ID FAN-5C

PM

ID FAN-5D

Overhaul

Sr.No.5
6
1

2
3
4
5
6
7
8

7
8
9
10
11
12
13
14

CEP 5A
NAME OF LT MOTOR
SEAL AIR FAN 5A CEP 5C

Work

PM

O/H

PM

SEAL AIR FAN 5B BCW 5A


BCW 5B
SEAL OIL PUMPAIR SIDE 1
BCW 5C
SEAL OIL PUMP AIR SIDE 2
FD FAN 5A
PAH 5B S/B MOTOR
FD FAN 5B
PAH 5B MAIN MOTOR
PA FAN 5A
PAH 5AMAIN MOTOR
PA FAN 5B
PAH 5A S/B MOTOR
COAL MILL 5A
CONTROL FLUID 5A
COAL MILL 5B
CONTROL FLUID
5B MILL 5C
COAL

O/H

PM

PM
MOTOR REPLACED
PM
O/H
PM
O/H
Overhaul
O/H
Overhaul
O/H
PM
O/H
Overhaul
O/H
Overhaul
O/H
PM

15

10

16

11

O/H

PM

12

NO.1MILL 5D
17 BCW BOOSTER
COAL
18 BCW BOOSTERNO.2
COAL MILL 5E

O/H

PM

13

19 CLINKER GRINDER
COAL1A
MILL 5F

O/H

Overhaul

14

20 CLINKER GRINDER
COAL1B
MILL 5G

O/H

PM

15

21 CLINKER GRINDER
COAL2A
MILL 5H

O/H

PM

16

22 CLINKER GRINDER
MDBFP-5C
2B

O/H

PM

17

23 VACUUM PUMP MDBFP-5D


5B
24 MOT AOP-1
ASDP 1 2 3 4

PM

PM

O/H

PM

25 MAIN JOP AC BSDP 1 2 3 4


26
CSDP 1
DC SEAL WATER PUMP 1 & 2

O/H

PM

18
19
20

PM

21

IAC-5A, B, C

PM

22

TDBFP-5A-AOP-1 & 2

O/H

23

TDBFP-5B-AOP-1 & 2

O/H

24

HP AWP-1 & 3

PM

25

MDBFP-5C AOP

O/H

26

MAIN DC JOP

PM

27

C/M LOP 5 C, D, G, H

PM

28

C/F- 5A, B, C, F

PM

29

AC SCANNER

O/H

30

89 SAH-5A MAIN

O/H

31

SAH-5B MAIN

O/H

32

SAH-5A STAND BY

O/H

33

SAH-5B STAND BY

O/H

PM

G)

OVERHAUL /
PREVENTIVE
MAINTENANCE
OF LT MOTOR
COH-2015 :

H) REVENTIVE MAINTENANCE OF BOARDS in COH U # 5:


Sr. No.

90

NAME OF BOARDS

UNIT BOARD-5A

UNIT BOARD-5B

UNIT BOARD-5C

UNIT BOARD-5D

UNIT BOARD-5E

5MB BOARD

5MC BOARD

5MD BOARD

5ME BOARD

10

5MF BOARD

11

5MG BOARD

12

SOOT BLOWER BOARD

13

EMPA SECTION -I

13

EMPA SECTION -II

14

PA SECTION -I

15

PA SECTION-II

16

STATION BOARD INCOMER BREAKER

17

ESP A PASS LT BOARD

18

ESP B PASS LT BOARD

19

ESP C PASS LT BOARD

20

ESP D PASS LT BOARD

21

AHP HT SECTION-I

22

AHP HT SECTION -II

INSTRUMENTATION AND CONTROL


1.
2.
3.
4.
5.
6.
7.
8.

ALL HAG SOLENOID SERVICING DONE.


C/M DP S/WS CALIBRATED.
BURNER TILT ALL INST. SERVICING DONE
FRF TANK LVL. S/W CALIBRATED
ALL C/M SEAL/PA DP S/WS IMPULSE LINE FLUSHING DONE
ALL C/M SEAL/PA DP JB CLEANING DONE
SADC P/C AND POSITIONER SERVICING DONE
C/M THRUST PAD RTD, SEAL AIR V/V CHECKING AND TRIAL TAKEN. LUB. OIL SYSTEM

PRESS. S/W AND GAUGESCALIBRATION DONE


9. MOT LVE S/WSCALIBRATED
10. ESP PASS, ECONOMISER DUCT HOPPER ASH V/V POWER CYLINDER AND SOLENOID
SERVICING DONE.
11. ID A TO D SUCTION/DISCHARGE PRESSURE TRANSMITTERS IMPULSE LINE
FLUSHING DONE
12. PA FLOW TRANSMITTERS CALIBRATED
13. REJECT GATE & HAG GATE SERVICING DONE & TRIAL TAKEN.
14. ID A TO D JB CLEANING DONE.
15. ESP ASH valve POWER CYLINDER AND SOLENIED SERVICING AND TRIAL TAKEN.
16. SECONDARY AIR FLOW TRASNMITER AND FURNACE PRESSURE TRANSMITTER
CALIBRATION DONE.
17. PA HEADER PRESSURE SWITCHES CALIBRATED
18. C/M A, B, C LOP PRESS. S/WS CALIBRATED AND RESTORED.
19. ALL A/H,FURNACE DRAFT PRESSURE/DP TRANSMITTERS IMPULSE LINE FLUSHING
DONE
20. FURNACE PRESSURE SWITCHES CALIBRATED.
21. FUR /WB, A /H FG DP TRANSMITTER CALIBRATED.
22. ELEATION CORNER SOLENOID AND HAG SOLENOID REPAIR/SERVICING DONE
23. ESP- ASH VALVE SEAL KIT REPLACED WITH NEW ONE. ESP MAIN WATER V/V P/C
REPLACED WITH HEALTHY P/C SINCE OLD ONE was PASSING.
24. FIRST STAGE PRESS. TRANSMITTER AND THROTTLE PRESS. TRANSMITTER
CALIBRATION done.
25. ALL IGNITOR ASSEMBLY SERVICING COMPLETED.
26. HP BYPASS SYSTEM BP-1&2, FOD-1&2, BD V/V SERVO/SOLENOID V/V SERVICING
done.

91

27. MAIN TURBINE L.O. SYSTEM PRESS. S/WS, HPCF PUMP PRESS S/WS calibrated. SEAL
OIL SYSTEM PRESS. S/W CALIBRATION done.
28. BOTTOM ASH P/CSERVICING done.
29. ID FAN-A, B, C, D PRESS. S/WS CALIBRATED.
30. SEAL OIL SYSTEM PRESS S/WS CALIBRATED.
31. IPT OUTER CASING T/C, HPT CASING T/C AND IPT CASING CHECKING DONE
32. HPSV AND IPSV LIMIT SWITCHES REPAIRING/ CHECKING DONE.
33. INST. AIR DRIER P/C CHECKED, FOUND PASSING, REPAIR WORK done.
34. C/M LRG & TIG P/C CHECKING DONE.
35. FLAME SCANNER SERVICING done.
36. ALL A/H JB AND TRB CLEANING AND IMPULSE LINE REPAIR WORK done.
37. ID FAN A, B, C, D LO FILTER DP S/WS CALIBRATED.
38. DEAERATOR SHELL PRESS. TRANSMITTER, CONDENSATE FLOW TO DEAERATOR
TRANSMITTER, DM MAKEUP FLOW TRANSMITTER, SEAL STM. HDR PRESS.
TRANSMITTER CALIBRATED.
39. C/M CONTROL DAMPER CALIBRATED.
40. HPCV & IPCV LIMIT S/WS SERVICING AND REPAIRING DONE.
41. GEN. LIQUID LEVEL DETECTOR, LLD CHECKED FOUND HEALTHY
42. FD FAN-A IGV ACTUATOR MOTOR CHECKED
43. SEC. AIR FLOW AEROFILE (LEFT SIDE) FLUSHING DONE.
44. HP BYPASS SYSTEM SERVO VALVE LINE FLUSHING DONE.
45. INST. AIR DRIER EXHAUST V/V (SV3) P/C SEAL KIT REPLACED.
46. BOTTOM ASH P/C SEAL KIT REPLACEMENT WORK DONE.
47. SEC. AIR FLOW AEROFILE (RIGHT SIDE) FLUSHING DONE.
48. IPT INNER CASING T/C REMOVED.
49. PRIMARY WATER PUMP PRESS. S/WS CALIBRATED AND RESTORED.
50. BFP-A, B, C, D SUCTION FLOW TRANSMITTER, CEP DISCHG. FLOW TRANSMITTER
CALIBRATED.
51. DAS PEM PACKAGE VALIDATION AND DAS CONTROLLER CHECKING WORK CARRIED
OUT. PEM PACKAGE OUTPUT REPORT SEND TO POG FOR VALIDATION.
52. CEP DISCHG. FLOW TRANSMITTER, CONDENSOR VACCUM TRANSMITTER
CALIBRATED.
53. SEAL STEAM SYSTEM MAW-10, 50 V/V FILTER CLEANING, and OIL TOP UP DONE.
54. C/M D MILL O/L T/C AND ITS CABLE REPLACED WITH NEW ONE.
55. GEN. EXCITER TEMP. S/WS CALIBRATED.
56. HOTWELL LEVEL VERY LOW S/WS HEALTHINESS CHECKED FOUND OK.
57. GEN. EXCITER TEMP. S/WS CALIBRATED.
58. S/H & R/H FLOW TRANSMITTER, FEED WATER FLOW TRANSMITTER CALIBRATED.
59. DR-17, 25 V/V INST. CALIBRATED.
60. O2 IN FG (LEFT AND RIGHT SIDE) PROBE INSPECTION, CLEANING AND CONNECTION
TIGHTENING CARRIED OUT.O2RIGHT SIDE PROBE SHIELD FOUND WORN OUT, SAME
IS REPAIRED BY PATCH WELDING.
61. HP BYPASS SYSTEM SERVO V/V SERVICING/REPAIRING DONE.
62. C/M HOT AIR GATE TRIAL TAKEN AND FEED BACK LIMIT SWITCHES CHECKED. 03
NOS. FEED BACK LIMIT SWITCHES FOUND MALFUNCTIONING; ITS REPAIR WORK
DONE.
63. ID FAN-A, B, C, D DISCHG. PRESS. TRANSMITTER CALIBRATED.
64. DR-39, 43 AND DM-2, 17, 21 V/V INST. SERVICING AND CALIBRATION DONE.

92

65. DEAERATOR LVL.TRANSMITTER CALIBRATED.


66. SADC POSITIONER CALIBRATED.
67. A SERIES SUMP LVL SENSOR SERVICED AND REPAIRED.
68. CD-81, 85, MDBFP-D R/C V/V INST. SERVICING AND CALIBRATION DONE.
69. MAIN TURBINE STARTING DEVICE LIMIT SWITCHES SERVICING DONE.
70. MAIN TURBINE GOVERNING RACK PRESSURE GAUGES CLEANING AND CHECKING
DONE. 03 NOS. FAULTY GAIGES REPLACED WITH NEW ONE.
71. MAIN TURBINE JOP LINE PRESSURE GAUGES (03 NOS.) REPLACED WITH NEW ONE.
72. FSSS PANEL BNC CONNECTOR TIGHTENING CARRIED OUT.
73. BFP-A, B, C R/C V/V INST. SERVICING, NORMALISATION AND CALIBRATION DONE.
74. DR-32 V/V CALIBRATED.
75. GENERATOR PRE CHAMBER LLD AND RTD RESTORED.
76. MDBFP-C,D R/C V/V REMOTE TRIAL TAKEN.
77. MAIN TURBINE TSE SYSTEM T/C (50% AND 100%) CHECKING DONE.
78. MAIN TURBINE SPEED PROBE CHECKING CARRIED OUT.
79. FD-49 P/C SEAL KIT REPLACED AND V/V CALIBRATED.DR-6,13 V/V INST. SERVICING
AND CALIBRATION DONE.
80. BOILER STM. O/L PRESS. TRANSMITTER ,GEN. MAIN BUSHING FLOW TRANSMITTER
CALIBRATED.
81. FSSS FLAME FAILURE TRIP LOGIC ALL ELEVATION ELEVATION 2/4 FLAME INPUT
SIGNAL RELOCATED(DISTRIBUTED) IN TWO I/P CARDS (EARLIER SIGNAL IS
INPUTTED THROUGH SINGLE I/P CARD) AND ACCORDINGLY PROGARM IS MODIFIED.
82. HPCF TEMP. CONTROL V/V CALIBRATION DONE.
83. GEN. MAIN BUSHING FLOW TRANSMITTER AND STATOR WATER FLOW TRANSMITTER
CALIBRATED.
84. FD FAN-5B FAN BRG NDE SIDE RTD FOUND FAULTY, REPLACED WITH NEW ONE.
85. PA FAN-5A 01 NOS. JB FOUND RUSTED AND DAMAGED, SAME IS REPLACED WITH
NEW ONE.
86. OHP R/C V/V HO-11 & LO-11 INST. SERVICING AND CALIBRATION DONE.
87. 02 NOS. DAS CONTROLLER (REMAINING FAULTY CONTROLLER) CHECKED , 01 NO.
DAS CONTROLLER REPAIRED AND PUT IN SERVICE.01 NO. DAS CONTROLLER
MOTHERBOARD FOUND FAULTY.
88. MAIN TURBINE IPT BOTTOM CASING T/C (04 NOS) HEALTHINESS CHECKED,FOUND
OK. ITS CABLE DRESSING DONE.
89. HPBP SYSTEM OSU-1 ACUUMULATOR N2 GAS FILLING DONE. OSU-2 ACUUMULATOR
N2 GAS FILLING DONEAAFTEWR BLADDER REPLACEMENT.
90. HPBP SYSTEM FOD BOTH ACCUMULATOR BLADDER FOUND PUNCTURED.
91. DR-02,,09,21,29,32 V/V INST. SERVICING AND CALIBRATION DONE.
92. HOT WELL TRANSMITTER CALIBRATION CARRIED OUT.
93. FD FAN-5A MOTOR ALONG WITH DRIVE CHECKED, MOTOR FOUND HEALTHY.
.

TESTING II
A) GENERATOR:

93

1.
2.
3.
4.
5.
6.
7.
8.
9.

Generator Protection Panel Micom Relay testing.


Generator PT fuses replacement.
Generator Stator, Rotor, Main exciter, Pilot exciter IR and Winding Resistance.
Exciter Diode Wheel diodes and Fuses checking.
Generator, GTR and UAT protection/metering CT resistance measurement.
GCB ON/OFF and protection Trip Trial from PCR in co-ordination with 400KV GCR.
Unit Switchgear A, B, C and D Incomer, Tie I/C and outgoing feeder Relay testing
Generator Rotor Earth Fault (REF) protection, CarbonBrush holder assembly internal wiring checking
Generator Dynamic testing completed at 0055 Hrs on 30.01.2016 and unit synchronized at 02.06.Hrs
on 30.01.2016.

Gen. Stator Resistance by TRM 104 using LR Meter wires:

R1-R2 resistance

Y1-Y2 resistance

B1-B2 resistance

1.694 m

1.581 m

1.589m

B) GENERATOR ROTOR:
a) Gen. Rotor IR
Rotor IR values taken at ambient temp. = 32.0 0 C by 250 V Megger = > 50 M
b) Gen. Rotor Resistance
Rotor winding resistance by LR 205 micro ohmmeter= 113.61 mohm and
Ambient temperature 320C
c) Gen. Rotor Impedance (Taken by Single phase Variac 15amp range)
Sr.

AC volt applied

Current in
Amps.

No.

V/I

Freq.

Impedence

Hz

10.35

2.99

3.461

49.96

20.45

5.96

3.431

49.96

30.43

8.79

3.461

49.97

40.23

11.59

3.471

49.99

45.06

12.93

3.484

49.95

94

Megger after rotor imp test > 50 M

C)

MAIN EXCITOR :
a) Exciter Upper & lower half field winding
Excitor Field Winding LOWER & UPPER Half Connected to each other
Megger value by 250 V Megger > 50 Mohm
Resistance by LR 205 Meter = 540 mohm ( Temp = 320 C )

b) Exciter Stator resistance


Main Exciter Armature Windings
R

0.218 mohm

0.214 mohm

0.226 mohm

Measured at + Ve Wheel side


( + Ve WHEEL Towards Exciter )

Main Exciter Armature Windings

TEST RESULT OF GEN. TESTING (STATOR, ROTOR, EXC, PILOT EXC. & CAPA.
Main Excitor Armature Windings
R

0.220 mohm

0.222 mohm

1.225 mohm

Measured at -- Ve Wheel side


(- Ve WHEEL Towards Generator )

c) Exciter IR Values
A) Megger By 250 V Megger : Neutral To Shaft > 50 Mohm
B) Megger By 250 V Megger : + Ve Wheel To
- Ve Wheel = 0 Mohm ( Rev.Bias)
C) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel => 50 Mohm (Forward Bias)
D) + Ve Wheel To Body > 50 Mohm
E) - Ve Wheel To Body > 50 Mohm

95

d) Quadrature coil
Quadrature Coil Res. Measurement

IR Value

A) COIL 1 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C )

IR > 50 Mohm

B) COIL 2 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C )

IR > 50 Mohm

Main Excitor Armature Windings


R

0.220 mohm

0.222 mohm

1.226 mohm

Measured at -- Ve Wheel side


(- Ve WHEEL Towards Geneator )

e) Exciter IR Values
A) Megger By 250 V Megger : Neutral To Shaft > 50 Mohm
B) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel = 0 Mohm ( Rev.Bias)
C) Megger By 250 V Megger : + Ve Wheel To - Ve Wheel => 50 Mohm(Forward Bias)
D) + Ve Wheel To Body > 50 Mohm
E) - Ve Wheel To Body > 50 Mohm

f) Quadrature coil

D)

Quadrature Coil Res. Measurement

IR Value

A) COIL 1 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C )

IR > 50 Mohm

B) COIL 2 :Resi. By LR 205 Meter = 7.3 OHM (Temp = 320 C )

IR > 50 Mohm

PMG (Pilot Exciter)

96

a) Pilot exciter resistance measured by LR-205 At Temp.= 32 0C


R-Y Res.

B-Y Res.

R-B Res.

5.68mOhm

5.70mOhm

5.69mOhm

R-N Res.

R-N Res.

R-N Res.

3.10mOhm

3.14mOhm

3.15mOhm

b) IR Value by 250 V hand operated megger > 50 Mohm


c) Unit Aux Boards
1. Unit Board A, B, C &D Incomer and Tie I/C Breaker timing and contact resistance measurement.
2. Unit Boards - A, B, C & D Bus Transfer Scheme (BTS) trials

E) VALVES:
1. ACTUATOR VALVES - TURBINE SIDE

97

SN

Valve

Description

no.

Connections
removed

Cabling
& LS

Trials
taken

setting

FD 44

HPH 5A-6A Inlet valve

EX 31

TDBFP 6A Exhaust valve

3.

EX 1

Extraction to HPH 6A

4.

EX 2

Extraction to HPH 6B

5.

EX 2A

Extraction to HPH 6B

6.

EX 3

Extraction common to HPH 6A & 6B

7.

EX 4

Extraction to HPH 5A

8.

EX 4A

Extraction to HPH 5A

9.

EX 5

Extraction to HPH 5B

10.

EX 5A

Extraction to HPH 5B

11.

EX 6

Extraction to Deareator

12.

AS 2

Aux. steam to Gland Steam Iso Valve

13.

AS 4

Aux. steam to Deareator Main Iso

14.

AS 12

Aux. steam to Deareator Bypass Iso

15.

EX 34

Gland steam from CRH Iso valve

16.

DR 4

HPH 6A Drip to HPH 5A Bypass

17.

DR 11

HPH 6B Drip to HPH 5B Bypass

18.

DR 19

HPH 5A Drip to Deareator Bypass

19.

DR 27

HPH 5A Drip to Deareator Bypass

20.

MS 502

HPCV 1 Strainer Drain

21.

MS 504

HPCV 2 Strainer Drain

22.

MS 506

HPCV 3 Strainer Drain

23.

MS 508

HPCV 4 Strainer Drain

24.

HR 502

IPCV 1 Strainer Drain

25.

HR 504

IPCV 2 Strainer Drain

26.

HR 506

IPCV 3 Strainer Drain

27.

HR 508

IPCV 4 Strainer Drain

28.

HR 113

LPBP Warm up Drain

98

Already removed

29.

HR 115

30.

HR 108

31.

Mal 11

HPCV1 to Turbine Line Drain

32.

Mal 12

33.

HPCV2 to Turbine Line Drain

Mal 13

HPCV3 to Turbine Line Drain

34.

Mal 14

HPCV4 to Turbine Line Drain

35.

Mal 22

HP Turbine Casing Drain

36.

MS-104

2. ACTUATOR VALVES - BOILER SIDE


SN

Valve

Description

no.

Connections Cabling &


removed

LS setting

Trials
taken

1) .

MS201

Main Steam

2)

MS203

Main Steam

2)

S 37

Superheat Spray

3)

S 38

Superheat Spray

4)

S 39

Superheat Spray

5)

S 40

Superheat Spray

6)

B 55

Drum Vent

7)

B 56

Drum Vent

8)

B 57

Drum Vent

9)

B 58

Drum Vent

10)

B 72

Drum Vent

11)

B 73

Drum Vent

12)

B 74

Drum Vent

13)

B 75

Drum Vent

14)

S 76

Start-up Vent

15)

S 77

Start-up Vent

16)

S 78

Start-up Vent

17)

S 79

Start-up Vent

99

Motor NA

18)

R 19

Reheat Spray

19)

R 20

Reheat Spray

20)

R 21

Reheat Spray

21)

R 22

Reheat Spray

22)

FD 50

Feed line Main

23)

FD 50A

Feed line Main

24)

GD 1A

Gas Damper

25)

GD 1B

Gas Damper

26)

GD 3A

Gas Damper

Actuator

27)

GD 3B

Gas Damper

NA
Actuator

28)

FD 40

Feed line Main

29)

BS 4

EBD

30)

BS 5

EBD

31)

E 19

Economizer Inlet

32)

FD 47

Full Load Line

33)

GD41

34)

GD4A1

35)

GD4B2

36)

GD 4B2

37)

GD 6A1

ESP A-Pass inlet damper

38)

GD 6A2

ESP A-Pass inlet damper

39)

GD 6B1

ESP B-Pass inlet damper

40)

GD 6B2

ESP B-Pass inlet damper

41)

GD6C1

ESP C-Pass inlet damper

42)

GD6C2

ESP C-Pass inlet damper

43)

GD6D1

ESP D-Pass inlet damper

44)

GD6D2

ESP D-Pass inlet damper

45)

GD 7A

ESP A-Pass outlet damper

46)

GD 7B

ESP B-Pass outlet damper

100

NA

F)

47)

GD 7C

ESP C-Pass outlet damper

48)

GD 7D

ESP D-Pass outlet damper

GTR R, Y, B :

1. GRP cubical panel 1-GT, Transformer Differential relay (87GT-1, 87GT-2) and Transformer

overall

differential relay (87OA-1, 87OA-2) testing work carried out. Cubical panel 1G, Relay 50Z1 and 50Z2
testing work carried out.
2. GTR- Y phase, UAT-5A transformer testing work carried out.
3. GTR- R, Y and B oil pumps auto pick-up trials taken.
G) PLANT AUXILIARIES
1. GTR - R, Y, B Transformer testing and Buchholz protection Trial.
2. GTR - R, Y, B HV Bushing Tan-delta and Capacitance measurement.
3. GTR R, Y and B,oil pumps ON/OFF and changeover trial.
4. UAT- A, B, C and D Transformer testing.
5. GTR - R, Y, B Water flow switch servicing.
6. GTR and UAT OTI and WTI calibration.
7. UAT- A, B, C and D Transformer Buchholz protection Trial.
8. GTR R, Y, B and UAT A to D, Buchholz local JB and RTD JB, polythene wrapping.
9. Generator Protection Panel Micom Relay testing.
10. Generator PT fuses replacement.
11. Generator Stator, Rotor, Main exciter, Pilot exciter IR and Winding Resistance.
12. Exciter Diode Wheel diodes and Fuses checking.
13. Generator, GTR and UAT protection/metering CT resistance measurement.
14. GCB ON/OFF and protection Trip Trial from PCR in co-ordination with 400KV GCR.
15. Unit Switchgear A, B, C and D Incomer, Tie I/C and outgoing feeder Relay testing.
16. MDBFP-5C and D, Motor feeders relay testing.
17. Unit Board A, B, C &D Incomer and Tie I/C Breaker timing and contact resistance measurement.
18. Unit Boards - A, B, C & D Bus Transfer Scheme (BTS) trials.
19. LT Boards - EMPA,PA,ME Incomer feeder relay testing.
20. LT Boards - EMPA, PA control connection tightening.
21. PA Boardoutgoing feeders relay testing.
22. MA, MB, MC, MD, ME and MG Board I/c and Control supply panel indication lamp replacement.
23. DG set auto pick up trial.
24. Station Boards SE11/1, SE11/2, SE12/1 and SE12/2 normal I/C relay testing.
25. Station Transformer ST-3,HT side Protection Panel relay testing.
26. Station Transformer ST-3, R & B phase Lightening arrester checked found OK and Y phase
Lightening arrester replaced by 400 KV GCR.
27. Compressor Board - 5E Incomer and motor feeder relay testing work.
28. Generator Rotor Earth Fault (REF) protection, CarbonBrush holder assembly internal wiring checking.
29. UPS filter cleaning and Fan replacement.
30. Bottom Ash panel cleaning and connection tightening.
31. IAC/SAC Compressor control panel cleaning and TB tightening work.
32. AHP HT Board Relay testing.
33. 220 V Battery charger No.2, panel cleaning and condenser replacement.
34. 220 V Battery charger No.1 panel cleaning.
35. +/- 24V Battery charger G1 and G2 panel cleaning and condenser replacement.
36. PAH and SAH, Rotor stop indication L/S restoration.
37. Hot keys provided for DC Seal water pump A/B and EOP of TDBFP A/B.

101

38. ALL ESP fields OC test after clearance from BM-II and EM-II.
39. ID, FD, PA, CEP, BCW, MDBFP and C/M breaker protection trial.
40. Motorized valve L/S setting and trials after completion of BM (38) and TM (35) work.
41. CCW pump house,CW(11 KV) and CWS(3.3KV) Board Incomersand outgoing feeders relay testing.
42. ACW, CCW control panelcleaning and connection tightening.
43. CCW BFV local panel connection tightening and local JB polythene wrapping.
44. CTPA Board relay testing and connection tightening.
45. CWX-A &B Transformer, OTI/WTI calibration.
46. 5CWXA/XB/XC and 5CTXA/XB, transformer Buchholzs alarm and trip protection trials.
47. CCW-A, CCW-C and CCW-D control panel annunciator replacement.
48. ACW and CCW pumps breaker protection trial.
49. Major modifications carried out
50. 100% Stator E/F protection, 40MW interlock introduced in MICOM 343 relay as approved by
competent authority.
51. Hot keys provision at PCR for EOP of TDBFP A/B and DC seal water pump A/B.
52. Following relays found faulty, same replaced with spare relays.
SE11/1, Incomer Y phaseOver current relay (CDG63).
PA Fan 5A, Motor protection relay (SPAM150)
5DBoard, TIE to CCW, E/F Relay (IBX164)
RWP- NDM pump B, Motor protection relay(CTMM)
53. Works carried out from 400 KV GCR side,
54. The Measurement of Tan delta & capacitance of R-phase synchronizing PT is done.
55. The IR of R, Y & B-phase L.A.'s of GT-5 is carried out. During, taking IR, the IR value of B-phase L.A.
of GT-5 is found low and hence, the B-phase L.A. is replaced by new ALSTOM make L.A.
56. Maintenance of CB & PG isolators is carried out.
57. The 01 no. disc insulator string of R-phase in gantry near to canteen is replaced.
58. Generator Dynamic testing completed at 0055 Hrs on 30.01.2016 and unit synchronized at 02.06.Hrs
on 30.01.2016.

U # 5 GENERATOR SCC : Date of test :- 29/01/2016


QUADRATUR
E. COIL
VOLT
( CJN04
PANEL ) TBLA005- 101 &
102

MANU
AL
POT.
POSN
( CJN0
4
PANEL
)

2.75 V

0.85

1997 A

3.60 V

0.8

Previous 9900 A

16.22 V

3.77

16.34 V

3.8

SR. NO.

GEN.
AMP

Previous 2100 A

10110

102

AUX.
EXC.
VOLT
(-L
TO +
L)
( CJN
01
PANE
L)

AUX. EXC.
FIELD AMP.
(mV ACROSS
SHUNT)
( CJN01
PANEL )
CA003(m)
(150A/60 mv)
CA004(a)
(150A/60 mv)

UST
(DQ069H2)
( CJN04
PANEL
)

2.65mV/2.4mV

GENERATOR PT VOLTAGE

FIELD
AMP

PT I
CJJ09X01RY/YB/B
R
Volts

PT II
CJJ09X01RY/YB/B
R
Volts

PT III
CJJ09X01RY/YB/B
R
Volts

COD
8
METE
R

(-)448
mV

1.81 V
(avg)

1.79 V
(avg)

1.79 V
(avg)

200 A

2.71 Mv/2.73mV

(-)425
mV

1.72V
(avg)

1.69
(avg)

1.70
(avg)

180 A

23.46
V

14.5mV/14.4mV

(-)765
mV

8.48 V
(avg)

8.45 V
(avg)

8.44 V
(avg)

1600
A

22.32

15.13 mV/15.20

(-)746

8.62

8.58 V

8.60 V

1400

4.56
V
5.13
V

mV

mV

(avg)

(avg)

(avg)

U # 5 GENERATOR OCC :
AUX. EXC.
AUX.
FIELD AMP.
EXC.
(mV ACROSS
QUADRATURE. MANUAL
VOLT
SHUNT)
COIL VOLT
POT.
GEN.
DC
( CJN01 PANEL
SR. NO.
( CJN04 PANEL POSN
VOLT
( - L TO
)
) TB- LA005( CJN04
+ L)
CA003(m)
101 & 102
PANEL )
( CJN01 (150A/60mv)
PANEL )
CA004(a)
(150A/60 mv)

UST DC
Volts
(DQ069H2)MAN
( CJN04
PANEL )
DC091S2(A)

RY
LA010251A252A
& WA511-512

YB
LA010252A253A
& WA512-513

BR
LA010253A251A
& WA513-511

Previous 19.5 KV

(-)635mV 95.1/94.9
/
V

95.2/95.2
V

95.2/95.2
V

105.37 /

105.38 /

105.31 V

105.35 V

11.42 V

2.55

16.17

9.1mV/9.2mV

AVR PT VOLT ( CJN-04 )


FIELD
AMP
COD 8
METER

(-)1.01 V
1

21.1 KV

13.08 V

2.98

18.71

11.14 mV/10.91 (-)660mV


105.06 /
mV
/
(-)9.2
105.28 V
V(pot 4.5)

GENERATOR DYNAMIC TEST :


Date of test :
29/01/2016

GENERATOR SHORT CKT

* TEST

GENERATOR PROTECTION RELAY GPR-1 & 2 ( P-343 )


S
r.
N
o
1

RELAY

GPR
1&2,
P-343,
87G
AND
OTHER
PROTEC
TION

103

CT NO. NEW
& CTR TB NO.

CT D1 1G,TB20000/ 1-15
5A
NEU.SI
13
DE
BIAS-1
11
Neutra
l- 9

MEASURED CURRENT READING


Previous( 2 Previous( 9
Current
100 A)
900 A )
(2008A)
GPRGPRGPR2
Meas
1
GPR-2 GPR-1 GPR-2
1
(Sec.
ure-1 (Pri.) (Sec.) (Pri.) (Sec.) (Pri.)
)
2105 526 9881 2.47 1990 0.49
IA-1
A
mA
A
A
A
7A
2101 524 9887 2.47 1986 0.49
IB-1
A
mA
A
A
A
8A
2112 526 9927 2.48 1994 0.49
IC-1
A
mA
A
A
A
8A

Current
(10080A )
GPR- GPR1
2
(Pri.) (Sec.)
1000 2.52
0
A
1000 2.53
0
A
1000 2.53
0
A

Meas
ure-3
CT D2
20000/
5 A HV
SIDE
BIAS-2

(GEN.
DIFF.)

1G,TB1-1

IA-2

IB-2

5
Neutra
l- 7

IC-2

Meas
ure-3
I(A)
Diff.
I(B)
SPILL
Diff.
I(C)
Diff.
Meas
ure-3
I(A)
Bias
I(B)
Bias
I(C)
Bias
Meas
ure-1
1G,TBIN
CT P
1-18 Measur
200/1
e
A
Magnit
19
ude
1GVN
NGT(9
TB1-48 Measur
5%)
e
18K/2
Magnit
40V
49
ude
Meas
ure-3
100%
VN 3rd
S-E/F
Hrm.

2111
A
2105
A
2099
A

0
mA
0
mA
0
mA
2104
A
2099
A
2115
A

527
mA
526
mA
528
mA

0 mA

49 V

2.52
A
2.51
A
2.51
A

0 mA 0 mA

0 mA 0 mA
91.50 18
0 mA
A
mA

0.017

0 mA

526
mA
525
mA
529
mA

0.0 A 0.0 A

0V

9886 2.47 1970 0.49 1000


A
A
A
5A
0
9865 2.47 1978 0.49 1000
A
A
A
5A
0
9926
1991 0.49 1000
A
2.47A
A
7A
0

663
mV

9883
A
9877
A
9930
A

2.47 1974 0.49 1000


A
A
7A
0
2.47 1971 0.49 1000
A
A
6A
0
2.48 1978 0.49 1000
A
A
8A
0

2.52
A
2.52
A
2.52
A

0.0 A 0.0 A

3.2 V 0.0 V

254

3.229
V

652.2 237.9 3.171 46.8 621.


mV
V
V
4V
7V

GEN. TRANSFORMER RELAY 87GT-1 and 87GT-2 ( P-642 )


Sr
.
N
o

RELAY

104

CT
NO.
&
CTR

NEW
TB NO.

Previous
Previous( 99
Current
Current
( 2100 A )
00 A )
(2010 A)
( 10000A )
87GT- 87GT- 87GT- 87GT- 87GT- 87GT- 87GT- 87GTMeas
1
2
1
2
1
2
1
2
ure-1
(Pri.) (Sec.) (Pri.) (Sec.) (Pri.) (Sec.) (Pri.) (Sec.)

1GTBCTTB1-45
2
1000
47
/5 A
HV
SIDE
49
BIAS- Neutral
1
-51

IA-1

107 A

IB-1

105 A

IC-1

107 A

535
mA
530
mA
533
mA

507 A

2.54
A
2.52
A
2.53
A

101.1 0.506 0.519


A
A
A
100.3 0.505 0.518
A
A
A
100.8 0.502 0.518
A
A
A

2.59
A
2.58
A
2.58
A

9913
A
9897
A
9965
A

4.13
A
4.12
A
4.15
A

1982 0.827 1014


A
A
0A
1977 0.828 1012
A
A
0A
1993 0.840 1018
A
A
0A

4.22
A
4.21
A
4.23
A

508 A
505 A

Meas
ure-1
1GT2100
BCTA
6+7 TB1-57 IA-2
2100
1200
87GT
59 IB-2
A
0/5 A
1&2,
LV
2130
P-642,
SIDE
61 IC-2
A
AND
BIAS- Neutral
OTHER
2
-63
PROTEC
Meas
TION
ure-2
2 ( TRANS
I(A) 0.003
. DIFF. )
Diff.
PU
I(B) 0.004
SPILL
Diff.
PU
I(C) 0.004
Diff.
PU
Meas
ure-2
I(A) 0.125
Bias
PU
I(B) 0.125
Bias
PU
I(C) 0.125
Bias
PU
Meas
GT HV
ure-1
SIDE
S/B
BCT1GT- IN-HV
BACKUP
4
TB1-53 Meas
0
E/F(51 1000
d
NGT)
/1 A
55 Mag.

105

875
mA
872
mA
879
mA

0.004 0.016 0.016 0.004 0.004 0.017 0.017


PU
PU
PU
PU
PU
PU
PU
0.004 0.016 0.016 0.004 0.004 0.017 0.017
mA
PU
PU
PU
PU
PU
PU
0.004 0.016 0.016 0.004 0.004 0.017 0.016
mA
PU
PU
PU
PU
PU
PU
0.125 0.594 0.593 0.119 0.120 0.607 0.607
PU
PU
PU
PU
PU
PU
PU
0.125 0.593 0.594 0.119 0.119 0.604 0.602
PU
PU
PU
PU
PU
PU
PU
0.125 0.594 0.594 0.119 0.119 0.607 0.606
PU
PU
PU
PU
PU
PU
PU

3.124
2.163
A
0.0 A
A

GENERATOR AND TRANSFORMER PROTECTION 870A-1 & 2 ( P-645 )


Sr
.
RELAY
N
o

CT NO. NEW TB
& CTR
NO.

3
CT
CORE-1
1000/1 A
HV SIDE
BIAS-1

Previous(2100 A)
Measu
87OA-2
87OA-1
re-1
(Sec)
(Pri)

1GTTB1-1

IA-1

106 A

107 mA

IB-1

106 A

107 mA

5
Neutral7

IC-1

106 A

106 mA

Previous(990
0 A)
87OA87OA2
1 (Pri) (Sec)
508
509 A mA
507
506 A mA
507
508 A mA

Current(2010
A)
87OA87OA2
1 (Pri) (Sec)
0.101
100 A
A
0.103
98 A
A
0.102
100 A
A

Current(1001
0A)
87OA87OA2
1 (Pri) (Sec)
520.8 0.518
A
A
518.5 0.514
A
A
520.4 0.520
A
A

Measu
re-1
1GTTB1-9

IA-2

9920
1988 0.496 10130 2.526
A
2.48 A
A
A
A
A
9900
1979 0.497 10110 2.523
2100 A 521 mA
A
2.43 A
A
A
A
A
9970
2009 0.502 10170 2.543
2100 A 520 mA
A
2.49 A
A
A
A
A
2100 A 521 mA

CT A
20000/5
11 IB-2
A GEN.
87 OA 1 (N)SIDE
13 IC-2
& 2 P645
BIAS-2
AND
NeutralOTHER
15
PROTEC
Measu
TION
re-3
I(A)
0.003
0.002
Diff.
mA
mA
I(B)
0.003
0.002
SPILL
Diff.
mA
mA
I(C)
0.003
0.004
Diff.
mA
mA
Measu
re-3
I(A)
Bias 0.125 A 0.125 A
I(B)
Bias 0.125 A 0.125 A
I(C)
Bias 0.125 A 0.126 A
GTR REF
Measu
64GT
re-1
BCT 3+5
INR ph
1GT, TV(R
1000/1A TB1-33 )
0
0
35

106

0.015 0.014 0.004 0.003 0.019 0.016


mA
mA
mA
mA
mA
mA
0.015 0.015 0.003 0.004 0.016 0.015
mA
mA
mA
mA
mA
mA
0.016 0.015 0.003 0.003 0.014 0.015
mA
mA
mA
mA
mA
mA
0.595 0.595 0.120 0.118 0.607 0.607
A
A
A
A
A
A
0.594 0.594 0.119 0.118 0.606 0.606
A
A
A
A
A
A
0.595 0.595 0.119 0.118 0.607 0.605
A
A
A
A
A
A

Spill Across Stab. Res.


SRR - 122 mV/
( 1GT-Panel )
0.42 mA
1GT,TB
IN-LV(Y
BCT 3+5
1-37 )
0
0
Y ph
1000/1A
39
Spill Across Stab. Res.
SRY - 322 mV/
( 1GT-Panel )
1.46 mA
INBCT 3+5 1GT,TB HV(B
1-41 )
0
0
B ph
1000/1A
43
Spill Across Stab. Res.
SRB - 157 mV/
( 1GT-Panel )
0.255 mA

SDR - 122
mV
0

SDY - 322
mV
0

SRR - 132.6
mV

SRY - 337.8 SDY - 313.01


mV
mV
0

SDB - 156
mV

SDR - 132.8
mV

SRB - 157.33 SDB - 156.8


mV
mV

GENERATOR LBB PROTECTION RELAY 50Z1 & Z2 (P-141)


Sr
.
RELAY
N
o

50Z1&
Z2
4
LBB
PROT.
P141

CT
NO. &
CTR

NEW TB
NO.
1G,
TB1-21

CORE
4
1000/
1A

23
25
Neutral27

Previous(210
0 A)
Measu 50Z-1 50Z-2
re-1 (Pri) (Sec)
106.5 106.8
IA-1
A
mA
106.9 105.6
IB-1
A
mA
105.5 106.9
IC-1
A
mA

CJJ-09 PANEL

5 Meterin
g CT

CT F
20000/
5A

6 EHG+A
VR CT

107

CT G
20000/

Previous(990
0 A)
50Z-1 50Z-2
(Pri) (Sec)
503.8 504.2
A
mA
502.8 502.2
A
mA
505.0 504.1
A
mA

Current(200
0 A)
50Z-1 50Z-2
(Pri) (Sec)
0.101
101 A A
99.9 0.102
A
A
100.7 0.100
A
A

Current( 100
00 A)
50Z-1 50Z-2
(Pri) (Sec)
516.1 0.514
A
A
512.8 0.512
A
A
515.6 0.513
A
A

MEASURED CURRENT READING


2100 A
9900 A
(1997

(10000

Previous

Previous

A)
Curre

A)
Current

CJJ09-X02-

499.2 mA

2.35 A

nt
0.460

2.40 A

1
5

500.2 mA

2.37 A

A
0.473

2.46 A

504.5 mA

2.39 A

A
0.454

2.39 A

CJJ09-X02-

491.7 mA

2.29 A

A
0.452

2.34 A

11
16

499.5 mA

2.34 A

A
0.454

2.41 A

5A
20
7 EHG CT

CT H

504.7 mA

2.38 A

A
0.460

2.41 A
2.47 A

CJJ09-X02-

501.7 mA

2.37 A

A
0.471

25
27

507.2 mA

2.36 A

A
0.472

2.43 A

29

496.7 mA

2.39 A

A
0.455

2.37 A

20000/
5A

DURING OC TEST
MEASUREMENT-1

UAT-A

UAT-B

UAT-C

UAT-D

VAB / IA - 1

12.23 mA

12.51 mA

10.01 mA

11.36 mA

VBC / IB - 1

13.80 mA

13.33 mA

10.03 mA

10.70 mA

VCA / IC - 1

18.07 mA

17.58 mA

11.74 mA

12.30 mA

U # 5 GENERATOR SCC ( READINGS OF COD 8 )

METERI
NG CT
1
CT ' F '
20000/5

COD 8

GEN. CURRENT ON
COD8/TRIVECTOR
Previ
Curr
Previ
Curre
ous
ent
ous
nt
2100 2012
9900 10010
A
A
A
A
2007
10010
2103A
9890A
A
A

CT
CURRENT
for
2100 A /
9900A

CT
CURRENT
for
2012 A /
10100 A

1T - 82
(R)

484 mA/2.33
A

460
mA/2.40 A

1T - 83
(Y)

500 mA/2.37
A

473
mA/2.46 A

2102A

2011
A

9897A

10003
A

1T - 84
(B)

502 mA/2.38
A

454
mA/2.39 A

2105A

2012
A

9905A

10010
A

SR
CT NO.
.
LOCATI
&
TB NO.
N
ON
CTR
O.

U # 5 GENERATOR OCC ( READINGS OF COD 8 )


SR.
NO PT III
.
1 METERI
NG PT

LOCATI
ON
COD 8

TB NO.

PT VOLTAGE
AT 19.5KV

PT VOLTAGE
AT 21.1KV

1T - 91 &
92 ( RY )

94.9 V

105 V

1T - 91 &
93 ( BR )
1T - 92 &

108

95.2V

105.2 V

95.3V

105.3 V

GENERATOR KV
ON COD8
BR
RY
YB
19.5
19.5
19.5
KV
KV
KV
(Previou
s)

(Previou
s)

(Previou
s)

93 ( YB )
2

GEN.
SYN.
PT

COD 8

3T - 105
& 106

54.4 V

65.3 V

21.32
(curren
t)

21.05
(curren
t)

20.91
(curren
t)

PART- III
1. LIGHT UP, ROLLING AND SYNCHRONIZATION OF UNIT:
A) BOILER HYDRAULIC TEST:
1. DepartmentaL : Date : 24/01/2016 at 17:58Hrs Boiler press : 250Kg/CM2. And drum depressurised at
18:26 Hrs.
2. In presence boiler inspector : Date ; 26/01/2016 at 14.38Hrs., Boiler press ; 250Kg/CM2 kept for 3
minute and that pressure reduced to 50 kg/cm2 at 15:00 hrs. and boiler hydraulic test done at 15:45
hrs.
B) REHEAT HYDRAULIC TEST: Date 24/01/2016 at 19:00Hrs. Press 50Kg/cm2
C) OTHER ACTIVITIES:
Generator Filling:

CO2 filling
Starting Date &Time
: 27/01/16 at 23.31hrs
Cylinder consumed
: 70Nos with purity 100%.
Filling done
: 28/01/16 at 14.25hrs
H2 filling activity carried out.
Starting Date &Time
: 28/01/16 at 15.00 Hrs
Cylinder consumed
: 171+52=123Nos. (pressure-3.25 kg/cm2)
Filling done
: 29/01/16 at 11.45hrs
First Boiler Light up on 29/01/16 at 06.45hrs, Second Boiler Light up on 21/07/15 at 00.42hrs,
First blow down given at 10kg/cm2 at11:42hrs., second blow down given at 20kg/cm2 at 12:50 hrs

and third blow down given at 30kg/cm2 at15:19 hrs.,


Fourth blow down given at 40kg/cm2 (i) 16:21hrs
Fifth blow down given at 40kg/cm2 (ii) 16:47hrs
Sixth blow down given at 40kg/cm2 (iii) 17:46hrs
At 14:04 vacuum pump-A and at 14:15 vacuum pump B started
Stop valve opened at 18:40, turbine rolled to 3000 rpm at 21:42 hrs.
Set synchronized on 30/02/16 at 02.07 hrs.

109

3. POST OVERHAUL ACHIEVEMENTS :


PERFORMANCE OF UNIT-V BEFORE AND AFTER
Sr.
No
.

Parameters

Design
Values

Before
OH

After

13-Dec15

24-Feb16
424

OH

Turbine Side Performance

Load (MW)

500

423

Main Steam Flow

1524

1298

Steam Flow / MW (T/MW)

3.05

3.06

Main steam Temp (Deg C)

537

530

540

HRH steam Temp (Deg C)

537

535

532

HP Cylinder Efficiency (%)

85.96

IP Cylinder Efficiency (%)

91.41

Gross Unit Efficiency (%)

38.37

10

Vacuum (mm of Hg)

670.60

8753

8843

11

CW Temp I/L (Deg C)

30.00

30.4

33

12

CW Temp O/L (Deg C)

40.20

42.0

44.2

13

Air ingress kg/hr

40.00

64

64

14

Cleanliness Factor

89.00

56

61

15

Gross Turbine Efficiency (%)

43.61

39

44

Boiler Side Performance

Gas inlet temp (PAH A/B) C

356

339/317

331/334

Gas Outlet temp (PAH A/B) C

136

101/96

97/112

Gas inlet temp (SAH A/B) C

356

372/371

353/352

Gas Outlet temp (SAH A/B) C

136

199/176

135/151

Pri.Air temp after (PAH A/B) C

332

235/207

265/254

Sec.Air temp after (SAH A/B) C

326

313/312

330/332

Pri. Air / Sec Air I/L Temp C

42/43

39/41

Gas side effy (PAH A/B) %

67

74/76

70/70

10

Air side effy (PAH A/B) %

92

69/65

76/75

11

Gas side effy(SAH A/B) %

67

54/52

70/55

12

Air side effy (SAH A/B) %

92

79/84

85/90

13

Seal leakage (PAH A/B) %

15.56

23

10

14

Seal leakage (SAH A/B) %

6.10

23

110

15

Total Air Flow (T/hr)

1853

1476

1813

16

Total Coal Flow (T/hr)

300

341

330

17

Excess air %

20

11

16

18

Economizer inlet temp C

253

204

241

19

SH Spray T/hr

157

131

20

RH Spray T/hr

62

15

Performance Indicators

Boiler Efficiency

88.1

81.1

83.9

Corrected Boiler Efficiency

88.1

85.6

87.1

Gross Turbine Heat rate

1972

2170

2016

GCV of Coal

3750

Gross Unit Heat rate

2241

Sp Coal Consumption (As per Heat


rate)

0.598

3168

0.804

0.77

Last Overhaul: 14-07-13 to 31-08-13 (AOH)


Current Overhaul Started from: 27-12-2015 (18:50 hrs) to 30-01-2016 (02:07 Hrs) (33 Days)
Following Major Works are being carried out:
Complete Air Heater Basket assembly is replaced.
Total 32 coal compartment assemblies replacement with Upgraded coal compartment assemblies.
TDBFP-5B Cartridge replacement & Overhaul.
ACW & CCW header separated.
IDCT new cell interconnection with CCW return line of tower 5A & 5B is completed successfully during
COH.

Unit-5 (COH) Surprises :


LPT 2R blade no. 35 found damaged
HPCV no. 3 cone found damaged.
HP Bypass 1 & 2 Seat found Damaged.
IPT B/H casing inlet 1st stage stationary blades one bolt observed entangled in blade.
Pitting marks observed on Gen Rotor exciter end face.
Compressor stationary blades 1st row observed denting marks.
Leakage observed in 2 nos Current Carrying bolts. Generator rotor & Exciter rotor 1 no. each

Works Carried out :


1. Resolving ESV 1 To 4 Opening Problem
ESV 1 to 4 pilot Valve found jam, 3 Nos. of ESV valves pilot opened & made free after servicing, One
No ESV found jam to open so replaced by new.
2. Resolving Turbine Speeding Problem
HPCV 3 seat Damage Seat Repaired & IPSV Seat damage repaired by machining.
3. Resolving Factors Responsible For Poor Vacuum
LPT inlet bellow found puncture Replaced with new

111

Condenser tubes found chocked/blocked - Tube cleaning by Hydro jetting & Bullet shot

4. Resolving Factors Responsible For Poor Vacuum


Both TDBFP diaphragm found raptured replaced with new
Both TDBFP Exhaust butterfly valve found damaged so sealing ring replaced.
Vacuum pump 5A/5B diaphragm observed rupture, replaced with new.

5. Resolving EHC hunting problem


Cleaning and servicing of EH amplifier block

6. Condenser Cathodic Protection


80 nos. of Condenser cathodic protection elements installed in Waterbox to avoid (Hydrogen
embrittlement) deposition of hard scales in condenser & Improving condenser performance and
reduction in fouling factor
7. GTR Cooler Cleaning By SILICO6
GTR coolers observed fully chocked up causing high temperature problem. Lot of Ash deposition
observed in tubes from ACW sump. Cleaned by new technique organic compound SILICO6.
8. New soot blowing line from PRDS station to A/H is provided for effective air heater soot blowing.
(previously soot blowing was done through service air)
9. 100% Stator earth fault protection which was initially bypassed during synchronization, since last two
and half years is now put in service after trial. Now 40 MW interlock introduced.
PERFORMANCE
Condenser Side
Date

Design

03/12/2015

05/02/2016

Load (MW)

500

420

459

Vacuum

-670

631

652

30

32.67

30.55

40.2

43.89

41.97

LPT Exhaust Temp

43

51.37

47.84

Condensate Temp

43.1

50.36

46.27

Actual TTD

2.9

8.62

5.82

C.W Inlet temp


C.W Outlet temp
(mean)

112

Condenser
Efficiency
Cleanliness Factor

77.86

56.6

66.2

89.29

56

61

Air Heater Side


03/12/2015
Air heater performance

05/02/2016

Design
L

a) O2 at AH inlet (%)

3.5

3.4

3.6

5.0

5.2

b) O2 at AH outlet (%)

6.0

6.7

6.8

6.2

6.6

d) Flue gas temp at PAH I/L (Oc)

356

340

312

331

334

e) Flue gas temp at SAH I/L (Oc)

356

373

354

376

354

136

173

154

134

154

g) PA temp at AH outlet (Oc)

332

246

216

261

261

h) SA temp at AH outlet (Oc)

326

303

305

326

322

67

74.8/54.7

76.2/52.8

69.9/70.1

70.2/54.2

j) Air side effy (%) (PAH / SAH)

92

69.2/79.3

65.3/84.6

76.4/85.3

75.6/90

k) Air inleakage (%)

---

23

23

10

Excess Air (%)

20

f) Flue gas temp at AH Comn


O/L (Oc)

i) Gas side effy (%) (PAH /


SAH)

113

11

16

Boiler Side
Date

Design

03/12/2015

05/02/2016

Load (MW)

500

420

459

Operating boiler Effy. (%)

88.1

81.05

83.96

a) Unburnt loss (%)

0.60

0.30

0.33

b) Dry flue gas loss (%)

4.64

9.85

7.48

c) Coal (Moisture+H2) loss (%)

5.61

7.46

7.03

d) GCV of COAL

3750

3215

3416

Corrected blr effy (Design coal)

88.1

85.58

86.74

Design

03/12/2015

05/02/2016

1524.3

1326

1310

MS temp at HPT inlet-Deg C

537

534.73

536.96

MS press. at HPT inlet-kg/cm2

170

141.64

140.92

HRH temp at IPT inlet Deg C

537

528.00

526.70

Turbine Side
Date
MS flow at HPT inlet-T/Hr

114

HRH press. at IPT inlet-kg/cm2

39.4

33.65

36.99

HPT exhaust steam temp Deg C

342.6

350.91

346.95

CRH pressure-kg/cm2

43.90

39.69

40.03

Gross Turbine Heat Rate

1972

2170

2016

Gross Turbine Efficiency

43.61

39.63

44.09

HR Deviations
Date

03/12/2015

05/02/2016

Saving (Rs/Day)

Deviation in GUHR (Controllable)


Loss due to un burnt carbon

-9.73

-7.40

Loss due to dry flue gas

183.83

81.25

Radiation & other losses

-7.20

-10.02

MS temp at HPT inlet

0.78

0.10

MS pressure at HPT inlet

26.99

27.65

Re heater pressure drop

7.97

-4.10

Condenser vacuum

52.55

22.92

Loss due to Partial Loading

43.87

15.65

FW Temp at Eco Inlet

6.01

6.01

SH Spray

4.27

4.60

6,45,337

1,90,768

Deviation in GUHR (Un-Controllable)


Loss due to moisture in fuel

46.05

46.88

Loss due to H2 in fuel

16.18

-6.48

HRH temp

4.54

4.58

RH Spray

14.75

4.90

65,010

POG Observations
1. Improvement in ID/PA Current by @15 & 10 Amp Respectively.
Auxiliary

115

Unit

Before

After

Reduction in Current

ID Fan-A

Amp

122

105

14

ID Fan-B

Amp

123

95

23

ID Fan-C

Amp

122

105

14

ID Fan-D

Amp

120

110

PA Fan-A

Amp

145

125

14

PA Fan-B

Amp

139

130

2. Increase in ID margin by 30% from 82% at 373 MW load to 52% at 443 MW load.

Before

After

ID Fan-A

81.6%

52.1%

29%

ID Fan-B

82.1%

52.5%

30%

ID Fan-C

81.7%

52.2%

30%

ID Fan-D

82.0%

52.4%

30%

IMPREOVEMENTS
1. Condenser Vacuum improved by @ 21 mmHg
2. Condenser cleanliness factor improved by @ 5 %
3. Improvement in Air side efficiency of Air heater observed.
4. Reduction in air in leakages @ 14 %
5. Reduction in RH spray by @ 52 T/hr resp.
6. Boiler efficiency improved by 2%
7. Improvement in Gross turbine heat rate by @154 Kcal/Kwh
8. Now after COH no boiler side drain valves are passing as per last test.
9. Windbox DP improved by @25 mmwcl i.e from 75 / 80 to 105 / 100

116

Gain in Vane

Auxiliary

Position

Unit-5 COH-2015 EXPENDITURE (In lakhs)


Unit-5 COH-2015-16 Expenditures (In Lakhs)
Section

R & M Expenditures
Supply

Works

Total
(R & M

Capex Expenditures
Supply

Works

Expenditures)

Total
(Capital
Expenditures
)

BM-II

1322.977

669.231

1992.209

540.898

52.582

593.481

TM-II

284.303

388.395

672.698

NIL

NIL

NIL

EM-II

52.75

50.63

103.38

NIL

NIL

NIL

I & C-II

14.46

21.72

36.18

NIL

NIL

NIL

Test-II

5.47112

7.97110

13.44222

NIL

NIL

NIL

ODP-II

119.58

46.51

166.09

NIL

NIL

NIL

117

Total

1799.54112

1184.4571

2983.99922

540.898

52.582

Grand Total (Rs. in Lakhs)

593.481

3577.48022

DETAIL COSTING OF EACH SECTION AS FOLLOWS:


Expenditures of Boiler Maintenance-II during COH-U5 in 2015-16
R & M EXPENDITURE
Sr.

Works carried out

No.
1
2
3
4
5

Name of

Supply

Works

Contractor

Cost

Cost

2665330

6810350

9475680

1777155

6817666

8594821

727685

2615503

3343188

698920

2615503

3314423

42448061

2138610

44586671

Work of repairs of HP parts in Furnace

M/S. Sunil Hi-

Zone ( I Pass)

Tech

Work of repairs of HP parts in Furnace

M/S. Adore

Zone ( I Pass)

Contractors

Work of repairs of HP parts repairs in

M/S. Bhavana

LTSH & Eco.(II Pass)

Const. Co.

Work of repairs of HP parts repairs in

M/S. V. K.

LTSH & Eco.(II Pass)

Enterprises

Work of Repairs of Air Pre-heaters (PAH

M/S. Bhavana

& SAH) RHS

Const. Co.

118

Total Cost

6
7
8
9
10

Work of Repairs of Air Pre-heaters (PAH

M/S. Sunil Hi-

& SAH) LHS

Tech

Servicing of BT Mechanism (Corner 1 &

M/S. Bhavana

2)

Const. Co.

Servicing of BT Mechanism (Corner 3 &

M/S. Adore

4)

Contractors

Servicing of FG & Air Dampers of PAH &

M/S. Ganesh

SAH

Engg.

Servicing of ID, FD, PA Fans

M/S. Ganesh

1710888

1710888

788930

12840667

631144

631144

289350

469232

758582

170550

467858

638408

6875865

1663489

8539354

111015

111015

1891444

1891444

5756006

1078656

6834662

2724730

2724730

12051737

Engg.
11

In-Situ repairs of Control and HP Isolating

M/S. Ideal

valves.

Engineering

Work of Radiographic Inspection of weld

M/S. Parikshak

joints.

Nirikshak

Work of Ultrasonic Thickness

M/S. P R

Measurement of Boiler Tubes

Sahare

Carrying out CAVT & Implementation of

M/S. Favourite

Erosion Control Device

Fabricators

Inspection & Scanning of WW Tubes by

M/S. MRP Nair

LFET

Engineers

16

Complete RLA Study of Boiler

M/S. BHEL

8696894

8696894

17

Providing Assistance to BHEL Team for

M/S. Ganesh

320816

320816

RLA Study

Engg.

Work of Replacement of BCWP motor &

M/S. V.A.

95000

170328

265328

its cooler cleaning

Constructions

Work of Replacement of SAH FG Outlet

M/S. Bhavana

4614645

574164

5188809

damper GD 4A

Const. Co.

Servicing of Actuators

M/S. S. K. Sales

65000

330550

395550

12
13
14
15

18
19
20

Corp.
TOTAL Rs.

78,235,30 42,627,77 120,863,074


4

COAL MILLS

119

S.No

Particular

Supply Cost

Work Cost

Consumables
4,655,550

All Coal Feeder Iso Gates Servicing

138400

49595

All Coal Feeder COC Modifications

246400

25000

All HAG/HAD Servicing

24812

All CAG/CAD Servicing

18609

CAD Hastalloy Seal replacement

2040000

552400

C/M 5A Airport replacement

400000

80000

C/M 5E 'C' Type

3471682

300000

Coal Pipe/Bends/Orifice Repl

12554266.96

4531156

Classifier Vanes Servicing

93903

10

Seal Air Fan Suction Filter Cleaning

46028

11

Painting of Coal Mills & Structures

12

Repair/Replacement of Drive Air Seal

2687304

1294541

21,538,053

7,016,044

System, MDV, MOE


4,655,550

33,209,647

ESP
S.NO
1

DESCRIPTION OF WOK
REPAIRS OF FLUE GAS DUCT FROM

COSTING

COSTING

TOTAL

SUPPLY

WORKS

3760500

2173954

5934454

2558246

3130324

5688570

1554000

407000

1961000

1475000

365000

1840000

5150000

1791098

6941098

200000

904616

1104616

ECO O/L TO ESP I/L, HOT AIR DUCT


AND ESP O/L DUCT
2

SERVICING OF BOTTOM ASH


EVACUATION SYSTEM INTERNAS AND
REPLACEMENT OF DAMAGED
REFRACTORY

WORK OF SERVISING OF COARSE ASH


EVACUATION SYSTEM AND REMOVAL
OF ASH & DEBRIES.

WORK OF SERVISING OF FLY ASH


EVACUATION SYSTEM.

WORK OF SERVISING AND


OVERHAULING OF COMPLETE ESP.

WORK OF SERVISING OF GUILLITINE

120

GATES OF ESP I/L & O/L.


7

WOKRK OF REPLACEMENT OF

4516352

1204616

5720968

850150

355000

1205150

2859350

1523184

4382534

4945250

5472400

10417650

27,868,848

17,327,192

45,196,040

METALLIC EXPANTION JOINTS


8

WORK OF SERVISING OF ASH FEED


GATE.

WOKRK OF REPLACEMENT OF FABRIC


EXPANTION JOINTS

10

WORK OF CFD ANALYSIS &


INSTALATION OF DIVERTER PLATES

TOTAL R & M

199,268,761

COST
CAPITAL EXPENDITURE
PRESSURE PARTS
S.No.
1
2
3

ITEMS
BASKETS
CCA

Supply Cost

Works Cost

Total Cost

38943998

1710888

40654886

1710888

1710888

631144

11162344

631144

631144

4614645

574164

5188809

54089843

5258228

10531200

FG DAMPER

Capital Exp. Total

59,348,071

COAL MILL
S.No

ITEMS

Supply Cost

Works Cost

Total Cost

NIL

ITEMS

Supply Cost

Works Cost

Total Cost

.
1

ESP
S.No

121

.
1

NIL

TOTAL SUPPLY COST

78235304

TOTAL WORKS COST

42627770

TOTAL COST

120863074

Less Capex Cost

59348071

Total R&M Cost (Total Cost - Capex)

61,515,003

Consumables

R&M

CAPEX

Supply

Works

78,235,304

42,627,770

CM

21,538,053

7,016,044

ESP

27,868,848

17,327,192

127,642,205

66,971,006

PP

4,655,550

Total

4,655,550

Supply

Works

54,089,843 5,258,228

54,089,843 5,258,228

132,297,755
GRAND

TOTAL

258,616,832

TURBINE MAINTENANCE - II
SR.

E-CODE

MATERIAL DESCRIPTION

UNIT

QTY

AMOUNT

NO
1

A115050250050004

PMP OIL TUSHACO T3SA38/36 PMP CTDG ASSY

EA

2,112,078.21

A036020220010003

FIRE RESISTANT FLUID REOLUBE TURBOFLUID

KG

690

1,995,273.00

A093240010050013

TBN STEAM MODULE CASING COMPENSATOR DN

EA

1,500,000.00

VALVE CONE FOR HPCV NO 3

EA

1,200,000.00

60
4
5

A133190010010025

DRG 09-SHF2 / 162-E5 COMPLETE MECH SEAL

EA

1,175,697.29

A031020010010001

HEATEXCH CRFLOW CONDNSR TUBE

EA

154

956,878.69

122

A133190010020001

M/SEAL BFP NDE COMPLT MECH SEAL

EA

944,763.38

A093590010010009

TBN LPT BLADE MOVING MOVING BLADE 2L

EA

886,206.90

A115090380050142

PMP WTR WEIR THRUST BRG

EA

742,320.00

10

A093590010010013

MVNG BLADE CLAMPING PIECE P.N.007

EA

504

737,409.32

11

A093290040010021

PILOT VALVE DRG.NO. 0-114-04-2000C PN 17

EA

661,396.04

12

A093290040010025

IPCV SM PILOT VALVE ASSY

EA

661,396.04

13

A115090380050122

PMP WTR WEIR RING SECTION SECOND STAGE

EA

444,182.13

14

A036020130010003

LUBRCNT OIL SP HYDR IOC SERVO SYS HLP 32

2730

408,004.01

15

A075170140170006

VLV CL2500WC9 65NB VALVE ASSY MANUAL BW

EA

407,818.95

16

A066010080030003

SIZE 8 X 6 MODEL-67-91222 - PLUG SEAL RI

EA

382,653.00

17

A036020160020011

LUBRCNT OIL TURB IOC SERVO PRIME 46

2310

371,576.49

18

A115090380050040

CU-MS GASKET 605 O / D X546 I / D X 3 TH

EA

306,658.40

19

A023010020100005

FRF SUPERFINE FILTER (SIZE 18"x5"x1")

EA

14

288,456.00

20

A023010020100002

ANY MAKE AS PER IS STANDARD DUPLEX FILER

EA

257,308.50

21

A036020160010008

LUBRCNT OIL TURB HPCL TURBINOL 46

1470

241,403.40

22

A035020050070016

LONG TRAVEL DRIVE SHAFT

EA

209,322.96

23

A118080080010011

TBTDJ2M CIRCLIP PN 2480061150

EA

33

195,525.00

24

A093290010100022

MODULE SHFT SEAL SCREW HEX PM 12 X 60

EA

55

192,555.00

25

A115090380050108

PMP WTR WEIR OUTLET GUIDE

EA

179,416.73

26

A066010080030002

SIZE 8 X 6 MODEL-67-91222 - BONNET SEAL

EA

174,277.20

27

A133300020010021

M/S CEP EB SILICONE CARBIDE FACE

EA

161,700.39

28

A115090380050135

PMP WTR WEIR SHEAR RING

EA

10

143,694.48

29

A093590010010014

MVNG BLADE CLAMPING PIECE P.N.008

EA

202

128,669.41

30

A075010030020006

VLV ENER SEAL RING (PLUG) PN 13

EA

127,551.00

31

A107080020010006

CR PLAIN SHEET SIZE 5000 X 1250 X 3.15MM

TO

123,200.00

32

A075190190100008

VLV 40NB ASSY RISING SPINDLE MANUAL SW

EA

121,961.31

33

A075170100030005

VLV CL150WCB CS 150NB VLV ASSY MANUAL FL

EA

117,959.51

34

A133300010010001

M/S CEP EN7J40D EB CARBON FACE (PN-B)

EA

106,150.28

35

A075190190110008

VLV 50NB ASSY RISING SPINDLE MANUAL SW

EA

102,372.07

36

A093510100010001

BLADDER 50L CAPACITY/35 KG/CM2 PRESSURE

EA

100,974.90

37

A107010010010110

ANGLE MS EQUAL 50 X 50 X 6 MM

TO

96,900.00

38

A075190190030008

VLV 15NB ASSY RISING SPINDLE MANUAL SW

EA

90,663.44

39

A115090380050098

PMP WTR WEIR OIL THROWER

EA

83,910.94

40

A088010040010017

TG500MW SEALING HALF RING BOTTOM

EA

124

82,138.00

41

A093290010100028

TBNSTEAM MODULE SHFT SEAL SEALING RING

EA

120

80,856.00

42

A075170100030005

VLV CL150WCB CS 150NB VLV ASSY MANUAL FL

EA

78,639.67

43

A031020010020003

SPONGE RUBBER BALL DIA 29 MM MEDIUM ELAS

EA

4400

75,488.55

123

44

A093530060040023

TEST VALVE FOR SERVOMOTOR LINER ITEM 01

EA

74,959.80

45

A093510090010004

STEAM TURB OIL REGEN SYS FULLER EARTH

KG

1950

70,609.50

46

A093560010030009

BRG HOSE EXTR BRG DRG 1142140100000001

EA

70,541.26

47

A027010010230006

JOINTINGSHET SUPER MET1525X1650MMTH3.0MM

KG

214

70,245.94

48

A133050010010003

M/S BOOSTR BFP EB SEAL FACE CARBON PN 11

EA

63,328.15

49

A036020020010027

LUBRCNT OIL CIRC IOC SERVO SYSTEM 68

420

62,654.38

50

A115090380050099

PMP WTR WEIR OIL THROWER NDE

EA

62,318.31

51

A075190160100008

VLV 40NB ASSY RISING SPINDLE MANUAL SW

EA

59,702.89

52

A133300010010005

M/S CEP EN7J40D EB MATING RING ( PN-2)

EA

58,933.64

53

A078010010030001

CHEM ADH COMP ST-SEL JOINT PASTE TYPE B

KG

19

58,860.48

54

A075010020040007

PTFE BACKUP RING P.N. 079003552-940

EA

56,132.71

55

A093390010040015

MODULE CASING STUD BM 80X 6X 600-25X 551

EA

53,915.00

56

A003060010020015

ACT HYD SLZ ASM100-10 PSTN SEAL PN 6078

EA

53,172.89

57

A066010080030009

8 X 6 -67-91222 - SEAT GASKET

EA

45,379.80

58

A115030230020039

PMP CHEM SHAPO DP-60-PNM WORMWHEEL

EA

45,000.00

59

A133050020010010

BFP PUMP FA-1B-75 INSERT MOUNT VITON PN6

EA

44,450.76

60

A133050020010009

BFP PUMP MOD FA-1B-75 INSERT CARBON PN.2

EA

42,656.66

61

A093390010070034

TRBN STM FITTED KEY PN 36

EA

41,642.00

62

A115030230010022

PMP CHEM SHAPO MAIN HD,NUT,PLNGR ASY

EA

41,600.00

63

A115030230010046

PMP SHAPOTOOL DP30PNM CRANK SHAFT

EA

40,000.00

64

A036020020010023

LUBRCNT OIL CIRC IOC SERVO SYSTEM: 176

250

39,943.46

65

A107040010030014

MS ISMC CHANNEL SIZE 150 X 75 MM

TO

39,205.95

66

A003060010010006

ACT HYD SLZ ASM250-10 PSTNROD SEL PN6021

EA

37,151.06

67

A027010010240007

GSKT&PCK JNT SHT1525 X 1650 MM TH 3.0 MM

EA

150

36,045.82

68

A093530020030020

TUR MOP RING D185 PN 41

EA

35,326.89

69

A003060010010008

ACT HYD SLZ ASM250-10 SCRPR RNG PN 6023

EA

34,212.56

70

A035020050070017

MICRO COUPLING GEARBOX SIDE HUB

EA

33,879.78

71

A027010010230007

JOINT SHEET 1525X1650MMTH4.0MM

KG

100

32,511.63

72

A093250010050002

MODULE CASING BOLT HEX PM 56 X 200

EA

31,925.93

73

A118080080080007

COMPR TBTDJ2M VLV SEAT DEL LP 2480070150

EA

12

31,920.68

74

A028040050010026

GLAND RING GRAFOIL 50 X 32 X 10 MM

EA

56

31,864.00

75

A003060010020008

ACT HYD SLZ ASM100-10 SCRPR RNG PN 6023

EA

30,434.48

76

A118080080050009

COMPR TBTDJ2M PISTON RING LP 2481033550

EA

30,223.48

77

A035020050070018

MICRO COUPLING MOTOR SIDE HUB

EA

30,115.36

78

A027010010240010

JOINTG SHEET STYLE 54 1525 X 1650 X 4 MM

KG

120

29,449.64

79

A075220030110006

VLV NRV FLAP CL150WCB CS SWING 80NB ASSY

EA

29,161.00

80

A070040040270001

WELDSOLBRAZ ELECTRODE CI CINOD160 2.5MM

KG

28,631.96

124

81

A133050010010004

H75F2/100E3 O-RINGS SET 1.2,3,5,7

ST

28,614.89

82

A003010040010004

ACTUAT MOTORD ROTORK BUSH

EA

28,554.24

83

A028120010030042

GSKT SEAL RING GRAFOIL ANG 680X635X40 MM

EA

28,521.75

84

A010010070020002

SPC NO 4500 SET OF 27 BELT

EA

29

28,146.03

85

A118080080080012

COMP TBTDJ2M VALVE GUARD DELIVERY H P

EA

53

27,354.36

86

A078020130070001

LUBRICANT MOLYKOTE MOLYKOTE 1000

EA

17

26,010.00

87

A118080080050018

COMPR TBTDJ2M GUIDE RING HP 2480038751

EA

16

25,344.00

88

A093590010010016

MVNG BLADE LOCKING PLATE P.N.010

EA

10

25,221.98

89

A003060010010007

ACT HYD SLZ ASM250-10 GUIDE RNG PN 6022

EA

25,187.16

90

A070040090100001

ELECTRODE SPRG ST UNILOY 624 2.5MM

KG

10

24,474.65

91

A133300010010019

MECH SEAL CEP EN-7-J-40-D CUP

EA

24,437.98

92

A028040050010048

GLAND RING GRAFOIL 68 X 44 X 12 MM

EA

42

23,898.00

93

A078020130070008

MOLYKOTE HSC PLUS PASTE

KG

23,669.10

94

A078010010050040

CHEM ADH COMP SEAL HY UBLUN-SET ST 100GM

EA

47

23,011.20

95

A093250010010013

TBNSTEAM 500MW MODULE CASING FITTED KEY

EA

22,942.00

96

A093390010070031

TRBN STM FITTED KEY PN 03

EA

22,942.00

97

A093390010070033

TRBN STM FITTED KEY PN 35

EA

22,942.00

98

A093390010070032

TRBN STM FITTED KEY PN 04

EA

22,501.00

99

A115090380050005

PMP WTR WEIR BAFFLE PLATE

EA

22,474.24

100

A115090380050079

IMPELLER WEAR RING KICKER STAGE

EA

22,285.24

101

A115050020010167

PMP OIL ALF/LVL MAB103 WTR ADNG DVIC CMP

EA

21,234.51

102

A093510010020007

MOP BRG BUSH

EA

19,590.01

103

A093240010090001

TBNSTEAM 500MW MODULE ATM DIAPH DIAPHRAG

EA

19,246.34

104

A115030160010026

PMP MC2/R LIQUID HEAD 25PBLH01

EA

18,872.54

105

A115080050020008

PMP VACCUM SIEMENS RETAINING RING

EA

18,660.00

106

A003060010020006

ACT HYD SLZ ASM100-10 PSTNROD SEL PN6021

EA

18,657.15

107

A027010010220007

JOINTINGSHET OIL NONMET1525X1650MMTH3MM

KG

71

18,413.46

108

A118080080040013

T-BTD-JM 06 PIECE PACKING TAN 2480102050

EA

20

16,000.00

109

A075010030020012

VLV SEAT RING GASKET PN 20

EA

15,126.60

110

A028040050010045

GLAND RING GRAFOIL 66 X 42 X 12 MM

EA

26

14,794.00

111

A003060010020007

ACT HYD SLZ ASM100-10 GUIDE RNG PN 6022

EA

13,526.43

112

A115090380070012

DE OIL GUARD IN BOARD PN 11

EA

13,361.04

113

A028040050010019

GLAND RING GRAFOIL 41.3 X 17.2 X 12 MM

EA

23

13,087.00

114

A118080080080006

COMPR TBTDJ2M VLV SEAT SUC HP 2480065150

EA

12,637.57

115

A115080040020014

PMP VCUM FIXED BEARING P/N 120

EA

12,500.00

116

A114010050020081

FASTNRS M 30 X 110

EA

13

11,850.16

117

A093390010070021

MODULE SHFT SEAL SCREW HEX AM 36 X 180

EA

10

11,720.64

125

118

A115090380050154

PMP WATER LUB OIL FILTER

EA

11,704.50

119

A003010040010054

ACTUAT MOTORD ROTORK K1000 THRUST BRG

EA

11,503.64

120

A118080080020002

AIR COMPR TBTDJ2M BRG PN 2510041850

EA

11,496.45

121

A036020160020009

LUB OIL TURBINE IOC SERVO PRIME 68

70

11,256.80

122

A093560010030006

BRG HOSE DN 16x2500 DRG 011814-02000/50

EA

11,025.59

123

A023010020100003

ANY MAKE AS PER IS STANDARD GOVERNING OI

EA

10,924.20

124

A072020010070058

BRG MET BALL SADR 2309 ETN9C3

EA

10,264.00

125

A028040050010014

GLAND RING GRAFOIL 35 X 25 X 08 MM

EA

18

10,242.00

126

A028100030010182

SPIRAGATE SS304 ASBT 5285 X 5025 X 45 MM

EA

10,000.00

127

A028100030010222

GSKT SS 304 ASBESTOS FILL 95 X80X 3.2 MM

EA

10,000.00

128

A115030230020038

PMP CHEM SHAPO DP-60-PNM WORM SHAFT

EA

10,000.00

129

A093560010030002

BRG HOSE DN 16x2200 DRG 011703-27000/31

EA

9,900.53

130

A115090380050001

PMP WTR WEIR AIR VENT 3 / 4" NPT

EA

9,831.97

131

A118080080080031

COMP TBTDJ2M VALVE GUARD SUCTION H P

EA

9,432.00

132

A003010040040029

ACTUAT MOTORD K600 L_SWITCDRIVESHFT

EA

10

9,151.58

133

A072020010070060

BRG MET BALL SADR 2310 C3

EA

8,935.20

134

A114070050020001

FASTNRS M 12 X 40

EA

346

8,650.00

135

A115090380050061

PMP WTR WEIR FLOATING SEAL

EA

8,571.25

136

A003010040010005

ACTUAT MOTORD ROTORK CENTRE COLUMN

EA

8,520.08

137

A028120010030035

GSKT SEAL RING GRAFOIL ANG 330X280X35 MM

EA

8,213.07

138

A072020010030016

BRG MET BALL DRANGCONT 3310 A

EA

8,172.57

139

A115050400010027

PMP OIL SHARPLES AS 12 FLEXIBLE COUPLING

EA

8,100.00

140

A072020010080065

BRG MET BALL SRACONT 7318 BEP

EA

7,800.39

141

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC SERVO GEM 03

KG

40

7,559.05

142

A036020100010018

LUBRCNT OIL IND GEAR IOC SERVOMESH SP68

50

7,548.00

143

A028100030010195

GSKT SS 304 ASBESTOS FILL 65 X25X 3.2 MM

EA

7,500.00

144

A027010010220005

GSKT&PCK JNT SHT1525 X 1650 MM TH 1.5 MM

KG

30

7,282.86

145

A134010060050003

CLOTH GENERAL CANVAS CLOTH

22

7,068.60

146

A119020180010002

NORMEX 128 COUPLING SPIDER

EA

7,038.00

147

A003010040040004

ACTUAT MOTORD ROTORK K600 BUSH

EA

6,884.44

148

A115090380050003

PMP WTR WEIR BAFFLE DE

EA

6,500.00

149

A093560010030001

BRG HOSE DN 16x2500 DRG 011604-18000/04

EA

6,311.59

150

A028040050010007

GLAND RING GRAFOIL 26.3 X 13.5 X 6.2 MM

EA

11

6,259.00

151

A118080080100001

AIR COMPR TBTDJ2M OIL WIPER RING

EA

43

6,235.00

152

A078010010030008

STEAM SEAL RTV 1080 NEUTRAL

EA

35

5,997.60

153

A036020060010011

LUBRCNT OIL ENGINE IOC SERVO PREM 15W40

32

5,712.00

154

A028040050010006

GLAND RING GRAFOIL 25 X 16 X 05 MM

EA

10

5,690.00

126

155

A028040050010029

GLAND RING GRAFOIL 54 X 32 X 11 MM

EA

10

5,690.00

156

A093560010030003

BRG HOSE DN 16x1200 DRG 011818-27000/49

EA

5,344.04

157

A072020050020006

BRG MET SPHR SEALGN 22207 E

EA

5,274.60

158

A001020010010005

ABR COMP CARLAP MESH SIZE80,200GMTIN

PAC

10

5,148.95

159

A075430200020003

BALL VALVE 40MM(CS BODY)

EA

5,102.89

160

A133300010010020

MECH SEAL CEP EN-7-J-40-D T-WASHER

EA

4,771.80

161

A075430200020006

BODY CS COMPLETE BALL VALVE 15 MM

EA

4,769.52

162

A003010040010029

ACTUAT MOTORD K1000 L_SWITCHDRIVESHFT

EA

4,655.15

163

A003010040040005

ACTUAT MOTORD K600 CENTRECOLACTUAT

EA

4,628.40

164

A027070010090001

GSKTMTRL 1000 MM X 2000 MM

KG

50

4,608.11

165

A072020010080039

BRG MET BALL SRACONT 7309 BEP

EA

4,520.85

166

A027130060070002

PTFE SHEET TH 3.0 MM 300 MM X 300 MM

EA

4,279.72

167

A003010040010035

ACTUAT MOTORD ROTORK K1000 OIL SEAL

EA

4,279.37

168

A107070010010027

RECTANGULAR TH 0.80 MM, 14" X 48"

EA

4,180.20

169

A028040050010062

GLAND RING GRAFOIL 85 X 60 X 12.5 MM

EA

3,983.00

170

A115030160020014

PMP CHEM MEATCHEM MC3/R PLNGR RNG PI D20

EA

3,926.61

171

A075430200020005

BALL VALVE CS COMP ASLY SIZE-20 MM

EA

3,813.57

172

A107070010010025

RECTANGULAR TH 0.70 MM, 14" X 48"

EA

3,799.79

173

A027190010010001

GSKTMTRL 3 MM THICK

KG

14

3,635.26

174

A075430200020004

BALL VALVE CS COMP ASLY SIZE-25 MM

EA

3,607.89

175

A115050020010171

PMP OIL ALF/LVL WORMWHEEL, PN:515799-04

EA

3,500.00

176

A028040050010004

GLAND RING GRAFOIL 19 X 13 X 07 MM

EA

3,414.00

177

A027070010080001

GSKTMTRL 1000 MM X 2000 MM

KG

35

3,341.02

178

A115050400010035

PMP OIL SHARPLES AS 12 IDLER SPINDLE

EA

3,200.00

179

A093560010090032

SHIM PN 118180200000016

EA

3,132.07

180

A027070010070001

GSKTMTRL 1000 MM X 2000 MM

KG

35

3,130.71

181

A028020060010001

GSKT H2 COOLR SILICON RUBBR 245x214x15

ST

3,060.00

182

A115090380050149

NEOPRENE RUBBER GASKET FOR CI QUENCH FIL

EA

3,037.00

183

A114010050010048

FASTNRS M 24 X 60

EA

40

3,030.92

184

A130060050010003

DUMMY PLUG TAPER SIZE 30 X 26.5 X 50 MM

EA

22

3,029.93

185

A115080050020015

PMP VACCUM SIEMENS THREADED PIN

EA

3,000.00

186

A070040080030001

ELECTRODE MS CHROMOTHERM II 2.5MM

KG

2,959.97

187

A115050020010206

PMP OILMAB-103 O-RING PN 66554

EA

20

2,900.00

188

A118080080040014

T-BTD-JM 03 PIECE PACKING RAD 2480102150

EA

2,850.00

189

A028040050010036

GLAND RING GRAFOIL 56 X 40 X 08 MM

EA

2,845.00

190

A001020010010006

ABR COMP CARLAP MESH SIZE140,200 GMTIN

PAC

2,801.27

191

A107070010010019

RECTANGULAR TH 0.45 MM, 14" X 48"

KG

2,796.84

127

192

A093560010090047

SHIM S=2 PN 118180200000011

EA

2,743.76

193

A028120010030021

BONNET SEAL RING 150 X 135 X 15 MM

EA

2,717.60

194

A114030080040014

FASTNRS M 4

KG

70

2,660.00

195

A072020020050007

BRG MET CYLROL NUTYPE NU 211

EA

2,575.05

196

A133300020010014

M/S CEP EN7J40D EB "O" RING - 25

EA

2,565.00

197

A093590020030041

PLATE PN 0107440200000048

EA

2,553.70

198

A028120010030004

GSKT SEAL RING GRAFOIL ANG 105 X91X14 MM

EA

2,535.00

199

A028080020030004

SERRTD METAL RING CIRCLR 104 X86X 3.2 MM

EA

2,512.00

200

A028080020030006

SERRTD METAL RING CIRCLR 105 X95X 3.2 MM

EA

2,512.00

201

A028100030010087

SPIRAGATE SS304 ASBT 149 X 133 X 4.5 MM

EA

2,500.00

202

A028100030010126

SPIRAGATE SS304 ASBT 224 X 198 X 35 MM

EA

2,500.00

203

A115030230010017

PMP CHEM SHAPO DP-30-PNM GLAND NUT

EA

2,500.00

204

A115050400010008

PMP OIL SHARPLES AS 12 BEARING SLEEVE

EA

2,500.00

205

A093560010090044

SHIM S=0.5 PN 118180200000012

EA

2,461.59

206

A118080080030002

COMPR TBTDJ2M SUC FILTER 500X500X50

EA

2,450.00

207

A027010010030006

1525 X 1650 MM, STYLE 59 / K SOE OIL

KG

12

2,423.52

208

A114070050010093

FASTNRS M 8 X 20

EA

307

2,410.48

209

A028040020020092

GLAND RING GRAFOIL 55 X 28 X 14 MM

ST

50

2,318.54

210

A114010050010047

FASTNRS M 24 X 100

EA

25

2,282.27

211

A118080080080005

TBTDJ2M VLV SPRING DEL HP 2460067250

EA

11

2,264.00

212

A070040080030002

ELECTRODE MS CHROMOTHERM II 3.15MM

KG

2,245.84

213

A107070010010166

SHIM SS N-M RECTAN TH 0.02MM 48X14 INCH

EA

2,177.70

214

A114010050010040

FASTNRS M 20 X 50

EA

45

2,169.98

215

A107070010010037

RECTANGULAR TH 3.00 MM, 14" X 48"

KG

2,148.75

216

A093560010090033

SHIM PN 118180200000017

EA

2,143.24

217

A027010010220006

STYLE 59 OIL NON METALLIC 1525X1650MM TH

KG

11

2,130.92

218

A107070010010036

RECTANGULAR TH 2.50 MM, 14" X 48"

KG

2,106.30

219

A115030160020032

PMP MC3/R LOCK NUT 35PA23L

EA

2,100.00

220

A114030120010007

FASTNRS M 16

EA

270

2,025.66

221

A114010090010146

FASTNRS M 33 X 175

KG

25

1,989.00

222

A114010090010145

FASTNRS M 33 X 150

KG

25

1,983.00

223

A115050020030070

PMP OIL ALF/LVL GLASS TUBE73921

EA

1,912.28

224

A093560010090042

SHIM S=0.2 PN 118180200000013

EA

1,884.39

225

A070040100060001

WELDSOLBRAZ ELECTRODE SS RUTOX B 2.5MM

KG

1,880.00

226

A072020010090008

BRG MET BALL SRDG 6309

EA

1,845.92

227

A093560010090034

SHIM PN 118180200000018

EA

1,813.24

228

A107070010010031

RECTANGULAR TH 1.00 MM, 14" X 48"

KG

1,766.45

128

229

A114010090010117

FASTNRS M 24 X 100

KG

20

1,724.29

230

A028040020020097

GLAND RING GRAFOIL 60 X 38 X 11 MM

ST

50

1,724.04

231

A078010010020017

CHEM ADH COMP STEEL M SEAL-FASTCURE 1KG

KG

1,723.82

232

A028040050010065

GLAND RING GRAFOIL 115 X 92 X 9.5 MM

EA

1,707.00

233

A107070010010123

SHIM RECT TH 0.30 MM, 48 X 14 INCH

KG

1,677.90

234

A047010080100029

VITON O-RING CS DIA 4 MM ID 297 MM

EA

1,671.19

235

A114010050010030

FASTNRS M 16 X 50

EA

94

1,665.86

236

A072020080010044

METRIC ADAPTER SLEEVE WITH LOC NUT H3124

EA

1,650.02

237

A093560010090035

SHIM PN 118180200000019

EA

1,647.66

238

A072020060010137

METRIC TAPER ROLLER SINGLE ROW 30306 J2

EA

1,645.60

239

A093560010090040

SHIM S=0.1 PN 118180200000014

EA

1,640.67

240

A078020060030001

CHEM CNTCT-CL KLINIT SPRAY TIN 350 ML

EA

1,612.72

241

A115050020010173

PMP OILMAB-103 BUSHING PN 523644-03

EA

1,600.00

242

A107070010010035

RECTANGULAR TH 2.00 MM, 14" X 48"

KG

1,596.77

243

A010010030380001

BELT V-BELT C NO 204 SET OF 4 BELT

EA

1,580.73

244

A115030160010021

PMP CHEMICAL METACHEM CIRCLIP FOR CONTRO

EA

20

1,580.00

245

A078020160070001

CHEM 1 GALLION TIN PACK

EA

1,547.34

246

A027190030010002

GSKTMTRL 5 MM X 50 MM IN 5 KG PK

KG

1,538.14

247

A115030160020007

PMP CHEM MEATCHEM MC3/R ECCENTRIC 35PA13

EA

1,499.00

248

A028120010030020

GSKT SEAL RING GRAFOIL ANG 145X127X18MM

EA

1,435.25

249

A114010090010088

FASTNRS M 20 X 100

KG

17

1,427.93

250

A075430180010001

VLV BALL SS 1/2INCH VALVE ASSY

EA

1,418.37

251

A114010050010120

FULL THREAD M 20 X 90

EA

30

1,415.25

252

A029090020010011

POWDER FORM DETERGENT SURF 0.5 KG PACK

EA

20

1,372.80

253

A115050020010221

PMP OILMAB-103 SPLIT PIN PN 16434

EA

18

1,350.00

254

A072020010030008

BRG MET BALL DRANGCONT 3305 AP

EA

1,342.91

255

A107070010010033

RECTANGULAR TH 1.50 MM, 14" X 48"

KG

1,326.00

256

A047010080050015

O-RING VITON CS DIA 3 MM ID 92 MM

EA

10

1,304.29

257

A114010090010078

FASTNRS M 18 X 50

KG

14

1,261.10

258

A028080020030012

SERRTD METAL RING CIRCLR 360 X 345 X 2MM

EA

1,256.00

259

A028100030010094

SPIRAGATE SS304 ASBT 160 X 138 X 35 MM

EA

1,250.00

260

A028100030010113

SPIRAGATE SS304 ASBT 199 X 173 X 32 MM

EA

1,250.00

261

A115050020010226

PUMP OILMAB-103 WEAR GASKET PN 535743-02

EA

1,250.00

262

A028040020020102

GLAND RING GRAFOIL 80 X 55 X 12 MM

ST

20

1,236.55

263

A114030080040004

FASTNRS M 16

KG

15

1,233.10

264

A031020010010005

DUMMY PLUG 31.5X 27.5X 45 MM L BRASS

EA

1,207.41

265

A072020010090236

BRG MET BALL SRDG 6310 ZC3

EA

1,195.05

129

266

A114010090010014

FASTNRS M 12 X 100

KG

13

1,171.84

267

A114030120010005

FASTNRS M 12

EA

220

1,169.04

268

A115090380050125

PMP WTR WEIR SET PIN M 24X110 LG

EA

1,144.02

269

A028120010030039

GSKT SEAL RING GRAFOIL ANG 505X465X40 MM

EA

1,138.48

270

A028040050010011

GLAND RING GRAFOIL 32 X 20 X 08 MM

EA

1,138.00

271

A028040050010052

GLAND RING GRAFOIL 73 X 47 X 13.5 MM

EA

1,138.00

272

A028040020020057

GLAND RNG GRAFOIL 64X44X10 MM

EA

35

1,123.60

273

A028120010030003

GSKT SEAL RING GRAFOIL ANG 325X290X40 MM

EA

1,110.00

274

A078020200030001

CHEM CLG AGNT DET PWDR SURF 1/2 KG PKT

EA

18

1,101.59

275

A028040020020053

GRAFOIL GLAND RING SIZE 75 X 50 X12.5 MM

EA

20

1,070.10

276

A027130060050002

PTFE SHEET TH 2.0 MM 300 MM X 300 MM

EA

1,060.80

277

A114010090010049

FASTNRS M 16 X 100

KG

13

1,042.20

278

A107070010010124

SHIM RECT TH 0.15 MM, 48 X 14 INCH

KG

1,030.20

279

A114010050010013

FASTNRS M 12 X 50

EA

95

1,020.54

280

A114010090010025

FASTNRS M 12 X 50

KG

12

1,000.14

281

A115050020010236

PMP ALPHALAVAL MAB103 GASKET PN-62812

EA

1,000.00

282

A115050400010025

PMP OIL SHARPLES AS 12 FEED NOZZLE

EA

1,000.00

283

A047010080050037

O-RING VITON CS DIA 3MM ID 66 MM

EA

10

996.78

284

A027130040010006

PTFE BAR ROUND 30 MM

EA

991.44

285

A072020010090048

BRG MET BALL SRDG 6311 C3

EA

972.63

286

A072020010100011

BRG MET BALL THRST 51111

EA

968.64

287

A078010010050013

CHEM ADH COMP SEAL ARALDITE 1.8 KG

EA

968.27

288

A114060100020043

FSTNR HEX SOC CAP SCREW M 20X150

EA

960.00

289

A119020040030018

FLEXIBLE LOVEJOY RUBBER SPIDER L 100

EA

937.18

290

A107070010010006

RECTANGULAR TH 0.07 MM, 14" X 48"

KG

936.36

291

A114030080040002

FASTNRS M 12

KG

11

904.34

292

A003010010550009

AUMA SA12A32 THRUST BRG PN 4403, 4404

ST

897.00

293

A028100030010054

SPIRAGATE SS304 ASBT 100 X 60 X 32 MM

EA

895.00

294

A010010020080001

BELT VBLT TYPB 62 SET OF 2 BELT

EA

889.77

295

A114060100020045

FSTNR HEX SOC CAP SCREW M 24X140

EA

870.00

296

A115050020010031

PMP OIL ALF/LVL CAP NUT, PN: 522997-01

EA

858.92

297

A115050400010039

PMP OIL SHARPLES AS 12 MALE CLUTCH B-512

EA

850.00

298

A115090300110017

PMP WATER SAM HEX SCREW

EA

840.00

299

A036020110040026

LUBRCNT OIL LUB IOC SAE-30

837.90

300

A093560010090046

SHIM S=1 PN 118180200000010

EA

819.75

301

A114010090010021

FASTNRS M 12 X 30

KG

10

794.02

302

A047010080100028

VITON O-RING CS DIA 4 MM ID 228 MM

EA

776.21

130

303

A114190060010008

FASTNRS M 24

KG

11

769.87

304

A028040020020089

GLAND RING GRAFOIL 48 X 30 X 9MM

ST

40

760.96

305

A115090390120002

PMP WATERIAK5089 BEARING FOR PACKING BOX

EA

750.00

306

A098130020010003

HNDTOOL HKSAW BLAD HSS 1/2"X12"X18TPI

EA

19

718.80

307

A114030120010011

FASTNRS M 24

EA

25

711.99

308

A114190060010004

FASTNRS M 16

KG

10

692.75

309

A003010040010006

ACTUAT MOTORD ROTORK CIRCLIP

EA

690.90

310

A001040030060001

ABR EMRY TAPE ROUG 50MMWIDTH50MTRROL

EA

684.18

311

A114030120010013

FASTNRS M 30

EA

12

656.29

312

A028120010030015

GSKT SEAL RING GRAFOIL ANG 120X107X14 MM

EA

652.76

313

A078020160040002

CHEM 5 LTR TIN PACK

EA

650.07

314

A114010090010198

FASTNRS M 6 X 40

KG

649.32

315

A114030120010004

FASTNRS M 10

EA

175

647.24

316

A078010010090001

CHEM ADH COMP AQB AQUASEAL FAST CURE 1KG

EA

605.21

317

A114010090010216

FASTNRS M 8 X 50

KG

604.33

318

A078010010050014

CHEM ADH COMP SEAL ARALDITE 180 GM

EA

600.81

319

A114010050010006

FASTNRS M 10 X 50

EA

75

590.68

320

A001040030040001

ABR EMRY TAPE MED 50MMWIDTH50MTRROL

EA

587.13

321

A111160010010002

CS ELBOW 90 DEG 100 MM NB

EA

573.24

322

A114010090010008

FASTNRS M 10 X 50

KG

569.95

323

A028040050010047

GLAND RING GRAFOIL 68 X 44 X 10 MM

EA

569.00

324

A078020160070002

CHEM 340 GM SPRAY CAN

EA

551.06

325

A115050400010014

PMP OIL SHARPLES AS 12 BOWL BOSS SLEEVE

EA

550.00

326

A111160070010001

CS UNION 1 1/2 IN HEVY DUTY MS SOCKT TYP

EA

542.64

327

A072020010090009

BRG MET BALL SRDG 6310

EA

541.58

328

A119020040030009

COUPL COUPLING NO L 95

EA

530.73

329

A115050400010005

PMP OIL SHARPLES AS 12 BEARING FILLER B-

EA

520.00

330

A133300010010011

M/S CEP EN7J40D EB SPRNG (PT NO-1C)

ST

512.00

331

A078020050060001

CHEM CLN PEN DVP FC CLEANER PC-21B

EA

506.85

332

A078020160040001

CHEM 1 / 2 LTR TIN PACK

EA

502.76

333

A114030120010009

HT 12.9 GR METRIC NUT PLAIN M 20

EA

20

501.47

334

A115050400010026

PMP OIL SHARPLES AS 12 FEMALE CLUTCH

EA

500.00

335

A028120010030010

GSKT SEAL RING GRAFOIL ANG 112 X96X13 MM

EA

494.70

336

A107070010010021

RECTANGULAR TH 0.50 MM, 14" X 48"

KG

489.60

337

A028120010030022

GSKT SEAL RING GRAFOIL ANG 175X151X24 MM

EA

475.74

338

A047010080080009

VITON O-RING CS DIA 3.55 MM ID 53 MM

EA

10

466.58

339

A114010050020014

FASTNRS M 12 X 55

EA

50

437.95

131

340

A114010050020007

FASTNRS M 10 X 80

EA

20

433.92

341

A114190060010001

FASTNRS M 10

KG

428.17

342

A047010080050007

O-RING VITON CS3MM ID 28 MM

EA

13

427.34

343

A114030080040018

FASTNRS M 6

KG

422.24

344

A114190060010020

FASTNRS M 8

KG

419.24

345

A114030080040019

FASTNRS M 8

KG

418.51

346

A028120010030040

GSKT SEAL RING GRAFOIL ANG 64 X44X 10 MM

EA

10

416.15

347

A003010040200003

ROTORK K 150 HAND WHEEL RETAINER

EA

412.00

348

A114010090010068

FASTNRS M 16X 80

KG

405.82

349

A114010090020076

FASTNRS M 16 X 100

KG

402.31

350

A115050400010021

PMP OIL SHARPLES AS 12 DRAG BUSHING-6372

EA

400.00

351

A133300010010008

M/S CEP EB SOCKET EST SCREW P NO12

EA

400.00

352

A028120010030016

GSKT SEAL RING GRAFOIL ANG 125X111X14 MM

EA

395.06

353

A114010090010011

FASTNRS M 10 X 75

KG

391.17

354

A114010090010196

FASTNRS M 6 X 30

KG

376.45

355

A072020010100004

BRG MET BALL THRST 51103

EA

368.00

356

A029080010010001

HARDWR MARK IDENTI BLUE PASTE TUBESIZE

EA

363.17

357

A003010040040078

ACTUAT MOTORD ROTORK TORSION SPRG

EA

363.09

358

A115050020010099

PMPOILALF/LVL ORING RUB3034-73D3X292MM

EA

350.00

359

A072020010090163

BRG MET BALL SRDG 6305 C3

EA

345.01

360

A114060100010020

FASTNRS M 12 X 50

EA

30

320.49

361

A028120010030018

GSKT SEAL RING GRAFOIL ANG 140X126X14 MM

EA

315.58

362

A047010080050032

VITON O-RING CS DIA 3 MM ID 74 MM

EA

313.88

363

A047010080050033

VITON O-RING CS DIA 3 MM ID 80 MM

EA

313.88

364

A107070010010004

RECTANGULAR TH 0.05 MM, 14" X 48"

KG

312.12

365

A114010050010031

FASTNRS M 16 X 60

EA

15

305.42

366

A028040020020100

GLAND RING GRAFOIL 74 X 48 X 13 MM

ST

303.19

367

A072020010100005

BRG MET BALL THRST 51104

EA

302.65

368

A114030120010006

FASTNRS M 14

EA

50

287.93

369

A072020010100001

BRG MET BALL THRST 51100

EA

281.13

370

A115050020010180

PUMP OILMAB-103 GASKET PN 14161

EA

280.00

371

A047010080080008

VITON O-RING CS DIA 3.55 MM ID 42.5 MM

EA

279.95

372

A072020010090160

BRG MET BALL SRDG 6305

EA

276.42

373

A028040020020087

GLAND RING GRAFOIL 38 X 22 X 8MM

ST

23

273.47

374

A114190060010018

FASTNRS M 6

KG

265.32

375

A003010010030010

ACTUATOR AUMA SA6A22 WORM GEAR PN 26

EA

258.00

376

A115090190820006

PMP KBL RKB65-19L4 OIL SEAL 65 X 54 X 12

EA

256.00

132

377

A003010040150010

ROTORK ACT K60 CIRCLIP FOR CENTER COLUMN

EA

250.00

378

A114030120010003

FASTNRS M 8

EA

125

224.51

379

A078010010070004

CHEM ADH COMP GSKT SPEB-7 500ML TIN

EA

211.17

380

A003060010010018

ACT HYD SLZ ASM250-10 O-RNG PN 6080

EA

198.23

381

A078020050060003

CHEM CLN PEN DVP FC PENETRANT PP-15B

EA

192.40

382

A078010010050015

SEALENT ANABOND 666 100 GM PKT

EA

191.72

383

A107070010010003

RECTANGULAR TH 0.04 MM, 14" X 48"

KG

179.52

384

A119020040030010

FLEXIBLE LOVEJOY COUPLING PAD FOR L 95

ST

179.52

385

A078020050060002

CHEM CLN PEN DVP FC DEVELOPER PD-31B

EA

171.10

386

A027130070010001

PTFE TAPE ROLL 12.5 MM W 12 M

EA

10

170.10

387

A098130020010004

HNDTOOL HKSAW BLAD HSS 1/2"X12"X24TPI

EA

166.01

388

A114010090010031

FASTNRS M 12 X 80

KG

156.79

389

A107070010010007

RECTANGULAR TH 0.08 MM, 14" X 48"

KG

156.06

390

A115050400010010

PMP OIL SHARPLES AS 12 BEARING SPACERS A

EA

150.00

391

A072020080010028

BRG MET SLV ADPTSLV H 2308

EA

140.00

392

A114070050010079

FASTNRS M 6 X 12

EA

35

140.00

393

A072020010090086

BRG MET BALL SRDG 6200 2Z

EA

136.99

394

A072020010090087

BRG MET BALL SRDG 6201

EA

135.53

395

A047010080050027

VITON O-RING CS DIA 3 MM ID 25 MM

EA

127.25

396

A115090191430018

PMP KBL BHR28/2STG BRG NUT PN 33501A3

EA

126.00

397

A032010020010007

HOSE RUBBER SSBRD 3/8"X3/8" BSP,L500MM

EA

125.67

398

A072020010090098

BRG MET BALL SRDG 6204 2Z

EA

116.40

399

A072020010090092

BRG MET BALL SRDG 6202 C3

EA

115.19

400

A111160010010005

CS ELBOW 90 DEG 90 DEG 25 MM NB

EA

97.92

401

A114090050010005

FASTNRS M 10 X 25

EA

20

96.06

402

A072020010090001

BRG MET BALL SRDG 6000

EA

92.12

403

A114030080040001

FASTNRS M 10

KG

85.69

404

A072020010090148

BRG MET BALL SRDG 6301

EA

82.59

405

A115030160010022

PMP CHEMICAL METACHEM CIRCLIP FOR CRANK

EA

80.00

406

A114010050010023

FASTNRS M 14 X 50

EA

78.21

407

A072020010090089

BRG MET BALL SRDG 6202

EA

77.81

408

A114190060010002

FASTNRS M 12

KG

70.91

409

A114030120010002

FASTNRS M 6

EA

50

65.59

410

A111030130020006

MS CONECTR 3/8"BSP(M)X3/8"BSP(M)

EA

56.06

411

A114090050010079

FASTNRS M 6 X 10

EA

20

41.26

412

A098130020020001

HNDTOOL HKSAW BLAD ALOY 1/2"X12"X18TPI

EA

40.51

413

A114090050010094

FASTNRS M 8 X 16

EA

20

30.60

133

414

A098130020020002

HNDTOOL HKSAW BLAD ALOY 1/2"X12"X24TPI

EA

22.53

415

A115080050020020

PMP VAC SIEMENS COUPLING PADS

EA

12.00

416

A115090380050117

PUMP SHAFT

EA

1,947,946.65

417

A115090380050086

LABYRINTH BUSH (DE/NDE)

EA

419,069.72

418

A115090380050042

3RD STAGE DIFFUSER

EA

408,895.37

419

A115090380050173

DIFFUSER 1ST STG

EA

408,895.37

420

A115090380050073

IMPELLER 4TH STAGE

EA

371,286.66

421

A115090380050072

IMPELLER 1ST STAGE

EA

332,160.59

422

A115090380050077

IMPELLER 3ED STAGE

EA

327,347.34

423

A115090380050065

GLAND SLEEVE NDE

EA

312,371.49

424

A115090380050076

IMPELLER SECOND STAGE

EA

286,595.90

425

A115090380050075

IMPELLER KICKER STAGE

EA

273,001.61

426

A115090380050168

SET OF FASTERNERS

EA

166,464.00

427

A115090380050172

PMP BFP THRUST PADS (16 NOS.)

EA

160,490.38

428

A115090380050171

BFP PMP CU-MS GSKT 605 X 546 X 4.2

EA

153,902.32

429

A115090380050033

CASING WEAR RING

EA

105,489.04

430

A115090380050006

BALANCE DRUM

EA

99,931.15

431

A115090380050143

THRUST COLLAR

EA

99,115.64

432

A115090380050094

IMPELLER WEAR RING (NECK)

EA

94,913.36

433

A115090380050153

DISC SPRING

EA

92,562.30

434

A115090380050078

IMPELLER WEAR RING (EYE)

EA

85,100.24

435

A115090380050064

GLAND SLEEVE DE

EA

66,203.56

436

A115090380050044

DIFFUSER WEAR RING

EA

63,109.64

437

A115090380050157

SET OF OIL GUARDS

EA

56,637.53

438

A115090380050009

BALANCE DRUM RESTRICTION BUSH

EA

53,983.18

439

A115090380050156

INTERSTAGE TAP OFF BUSH

EA

44,368.69

440

A115090380050085

JOURNAL BEARING DE

EA

36,088.70

441

A115090380050160

JOURNAL BEARING NDE

EA

34,118.56

442

A115090380050088

METAFLEX GSKT

EA

30,581.82

443

A115090380050034

CASING WEAR RING KICKER STAGE

EA

24,735.95

444

A115090380050176

SET OF KEYS

SET

22,054.20

445

A115090380050133

SHAFT NUT THROWER M 115 X 2 LH (NDE)

EA

18,707.32

446

A115090380050175

ROTOR LOCKING CHANNEL ASSLY

SET

15,542.96

447

A115090380050002

SET OF O RINGS & BACK UP RINGS

EA

15,001.06

448

A115090380050134

SHAFT NUT THROWER M 140 X 2 RH (DE)

EA

14,833.04

449

A115090380050114

PLUG FOR OUTLET GUIDE

EA

14,772.11

450

A115090380050119

RESTRICTION BUSH (DE/NDE)

EA

10,713.14

134

451

A115090380050145

THRUST COLLAR NUT M 80 X 2 LH

EA

8,212.13

452

A115090380050110

PACKING RING FOLLOWER

EA

6,826.30

453

A115090380050008

BALANCE DRUM LOCK WASHER

EA

5,368.29

454

A115090380050067

SET OF LOCKING SCREWS

EA

2,415.46

455

A115090380050109

PACKING RING

EA

1,575.30

456

A115090380050144

THRUST COLLAR LOCK WASHER

EA

1,542.13

457

A115090380050007

BALANCE DRUM NUT

EA

0.01

TEMPORARY IMPREST

48,109.00

TOTAL COST

28,430,313.37

UNIT-5 COH COSTING WORKS :


Sr.

Details of Work

No.
1

Work of the surface painting of Turbine Auxiliaries in


Unit-5, 6 & 7.

PO No.

Amount spent in
Unit-5 COH

4500045011

104,110.00

4500046230

11,129.00

4500057747

78,652.00

4500050968

10,496.00

Provision of work assistance for CEP strainer / filter


2

cleaning and turbine side routine miscellaneous


works in Unit-5, 6 & 7.
Work of cleaning coolers of various auxiliaries of

Unit-5, 6 & 7 during Unit Overhauling, outages or as


& when required.

Work of Condenser Hot well Inspection, Condenser


Tube Leakage Attending & CEP Suction Strainer
Cleaning as & when required or during outages of

135

Unit-5, 6 & 7.
Work of HP Welding of Valves & Pipelines during
5

routine maintenance, short shutdown & overhaul of

4500050531

4,400.00

4500056607

12,023.00

4500060249

4500057930

4500059534

157,940.00

4500062431

217,550.00

4500061735

672,198.00

4500062874

350,719.00

4500065165

170,107.00

4500050958

197,636.00

4500062260

1,923,124.00

4500062823

1,250,366.00

Unit-5, 6 & 7.
Work of Replacement of Fullers Earth, Bucket
6

Strainer Cleaning & Superfine Filter


Cleaning/Replacement in FRF system as & when
required or during outages of Unit-5, 6 &7.

7
8
9
10

Work of Servicing/Overhauling of Various Pumps


Unit-5, 6 & 7 on as & when required basis.
Work of replacement of High Pressure Valves in U5, 6 & 7.
Work of repairing of BFP, CEP & FRF strainers at
Unit-5, 6 & 7.
Work of fitting cathodic elements in condenser
during AOH/COH Overhaul Unit-6.
Work of Machining of Turbine Fitted Keys, HPBP

11

valve Stem , hydrogen Seal Brg & Reconditioning of


Recirculation valve of BFP of U # 5, 6 & 7 on as &
when required basis.

12

Work of inspection and servicing of ACW valves


during Capital Overhauling of Unit-5.
Work of internal inspection & repairs of Deaerator,

13 FST and HP/LP heater & Oil Tank Cleaning during


COH Unit-5.
Work of Machining of TG Set Bearing Oil Catchers
14

& Machining & matching of stellited bush of Control


Valves as per dimensions during overhauls of U-5, 6
& 7.

15

Work of cleaning / revisioning of MS / HRH strainers


during Capital overhaul of Unit-5.

16 Work of spray insulation of HP / IP turbine module,


connected piping, HP / IP / LPBP stop and control

136

valves during Capital Overhaul of U-5


Work of cleaning of GTR coolers with De-scaling
17 agent Silico-6 during respective overhaul of Unit-5,

4500063667

616,815.00

4500062595

27,474,447.00

4500062886

1,941,399.00

4500063652

576,910.00

4500062876

183,171.00

4500064237

977,012.00

4500061659

65,664.00

4500066156

1,011,608.00

4500056401

332,050.00

4500041950

4500066293

500,000.00

6&7
Work of Overhauling of HP/IP/LP Turbine,
18 Generator, Exciter& Associated Works during
Capital Overhaul of Unit-5.
Work of inspection and servicing of Steam & Feed
19

line valves during Capital Overhauling of Unit-5 and


as & when required during shut down of Unit-5, 6 &
7.
Work of Cleaning of Condenser Tubes by High

20 pressure water jetting followed by bullet shot


cleaning of Main Condenser Unit-5 during Overhaul.
21
22
23
24

Work of Machining of TG Set Bearing Oil Catchers


& as per dimensions during Overhauls of U-5, 6 & 7.
Work of complete overhauling of TDBFP turbines
Unit-5, 6 & 7
Work of Cleaning of Condenser tubes by high
pressure Hydro-jetting at Unit-6 during COH
Work of in-situ machining repair & reconditioning of
HP Control Valves of Unit-5.
Work of carrying out Overhauling & various

25

miscellaneous inspections & replacements in


Condensate Extraction Pump in Unit-5, 6 & 7 on as
& when required basis.
Work of cleaning of Control Fluid Tank &

26 Overhauling, Preventive Maintainance of Control


Fluid Pumps in Unit-5, 6 & 7.
Work of thermal insulation of heat exchangers,
27 turbine pipings, valves etc. of turbine house U-5, 6
& 7.

38,839,526.00

137

ODP-II (AHP) :
S
N

AUXILLARY

1 Raw water tank cleaning


2 5 A,B,C sump

Raw water Line A & B

WORK
NATURE OF
AGENCY/ Uni
WORK
GROUP
t
Tank cleaning work
Sump cleaning
work

M/S Babu
Enterprises
M/S Babu
Enterprises

QTY

RATE

Amoun
t

EA

2704.19

2704.19

EA

4924.98 14774.94

Servicing

M/s Aarti

EA

10171.4

20342.7

4 Tank inlet- 350NB B/F

Servicing

M/s Aarti

EA

9595.95

9595.95

5 Tank inlet- 500NB B/F

Servicing

M/s Aarti

EA

10171.4

20342.7

6 HP R-C VALVE Plug valve

Servicing

M/s Aarti

EA

4970.7

9941.4

500NB B/F

138

250NB
Fly ash sump
selection v/v
7 Sump selection valve

servicing
Bottom ash sump

200153.3

EA

66717.8

EA

11424.8 34274.31

EA

9595.95

19191.9

EA

9595.95

9595.95

EA

9596.95

9596.95

EA

9597.95

9597.95

EA

9595.95

9595.95

EA

9596.95

9596.95

EA

9597.95

9597.95

EA

EA

9595.95

9595.95

EA

9596.95

9596.95

EA

9597.95

9597.95

EA

EA

4970.7

4970.7

M/s Dwiwedi

selection v/v
servicing
8

Sump Make up main

Servicing/

isolation Valve

Replacement

M/s Aarti

Suction valve
servicing
Discharge valve
9 HPAWP-1

servicing

M/s Aarti

NRV servicing

Suction valve
servicing
1
0

Discharge valve
HPAWP-2

M/s Aarti

servicing
NRV servicing
Strainer cleaning

deparmental
work

Suction valve
servicing
Discharge valve
11 HPAWP-3

servicing

M/s Aarti

NRV servicing

Strainer cleaning
1 LPAWP-1

139

Suction valve

deparmental
work
M/s Aarti

servicing
Discharge valve
2

Suction valve
servicing

Discharge valve
LPAWP-2

servicing
NRV servicing
Strainer cleaning
Suction valve
servicing

1
4

HPSWP-1

Discharge valve
servicing
NRV servicing
Suction valve
servicing

1
5

HPSWP-2

Discharge valve
servicing
NRV servicing
Suction valve
servicing

1
6

4971.7

4971.7

EA

4972.7

4972.7

EA

M/s Aarti

EA

4970.7

4970.7

M/s Aarti

EA

4971.7

4971.7

M/s Aarti

EA

4972.7

4972.7

EA

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

EA

------

------

NRV servicing
Strainer cleaning

EA

servicing

LPSWP-1

Discharge valve
servicing
NRV servicing

1 LPSWP-2

Suction valve

servicing
Discharge valve
servicing

140

deparmental
work

deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work
deparmental
work

deparmental

NRV servicing
1
8

Bottom ash & fly ash sump


strengthning work &Grating
replacement work

EA

------

------

11195.1

33585.3

20

587.33

11746.6

80

473.57

37885.6

30

473.57

14207.1

4.5

11195.1 50377.95

Sq.

463.9

mtr

M/s Adore

60

587.33

35239.8

M/s Adore

46

587.33

27017.18

work

Bottom ash & fly


ash sump

M/s Dwiwedi

Flushing line header ,


1 flushing line, Seal water

Flushing line heade

9 header, seal water line

& Nozzle replaced

M/s Adore

replacement.

2 Fly ash strench strainer &


0 support fabrication work
2
1

Sump grill &


support

M/s Dwiwedi

replacement
various paining

Painting Work

work

2 LPAWP Header line

LPAWP Header line

2 modification

modification

2 HPAWP Header line

HPAWP Header line

3 replacement work

replacement work

M/s Dwiwedi

231

107173.8
4

SUPPLY
E CODE

SPARE

Unit

QTY.

A028140010010021

NON METALLIC ROUND- ID 400 OD


600 THK 5M

EA

A028140010010006

NON METALLIC ROUND- ID 400 OD


600 THK 3M

EA

A028140010010001

NON METALLIC ROUND- ID 350 OD


530 THK 1M

EA

10

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A027100010080001 GSKTMTRL 1000 MM X 2000 MM

KG

141

RATE AMOUNT
436.52

3492.13

336.60

1683.00

71.40

714.00

187.68

375.36

218.73

1093.64

A028140010010031

NON METALLIC ROUND- ID 300 OD


600 THK 1M

A036010010050001

109.09

1090.94

187.68

938.40

412.70

2063.52

450.21

5852.79

214.58

858.31

EA

298390.78

895172.34

187.68

938.40

450.21

5402.57

355.00

2130.00

183.76

3675.23

207.20

2279.17

214.58

429.15

374.63

1123.90

355.00

2130.00

214.58

429.15

183.76

3675.23

207.20

2279.17

187.68

375.36

218.73

656.18

EA

10

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A028140010010027

NON METALLIC ROUND- ID 300 OD


595 THK 5M

EA

A028140010010022

STYLE -20N/M ROUND-ID 300 OD600


TH5MM

EA

13

KG

A027100010070001 GSKTMTRL 1000 MM X 2000 MM


A075270150010001

VLV PLUG 150CI FG200 600NB COMP


ISOLATION VALVE

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A028140010010022

STYLE -20N/M ROUND-ID 300 OD600


TH5MM

EA

A028140010010051

METALLIC ROUND-ID300 OD 530THK


5.0 MM

EA

A028140010010036

NON METALLIC ROUND- ID 350 OD


530 THK 3.

EA

20

A028140010010033

NON METALLIC ROUND- ID 300 OD


530 THK 3.

EA

11

KG

A027100010070001 GSKTMTRL 1000 MM X 2000 MM

12

A027050010050005

GSKTMTRL 16 MM SQ IN PACK OF 5
KG

KG

A028140010010051

METALLIC ROUND-ID300 OD 530THK


5.0 MM

EA

KG

A027100010070001 GSKTMTRL 1000 MM X 2000 MM


A028140010010036

NON METALLIC ROUND- ID 350 OD


530 THK 3.

EA

20

A028140010010033

NON METALLIC ROUND- ID 300 OD


530 THK 3.

EA

11

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A027100010080001 GSKTMTRL 1000 MM X 2000 MM

KG

142

A028140010010051

METALLIC ROUND-ID300 OD 530THK


5.0 MM

EA

A027050010050005

GSKTMTRL 16 MM SQ IN PACK OF 5
KG

KG

A028140010010036

NON METALLIC ROUND- ID 350 OD


530 THK 3.

EA

20

A028140010010033

NON METALLIC ROUND- ID 300 OD


530 THK 3.

EA

11

A027100010080001 GSKTMTRL 1000 MM X 2000 MM

KG

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A036010010050001

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A027100010080001 GSKTMTRL 1000 MM X 2000 MM

KG

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

A027100010080001 GSKTMTRL 1000 MM X 2000 MM

KG

A027100010070001 GSKTMTRL 1000 MM X 2000 MM

355.00

2130.00

374.63

749.26

183.76

3675.23

207.20

2279.17

218.73

656.18

187.68

187.68

187.68

187.68

218.73

437.45

187.68

187.68

218.73

437.45

KG

214.58

214.58

A027100010070001 GSKTMTRL 1000 MM X 2000 MM

KG

214.58

214.58

A027100010070001 GSKTMTRL 1000 MM X 2000 MM

KG

214.58

214.58

A027100010070001 GSKTMTRL 1000 MM X 2000 MM

KG

214.58

214.58

LUBRCNT GRS EQ&MC/NRY IOC


SERVO GEM 03

KG

187.68

187.68

A036010010050001

A036010010050001

MS ISMC CHANNEL SIZE 150 X 75


A107040010030014 MM

TO

0.600 39204.03023

A107030010040005 BEAM MS ISMB 200 X100 MM

TO

1.000

39793

39793.00

20

1857.02

37140.42

455.6625

36453.00

MSERW/PIPE/IS-3589/SIZE200X219.1X7.9 MM

MSERW/PIPE/IS-1239/SIZEA111010020030011 80X89.5X4.85 MM

80

MSERW/PIPE/IS-1239/SIZEA111010020030001 100X115X5.4 MM

30

A111010020040003

143

670.50

23522.42

20115.00

A027010010240007

GSKT&PCK JNT SHT1525 X 1650 MM


TH 3.0 MM

EA

A027010010220007

JOINTINGSHET OIL
NONMET1525X1650MMTH3MM

KG

10

A107030010040005 BEAM MS ISMB 200 X100 MM

TO

1.540

MS ISMC CHANNEL SIZE 150 X 75


A107040010030014 MM

TO

1.000 39204.03023

MSERW/PIPE/IS-3589/SIZEA111010020040003 200X219.1X7.9 MM

60

KG

46

KG

A027010010220007

JOINTINGSHET OIL
NONMET1525X1650MMTH3MM

MSERW/PIPE/IS-3589/SIZEA111010020040011 400X406.4X9.5 MM
A027010010220007

JOINTINGSHET OIL
NONMET1525X1650MMTH3MM

253.60

1775.19

265.94

2659.42

39793

61281.22
39204.03

1857.02

111421.26

265.94

1329.71
220800.00

4800.00
265.94

1329.71

Total

1547656.10

ODP-II WHP:
SUPPLY

MATERIAL

SAP CODE

QTY.

RATE

AMOUNT

A027010010240008 115

212.82

24474.30

A114010090020124 100

88.38

8838.00

A027070010070001 105

89.44

9391.20

A027010010190005

34

110.41

3753.94

A075030020110001

10

125657.6

1256576.00

EXPENDITURES
1

STYEL 54 SUPER
NON METAL
FASTNER M 20 X
U#5 CT 5A/5B RISER

120

VALVE REPLACEMENT

GASKET 1000MM X

WORK (600NB

2000MM

BUTTERFLY)

JOINT SHEET NON


METAL
BUTTERFLY VALVE
600NB

2 CT 5A/5B HOT WATER


PIPE REPLACEMENT

ASBESTOS
CEMENT PIPE

WORK 150 NB & 200 NB 150NB

144

0
A083050010010003 109

3241.75

353350.75

ASBESTOS

A083050010010004

31

4095.63

126964.53

CEMENT PIPE
200NB
3

U# 5 CT 5A/5B NOZZLE
CLEANING & REPL
WORK

COOLTWR NOZZLE

A083050050010002 8000

16.32

130560.00

COOLTWR

A083050050010001 5000

114.01

570050.00

659886.5

1319773.18

MODIFIED NOZZLE
GB GRV VH

A097080090010002

M1700R15-1 I/P

BEVEL & PINION


CT FAN 5B/6 & 5B/8

GB GRV VH

COMPLETE GEAR BOX

M1700R15-1 CSNG

REPLACE WORK

UPR & LWR SET


GB GRV VH

A097080090010003

268482.7

536965.40

0
A097080090010004

711181.20 1422362.40

A072020060010104

17263.50

34527.00

A072020020050054

8524.00

8524.00

A072020060010110

26637.30

53274.60

A072020060010207

23116.87

46233.74

CT FAN 5B/1 GEAR BOX BRG MET TAPROL


OVERHAUL WORK SR 32319 J2

A072020060010060

16022.00

32044.00

PREMIUM ( BRG REPL ) GEAR BOX OIL SP-

A036020100010013 560

167.52

93811.20

COUPLING BUSH

A119010010010122

59

524.89

30968.51

BAR MS ROUND 10

A107020070010003

0.3

36954.27

11086.28

M1700R15-1
OUTPUT WHEEL
5

I/P FRONT( WORM


SHAFT)
CT FAN 5A/5 GEAR BOX I/P BACK (WORM
OVERHAUL WORK -

SHAF)

RADICON ( BRG REPL ) O/P shaft Top &


BOTTOM
(WORM WHEEL)
6

TAPER ROLLER
SINGLE ROW BRG
32321 J2

320

7 U#5 ACW/CCW SUMP


SUCTION STRAINER
REPAIRING WORK

145

MM

8 CT FAN 5A/1 & 5B/1


MOTOR FOUNDATION

CHANNEL MS ISMC

A107040010030002

42464.58

42464.58

GATE VALVE 150NB A075170080070001

30

16445.00

493350.00

MSERW PIPE

90

12263.00

1103670.00

60

4800.51

288030.60

MSERW PIPE 350NB A111010020040009 280

4177.02

1169565.60

MSERW PIPE

A111010020040007 100

3525.93

352593.00

MSERW PIPE 300NB A111010020040006 100

3094.77

309477.00

MSERW PIPE 150NB A111010020040001 210

1813.88

380914.80

CHANNEL MS ISMC

100X50

FRAME REPLACEMENT
9

600NBX2000MM

AC04309001004001
0

MSERW PIPE 400NB A111010020040011

U#5 ACW RETURN LINE 300NBX323.9X9.5M


SEPARATION WORK AT M
5A & 5B TOWER

A107040010030014

39205.94

39205.94

A107060010020012

0.2

40000.00

8000.00

150 X 75
MS PLATE 25MM
Paint

150000.00
TOTAL SUPPLY

10410800.5
5

WORK ITEM

TOTAL

U#5 CT 5A/5B RISER VALVE REPLACEMENT WORK (600NB


BUTTERFLY)

37020

146

U# 5 CT POND CLEANING WORK & U#5 ACW/CCW SUMP CLEANING


WORK & U#5 ACW/CCW SUMP SUCTION STRAINER REPAIRING WORK

592204

U# 5 CT 5A/5B HOT WATER BASIN CLEANING WORK

242000

CT 5A/5B SPLASH BAR CLEANING & REMOVAL BY SCRAPPING

405,466

U#5 CCW/ACW PUMP HOUSE VARIOUS VALVE SERVICING WORK

200000

U#5 ACW RETURN LINE SEPARATION WORK & anchoring of pipes

1600000

CCW BFV servicing by VAG

810000

TOTAL WORKS

3886690

INSTRUMENTATION & CONTROL - II :


WORKS

147

S
N
1

RP
No.

P.O.No.

450005927
T-766
5

450006362
1

Vendor Name

Description

Amount

B. Code

Shubham
Enterprises,
Chandrapur

Servicing of Power
cylinder in bottom ash
system, burner tilt, PA
general gate

Rs.
525,271

CHN/WP/OH/E0
7

Dharma B.
Chanekar,
Chandrapur

Work contract for cleaning


and painting of JB, TRB/
TRT Panel,
Instrument racks &
impulse Line flushing
during AOH/ COH of unit5.

Rs.
569,759

CHN/WP/OH/E0
7

T-1954

450006375
T-1956
2

Panchajanya
Services,
Kolkata

Work contract for


modification in coal mill
DP measurement system
of unit-5

Rs.
433,200

CHN/WP/OH/E0
7

450006378
T-2092
1

Panchajanya
Services,
Kolkata

Work of servicing and


modification of complete
Gland Drain Tank level
control system of Unit 5

Rs.
68,700

CHN/WP/OH/E0
7

Panchajanya
Services,
Kolkata

Work of servicing and


calibration of pneumatic
control valves, dampers
and various transmitters
during AOH/COH of Unit5.

Rs.
720,339

CHN/WP/OH/E0
7

J. P. Nagdeve

Work contract for servicing


of Igniter, Flame Scanners
and SADC during AOH,
COH of unit-5.

Rs.
128,741

CHN/WP/OH/E0
7

Work contract for servicing


of HP Bypass system
instruments with FOD
during 500MW U-5, AOH /
COH.

Rs.
247,303

CHN/WP/OH/E0
7

450006533
T-1938
9

450006528
T-1955
1

T-1957

450006554
6

PRIYA
ENGINEERING
WORKS

T-331

450004430
0

PRIYA
ENGINEERING
WORKS

Work contract for servicing


of solenoid valves

Rs.
67,415

CHN/WP/OH/E0
7

T-741

450004861
3

PRIYA
ENGINEERING
WORKS

Work contract for servicing


of solenoid valves

Rs.
74,050

CHN/WP/OH/E0
7

Total

SUPPLY :

148

Rs.
2,834,778

S/
N Material
A11419006001
1 0004
A11403008004
2 0017
A11403008004
3 0004
A11401009001
4 0196
A11401009001
5 0181
A11401009001
6 0043
A11401005001
7 0015
A11401005001
8 0006
A11112027001
9 0009
A11112026001
10 0007
A11112020002
11 0027
A11112020001
12 0008
A11112020001
13 0006
A11112020001
14 0006
A11112020001
15 0006
A11112020001
16 0006
A11112020001
17 0005
A11112015002
18 0014
A11103013002
19 0035
A11103013002
20 0033
A11103013002
21 0033
A11103013002
22 0033
A11103013002
23 0033
A11103013002
24 0033
25 A11103013002

149

Material Description

Quant Amount
ity
in LC

Text

FASTNRS M 16

-3

-207.82

UNIT # 5

FASTNRS M 5

-2

-183.01

UNIT # 5

FASTNRS M 16

-4

-328.83

UNIT # 5

FASTNRS M 6 X 30

-1

-94.11

UNIT # 5

FASTNRS M 5 X 30

-1

-47.00

UNIT # 5

FASTNRS M 14 X 65

-2

-167.20

UNIT # 5

FASTNRS M 12 X 65

-1

-8.57

UNIT # 5

FASTNRS M 10 X 50

-1

-7.88

UNIT # 5

REDUCER MALE 1 / 4 TUBE X 3 / 8

-7

-1176.23

UNIT # 5

MALE X MALE 1 / 4 TUBE X 3 / 16 TUBE

-4

-320.00

UNIT # 5

CONECTR FEMALE 1 / 4" X 3 / 8" BSP


CONNECTOR MALE 1 / 4 TUBE X 3 / 8
NPT
CONNECTOR MALE 1 / 4 TUBE X 1 / 4
NPT
CONNECTOR MALE 1 / 4 TUBE X 1 / 4
NPT
CONNECTOR MALE 1 / 4 TUBE X 1 / 4
NPT
CONNECTOR MALE 1 / 4 TUBE X 1 / 4
NPT
CONNECTOR MALE 1 / 4 TUBE X 1 / 2
NPT
TEE BRANCH MALE 1 / 4 TUBE X 1 / 4
BSP
MS CONNECTOR 1/2" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"
NPT (M)
MS CONNECTOR 1/4" BSP (M) X 1/2"

-1

-241.77

UNIT # 5

-3

-504.10

UNIT # 5

-2

-411.78

UNIT # 5

-2

-411.78

UNIT # 5

-1

-205.89

UNIT # 5

-4

-823.57

UNIT # 5

-5

-1102.71

UNIT # 5

-2

-551.41

UNIT # 5

-1

-24.48

UNIT # 5

-3

-73.44

UNIT # 5

-1

-24.48

UNIT # 5

-2

-48.96

UNIT # 5

-3

-73.44

UNIT # 5

-5
-1

-122.40
-24.48

UNIT # 5
UNIT # 5

26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50

0033
A11103013002
0032
A11103013002
0031
A11103013002
0018
A11103013002
0007
A11103003003
0002
A11102001001
0006
A11006013003
0004
A11006013003
0004
A10403040001
0002
A10403040001
0002
A10403040001
0001
A10403039001
0002
A10403039001
0001
A10403038001
0002
A10403038001
0002
A10403038001
0001
A10403038001
0001
A10403038001
0001
A10403037002
0002
A10403006003
0001
A10403006003
0001
A10403006003
0001
A10403006003
0001
A10403006003
0001
A10403006003
0001

150

NPT (M)
MS CONNECTOR 1/2" BSP (M) X 3/8"
NPT (M)
MS CONNECTOR 1/2" BSP (M) X 1/4"
NPT (M)

-1

-24.48

UNIT # 5

-2

-48.96

UNIT # 5

PIP FT FE CNCTR 4 / 8" X 1 / 4"

-3

-68.18

UNIT # 5

MS CONECTR TUBEOD1/4"X1/4"NPT(M)
MS REDUCER 1 / 4" BSP (M) X 3 / 8"
BSP (
PIPE SCH 10 FLEXIBLE OD 8 MM X ID 6
MM

-1

-13.26

UNIT # 5

-54

-1350.00

UNIT # 5

-1.500

-134.14

UNIT # 5

MS 80 NB FLANGE DUMMY

-2

-507.96

UNIT # 5

MS 80 NB FLANGE DUMMY

-2

-507.96

UNIT # 5

LUG CU I/L CNCTR WITH SLV 2.5SQMM

-10

-30.62

UNIT # 5

LUG CU I/L CNCTR WITH SLV 2.5SQMM

-25

-76.55

UNIT # 5

LUG CU I/L CNCTR WITH SLV 1.5SQMM

-10

-30.60

UNIT # 5

LUGS CU FL WITH SLV 2.5SQMM

-50

-156.16

UNIT # 5

LUGS CU FL WITH SLV 1.5SQMM

-10

-30.09

UNIT # 5

LUG CU PIN TYPE WITH SLV 2.5MM2

-25

-36.33

W T PLANT

LUG CU PIN TYPE WITH SLV 2.5MM2

-60

-87.20

UNIT # 5

LUG CU PIN TYPE WITH SLV 1.5MM2

-10

-26.07

UNIT # 5

LUG CU PIN TYPE WITH SLV 1.5MM2

-25

-65.18

W T PLANT

LUG CU PIN TYPE WITH SLV 1.5MM2

-10

-26.07

UNIT # 5

LUGS CU U-TYPE WITH SLV 1.5SQMM


CU RECT FRK SLDRLES 2.5MMSQ LUG7928
CU RECT FRK SLDRLES 2.5MMSQ LUG7928
CU RECT FRK SLDRLES 2.5MMSQ LUG7928
CU RECT FRK SLDRLES 2.5MMSQ LUG7928
CU RECT FRK SLDRLES 2.5MMSQ LUG7928
CU RECT FRK SLDRLES 2.5MMSQ LUG7928

-50

-68.70

UNIT # 5

-10

-18.15

UNIT # 5

-25

-45.37

UNIT # 5

-10

-18.15

UNIT # 5

-10

-18.15

UNIT # 5

-10

-18.15

UNIT # 5

-25

-45.37

W T PLANT

A10403006003
51 0001
A10403006003
52 0001
A10403006003
53 0001
A10403006003
54 0001
A10403006003
55 0001
A10313004001
56 0002
A10307014001
57 0009
A10307014001
58 0006
A10224001001
59 0006
A10223002002
60 0017
A10223002001
61 0001
A10223001002
62 0001
A10218003002
63 0003
A10218003001
64 0031
65
66
67
68
69
70
71
72
73
74
75

A10218001002
0006
A10216012001
0016
A10216009001
0012
A10216008001
0020
A10216007002
0002
A10216006002
0221
A10216006002
0180
A10216006002
0105
A10216006002
0051
A10216006002
0025
A10216001001
0351

151

CU RECT
7928
CU RECT
7928
CU RECT
7928
CU RECT
7928
CU RECT
7928

FRK SLDRLES 2.5MMSQ LUG-10

-18.15

UNIT # 5

-10

-18.15

UNIT # 5

-50

-90.74

UNIT # 5

-79

-143.38

UNIT # 5

-10

-18.15

UNIT # 5

-4

-101.87

UNIT # 5

-31

-62.00

UNIT # 5

LMP FT LAMP IND TYPE V 30, A


300 (L) X 315 (B) X 170 (H) MM WITH
HING
LLGS,CEE EM45 SERIES WITH NORMAL
ROLLER
JAI BALAJI 2 NO + 2 NC TYPEJB2700DPDT
INSTRFLD LMTSWT BCH 1NO+1NC
TYPE: LTPR

-5

-50.00

UNIT # 5

-1

-3473.08

UNIT # 5

-1

-265.00

UNIT # 5

-1

-3120.00

UNIT # 5

-1

-771.43

UNIT # 5

PR SWITCH-DIFF SWITZER 0.2TO 4 BAR

-1

-8200.00

UNIT # 5

INST FLD PR SW DIF 5-60 PSI MP55

-3

UNIT # 5

-1

-8070.00
111384.4
2

-1

-0.01

UNIT # 5

-4

-29281.20

UNIT # 5

K-TYPE NIPPLE FOR IP TURBINE T / C

-4

-2066.67

UNIT # 5

TC-MI WELDING PAD OD 6 MM T / C


TC-DUPLEX, K-TYPE, IL 300 MM, EL 100
MM

-1

-272.34

UNIT # 5

-1

-15403.86

UNIT # 5

INST FLD TMP SNSR HP OUTER CASING

-5

-30550.00

UNIT # 5

K-TYPE L 840 MM, OD 8 MM ELEMENT

-1

-0.01

UNIT # 5

K-TYPE IL 700 MM, EL 140 MM ASSY

-1

-5507.44

UNIT # 5

K-TYPE IL 150 MM, EL 90 MM ASSY


RTD-DUP, PT-100, L13 MM, OD3MM,
2WIRE

-1

-0.01

UNIT # 5

-4

-3366.00

UNIT # 5

FRK SLDRLES 2.5MMSQ LUGFRK SLDRLES 2.5MMSQ LUGFRK SLDRLES 2.5MMSQ LUGFRK SLDRLES 2.5MMSQ LUG-

TOP PIN PVC PLUG TOP V240 5 AMP


LMP FT LAMP IND V 30 A 50 MA

SWITCH GEORGIN RANGE - 0 TO 5000


PA
INSTRFLD TEMP THERMOWEL HP IL:
250 MM
TC-MI SIMPLEX K-TYPE L 4 METER OD 3
MM

UNIT # 5

A10216001001
76 0350
A10216001001
77 0299
A10216001001
78 0299
A10216001001
79 0299
A10216001001
80 0299
A10216001001
81 0299
A10216001001
82 0299
A10216001001
83 0267
A10216001001
84 0226
A10216001001
85 0226
A10216001001
86 0109
A10216001001
87 0109
A10215006002
88 0029
A10215002002
89 0204
A10215002002
90 0081
A10215002002
91 0081
A10214049001
92
0002
A10214049001
93
0001
A10214047001
94
0002
A10214043001
95
0002
A10214043001
96
0002
A10214043001
97
0002
A10214043001
98
0002
A10213005006
99 0078
10 A10213005006
0 0078
10 A10213005006

152

RTD L 70 MM, OD 6.5 MM, 3 WIRE


ELEMENT
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
INST FLD TMP SNSR
OD8MM,L400MM,3WIRE
PT100 L 100 MM, OD 8 MM, 3 WIRE
ELEMENT
PT100 L 306 MM, OD 6 MM, 3 WIRE
ELEMENT
PT100 L 306 MM, OD 6 MM, 3 WIRE
ELEMENT
PT100 L 220 MM, OD 8 MM, 3 WIRE
ELEMENT
PT100 L 220 MM, OD 8 MM, 3 WIRE
ELEMENT
0 TO 120 DEG C, DIA-6 MM, STEM L
300 MM
0 TO 250 DEG C, BULB DIA-8 MM, CAP
L 5.0
0 TO 120 DEG C, BULB DIA-8 MM, CAP
L 5.0
0 TO 120 DEG C, BULB DIA-8 MM, CAP
L 5.0

-1

-1535.54

UNIT # 5

-1

-1312.74

UNIT # 5

-2

-2625.48

UNIT # 5

-1

-1312.74

UNIT # 5

-1

-1312.74

UNIT # 5

-1

-1312.74

UNIT # 5

-1

-1312.74

UNIT # 5

-1

-982.26

UNIT # 5

-1

-954.72

UNIT # 5

-1

-954.72

UNIT # 5

-1

-783.96

UNIT # 5

-1

-783.96

UNIT # 5

-1

-2236.86

UNIT # 5

-1

-2236.86

UNIT # 5

-1

-2236.86

UNIT # 5

-1

-2236.86

UNIT # 5

REPAIR KIT ASCO P / N A302 322


COMPLETE SOLENOID VALVE ASSY
ASCO P / N

-1

-3540

UNIT # 5

-1

-4446.36

UNIT # 5

REPAIR KIT ASCO P / N A316 753V

-1

-6239.64

UNIT # 5

REPAIR KIT ASCO P / N A302 725 MO

-1

-816

UNIT # 5

REPAIR KIT ASCO P / N A302 725 MO

-1

-816

UNIT # 5

REPAIR KIT ASCO P / N A302 725 MO

-1

-816

UNIT # 5

REPAIR KIT ASCO P / N A302 725 MO


INST FLD PR GAUG 02.5KG/CM2,CON1/2"BSP
INST FLD PR GAUG 02.5KG/CM2,CON1/2"BSP
0-25 KG/CM2, CON 1 / 2" BSP

-1

-816

UNIT # 5

-1

-845.42

UNIT # 5

-1
-3

-845.42
-2274.01

UNIT # 5
UNIT # 5

1
10
2
10
3
10
4
10
5
10
6
10
7
10
8
10
9
11
0
11
1
11
2
11
3
11
4
11
5
11
6
11
7
11
8
11
9
12
0
12
1
12
2
12
3
12
4
12
5
12
6

0016
A10213005003
0098
A10213005002
0060
A10213005002
0059
A10213005002
0059
A10213005001
0017
A10213005001
0017
A10213005001
0001
A10213005001
0001
A10213004004
0001
A10213004004
0001
A10213004001
0025
A10213004001
0001
A10213004001
0001
A10212002005
0002
A10208007003
0003
A10208007003
0003
A10207001002
0002
A10207001002
0002
A10206001001
0001
A10206001001
0001
A10206001001
0001
A10206001001
0001
A10205001006
0017
A10202004005
0001
A10012001001
0019

153

PR GAUGE DIAL 100 MM 0-2.5 KG / CM2

-2

-1397.46

UNIT # 5

0 TO 6 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0 TO 40 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0 TO 40 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0-16 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0-16 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-1

-698.73

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-4

-2794.92

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-1

-789.17

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-1

-789.17

UNIT # 5

0-250 KG/CM2, CON 1 / 2" BSP

-3

-2034.67

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-1

-763.00

UNIT # 5

0-10 KG/CM2, CON 1 / 2" BSP

-1

-763.00

UNIT # 5

ILK MODEL HTPWO / BP

-1

-0.01

UNIT # 5

ROTAMETER 0 TO 45 LPH FOR SWAS

-2

-6485.16

UNIT # 5

ROTAMETER 0 TO 45 LPH FOR SWAS


ELECTRONIC PFTRANSM. MODEL
EPT002, I / P
ELECTRONIC PFTRANSM. MODEL
EPT002, I / P
I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG /
SQ.C
I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG /
SQ.C
I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG /
SQ.C
I/P 4 TO 20 MA, O/P 0.2 TO 1.0 KG /
SQ.C
FORBE MARSHALL DIGITAL INDICATOR
ASSY
FORBES MARSHAL CONDUCTIVITY
METER

-1

-3242.58

UNIT # 5

-2

-40166.28

UNIT # 5

-1

-20083.14

UNIT # 5

-1

-14040.50

UNIT # 5

-1

-14040.50

UNIT # 5

-1

-14040.50

UNIT # 5

-1

-14040.50

UNIT # 5

-1

-4584.29

UNIT # 5

-1

-34382.16

UNIT # 5

I&C TRBVSRYSENSOR PROBE ASSY

-1

-0.01

UNIT # 5

12
7
12
8
12
9
13
0
13
1
13
2
13
3
13
4
13
5
13
6
13
7
13
8
13
9
14
0
14
1
14
2

A10009004002
0059
A10007004001
0004
A10007003006
0015
A10007003006
0015
A10007003006
0010
A10007003006
0009
A10007003006
0006
A10007003005
0064
A10007003005
0064
A10007003005
0008
A10007003004
0006
A10007003002
0005
A10006008001
0014
A10006006002
0016
A10006006002
0016
A10006006002
0015

TRIP INDICATION LAMP IDENT


CODE3SB12 91
PRESSURE FILTER ELEMENT PN 60 /
00018.
SET OF PICKINGS OF SERVO VALVE ST10.65
SET OF PICKINGS OF SERVO VALVE ST10.65
SET OF PICKINGS TO SERVO VALVE
ST10 4+R6
SB FILTER FOR SERVO VALVE ST10-63 /
4
SERVO VALVE FIXING BOLT M6 X 130
WITH WA

14
3
14
4
14
5
14
6
14
7
14
8
14
9
15
0
15
1

A10006001005
0014
A10006001005
0001
A10006001005
0001
A10006001005
0001
A10006001004
0015
A10006001004
0014
A10006001004
0014
A10006001004
0014
A10006001004
0012

154

-5

-765.00

UNIT # 5

-2

-15140.00

UNIT # 5

-1

-19683.96

UNIT # 5

-1

-19683.96

UNIT # 5

-1

-6921.93

UNIT # 5

-1

-22172.76

UNIT # 5

-1

-1131.18

UNIT # 5

FILTER INSERT FOR HC9020 OIL UNIT

-4

-47209.19

UNIT # 5

FILTER INSERT FOR HC9020 OIL UNIT


FILTERS FILTER INSERT BIG HC9600
FUP4H H

-1

-11802.30

UNIT # 5

-2

-35233.69

UNIT # 5

SULZER HOSE O' RING SET


BL-10 SET OF PACKING CODE
97450240
COAL FEEDER CONTROL PANEL
TRANSFORMER, O

-2

-2262.36

UNIT # 5

-1

-2899.12

UNIT # 5

-1

-8000.00

UNIT # 5

PROCESSOR POWER SUPPLY

-3

-0.03

UNIT # 5

PROCESSOR POWER SUPPLY

-1

-0.01

UNIT # 5

I&C FSSS MODICON MA-0185-100

-1

UNIT # 5

I&C FSSS BHEL SPARK ROD TIPIMPORTED

-4

-0.01
227430.8
1

ALLAN SCREW FOR IGNITOR 4 MM

-2

-36.72

UNIT # 5

ALLAN SCREW FOR IGNITOR 4 MM

-4

-73.44

UNIT # 5

-10

-183.60

UNIT # 5

-4

-913.92

UNIT # 5

-2

-5672.16

UNIT # 5

-3

-8508.24

UNIT # 5

-4

-11344.32

UNIT # 5

-1

-2688.14

UNIT # 5

ALLAN SCREW FOR IGNITOR 4 MM


FSSS HEA ADV/RET ASSY SPARK ROD
CLAMPS
AS PER SPEC HEA ADV/RET ASSY
SPARK ROD
AS PER SPEC HEA ADV/RET ASSY
SPARK ROD
AS PER SPEC HEA ADV/RET ASSY
SPARK ROD
AS PER SPEC HEA ADV/RET ASSY PC
SEAL KIT

UNIT # 5

15
2
15
3
15
4
15
5
15
6
15
7
15
8
15
9

A10006001004
0012
A10006001004
0012
A10006001003
0020
A10006001002
0042
A10006001002
0040
A10006001002
0040
A10006001002
0039
A10006001002
0035

AS PER SPEC HEA ADV/RET ASSY PC


SEAL KIT
AS PER SPEC HEA ADV/RET ASSY PC
SEAL KIT

16
0
16
1
16
2
16
3
16
4
16
5
16
6
16
7
16
8
16
9
17
0
17
1
17
2
17
3
17
4
17
5
17
6

A10006001002
0022
A10006001002
0015
A10006001002
0015
A10006001002
0005
A10004001002
0009
A10003001002
0009
A10001002001
0009
A09817001001
0001
A09813002002
0001
A09813002001
0004
A09813002001
0003
A09811001001
0009
A09805001002
0002
A09803005001
0003
A09803005001
0003
A09802001001
0074
A09802001001
0025

155

-2

-5376.29

UNIT # 5

-2

-5376.29

UNIT # 5

-2

-62393.76

UNIT # 5

-5

-472.68

UNIT # 5

-5

-640.71

UNIT # 5

-18

-2306.54

-15

-18054.00

SAFE SCAN II FIBRE OPTIC CABLE

-16

SAFE SCAN II HOUSING ELECTRONIC


CARD

-18

-49543.68
132192.0
0

SAFE SCAN II COLLIMATOR TUBE

-5

-3069.33

SAFE SCAN II COLLIMATOR TUBE


FLAME SCANNER SAFE SCAN II ALLAN
SCREWS
I&C DCS ABBPRO POWER AMPFR AVLAA
I&C DAS SIEMEN HARD DISK DRIVE
160GB
I&C ACS H&B AV-42:PROT&ANLG SIGNL
DISTR
HNDTOOL OILCAN FIXSPOUT WESCO
1/2
HNDTOOL HKSAW BLAD ALOY
1/2"X12"X18TPI
HNDTOOL HKSAW BLAD HSS
1/2"X12"X24TPI
HNDTOOL HKSAW BLAD HSS
1/2"X12"X18TPI
HNDTOOL DRILBIT MET PARALLSHANK
6MM
HNDTOOL FILE FLAT SMOOTH
200MM/8"

-5

-3069.32

-2

-20.00

-1

-88700.00

SCANNER
REPAIR
SCANNER
REPAIR
SCANNER
REPAIR
SCANNER
REPAIR
SCANNER
REPAIR

-1

-3000.00

UNIT # 5

-1

-0.01

UNIT # 5

-1

-1236.24

UNIT # 5

-5

-40.51

UNIT # 5

-5

-166.01

UNIT # 5

-3

-113.49

UNIT # 5

-1

-115.20

UNIT # 5

-1

-663.00

UNIT # 5

HNDTOOL PLIR COMB ELEC 8"

-2

-655.20

UNIT # 5

HNDTOOL PLIR COMB ELEC 8"


ELECTRICAL PATTERN TAPARIA
PRODUCT
HNDTOOL SCRWDRIVER FLAT ELEC
125MMELECT

-1

-327.60

UNIT # 5

-1

-95.68

UNIT # 5

-1

-77.28

UNIT # 5

HEAI EXCITER COMPLETE ASSY


SAFE SCAN II LITTLE FUSE FOR LAMP &
METE
SAFE SCAN II FLAT LENS THK 1.5 MM X
OD 2
SAFE SCAN II FLAT LENS THK 1.5 MM X
OD 2
SAFE SCAN II COLLIMETER LENS &
BARREL AS

SCANNER
REPAIR
SCANNER
REPAIR
SCANNER
REPAIR

17
7
17
8
17
9
18
0
18
1
18
2
18
3
18
4
18
5
18
6
18
7
18
8
18
9
19
0
19
1
19
2
19
3
19
4
19
5
19
6
19
7
19
8
19
9
20
0
20
1
20

A09802001001
0025
A09801003001
0003
A09801003001
0003
A09577008001
0001
A09513004001
0002
A09101009007
0001
A08506007012
0016
A08506007012
0014
A08506007006
0028
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016007
0002
A07802016004
0001
A07802016004
0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802016001

156

HNDTOOL SCRWDRIVER FLAT ELEC


125MMELECT
HNDTOOL SPANNER SINGLEND
300MM/12"
HNDTOOL SPANNER SINGLEND
300MM/12"
VSLOW-BLOW GLASS FUSE 500 VAC
FNO-6 TIME
FUSE FUSE, TYPE: HF, CAT NO: SF
90152

-1

-77.27

UNIT # 5

-1

-490.12

UNIT # 5

-1

-490.12

UNIT # 5

-1

-900.00

UNIT # 5

-1

-56.00

UNIT # 5

ROT2W2P 16A SWITCH KAYCEE RP125B

-1

-520.00

UNIT # 5

ELECTINSU FOR 4.0 SQ.MM WIRE

-1

-48.86

UNIT # 5

ELECTINSU FOR 2.5 SQ.MM WIRE


SLEEVE GLASS FIBER VARNISHED 10
SQ MM

-1

-34.68

UNIT # 5

-1

-12.24

UNIT # 5

CHEM 340 GM SPRAY CAN

-2

-367.37

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 340 GM SPRAY CAN

-1

-183.69

UNIT # 5

CHEM 1 / 2 LTR TIN PACK

-1

-71.82

UNIT # 5

CHEM 1 / 2 LTR TIN PACK

-1

-71.82

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.75

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.74

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.74

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.74

UNIT # 5

CHEM 340 ML SPRAY CAN


CHEM 340 ML SPRAY CAN

-2
-1

-347.49
-173.74

UNIT # 5
UNIT # 5

2
20
3
20
4
20
5
20
6
20
7
20
8
20
9
21
0
21
1
21
2
21
3
21
4
21
5
21
6
21
7
21
8
21
9
22
0
22
1
22
2
22
3
22
4
22
5
22
6
22
7

0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802016001
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802006003
0001
A07802003001
0008
A07802003001
0008
A07801001008
0002
A07801001008
0002
A07801001007
0004
A07801001005
0015
A07801001005
0015

157

CHEM 340 ML SPRAY CAN

-1

-173.75

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.74

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.75

UNIT # 5

CHEM 340 ML SPRAY CAN

-1

-173.75

UNIT # 5

CHEM
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML
CHEM
ML

-1

-173.74

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

-1

-230.39

UNIT # 5

CHEM COLIN BOTTLE

-1

-57.85

UNIT # 5

CHEM COLIN BOTTLE

-2

-115.69

UNIT # 5

CHEM ADH COMP GP FEVICOL 100ML

-4

-103.54

UNIT # 5

CHEM ADH COMP GP FEVICOL 100ML


CHEM ADH COMP GSKT SPEB-7 500ML
TIN

-5

-129.43

UNIT # 5

-2

-211.17

UNIT # 5

SEALENT ANABOND 666 100 GM PKT

-1

-95.86

UNIT # 5

SEALENT ANABOND 666 100 GM PKT

-1

-95.86

UNIT # 5

340 ML SPRAY CAN


CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350
CNTCT-CL KLINIT SPRAY TIN 350

22
8
22
9
23
0
23
1
23
2
23
3
23
4
23
5
23
6
23
7
23
8
23
9
24
0
24
1
24
2
24
3
24
4
24
5
24
6
24
7
24
8
24
9
25
0
25
1
25
2
25

A07801001005
0012
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07801001002
0017
A07711001002
0002
A07711001002
0001
A07704003001
0001
A05103078001
0002
A05103025001
0008
A05103025001
0008
A05103002001
0004
A05102011001
0006
A05102011001
0004
A05002002011
0001
A04801004038
0001
A04801004003
0003
A04801004001
0003
A04706001001

158

CHEM ADH COMP SEAL INDIAN


HDSHELLAC 60ML
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CHEM ADH COMP STEEL M SEALFASTCURE 1KG
CBLMTL CONCTR BKLT 12WAY 2.5
SQMM
CBLMTL CONCTR BKLT 12WAY 1.5
SQMM
CABLE CBLE TIE NYLON 2 MM TH TIE
2.5 MM

-3

-39.00

UNIT # 5

-0.250

-53.87

UNIT # 5

-3

-646.43

UNIT # 5

-0.250

-53.87

UNIT # 5

-0.250

-53.87

UNIT # 5

-1

-215.48

UNIT # 5

-0.250

-53.87

UNIT # 5

-0.250

-53.87

W T PLANT

-1

-215.48

UNIT # 5

-3

-646.43

UNIT # 5

-0.250

-53.87

UNIT # 5

-0.250

-53.87

UNIT # 5

-8

-530.00

UNIT # 5

-9

-321.30

UNIT # 5

-35

-89.25

UNIT # 5

POW CYL SEAL KIT


PWR CYL BR330MMXSTR 600MM SEAL
KIT
PWR CYL BR330MMXSTR 600MM SEAL
KIT

-1

-1122.00

UNIT # 5

-1

-1530.00

UNIT # 5

-2

-3060.00

UNIT # 5

PWR CYL 1ACT,ON-OFF SHAFT SL


PWR CYL PISTN
ROD,DISC,LCK,CHCKNUT

-3

-198.90

UNIT # 5

-1

-32211.83

UNIT # 5

MAKE WIPRO SLEEVE

-1

-39688.20

UNIT # 5

WITHOUT SLEEVE 8 MM DIA TH 1.0 MM

-2

-120.00

UNIT # 5

PAINT STANDARD WHITE 1 LITRE PACK


PAINT STANDARD LIGHT GREY 1 LITRE
PACK

-1

-279.48

UNIT # 5

-1

-279.48

UNIT # 5

PAINT STANDARD BLACK 1 LITRE PACK


SQUARE NEOPRENE 7 MM IN

-2
-50

-546.72
-7650.00

UNIT # 5
UNIT # 5

3
25
4
25
5
25
6
25
7
25
8
25
9
26
0
26
1
26
2
26
3
26
4
26
5
26
6
26
7
26
8
26
9
27
0
27
1
27
2
27
3
27
4
27
5
27
6
27
7
27
8

0001
A03908001001
0004
A03908001001
0001
A03908001001
0001
A03602016002
0001
A03602013001
0002
A03602009003
0006
A03303001036
0012
A03302006006
0018
A03302004009
0027
A03302004009
0027
A03302004009
0027
A03201005002
0002
A03201005002
0002
A03201005002
0002
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0039
A03201002001
0038

159

CONTINEOUS L
DIGITL MLTIMTR STD MOTWANE DM
6K3
DIGITL MLTIMTR STD MOTWANE LEAD
ACCSRS
DIGITL MLTIMTR STD MOTWANE LEAD
ACCSRS
LUBRCNT OIL TURB IOC SERVO PRIME:
32
LUBRCNT OIL SP HYDR IOC SERVO SY
HLP:68
LUBRCNT OIL CV HYDR IOC SERVO
CONVAL-46
INSTPNL INDCTRANLG1SCL O/P0199.50A
INSTPNL DESK PUSH BUTTONS FOR
CPU
LED INDICATOR 24 VAC MINIATURE
LAMP
LED INDICATOR 24 VAC MINIATURE
LAMP
LED INDICATOR 24 VAC MINIATURE
LAMP
HOSE FLX SSCORRU 1/4"BSP(F),L 0.8
M
HOSE FLX SSCORRU 1/4"BSP(F),L 0.8
M
HOSE FLX SSCORRU 1/4"BSP(F),L 0.8
M

-1

-6538.20

UNIT # 5

-1

-213.74

UNIT # 5

-1

-213.74

UNIT # 5

-5

-895.50

UNIT # 5

-50

-7211.35

UNIT # 5

-60

-9654.24

UNIT # 5

-2

-0.02

UNIT # 5

-1

-0.01

UNIT # 5

-10

-1224.00

UNIT # 5

-10

-1224.00

UNIT # 5

-5

-612.00

UNIT # 5

-2

-580.00

UNIT # 5

-3

-870.00

UNIT # 5

-2

-580.00

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-1

-42.84

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-3

-128.52

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-3

-128.52

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-4

-171.36

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-10

-428.40

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-12

-514.08

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-1

-42.84

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-5

-214.20

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-2

-85.68

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-4

-171.36

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-6

-171.36

UNIT # 5

27
9
28
0
28
1
28
2
28
3
28
4
28
5
28
6
28
7
28
8
28
9
29
0
29
1
29
2
29
3
29
4
29
5
29
6
29
7
29
8
29
9
30
0
30
1
30
2
30
3
30

A03201002001
0038
A03201002001
0038
A03201002001
0038
A03201002001
0038
A03201002001
0038
A03201002001
0038
A03201002001
0038
A03201002001
0007
A03201002001
0007
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002

160

SS BRAIDED LOW PR RUBBER HOSE

-4

-114.24

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-4

-114.24

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-6

-171.36

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-5

-142.80

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-1

-28.56

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE

-4

-114.24

UNIT # 5

SS BRAIDED LOW PR RUBBER HOSE


HOSE RUBBER SSBRD 3/8"X3/8"
BSP,L500MM
HOSE RUBBER SSBRD 3/8"X3/8"
BSP,L500MM
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK

-2

-57.12

UNIT # 5

-4

-251.33

UNIT # 5

-2

-125.67

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-10.05

UNIT # 5

-1

-10.05

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-10.05

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-2

-18.77

UNIT # 5

-1

-9.38

W T PLANT

-1
-2

-9.38
-18.77

UNIT # 5
UNIT # 5

4
30
5
30
6
30
7
30
8
30
9
31
0
31
1
31
2
31
3
31
4
31
5
31
6
31
7
31
8
31
9
32
0
32
1
32
2
32
3
32
4
32
5
32
6
32
7
32
8
32
9

0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02912002002
0002
A02910003001
0006
A02910003001
0006
A02910003001
0006
A02910003001
0006
A02910003001
0006
A02910001001
0005
A02907003002
0005
A02907003002
0004
A02907003002
0001
A02907003001
0003
A02907003001
0001
A02907001001
0002
A02907001001
0002
A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0003

161

-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
ELECT INSUL TAPE STEEL GRIP BLACK
-BHOR
HARDWR TORCH CELL PAPERSEAL
NORMAL1,5VCE
HARDWR TORCH CELL PAPERSEAL
NORMAL1,5VCE
HARDWR TORCH CELL PAPERSEAL
NORMAL1,5VCE
HARDWR TORCH CELL PAPERSEAL
NORMAL1,5VCE
HARDWR TORCH CELL PAPERSEAL
NORMAL1,5VCE

-2

-18.77

UNIT # 5

-1

-9.38

UNIT # 5

-2

-18.77

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-9.38

UNIT # 5

-1

-10.05

UNIT # 5

-3

-30.45

UNIT # 5

-3

-30.45

UNIT # 5

-3

-30.45

UNIT # 5

-2

-20.30

UNIT # 5

-3

-30.45

UNIT # 5

-2

-306.00

UNIT # 5

-6

-1158.95

UNIT # 5

-20

-3266.99

UNIT # 5

HARDWR POLY BAG 0.2MM 6X9 INCH

-3

-502.90

UNIT # 5

HARDWR POLY BAG 0.1MM 12X18 INCH

-5

-712.55

UNIT # 5

-8.500

-1164.20

UNIT # 5

-2

-398.80

UNIT # 5

-5

-996.99

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.55

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

TORCH EVEREADY DIGILED


POLYTHENE BAG THK 0.2 MM 12 X 18
INCH
HARDWR POLY BAG 0.2MM SIZE24X24
INCH

HARDWR POLY BAG 0.1MM 6X9 INCH


HARDWR POLY PAPER 0.2MM 1.5 M
WIDE
HARDWR POLY PAPER 0.2MM 1.5 M
WIDE

33
0
33
1
33
2
33
3
33
4
33
5
33
6
33
7
33
8
33
9
34
0
34
1
34
2
34
3
34
4
34
5
34
6
34
7
34
8
34
9
35
0
35
1
35
2
35
3
35
4
35

A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0003
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001

162

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-2

-67.71

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.85

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-2

-67.71

UNIT # 5

PTFE TAPE ROLL 25 MM W 12 M

-1

-33.55

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-2

-34.64

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.01

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-2

-34.64

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.01

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

W T PLANT

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.01

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-2

-34.64

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-2

-34.64

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-9

-153.09

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M


PTFE TAPE ROLL 12.5 MM W 12 M

-2
-2

-34.64
-34.64

UNIT # 5
UNIT # 5

5
35
6
35
7
35
8
35
9
36
0
36
1
36
2
36
3
36
4
36
5
36
6
36
7
36
8
36
9
37
0
37
1
37
2
37
3

0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02713007001
0001
A02701001019
0004
A02304001004
0011
A02304001004
0011
A02304001004
0011
A02304001004
0011
A02304001003
0001
A01901001007
0038
A01604002002
0003
A01601002003
0001
A01404002021
0001
A00302009014
0001

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.01

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-2

-34.64

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M

-1

-17.32

UNIT # 5

PTFE TAPE ROLL 12.5 MM W 12 M


STYLE 20 STEAM NON METALLIC
1525X1650MM
COMPLETE REGULATOR HIGH FLOW
WITH PRESSU
COMPLETE REGULATOR HIGH FLOW
WITH PRESSU
COMPLETE REGULATOR HIGH FLOW
WITH PRESSU
COMPLETE REGULATOR HIGH FLOW
WITH PRESSU
COMPLETE REGULATOR WITH
PRESSURE GAUGE 1

-2

-34.64

UNIT # 5

-17

-1707.99

UNIT # 5

-1

-920

UNIT # 5

-2

-1840

UNIT # 5

-1

-920

UNIT # 5

-1

-920

UNIT # 5

-6

-9487.74

UNIT # 5

CNTCTR&STRTR 3TH 30-22-0AF0


CBLINS CMPN TC KTYPE PVC-UARMR
PR2
CBLINS 1.1SCR CUMLTUAR CR4
1.50SQMM

-1

-0.01

UNIT # 5

-4

-440

UNIT # 5

-3

-302.94

UNIT # 5

CORE 1 1.5 SQMM


ACTUATOR PNEUMATIC ILP M-SPA1M
SEAL KIT

-20

-387.6

UNIT # 5

-1

-1530
1446401.
00

UNIT # 5

Total

163

TESTING - II :
SUPPLY
SR.

MATERIAL DESCRIPTION

AMOUNT

NO.
1.

Relays

2.

Ammeter / Annunciators

26,246

3.

Capacitor / Fuses

32,972

4.

Push buttons/ LEDs

17,332

5.

Actuator spares

6.

Consumables

1,53,799

3,13,763
3,000

Total Amount in Rs.

5,47,112

WORKS
SR.
NO.

Order details

1.

AMOUNT

Work of servicing of actuator limit switch assembly of


motorised valves, gates & dampers

1,97,110

CSTPS/4500060623, Dtd. 23.09.15


2.

Work contract for testing of ABB/EE make switchgear


protection relays

6,00,000

CSTPS/4500061878, Dtd. 26.09.15


Total Amount in Rs.

7,97,110

Total R&M expenditure during Unit#5 COH in Rs. = Rs. 5,47,112 + Rs. 7,97,110
= Rs. 13,44,222/= Rs. 13.44 lakhs

164